Exhibit 2 - Presentation - CCRay Roberts Water Treatment Plant 20 MGD Expansion Design Services City Council 10/22/2024 – 24-2084 1 Katherine Koch Project Manager Water Utilities Ray Roberts Water Treatment Plant •The Ray Roberts Water Treatment (RRWTP) was placed into service in 2002 and has a treatment capacity of 20 million gallons a day (MGD). •To meet the growing water demands, the City is planning on increasing treatment capacity of the plant by an additional 20 MGD. City Council 10/22/24 24-2084 2 Major Project Components This Project includes the following: •Initial Pilot testing for Texas Commission of Environmental Quality (TCEQ) approval of Membrane Filtration at the location. •Design of the Low-Pressure Membrane Process Train with an initial capacity of 20 MGD. •Membrane Process Building designed to accommodate an additional 30 MGD capacity for future demand. •Design of additional ancillary equipment needed for the initial phase of expansion. 3City Council 10/22/24 24-2084 Project Delivery •Staff will be utilizing the Construction Manager at Risk (CMAR) alternate delivery method for the project to achieve optimized schedule coordination, cost modeling, and stakeholder engagement, which mitigates increasing costs and prioritizes overall cost value. •Staff is pursuing a low-interest loan through the Texas Water Development Board to fully fund the expansion project. The consultant will assist the City with the TWDB funding process from pre- application through post-application activities. 4City Council 10/22/24 24-2084 •RFQ 7574 Prequalification list utilized •Staff recommends Freese and Nichols Inc. for design •Design Contract amount: $21,000,000. Engineering Firm Selection 5 Funding for the design contract was made available through budgeted FY 23/24 CO issuance City Council 10/22/24 24-2084 Questions? 6City Council 10/22/2024 – 24-2084