Loading...
RFP 7177 - SOW Exhibit E - Testing and Inspection Services01 45 23 - 1 TESTING AND INSPECTION SERVICES Page 1 of 3 CITY OF DENTON RFP# 7177 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised September 20, 2018 SECTION 01 45 23 1 TESTING AND INSPECTION SERVICES 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Testing and inspection services procedures and coordination 6 B. Deviations from this City of Denton Standard Specification 7 1. None 8 C. Related Specification Sections include, but are not necessarily limited to: 9 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 10 2. Division 1 – General Requirements 11 1.2 PRICE AND PAYMENT PROCEDURES 12 A. Measurement and Payment 13 1. Work associated with this Item is considered incidental to the various Items bid. 14 No separate payment will be allowed for this Item. 15 a. In accordance with Article 13 of the General Conditions, Contractor is 16 responsible for performing, coordinating, and payment of all inspections, tests, 17 re-tests, or approvals. 18 b. In accordance with Article 13 of the General Conditions, City is responsible for 19 performing and payment for first set additional independent testing chosen by 20 the City to be performed. 21 1) If the first independent test performed by the City fails, the Contractor is 22 responsible for payment of subsequent testing until a passing test occurs. 23 a) Final acceptance will not be issued by City until all required payments 24 for testing by Contractor have been paid in full. 25 1.3 REFERENCES [NOT USED] 26 1.4 ADMINISTRATIVE REQUIREMENTS 27 A. Testing 28 1. Complete testing in accordance with the Contract Documents. 29 2. Coordination 30 a. When testing is required to be performed by the City, notify City, sufficiently 31 in advance, when testing is needed. 32 b. When testing is required to be completed by the Contractor, notify City, 33 sufficiently in advance, that testing will be performed. 34 3. Distribution of Testing Reports 35 a. Electronic Distribution 36 1) Provide all reports to Project Manager and their duly appointed 37 representative electronically via email. 38 4. Provide Project Manager’s duly appointed representative with trip tickets for each 39 delivered load of Concrete or Lime material including the following information: 40 01 45 23 - 2 TESTING AND INSPECTION SERVICES Page 2 of 3 CITY OF DENTON RFP# 7177 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised September 20, 2018 a. Name of pit 1 b. Date of delivery 2 c. Material delivered 3 B. Inspection 4 1. Inspection or lack of inspection does not relieve the Contractor from obligation to 5 perform work in accordance with the Contract Documents. 6 1.5 SUBMITTALS 7 A. Submittals shall be in accordance with Section 01 33 00. 8 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 9 A. Materials Testing Reports sealed by a Professional Engineer or Professional 10 Geoscientist licensed in the State of Texas. 11 1.7 CLOSEOUT SUBMITTALS [NOT USED] 12 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 13 1.9 QUALITY ASSURANCE [NOT USED] 14 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 15 1.11 FIELD [SITE] CONDITIONS [NOT USED] 16 1.12 WARRANTY [NOT USED] 17 PART 2 - PRODUCTS [NOT USED] 18 PART 3 - EXECUTION [NOT USED] 19 20 01 45 23 - 3 TESTING AND INSPECTION SERVICES Page 3 of 3 CITY OF DENTON RFP# 7177 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised September 20, 2018 END OF SECTION 1 2 Revision Log DATE NAME SUMMARY OF CHANGE 3