Loading...
HomeMy WebLinkAboutIFB 8833 Baker Offsite Sewer Project Manual - SPECS PROJECT MANUAL FOR THE CONSTRUCTION OF Baker Offsite Sewer IFB 8833 Gerard Hudspeth Sara Hensley Mayor City Manager Seth Garcia Director, Capital Projects Steven Gay Director, Water and Wastewater Prepared for The City of Denton FEBRUARY 2026 Prepared by: Texas Registered Engineering Firm F-928 KHA No. 063248015 Effective January 2021 City of Denton Table of Contents 00 00 00 TABLE OF CONTENTS Page 1 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 15, 2021 SECTION 00 00 00 TABLE OF CONTENTS Division 00 - General Conditions 00 05 15 Addenda 00 11 13 Invitation to Bidders 00 21 13 Instructions to Bidders 00 35 13 Conflict of Interest Affidavit 00 41 00 Bid Form 00 42 43 Unit Price Bid Form 00 43 13 Bid Bond 00 43 36 Proposed Subcontractors Form 00 43 37 Vendor Compliance to State Law Nonresident Bidder 00 45 13 Bidder’s Minimum Qualification Statement 00 45 26 Contractor Compliance with Workers' Compensation Law 00 45 43 Corporate Resolution of Authorizing Signatories 00 52 43 Agreement 00 61 13 Performance Bond 00 61 14 Payment Bond 00 61 19 Maintenance Bond 00 61 25 Certificate of Insurance 00 72 00 General Conditions 00 73 00 Supplementary Conditions 00 73 73 Form 1295 – Certificate of Interested Parties Division 01 - General Requirements 01 11 00 Summary of Work 01 25 00 Substitution Procedures 01 29 76 Stored Materials and Equipment (Materials On Hand) 01 31 19 Preconstruction Meeting 01 31 20 Project Meetings 01 32 16 Construction Progress Schedule 01 32 33 Preconstruction Video 01 33 00 Submittals 01 35 13 Special Project Procedures 01 45 23 Testing and Inspection Services 01 50 00 Temporary Facilities and Controls 01 57 13 Storm Water Pollution Prevention Plan 01 58 13 Temporary Project Signage 01 66 00 Product Storage and Handling Requirements 01 70 00 Mobilization and Remobilization 01 71 23 Construction Staking and Survey 01 74 23 Cleaning 01 77 19 Closeout Requirements 01 78 23 Operation and Maintenance Data 01 78 39 Project Record Documents 00 00 00 TABLE OF CONTENTS Page 2 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 15, 2021 TECHNICAL SPECIFICATIONS Division 02 – Existing Conditions 02 41 13 Selective Site Demolition 02 41 14 Utility Removal/Abandonment 02 41 15 Paving Removal Division 03 – Concrete 03 00 00 Concrete and Concrete Reinforcing 03 30 00 Cast-In-Place Concrete 03 34 13 Controlled Low Strength Material (CLSM) 03 80 00 Modifications to Existing Concrete Structures Division 26 – Electrical 26 05 00 Common Work Results for Electrical 26 05 10 Demolition for Electrical Systems 26 05 13 Zinc Coated Steel Wire 26 05 19 Signal Cables 26 05 20 Tray Cables 26 05 26 Grounding Conductors, Ground Rods, and Power Lead-in Cable 26 05 33 Raceways and Boxes for Electrical Systems 26 05 35 Ground Boxes 26 56 00 Roadway Illumination Assemblies Division 31 – Earthwork 31 10 00 Site Clearing 31 23 16 Unclassified Excavation 31 24 00 Embankment 31 25 14 Erosion and Sediment Control 31 34 19 Geosynthetic Soil Reinforcement 31 36 00 Gabions 31 37 00 Riprap Division 32 – Exterior Improvements 32 01 17 Flexible Paving Repair 32 01 29 Concrete Repair 32 05 16 Aggregates for Exterior Improvements 32 11 23 Flexible Base Courses 32 11 29 Lime Treated Base Courses 32 11 33 Cement Treated Base Courses 32 12 16 Asphalt Paving 32 12 73 Asphalt Paving Crack Sealants 32 13 13 Concrete Paving 32 13 16 Decorative Concrete Paving 32 13 73 Concrete Paving Joint Sealants 32 16 00 Curbs, Gutters, Sidewalks, and Driveways 32 17 23 Pavement Markings 32 31 00 Fences and Gates 32 32 00 Retaining Walls 32 84 00 Irrigation Installation and Restoration 00 00 00 TABLE OF CONTENTS Page 3 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 15, 2021 32 93 00 Plantings Division 33 – Utilities 33 01 10 Cleaning and Acceptance Testing of Water and Sewer Force Mains 33 01 12 Joint Bonding and Electrical Isolation 33 01 30 Closed Circuit Television (CCTV) Inspection 33 01 31 Sewer and Manhole Testing 33 01 32 Cleaning of Sewer Mains 33 01 33 Sanitary Sewer Pipe Bursting 33 01 34 Cured in Place Pipe (CIPP) 33 01 40 Liners for Sanitary Sewer Structures 33 01 50 Adjusting Manholes, Inlets, Valve Boxes, and Other Structures to Grade 33 05 02 Water Line Lowering 33 05 05 Utility Trench Excavation, Embedment, and Backfill 33 05 07 Steel Casing Pipe 33 05 08 Tunnel Liner Plate 33 05 10 Auger Boring 33 05 11 Hand Tunneling 33 05 15 Installation of Carrier Pipe in Casing or Tunnel Liner Plate 33 05 61 Cast-in-Place Concrete Manholes 33 05 62 Precast Concrete Manholes 33 05 63 Concrete Water Vaults 33 05 76 Fiberglass Manholes 33 05 81 Frame, Cover, and Grade Rings 33 05 97 Utility Markers/Locators 33 05 98 Location of Existing Utilities 33 14 05 Bolts, Nuts, and Gaskets 33 14 10 Ductile Iron Pipe and Fittings 33 14 11 Polyvinyl Chloride (PVC) Pressure Pipe 33 14 12 Concrete Pressure Pipe, Bar-Wrapped Steel Cylinder Type 33 14 13 Buried Steel Pipe 33 14 14 High Density Polyethylene (HDPE) Pipe 33 14 17 Water Services 1-inch to 2-inch 33 14 18 Large Water Meters 33 14 20 Resilient Seated Gate Valve 33 14 21 AWWA Rubber-Seated Butterfly Valves 33 14 25 Connection to Existing Water Mains 33 14 30 Combination Air Valve Assemblies for Potable Water Systems 33 14 40 Fire Hydrants 33 31 10 Fiberglass Reinforced Pipe for Gravity Sanitary Sewers 33 31 14 Polyvinyl Chloride (PVC) Gravity Sanitary Sewer Pipe 33 31 16 Sanitary Sewer Service Connections and Service Lines 33 31 23 Combination Air Valve for Sanitary Sewer Force Mains 33 32 11 Bypass Pumping of Existing Sewer Systems 33 42 11 Stormwater Pipe and Boxes 33 42 23 Stormwater Headwalls, Wingwalls, and End Treatments 33 42 30 Stormwater Junction Boxes 33 42 33 Stormwater Curb Inlets and Drop Inlets 33 46 00 Subdrainage 00 00 00 TABLE OF CONTENTS Page 4 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 15, 2021 Division 34 – Transportation 34 41 10 Signal Heads 34 41 11 Accessible Pedestrian Signal 34 41 12 Radar Detection Equipment and Cable 34 41 14 Video Imaging Vehicle Detection System (VIVDS) - 360 Degree Fish-Eye Camera 34 41 15 Emergency Vehicle Preemption Equipment and Cable 34 41 16 Battery Back-up System 34 41 21 Traffic Signal Structures 34 41 23 Treated Timber Poles 34 41 24 Drilled Shaft Foundations 34 41 26 LED Internally Illuminated Street Name Signs 34 41 27 Signal Controller and Cabinet Assembly 34 41 28 Traffic Signal LED Luminaire 34 41 29 Pan-Tilt Zoom Camera 34 41 32 Temporary Traffic Signals 34 41 33 Removing Traffic Signals 34 41 34 Rectangular Rapid Flashing Beacon 34 41 35 Pedestrian Hybrid Signal 34 41 50 Aluminum Signs and Signposts 34 71 13 Traffic Control Division 41 – Bulk Material Processing Equipment 41 14 00 Batching Equipment Appendix GC-5.01 Availability of Lands GC-5.03 Subsurface and Physical Conditions GC-5.05 Underground Facilities GC-5.06 Hazardous Environmental Condition at Site GC-7.08 Required Subcontractors GC-7.11 Permits and Utilities END OF SECTION 00 05 15 ADDENDA Page 1 of 1 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 15, 2021 SECTION 00 05 15 1 ADDENDA 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 END OF SECTION 22 00 11 13 INVITATION TO BIDDERS Page 1 of 2 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 15, 2021 SECTION 00 11 13 1 INVITATION TO BIDDERS 2 RECEIPT OF BIDS 3 Sealed bids for the construction of Baker Offsite Sewer will be received by the City of Denton 4 Purchasing Office as outlined at http://dentontx.ionwave.net/CurrentSourcingEvents.aspx. 5 6 GENERAL DESCRIPTION OF WORK 7 The major work will consist of the (approximate) following: 8 • ~ 4,100 LF of 18-Inch ASTM F679 PS-115 PVC by open cut and associated 9 appurtenances 10 • ~4,700 LF of 21-Inch ASTM F679 PS-115 PVC by open cut and associated 11 appurtenances 12 • ~100 LF of 36-Inch steel casing pipe by other than open cut with 21-Inch carrier pipe 13 (ASTM F679 PS-115 PVC). 14 • ~260 LF of 30-Inch steel casing pipe by other than open cut with 18-Inch carrier pipe 15 (ASTM F679 PS-115 PVC). 16 • 1 – Lift Station Abandonment with associated appurtenances, electrical equipment, and 17 force main pipe. 18 • 2 – Force Main PVC tie-in to proposed manhole. 19 20 DOCUMENT EXAMINATION AND PROCUREMENTS 21 The Bidding and Contract Documents may be examined or obtained on-line by visiting the City 22 of Denton’s Purchasing Division website at http://dentontx.ionwave.net. The Contract Documents 23 may be downloaded, viewed, and printed by interested contractors and/or suppliers. The 24 contractor is required to fill out the Certificate of Interested Parties Form 1295 and the 25 form must be submitted to the Project Manager before the contract will be presented to the 26 City Council. The form can be obtained at https://www.ethics.state.tx.us/tec/1295-Info.htm . 27 28 PREBID CONFERENCE 29 A prebid conference will be held as described in Section 00 21 13 - INSTRUCTIONS TO 30 BIDDERS at the following location, date, and time outlined in the City’s solicitation website. To 31 view pre-bid invitation log-in to your account at http://dentontx.ionwave.net, and click the 32 ‘Activities’ tab of this solicitation. 33 34 CITY'S RIGHT TO ACCEPT OR REJECT BIDS 35 City reserves the right to waive irregularities and to accept or reject bids. 36 37 00 11 13 INVITATION TO BIDDERS Page 2 of 2 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 15, 2021 INQUIRIES 1 All inquiries relative to this procurement should be addressed in the City’s solicitations website. 2 To submit and view questions log-in to your account at http://dentontx.ionwave.net, and click the 3 ‘Questions’ tab of this solicitation. 4 5 END OF SECTION 6 00 21 13 INSTRUCTIONS TO BIDDERS Page 1 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised January 31, 2024 Effective January 31, 2024 1 SECTION 00 21 13 2 INSTRUCTIONS TO BIDDERS 3 1. Defined Terms 4 5 1.1. Terms used in these INSTRUCTIONS TO BIDDERS, which are defined in Section 00 72 6 00 - GENERAL CONDITIONS. 7 8 1.2. Certain additional terms used in these INSTRUCTIONS TO BIDDERS have the 9 meanings indicated below which are applicable to both the singular and plural thereof. 10 11 1.2.1. Bidder: Any person, firm, partnership, company, association, or corporation acting 12 directly through a duly authorized representative, submitting a bid for performing 13 the work contemplated under the Contract Documents. 14 15 1.2.2. Nonresident Bidder: Any person, firm, partnership, company, association, or 16 corporation acting directly through a duly authorized representative, submitting a 17 bid for performing the work contemplated under the Contract Documents whose 18 principal place of business is not in the State of Texas. 19 20 1.2.3. Successful Bidder: The lowest responsible and responsive Bidder to whom City 21 (on the basis of City's evaluation as hereinafter provided) makes an award. 22 23 1.2.4. Purchasing Agent: City designated representative to assist in solicitation of bids 24 from vendors for City contracts. 25 26 2. Copies of Bidding Documents 27 28 2.1. Neither City nor Engineer shall assume any responsibility for errors or misinterpretations 29 resulting from the Bidders use of incomplete sets of Bidding Documents. 30 31 2.2. City and Engineer in making Bidding Documents available do so only for the purpose of 32 obtaining Bids for the Work and do not authorize or confer a license or grant for any 33 other use. 34 35 3. Minimum Qualifications 36 37 3.1. The following minimum requirements must be demonstrated in order for the submission 38 to be considered responsive. The form can be found in Section 00 45 13 – Bidder’s 39 Minimum Qualification Statement. 40 41 3.1.1. Bidder shall provide documentation demonstrating three (3) years minimum 42 experience providing services similar to those indicated in Section 00 11 13 – 43 Invitation to Bidders. 44 45 3.1.2. Bidder shall provide documentation of three (3) references from governmental 46 entities for which Bidder has performed similar services to those indicated in 47 Section 00 11 13 – Invitation to Bidders. 48 00 21 13 INSTRUCTIONS TO BIDDERS Page 2 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised January 31, 2024 Effective January 31, 2024 1 3.1.3. Bidder shall fill out provided safety record questionnaire. 2 3 4. Examination of Bidding and Contract Documents, Other Related Data, and Site 4 5 4.1. Before submitting a Bid, each Bidder shall: 6 7 4.1.1. Examine and carefully study the Contract Documents and other related data 8 identified in the Bidding Documents (including "technical data" referred to in 9 Paragraph 5.2 below). No information given by City or any representative of the 10 City other than that contained in the Contract Documents and officially 11 promulgated addenda thereto, shall be binding upon the City. 12 13 4.1.2. Visit the site to become familiar with and satisfy Bidder as to the general, local and 14 site conditions that may affect cost, progress, performance or furnishing of the 15 Work. 16 17 4.1.3. Consider federal, state and local Laws and Regulations that may affect cost, 18 progress, performance or furnishing of the Work. 19 20 4.1.4. Study all: (i) reports of explorations and tests of subsurface conditions at or 21 contiguous to the Site and all drawings of physical conditions relating to existing 22 surface or subsurface structures at the Site (except Underground Facilities) that 23 have been identified in the Contract Documents as containing reliable "technical 24 data" and (ii) reports and drawings of Hazardous Environmental Conditions, if any, 25 at the Site that have been identified in the Contract Documents as containing 26 reliable "technical data." 27 28 4.1.5. Be advised that the Contract Documents on file with the City shall constitute all of 29 the information which the City will furnish. All additional information and data 30 which the City will supply after promulgation of the formal Contract Documents 31 shall be issued in the form of written addenda and shall become part of the Contract 32 Documents just as though such addenda were actually written into the original 33 Contract Documents. No information given by the City other than that contained in 34 the Contract Documents and officially promulgated addenda thereto, shall be 35 binding upon the City. 36 37 4.1.6. Perform independent research, investigations, tests, borings, and such other means 38 as may be necessary to gain a complete knowledge of the conditions which will be 39 encountered during the construction of the project. On request, City may provide 40 each Bidder access to the site to conduct such examinations, investigations, 41 explorations, tests and studies as each Bidder deems necessary for submission of a 42 Bid. Bidder must fill all holes and clean up and restore the site to its former 43 conditions upon completion of such explorations, investigations, tests and studies. 44 45 00 21 13 INSTRUCTIONS TO BIDDERS Page 3 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised January 31, 2024 Effective January 31, 2024 4.1.7. Determine the difficulties of the Work and all attending circumstances affecting the 1 cost of doing the Work, time required for its completion, and obtain all information 2 required to make a proposal. Bidders shall rely exclusively and solely upon their 3 own estimates, investigation, research, tests, explorations, and other data which are 4 necessary for full and complete information upon which the proposal is to be based. 5 It is understood that the submission of a proposal is prima-facie evidence that the 6 Bidder has made the investigation, examinations and tests herein required. Claims 7 for additional compensation due to variations between conditions actually 8 encountered in construction and as indicated in the Contract Documents will not be 9 allowed. 10 11 4.1.8. Promptly notify City of all conflicts, errors, ambiguities or discrepancies in or 12 between the Contract Documents and such other related documents. The Contractor 13 shall not take advantage of any gross error or omission in the Contract Documents, 14 and the City shall be permitted to make such corrections or interpretations as may 15 be deemed necessary for fulfillment of the intent of the Contract Documents. 16 17 4.2. Reference is made to Section 00 73 00 – Supplementary Conditions for identification of: 18 19 4.2.1. those reports of explorations and tests of subsurface conditions at or contiguous to 20 the site which have been utilized by City in preparation of the Contract Documents. 21 The logs of Soil Borings, if any, on the plans are for general information only. 22 Neither the City nor the Engineer guarantee that the data shown is representative of 23 conditions which actually exist. 24 25 4.2.2. those drawings of physical conditions in or relating to existing surface and 26 subsurface structures (except Underground Facilities) which are at or contiguous to 27 the site that have been utilized by City in preparation of the Contract Documents. 28 29 4.2.3. copies of such reports and drawings will be made available by City to any Bidder 30 on request. Those reports and drawings may not be part of the Contract 31 Documents, but the "technical data" contained therein upon which Bidder is entitled 32 to rely as provided in Paragraph 5.03. of the General Conditions has been identified 33 and established in Paragraph SC 5.03 of the Supplementary Conditions. Bidder is 34 responsible for any interpretation or conclusion drawn from any "technical data" or 35 any other data, interpretations, opinions or information. 36 37 4.3. The submission of a Bid will constitute an incontrovertible representation by Bidder (i) 38 that Bidder has complied with every requirement of this Paragraph 5, (ii) that without 39 exception the Bid is premised upon performing and furnishing the Work required by the 40 Contract Documents and applying the specific means, methods, techniques, sequences or 41 procedures of construction (if any) that may be shown or indicated or expressly required 42 by the Contract Documents, (iii) that Bidder has given City written notice of all 43 conflicts, errors, ambiguities and discrepancies in the Contract Documents and the 44 written resolutions thereof by City are acceptable to Bidder, and when said conflicts, 45 etc., have not been resolved through the interpretations by City as described in 46 Paragraph 7, and (iv) that the Contract Documents are generally sufficient to indicate 47 and convey understanding of all terms and conditions for performing and furnishing the 48 Work. 49 50 00 21 13 INSTRUCTIONS TO BIDDERS Page 4 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised January 31, 2024 Effective January 31, 2024 4.4. The provisions of this Paragraph 5, inclusive, do not apply to Asbestos, Polychlorinated 1 biphenyls (PCBs), Petroleum, Hazardous Waste or Radioactive Material covered by 2 Paragraph 5.06. of the General Conditions, unless specifically identified in the Contract 3 Documents. 4 5 4.5. The Bidder acknowledges and agrees to comply with the requirements of City Ethics 6 Ordinance No. 23-1165. 7 8 5. Availability of Lands for Work, Etc. 9 10 5.1. The lands upon which the Work is to be performed, rights-of-way and easements for 11 access thereto and other lands designated for use by Contractor in performing the Work 12 are identified in the Contract Documents. All additional lands and access thereto 13 required for temporary construction facilities, construction equipment or storage of 14 materials and equipment to be incorporated in the Work are to be obtained and paid for 15 by Contractor. Easements for permanent structures or permanent changes in existing 16 facilities are to be obtained and paid for by City unless otherwise provided in the 17 Contract Documents. 18 19 5.2. Outstanding right-of-way, easements, and/or permits to be acquired by the City are listed 20 in Paragraph SC 5.01 of the Supplementary Conditions. In the event the necessary right-21 of-way, easements, and/or permits are not obtained, the City reserves the right to cancel 22 the award of contract at any time before the Bidder begins any construction work on the 23 project. 24 25 5.3. The Bidder shall be prepared to commence construction without all executed right-of-26 way, easements, and/or permits, and shall submit a schedule to the City of how 27 construction will proceed in the other areas of the project that do not require permits 28 and/or easements. 29 30 6. Interpretations and Addenda 31 32 6.1. All questions about the meaning or intent of the Bidding Documents are to be directed to 33 the City in Ionwave on or before the deadline advertised on this solicitation’s page at 34 http://dentontx.ionwave.net. Questions received after this day WILL NOT be 35 responded to. Interpretations or clarifications considered necessary by City in response 36 to such questions will be issued by Addenda delivered to all parties recorded by City as 37 having received the Bidding Documents or by responding to individual questions via this 38 solicitation’s page at http://dentontx.ionwave.net. Only questions answered by formal 39 written Addenda will be binding. Oral and other interpretations or clarifications will be 40 without legal effect. 41 42 Address questions for this solicitation’s IONWAVE page to the ‘Questions’ tab 43 (dentontx.ionwave.net). 44 45 6.2. Addenda may also be issued to modify the Bidding Documents as deemed advisable by 46 City. 47 48 00 21 13 INSTRUCTIONS TO BIDDERS Page 5 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised January 31, 2024 Effective January 31, 2024 6.3. Addenda or clarifications may be posted via the City’s online hosting site, which can be 1 located by visiting and logging-in to the City of Denton’s Purchasing solicitation website 2 at http://dentontx.ionwave.net and clicking on this solicitation’s link. 3 4 6.4. A pre-bid conference may be held at the time and place indicated in the Advertisement or 5 INVITATION TO BIDDERS. Representatives of City will be present to discuss the 6 Project. Bidders are encouraged to attend and participate in the conference. City will 7 transmit to all prospective Bidders of record such Addenda as City considers necessary 8 in response to questions arising at the conference. Oral statements may not be relied 9 upon and will not be binding or legally effective. 10 11 7. Bid Security 12 13 7.1. Each Bid for projects over $100,000, must be accompanied by Bid Bond made payable to 14 City in an amount of five (5) percent of Bidder's maximum Bid price on form attached, 15 issued by a surety meeting the requirements of Paragraphs 6.01 of the General 16 Conditions. 17 18 7.2. The Bid Bond of all Bidders will be retained until the conditions of the Notice of Award 19 have been satisfied. If the Successful Bidder fails to execute and deliver the complete 20 Agreement within 10 days after the Notice of Award, City may consider Bidder to be in 21 default, rescind the Notice of Award, and the Bid Bond of that Bidder will be forfeited. 22 Such forfeiture shall be City's exclusive remedy if Bidder defaults. The Bid Bond of all 23 other Bidders whom City believes to have a reasonable chance of receiving the award 24 will be retained by City until final contract execution. 25 26 8. Contract Times 27 The number of days within which, or the dates by which, Milestones are to be achieved in 28 accordance with the General Requirements and the Work is to be completed and ready for 29 Final Acceptance is set forth in the Agreement or incorporated therein by reference to the 30 attached Bid Form. 31 32 9. Liquidated Damages 33 Provisions for liquidated damages are set forth in the Agreement. 34 35 10. Substitute and "Or-Equal" Items 36 The Contract, if awarded, will be on the basis of materials and equipment described in the 37 Bidding Documents without consideration of possible substitute or "or-equal" items. 38 Whenever it is indicated or specified in the Bidding Documents that a "substitute" or "or-39 equal" item of material or equipment may be furnished or used by Contractor if acceptable to 40 City, application for such acceptance will not be considered by City until after the Effective 41 Date of the Agreement. The procedure for submission of any such application by Contractor 42 and consideration by City is set forth in Paragraphs 7.06 and 7.07 of the General Conditions 43 and is supplemented in Section 01 25 00 of the General Requirements. 44 45 11. Subcontractors, Suppliers and Others 46 47 11.1. No Contractor shall be required to employ any Subcontractor, Supplier, other person 48 or organization against whom Contractor has reasonable objection. 49 50 00 21 13 INSTRUCTIONS TO BIDDERS Page 6 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised January 31, 2024 Effective January 31, 2024 12. Bid Form 1 2 12.1. The Bid Form is included with the Bidding Documents; additional copies may be 3 obtained from the City. 4 5 12.2. All blanks on the Bid Form must be completed and the Bid Form signed. Erasures or 6 alterations shall be initialed by the person signing the Bid Form. A Bid price shall be 7 indicated for each Bid item, alternative, and unit price item listed therein. In the case 8 of optional alternatives, the words "No Bid," "No Change," or "Not Applicable" may 9 be entered. Bidder shall state the prices, in both words and numerals, for which the 10 Bidder proposes to do the work contemplated or furnish materials required. If 11 handwritten, all prices shall be written legibly. In case of discrepancy between price 12 in written/typed words and the price in written/typed numerals, the price in 13 written/typed words shall govern. 14 15 12.3. Bids by corporations shall be executed in the corporate name by the president or a 16 vice-president or other corporate officer accompanied by evidence of authority to 17 sign, as provided herein, Section 00 45 43 – Corporate Resolution of Authorized 18 Signatories. The corporate address and state of incorporation shall be shown below 19 the signature. 20 21 12.4. Bids by partnerships shall be executed in the partnership name and signed by a 22 partner, whose title must appear under the signature accompanied by evidence of 23 authority to sign. The official address of the partnership shall be shown below the 24 signature. 25 26 12.5. Bids by limited liability companies shall be executed in the name of the firm by a 27 member and accompanied by evidence of authority to sign. The state of formation of 28 the firm and the official address of the firm shall be shown. 29 30 12.6. Bids by individuals shall show the Bidder's name and official address. 31 32 12.7. Bids by joint ventures shall be executed by each joint venture in the manner indicated 33 on the Bid Form. The official address of the joint venture shall be shown. 34 35 12.8. All names shall be typed below the signature. 36 37 12.9. The Bid shall contain an acknowledgement of receipt of all Addenda, the numbers of 38 which shall be filled in on the Bid Form. 39 40 12.10. Postal and e-mail addresses and telephone number for communications regarding the 41 Bid shall be shown. 42 43 12.11. Evidence of authority to conduct business as a Nonresident Bidder in the state of 44 Texas shall be provided in accordance with Section 00 43 37 – Vendor Compliance 45 to State Law Non Resident Bidder. 46 47 13. Submission of Bids 48 49 00 21 13 INSTRUCTIONS TO BIDDERS Page 7 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised January 31, 2024 Effective January 31, 2024 13.1. Bids may be submitted electronically or by hard copy. Electronic submittals must be 1 submitted using this solicitation’s page in http://dentontx.ionwave.net. Electronic 2 submittals will not be accepted via email. 3 4 13.2. Hard copies of bid bonds shall be submitted for both electronic and hard copy 5 submissions. Bonds must be submitted in a sealed envelope before the due date and 6 time as indicated in Section 00 11 13 – Invitation to Bidders. 7 8 13.3. Bids shall be submitted on the prescribed Bid Form, provided with the Bidding 9 Documents, at the time and place indicated in the Advertisement or INVITATION 10 TO BIDDERS. 11 12 13.4. Hard copy submittals shall be enclosed in an opaque sealed envelope, marked with 13 the Bid Number, Project Title, the name and address of Bidder, and accompanied by 14 the Bid security and other required documents, as indicated in Section 00 41 00 – Bid 15 Form. If the Bid is sent through the mail or other delivery system, the sealed 16 envelope shall be enclosed in a separate envelope with the notation "BID 17 ENCLOSED" on the face of it. 18 19 13.5. Hard copy submissions shall also include a flash drive, containing a complete copy of 20 the response 21 22 13.6. Address Hard copy submissions as follows: 23 24 City of Denton 25 901-B Texas Street 26 Denton, TX 76209 27 Attn: Purchasing Division, IFB 8833 - Baker Offsite Sewer28 29 00 21 13 INSTRUCTIONS TO BIDDERS Page 8 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised January 31, 2024 Effective January 31, 2024 14. Modification and Withdrawal of Bids 1 2 14.1. Bids addressed to the Purchasing Agent and filed with the Purchasing Division may 3 be withdrawn prior to the time set for bid opening. A request for withdrawal must be 4 made in writing by an appropriate document duly executed in the manner that a Bid 5 must be executed and delivered to the place where Bids are to be submitted at any 6 time prior to the opening of Bids. After all Bids not requested for withdrawal are 7 opened and publicly read aloud, the Bids for which a withdrawal request has been 8 properly filed may, at the option of the City, be returned unopened. 9 10 14.2. Bidders may modify their Bid by electronic communication at any time prior to the 11 time set for the closing of Bid receipt. 