Exhibit 5- PresentationCarl Young Sr. Park
Splashpad Phase 2
06/27/2023 ID23-1047
Splashpad Phase 1
Splashpad was approved through Proposition 4 of the 2014 Bond Package:
•Ballot Project Description: This project will fund the construction of a small/medium
splash park. The park will contain spray jets and water features such as water cannons and
dumping buckets. Since there is no standing water at a splash park, no life-guards will be
required, and it will be available for use more hours per week than a standard pool.
•Through community engagement a desire for a dedicated parking space and
bathroom facility was also requested.
•The Carl Young Sr. Splashpad Grand Opening was held May 2018
•Total Approximate Cost of Project: $496,546.97 (Splashpad, Restroom Facility, Parking
Including Design & Construction)
2014 Bond Package
Prop 4 –
PASSED
(Splashpad)
Community Block
Development Grant
(CDBG) –(Restroom
Facility)
Park Land Dedication
& Development Funds
Community
Fundraised
Misc. Operating
Account Funds
$200,000.00 $114,585.00 $60,000.00 $10,439.80 $111,522.17
06/27/2023 ID23-1047
Splashpad Phase 2
Background: FY22-23, City Council allocated funding from the
American Rescue Plan Act (ARPA) to be used for various park
projects throughout the City. ($3.4M)
•Denia Park
•Joe Skiles Park
•Carl Young Sr. Park Splashpad Phase 2
•Pecan Creek Trail
Allocated Budget for Splashpad: $700,000
Summary of Engagement Events
Event #Date Event Location
1 4/24/2023 SEDNA Meeting MLK Rec Center
2 5/4/2023 Twilight Tunes Downtown Square
3 5/11/223 Twilight Tunes Downtown Square
4 5/18/2023 Twilight Tunes Downtown Square
5 5/25/2023 Twilight Tunes Downtown Square
6 6/1/2023 Twilight Tunes Downtown Square
7 6/8/2023 Park Board Civic Center
10 May 4-June 30, 2023 Stationary Board MLK Rec Center
11 May 4-June 30, 2023 Stationary Board American Legion Senior
Center
12 Last Update 5/22 ONLINE ONLINE
Survey received over
280 individuals
Online Participation
over 125 responses
Positive feedback and
excitement for expansion
06/27/2023 ID23-1047
Project Comparison
Elements Phase 1 Phase 2 Combined
Total
Square Foot 1,250 1,250 2,500
Vertical
Elements 1 4 5
In-Ground
Sprayers 6 5 11
Amenities Selection &
Render
06/27/2023 ID23-1047
Ph. 2 Planning & Construction Next Steps
With the approval of this contract:
•Kraftsman will be authorized to begin
construction documentation to meet desired
construction deadlines. If the contract approval is
delayed, it will result in delays in meeting project
deadlines.
Estimated Completion Date:
Summer 2024
(Want to be open by next summer season)
Construction Start Date:
September 2023
06/27/2023 ID23-1047
Project updates & details will be posted on
www.discussdenton.com