Exhibit 2 - Pricing SheetRFB 2022-191 Annual Contract for Asphalt Road Surfacing Products
Austin Asphalt,
Inc.
Coppell, TX
HUB - No
CO-OP - Yes
Reynolds Asphalt
& Construction
Company
North Richland
Hills, TX
HUB - No
CO-OP - Yes
Texas Materials,
Inc.
Irving, TX
HUB - No
CO-OP - Yes
Vulcan
Construction
Materials, LLC
San Antonio, TX
HUB - No
CO-OP - Yes
Item
No.Descriptions
Estimated
Usage in
Tons
Unit Price per Ton Unit Price per Ton Unit Price per Ton Unit Price per Ton
Primary Award Primary Award Primary Award Primary Award1Type D SAC B PG 64-22 HMAC 20,000 89.65$ 85.00$ 93.00$ 78.06$ 2 Type D SAC B PG 70-22 HMAC 20,000 99.65$ 91.00$ 98.00$ 83.06$ Primary Award Primary Award Primary Award Primary Award3Type B PG 64-22 HMAC 20,000 67.75$ 65.00$ 79.00$ 68.85$
4 Type D SAC B PG 64-22 HMAC 20,000 76.80$ 70.00$ 85.00$ 78.06$ 5 Type D SAC B PG 70-22 HMAC 20,000 87.50$ 75.00$ 93.00$ 83.06$ Primary Award Primary Award6High Performance Cold Mix Patch Material 60 127.90$ No Bid 125.00$ No Bid
$9.00 Per Ton
$.70 Per Mile
$7.08 Per Ton < 5
Miles
$.25 Per Mile > 5
Miles
$15.00 Per Ton
$.85 Per Mile
$0.00 Per Ton
$.00 Per Mile
150.00$ 84.96$ 125.00$ 130.00$ 13 Tons 12 Tons 12 Tons No Minimum
$7.00 Per Ton
$.70 Per Mile
$6.00 Per Ton < 5
Miles
$.25 Per Mile > 5
Miles
$12.00 Per Ton
$.65 Per Mile
$0.00 Per Ton
$.00 Per Mile
150.00$ 132.00$ 185.00$ 130.00$
22 Tons 22 Tons 24 Tons No Minimum$120.00 Per Hour $60.30 Per Hour $90.00 Per Hour $100.00 Per Hour1 Day Within the hour 24 HoursNotes: A no bid response was received from Ergon Asphalt & Emulsions, Inc.
Delivery - Tandem Truck
Minimum Delivery Charge
Delivery Charges
Section 3 - DMS9202 Patch Material
Section 2 - Item 340 HMAC Fractionated RAP
Section 1 - Item 340 HMAC Virgin Aggregate
Minimum Delivery SizeDelivery - Flow Boy
Normal Expected Delivery ARO: Demurrage ChargeMinimum Delivery SizeMinimum Delivery Charge
Delivery Charges