12 13 15. Opening of Bids 14 15 15.1. Bids will be opened and read aloud publicly at the place where Bids are to be 16 submitted. An abstract of the amounts of the base Bids and major alternates (if any) 17 will be made available to Bidders after the opening of Bids. 18 19 16. Bids to Remain Subject to Acceptance 20 21 16.1. All Bids will remain subject to acceptance for the time period specified for Notice of 22 Award and execution and delivery of a complete Agreement by Successful Bidder. 23 City may, at City's sole discretion, release any Bid and nullify the Bid security prior 24 to that date. 25 26 17. Evaluation of Bids and Award of Contract 27 28 17.1. City reserves the right to reject any or all Bids, including without limitation the rights 29 to reject any or all nonconforming, nonresponsive, unbalanced or conditional Bids 30 and to reject the Bid of any Bidder if City believes that it would not be in the best 31 interest of the Project to make an award to that Bidder, whether because the Bid is 32 not responsive or the Bidder is unqualified or of doubtful financial ability or fails to 33 meet any other pertinent standard or criteria established by City. City also reserves 34 the right to waive informalities not involving price, contract time or changes in the 35 Work with the Successful Bidder. Discrepancies between the multiplication of units 36 of Work and unit prices will be resolved in favor of the unit prices. Discrepancies 37 between the indicated sum of any column of figures and the correct sum thereof will 38 be resolved in favor of the correct sum. Discrepancies between words and figures 39 will be resolved in favor of the words. 40 41 17.1.1. The Bid is not signed by a person empowered to bind the Offeror. 42 17.1.2. The Bid is not accompanied by an acceptable Bid Bond, with Power of Attorney 43 attached. 44 17.1.3. The Bid is submitted by an Offeror that has submitted more than one Bid. 45 17.1.4. There is evidence of collusion between the Offeror submitting the Proposal and 46 one or more other Offerors. 47 17.1.5. The Bidder did not attend or have an authorized agent attend a mandatory Pre-48 Proposal Conference, if applicable. 49 17.1.6. The Bidder is under debarment or suspension by the Owner. 50 00 21 13 INSTRUCTIONS TO BIDDERS Page 9 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised January 31, 2024 Effective January 31, 2024 17.1.7. The Bidder or a principal of the Bidder is currently debarred or suspended by a 1 Federal, State or local governmental agency. (Applicable for Proposal amounts 2 equal to or in excess of $25,000.00) 3 17.1.8. The Bidder is an interested party to any litigation against City, or City or Offeror 4 may have a claim against the other or be engaged in litigation, or Offeror is in 5 arrears on any existing contract or has defaulted on a previous contract. 6 17.1.9. The Bidder has performed a prior contract in an unsatisfactory manner. 7 17.1.10. The Bidder has uncompleted work which in the judgement of the City will 8 prevent or hinder the prompt completion of additional work if awarded. 9 17.1.11. Incompleteness or an omission, alteration of form, or addition, or the inclusion of 10 a qualification or condition not called for or authorized in the Bid Documents. 11 17.1.12. Ambiguity or lack of clarity in a Bid, in which case the City reserves the right to 12 interpret the Bid in the most advantageous manner for the City, or to reject the 13 Bid. 14 17.1.13. Failure to acknowledge receipt of Addenda. 15 17.1.14. Failure to identify a dollar amount for one or more unit prices required to be 16 provided in the Unit Price Proposal Form. 17 17.1.15. Failure to submit post-bid information within the allotted time(s). 18 17.1.16. Failure to timely execute and deliver the Contract to the City after award. 19 20 17.2. City may consider the qualifications and experience of Subcontractors, Suppliers, and 21 other persons and organizations proposed for those portions of the Work as to which 22 the identity of Subcontractors, Suppliers, and other persons and organizations must 23 be submitted as provided in the Contract Documents or upon the request of the City. 24 City also may consider the operating costs, maintenance requirements, performance 25 data and guarantees of major items of materials and equipment proposed for 26 incorporation in the Work when such data is required to be submitted prior to the 27 Notice of Award. 28 29 17.3. City may conduct such investigations as City deems necessary to assist in the 30 evaluation of any Bid and to establish the responsibility, qualifications, and financial 31 ability of Bidders, proposed Subcontractors, Suppliers and other persons and 32 organizations to perform and furnish the Work in accordance with the Contract 33 Documents to City's satisfaction within the prescribed time. 34 35 17.4. Contractor shall perform with his own organization, work of a minimum value as 36 outlined in Section 00 43 36 – Proposed Subcontractors Form, unless otherwise 37 approved by the City. Contractor shall complete and submit Section 00 43 36 – 38 Proposed Subcontractors Form. 39 40 17.5. If the Contract is to be awarded, it will be awarded to lowest responsible and 41 responsive Bidder whose evaluation by City indicates that the award will be in the 42 best interests of the City. 43 44 17.6. Additional approvals could be required if outside funding is used. 45 46 00 21 13 INSTRUCTIONS TO BIDDERS Page 10 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised January 31, 2024 Effective January 31, 2024 17.7. Pursuant to Texas Government Code Chapter 2252.001, the City will not award 1 contract to a Nonresident Bidder unless the Nonresident Bidder’s bid is lower than 2 the lowest bid submitted by a responsible Texas Bidder by the same amount that a 3 Texas resident bidder would be required to underbid a Nonresident Bidder to obtain a 4 comparable contract in the state in which the nonresident’s principal place of 5 business is located. 6 7 17.8. A contract is not awarded until formal City Council authorization. If the Contract is 8 to be awarded, City will award the Contract within 120 days after the day of the Bid 9 opening unless extended in writing. No other act of City or others will constitute 10 acceptance of a Bid. Upon the contractor award a Notice of Award will be issued by 11 the City. 12 13 17.9. Failure or refusal to comply with the requirements may result in rejection of Bid. 14 15 17.10. Contractor is required to fill out the Certificate of Interested Parties Form 1295 and 16 the form must be submitted to the City Project Manager before the contract will be 17 presented to the City Council. The form can be obtained at 18 https://www.ethics.state.tx.us/tec/1295-Info.htm. 19 20 18. Signing of Agreement 21 22 18.1. When City issues a Notice of Award to the Successful Bidder, it will be accompanied 23 by the required number of unsigned counterparts of the Agreement. Within 14 days 24 thereafter Contractor shall sign and deliver the required number of counterparts of the 25 Agreement to City with the required Bonds, Certificates of Insurance, and all other 26 required documentation. City shall thereafter deliver one fully signed counterpart to 27 Contractor. 28 29 END OF SECTION 30 00 35 13 CONFLICT OF INTEREST AFFIDAVIT Page 1 of 1 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 15, 2021 SECTION 00 35 13 1 CONFLICT OF INTEREST AFFIDAVIT 2 END OF SECTION 3 CONFLICT OF INTEREST QUESTIONNAIRE - FORM CIQ For vendor or other person doing business with local governmental entity This questionnaire reflects changes made to the law by H.B. 23, 84th Leg., Regular Session. This questionnaire is being filed in accordance with Chapter 176, Local Government Code, by a vendor who has a business relationship as defined by Section 176.001(1-a) with a local governmental entity and the vendor meets requirements under Section 176.006(a). By law this questionnaire must be filed with the records administrator of the local government entity not later than the 7th business day after the date the vendor becomes aware of facts that require the statement to be filed. See Section 176.006(a-1), Local Government Code. A vendor commits an offense if the vendor knowingly violates Section 176.006, Local Government Code. An offense under this section is a misdemeanor. 1 Name of vendor who has a business relationship with local governmental entity. 2 Check this box if you are filing an update to a previously filed questionnaire. (The law requires that you file an updated completed questionnaire with the appropriate filing authority not later than the 7th business day after the date on which you became aware that the originally filed questionnaire was incomplete or inaccurate.) 3 Name of local government officer about whom the information in this section is being disclosed. Name of Officer This section, (item 3 including subparts A, B, C & D), must be completed for each officer with whom the vendor has an employment or other business relationship as defined by Section 176.001(1-a), Local Government Code. Attach additional pages to this Form CIQ as necessary. A. Is the local government officer named in this section receiving or likely to receive taxable income, other than investment income, from the vendor? Yes No B. Is the vendor receiving or likely to receive taxable income, other than investment income, from or at the direction of the local government officer named in this section AND the taxable income is not received from the local governmental entity? Yes No C. Is the filer of this questionnaire employed by a corporation or other business entity with respect to which the local government officer serves as an officer or director, or holds an ownership of one percent or more? Yes No D. Describe each employment or business and family relationship with the local government officer named in this section. 4 I have no Conflict of Interest to disclose. 5 Signature of vendor doing business with the governmental entity Date 00 41 00 BID FORM Page 1 of 3 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised January 31, 2024 Effective January 31, 2024 SECTION 00 41 00 1 BID FORM 2 TO: City of Denton 3 c/o: Purchasing Division 4 901-B Texas Street 5 Denton, Texas 76209 6 7 FOR: IFB 8833 – Baker Offsite Sewer 8 9 1 Enter Into Agreement 10 11 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement 12 with City in the form included in the Bidding Documents to perform and furnish all Work as 13 specified or indicated in the Contract Documents for the Bid Price and within the Contract Time 14 indicated in this Bid and in accordance with the other terms and conditions of the Contract 15 Documents. 16 17 2 BIDDER Acknowledgements and Certification 18 19 2.1 In submitting this Bid, Bidder accepts all of the terms and conditions of the INVITATION 20 TO BIDDERS and INSTRUCTIONS TO BIDDERS, including without limitation those 21 dealing with the disposition of Bid Bond. 22 2.2 Bidder is aware of all costs to provide the required insurance, will do so pending contract 23 award, and will provide a valid insurance certificate meeting all requirements within 14 24 days of notification of award. 25 2.3 Bidder certifies that this Bid is genuine and not made in the interest of or on behalf of any 26 undisclosed individual or entity and is not submitted in conformity with any collusive 27 agreement or rules of any group, association, organization, or corporation. 28 2.4 Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false 29 or sham Bid. 30 2.5 Bidder has not solicited or induced any individual or entity to refrain from bidding. 31 2.6 Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing 32 for the Contract. For the purposes of this Paragraph: 33 a. "corrupt practice" means the offering, giving, receiving, or soliciting of anything 34 of value likely to influence the action of a public official in the bidding process. 35 36 b. "fraudulent practice" means an intentional misrepresentation of facts made (a) to 37 influence the bidding process to the detriment of City (b) to establish Bid prices 38 at artificial non-competitive levels, or (c) to deprive City of the benefits of free 39 and open competition. 40 41 c. "collusive practice" means a scheme or arrangement between two or more 42 Bidders, with or without the knowledge of City, a purpose of which is to 43 establish Bid prices at artificial, non-competitive levels. 44 45 d. "coercive practice" means harming or threatening to harm, directly or indirectly, 46 persons or their property to influence their participation in the bidding process or 47 affect the execution of the Contract. 48 00 41 00 BID FORM Page 2 of 3 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised January 31, 2024 Effective January 31, 2024 1 2.7 The Bidder acknowledges and agrees to comply with the requirements of City Ethics 2 Ordinance No. 23-1165. 3 4 3 Time of Completion 5 6 3.1 The Work will be complete for Final Acceptance within 300 Working Days after the date 7 when the Contract Time commences to run, which is the day indicated in the Notice to 8 Proceed, plus any extension thereof allowed in accordance with Article 11 of the General 9 Conditions. 10 11 3.2 Bidder accepts the provisions of the Agreement as to Liquidated Damages in the event of 12 failure to obtain Milestones (if applicable) and Final Acceptance within the times specified 13 in the Agreement. 14 15 4 Attached to this Bid 16 17 The following documents are attached to and made a part of this Bid: 18 a. Section 00 35 13 – Conflict of Interest Affidavit 19 b. Section 00 41 00 – This Bid Form 20 c. Section 00 42 43 – Unit Price Proposal Form – Electronic Copy (either included 21 in the Bid, or submitted via Ion Wave) 22 d. Section 00 42 13 – Required Bid Bond, issued by a surety meeting the requirements 23 of Paragraph 6.01 of the General Conditions 24 e. Section 00 43 36 – Proposed Subcontractors Form 25 f. Section 00 43 37 – Vendor Compliance to State Law Non-Resident Bidder 26 g. Section 00 45 13 – Bidders Minimum Qualification Statement 27 h. Section 00 45 26 – Contractor Compliance with Workers Compensation Law 28 i. Section 00 45 43 – Corporate Resolution of Authorized Signatories 29 j. Any additional documents that may be required by Section 00 21 13 – Instructions to 30 Bidders 31 32 33 00 41 00 BID FORM Page 3 of 3 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised January 31, 2024 Effective January 31, 2024 5 Total Bid Amount 1 2 5.1 3 4 5 5.2 6 7 8 9 10 5.3 Bidder will complete the Work in accordance with the Contract Documents for the following bid amount. In the space provided below, please enter the total bid amount for this project. Only this figure will be read publicly by the City at the bid opening. It is understood and agreed by the Bidder in signing this proposal that the total bid amount entered below is subject to verification and/or modification by multiplying the unit bid prices for each pay item by the respective estimated quantities shown in this proposal and then totaling all of the extended amounts. Evaluation of Alternate Bid Items 11 12 Total Bid Amount: $____________________________ 13 14 15 16 17 18 6 Bid Submittal 19 20 This Bid is submitted on _____________________________, 20___ by the entity named below. 21 22 23 Respectfully submitted, 24 25 By: ______________________________ 26 (Signature) 27 28 _________________________________ 29 (Printed Name) 30 31 Title: _____________________________ 32 33 Company: _________________________ 34 35 Address: __________________________ 36 ___________________________ 37 State of Incorporation: _______________ 38 Email: ____________________________ 39 Phone: ____________________________ 40 41 END OF SECTION 42 Receipt is acknowledged of the following Addenda: Initial Addenda No. 1: Addenda No. 2: Addenda No. 3: Addenda No. 4: Addenda No. 5: To:From: IFB:8833 ENG PMO: Item No.Spec. Section No.Description UOM BID QTY Unit Price Extended Price 1 00 61 13 PERFORMACE BOND EA 1 2 00 61 14 PAYMENT BOND EA 1 3 00 61 19 MAINTENANCE BOND EA 1 4 01 11 00 SURVEY, PLATTING, ENGINEERING, PERMITTING & CPS EA 1 5 01 11 00 MISCELLANEOUS PERMITTING FEE ALLOWANCE EA 1 6 01 45 23 TESTING (PRESSURE & T.V.)LF 9,105 7 01 45 23 TESTING (GEOTECH)LF 9,105 8 01 45 23 INSPECTION FEE EA 1 9 01 50 00 TEMPORARY CONSTRUCTION EASEMENT ACQUISITION SF 225,000 10 01 57 13 SWPPP, INSPECTION, MAINTENANCE, & OTHER LS 1 11 01 74 23 CLEANING AND GRUBBING AC 9 12 02 41 13 FENCE REMOVAL AND REPLACEMENT IN KIND LS 1 13 02 41 13 OPEN CUT AND REPLACE EXISTING GRAVEL DRIVE SY 3,373 14 02 41 15 DEMOLISH EXISTING LIFT STATION LS 2 15 02 41 15 REMOVAL OF EXISTING SANITARY SEWER FORCE MAIN (SAME TRENCH)LF 1,019 16 31 10 00 ESA RESTORATION ALLOWANCE LS 1 17 31 23 16 TRENCH SAFETY LF 9,105 18 31 25 14 EROSION CONTROL (SILT FENCE)LF 11,700 19 31 25 14 CONSTRUCTION ENTRANCE LS 1 20 31 37 00 12'' STONE RIPRAP, GROUTED (ASSUMES 1.5' OF DEPTH)CY 180 21 33 05 07 30'' STEEL CASING BY OTHER THAN OPEN CUT (1/2'' THICK)LF 263 22 33 05 07 36'' STEEL CASING BY OTHER THAN OPEN CUT (5/8'' THICK)LF 106 23 33 05 10 SEWER LINE BORE LF 369 24 33 05 61 4' DIAMETER CONCRETE MANHOLE (0' - 6') AND LINER EA 2 25 33 05 61 5' DIAMETER CONCRETE MANHOLE (0' - 6') AND LINER EA 17 26 33 05 61 5' DIAMETER CONCRETE MANHOLE AND LINER EXTRA DEPTH VF 117 27 33 05 62 5' DIAMETER MONOLITHICALLY PRECAST FIBERGLASS MANHOLE (0' - 6')EA 2 28 33 05 62 5' DIAMETER MONOLITHICALLY PRECAST FIBERGLASS MANHOLE EXTRA DEPTH VF 17 29 33 05 62 5' DIAMETER MONOLITHICALLY PRECAST FIBERGLASS DROP MANHOLE PLACED ON EXISTING LINE (0' - 6')EA 1 30 33 05 62 5' DIAMETER MONOLITHICALLY PRECAST FIBERGLASS DROP MANHOLE PLACED ON EXISTING LINE (0' - 6')VF 19 31 33 14 13 8'' ATSM F679 PS-115 PVC SANTITARY SEWER PIPE LF 420 32 33 14 13 18'' ATSM F679 PS-115 PVC SANTITARY SEWER PIPE LF 4,274 33 33 14 13 21'' ATSM F679 PS-115 PVC SANTITARY SEWER PIPE LF 4,831 34 33 14 13 18'' ASTM F679 PS-115 PVC SANITARY SEWER CARRIER PIPE LF 263 35 33 14 13 21'' ASTM F679 PS-115 PVC SANITARY SEWER CARRIER PIPE LF 106 36 33 32 11 BYPASS PUMPING ALLOWANCE (EX. SERVICE & MAINS)LS 1 -$ Baker Offsite Sewer TOTAL PROJECT BID AMOUNT: PROJ.: 901-B Texas Street Denton, TX 76209 BIDDERS APPLICATION - UNIT PRICE BID STREET ADDRESS CITY, STATE CONTACT PHONE EMAIL SECTION 00 42 43 - UNIT PRICE BID FORM Purchasing Dept. Baker Offsite Sewer City of Denton - Capital Projects COMPANY NAME 00 43 13 BID BOND Page 1 of 2 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 15, 2021 SECTION 00 43 13 1 BID BOND 2 3 KNOW ALL BY THESE PRESENTS: 4 That we, (Bidder Name)___________________________________________________, 5 known as “Principal” herein, and (Surety Name)_____________________________________, a 6 corporate surety duly authorized to do business in the State of Texas, known as “Surety” herein, 7 are held and firmly bound unto the City of Denton, a Texas home-rule municipal corporation 8 created pursuant to the laws of Texas, known as “City” herein, in the penal sum of five percent 9 (5%) of Bidder’s maximum bid price, in lawful money of the United States, to be paid in Denton, 10 Denton County, Texas for the payment of which sum well and truly to be made, we bind 11 ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, 12 firmly by these presents. 13 WHEREAS, the Principal has submitted a proposal to perform work for the following 14 project designated as 15 IFB 8833 – Baker Offsite Sewer 16 17 NOW, THEREFORE, the condition of this obligation is such that if the City shall 18 award the Contract for the foregoing project to the Principal, and the Principal shall satisfy all 19 requirements and conditions required for the execution of the Contract and shall enter into the 20 Contract in writing with the City in accordance with the terms of such same, then this obligation 21 shall be and become null and void. If, however, the Principal fails to execute such Contract in 22 accordance with the terms of same or fails to satisfy all requirements and conditions required for 23 the execution of the Contract, this bond shall become the property of the City, without recourse of 24 the Principal and/or Surety, not to exceed the penalty hereof, and shall be used to compensate 25 City for the difference between Principal’s total bid amount and the next selected bidder’s total 26 bid amount. 27 PROVIDED FURTHER, that if any legal action be filed on this Bond, venue shall lie in 28 the state district court of Denton County, Texas. 29 30 00 43 13 BID BOND Page 2 of 2 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 15, 2021 IN WITNESS WHEREOF, the Principal and the Surety have SIGNED and SEALED 1 this instrument by duly authorized agents and officers on this the _______ day of 2 ____________________, 20___. 3 4 5 By: ___________________________________________________________________________ 6 (Principal Name) 7 8 ______________________________________________________________________________ 9 (Signature and Title of Principal) 10 11 *By: __________________________________________________________________________ 12 (Surety Name) 13 14 ______________________________________________________________________________ 15 (Signature of Attorney-in-Fact) 16 17 *Attach Power of Attorney (Surety) for Attorney-in-Fact 18 END OF SECTION 19 Impressed Surety Seal Only 00 43 36 PROPOSED SUBCONTRACTORS FORM Page 1 of 1 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 15, 2021 SECTION 00 43 36 1 PROPOSED SUBCONTRACTORS FORM 2 3 Each Bidder for a City procurement is required to complete the information below by identifying 4 the proposed subcontractors whom they intend to utilize and the approximate percentage of the 5 overall contract that will be allocated to each entity. Bidder is reminded that a minimum of 35% 6 of the Contract must be performed by Bidder’s company. 7 8 Company Name Type of Work to be Performed Overall Contract Percentage (%) General Contractor: Subcontractors: 9 10 The undersigned hereby certifies that the subcontractors described in the table above will 11 be utilized for this project at the approximate percentage levels indicated above. 12 13 BIDDER: 14 15 _____________________________________ By: ___________________________________ 16 Company (Please Print) 17 18 _____________________________________ Signature: ______________________________ 19 Address 20 21 _____________________________________ Title: __________________________________ 22 City/State/Zip (Please Print) 23 24 Date: __________________________________ 25 26 END OF SECTION 27 00 43 37 VENDOR COMPLIANCE TO STATE LAW Page 1 of 1 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 15, 2021 SECTION 00 43 37 1 VENDOR COMPLIANCE TO STATE LAW NON- RESIDENT BIDDER 2 3 Texas Government Code Chapter 2252 was adopted for the award of contracts to nonresident 4 bidders. This law provides that, in order to be awarded a contract as low bidder, nonresident 5 bidders (out-of-state contractors whose corporate offices or principal place of business are outside 6 the State of Texas) bid projects for construction, improvements, supplies or services in Texas at 7 an amount lower than the lowest Texas resident bidder by the same amount that a Texas resident 8 bidder would be required to underbid a nonresident bidder in order to obtain a comparable 9 contract in the State which the nonresident’s principal place of business is located. 10 The appropriate blanks in Section A must be filled out by all nonresident bidders in order for your 11 bid to meet specifications. The failure of nonresident bidders to do so will automatically 12 disqualify that bidder. Resident bidders must check the box in Section B. 13 A. Nonresident bidders in the State of ______________________, our principal place of 14 business, are required to be ________________ percent lower than resident bidders by State 15 Law. A copy of the statute is attached. 16 Nonresident bidders in the State of _____________________, our principal place of business, 17 are not required to underbid resident bidders. 18 B. The principal place of business of our company or our parent company or majority owner is 19 in the State of Texas. 20 21 BIDDER: 22 23 _____________________________________ By: ___________________________________ 24 Company (Please Print) 25 26 _____________________________________ Signature: ______________________________ 27 Address 28 29 _____________________________________ Title: __________________________________ 30 City/State/Zip (Please Print) 31 32 Date: __________________________________ 33 34 END OF SECTION 35 00 45 13 BIDDER'S MINIMUM QUALIFICATION STATEMENT Page 1 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 15, 2021 SECTION 00 45 13 1 BIDDER'S MINIMUM QUALIFICATION STATEMENT 2 3 List three (3) Government references, other than the City of Denton, who can verify the quality of service 4 your company provides. The City prefers customers of similar size and scope of work to this solicitation. 5 6 REFERENCE ONE 7 GOVERNMENT/COMPANY NAME: 8 LOCATION: 9 CONTACT PERSON AND TITLE: 10 TELEPHONE NUMBER: 11 SCOPE OF WORK: 12 CONTRACT PERIOD: 13 14 REFERENCE TWO 15 GOVERNMENT/COMPANY NAME: 16 LOCATION: 17 CONTACT PERSON AND TITLE: 18 TELEPHONE NUMBER: 19 SCOPE OF WORK: 20 CONTRACT PERIOD: 21 22 REFERENCE THREE 23 GOVERNMENT/COMPANY NAME: 24 LOCATION: 25 CONTACT PERSON AND TITLE: 26 TELEPHONE NUMBER: 27 SCOPE OF WORK: 28 CONTRACT PERIOD: 29 30 31 32 33 00 45 13 BIDDER'S MINIMUM QUALIFICATION STATEMENT Page 2 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 15, 2021 PROJECT INFORMATION FORM 1 2 Detail three (3) of the most recent projects Bidder’s firm has completed providing 3 services similar to this project: 4 5 Project #1 6 Name of Project: 7 8 Project Owner Name, Address and Phone Number: 9 10 Original Contract Amount: 11 12 Final Contract Amount: 13 14 Contract Time Allotted (Calendar Days): 15 16 Start Date for Project: 17 18 Final Completion Date for Project: 19 20 Number of Days to complete (calendar days): 21 22 23 Detail the project, including size, length, and materials used. Also describe any known contractual issues, 24 successes, or potential problems and solutions encountered. 25 26 _________________________________________________________________________________________27 _________________________________________________________________________________________28 _________________________________________________________________________________________29 _________________________________________________________________________________________30 _________________________________________________________________________________________31 _________________________________________________________________________________________32 _________________________________________________________________________________________33 _________________________________________________________________________________________34 _________________________________________________________________________________________35 _________________________________________________________________________________________36 _________________________________________________________________________________________37 _________________________________________________________________________________________ 38 39 00 45 13 BIDDER'S MINIMUM QUALIFICATION STATEMENT Page 3 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 15, 2021 1 PROJECT INFORMATION FORM 2 3 4 5 6 Project #2 7 Name of Project: 8 9 Project Owner Name, Address and Phone Number: 10 11 Original Contract Amount: 12 13 Final Contract Amount: 14 15 Contract Time Allotted (Calendar Days): 16 17 Start Date for Project: 18 19 Final Completion Date for Project: 20 21 Number of Days to complete (calendar days): 22 23 24 Detail the project, including size, length, and materials used. Also describe any known contractual issues, 25 successes, or potential problems and solutions encountered. 26 27 _________________________________________________________________________________________28 _________________________________________________________________________________________29 _________________________________________________________________________________________30 _________________________________________________________________________________________31 _________________________________________________________________________________________32 _________________________________________________________________________________________33 _________________________________________________________________________________________34 _________________________________________________________________________________________35 _________________________________________________________________________________________36 _________________________________________________________________________________________37 _________________________________________________________________________________________38 _________________________________________________________________________________________39 _________________________________________________________________________________________40 __ 41 42 00 45 13 BIDDER'S MINIMUM QUALIFICATION STATEMENT Page 4 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 15, 2021 1 PROJECT INFORMATION FORM 2 3 4 5 Project #3 6 Name of Project: 7 8 Project Owner Name, Address and Phone Number: 9 10 Original Contract Amount: 11 12 Final Contract Amount: 13 14 Contract Time Allotted (Calendar Days): 15 16 Start Date for Project: 17 18 Final Completion Date for Project: 19 20 Number of Days to complete (calendar days): 21 22 23 Detail the project, including size, length, and materials used. Also describe any known contractual issues, 24 successes, or potential problems and solutions encountered. 