Exhibit 2 - Pricing EvaluationJC Commercial, Inc.Northridge Construction Group Mart, Inc.
Lewisville, TX North Richland Hills, TX Irving, TX
Line #Description QTY UOM Unit Unit Unit
1
1.1 General Conditions, General Requirements, Mobilization Other Onsite Contractor Costs 1 EA $325,000.00 $417,600.00 $580,750.00
1.2 Subcontractor's Cost of Work (total of subcontracts)1 EA $3,642,777.00 $3,088,480.00 $3,815,250.00
1.3 Insurance to include:1 EA $0.00 $0.00 $0.00
1.31 Performance Payment Bond 1 EA 1.1%2.0%0.9%
1.32 Maintenance Bond 1 EA 0.25%0.0%0.2%
1.33 All other insurances required by the contract documents 1 EA 0.4%0.6%0.4%
1.4 Home Office Overhead Profit 1 EA 4.03%7.2%5.0%
Contractor's Schedule: Notice to Proceed to Substantial Completion 1 EA $365.00 $365.00 $365.00
2
2.1
Alternate Bid Item No. 1: Identify the cost to construct an expansion to the existing flush truck
storage building.1 EA
2.2
Alternate Bid Item No. 2: Identify the cost to add gutters and downspouts to the existing west
canopy and the new west canopy as shown on the drawings.1 EA $171,000.00 $13,125.00 $20,000.00
2.3
Alternate Bid Item No. 3: Identify the cost to add new canopy on the east side of building with
gutters and downspouts full length as shown on the drawings.1 EA $301,300.00 $146,614.00 $100,000.00
2.4
Alternate Bid Item No. 4: Identify the cost to add new exterior wash bay on the northwest side
of the new Fleet Services addition as shown on the drawings.1 EA $325,000.00 $205,660.00 $221,000.00
2.5
Alternate Bid Item No. 5: Identify the cost to add new 5-ton crane in new addition as shown on
the drawings.1 EA $0.10 $130,000.00 $217,000.00
2.6
Alternate No. 6 - Contractor's Proposed Unit Cost for Delays Caused by Unforeseeable
Conditions as Defined by Contract (To Include All Contractor Costs + Fee for Any Biz Day of
Delay)22 EA $33,000.00 $1,500.00 $2,000.00
2.7 Alternate No. 7 -Cost to Accelerate to City's Schedule 1 EA $0.10 $0.01 $40,000.00
2.8 Alternate No. 8 - Reduction in Cost to Remove Liquidated Damages from Agreement 1 EA $0.10 -$40,000.00 $1,000.00
$4,765,077.10 $4,001,479.00 $4,954,000.00
Item #JC Commercial, Inc.Northridge Construction Group Mart, Inc.
1 8.67 6.67 6.00
2 9.33 6.00 6.00
3 28.00 21.00 16.33
4 4.67 4.00 3.33
5 34.00 40.00 38.00
84.67 77.67 69.67Total Score:
Price, Total Cost of Ownership - 40%
Cost Proposal
Exhibit 2
CSP 7750 - Pricing Evaluation for Fleet Services Expansion
Total Price:
Respondent's Business Name:
Principal Place of Business (City and State):
Alternates
Evaluation
Scoring Criteria
Key personnel and project team - 10%
Detailed Schedule, Quality, Cost & Information Management Plans - 10%
Quality, Reputation, and Ability to Complete Similar Projects on Schedule and Within Budget - 35%
Offeror’s Safety Record - 5%