Exhibit 3 - Project Timeline1 1
Morse Street Road Diet
From Loop 288 to Mayhill Road
Design Start: June 6, 2018 Est. Constr. Completion: November 27, 2020
6/1/2018 8/31/2018 11/30/2018 3/1/2019 5/31/2019 8/30/2019 11/29/2019 2/28/2020 5/29/2020 8/28/2020 11/27/2020
DESIGN
Contract Awarded
Design Management
Conceptual Design
Preliminary Design
Project on Hold
Traffic Study
Preliminary Redesign
Final Design
PROCUREMENT
Bid Phase
CONSTRUCTION
Construction Phase
RIGHT-OF-WAY
ROW/Easement
SURVEY
Survey and SUE
PERMITTING
SWPPP
TDLR Review
TDLR Inspection
WATER
Water Utilities
DESIGN
PROCUREMENT
CONSTRUCTION
PERMITTING
WATER
RIGHT OF WAY
SURVEY