25 26 _________________________________________________________________________________________27 _________________________________________________________________________________________28 _________________________________________________________________________________________29 _________________________________________________________________________________________30 _________________________________________________________________________________________31 _________________________________________________________________________________________32 _________________________________________________________________________________________33 _________________________________________________________________________________________34 _________________________________________________________________________________________35 _________________________________________________________________________________________36 _________________________________________________________________________________________37 _________________________________________________________________________________________38 _________________________________________________________________________________________39 __ 40 41 00 45 13 BIDDER'S MINIMUM QUALIFICATION STATEMENT Page 5 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 15, 2021 SAFETY RECORD QUESTIONNAIRE 1 2 The City of Denton desires to avail itself of the benefits of Section 252.0435 of the Local 3 Government Code, and consider the safety records of potential contractors prior to award of City 4 contracts. Pursuant to Section 252.0435 of the Local Government Code, the City of Denton has 5 adopted the following written definition and criteria for accurately determining the safety record 6 of a respondent prior to awarding City contracts. 7 8 The definition and criteria for determining the safety record of a respondent for this consideration 9 shall be: 10 11 The City of Denton shall consider the safety record of the respondent in determining the 12 responsibility thereof. The City may consider any incidence involving worker safety or 13 safety of the citizens of the City of Denton, be it related or caused by environmental, 14 mechanical, operational, supervision or any other cause or factor. Specifically, the City 15 may consider, among other things: 16 A. Complaints to, or final orders entered by, the Occupational Safety and Health Review 17 Commission (OSHRC), against the respondent for violations of OSHA regulations 18 within the past three (3) years. 19 B. Citations (as defined below) from an Environmental Protection Agency (as defined 20 below) for violations within the past five (5) years. Environmental Protection 21 Agencies include, but are not necessarily limited to, the U.S. Army Corps of 22 Engineers (USACOE), the U.S. Fish and Wildlife Service (USFWS), the 23 Environmental Protection Agency (EPA), the Texas Commission on Environmental 24 Quality (TCEQ), the Texas Natural Resource Conservation Commission (TNRCC) 25 (predecessor to the TCEQ), the Texas Department of Health (TDH), the Texas Parks 26 and Wildlife Department (TPWD), the Structural Pest Control Board (SPCB), 27 agencies of local governments responsible for enforcing environmental protection or 28 worker safety related laws or regulations, and similar regulatory agencies of other 29 states of the United States. Citations include notices of violation, notices of 30 enforcement, suspension/revocations of state or federal licenses or registrations, fines 31 assessed, pending criminal complaints, indictments, or convictions, administrative 32 orders, draft orders, final orders, and judicial final judgments. 33 C. Convictions of a criminal offense within the past ten (10) years, which resulted in 34 bodily harm or death. 35 D. Any other safety related matter deemed by the City Council to be material in 36 determining the responsibility of the respondent and his or her ability to perform the 37 services or goods required by the solicitation documents in a safe environment, both 38 for the workers and other employees of respondent and the citizens of the City of 39 Denton. 40 41 In order to obtain proper information from respondents so that City of Denton may consider the 42 safety records of potential contractors prior to awarding bids on City contracts, City of Denton 43 requires that respondents answer the following three (3) questions and submit them with their 44 submissions: 45 46 47 00 45 13 BIDDER'S MINIMUM QUALIFICATION STATEMENT Page 6 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 15, 2021 QUESTION ONE 1 2 Has the respondent, or the firm, corporation, partnership, or institution represented by the 3 respondent, or anyone acting for such firm, corporation, partnership or institution, received 4 citations for violations of OSHA within the past three (3) years? 5 6 YES NO 7 8 If the respondent has indicated YES for question number one above, the respondent must provide 9 to City of Denton, with its submission, the following information with respect to each such 10 citation: 11 12 Date of offense, location of establishment inspected, category of offense, final disposition of 13 offense, if any, and penalty assessed. 14 15 QUESTION TWO 16 17 Has the respondent, or the firm, corporation, partnership, or institution represented by the 18 respondent, or anyone acting for such firm, corporation, partnership or institution, received 19 citations for violations of environmental protection laws or regulations, of any kind or type, 20 within the past five years? Citations include notice of violation, notice of enforcement, 21 suspension/revocations of state or federal licenses, or registrations, fines assessed, pending 22 criminal complaints, indictments, or convictions, administrative orders, draft orders, final orders, 23 and judicial final judgments. 24 25 YES NO 26 27 If the respondent has indicated YES for question number two above, the respondent must provide 28 to City of Denton, with its submission, the following information with respect to each such 29 conviction: 30 31 Date of offense or occurrence, location where offense occurred, type of offense, final disposition 32 of offense, if any, and penalty assessed. 33 34 QUESTION THREE 35 36 Has the respondent, or the firm, corporation, partnership, or institution represented by respondent, 37 or anyone acting for such firm, corporation, partnership, or institution, ever been convicted, 38 within the past ten (10) years, of a criminal offense which resulted in serious bodily injury or 39 death? 40 41 YES NO 42 43 If the respondent has indicated YES for question number three above, the respondent must 44 provide to City of Denton, with its submission, the following information with respect to each 45 such conviction: 46 Date of offense, location where offense occurred, type of offense, final disposition of offense, if 47 any, and penalty assessed. 48 49 00 45 13 BIDDER'S MINIMUM QUALIFICATION STATEMENT Page 7 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 15, 2021 Bidder must provide records, with its submission, supporting the Safety Record Rates for the past 1 5 years listed below: 2 3 Experience Modification Rate (EMR) 4 5 2025: _____________ 6 2024: _____________ 7 2023: _____________ 8 2022: _____________ 9 2021: _____________ Total Recordable Incident Rate (TRIR) 10 11 2025: _____________ 12 2024: _____________ 13 2023: _____________ 14 2022: _____________ 15 2021: _____________ 16 END OF SECTION 17 00 45 26 CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW Page 1 of 1 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Bakr Offsite Sewer Revised November 23, 2020 Effective January 15, 2021 SECTION 00 45 26 1 CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW 2 3 Pursuant to Texas Labor Code Section 406.096(a), as amended, Contractor certifies that it 4 provides worker’s compensation insurance coverage for all of its employees employed on Baker 5 Offsite Sewer. Contractor further certifies that, pursuant to Texas Labor Code, Section 6 406.096(b), as amended, it will provide to City its subcontractor’s certificates of compliance with 7 worker’s compensation coverage. 8 9 CONTRACTOR: 10 11 _____________________________________ By: ___________________________________ 12 Company (Please Print) 13 14 _____________________________________ Signature: ______________________________ 15 Address 16 17 _____________________________________ Title: __________________________________ 18 City/State/Zip (Please Print) 19 20 21 THE STATE OF TEXAS § 22 23 COUNTY OF DENTON § 24 25 BEFORE ME, the undersigned authority, on this day personally appeared 26 ___________________________________, known to me to be the person whose name is 27 subscribed to the foregoing instrument, and acknowledged to me that he/she executed the same as 28 the act and deed of ____________________________________ for the purposes and 29 consideration therein expressed and in the capacity therein stated. 30 31 GIVEN UNDER MY HAND AND SEAL OF OFFICE this ____________day of 32 _______________________, 20__. 33 34 35 __________________________________ 36 Notary Public in and for the State of Texas 37 38 END OF SECTION 39 40 00 45 43 CORPORATE RESOLUTION AUTHORIZING SIGNATORIES Page 1 of 1 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 15, 2021 SECTION 00 45 43 1 CORPORATE RESOLUTION AUTHORIZING SIGNATORIES 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 END OF SECTION 23 00 52 43 AGREEMENT Page 1 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 21, 2021 1 SECTION 00 52 43 2 AGREEMENT – UNIT PRICE BID 3 4 THIS AGREEMENT, authorized on ______________is made by and between the City of Denton, 5 a Texas home-rule municipal corporation, acting by and through its duly authorized City Manager, 6 (“City”), and ______________________________________________________________, 7 authorized to do business in Texas, acting by and through its duly authorized representative, 8 (“Contractor”). 9 City and Contractor, in consideration of the mutual covenants hereinafter set forth, agree as follows: 10 Article 1. WORK 11 Contractor shall complete all Work as specified or indicated in the Contract Documents for the 12 Project identified herein. 13 Article 2. PROJECT 14 The project for which the Work under the Contract Documents may be the whole or only a part is 15 generally described as follows: 16 Baker Offsite Sewer 17 IFB 8833 18 Article 3. CONTRACT PRICE 19 City agrees to pay Contractor for performance of the Work in accordance with the Contract 20 Documents an amount, in current funds, of __________________________________Dollars 21 ($___________________). At the sole option of the City, five (5) percent contingency in the 22 amount of __________________________________Dollars ($___________________) may be 23 used for a total not-to-exceed amount of __________________________________Dollars 24 ($___________________). 25 Article 4. CONTRACT TIME 26 4.1 Time is of the essence. 27 All time limits for Milestones, if any, and Final Acceptance as stated in the Contract 28 Documents are of the essence to this Contract. 29 4.2 Final Acceptance. 30 The Work will be completed for Final Acceptance within 300 Working Days after the date 31 when the Contract Time commences to run, which is the day indicated in the Notice to 32 Proceed, plus any extension thereof allowed in accordance with Article 11 of the General 33 Conditions. 34 35 00 52 43 AGREEMENT Page 2 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 21, 2021 4.4 Liquidated Damages: 1 A.Contractor recognizes that time is of the essence to achieve Milestones and Final2 Acceptance of the Work, and City will suffer financial and other losses if the Work is3 not completed within the times specified in the Contract Documents. The Contractor4 also recognizes the delays, expense and difficulties involved in proving, in a legal or5 arbitration proceeding, the actual loss suffered by the City if the Work related to the6 Milestones or Final Acceptance is not completed on time. Accordingly, instead of7 requiring any such proof, Contractor agrees that liquidated damages for delay (but not8 as a penalty):9 1.Final Acceptance: If Contractor neglects, refuse, or fails to complete the Work10 within the time (as duly adjusted pursuant to the Contract) specified in Paragraph11 4.2, for completion and readiness for Final Payment, Contractor shall pay City12 _Six Hundred and Twenty Five___ Dollars ($__625.00___) for each day that13 expires after such time, until the date determined by City as stated in the City-14 issued Letter of Final Acceptance.15 Article 5. CONTRACT DOCUMENTS 16 5.1 CONTENTS: 17 18 19 20 21 22 23 24 25 26 27 28 29 30 A. The Contract comprises the entire agreement between City and Contractor concerning the Work and consists of this Agreement and the items set forth below. The Contract Documents consist of all items below other than this Agreement. 1.Attachments to this Agreement: a.Proposal Form1)Bid Form2)Unit Price Proposal Form 3)Vendor Compliance to State Law Non-Resident Offeror4)State and Federal documents (project specific)b.Current Prevailing Wage Rate Table c.Worker’s Compensation Affidavitd.General Conditions.e.Supplementary Conditions. 2.The following located in File 8833 at:31 https://lfpubweb.cityofdenton.com/MaterialsManagement/Browse.aspx?id=19&32 dbid=0&repo=MaterialsManagement&cr=1 33 a.Specifications described in the Table of Contents of the Project’s Contract34 Documents.35 b.Drawings.36 c.Addenda.37 d.Documentation submitted by Contractor prior to Notice of Award.38 3.The following which shall be issued after the Effective Date and delivered to the City39 within ten (10) days of the Effective Date and before beginning Work:40 a.Payment Bond41 b.Performance Bond42 c.Maintenance Bond43 d.Power of Attorney for the Bonds44 e.Form 1295 – Certificate of Interested Parties (email to purchasing)45 f.Insurance Certificate46 00 52 43 AGREEMENT Page 3 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 21, 2021 4. Specifications specifically made a part of the Contract Documents by attachment or, 1 if not attached, as incorporated by reference and described in the Table of Contents 2 of the Project’s Contract Documents. 3 5. The following which may be delivered or issued after the Effective Date of the 4 Agreement and, if issued, become an incorporated part of the Contract Documents: 5 a. Notice to Proceed. 6 b. Field Orders. 7 c. Change Orders. 8 d. Letter of Final Acceptance. 9 Article 6. INDEMNIFICATION 10 6.1 CONTRACTOR COVENANTS AND AGREES TO INDEMNIFY, HOLD 11 HARMLESS AND DEFEND, AT ITS OWN EXPENSE, THE CITY, ITS OFFICERS, 12 ELECTED AND APPOINTED OFFICIALS, AND EMPLOYEES, FROM AND 13 AGAINST ANY AND ALL CLAIMS FOR PERSONAL INJURY OR DEATH, 14 ARISING OUT OF, OR ALLEGED TO ARISE OUT OF, RELATED TO OR IN 15 CONNECTION WITH THE WORK AND SERVICES TO BE PERFORMED BY THE 16 CONTRACTOR, ITS OFFICERS, AGENTS, EMPLOYEES, SUBCONTRACTORS, 17 LICENSEES OR INVITEES UNDER THIS CONTRACT. THIS 18 INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE 19 AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR 20 SOME OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN 21 PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. THIS 22 INDEMNITY PROVISION IS INTENDED TO INCLUDE, WITHOUT 23 LIMITATION, INDEMNITY FOR ANY AND ALL COSTS, EXPENSES AND 24 LEGAL FEES INCURRED BY THE CITY IN DEFENDING AGAINST SUCH 25 CLAIMS AND CAUSES OF ACTIONS. 26 27 6.2 CONTRACTOR COVENANTS AND AGREES TO INDEMNIFY, HOLD 28 HARMLESS AND DEFEND, AT ITS OWN EXPENSE, THE CITY, ITS OFFICERS, 29 ELECTED AND APPOINTED OFFICIALS, AND EMPLOYEES, FROM AND 30 AGAINST ANY AND ALL CLAIMS FOR, LOSS OF, DAMAGE TO, OR 31 DESTRUCTION OF, PROPERTY OF THE CITY OR OF A THIRD PARTY, 32 ARISING OUT OF, OR ALLEGED TO ARISE OUT OF, RELATED TO OR IN 33 CONNECTION WITH THE WORK AND SERVICES TO BE PERFORMED BY THE 34 CONTRACTOR, ITS OFFICERS, AGENTS, EMPLOYEES, SUBCONTRACTORS, 35 LICENSEES OR INVITEES UNDER THIS CONTRACT. THIS 36 INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE 37 AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR 38 SOME OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN 39 PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. THIS 40 INDEMNITY PROVISION IS INTENDED TO INCLUDE, WITHOUT 41 LIMITATION, INDEMNITY FOR ANY AND ALL COSTS, EXPENSES AND 42 LEGAL FEES INCURRED BY THE CITY IN DEFENDING AGAINST SUCH 43 CLAIMS AND CAUSES OF ACTIONS. 44 Article 7. MISCELLANEOUS 45 00 52 43 AGREEMENT Page 4 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 21, 2021 7.1 Capitalized Terms. 1 Unless otherwise provided herein, capitalized terms used in this Agreement which are 2 defined in Article 1 of the General Conditions will have the meanings indicated in the General 3 Conditions. 4 7.2 Assignment of Contract. 5 This Agreement, including all of the Contract Documents may not be assigned by the 6 Contractor without the advance express written consent of the City. 7 7.3 Successors and Assigns. 8 City and Contractor each binds itself, its partners, successors, assigns and legal 9 representatives to the other party hereto, in respect to all covenants, agreements and 10 obligations contained in the Contract Documents. 11 7.4 Severability. 12 Any provision or part of the Contract Documents held to be unconstitutional, void or 13 unenforceable by a court of competent jurisdiction shall be deemed stricken, and all 14 remaining provisions shall continue to be valid and binding upon City and Contractor. 15 7.5 Venue and Waiver of Sovereign Immunity. 16 This Agreement, including all of the Contract Documents is performable in the State of 17 Texas. Venue shall be in the state district courts of Denton County, Texas. The City’s 18 sovereign immunity is waived only to the extent set forth and in accordance with the 19 provisions of Subchapter I, Chapter 271 of the Texas Local Government Code or as otherwise 20 specifically waived by law. The City does not waive its sovereign immunity to suit in federal 21 court. 22 7.6 Authority to Sign. 23 Contractor hereby certifies that the person signing the Agreement on its behalf is the duly 24 authorized signatory of the Contractor. 25 7.7 Prohibition on Contracts with Companies Boycotting Israel. 26 Contractor acknowledges that in accordance with Chapter 2270 of the Texas Government 27 Code, the City is prohibited from entering into a contract with a company for goods or 28 services unless the contract contains a written verification from the company that it: (1) does 29 not boycott Israel; and (2) will not boycott Israel during the term of the contract. The terms 30 “boycott Israel” and “company” shall have the meanings ascribed to those terms in Section 31 808.001 of the Texas Government Code. By signing this contract, Contractor certifies that 32 Contractor’s signature provides written verification to the City that Contractor: (1) does not 33 boycott Israel; and (2) will not boycott Israel during the term of the contract. 34 7.8 Prohibition on Contracts with Companies Boycotting Certain Energy Companies 35 00 52 43 AGREEMENT Page 5 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 21, 2021 Contractor acknowledges that in accordance with Chapter 2274 of the Texas Government 1 Code, City is prohibited from entering into a contract with a company for goods or services 2 unless the contract contains written verification from the company that it (1) does not boycott 3 energy companies; and (2) will not boycott energy companies during the term of the contract. 4 The terms “boycott energy company” and “company” shall have the meanings ascribed to 5 those terms in Section 809.001 of the Texas Government Code. By signing this agreement, 6 Contractor certifies that Contractor’s signature provides written verification to the City that 7 Contractor: (1) does not boycott energy companies; and (2) will not boycott energy 8 companies during the term of the agreement. Failure to meet or maintain the requirements 9 under this provision will be considered a material breach. 10 7.9 Prohibition on Contracts with Companies Boycotting Certain Firearm Entities and Firearm 11 Trade Associations. 12 Contractor acknowledges that in accordance with Chapter 2274 of the Texas Government 13 Code, City is prohibited from entering into a contract with a company for goods or services 14 unless the contract contains written verification from the company that it (1) does not have a 15 practice, policy, guidance, or directive that discriminates against a firearm entity or firearm 16 trade association; and (2) will not discriminate during the term of the contract against a 17 firearm entity or firearm trade association. The terms “discriminate against a firearm entity 18 or firearm trade association,” “firearm entity” and “firearm trade association” shall have the 19 meanings ascribed to those terms in Chapter 2274 of the Texas Government Code. By 20 signing this agreement, Contractor certifies that Contractor’s signature provides written 21 verification to the City that Contractor: (1) does not have a practice, policy, guidance, or 22 directive that discriminates against a firearm entity or firearm trade association; and (2) 23 will not discriminate during the term of the contract against a firearm entity or firearm 24 trade association. Failure to meet or maintain the requirements under this provision will be 25 considered a material breach. 26 7.10 Prohibition on Contracts with Companies Doing Business with Iran, Sudan, or a Foreign 27 Terrorist Organization 28 Sections 2252 and 2270 of the Texas Government Code restricts CITY from contracting with 29 companies that do business with Iran, Sudan, or a foreign terrorist organization. By signing 30 this agreement, Contractor certifies that Contractor’s signature provides written 31 verification to the City that Contractor, pursuant to Chapters 2252 and 2270, is not 32 ineligible to enter into this agreement and will not become ineligible to receive payments 33 under this agreement by doing business with Iran, Sudan, or a foreign terrorist 34 organization. Failure to meet or maintain the requirements under this provision will be 35 considered a material breach. 36 7.11 Termination Right for Contracts with Companies Doing Business with Certain Foreign- 37 Owned Companies 38 The City of Denton may terminate this Contract immediately without any further liability if 39 the City of Denton determines, in its sole judgment, that this Contract meets the requirements 40 under Chapter 2274, and Contractor is, or will be in the future, (i) owned by or the majority 41 of stock or other ownership interest of the company is held or controlled by individuals who 42 are citizens of China, Iran, North Korea, Russia, or other designated country (ii) directly 43 controlled by the Government of China, Iran, North Korea, Russia, or other designated 44 country, or (iii) is headquartered in China, Iran, North Korea, Russia, or other designated 45 country. 46 00 52 43 AGREEMENT Page 6 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 21, 2021 7.12 Immigration Nationality Act. 1 Contractor shall verify the identity and employment eligibility of its employees who perform 2 work under this Agreement, including completing the Employment Eligibility Verification 3 Form (I-9). Upon request by City, Contractor shall provide City with copies of all I-9 forms 4 and supporting eligibility documentation for each employee who performs work under this 5 Agreement. Contractor shall adhere to all Federal and State laws as well as establish 6 appropriate procedures and controls so that no services will be performed by any Contractor 7 employee who is not legally eligible to perform such services. CONTRACTOR SHALL 8 INDEMNIFY CITY AND HOLD CITY HARMLESS FROM ANY PENALTIES, 9 LIABILITIES, OR LOSSES DUE TO VIOLATIONS OF THIS PARAGRAPH BY 10 CONTRACTOR, CONTRACTOR’S EMPLOYEES, SUBCONTRACTORS, 11 AGENTS, OR LICENSEES. City, upon written notice to Contractor, shall have the right 12 to immediately terminate this Agreement for violations of this provision by Contractor. 13 7.13 No Third-Party Beneficiaries. 14 This Agreement gives no rights or benefits to anyone other than the City and the Contractor 15 and there are no third-party beneficiaries. 16 7.14 No Cause of Action Against Engineer. 17 Contractor, its subcontractors and equipment and materials suppliers on the Project or their 18 sureties, shall maintain no direct action against the Engineer, its officers, employees, and 19 subcontractors, for any claim arising out of, in connection with, or resulting from the engineering 20 services performed. Only the City will be the beneficiary of any undertaking by the Engineer. 21 The presence or duties of the Engineer's personnel at a construction site, whether as on-site 22 representatives or otherwise, do not make the Engineer or its personnel in any way 23 responsible to Contractor or any other entity for those duties that belong to the City, and do 24 not relieve Contractor or any other entity of its obligations, duties, and responsibilities, 25 including, but not limited to, all construction methods, means, techniques, sequences, and 26 procedures necessary for performing, coordinating and completing all portions of the Work 27 in accordance with the Contract Documents and any health or safety precautions required by 28 such Work. The Engineer and its personnel have no authority to exercise any control over 29 any construction contractor or other entity or their employees in connection with their work 30 or any health or safety precautions. 31 32 SIGNATURE PAGE TO FOLLOW 33 34 00 52 43 AGREEMENT Page 7 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 21, 2021 IN WITNESS WHEREOF, City and Contractor have each executed this Agreement to be effective 1 as of the date subscribed by the City’s City Manager or his designee (“Effective Date”). 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 ATTEST: 39 INGRID REX, CITY SECRETARY 40 41 42 _______________________________________ 43 44 45 APPROVED AS TO LEGAL FORM: 46 MACK REINWAND, CITY ATTORNEY 47 48 49 _______________________________________ 50 CITY OF DENTON BY: ___________________________________ TITLE: _________________________________ DATE: _________________________________ CONTRACTOR BY: ___________________________________ AUTHORIZED AGENT _______________________________________ NAME _______________________________________ TITLE _______________________________________ PHONE NUMBER _______________________________________ EMAIL ADDRESS _______________________________________ 51 TEXAS ETHICS COMMISSION 52 1295 CERTIFICATE NUMBER 53 THIS AGREEMENT HAS BEEN BOTH REVIEWED AND APPROVED as to financial and operational obligations and business terms. _______________ ________________ SIGNATURE PRINTED NAME __________________________________ TITLE __________________________________ DEPARTMENT 00 61 13 - 1 PERFORMANCE BOND Page 1 of 2 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 SECTION 00 61 13 1 PERFORMANCE BOND 2 3 THE STATE OF TEXAS § 4 § KNOW ALL BY THESE PRESENTS: 5 COUNTY OF DENTON § 6 7 That we, _______________________________________________, known as “Principal” 8 herein and ____________________________________________, a corporate surety(sureties, if 9 more than one) duly authorized to do business in the State of Texas, known as “Surety” herein 10 (whether one or more), are held and firmly bound unto the City of Denton, a municipal corporation 11 created pursuant to the laws of Texas, known as “City” herein, in the penal sum of, 12 ___________________________________________ Dollars ($_______________________), 13 lawful money of the United States, to be paid in Denton, Denton County, Texas for the payment of 14 which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, 15 successors and assigns, jointly and severally, firmly by these presents. 16 WHEREAS, the Principal has entered into a certain written contract with the City awarded 17 the _____ day of ________________, 20____, which Contract is hereby referred to and made a 18 part hereof for all purposes as if fully set forth herein, to furnish all materials, equipment labor and 19 other accessories defined by law, in the prosecution of the Work, including any Change Orders, as 20 provided for in said Contract designated as Baker Offsite Sewer. 21 NOW, THEREFORE, the condition of this obligation is such that if the said Principal 22 shall faithfully perform it obligations under the Contract and shall in all respects duly and faithfully 23 perform the Work, including Change Orders, under the Contract, according to the plans, 24 specifications, and contract documents therein referred to, and as well during any period of 25 extension of the Contract that may be granted on the part of the City, then this obligation shall be 26 and become null and void, otherwise to remain in full force and effect. 27 PROVIDED FURTHER, that if any legal action be filed on this Bond, venue shall lie in 28 Denton County, Texas or the United States District Court for the Eastern District of Texas, Sherman 29 Division. 30 00 61 13 - 2 PERFORMANCE BOND Page 2 of 2 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 This bond is made and executed in compliance with the provisions of Chapter 2253 of the 1 Texas Government Code, as amended, and all liabilities on this bond shall be determined in 2 accordance with the provisions of said statue. 3 IN WITNESS WHEREOF, the Principal and the Surety have SIGNED and SEALED this 4 instrument by duly authorized agents and officers on this the ______day of ____________, 20 5 . 