6221C - Construction of WaterWorks Park Wave Pool and Concession, Addendum 1 (2)Exhibit 1
RFP 6221 - Denton WaterWorks Wave Pool and Concession - Pricing Sheet
The respondent shall complete the following section, which directly corresponds to the specifications. The contractor shall not make changes to this format.
1
2
3
3a
4
Proposal Pricing:
5
6
Detailed Pricing:
Item #
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
ALTERNATES:
Item #
1A
2A
3A
4A
5A
Payment Term Discounts
QTY
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Allowance
1
1
1
QTY
1
10
2
1
1
Respondent's Name:
Respondent is a Corporation, Partnership, sole Proprietorship, Individual?
Total working days (Monday - Friday/Saturday) after Notice to Proceed is issued by City for substantial completion:
Construction of the WaterWorks Wave Pool and Concession, shall be scheduled to be completed on or before May 1, 2017. If this date cannot be met, please insert the date that your firm
can complete the project. The remainder of the project shall follow the schedule provided in Specification Section 01310 Construction Schedules :
Total working days (Monday - Friday/Saturday) after Notice to Proceed is issued by City for project start:
Base Bid amount to construct project per specifications:
Pricing in typed words
Base Bid + Alternate Bid amount to construct project per specifications:
Pricing in typed words
UOM
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
UOM
LS
EA
EA
LS
LS
Product Description
General Conditions
Mobilization & Demobilization for Project
Bonds (Labor and Materials & Performance)
Spec 33 11 16, 01 50 00, 01 57 23, 02 41 13 50 - Existing Conditions - Complete 8-inch water line relocation, clear and grub trees and shrubs, remove old structures, remove fencing,
relocate secondary and electrical distribution, erect silt and erosion protection
Spec 31 00 00 - Complete earthwork excavation and furnish and install select fill to bring site to grade. Install storm drainage.
Spec 32 32 23 13, 32 13 13 - Install retaining walls, chainlink fencing, composite wood screening, mow strips, related flatwork, complete in place
Spec 33 11 46 - Complete underground pipe and fittings for swimming pool main drain, filtered return, potable water service, overflow and gutter drain
Spec 03 30 53, 32 31 13, 06 10 00, 07 41 00, 03 20 00, 03 15 13 - Construct mechanical room concrete walls, pits, roof structure, slab, fence and gates, complete in place.
Spec 13 11 46, 22 51 19, 13 11 00 - Complete pool mechanical equipment installation excluding wave equipment but including pipe, valves, pump(s), strainer(s), filters, autofill control,
chemical feed system, UV system, and accessories
Spec 03 15 13, 03 20 00, 03 30 53, 03 37 19 - Install reinforced concrete wave pool structure including caissons, blower room, pool walls and floors and beach entry. Install ventilation
fans, grille(s), doors and frames.
Spec 03 50 00 - Install decks and walks
Spec 26 00 00 - Install electrical distribution, overhead pole lighting, building interior lighting, panels, transformers complete and in place for the project
Spec 03 20 00, 03 30 53, 03 62 13, 04 20 00, 06 10 00, 07 21 00, 07 41 00, 08 11 13, 08 56 59 - Construct concession building including foundations, carpentry, masonry, insulation roofing,
HVAC, and electrical lighting, Complete building.
Spec Scheduled on Plans - Furnish and install kitchen equipment from Owner's selected list of appliances, hood(s), cooler, freezer, stainless tables.
Spec 13 11 00, 26 00 00 - Install underwater pool lighting, niches, transformers
Spec 33 11 16 - Repair the irrigation system.
Spec 09 25 13, 09 91 00 - Install Ecofinish AquaBright pool Coating system
Spec 32 92 23 - Furnish and Install bermudagrass sod
Spec 13 -14 16 Allowance to purchase and deliver Wave Pool Equipment
Spec 13 -14 16 Install wave pool equipment furnished under allowance
Spec 13 11 00, 26 00 00 - Install underwater pool lighting, niches, transformers
All other Construction Items not noted above
Product Description
Spec 09 25 13, 09 91 00, 13 11 00 - Add (Deduct) to delete AquaBright finish
from some floor and wall locations and instead install PebbleTec PebbleSheen aggregate plaster including required waterline, stripe, target and gutter trim tile.
Spec 13 11 00 - Add to the base bid to furnish and install 12’ x 12’ cabana shelters with anchors per the specifications
Spec 13 11 00 - Add to the base bid to furnish and install 20’ x 40’ hipped roof fabric shelters with foundations per the specifications.
Spec Scheduled on Plans - Deduct from the base bid to delete Item 11. Above with the exception of: Captive Aire Hood Walk in freezer/cooler, Instead, Owner will purchase and deliver
to site. Contractor will assemble and install
Spec 33 11 16 - Delete 8-inch water line relocation. City will perform.
Payment Terms
Invoice Paid in 15 days
Subcontractor
Subcontractor
Additional Discount %
___________,___,2017
Unit Price
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
153000
0
0
0
Total Base Bid (Item #5)
Unit Price
0
0
0
0
0
Total Alternate Bid (Item #6)
153000
153000
Total
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
153000
0
0
0
153000
Total
0
0
0
0
0
0