Exhibit 2 - Pricing EvaluationMann Robinson
and Son, Inc.
DynaGrid Construction
Group, LLC Reyes Tx Inc Capko Concrete
Structures, LLC.
Aubrey, TX Lewisville, TX Grand Prairie, TX Azle, TX
Line #Description Unit Unit Unit Unit
1 Total proposal amount $2,553,071.00 $2,927,713.00 $3,000,000.00 $3,136,750.00
$127,653.55
$2,680,724.55
Item #Scoring Criteria Mann Robinson
and Son, Inc.
DynaGrid Construction
Group, LLC Reyes Tx Inc Capko Concrete
Structures, LLC.
1
Quality, Reputation, and Ability to Complete Similar Projects
on Schedule and Within Budget - 35%32.67 28.00 23.33 18.67
2 Detailed Schedule and Written Plan - 20%16.00 13.33 13.33 12.00
3 Offeror’s Safety Record - 5%5.00 4.00 2.00 5.00
4 Price, Total Cost of Ownership - 40%40.00 34.88 34.04 32.56
93.67 80.21 72.71 68.23
Respondent's Business Name:
Total Score:
Contingency:
Total Bid:
Exhibit 2
CSP 8419 - Pricing Evaluation for Site Preparation for Underwood Substation
Principal Place of Business (City and State):
Evaluation