6 PRINCIPAL: 7 ____________________________________ 8 ____________________________________ 9 10 BY: ________________________________ 11 Signature 12 ATTEST: 13 14 ______________________________ ____________________________________ 15 (Principal) Secretary Name and Title 16 17 Address: ____________________________ 18 ____________________________ 19 ____________________________ 20 _____________________________ 21 Witness as to Principal 22 SURETY: 23 ____________________________________ 24 ____________________________________ 25 26 BY: ________________________________ 27 Signature 28 29 ____________________________________ 30 Name and Title 31 32 Address: ____________________________ 33 ____________________________ 34 ____________________________ 35 _____________________________ 36 Witness as to Surety Telephone Number: ___________________ 37 38 39 40 *Note: If signed by an officer of the Surety Company, there must be on file a certified extract 41 from the by-laws showing that this person has authority to sign such obligation. If 42 Surety’s physical address is different from its mailing address, both must be provided. 43 The date of the bond shall not be prior to the date the Contract is awarded. 44 45 00 61 14 - 1 PAYMENT BOND Page 1 of 2 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 SECTION 00 61 14 1 PAYMENT BOND 2 3 THE STATE OF TEXAS § 4 § KNOW ALL BY THESE PRESENTS: 5 COUNTY OF DENTON § 6 That we, _____________________________________________________, known as 7 “Principal” herein, and _________________________________________________________, a 8 corporate surety (sureties), duly authorized to do business in the State of Texas, known as “Surety” 9 herein (whether one or more), are held and firmly bound unto the City of Denton, a municipal 10 corporation created pursuant to the laws of the State of Texas, known as “City” herein, in the penal 11 sum of___________________________________________ Dollars 12 ($_______________________), lawful money of the United States, to be paid in Denton, Denton 13 County, Texas, for the payment of which sum well and truly be made, we bind ourselves, our heirs, 14 executors, administrators, successors and assigns, jointly and severally, firmly by these presents: 15 WHEREAS, Principal has entered into a certain written Contract with City, awarded the 16 _____ day of ______________________, 20_____, which Contract is hereby referred to and made 17 a part hereof for all purposes as if fully set forth herein, to furnish all materials, equipment, labor 18 and other accessories as defined by law, in the prosecution of the Work as provided for in said 19 Contract and designated as Baker Offsite Sewer. 20 NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that if 21 Principal shall pay all monies owing to any (and all) payment bond beneficiary (as defined in 22 Chapter 2253 of the Texas Government Code, as amended) in the prosecution of the Work under 23 the Contract, then this obligation shall be and become null and void; otherwise to remain in full 24 force and effect. 25 This bond is made and executed in compliance with the provisions of Chapter 2253 of the 26 Texas Government Code, as amended, and all liabilities on this bond shall be determined in 27 accordance with the provisions of said statute. 28 29 00 61 14 - 2 PAYMENT BOND Page 2 of 2 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 IN WITNESS WHEREOF, the Principal and Surety have each SIGNED and SEALED 1 this instrument by duly authorized agents and officers on this the _________ day of 2 ___________________, 20_____. 3 4 PRINCIPAL: _________________________________ _________________________________ ATTEST: BY: _____________________________ Signature ___________________________________ _____________________________ (Principal) Secretary Name and Title Address: _________________________ _________________________ ___________________________________ _________________________ Witness as to Principal SURETY: _________________________________ _________________________________ ATTEST: BY: _____________________________ Signature __________________________________ _____________________________ (Surety) Secretary Name and Title Address: _________________________ _________________________ __________________________________ _________________________ Witness as to Surety Telephone Number: ________________ 5 Note: If signed by an officer of the Surety, there must be on file a certified extract from the bylaws 6 showing that this person has authority to sign such obligation. If Surety’s physical address is 7 different from its mailing address, both must be provided. 8 9 THE DATE OF THE BOND SHALL NOT BE PRIOR 10 TO THE DATE THE CONTRACT IS AWARDED. 11 END OF SECTION 12 13 00 61 19 - 1 MAINTENANCE BOND Page 1 of 3 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 SECTION 00 61 19 1 MAINTENANCE BOND 2 3 THE STATE OF TEXAS § 4 § KNOW ALL BY THESE PRESENTS: 5 COUNTY OF TARRANT § 6 7 That we_____________________________________________________, known as 8 “Principal” herein and ____________________________________________, a corporate surety 9 (sureties, if more than one) duly authorized to do business in the State of Texas, known as 10 “Surety” herein (whether one or more), are held and firmly bound unto the City of Denton, a 11 municipal corporation created pursuant to the laws of the State of Texas, known as “City” herein, 12 in the sum of_________________________________________ Dollars 13 ($_______________________), lawful money of the United States, to be paid in Denton, Denton 14 County, Texas, for payment of which sum well and truly be made unto the City and its 15 successors, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly 16 and severally, firmly by these presents. 17 18 WHEREAS, the Principal has entered into a certain written contract with the City awarded 19 the_____ day of , 20 , which Contract is hereby 20 referred to and a made part hereof for all purposes as if fully set forth herein, to furnish all 21 materials, equipment labor and other accessories as defined by law, in the prosecution of the 22 Work, including any Work resulting from a duly authorized Change Order (collectively herein, 23 the “Work”) as provided for in said contract and designated as Baker Offsite Sewer; and 24 25 WHEREAS, Principal binds itself to use such materials and to so construct the Work in 26 accordance with the plans, specifications and Contract Documents that the Work is and will 27 remain free from defects in materials or workmanship for and during the period of two (2) years 28 after the date of Final Acceptance of the Work by the City (“Maintenance Period”); and 29 30 WHEREAS, Principal binds itself to repair or reconstruct the Work in whole or in part 31 upon receiving notice from the City of the need therefor at any time within the Maintenance 32 Period. 33 34 00 61 19 - 2 MAINTENANCE BOND Page 2 of 3 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 NOW THEREFORE, the condition of this obligation is such that if Principal shall 1 remedy any defective Work, for which timely notice was provided by City, to a completion 2 satisfactory to the City, then this obligation shall become null and void; otherwise to remain in 3 full force and effect. 4 5 PROVIDED, HOWEVER, if Principal shall fail so to repair or reconstruct any timely 6 noticed defective Work, it is agreed that the City may cause any and all such defective Work to 7 be repaired and/or reconstructed with all associated costs thereof being borne by the Principal and 8 the Surety under this Maintenance bond; and 9 10 PROVIDED FURTHER, that if any legal action be filed on this Bond, venue shall lie in 11 Denton County, Texas or the United States District Court for the Eastern District of Texas, 12 Sherman Division; and 13 14 PROVIDED FURTHER, that this obligation shall be continuous in nature and 15 successive recoveries may be had hereon for successive breaches. 16 17 18 19 00 61 19 - 3 MAINTENANCE BOND Page 3 of 3 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 IN WITNESS WHEREOF, the Principal and the Surety have each SIGNED and SEALED this 1 instrument by duly authorized agents and officers on this the day of 2 , 20 __. 3 4 PRINCIPAL: 5 ____________________________________ 6 ____________________________________ 7 8 BY: ________________________________ 9 Signature 10 ATTEST: 11 12 ______________________________ ____________________________________ 13 (Principal) Secretary Name and Title 14 15 Address: ____________________________ 16 ____________________________ 17 ____________________________ 18 _____________________________ 19 Witness as to Principal 20 SURETY: 21 ____________________________________ 22 ____________________________________ 23 24 BY: ________________________________ 25 Signature 26 27 ____________________________________ 28 ATTEST: Name and Title 29 30 _____________________________ Address: ____________________________ 31 (Surety) Secretary ____________________________ 32 ____________________________ 33 _____________________________ 34 Witness as to Surety Telephone Number: ___________________ 35 36 *Note: If signed by an officer of the Surety Company, there must be on file a certified extract 37 from the by-laws showing that this person has authority to sign such obligation. If 38 Surety’s physical address is different from its mailing address, both must be provided. 39 The date of the bond shall not be prior to the date the Contract is awarded. 40 41 00 61 25 CERTIFICATE OF INSURANCE Page 1 of 1 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Effective January 15, 2021 SECTION 00 61 25 1 CERTIFICATE OF INSURANCE 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 END OF SECTION 23 00 72 00 GENERAL CONDITIONS Page i of vi CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised November 20, 2020 STANDARD GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT 00 72 00 GENERAL CONDITIONS Page ii of vi CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised November 20, 2020 STANDARD GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT TABLE OF CONTENTS Page ARTICLE 1 – DEFINITIONS AND TERMINOLOGY .............................................................................. 1 1.01 Defined Terms .............................................................................................................................. 1 1.02 Terminology .................................................................................................................................. 6 ARTICLE 2 – PRELIMINARY MATTERS ................................................................................................ 7 2.01 Delivery of Performance and Payment Bonds; Evidence of Insurance ........................................ 7 2.02 Copies of Documents .................................................................................................................... 7 2.03 Before Starting Construction ........................................................................................................ 7 2.04 Preconstruction ConferenceMeeting ............................................................................................. 7 2.05 Public Meeting .............................................................................................................................. 7 2.06 Initial Acceptance of Schedules .................................................................................................... 8 2.07 Electronic Submittals and Transmittals ........................................................................................ 8 ARTICLE 3 – CONTRACT DOCUMENTS: INTENT, REQUIREMENTS, REUSE ............................... 8 3.01 Intent ............................................................................................................................................. 8 3.02 Reference Standards ...................................................................................................................... 8 3.03 Reporting and Resolving Discrepancies ....................................................................................... 9 3.04 Requirements of the Contract Documents .................................................................................. 10 3.05 Reuse of Documents ................................................................................................................... 10 ARTICLE 4 – COMMENCEMENT AND PROGRESS OF THE WORK................................................ 10 4.01 Commencement of Contract Time; Notice to Proceed ............................................................... 10 4.02 Starting the Work ........................................................................................................................ 10 4.03 Delays in Contractor’s Progress .................................................................................................. 10 ARTICLE 5 – SITE; SUBSURFACE AND PHYSICAL CONDITIONS; HAZARDOUS ENVIRONMENTAL CONDITIONS......................................................................................................... 12 5.01 Availability of Lands .................................................................................................................. 12 5.02 Use of Site and Other Areas ........................................................................................................ 13 5.03 Subsurface and Physical Conditions ........................................................................................... 14 5.04 Differing Subsurface or Physical Conditions .............................................................................. 15 5.05 Underground Facilities ................................................................................................................ 15 5.06 Hazardous Environmental Conditions at Site ............................................................................. 16 00 72 00 GENERAL CONDITIONS Page iii of vi CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised November 20, 2020 ARTICLE 6 – BONDS AND INSURANCE .............................................................................................. 18 6.01 Licensed Sureties and Insurers .................................................................................................... 18 6.02 Performance, Payment, and Maintenance Bonds ........................................................................ 18 6.03 Certificates of Insurance ............................................................................................................. 18 6.04 Contractor’s Insurance ................................................................................................................ 20 6.05 Acceptance of Bonds and Insurance; Option to Replace ............................................................ 21 ARTICLE 7 – CONTRACTOR’S RESPONSIBILITIES .......................................................................... 21 7.01 Contractor’s Means and Methods of Construction ..................................................................... 21 7.02 Supervision and Superintendence ............................................................................................... 22 7.03 Labor; Working Hours ................................................................................................................ 22 7.04 Services, Materials, and Equipment ............................................................................................ 22 7.05 Project Schedule .......................................................................................................................... 23 7.06 “Or Equals” ................................................................................................................................. 23 7.07 Substitutions ................................................................................................................................ 24 7.08 Concerning Subcontractors and Suppliers .................................................................................. 26 7.09 Wage Rates ................................................................................................................................. 27 7.10 Patent Fees and Royalties ........................................................................................................... 28 7.11 Permits and Utilities .................................................................................................................... 28 7.12 Taxes ........................................................................................................................................... 29 7.13 Laws and Regulations ................................................................................................................. 29 7.14 Record Documents ...................................................................................................................... 30 7.15 Safety and Protection .................................................................................................................. 30 7.16 Hazard Communication Programs .............................................................................................. 31 7.17 Emergencies and/or Rectification ............................................................................................... 31 7.18 Submittals ................................................................................................................................... 32 7.19 Continuing the Work ................................................................................................................... 33 7.20 Contractor’s General Warranty and Guarantee ........................................................................... 33 7.21 Indemnification ........................................................................................................................... 34 7.22 Delegation of Professional Design Services ............................................................................... 34 7.23 Right to Audit ............................................................................................................................. 35 7.24 Nondiscrimination ....................................................................................................................... 36 ARTICLE 8 – OTHER WORK AT THE SITE .......................................................................................... 36 8.01 Other Work ................................................................................................................................. 36 8.02 Coordination ............................................................................................................................... 37 00 72 00 GENERAL CONDITIONS Page iv of vi CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised November 20, 2020 8.03 Legal Relationships ..................................................................................................................... 37 ARTICLE 9 – CITY’S RESPONSIBILITIES ............................................................................................ 37 9.01 Communications to Contractor ................................................................................................... 37 9.02 Furnish Data ................................................................................................................................ 38 9.03 Pay When Due ............................................................................................................................ 38 9.04 Lands and Easements; Reports, Tests, and Drawings ................................................................. 38 9.05 Change Orders ............................................................................................................................ 38 9.06 Inspections, Tests, and Approvals ............................................................................................... 38 9.07 Limitations on City’s Responsibilities ........................................................................................ 38 9.08 Undisclosed Hazardous Environmental Condition ..................................................................... 38 9.09 Compliance with Safety Program ............................................................................................... 38 ARTICLE 10 – CITY’S OBSERVATION DURING CONSTRUCTION ................................................ 38 10.01 City’s Project Manager or Duly Authorized Representative .................................................. 38 10.02 Visits to Site ............................................................................................................................ 39 10.03 Determinations for Work Performed ...................................................................................... 39 10.04 Decisions on Requirements of Contract Documents and Acceptability of Work ................... 39 ARTICLE 11 – CHANGES IN THE WORK; CLAIMS; EXTRA WORK ............................................... 39 11.01 Amending and Supplementing the Contract ........................................................................... 39 11.02 Execution of Change Orders ................................................................................................... 40 11.03 Field Orders ............................................................................................................................ 40 11.04 Authorized Changes in the Work – Extra Work ..................................................................... 40 11.05 Unauthorized Changes in the Work ........................................................................................ 40 11.06 Dispute of Extra Work ............................................................................................................ 40 11.07 Contract Claims Process ......................................................................................................... 41 11.08 Change of Contract Price ........................................................................................................ 42 11.09 Change of Contract Time ........................................................................................................ 43 11.10 Notification to Surety .............................................................................................................. 43 ARTICLE 12 – COST OF THE WORK; ALLOWANCES; UNIT PRICE WORK; PLANS QUANTITY MEASUREMENT ...................................................................................................................................... 43 12.01 Cost of the Work ..................................................................................................................... 43 12.02 Allowances .............................................................................................................................. 46 12.03 Unit Price Work ...................................................................................................................... 46 12.04 Plans Quantity Measurement for Unclassified Excavation or Embankment .......................... 47 00 72 00 GENERAL CONDITIONS Page v of vi CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised November 20, 2020 ARTICLE 13 – TESTS AND INSPECTIONS; CORRECTION, REMOVAL, OR ACCEPTANCE OF DEFECTIVE WORK .................................................................................................................................. 48 13.01 Access to Work ....................................................................................................................... 48 13.02 Tests, Inspections .................................................................................................................... 48 13.03 Defective Work ....................................................................................................................... 49 13.04 Rejecting Defective Work ....................................................................................................... 50 13.05 Acceptance of Defective Work ............................................................................................... 50 13.06 Uncovering Work .................................................................................................................... 50 13.07 City May Stop the Work ......................................................................................................... 50 13.08 City May Correct Defective Work .......................................................................................... 51 ARTICLE 14 – PAYMENTS TO CONTRACTOR; COMPLETION; CORRECTION PERIOD ............ 51 14.01 Progress Payments .................................................................................................................. 51 14.02 Contractor’s Warranty of Title ................................................................................................ 54 14.03 Partial Utilization .................................................................................................................... 54 14.04 Final Inspection ....................................................................................................................... 55 14.05 Final Acceptance ..................................................................................................................... 55 14.06 Final Payment ......................................................................................................................... 55 14.07 Final Completion Delayed and Partial Retainage Release ...................................................... 56 14.08 Waiver of Claims .................................................................................................................... 56 14.09 Correction Period .................................................................................................................... 56 ARTICLE 15 – SUSPENSION OF WORK AND TERMINATION ......................................................... 57 15.01 City May Suspend Work ......................................................................................................... 57 15.02 City May Terminate for Cause ................................................................................................ 58 15.03 City May Terminate for Convenience..................................................................................... 59 ARTICLE 16 – FINAL RESOLUTION OF DISPUTES ........................................................................... 61 16.01 Methods and Procedures ......................................................................................................... 61 ARTICLE 17 – MISCELLANEOUS ......................................................................................................... 62 17.01 Giving Notice .......................................................................................................................... 62 17.02 Computation of Times ............................................................................................................ 62 17.03 Cumulative Remedies ............................................................................................................. 62 17.04 Limitation of Damages ............................................................................................................ 62 17.05 No Waiver ............................................................................................................................... 62 17.06 Survival of Obligations ........................................................................................................... 62 17.07 Assignment of Contract .......................................................................................................... 63 00 72 00 GENERAL CONDITIONS Page vi of vi CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised November 20, 2020 17.08 Successors and Assigns ........................................................................................................... 63 17.09 Headings ................................................................................................................................. 63 00 72 00 GENERAL CONDITIONS Page 1 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 ARTICLE 1 – DEFINITIONS AND TERMINOLOGY 1.01 Defined Terms A. Wherever used in the Contract or in other Contract Documents, the terms listed below have the meanings indicated which are applicable to both the singular and plural thereof, and words denoting gender shall include the masculine, feminine and neuter. When used in a context consistent with the definition of a listed-defined term, the term shall have a meaning as defined below whether capitalized or italicized or otherwise. In addition to terms specifically defined, terms with initial capital letters in the Contract Documents include references to identified articles and paragraphs, and the titles of other documents or forms. 1. Addenda—Written or graphic instruments issued prior to the opening of Bids which clarify, correct, or change the Bidding Requirements or the proposed Contract Documents. 2. Agreement—The written instrument titled “Agreement”, “Agreement – CSP”, or “Agreement – Unit Price Bid” executed by the City and Contractor for the Work, setting forth the name of the Project, Contract Price, Contract Time and the items included in the Contract. 3. Application for Payment—The form acceptable to City which is to be used by Contractor during the course of the Work in requesting progress or final payments and which is to be accompanied by such supporting documentation as is required by the Contract. 