AGENDA INFORMATION SHEET
DEPARTMENT: Procurement
ACM: Christine Taylor
DATE: March 24, 2026
SUBJECT
Consider adoption of an ordinance of the City of Denton, a Texas home-rule municipal corporation,
authorizing the City Manager to execute a contract with RT Solutions Group LLC., for uninterrupted power
supply services for various city buildings for the Facilities Management Department, providing for the
expenditure of funds therefor; and providing an effective date (RFP 8960 – awarded to RT Solutions Group
LLC., for one (1) year, with the option for four (4) additional one (1) year extensions, in total five (5) year
not-to-exceed amount of $2,123,920.00).
STRATEGIC ALIGNMENT
This action supports the Key Focus Area: Enhance Infrastructure and Mobility.
INFORMATION/BACKGROUND
Facilities Management oversees essential infrastructure, including Uninterrupted Power Supplies (UPS),
which provide backup power to critical systems such as fire suppression equipment, emergency lighting,
and electrical distribution networks. These systems ensure operational continuity during power fluctuations
or outages, preventing disruptions in key municipal facilities such as government offices, emergency
response centers, and public utilities. Reliable operation of UPS units is fundamental to maintaining safety,
efficiency, and service delivery across the city.
Due to deferred maintenance and the aging of critical components, several UPS units are exhibiting signs
of performance degradation. In November 2023, assessments conducted by facility engineers identified an
increased risk of failures, emphasizing the need for proactive intervention. Without timely maintenance and
component replacements, these units may struggle to provide consistent backup power, leaving essential
systems vulnerable to electrical disturbances and unexpected power loss. Addressing these concerns now
mitigates long-term risks and ensures uninterrupted operations.
Regular upkeep—including battery replacements, circuit evaluations, and load testing—will ensure system
reliability, enhance energy efficiency, and prevent costly emergency repairs. If preventative maintenance is
not carried out, the likelihood of equipment failure will increase, potentially resulting in operational
inefficiencies, disruptions to municipal services, and financial burdens associated with reactive
maintenance and emergency equipment replacements. By proactively addressing these maintenance needs,
Facilities Management ensures the continued resilience of essential infrastructure, supporting the city’s
ability to operate without interruption.
City Hall
215 E. McKinney Street
Denton, Texas
www.cityofdenton.com
The contract amount is based on past spending at City properties, focusing on Uninterrupted Power Supply
systems. It includes costs for backup power, batteries, and system reliability. Future estimates also look at
current power setups, how facilities may be used differently, and planned improvements like stronger power
systems and smarter energy controls. The cost supports the City’s goal of keeping services running during
outages and improving energy reliability.
ESTIMATED CONTRACTED EXPENSES
FY25-26 FY 26-27 FY 27-28 FY28-29 FY 29-30 Total
Maintenance and repairs $111,000 $114,330 $117,760 $121,293 $124,931 $583,314
Replacement/Additions 270,000 278,100 286,443 295,036 303,887 1,433,466
Sub Total $381,000 $392,430 $404,203 $416,329 $428,818 $2,022,780
Contingency 19,050 19,622 20,210 20,816 21,442 101,140
Total $400,050 $412,052 $424,413 $437,145 $450,260 $2,123,920
Request for Proposals was sent to 408 prospective suppliers, including 11 Denton firms. In addition,
specifications were placed on the Procurement website for prospective suppliers to download and advertised
in the local newspaper. Three (3) proposals were received, references were checked, and proposals were
evaluated based upon published criteria, including price, compliance with specifications, and probable
performance. Best and Final Offers (BAFO) were requested from the top firm. Based upon this evaluation,
RT Solutions Group LLC. was ranked the highest and determined to be the best value for the City.
NIGP Code Used for Solicitation: 207 - Computer Accessories & Supplies
Notifications sent for Solicitation sent in IonWave: 408
Number of Suppliers that viewed Solicitation in IonWave: 26
HUB-Historically Underutilized Business Invitations sent out: 83
SBE-Small Business Enterprise Invitations sent out: 171
Responses from Solicitation: 3
RECOMMENDATION
Award a contract with RT Solutions Group LLC., for uninterrupted power supply services for various city
buildings for the Facilities Management Department, in a one (1) year, with the option for four (4) additional
one (1) year extensions, in the total five (5) year not-to-exceed amount of $2,123,920.
PRINCIPAL PLACE OF BUSINESS
RT Solutions Group LLC.
Fort Worth, TX
SUSTAINABILITY MEASURES
The most cost-effective and efficient parts available will be used when using Uninterrupted Power Supply
services.
ESTIMATED SCHEDULE OF PROJECT
This is an initial one (1) year contract with options to extend the contract for four (4) additional one (1) year
periods, with all terms and conditions remaining the same.
FISCAL INFORMATION
These services will be funded from Outside Contracted Services account 880200.6545 or different
department accounts. Requisitions will be entered into the Purchasing software system on an as-needed
basis. New additions or new construction will be funded from the capital budget. The budgeted amount for
this item is $2,123,920.
EXHIBITS
Exhibit 1: Agenda Information Sheet
Exhibit 2: Pricing Evaluation
Exhibit 3: Ordinance and Contract
Respectfully submitted:
Lori Hewell, 940-349-7100
Purchasing Manager
For information concerning this acquisition, contact: David Moore, 940-349-7247.
Legal point of contact: Leah Bush at 940-349-8333.