Loading...
Exhibit 4 - Project List and Estimated ScheduleExhibit 4 - Project List and Estimated Schedule Project Estimated Construction Cost Brinker Tie-In 210,000.00$ Hickory Creek Rd (2 Poles)260,000.00$ Denton West to Jim Christal (1 Pole)470,000.00$ Year 1 Total 940,000.00$ Hickory to Locust 2,900,000.00$ RD Wells to Hickory (I35 Project)630,000.00$ Denton North to Masch Branch (I35 Project)1,500,000.00$ Year 2 Total 5,030,000.00$ Woodrow to Brinker 930,000.00$ Brinker to Cooper Creek 1,100,000.00$ Hickory Substation Tie-In 850,000.00$ Year 3 Total 2,880,000.00$ Underwood Substation Tie-In 630,000.00$ RD Wells to Denton West 2,700,000.00$ RD Wells to Hickory 1,600,000.00$ Spencer to Locust 2,100,000.00$ Year 4 Total 7,030,000.00$ 15,880,000.00$ Year 1 Year 2 Year 3 Year 4