4. Asbestos—Any material that contains more than one percent asbestos and is friable or is releasing asbestos fibers into the air above current action levels established by the United States Occupational Safety and Health Administration. 5. Award—Authorization by the City Council for the City to enter into an Agreement. 6. Bid—The offer or proposal of a Bidder submitted on the prescribed form setting forth the prices for the Work to be performed. The term “Bid” shall be defined to include the term “Proposal” in those instances where the City utilizes a Request for Proposal rather than an Invitation for Bid. 7. Bidder—The individual or entity that submits a Bid directly to City. The term “Bidder” shall be defined to include the terms “Proposer” or “Offeror” in those instances where the City utilizes a Request for Proposal rather than an Invitation for Bid. 8. Bidding Documents—The Bidding Requirements and the proposed Contract Documents (including all Addenda). The term “Bidding Documents” shall be defined to include the terms “Proposal Documents” in those instances where the City utilizes a Request for Proposal rather than an Invitation for Bid. 9. Bidding Requirements—The Advertisement or Invitation to Bid, Instructions to Bidders, Bid Bond or other Bid security, if any, the Bid Form, and the Bid with any attachments. The term “Bidding Requirements” shall be defined to include the terms “Proposal Requirements” in those instances where the City utilizes a Request for Proposal rather than an Invitation for Bid and will include the Request for Proposal or Invitation to Offerors, Instructions to Offerors, Offerors Bond or other Proposal security, if any, the Proposal Form, and the Proposal with any attachments. 00 72 00 GENERAL CONDITIONS Page 2 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 10. Business Day—A day that the City conducts normal business, generally Monday through Friday, except for federal or state holidays observed by the City. 11. Calendar Day—A day consisting of 24 hours measured from midnight to the next midnight. 12. Change Order—A document which is prepared by the Contractor or City, approved by the City, and signed by Contractor and City, authorizing an addition, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on or after the Effective Date of the Agreement. 13. City—The City of Denton is, a Texas home-rule municipal corporation acting by its City Council through its City Manager or his or her designee. 14. City Attorney—The officially appointed City Attorney of the City of Denton or his or her designee. 15. City Council—The duly elected and qualified governing body of the City of Denton. 16. City Manager—The officially appointed authorized City Manager of the City of Denton. 17. Contract—The entire and integrated set of written instruments between the City and Contractor concerning the Work comprised of the Agreement and all Contract Documents, which written instruments supersede all prior negotiations, representations, or agreements, whether written or oral, concerning the Work. 18. Contract Claim—A demand or assertion by City or Contractor seeking an adjustment of Contract Price or Contract Time, or both, or other relief with respect to the terms of the Contract. A demand for money or services by a third party is not a Contract Claim. 19. Contract Documents—Those items so designated as “Contract Documents.” in the Agreement at Paragraph 5.1.A. Approved Submittals, other Contractor submittals, and the reports and drawings of subsurface and physical conditions are not Contract Documents. 20. Contract Price—The moneys payable by City to Contractor for completion of the Work in accordance with the Contract Documents as stated in the Agreement (subject to the provisions of Paragraph 12.03 in the case of Unit Price Work). The Contract Price does not include any “Incentive”, if applicable. 21. Contract Time—The number of days or the dates stated in the Agreement to: (a) achieve Milestones, if any and (bb) complete the Work so that it is ready for Final Acceptance. 22. Contractor—The individual or entity with whom City has entered into the Agreement. 23. Cost of the Work—See Paragraph 12.01 of these General Conditions for definition. 24. Damage Claims—A demand for money or services arising from the Project or Site from a third party, City or Contractor exclusive of a Contract Claim. 25. Day or day—A day, unless otherwise defined, shall mean a Calendar Day. 26. Drawings—The part of the Contract Documents prepared or approved by an Engineer that graphically shows the scope, extent, and character of the Work to be performed by Contractor. Submittals, as defined, are not considered Drawings as so defined here. 00 72 00 GENERAL CONDITIONS Page 3 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 27. Effective Date of the Agreement—The date, indicated in the Agreement, on which it becomes effective,, but if no such date is indicated, it means the date on which the Agreement is signed and delivered by the City. 28. Electronic Document—Any Project-related correspondence, attachments to correspondence, text, data, documents, drawings, information, or graphics, including but not limited to Shop Drawings and other Submittals, that are in an electronic or digital format. 29. Electronic Means—Electronic mail (email), upload/download from a secure Project website, or other communications methods that allow: (a) the transmission or communication of Electronic Documents; (b) the documentation of transmissions, including sending and receipt; (c) printing of the transmitted Electronic Document by the recipient; (d) the storage and archiving of the Electronic Document by sender and recipient; and (e) the use by recipient of the Electronic Document for purposes permitted by the Contract. Electronic Means does not include the use of text messaging, or of Facebook, Twitter, Instagram, or similar social media services for transmission of Electronic Documents. 30. Engineer—The licensed professional engineer or engineering firm registered in the State of Texas performing professional services for the City. 31. Extra Work—Additional work made necessary by City-approved changes or alterations to the Contract Documents. Extra Work shall be part of the Work. 32. Field Order—A written directive issued by City that requires changes in the Work but does not involve a change to the Contract Price, Contract Time, or Drawings, Plan, or Shop Drawings. 33. Final Acceptance—The written notice given by the City to the Contractor that the Work specified in the Contract Documents has been completed to the satisfaction of the City. 34. Final Inspection—The inspection performed by the City to determine whether the Contractor has completed each and every part or appurtenance of the Work fully, entirely, and in conformance with the Contract Documents. 35. General Requirements—Sections of The information set forth in “Division 101 – General Requirements” of the Standard Construction Specification Documents. 36. Hazardous Environmental Condition—The presence at the Site of Asbestos, PCBs , Petroleum, Hazardous Waste, Radioactive Material, or any other substance, product, waste or materials, in such quantities or circumstances that may present a substantial danger to persons or property exposed thereto. 37. Hazardous Waste—Any solid waste listed as hazardous or which possesses one or more hazardous characteristics as defined in applicable Laws and Regulations. 38. Incidental or incidental—Work items that the Contractor is not paid for directly, but costs for which are included under the various bid items of the Project. 39. Laws and Regulations—Any and all applicable laws, statutes, rules, regulations, ordinances, codes, and binding decrees, resolutions, and orders of any and all governmental bodies, agencies, authorities, and courts having jurisdiction over the Site or any portion or part of the Work to be performed. 00 72 00 GENERAL CONDITIONS Page 4 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 40. Liens—Charges, security interests, or encumbrances upon Project funds, real property, or personal property. 41. Major Item—An item of work included in the Contract Documents that has a total cost equal to or greater than 5% of the original Contract Price. 42. Milestone—A principal event specified in the Contract Documents relating to the performance of an identified portion of the Work by an intermediate Contract Time prior to Final Acceptance of the Work. 43. Notice of Award—The written notice by City to the Successful Bidder stating that upon timely compliance by the Successful Bidder with the conditions precedent listed in such notice, City will sign and deliver the Agreement. 44. Notice to Proceed—A written notice given by City to Contractor fixing the date on which the Contract Time will commence to run and on which Contractor shall start to perform the Work specified in Contract Documents. 45. PCBs—Polychlorinated biphenyls. 46. Petroleum—Petroleum, including crude oil or any fraction thereof which is liquid at standard conditions of temperature and pressure (60 degrees Fahrenheit and 14.7 pounds per square inch absolute), and including but not limited to oil, fuel oil, oil sludge, oil refuse, gasoline, diesel fuel, kerosene, and oil mixed with other non-Hazardous Waste and crude oils. 47. Plans—This term will have the same definition of as “Drawings”. 48. Project —The Work to be performed under the Contract. 49. Project Manager—The authorized representative of the City who will be assigned to the Project. 50. Project Manual—The documentary information prepared for bidding or proposing and furnishing the Work. 51. Project Schedule—A schedule, prepared and maintained by Contractor, in accordance with the General Requirements, describing the sequence and duration of the activities comprising Contractor’s plan to achieve each Milestone and accomplish the Work within the Contract Time. 52. Public Meeting—An announced meeting conducted by the City to facilitate public participation and to assist the public in gaining an informed view of the Project. 53. Samples—Physical examples of materials, equipment, or workmanship that are representative of some portion of the Work and that establish the standards by which such portion of the Work will be judged. 54. Schedule of Submittals—A schedule, prepared and maintained by Contractor, of required submittals and the time requirements toto support scheduled performance of related construction activities. 55. Schedule of Values—A schedule, prepared and maintained by Contractor, allocating portions of the Contract Price to various portions of the Work and used as the basis for reviewing Contractor’s Applications for Payment. 00 72 00 GENERAL CONDITIONS Page 5 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 56. Shop Drawings—All drawings, diagrams, illustrations, schedules, and other data or information that are specifically prepared or assembled by or for Contractor and submitted by Contractor to illustrate some portion of the Work. Shop Drawings, whether approved or not, are not Drawings and are not Contract Documents. 57. Site—Lands or areas indicated in the Contract Documents as being furnished by City upon which the Work is to be performed, including rights-of-way, permits, and easements for access thereto, and such other lands furnished by City which are designated for the use of Contractor. 58. Specifications or Technical Specifications —The part of the Contract that consists of written requirements for materials, equipment, systems, standards, and workmanship as applied to the Work, and certain administrative requirements and procedural matters applicable to the Work. Specifications may be specifically made a part of the Contract Documents by attachment or, if not attached, may be incorporated by reference as indicated in the Table of Contents (Section 00 00 00) of the Project. 59. Subcontractor—An individual or entity having a direct contract with Contractor or with any other Subcontractor for the performance of a part of the Work at the Site. 60. Submittal—All drawings, diagrams, illustrations, schedules and other data or information which are specifically prepared or assembled by or for Contractor and submitted by Contractor to the City to illustrate some portion of the Work. 61. Subsidiary or subsidiary—These terms will have the same definition as “Incidental. or incidental”. 62. Successful Bidder—The Bidder to whom City issues a Notice of Award. The term “Bidder” shall be defined to include the terms “Proposer” or “Offeror” in those instances where the City utilizes a Request for Proposal rather than an Invitation for Bid and is the Proposer or Offeror submitting the proposal or offer that provides the best value to the City and to whom the City issues a Notice of Award. 63. Superintendent—The representative of the Contractor who is available at all times and able to receive instructions from the City and to act for the Contractor. 64. Supplementary Conditions—The part of the Contract set forth at Division 00 73 00 that amends or supplements these General Conditions. 65. Supplier—A manufacturer, fabricator, supplier, distributor, materialman, or vendor having a direct contract with Contractor or with any Subcontractor to furnish materials or equipment to be incorporated in the Work by Contractor or a Subcontractor. 66. Underground Facilities—All underground lines, pipelines, conduits, ducts, encasements, cables, wires, manholes, vaults, tanks, tunnels, or other such facilities or systems at the Site, including but not limited to those facilities or systems that produce, transmit, distribute, or convey telephone or other communications, cable television, fiber optic transmissions, power, electricity, light, heat, gases, oil, crude oil products, liquid petroleum products, water, steam, waste, wastewater, storm water, other liquids or chemicals, or traffic or other control systems. 67. Unit Price Work—Work for which the Contract Price is determined by multiplying the unit price for the item by the estimated quantity of the item. 00 72 00 GENERAL CONDITIONS Page 6 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 68. Weekend Working Hours—Those hours between 8:00 a.m. and 8:30 p.m. on Saturday, and between 1:00 p.m. and 8:30 p.m. on Sunday or on a federal or state holiday observed by the City, as approved in advance by the City for performing Work. 69. Work—The entire construction or the various separately identifiable parts thereof required to be provided under the Contract Documents. Work includes and is the result of performing or providing all labor, services, and documentation necessary to produce such construction including any Change Order or Field Order,, and furnishing, installing, and incorporating all materials and equipment into such construction, all as required by the Contract Documents. 70. Working Day—Defined as a Business Day but excluding any days that weather or other conditions beyond the reasonable control of the Contractor prevents the performance of the principal unit of work underway for a continuous period of not less than 7 hours between 7:00 a.m. and 8:00 p.m. 1.02 Terminology A. The words and terms discussed in Paragraphs 1.02.B, C, D, and E are not defined terms that require initial capital letters, but, when used in the Bidding Requirements or Contract, have the indicated meaning. B. Intent of Certain Terms or Adjectives: The Contract includes the terms “as allowed,” “as approved,” “as ordered,” “as directed” or terms of like effect or import to authorize an exercise of judgment by City. In addition, the adjectives “reasonable,” “suitable,” “acceptable,” “proper,” “satisfactory,” or adjectives of like effect or import are used to describe an action or determination of City as to the Work. It is intended that such exercise of judgment, action, or determination will be to evaluate, in general, the Work for compliance with the information in the Contract Documents and with the design concept of the Project as a functioning whole as shown or indicated in the Contract Documents (unless there is a specific statement indicating otherwise). C. Defective: The word “defective,” when modifying the word “Work,” refers to Work that is unsatisfactory, faulty, or deficient in that it: 1. does not conform to the Contract Documents; or 2. does not meet the requirements of any applicable inspection, reference standard, test, or approval referred to in the Contract Documents; or 3. has been damaged prior to City’s written notice of Final Acceptance. D. Furnish, Install, Perform, Provide 1. The word “furnish,” when used in connection with services, materials, or equipment, means to supply and deliver said services, materials, or equipment to the Site (or some other specified location) ready for use or installation and in usable or operable condition. 2. The word “install,” when used in connection with services, materials, or equipment, means to put into use or place in final position said services, materials, or equipment complete and ready for intended use. 3. The words “perform” or “provide,” when used in connection with services, materials, or equipment, means to execute, carry out, furnish and install said services, materials, or equipment complete and ready for intended use. 00 72 00 GENERAL CONDITIONS Page 7 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 4. If the Contract Documents establish an obligation of Contractor with respect to specific services, materials, or equipment, but do not expressly use any of the four words “furnish,” “install,” “perform,” or “provide,” then Contractor shall furnish and install said services, materials, or equipment complete and ready for intended use. E. Unless stated otherwise in the Contract, words or phrases that have a well-known technical or construction industry or trade meaning are used in the Contract in accordance with such recognized meaning. ARTICLE 2 – PRELIMINARY MATTERS 2.01 Delivery of Performance and Payment Bonds; Evidence of Insurance A. Performance and Payment Bonds: When Contractor delivers the signed counterparts of the Agreement to City, Contractor shall also deliver to City the performance bond , payment bond and maintenance bond that comply with the provisions of Chapter 2253 of the Texas Government Code. Work will not be allowed to begin until the performance and payment bonds have been provided by the Contractor to the City. B. Evidence of Contractor’s Insurance: When Contractor delivers the signed counterparts of the Agreement to City, Contractor shall also deliver to City, with copies to each additional insured (as identified in the Contract), the certificates, endorsements, and other evidence of insurance required to be provided by Contractor in accordance with Article 6. Work will not be allowed to begin until the evidence of insurance has been provided by the Contractor to the City. 2.02 Copies of Documents A. City shall furnish to Contractor one (1) original executed copy and one (1) electronic copy of the Contract, and three (3) additional copies of the Drawings. Additional printed copies will be furnished upon request at the cost of reproduction. 2.03 Before Starting Construction Baseline starting Work, Contractor shall submit for review by City the following in accordance with the Contract Documents: A. Baseline Schedules in accordance with General Requirements, Section 01 32 16. B. Preliminary Schedule of Submittals. C. Preliminary Schedule of Values: For lump sum contracts, a Schedule of Values for all of the Work that includes quantities and prices of items that when added together equal the Contract Price and subdivides the Work into component parts in sufficient detail to serve as the basis for progress payments during performance of the Work. Such prices will include an appropriate amount of overhead and profit applicable to each item of Work. 2.04 Preconstruction Meeting A. Before any Work at the Site is started, the Contractor shall attend a Preconstruction Meeting as specified in Section 01 31 19. 2.05 Public Meeting A. Contractor may not mobilize any equipment, materials, or resources to the Site prior to Contractor attending the Public Meeting as scheduled by the City. 00 72 00 GENERAL CONDITIONS Page 8 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 2.06 Initial Acceptance of Schedules A. No progress payment shall be made to Contractor until acceptable Project Schedules are submitted to City in accordance with the Contract Documents. 2.07 Electronic Submittals and Transmittals A. Except as otherwise stated elsewhere in the Contract, the City and Contractor may send, and shall accept, Electronic Documents transmitted by Electronic Means. B. If the Contract does not establish protocols for Electronic Means, then City and Contractor shall jointly develop such protocols. C. Subject to any governing protocols for Electronic Means, when transmitting Electronic Documents by Electronic Means, the transmitting party makes no representations as to long- term compatibility, usability, or readability of the Electronic Documents resulting from the recipient’s use of software application packages, operating systems, or computer hardware differing from those used in the drafting or transmittal of the Electronic Documents. ARTICLE 3 – CONTRACT DOCUMENTS: INTENT, REQUIREMENTS, REUSE 3.01 Intent A. The Contract Documents are complementary; what is required by one Contract Document is as binding as if required by all. B. It is the intent of the Contract to describe a functionally complete Project to be constructed in accordance with the Contract Documents. Any labor, documentation, services, materials, or equipment that reasonably may be inferred from the Contract Documents or from prevailing custom or trade usage as being required to produce the indicated result will be provided whether or not specifically called for, at no additional cost to City. C. City will issue clarifications and interpretations of the Contract Documents as provided herein. D. The Specifications may vary in form, forma and style. Some Specification sections may be written in varying degrees of streamlined or declarative style, and some sections may be relatively narrative by comparison. Omission of such words and phrases as “the Contractor shall,” “in conformity with,” “as shown,” or “as specified” are intentional in streamlined sections. Omitted words and phrases shall be supplied by inference. Similar types of provisions may appear in various parts of a section or articles within a part depending on the format of the section. The Contractor shall not take advantage of any variation of form, format or style in making Contract Claims or Damage Claims. E. The cross-referencing of Specification sections under the subparagraph heading “Related Sections include but are not necessarily limited to:” and elsewhere within each Specification section is provided as an aid and convenience to the Contractor. The Contractor shall not rely on the cross-referencing provided and shall be responsible to coordinate the entire Work under the Contract Documents and provide a complete Project whether or not cross-referencing is provided in each section or whether the cross-referencing is complete or accurate. 3.02 Reference Standards A. Standards Specifications, Codes, Laws and Regulations 00 72 00 GENERAL CONDITIONS Page 9 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 1. Reference in the Contract Documents to standard specifications, manuals, reference standards, or codes of any technical society, organization, or association, or to Laws or Regulations, whether such reference be specific or by implication, means the standard specification, manual, reference standard, code, or Laws or Regulations in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there were no Bids), except as may be otherwise specifically stated in the Contract Documents. 2. No provision of any such standard specification, manual, reference standard, or code, and no instruction of a Supplier, will be effective to change the duties or responsibilities of City, Contractor, or any of their subcontractors, consultants, agents, or employees from those set forth in the Contract Documents. No such provision or instruction shall be effective to assign to City or any of its officers, elected or appointed officials, directors, members, partners, employees, agents, consultants, or subcontractors, any duty or authority to supervise or direct the performance of the Work or any duty or authority to undertake responsibility inconsistent with the provisions of the Contract Documents. 3.03 Reporting and Resolving Discrepancies A. Reporting Discrepancies 1. Contractor’s Verification of Figures and Field Measurements: Before undertaking each part of the Work, Contractor shall carefully study the Contract Documents, and check and verify pertinent figures and dimensions therein, particularly with respect to applicable field measurements, and conditions. Contractor shall promptly report in writing to City any conflict, error, ambiguity, or discrepancy that Contractor discovers, or has actual knowledge of, and shall obtain a written interpretation or clarification from City before proceeding with any Work affected thereby. 2. Contractor’s Review of Contract Documents: If, before or during the performance of the Work, Contractor discovers any conflict, error, ambiguity, or discrepancy within the Contract Documents, or between the Contract Documents and (a) any applicable Law or Regulation, (b) actual field conditions, (c) any standard specification, manual, reference standard, or code, or (d) any instruction of any Supplier, then Contractor shall promptly report it to City in writing. Contractor shall not proceed with the Work affected thereby (except in an emergency as required by Paragraph 7.1717) until the conflict, error, ambiguity, or discrepancy is resolved, by a clarification or interpretation by City, or by an amendment or supplement to the Contract issued pursuant to Paragraph 11.01. 3. Contractor shall not be liable to City for failure to report any conflict, error, ambiguity, or discrepancy in the Contract Documents unless Contractor had actual knowledge thereof. B. Resolving Discrepancies 1. Except as may be otherwise specifically stated in the Contract Documents, the provisions of the Contract Documents take precedence in resolving any conflict, error, ambiguity, or discrepancy between such provisions of the Contract Documents and: a. the provisions of any standard specification, manual, reference standard, or code, or the instruction of any Supplier; or b. the provisions of any Laws or Regulations applicable to the performance of the Work (unless such an interpretation of the provisions of the Contract Documents would result in violation of such Law or Regulation). 00 72 00 GENERAL CONDITIONS Page 10 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 2. In case of discrepancies, figured dimensions shall govern over scaled dimensions, Drawings shall govern over Specifications, and Supplementary Conditions shall govern over General Conditions and Specifications. 3.04 Requirements of the Contract Documents A. During the performance of the Work and until final payment, Contractor shall submit to the City in writing all matters in question concerning the requirements of the Contract Documents (sometimes referred to as requests for information or interpretation—RFIs), or relating to the acceptability of the Work under the Contract Documents, as soon as possible after such matters arise. City will be the interpreter of the requirements of the Contract Documents, and judge of the acceptability of the Work. B. City will, with reasonable promptness, render a written clarification, interpretation, or decision on the issue submitted, or initiate an amendment or supplement to the Contract Documents. City’s written clarification, interpretation, or decision will be final and binding on Contractor, unless Contractor appeals by filing a Contract Claim. 3.05 Reuse of Documents A. Contractor and its Subcontractors and Suppliers shall not: 1. have or acquire any title to or ownership rights in any of the Drawings, Specifications, or other documents (or copies of any thereof) prepared by or bearing the seal of Engineer or its consultants, including electronic media versions, or reuse any such Drawings, Specifications, other documents, or copies thereof on extensions of the Project or any other project without written consent of City and specific written verification or adaptation by Engineer; or 2. have or acquire any title or ownership rights in any other Contract Documents, reuse any such Contract Documents for any purpose without City’s express written consent, or violate any copyrights pertaining to such Contract Documents. B. The prohibitions of this Paragraph 3.05 05 will survive final payment, or termination of the Contract. Nothing herein precludes Contractor from retaining copies of the Contract Documents for record purposes. ARTICLE 4 – COMMENCEMENT AND PROGRESS OF THE WORK 4.01 Commencement of Contract Time; Notice to Proceed A. The Contract Time will commence to run on the day indicated in the Notice to Proceed. A Notice to Proceed may be given at any time within 30 days after the Effective Date of the Contract. 