7420 - ADDENDUM 2 - Hickory GIS Duct Bank ImprovementsHickory GIS Duct Bank Improvements
Addendum # 2
I. Technical Specifications, B. Price Items, Item G-03 – Portable Changeable Message Sign, General,
Change sentence to read:
“The signs shall be placed for a minimum duration of 2 months per location per general phase of the
project.”
II. Clarifications
A) The Contractor shall verify vertical and horizontal location of existing utilities along each
transmission and distribution alignment prior to construction. The Contractor shall
communicate any conflicts to the Engineer for conflict resolution prior to construction. This shall
be incidental work associated with the transmission and distribution duct bank work and no
separate proposal item is included.
B) Ground grid exists within the existing Hickory Substation. The Contractor shall cut the ground
grid on each side of the trench making sure not to damage ground grid to remain and remove
the ground grid prior to continue trench work. Ground grid on either side of the trench shall not
be damaged. After completion of the duct bank improvements, the contractor shall install and
reattached new ground grid to the existing ground grid as required by the City. All ground grid
work shall be incidental to the transmission and distribution duct bank improvements and no
separate proposal item is included.