Exhibit 2 - Pricing EvaluationHammett
Excavation, Inc.
MSB
Constructors, Inc.
C. Green
Scaping, LP Mart, Inc
Dodd City, TX Boyd, TX Fort Worth, TX Irving, TX
Item #Description
1 Offeror's Key Personnel - 10%8.67 8.00 6.67 8.00
2 Quality, Reputation and Ability to Complete Similar Projects on Schedule and within Budget - 15%12.00 8.00 8.00 7.00
3 Detailed Schedule and Written Plan to achieve Substantial Completion and Final Acceptance Contract Time - 10%8.67 8.00 6.00 8.00
4 Offeror's Safety Record - 5%4.67 4.67 4.33 4.33
5 Price, Total Cost of Ownership - 60%56.41 60.00 58.24 55.51
90.41 88.67 83.24 82.84
$2,297,120.31 $2,197,398.00 $2,263,885.49 $2,375,345.20
$229,712.03
$2,526,832.34
Exhibit 2
CSP 7568 - Pricing Evaluation for Public Disposal Facility
Total Scores:
Total:
10% Contingency:
Contract Total:
Respondent's Business Name:
Principal Place of Business (City and State):