4.02 Starting the Work A. Contractor shall start to perform the Work on the date when the Contract Time commences to run. No Work may be done at the Site prior to the date on which the Contract Time commences to run. 4.03 Delays in Contractor’s Progress A. If Contractor is delayed, City shall not be liable to Contractor for any claims, costs, losses, or damages (including but not limited to all fees and charges of engineers, architects, attorneys, 00 72 00 GENERAL CONDITIONS Page 11 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 and other professionals and all court or arbitration or other dispute resolution costs) sustained by Contractor on or in connection with any other project or anticipated project. The City shall be liable only to the extent allowed by the provisions of the Contract and as allowed by Subchapter I, Chapter 271 of the Texas Local Government Code. B. Contractor shall not be entitled to an adjustment in Contract Price or Contract Time for delay, disruption, or interference caused by or within the control of Contractor. Delay, disruption, and interference attributable to and within the control of a Subcontractor or Supplier shall be deemed to be within the control of Contractor. C. The Contractor shall receive no compensation for delays or hindrances to the Work, except when direct and unavoidable extra cost to the Contractor is caused by the failure of the City to provide information or material, if any, that the Contract specifies is to be furnished by the City. D. If Contractor’s performance or progress is delayed, disrupted, or interfered with by unanticipated causes not the fault of and beyond the control of City, Contractor, and those for whom they are responsible, then Contractor shall be entitled to an equitable adjustment in Contract Time. Such an adjustment will be Contractor’s sole and exclusive remedy for the delays, disruption, and interference described in this Paragraph 4.03. D. The Contractor is responsible for the prompt submission of a request for an adjustment to the Contract Time under this Paragraph to the City. Causes of delay, disruption, or interference that may give rise to an adjustment in Contract Time under this Paragraph include but are not limited to the following: 1. Severe and unavoidable natural catastrophes such as fires, floods, epidemics, and earthquakes; 2. Abnormal weather conditions; 3. Acts or failures to act of third-party utility owners or other third-party entities (other than those third-party utility owners or other third-party entities performing other work at or adjacent to the Site as arranged by or under contract with City, as contemplated in Article 8); and 4. Acts of war or terrorism. E. Contractor’s entitlement to an adjustment of Contract Time or Contract Price is limited as follows: 1. Contractor’s entitlement to an adjustment of the Contract Time is conditioned on the delay, disruption, or interference adversely affecting an activity on the critical path to completion of the Work, as of the time of the delay, disruption, or interference. 2. Contractor shall not be entitled to an adjustment in Contract Price for any delay, disruption, or interference if such delay is concurrent with a delay, disruption, or interference caused by or within the control of Contractor. Such a concurrent delay by Contractor shall not preclude an adjustment of Contract Time to which Contractor is otherwise entitled. 3. Adjustments of Contract Time or Contract Price are subject to the provisions of Article 11. F. Each Contractor request or Change Order seeking an increase in Contract Time or Contract Price must be supplemented by supporting data that sets forth in detail the following: 00 72 00 GENERAL CONDITIONS Page 12 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 1. The circumstances that form the basis for the requested adjustment; 2. The date upon which each cause of delay, disruption, or interference began to affect the progress of the Work; 3. The date upon which each cause of delay, disruption, or interference ceased to affect the progress of the Work; 4. The number of days’ increase in Contract Time claimed as a consequence of each such cause of delay, disruption, or interference; and 5. The impact on Contract Price, in accordance with the provisions of Paragraph 11.08. 6. Contractor shall also furnish such additional supporting documentation as City may require including, where appropriate, a revised Project Schedule indicating all the activities affected by the delay, disruption, or interference, and an explanation of the effect of the delay, disruption, or interference on the critical path to completion of the Work. G. Delays, disruption, and interference to the performance or progress of the Work resulting from the existence of a differing subsurface or physical condition, an Underground Facility that was not shown or indicated by the Contract Documents, or not shown or indicated with reasonable accuracy, and those resulting from undisclosed Hazardous Environmental Conditions, are governed by Article 5, together with the provisions of Paragraphs 4.03.F and 4.03.G. ARTICLE 5 – SITE; SUBSURFACE AND PHYSICAL CONDITIONS; HAZARDOUS ENVIRONMENTAL CONDITIONS 5.01 Availability of Lands A. City shall furnish the Site. City shall notify Contractor in writing of any encumbrances or restrictions not of general application but specifically related to use of the Site with which Contractor must comply in performing the Work. City will be responsible for obtaining any necessary easements for permanent structures or permanent changes in existing facilities. 1. The City has obtained or anticipates acquisition of and/or access to right-of-way, and/or easements. Any outstanding right-of-way and/or easements are anticipated to be acquired in accordance with the schedule set forth in the Supplementary Conditions. The Project Schedule submitted by the Contractor in accordance with the Contract Documents must consider any outstanding right-of-way, and/or easements. 2. Unless otherwise specified in the Contract Documents, the City has or anticipates moving and/or relocating utilities, and obstructions to the Site. Any outstanding movement or relocation of utilities or obstructions is anticipated in accordance with the schedule set forth in the Supplementary Conditions. The Project Schedule submitted by the Contractor in accordance with the Contract Documents must consider any outstanding utilities or obstructions to be moved and/or relocated by others. B. Upon reasonable written request of Contractor, City shall furnish Contractor with a current statement of record legal title and legal description of the lands upon which the Work is to be performed. 00 72 00 GENERAL CONDITIONS Page 13 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 C. Contractor shall provide for any additional lands and access thereto not included in the Site that may be required for construction facilities or storage of materials and equipment. The cost of such shall be part of the Contract Price. 5.02 Use of Site and Other Areas A. Limitation on Use of Site and Other Areas 1. Contractor shall confine construction equipment, temporary construction facilities, the storage of materials and equipment, worker car parking and the operations of workers to the Site, to adjacent areas that Contractor has arranged to use through construction easements or otherwise, and to other adjacent areas permitted by Laws and Regulations, and shall not unreasonably encumber the Site and such other adjacent areas with worker car parking, construction equipment or other materials or equipment. Contractor shall assume full responsibility for (a) damage to the Site; (b) damage to any such other adjacent areas used for Contractor’s operations; (c) damage to any other adjacent land or areas, or to improvements, structures, utilities, or similar facilities located at such adjacent lands or areas; and (d) for injuries, including death, and damage to or losses of property sustained by the owners or occupants of any such land or areas; provided that such damage, losses, injuries or deaths arose out of or result from the performance of the Work or arose out of or resulted from any other actions or conduct of the Contractor or those for whom Contractor is responsible. 2. At any time when, in the judgment of the City, the Contractor has obstructed, closed, or is carrying on operations in a portion of a street, right-of-way, or easement greater than is necessary for proper execution of the Work, the City may require the Contractor to reduce the area impacted to only that necessary for proper execution of the Work and/or to finish the section on which operations are in progress before work is commenced on any additional area of the Site. 3. Construction equipment, spoil materials, supplies, forms, buildings, labs, or equipment and supply storage buildings, or any other item that may be transported by flood flows, shall not be stored within existing federal floodways during the course of the Work. 4. Should any Damage Claim be made by any such owner or occupant adversely impacted because of the performance of the Work, Contractor shall promptly attempt to resolve the Damage Claim. 5. PURSUANT TO PARAGRAPH 7.21, CONTRACTOR SHALL INDEMNIFY AND HOLD HARMLESS CITY AND ITS OFFICERS, ELECTED AND APPOINTED OFFICIALS, AND EMPLOYEES, FROM AND AGAINST ALL CLAIMS, COSTS, LOSSES, AND DAMAGES ARISING OUT OF OR RELATING TO ANY CLAIM OR ACTION, LEGAL OR EQUITABLE, BROUGHT BY ANY SUCH ADVERSELY IMPACTED OWNER OR OCCUPANT AGAINST CITY. B. Removal of Debris During Performance of the Work: During the progress of the Work the Contractor shall keep the Site and other adjacent areas free from accumulations of waste materials, rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other debris will conform to applicable Laws and Regulations. C. Site Maintenance Cleaning: If 24 hours after written notice is given to the Contractor that the clean-up at the Site is insufficient or occurring in a manner unsatisfactory to the City, the Contractor fails to correct the unsatisfactory condition and/or procedures, the City may take 00 72 00 GENERAL CONDITIONS Page 14 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 such direct action as the City deems appropriate to correct the clean-up deficiencies cited to the Contractor in the written notice, and the costs of such direct corrective action, plus 25 % of such costs, shall be deducted from the monies due or to become due to the Contractor under the Contract. D. Final Site Cleaning: Prior to Final Acceptance of the Work, Contractor shall clean the Site and the Work and make it ready for utilization by City and any adjacent property owners, if applicable. At the completion of the Work, Contractor shall remove from the Site and adjacent areas all tools, appliances, construction equipment and machinery, surplus materials, waste materials, rubbish and other debris and shall restore to original condition or better all areas impacted or disturbed by the Work. E. Loading of Structures: Contractor shall not load nor permit any part of any structure to be loaded in any manner that will endanger the structure, nor shall Contractor subject any part of the Work or adjacent structures or land to stresses or pressures that will endanger them. 5.03 Subsurface and Physical Conditions A. Reports and Drawings: The Supplementary Conditions identify: 1. Those reports known to City of explorations and tests of subsurface conditions at or contiguous to the Site; and 2. Those drawings known to City of existing physical conditions at or contiguous to the Site, including those drawings known to City depicting existing surface or subsurface structures at or contiguous to the Site (except Underground Facilities.). B. Underground Facilities: Underground Facilities are shown or indicated on the Drawings, pursuant to Paragraph 5.05, and not in the drawings referred to in Paragraph 5.03.A. Information and data regarding the presence or location of Underground Facilities are not intended to be categorized, identified, or defined as technical data. C. Reliance by Contractor on Technical Data: Contractor is provided certain technical data identified in the Supplementary Conditions with respect to such reports and drawings for its use, but the City does not warrant or guarantee the accuracy of the information, and such information including reports and drawings are not Contract Documents. Contractor may not make any Contract Claim against City, or any of theirits officers, elected or appointed officials, directors, members, partners, employees, agents, consultants, or subcontractors with respect to: 1. the completeness or accuracy of such reports and drawings for Contractor’s purposes, including, but not limited to, any aspects of the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor, and safety precautions and programs incident thereto; or 2. other data, interpretations, opinions, and information contained in such reports or shown or indicated in such drawings; or 3. the contents of other Site-related documents made available to Contractor, such as record drawings from other projects at or adjacent to the Site, or City’s archival documents concerning the Site; or 4. any Contractor interpretation of or conclusion drawn from any “technical data” or any such other data, interpretations, opinions, or information. 00 72 00 GENERAL CONDITIONS Page 15 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 5.04 Differing Subsurface or Physical Conditions A. Notice by Contractor: If Contractor believes that any subsurface or physical condition that is uncovered or revealed at the Site either: 1. is of such a nature as to establish that any “technical data” is materially inaccurate; or 2. is of such a nature as to require a change in the Contract Documents; or 3. differs materially from that shown or indicated in the Contract Documents; or 4. is of an unusual nature, and differs materially from conditions ordinarily encountered and generally recognized as inherent in work of the character provided for in the Contract Documents; then Contractor shall, promptly after becoming aware thereof and before further disturbing the subsurface or physical conditions or performing any Work in connection therewith (except in an emergency as required by Paragraph 7.17), notify City in writing about such condition. B. Possible Price and Time Adjustments 1. Contractor shall not be entitled to any adjustment in the Contract Price or Contract Time if: a. Contractor knew of the existence of such condition at the time Contractor made a final commitment to City with respect to Contract Price and Contract Time by the submission of a Bid or becoming bound under the Contract; or b. The existence of such condition reasonably could have been discovered or revealed as a result of the examination of the Contract Documents or the Site; or c. Contractor failed to give the written notice required by Paragraph 5.04.A. C. Underground Facilities; Hazardous Environmental Conditions: Paragraph 5.05 governs rights and responsibilities regarding the presence or location of Underground Facilities. Paragraph 5.06 governs rights and responsibilities regarding Hazardous Environmental Conditions. The provisions of Paragraphs 5.03 and 5.04 are not applicable to the presence or location of Underground Facilities, or to Hazardous Environmental Conditions. 5.05 Underground Facilities A. Shown or Indicated: The information and data shown or indicated in the Contract Documents with respect to Underground Facilities at or contiguous to the Site is based on information and data furnished to City or Engineer by the owners of such Underground Facilities, including City, or by others, unless it is otherwise expressly provided in the Supplementary Conditions:: 1. City and Engineer shall not be responsible for the accuracy or completeness of any such information or data provided by others; and 2. the cost of all of the following are included in the Contract Price, and Contractor shall have full responsibility for: a. reviewing and checking all information and data; b. verifying the actual location of those Underground Facilities shown or indicated in the Contract Documents as being within the area affected by the Work, by exposing such Underground Facilities during the course of construction; 00 72 00 GENERAL CONDITIONS Page 16 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 c. coordination and adjustment of the Work with the owners (including City) of such Underground Facilities, during construction; and d. the safety and protection of all existing Underground Facilities at the Site, and repairing any damage thereto resulting from the Work. B. Not Shown or Indicated: 1. If an Underground Facility that is uncovered or revealed at the Site was not shown or indicated on the Drawings or otherwise indicated in the Contract Documents, or was not shown or indicated on the Drawings or in the Contract Documents with reasonable accuracy, then Contractor shall, promptly after becoming aware thereof and before further disturbing conditions affected thereby or performing any Work in connection therewith (except in an emergency as required by Paragraph 7.17), identify the owner of such Underground Facility and give notice to that owner and to City. Contractor shall be responsible for the safety and protection of such discovered Underground Facility. 2. If City concludes that a change in the Contract Documents is required, a Change Order may be issued to reflect and document such consequences, subject to the provisions of Article 11. 3. Verification of existing utilities, structures, and service lines shall include notification of all utility companies a minimum of 48 hours in advance of construction including exploratory excavation if necessary. 5.06 Hazardous Environmental Conditions at Site A. Reports and Drawings: The Supplementary Conditions identify: 1. those reports known to City relating to Hazardous Environmental Conditions that have been identified at the Site; or 2. drawings known to City relating to Hazardous Environmental Conditions that have been identified at the Site. B. Reliance by Contractor on Technical Data: Contractor is provided certain technical data identified in the Supplementary Conditions with respect to such reports and drawings for its use, but the City does not warrant or guarantee the accuracy of the information, and such information including reports and drawings are not Contract Documents. Contractor may not make any Contract Claim against City, or any of its officers, elected or appointed officials, directors, members, partners, employees, agents, consultants, or subcontractors with respect to: 1. the completeness or accuracy of such reports and drawings for Contractor’s purposes, including, but not limited to, any aspects of the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor, and safety precautions and programs incident thereto; or 2. other data, interpretations, opinions, and information contained in such reports or shown or indicated in such drawings; or 3. the contents of other Site-related documents made available to Contractor, such as record drawings from other projects at or adjacent to the Site, or City’s archival documents concerning the Site; or 00 72 00 GENERAL CONDITIONS Page 17 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 4. any Contractor interpretation of or conclusion drawn from any “technical data” or any such other data, interpretations, opinions, or information. C. Contractor shall not be responsible for a Hazardous Environmental Condition uncovered or revealed at the Site if such Hazardous Environmental Condition was not shown or indicated in Drawings or Specifications or identified if the removal or remediation of such Hazardous Environmental Condition was not identified in the Contract Documents to be within the scope of the Work. Contractor shall be responsible for a Hazardous Environmental Condition created by the actions of or with any materials brought to the Site by Contractor, Subcontractors, Suppliers or anyone else for whom Contractor is responsible and the costs associated with the same. D. If Contractor encounters, uncovers, or reveals a Hazardous Environmental Condition whose removal or remediation is not expressly identified in the Contract Documents as being within the scope of the Work, or if Contractor or anyone for whom Contractor is responsible creates a Hazardous Environmental Condition, then Contractor shall immediately: (1) secure or otherwise isolate such condition; (2) stop all Work in connection with such condition and in any area affected thereby (except in an emergency as required by Paragraph 7.17); and (3) notify City (and promptly thereafter confirm such notice in writing). City may consider the necessity to retain a qualified expert to evaluate such condition or take corrective action, if any. E. Contractor shall not be required to resume Work in connection with a Hazardous Environmental Condition identified pursuant to Paragraph 5.06.D or in any affected area until after City has obtained any required permits related thereto, and delivered written notice to Contractor either (1) specifying that such condition and any affected area is or has been rendered safe for the resumption of Work, or (2) specifying any special conditions under which such Work may be resumed. F. If, after receipt of such written notice, Contractor does not agree to resume such Work based on a reasonable belief it is unsafe, or does not agree to resume such Work under such special conditions, then City may order the portion of the Work that is in the area affected by such condition to be deleted from the Work and the Contract Price. City may have such deleted portion of the Work performed by City’s own forces or others. G. TO THE FULLEST EXTENT PERMITTED BY LAWS AND REGULATIONS, CONTRACTOR SHALL INDEMNIFY AND HOLD HARMLESS CITY, AND ITS OFFICERS, ELECTED AND APPOINTED OFFICIALS, DIRECTORS, MEMBERS, PARTNERS, EMPLOYEES, AGENTS, CONSULTANTS, AND SUBCONTRACTORS OF EACH AND ANY OF THEM, FROM AND AGAINST ALL CLAIMS, COSTS, LOSSES, AND DAMAGES (INCLUDING BUT NOT LIMITED TO ALL FEES AND CHARGES OF ENGINEERS, ARCHITECTS, ATTORNEYS, AND OTHER PROFESSIONALS AND ALL COURT ARBITRATION OR OTHER DISPUTE RESOLUTION COSTS) FOR PERSONAL INJURY, DEATH OR PROPERTY DAMAGE ARISING OUT OF OR RELATING TO A HAZARDOUS ENVIRONMENTAL CONDITION CREATED BY CONTRACTOR OR BY ANYONE FOR WHOM CONTRACTOR IS RESPONSIBLE. NOTHING IN THIS PARAGRAPH 5.06.CityG OBLIGATES CONTRACTOR TO INDEMNIFY ANY INDIVIDUAL OR ENTITY FROM AND AGAINST THE CONSEQUENCES OF THAT INDIVIDUAL’S OR ENTITY’S OWN NEGLIGENCE. H. The provisions of Paragraphs 5.03, 5.04, and 5.05 do not apply to the presence of a Hazardous Environmental Condition uncovered or revealed at the Site. 00 72 00 GENERAL CONDITIONS Page 18 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 ARTICLE 6 – BONDS AND INSURANCE 6.01 Licensed Sureties and Insurers A. All bonds and insurance required by the Contract Documents to be purchased and maintained by Contractor shall be obtained from surety or insurance companies that are duly licensed or authorized in the State of Texas to issue bonds or insurance policies for the limits and coverages required. Such surety and insurance companies shall also meet such additional requirements and qualifications as may be provided in the Supplementary Conditions. 6.02 Performance, Payment, and Maintenance Bonds A. Contractor shall furnish a performance bond and a payment bond, in accordance with the provisions of the Texas Government Code Chapter 2253 or successor statute and as required by the City, each in an amount at least equal to the Contract Price, as security for the faithful performance and payment of all of Contractor’s obligations under the Contract. The performance and payment bonds must be provided by the Contractor to the City prior to the Contractor beginning any Work. B. Contractor shall furnish maintenance bonds in an amount equal to the Contract Price as security to protect the City against any defects in any portion of the Work described in the Contract Documents. Maintenance bonds shall remain in effect for two (2) years after the date of Final Acceptance by the City. The maintenance bond(s) shall be provided as directed by the City as part of the close-out of the Contract and shall be provided prior to the final payment being made. C. All bonds shall be in the form prescribed by the Contract Documents, except as provided otherwise by Laws and Regulations, and must be issued and signed by a surety named in “Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring Companies” as published in Department Circular 570 (as amended and supplemented) by the Bureau of the Fiscal Service, U.S. Department of the Treasury. A bond signed by an agent or attorney-in-fact must be accompanied by a certified copy of that individual’s authority to bind the surety. The evidence of authority must show that it is effective on the date the agent or attorney-in-fact signed the accompanying bond. D. If the surety on a bond furnished by Contractor is declared bankrupt or becomes insolvent, or the surety ceases to meet the requirements above, or its right to do business is terminated in the State of Texas, then Contractor shall promptly notify City in writing and shall, within 30 days after the event giving rise to such notification, provide another bond and surety, both of which must comply with the bond and surety requirements above. E. If Contractor has failed to obtain a required bond, City may refuse to allow the Contractor to begin Work, exclude the Contractor from the Site and exercise City’s termination rights under Article 15. F. Upon request to Contractor from any Subcontractor, Supplier, or other person or entity claiming to have furnished labor, services, materials, or equipment used in the performance of the Work, Contractor shall provide a copy of the payment bond to such person or entity. 6.03 Certificates of Insurance A. Contractor shall deliver to City, with copies to each additional insured and loss payee identified in the Supplementary Conditions, certificates of insurance and endorsements (and 00 72 00 GENERAL CONDITIONS Page 19 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 other evidence of insurance requested by City or any other additional insured) establishing that Contractor has obtained and is maintaining the policies and coverages required by these General Conditions and the Supplementary Conditions prior to beginning any Work. 1. The certificate of insurance shall document the City, and all identified entities named in the Supplementary Conditions as “additional insureds” on all liability policies. 2. The Contractor’s general liability insurance shall include a “per project” or “per location” endorsement, that shall be identified in the certificate of insurance provided to the City. 3. The certificate shall be signed by an agent authorized to bind coverage on behalf of the insured, be complete in its entirety, and show complete insurance carrier names as listed in the current A.M. Best Property & Casualty Guide. 4. The insurers for all policies must be licensed and/or approved to do business in the State of Texas. Except for workers’ compensation, all insurers must have a minimum rating of A-: VII in the current A. M. Best Key Rating Guide or have reasonably equivalent financial strength and solvency to the satisfaction City. If the rating is below that required, written approval of City is required. 5. All applicable policies shall include a Waiver of Subrogation (Rights of Recovery) in favor of the City. In addition, the Contractor agrees to waive all rights of subrogation against the Engineer (if applicable), and each additional insured identified in the Supplementary Conditions 6. Failure of the City to demand such certificates or other evidence of full compliance with the insurance requirements or failure of the City to identify a deficiency from evidence that is provided shall not be construed as a waiver of Contractor’s obligation to maintain such lines of insurance coverage or to provide such certificates or other evidence of full compliance with the insurance requirements. 7. If insurance policies are not written for specified coverage limits, an Umbrella or Excess Liability insurance for any differences is required. Excess Liability shall follow form of the primary coverage. 8. Unless otherwise stated, all required insurance shall be written on the “occurrence basis”. If If City agrees in writing that coverage is underwrittenmay be written on a claims-made basis, the retroactive date shall be coincident with or prior to the date of the effective date of the Agreement and the certificate of insurance shall state that the coverage is claims- made and the retroactive date. The insurance coverage shall be maintained for the duration of the Contract and for three (3) years following Final Acceptance or for the warranty period provided for under the Contract Documents or for the warranty period, whichever is longer. An annual certificate of insurance submitted to the City shall evidence such insurance coverage. 9. Policies shall have no exclusions by endorsements that either nullify or amend the required lines of coverage, nor or decrease the limits of said coverage unless such endorsements are approved in writing by the City. In the event a Notice of an Award has been issued or the Agreement executed, and the policy exclusions are determined to be unacceptable or the City desires that the Contractor obtain additional insurance coverage the contract price shall be adjusted by the cost of the premium for such additional coverage plus 10%. 