RFP 7177 - SOW Exhibit B - Construction Progress Schedule01 32 16 - 1 CONSTRUCTION PROGRESS SCHEDULE Page 1 of 4 CITY OF DENTON RFP# 7177 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised September 20, 2018 SECTION 01 32 16 1 CONSTRUCTION PROGRESS SCHEDULE 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. General requirements for the preparation, submittal, updating, status reporting and 6 management of the Construction Progress Schedule 7 B. Deviations from this City of Denton Standard Specification 8 1. None. 9 C. Related Specification Sections include, but are not necessarily limited to: 10 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 11 2. Division 1 – General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Work associated with this Item is considered incidental to the various items bid. 15 No separate payment will be allowed for this Item. 16 1.3 REFERENCES 17 A. Definitions 18 1. Baseline Schedule - Initial schedule submitted before work begins that will serve 19 as the baseline for measuring progress and departures from the schedule. 20 2. Progress Schedule - Monthly submittal of a progress schedule documenting 21 progress on the project and any changes anticipated. 22 3. Schedule Narrative - Concise narrative of the schedule including schedule 23 changes, expected delays, key schedule issues, critical path items, etc 24 B. Reference Standards 25 1. None 26 1.4 ADMINISTRATIVE REQUIREMENTS 27 A. Baseline Schedule 28 1. General 29 a. Prepare a baseline Schedule using approved software and the Critical Path 30 Method (CPM). 31 b. Review the draft baseline Schedule with the City to demonstrate understanding 32 of the work to be performed and known issues and constraints related to the 33 schedule. 34 c. Designate an authorized representative (Project Scheduler) responsible for 35 developing and updating the schedule and preparing reports. 36 B. Progress Schedule 37 1. Update the progress Schedule monthly. 38 01 32 16 - 2 CONSTRUCTION PROGRESS SCHEDULE Page 2 of 4 CITY OF DENTON RFP# 7177 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised September 20, 2018 2. Prepare the Schedule Narrative to accompany the monthly progress Schedule. 1 3. Change Orders 2 a. Incorporate approved change orders, resulting in a change of contract time, in 3 the baseline Schedule. 4 C. Responsibility for Schedule Compliance 5 1. Whenever it becomes apparent from the current progress Schedule and CPM Status 6 Report that delays to the critical path have resulted and the Contract completion 7 date will not be met, or when so directed by the City, make some or all of the 8 following actions at no additional cost to the City 9 a. Submit a Recovery Plan to the City for approval revised baseline Schedule 10 outlining: 11 1) A written statement of the steps intended to take to remove or arrest the 12 delay to the critical path in the approved schedule 13 2) Increase construction manpower in such quantities and crafts as will 14 substantially eliminate the backlog of work and return current Schedule to 15 meet projected baseline completion dates 16 3) Increase the number of working hours per shift, shifts per day, working 17 days per week, the amount of construction equipment, or any combination 18 of the foregoing, sufficiently to substantially eliminate the backlog of work 19 4) Reschedule activities to achieve maximum practical concurrency of 20 accomplishment of activities, and comply with the revised schedule 21 2. If no written statement of the steps intended to take is submitted when so requested 22 by the City, the City may direct the Contractor to increase the level of effort in 23 manpower (trades), equipment and work schedule (overtime, weekend and holiday 24 work, etc.) to be employed by the Contractor in order to remove or arrest the delay 25 to the critical path in the approved schedule. 26 a. No additional cost for such work will be considered. 27 D. The Contract completion time will be adjusted only for causes specified in this 28 Contract. 29 a. Requests for an extension of any Contract completion date must be 30 supplemented with the following: 31 1) Furnish justification and supporting evidence as the City may deem 32 necessary to determine whether the requested extension of time is entitled 33 under the provisions of this Contract. 34 a) The City will, after receipt of such justification and supporting 35 evidence, make findings of fact and will advise the Contractor, in 36 writing thereof. 37 2) If the City finds that the requested extension of time is entitled, the City's 38 determination as to the total number of days allowed for the extensions 39 shall be based upon the approved total baseline schedule and on all data 40 relevant to the extension. 41 a) Such data shall be included in the next updating of the Progress 42 schedule. 43 b) Actual delays in activities which, according to the Baseline schedule, 44 do not affect any Contract completion date shown by the critical path in 45 the network will not be the basis for a change therein. 46 2. Submit each request for change in Contract completion date to the City within 30 47 days after the beginning of the delay for which a time extension is requested but 48 before the date of final payment under this Contract. 