00 72 00 GENERAL CONDITIONS Page 20 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 10. For any proposed self-insured retention (SIR),) in excess of $25,000.00, affecting insurance coverage, Contractor must obtain the written approval of the City in regard to asset value and stockholders' equity. In lieu of traditional insurance, proposed alternative coverage maintained through insurance pools or, risk retention groups, or self-funding will also require the written approval of the City. 11. Any deductible in excess of $5,000.00, for any policy that does not provide coverage on a first-dollar basis must be acceptable to and approved in writing by the City. 12. City, at its sole discretion, reserves the right to review the insurance requirements and to make reasonable adjustments to insurance coverages and limits when deemed necessary and prudent by the City based upon the scope of the Work, changes in statutory law, court decision or the claims history of the industry as well as of the contracting party to the City. The City will provide prior notice of 90 days and the insurance adjustments shall be incorporated into the Work by Change Order. 13. City shall be entitled, upon written request to Contractor and without expense to City, to receive copies of policies and endorsements thereto and. City may make any reasonable requests for deletion or revision or modifications of particular policy terms, conditions, limitations, or exclusions necessary to conform the policy and endorsements to the requirements of the Contract. Deletions, revisions, or modifications shall not be required where policy provisions are established by law or regulations binding upon either party or the underwriter on any such policies. 14. City shall not be responsible for the direct payment of insurance premium costs for Contractor’s insurance. 6.04 Contractor’s Insurance A. Workers Compensation and Employers’ Liability: Contractor shall purchase and maintain such insurance coverage with limits consistent with statutory benefits outlined in the Texas Workers’ Compensation Act (Texas Labor Code, Ch. 406, as amended), and minimum limits for Employers’ Liability as is appropriate for the Work being performed and as will provide protection from claims set forth below which may arise out of or result from Contractor’s performance of the Work and Contractor’s other obligations under the Contract Documents, whether it is to be performed by Contractor, any Subcontractor or Supplier, or by anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts any of them may be liable: 1. claims under workers’ compensation, disability benefits, and other similar employee benefit acts; 2. claims for damages because of bodily injury, occupational sickness or disease, or death of employees. B. Commercial General Liability. Coverage shall include but not be limited to covering liability (bodily injury, including death, or property damage) arising from: premises/operations, independent contractors, products/completed operations, personal injury including death, liability under an insured contract, and explosion/collapse/underground (where those exposures exist). Insurance shall be provided on an occurrence basis, and as comprehensive as the current Insurance Services Office (ISO) policy. This insurance shall apply as primary insurance with respect to any other insurance or self-insurance programs afforded to the City. The Commercial General Liability policy shall have no exclusions by endorsements that 00 72 00 GENERAL CONDITIONS Page 21 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 would alter or nullify premises/operations, products/completed operations, contractual, personal injury, or advertising injury, that are normally contained with the policy, unless the City approves such exclusions in writing. For construction projects that present a substantial completed operation exposure, the City may require the Contractor to maintain completed operations coverage for a minimum of no less than three (3) years following the completion of the project (if identified in the Supplementary Conditions)). C. Automobile Liability. A commercial business auto policy shall provide coverage on “any auto”, defined as autos owned, hired and non-owned and provide indemnity for claims for damages because of bodily injury or death of any person and/or property damage arising out of or related to the work, maintenance or use of any motor vehicle by the Contractor, any Subcontractor or Supplier, or by anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts any of them may be liable. D. Railroad Protective Liability. If any of the Work or any warranty work is within the limits of railroad right-of-way, the Contractor shall comply with the requirements identified in the Supplementary Conditions. E. Notification of Policy Cancellation: Contractor shall immediately notify City upon cancellation or other loss of insurance coverage. Contractor shall stop Work until replacement insurance has been procured. There shall be no time credit for delays or days not worked pursuant to this section. 6.05 Acceptance of Bonds and Insurance; Option to Replace A. If City has any objection to the coverage afforded by or other provisions of the bonds or insurance required to be purchased and maintained by the Contractor in accordance with Article 6 or the Supplementary Conditions on the basis of non-conformance with the Contract Documents, the City shall so notify the Contractor in writing within 10 Business Days after receipt of the certificates (or other evidence requested). Contractor shall provide to the City such additional information in respect of insurance provided as the City may reasonably request. If Contractor does not purchase or maintain all of the bonds and insurance required by the Contract Documents, the City shall notify the Contractor in writing of such failure prior to the start of the Work, or of such failure to maintain prior to any change in the required coverage. Such failure to provide bonds or insurance as required by the Contract Documents is a breach of the terms of the Contract and the City may terminate the Contractor in accordance with the provisions of the Contract Documents. ARTICLE 7 – CONTRACTOR’S RESPONSIBILITIES 7.01 Contractor’s Means and Methods of Construction A. Contractor shall be solely responsible for the means, methods, techniques, sequences, and procedures of construction. B. If the Contract Documents note, or Contractor determines, that professional engineering or other design services are needed to carry out Contractor’s responsibilities for construction means, methods, techniques, sequences, and procedures, or for Site safety, then Contractor shall cause such services to be provided by a properly licensed design professional, at Contractor’s expense. Such services are not City-delegated professional design services under this Contract, and neither City nor Engineer has any responsibility with respect to (1) 00 72 00 GENERAL CONDITIONS Page 22 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 Contractor’s determination of the need for such services, (2) the qualifications or licensing of the design professionals retained or employed by Contractor, (3) the performance of such services, or (4) any errors, omissions, or defects in such services. 7.02 Supervision and Superintendence A. Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting such attention thereto and applying such skills and expertise as may be necessary to perform the Work in accordance with the Contract Documents. B. At all times during the progress of the Work, Contractor shall identify and assign a competent superintendent, who is proficient in English, and who shall not be replaced without written notice to City of the name of the replacement superintendent. If at any time the superintendent is not satisfactory to the City, Contractor shall, if requested by City, replace the superintendent with another satisfactory to City. C. Contractor shall notify the City 24 hours prior to moving areas during the sequence of construction. 7.03 Labor; Working Hours A. Contractor shall provide competent, suitably qualified personnel to survey and lay out the Work and perform construction as required by the Contract Documents. Contractor shall at all times maintain good discipline and order at the Site. B. Contractor shall be fully responsible to City for all acts and omissions of Contractor’s employees; of Suppliers and Subcontractors, and their employees; and of any other individuals or entities performing or furnishing any of the Work, just as Contractor is responsible for Contractor’s own acts and omissions. C. Except as otherwise required for the safety or protection of persons or the Work or property at the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work at the Site shall be performed during regular working hours on Business Days. Contractor will not permit the performance of Work outside of regular working hours on Business Days without City’s prior written consent (which will not be unreasonably withheld)). Contractor’s written request (by letter or electronic communication) for City’s written consent must be made as follows: 1. for Work beyond regular working hours on Business Days, request must be made by noon at least two (2) Business Days prior; 2. for Work during Weekend Working Hours, request must be made by noon of the preceding Wednesday; and 3. for Work on state or federal holidays observed by the City, request must be made sufficiently in advance of the holiday, to satisfy requirements for City Council approval. 7.04 Services, Materials, and Equipment A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full responsibility for all services, materials, equipment, labor, transportation, construction equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary facilities, temporary facilities, and all other facilities and incidentals necessary for the performance, Contractor required testing, start up, and completion of the Work, whether or not such items are specifically called for in the Contract Documents. 00 72 00 GENERAL CONDITIONS Page 23 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 B. All materials and equipment incorporated into the Work shall be as specified or, if not specified, shall be of sufficient quality to complete the Work, and must be new and of good quality, except as otherwise provided in the Contract Documents. All special warranties and guarantees required by the Specifications shall expressly run to the benefit of City. If required by City, Contractor shall furnish satisfactory evidence (including reports of required tests) as to the source, kind, and quality of materials and equipment. C. All materials and equipment to be incorporated into the Work shall be stored, applied, installed, connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of the applicable Supplier, except as otherwise may be provided in the Contract Documents. D. All items of standard equipment to be incorporated into the Work shall be the latest model at the time of bid, unless otherwise specified. 7.05 Project Schedule A. Contractor shall adhere to the Project Schedule established in accordance with Paragraph 2.06 and the General Requirements as it may be adjusted from time to time as provided below. 1. Contractor shall submit to the City for acceptance (to the extent indicated in Paragraph 2.06 and the General Requirements) proposed adjustments in the Project Schedule that will not result in changing the Contract Time. Such adjustments must comply with any provisions of the General Requirements applicable thereto. 2. Contractor shall submit to City a monthly Project Schedule with a monthly progress payment request for the duration of the Contract in accordance with the Construction Progress Schedule, General Requirements 01 32 16. 3. Proposed adjustments in the Project Schedule that will change the Contract Time shall be submitted in accordance with the requirements of Article 11. Adjustments in Contract Time may only be made by a Change Order. 7.06 “Or Equals” A. Contractor’s Request; Governing Criteria: Whenever an item of equipment or material is specified or described in the Contract Documents by using the names of one or more proprietary items or specific Suppliers, the Contract Price has been based upon Contractor furnishing such item as specified. The specification or description of such an item is intended to establish the type, function, appearance, and quality required. Unless the specification or description contains or is followed by words reading that no like, equivalent, or “or equal” item is permitted, Contractor may request that City permit the use of other items of equipment or material, or items from other proposed Suppliers, under the circumstances described below. 1. If City in its sole discretion determines that an item of equipment or material proposed by Contractor is functionally equal to that named and sufficiently similar so that no change in related Work will be required, it may be considered by City as an “or equal” item. For the purposes of this Paragraph, a proposed item of equipment or material will be considered functionally equal to an item so named if: a. the City determines that: 1) it is at least equal in materials of construction, quality, durability, appearance, strength, and design characteristics; 00 72 00 GENERAL CONDITIONS Page 24 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 2) it will reliably perform at least equally well the function and achieve the results imposed by the design concept of the completed Project as a functioning whole; 3) it has a proven record of performance and availability of responsive service; and 4) it is not objectionable to City. b. Contractor certifies that, if the proposed item is approved and incorporated into the Work: 1) there will be no increase in cost to the City or increase in Contract Time; and 2) the item will conform substantially to the detailed requirements of the item named in the Contract Documents. B. Contractor’s Expense: Contractor shall provide all data in support of any proposed “or equal” item at Contractor’s expense. C. City’s Evaluation and Determination: City will be allowed a reasonable time to evaluate each “or-equal” request. City may require Contractor to furnish additional data about the proposed “or-equal” item. City will be the sole judge of acceptability. No “or-equal” item will be ordered, furnished, installed, or utilized until City’s review is complete and City determines that the proposed item is an “or-equal.” City.” City will advise Contractor in writing of its determination. D. Effect of City’s Determination: Neither approval nor denial of an “or-equal” request will result in any change in Contract Price. The City’s denial of an “or-equal” request will be final and binding, and may not be reversed through an appeal under any provision of the Contract. E. Treatment as a Substitution Request: If City determines that an item of equipment or material proposed by Contractor does not qualify as an “or-equal” item, Contractor may request that City consider the item a proposed substitution pursuant to Paragraph 7.07. 7.07 Substitutions A. Contractor’s Request; Governing Criteria: Unless the specification or description of an item of equipment or material required to be furnished under the Contract Documents contains or is followed by words reading that no substitution is permitted, Contractor may request that City permit the use of other items of equipment or material under the circumstances described below. To the extent possible such requests must be made before commencement of related Work at the Site. 1. Contractor shall submit sufficient information as provided below to allow City to determine if the item of material or equipment proposed is functionally equivalent to that named and an acceptable substitution therefor. City will not accept requests for review of proposed substitute items of equipment or material from anyone other than Contractor. 2. The requirements for review by City will be as set forth in Paragraph 7.07.B, as supplemented by the Specifications, and as City may decide is appropriate under the circumstances. 3. Contractor shall make written application to City for review of a proposed substitute item of equipment or material that Contractor seeks to furnish or use. The application shall comply with Section 01 25 00 and: 00 72 00 GENERAL CONDITIONS Page 25 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 a. will certify that the proposed substitute item will: 1) perform adequately the functions and achieve the results called for by the general design; 2) be substantially similar in substance to the item specified; and 3) be well-suited to the same use as the item specified. b. will state: 1) the extent, if any, to which the use of the proposed substitute item will adversely impact Contractor’s achievement of Final Acceptance on or before the Contract Time; 2) whether use of the proposed substitute item in the Work will require a change in any of the Contract Documents (or in the provisions of any other direct contract with City for other work on the Project) to adapt the design to the proposed substitute item; and 3) whether incorporation or use of the proposed substitute item in connection with the Work is subject to payment of any license fee or royalty. c. will identify: 1) all variations of the proposed substitute item from the item specified; and 2) available engineering, sales, maintenance, repair, and replacement services. d. will contain an itemized estimate of all costs or credits that will result directly or indirectly from use of such substitute item, including but not limited to changes in Contract Price, shared savings, costs of redesign, and Damage Claims of other contractors affected by any resulting change. B. City’s Evaluation and Determination: City will be allowed a reasonable time to evaluate each substitution request. City may require Contractor to furnish additional data about the proposed substitute item. City will be the sole judge of acceptability. No substitute will be ordered, furnished, installed, or utilized until City’s review is complete and City determines that the proposed item is an acceptable substitution. City’s approval determination will be evidenced by a Change Order accounting for the substitution itself and all related impacts, including changes in Contract Price or Contract Time. City will advise Contractor in writing of any denial determination. C. Special Guarantee: City may require Contractor to furnish at Contractor’s expense a special performance guarantee or other surety with respect to any substitution. Contractor shall indemnify and hold harmless City and its officers, elected and appointed officials, employees, agents, consultants and subcontractors and anyone directly or indirectly employed by them from and against any and all claims, damages, losses and expenses (including attorney’s fees) arising out of or relateds to the use of substituted materials or equipment. D. Reimbursement of City’s Cost: City will record City’s costs in evaluating a substitution proposed or submitted by Contractor. Whether or not City approves a substitute so proposed or submitted by Contractor, Contractor shall reimburse City for evaluating each such proposed substitute. Contractor shall also reimburse City for the charges for making changes in the 00 72 00 GENERAL CONDITIONS Page 26 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 Contract Documents (or in the provisions of any other direct contract with City) resulting from the acceptance of each proposed substitute. E. Contractor’s Expense: Contractor shall provide all data in support of any proposed substitute at Contractor’s expense. F. City Substitution Reimbursement: Cost savings attributable to acceptance of a substitution shall be paid to City by Contractor by an appropriate Change Order decreasing the Contract Price. G. Effect of City’s Determination: If City approves the substitution request, Contractor shall execute the proposed Change Order and proceed with the substitution. The City’s denial of a substitution request will be final and binding, and may not be reversed through an appeal under any provision of the Contract. Contractor may challenge the scope of reimbursement costs imposed under Paragraph 7.07.D, by timely submittal of a Change Order. 7.08 Concerning Subcontractors and Suppliers A. Contractor shall perform with its own organization, and with the assistance of workmen under its immediate superintendence, work of a value not less than 35% of the Contract Price, unless otherwise approved by the City. B. Contractor may retain Subcontractors and Suppliers for the performance of parts of the Work. Contractor shall not employ any Subcontractor, Supplier, or other individual or entity, whether initially or as a replacement, against whom City may have reasonable objection. Contractor shall not be required to employ any Subcontractor, Supplier, or other individual or entity to furnish or perform any of the Work against whom Contractor has reasonable objection, except as provided in Paragraph 7.08.C. The Contractor’s retention of a Subcontractor or Supplier for the performance of parts of the Work will not relieve Contractor’s obligation to City to perform and complete the Work in accordance with the Contract. C. The City may require the use of specific Subcontractors, Suppliers, or other individuals or entities for the performance of designated parts of the Work , and will provide such requirements in the Supplementary Conditions. D. Contractor shall provide to City as part of the Bid, the identity of all proposed Subcontractors and Suppliers. Such proposed Subcontractor or Supplier shall be deemed acceptable to City unless City raises a substantive, reasonable objection prior to execution of the Agreement. E. Contractor shall be fully responsible to City for all acts and omissions of the Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the Work under a direct or indirect contract with Contractor just as Contractor is responsible for Contractor’s own acts and omissions. Nothing in the Contract: 1. shall create for the benefit of any such Subcontractor, Supplier, or other individual or entity any contractual relationship between City and any such Subcontractor, Supplier or other individual or entity; nor 2. shall create any obligation on the part of City to pay or to see to the payment of any moneys due any such Subcontractor, Supplier, or other individual or entity except as may otherwise be required by Laws and Regulations. F. No acceptance by City of any such Subcontractor or Supplier, whether initially or as a replacement, will constitute a waiver of the right of City to the completion of the Work in accordance with the Contract Documents, Contract Price and Contract Time. 00 72 00 GENERAL CONDITIONS Page 27 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 G. Contractor shall be solely responsible for scheduling and coordinating the tasks of Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the Work under a direct or indirect contract with Contractor. H. All Work performed for Contractor by a Subcontractor or Supplier must be pursuant to an appropriate contractual agreement that specifically binds the Subcontractor or Supplier to the applicable terms and conditions of the Contract for the benefit of City. Contractor must comply with all applicable federal, state, and local laws, statutes, ordinances or regulations, including but not limited to immigration laws, workers compensation laws and wage laws, in the hiring of any Subcontractor or Supplier and shall ensure that each Subcontractor or Supplier has the same obligations. I. Contractor shall restrict all Subcontractors and Suppliers from communicating with City, except through Contractor or in case of an emergency, or as otherwise expressly allowed in this Contract. 7.09 Wage Rates A. Duty to pay Prevailing Wage Rates: The Contractor shall comply with all requirements of Chapter 2258, Texas Government Code (as amended), including the payment of not less than the rates determined by the City Council of the City of Denton to be the prevailing wage rates in accordance with Chapter 2258. The then current prevailing wage rates at the time of execution of the Agreement are included in these Contract Documents. B. Penalty for Violation: A Contractor or any Subcontractor who does not pay the prevailing wage shall, upon demand made by the City, pay to the City $60 for each worker employed for each calendar day or part of the day that the worker is paid less than the prevailing wage rates stipulated in these contract documents. This penalty shall be retained by the City to offset its administrative costs, pursuant to Texas Government Code Section 2258.023. C. Complaints of Violations and City Determination of Good Cause: On receipt of information, including a complaint by a worker, concerning an alleged violation of Section 2258.023, Texas Government Code, by a Contractor or Subcontractor, the City shall make an initial determination, before the 31st day after the date the City receives the information, as to whether good cause exists to believe that the violation occurred. The City shall notify in writing the Contractor or Subcontractor and any affected worker of its initial determination. Upon the City’s determination that there is good cause to believe the Contractor or Subcontractor has violated Chapter 2258, the City shall retain the full amounts claimed by the claimant or claimants as the difference between wages paid and wages due under the prevailing wage rates, such amounts being retained from successive progress payments pending a final determination of the violation. D. Arbitration Required if Violation Not Resolved: An issue relating to an alleged violation of Section 2258.023, Texas Government Code, including a penalty owed to the City or an affected worker, shall be submitted to binding arbitration in accordance with the Texas General Arbitration Act (Article 224 et seq., Revised Statutes) if the Contractor or Subcontractor and any affected worker does not resolve the issue by agreement before the 15th day after the date the City makes its initial determination pursuant to Paragraph 7.09.C. If the persons required to arbitrate under this section do not agree on an arbitrator before the 11th day after the date that arbitration is required, a district court shall appoint an arbitrator on the petition of any of the persons. The City is not a party in the arbitration. The decision and 00 72 00 GENERAL CONDITIONS Page 28 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 award of the arbitrator is final and binding on all parties and may be enforced in any court of competent jurisdiction. E. Records to be Maintained: The Contractor and each Subcontractor shall, for a period of three (3) years following the date of Final Acceptance, maintain records that show (i) the name and occupation of each worker employed by the Contractor in the construction of the Work provided for in this Contract; and (ii) the actual per diem wages paid to each worker. The records shall be available in Denton County, Texas at all reasonable hours for inspection by the City. The provisions of Paragraph 7.23, Right to Audit, shall pertain to this inspection. F. Progress Payments: With each progress payment request or payroll period, whichever is less, the Contractor shall submit an affidavit stating that the Contractor has complied with the requirements of Chapter 2258, Texas Government Code. G. Posting of Wage Rates: The Contractor shall post prevailing wage rates in a conspicuous place at the Site at all times. H. Subcontractor Compliance: The Contractor shall include in its subcontracts and/or shall otherwise require all of its Subcontractors to comply with Paragraphs 7.09.A through 7.09.G. 7.10 Patent Fees and Royalties A. Contractor shall pay all patent or license fees and royalties and pay all costs incident to the use in the performance of the Work or the incorporation in the Work of any invention, design, process, product, or device which is the subject of patent rights or copyrights held by others. If an invention, design, process, product, or device is specified in the Contract Documents for use in the performance of the Work and if, to the actual knowledge of City, its use is subject to patent rights or copyrights calling for the payment of any patent or license fee or royalty to others, the existence of such rights will be disclosed in the Contract Documents. Failure of the City to disclose such information does not relieve the Contractor from its obligations to pay said fees or, royalties or costs to others. B. TO THE FULLEST EXTENT PERMITTED BY LAWS AND REGULATIONS, CONTRACTOR SHALL INDEMNIFY AND HOLD HARMLESS CITY, AND ITS OFFICERS, ELECTED AND APPOINTED OFFICIALS, DIRECTORS, MEMBERS, PARTNERS, EMPLOYEES, AGENTS, CONSULTANTS AND SUBCONTRACTORS OF EACH AND ANY OF THEM, FROM AND AGAINST ALL CLAIMS, COSTS, LOSSES, AND DAMAGES (INCLUDING BUT NOT LIMITED TO ALL FEES AND CHARGES OF ENGINEERS, ARCHITECTS, ATTORNEYS, AND OTHER PROFESSIONALS AND ALL COURT OR ARBITRATION OR OTHER DISPUTE RESOLUTION COSTS) ARISING OUT OF OR RELATING TO ANY INFRINGEMENT OF PATENT RIGHTS OR COPYRIGHTS INCIDENT TO THE USE IN THE PERFORMANCE OF THE WORK OR RESULTING FROM THE INCORPORATION IN THE WORK OF ANY INVENTION, DESIGN, PROCESS, PRODUCT, OR DEVICE. 