49 01 32 16 - 3 CONSTRUCTION PROGRESS SCHEDULE Page 3 of 4 CITY OF DENTON RFP# 7177 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised September 20, 2018 a. No time extension will be granted for requests which are not submitted within 1 the foregoing time limit. 2 b. From time to time, it may be necessary for the Contract schedule or completion 3 time to be adjusted by the City to reflect the effects of job conditions, weather, 4 technical difficulties, strikes, unavoidable delays on the part of the City or its 5 representatives, and other unforeseeable conditions which may indicate 6 schedule adjustments or completion time extensions. 7 1) Under such conditions, the City will direct the Contractor to reschedule the 8 work or Contract completion time to reflect the changed conditions and the 9 Contractor shall revise his schedule accordingly. 10 a) No additional compensation will be made to the Contractor for such 11 schedule changes except for unavoidable overall contract time 12 extensions beyond the actual completion of unaffected work, in which 13 case the Contractor shall take all possible action to minimize any time 14 extension and any additional cost to the City. 15 b) Available float time in the Baseline schedule may be used by the City 16 as well as by the Contractor. 17 3. Float or slack time is defined as the amount of time between the earliest start date 18 and the latest start date or between the earliest finish date and the latest finish date 19 of a chain of activities on the Baseline Schedule. 20 a. Float or slack time is not for the exclusive use or benefit of either the 21 Contractor or the City. 22 b. Proceed with work according to early start dates, and the City shall have the 23 right to reserve and apportion float time according to the needs of the project. 24 c. Acknowledge and agree that actual delays, affecting paths of activities 25 containing float time, will not have any effect upon contract completion times, 26 providing that the actual delay does not exceed the float time associated with 27 those activities. 28 E. Coordinating Schedule with Other Contract Schedules 29 1. Where work is to be performed under this Contract concurrently with or contingent 30 upon work performed on the same facilities or area under other contracts, the 31 Baseline Schedule shall be coordinated with the schedules of the other contracts. 32 a. Obtain the schedules of the other appropriate contracts from the City for the 33 preparation and updating of Baseline schedule and make the required changes 34 in his schedule when indicated by changes in corresponding schedules. 35 2. In case of interference between the operations of different contractors, the City will 36 determine the work priority of each contractor and the sequence of work necessary 37 to expedite the completion of the entire Project. 38 a. In such cases, the decision of the City shall be accepted as final. 39 b. The temporary delay of any work due to such circumstances shall not be 40 considered as justification for claims for additional compensation. 41 1.5 SUBMITTALS 42 A. Baseline Schedule 43 1. Submit Schedule in native file format and pdf format. 44 a. Native file format shall be: 45 1) Microsoft Project 46 2. Submit draft baseline Schedule to City prior to the pre-construction meeting and 47 bring in hard copy to the meeting for review and discussion. 48 01 32 16 - 4 CONSTRUCTION PROGRESS SCHEDULE Page 4 of 4 CITY OF DENTON RFP# 7177 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised September 20, 2018 B. Progress Schedule 1 1. Submit progress Schedule in native file format and pdf format. 2 2. Submit progress Schedule monthly no later than the 25th day of the month. 3 C. Schedule Narrative 4 1. Submit the schedule narrative in pdf format. 5 2. Submit schedule narrative monthly no later than the 25th day of the month. 6 D. Submittal Process 7 1. 8 2. Contractor shall submit one (1) hard copy of documents to the Project Manager’s 9 duly appointed representative. 10 3. Contractor shall submit documents via email to the Project Manager and their duly 11 appointed representative. 12 4. Once the project has been completed and Final Acceptance has been issued by the 13 City, no further progress schedules are required. 14 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 15 1.7 CLOSEOUT SUBMITTALS [NOT USED] 16 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 17 1.9 QUALITY ASSURANCE 18 A. The person preparing and revising the construction Progress Schedule shall be 19 experienced in the preparation of schedules of similar complexity. 20 B. Schedule and supporting documents addressed in this Specification shall be prepared, 21 updated and revised to accurately reflect the performance of the construction. 22 C. Contractor is responsible for the quality of all submittals in this section meeting the 23 standard of care for the construction industry for similar projects. 24 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 25 1.11 FIELD [SITE] CONDITIONS [NOT USED] 26 1.12 WARRANTY [NOT USED] 27 PART 2 - PRODUCTS [NOT USED] 28 PART 3 - EXECUTION [NOT USED] 29 END OF SECTION 30