7.11 Permits and Utilities A. Contractor obtained permits and licenses. Unless otherwise expressly provided in the Contract Documents, Contractor shall obtain and pay for all construction permits and licenses. City shall provide reasonable assistance to Contractor, if necessary, in obtaining such permits and licenses. Contractor shall pay all governmental charges and inspection fees necessary for the prosecution of the Work applicable at the time the Notice of Award is issued, except for 00 72 00 GENERAL CONDITIONS Page 29 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 permits provided by the City as specified in Paragraph 7.11.B. City shall pay the charges of utility service providers for connections for providing permanent service to the Work. B. City obtained permits and licenses. City will obtain and pay for those permits and licenses identified as City’s responsibility in the Supplementary Conditions or Contract Documents. It will be the Contractor’s responsibility to comply with and carry out the provisions of the permit. If the Contractor initiates changes to the Contract and the City approves the changes, the Contractor is responsible for obtaining clearances and coordinating with the appropriate regulatory agency. relating to the changes. The City will not reimburse the Contractor for any cost associated with the requirements of any City acquired permit. The following are permits the City will obtain if required: 1. Texas Department of Transportation Permits 2. U.S. Army Corps of Engineers Permits 3. Texas Commission on Environmental Quality Permits 4. Railroad Company Permits 5. Texas Department of Licensing and Regulation (TDLR) Permits C. Outstanding permits and licenses. Any outstanding permits and licenses are anticipated to be acquired in accordance with the schedule set forth in the Supplementary Conditions. The Project Schedule submitted by the Contractor in accordance with the Contract Documents must consider any outstanding permits and licenses. 7.12 Taxes A. On issuance of a Notice of Award by the City, an organization which qualifying for exemption pursuant to Texas Tax Code, Subchapter H (as amended), the Contractor may purchase, rent or lease all materials, supplies and equipment used or consumed in the performance of this contract by issuing to hisits Supplier an exemption certificate in lieu of the tax, said exemption certificate to comply with State Comptroller’s Rulings applicable to Texas Tax Code, Subchapter H. Any such exemption certificate issued to the Contractor in lieu of the tax shall be subject to and shall comply with all applicable rulings pertaining to the Texas Tax Code, Subchapter H. B. Texas tax permits and information may be obtained from: 1. Comptroller of Public Accounts Sales Tax Division Capitol Station Austin, TX 78711; or 2. http://www.window.state.tx.us/taxinfo/taxforms/93-forms.html 7.13 Laws and Regulations A. Contractor shall give all notices required by and shall comply with all Laws and Regulations applicable to the performance of the Work. Except where otherwise expressly required by applicable Laws and Regulations, City shall not be responsible for monitoring Contractor’s compliance with any Laws and Regulations. B. If Contractor performs any Work or takes any other action knowing or having reason to know that it is contrary to Laws and Regulations, Contractor shall be liable for all resulting claims, 00 72 00 GENERAL CONDITIONS Page 30 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 costs losses, and damages, and shall indemnify and hold harmless City, and its officers, elected and appointed officials, directors, members, partners, employees, agents, consultants, and subcontractors of each and any of them, from and against all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such Work or other action. C. Changes in Laws and Regulations not known at the time of the City’s issuance of a Notice of Award having an effect on the cost or time of performance of the Work may be the subject of an adjustment in Contract Price or Contract Time. 7.14 Record Documents A. Contractor shall maintain in a safe place at the Site one printed record copy of all Drawings, Specifications, Addenda, Change Orders, Field Orders, written interpretations and clarifications, and approved Shop Drawings. Contractor shall keep such record documents in good order and annotate them to show changes made during construction. Contractor shall include accurate locations for buried and imbedded items. These record documents, together with all approved Samples, will be available to City for reference. Upon completion of the Work, Contractor shall deliver these record documents to City prior to Final Inspection. 7.15 Safety and Protection A. As between City and Contractor, Contractor shall be responsible for the safety of persons and property in the performance of the Work, for initiating, maintaining, and supervising all safety precautions and programs in connection with the Work and for compliance with applicable safety Laws and Regulations. B. Contractor shall designate a qualified and experienced safety representative whose duties and responsibilities are the prevention of Work-related accidents and the maintenance and supervision of safety precautions and programs. Contractor shall inform the City in writing of Contractor’s designated safety representative at the Site. C. Contractor shall take all necessary precautions for the safety of, and shall provide the necessary protection to prevent damage, injury, or loss to: 1. all persons on the Site or who may be affected by the Work; 2. all the Work and materials and equipment to be incorporated therein, whether in storage on or off the Site; and 3. other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures, other work in progress, utilities, and Underground Facilities not designated for removal, relocation, or replacement in the course of construction. D. All damage, injury, or loss to any property referred to in Paragraph 7.1515.C.2 or 7.1515.C.3 caused, directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any other individual or entity directly or indirectly employed by any of them to perform any of the Work, or anyone for whose acts any of them may be liable, shall be the responsibility of and remedied by Contractor at its expense. E. Contractor shall comply with all applicable Laws and Regulations relating to the safety of persons or property, or to the protection of persons or property from damage, injury, or loss; 00 72 00 GENERAL CONDITIONS Page 31 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 and shall implement, erect and maintain all necessary safeguards for such safety and protection. F. Contractor shall notify City; the owners of adjacent property; the owners of Underground Facilities and other utilities (if the identity of such owners is known to Contractor); and other contractors and utility owners performing work at or adjacent to the Site, in writing, when Contractor knows that prosecution of the Work may affect them, and shall cooperate with them in the protection, removal, relocation, and replacement of their property or work in progress. G. Contractor shall comply with the applicable requirements of City’s safety programs, if any. H. Contractor shall inform City in advance in writing of the specific requirements of Contractor’s safety program with which City’s and Engineer’s employees and representatives must comply while at the Site. I. Contractor’s duties and responsibilities for safety and protection will continue until all the Work is completed and City has issued a Letter of Final Acceptance. J. Contractor’s duties and responsibilities for safety and protection will resume whenever Contractor or any Subcontractor or Supplier returns to the Site to fulfill warranty or correction obligations, or to conduct other tasks arising from the Contract Documents. 7.16 Hazard Communication Programs A. Contractor shall be responsible for coordinating any exchange of safety data sheets (formerly known as material safety data sheets) or other hazard communication information required to be made available to or exchanged between or among employers at the Site in accordance with Laws and Regulations. 7.17 Emergencies and/or Rectification A. In the event of threatened or actual emergencies affecting the safety or protection of persons or the Work or property at the Site or adjacent thereto, Contractor is obligated to immediately act to prevent damage, injury, or loss. Contractor shall give City prompt written notice if Contractor believes that any significant changes in the Work or variations from the Contract Documents have been caused by an emergency or are required as a result of Contractor’s response to an emergency. If City determines that a change in the Contract Documents is required because of an emergency or Contractor’s response, a Change Order may be issued. B. Should the Contractor fail to respond to a request from the City to rectify any discrepancies, omissions, or correction necessary to conform with the requirements of the Contract Documents, the City shall give the Contractor written notice that such work or changes are to be performed. The written notice shall direct attention to the discrepant condition and request the Contractor to take remedial action to correct the condition. In the event the Contractor does not take proper action within 24 hours to fulfill this written request or fails to show just cause for not taking the proper action, within 24 hours, the City may take such remedial action with City resources or by contract. The City shall deduct an amount equal to the entire cost for such remedial action, plus 25% from any funds due or to become due the Contractor on the Project. 00 72 00 GENERAL CONDITIONS Page 32 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 7.18 Submittals A. Submittal Procedures for Shop Drawings and Samples: Contractor shall submit required Submittals to City for review and acceptance in accordance with the accepted Schedule of Submittals (as required by Paragraph 2.03). 1. Contractor shall submit the Submittals in accordance with Section 01 33 00 of the General Requirements. 2. Data shown on the Submittals must be complete with respect to quantities, dimensions, specified performance and design criteria, materials, and similar data to demonstrate to City the services, materials, and equipment Contractor proposes to provide, and to enable City to review the information for the limited purposes required by Paragraph 7.18.C. 3. Submittals reviewed and accepted by City for conformance with the design concept shall be executed in conformity with the Contract Documents unless otherwise required by City. 4. When Submittals are submitted for the purpose of showing the installation in greater detail, their review shall not excuse Contractor from requirements shown on the Drawings and Specifications. 5. For-Information-Only submittals upon which the City is not expected to conduct a review or take responsive action may be so identified in the Contract Documents. 6. Contractor shall submit the required number of Samples specified in the Specifications. 7. Contractor shall clearly identify each Sample as to material, Supplier, pertinent data such as catalog numbers, the use for which it is intended and other data as City may require to enable City to review the Submittal for the limited purposes set forth in Paragraph 7.18.C. B. Where a Submittal is required by the Contract Documents or the Schedule of Submittals, any related Work performed prior to City’s review and acceptance of the pertinent submittal will be at the sole risk, expense and responsibility of Contractor. C. City’s Review 1. City will provide timely review of Submittals in accordance with the accepted Schedule of Submittals. City’s review and acceptance will be to determine if the items covered by the Submittals will, after installation or incorporation in the Work, comply with the requirements of the Contract Documents, and be compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. 2. City’s review and acceptance will not extend to means, methods, techniques, sequences, or procedures of construction (except where a particular means, method, technique, sequence or procedure of construction is specifically and expressly called for by the Contract Documents), or to safety precautions or programs incident thereto. 3. City’s review and acceptance of a separate item as such will not indicate approval of the assembly in which the item functions. 4. City’s review and acceptance of a Submittal will not relieve Contractor from responsibility for any variation from the requirements of the Contract Documents unless Contractor has complied with the requirements of Section 01 33 00 of the General Requirements, and City has given written acceptance of each such variation by specific written notation thereof incorporated in or accompanying the Submittal. 00 72 00 GENERAL CONDITIONS Page 33 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 5. City’s review and acceptance of a Submittal will not relieve Contractor from responsibility for complying with the requirements of the Contract Documents. 6. City’s review and acceptance of a Submittal, or of a variation from the requirements of the Contract Documents, will not, under any circumstances, change the Contract Time or Contract Price, unless such changes are included in a Change Order. 7. Neither City’s receipt, review, or acceptance of a Submittal will result in such item becoming a Contract Document. 8. Contractor shall perform the Work in compliance with the requirements and commitments set forth in accepted Submittals, subject to the provisions of Section 01 33 00 of the General Requirements. 7.19 Continuing the Work A. Except as otherwise provided, Contractor shall carry on the Work and adhere to the Project Schedule during all disputes or disagreements with City. No Work shall be delayed or postponed pending resolution of any disputes or disagreements, except as City and Contractor may otherwise agree in writing. 7.20 Contractor’s General Warranty and Guarantee A. Contractor warrants and guarantees to City that all Work will be in accordance with the Contract Documents and will not be defective. City and its officers, elected and appointed officials, directors, members, partners, employees, agents, consultants, and subcontractors shall be entitled to rely on Contractor’s warranty and guarantee. B. Contractor’s warranty and guarantee hereunder excludes defects or damage caused by: 1. abuse, or improper modification, maintenance, or operation, by persons other than Contractor, Subcontractors, Suppliers, or any other individual or entity for whom Contractor is responsible; or 2. normal wear and tear under normal usage. C. Contractor’s obligation to perform and complete the Work in accordance with the Contract Documents is absolute. None of the following will constitute an acceptance of Work that is not in accordance with the Contract Documents, a release of Contractor’s obligation to perform the Work in accordance with the Contract Documents, or a release of Contractor’s warranty and guarantee under this Paragraph 7.20: 1. Observations by Engineer or City; 2. Recommendation by Engineer or payment by City of any progress or final payment; 3. The issuance of a letter or certificate of Final Acceptance by City or any payment related thereto by City; 4. Use or occupancy of the Work or any part thereof by City; 5. Any review and acceptance of a Submittal by City; 6. Any inspection, test, or acceptance by others; or 7. Any correction of defective Work by City. 00 72 00 GENERAL CONDITIONS Page 34 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 D. The Contractor shall remedy any defects or damages in the Work and pay for any damage to other work or property resulting therefrom which shall appear within a period of two (2) years from the date of Final Acceptance of the Work unless a longer period is specified. Contractor shall furnish a good and sufficient maintenance bond, complying with the requirements of Paragraph 6.02.B. The City will give notice of observed defects with reasonable promptness. 7.21 Indemnification A. CONTRACTOR COVENANTS AND AGREES TO INDEMNIFY, HOLD HARMLESS, AND DEFEND, AT ITS OWN EXPENSE, THE CITY, ITS OFFICERS, ELECTED AND APPOINTED OFFICIALS, EMPLOYEES, AGENTS, CONSULTANTS AND SUBCONTRACTORS AND ANYONE DIRECTLY OR INDIRECTLY EMPLOYED BY THEM , FROM AND AGAINST ANY AND ALL CLAIMS FOR PERSONAL OR BODILY INJURY OR DEATH, ARISING OUT OF OR RELATED TO, OR ALLEGED TO ARISE OUT OF OR BE RELATED TO, THE WORK AND SERVICES TO BE PERFORMED BY THE CONTRACTOR, ITS OFFICERS, AGENTS, EMPLOYEES, SUBCONTRACTORS, LICENSEES OR INVITEES UNDER THESE CONTRACT DOCUMENTS. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. OR ITS OFFICERS, ELECTED OR APPOINTED OFFICIALS, EMPLOYEES, AGENTS, CONSULTANTS OR SUBCONTRACTORS OR ANYONE DIRECTLY OR INDIRECTLY EMPLOYED BY THEM. THIS INDEMNITY PROVISION IS INTENDED TO INCLUDE, WITHOUT LIMITATION, INDEMNITY FOR COSTS, EXPENSES AND LEGAL FEES INCURRED IN DEFENDING AGAINST SUCH CLAIMS AND CAUSES OF ACTIONS. B. CONTRACTOR COVENANTS AND AGREES TO INDEMNIFY AND HOLD HARMLESS, AT ITS OWN EXPENSE, THE CITY, ITS OFFICERS, ELECTED AND APPOINTED OFFICIALS, EMPLOYEES, AGENTS, CONSULTANTS AND SUBCONTRACTORS AND ANYONE DIRECTLY OR INDIRECTLY EMPLOYED BY THEM FROM AND AGAINST ANY AND ALL LOSS, DAMAGE OR DESTRUCTION OF PROPERTY OF THE CITY, ARISING OUT OF OR RELATED TO, OR ALLEGED TO ARISE OUT OF OR BE RELATED TO, THE WORK AND SERVICES TO BE PERFORMED BY THE CONTRACTOR, ITS OFFICERS, AGENTS, EMPLOYEES, SUBCONTRACTORS, LICENSEES OR INVITEES UNDER THIS CONTRACT. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY OR ITS OFFICERS, ELECTED OR APPOINTED OFFICIALS, EMPLOYEES, AGENTS, CONSULTANTS OR SUBCONTRACTORS OR ANYONE DIRECTLY OR INDIRECTLY EMPLOYED BY THEM. 7.22 Delegation of Professional Design Services A. Contractor will not be required to provide professional design services unless such services are specifically required by the Contract Documents for a portion of the Work or unless such 00 72 00 GENERAL CONDITIONS Page 35 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 services are required to carry out Contractor’s responsibilities for construction means, methods, techniques, sequences and procedures. B. If professional design services or certifications by a design professional related to systems, materials or equipment are specifically required of Contractor by the Contract Documents, City will specify all performance and design criteria that such services must satisfy. Contractor shall cause such services or certifications to be provided pursuant to the professional standard of care by a properly licensed design professional, whose signature and seal must appear on all drawings, calculations, specifications, certifications, and Submittals prepared by such design professional. Such design professional must issue all certifications of design required by Laws and Regulations. C. If a Submittal related to the requirements indicated in Paragraph 7.22.B is prepared by Contractor, a Subcontractor, or others for submittal to City, then such Submittal must bear the written approval of Contractor’s design professional when submitted by Contractor to City. D. City shall be entitled to rely upon the adequacy, accuracy, and completeness of the services, certifications, and approvals performed or provided by the design professionals retained or employed by Contractor under the conditions indicated in Paragraph 7.22.B, subject to the professional standard of care and the performance and design criteria stated in the Contract Documents. E. Pursuant to this Paragraph 7.22, City’s review, acceptance, and other determinations regarding design drawings, calculations, specifications, certifications, and other Submittals furnished by Contractor pursuant to the conditions indicated in Paragraph 7.22.B, will be only for the following limited purposes: 1. Checking for conformance with the requirements of this Paragraph 7.22; 2. Confirming that Contractor (through its design professionals) has used the performance and design criteria specified in the Contract Documents; and 3. Establishing that the design furnished by Contractor is consistent with the design concept expressed in the Contract Documents. 7.23 Right to Audit A. The City shall have the right to audit and make copies of the books, records and computations pertaining to the Contract. The Contractor shall retain such books, records, documents and other evidence pertaining to the Contract during the term of the Contract and for five years thereafter, except if an audit is in progress or audit findings are yet unresolved, in which case records shall be kept until all audit tasks are completed and resolved. These books, records, documents and other evidence shall be made available, in Denton County, Texas within ten (10) Business Days of City’s written request. Further, the Contractor shall also require all Subcontractors, material suppliers, and other payees to retain all books, records, documents and other evidence pertaining to the Contract, and to allow the City similar access to those documents. All books and records will be made available within Denton County, Texas. Except as otherwise provided herein, the cost of the audit will be borne by the City unless the audit reveals an overpayment of 1% or greater. If the City is undertaking an audit or inspection pursuant to Paragraph 7.09 or if an overpayment of 1% or greater occurs, the City’s reasonable cost of the audit, including any travel costs, must be paid by the Contractor within five (5) Business Days of receipt of City’s invoice for such costs. 00 72 00 GENERAL CONDITIONS Page 36 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 B. Failure to comply with the provisions of this section shall be a material breach of the Contract and shall constitute, in the City’s sole discretion, grounds for termination thereof. Each of the terms “books”, “records”, “documents” and “other evidence”, as used above, shall be construed to include drafts and electronic files, even if such drafts or electronic files are subsequently used to generate or prepare a final printed document. 7.24 Nondiscrimination A. The City is responsible for operating Public Transportation Programs and implementing transit-related projects, funded in part with Federal financial assistance awarded by the U.S. Department of Transportation and the Federal Transit Administration (FTA), without discriminating against any person in the United States on the basis of race, color, or national origin. B. Contractor shall comply with the requirements of Title VI, Civil Rights Act of 1964 as amended and the regulations promulgated thereunder, as may be further defined in the Supplementary Conditions, for any project receiving Federal assistance. ARTICLE 8 – OTHER WORK AT THE SITE 8.01 Other Work A. In addition to and apart from the Work under the Contract Documents, the City may perform other work at or adjacent to the Site. Such other work may be performed by City’s employees, or through contracts between the City and third parties. City may also arrange to have third- party utility owners perform work on their utilities and facilities at or adjacent to the Site. B. If City performs other work at or adjacent to the Site with City’s employees, or through contracts for such other work, then City shall give Contractor written notice thereof prior to starting any such other work, if such other work is not noted in the Contract Documents. C. Contractor shall afford proper and safe access to the Site to each contractor that performs such other work, each utility owner performing other work, and City, if City is performing other work with City’s employees, and provide a reasonable opportunity for the introduction and storage of materials and equipment and the execution of such other work. D. Contractor shall do all cutting, fitting, and patching of the Work that may be required to properly connect or otherwise make its several parts come together and properly integrate with such other work. Contractor shall not endanger any work of others by cutting, excavating, or otherwise altering such work; provided, however, that Contractor may cut or alter others' work with the written consent of City and the others whose work will be affected. E. If the proper execution or results of any part of Contractor’s Work depends upon work performed by others, Contractor shall inspect such other work and promptly report to City in writing any delays, defects, or deficiencies in such other work that render it unavailable or unsuitable for the proper execution and results of Contractor’s Work. Contractor’s failure to so report will constitute an acceptance of such other work as fit and proper for integration with Contractor’s Work except for latent defects and deficiencies in such other work that could not have been discovered through a proper inspection. F. The provisions of this Article 8 are not applicable to work that is performed by third-party utilities or other third-party entities without a contract with City, or that is performed without 00 72 00 GENERAL CONDITIONS Page 37 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 having been arranged by City. If such work occurs, then any related delay, disruption, or interference incurred by Contractor is governed by the provisions of Paragraph 4.03.D.3. 8.02 Coordination A. If City intends to contract with others for the performance of other work at or adjacent to the Site, to perform other work at or adjacent to the Site with City’s employees, or to arrange to have utility owners perform work at or adjacent to the Site, the following will be set forth in the Supplementary Conditions or provided to Contractor prior to the start of any such other work: 1. The identity of the individual or entity that will have authority and responsibility for coordination of the activities among the various contractors; 2. An itemization of the specific matters to be covered by such authority and responsibility; and 3. The extent of such authority and responsibilities. B. Unless otherwise provided in the Supplementary Conditions, City shall have authority for such coordination. 8.03 Legal Relationships A. Contractor shall take reasonable and customary measures to avoid damaging, delaying, disrupting, or interfering with the work of City, any other contractor, or any utility owner performing other work at or adjacent to the Site. 1. When City is performing other work at or adjacent to the Site with City’s employees, Contractor shall be liable to City for damage to such other work, and for the reasonable direct delay, disruption, and interference costs incurred by City as a result of Contractor’s failure to take reasonable and customary measures with respect to City’s other work. B. If Contractor damages, delays, disrupts, or interferes with the work of any other contractor, or any utility owner performing other work at or adjacent to the Site, through Contractor’s failure to take reasonable and customary measures to avoid such impacts, or if any Damage Claim arising out of Contractor’s actions, inactions, or negligence in performance of the Work at or adjacent to the Site is made by any such other contractor or utility owner against Contractor, City, or Engineer, then Contractor shall (1) promptly attempt to settle the claim as to all parties through negotiations with such other contractor or utility owner, or otherwise resolve the claim by arbitration or other dispute resolution proceeding or at law, and (2) indemnify, defend and hold harmless City and Engineer, and the officers, elected and appointed officials, directors, members, partners, employees, agents, consultants and subcontractors of each and any of them from and against any such claims, and against all costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such damage, delay, disruption, or interference. ARTICLE 9 – CITY’S RESPONSIBILITIES 9.01 Communications to Contractor A. Except as otherwise provided in the Supplementary Conditions, City shall issue all communications to Contractor. 00 72 00 GENERAL CONDITIONS Page 38 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 9.02 Furnish Data A. City shall promptly furnish the data required of City under the Contract Documents. 9.03 Pay When Due A. City shall make payments to Contractor when they are due in accordance with and subject to the provisions of Article 14. 9.04 Lands and Easements; Reports, Tests, and Drawings A. City’s duties with respect to providing lands and easements are set forth in Paragraph 5.01. B. Article 5 refers to City’s identifying and making available to Contractor copies of reports of explorations and tests of subsurface conditions at the Site, and drawings of physical conditions relating to existing surface or subsurface structures at or contiguous to the Site that have been utilized by City in preparing the Contract Documents. 9.05 Change Orders A. City’s responsibilities with respect to Change Orders are set forth in Article 11. 9.06 Inspections, Tests, and Approvals A. City’s responsibility with respect to certain inspections, tests, and approvals is set forth in Paragraph 13.02.DD. 9.07 Limitations on City’s Responsibilities A. The City shall not supervise, direct, or have control or authority over, nor be responsible for, Contractor’s means, methods, techniques, sequences, or procedures of construction, or the safety precautions and programs incident thereto, or for any failure of Contractor to comply with Laws and Regulations applicable to the performance of the Work. City will not be responsible for Contractor’s failure to perform the Work in accordance with the Contract Documents. 9.08 Undisclosed Hazardous Environmental Condition A. City’s responsibility in respect to an undisclosed Hazardous Environmental Condition is set forth in Paragraph 5.06. 9.09 Compliance with Safety Program A. While at the Site, City’s employees and representatives shall comply with the specific applicable requirements of Contractor’s safety programs of which City has been informed in advance in writing pursuant to Paragraph 7.15. ARTICLE 10 – CITY’S OBSERVATION DURING CONSTRUCTION 10.01 City’s Project Manager or Duly Authorized Representative A. City will provide a Project Manager or duly authorized representative during the construction period. The duties and responsibilities and the limitations of authority of City’s Project Manager or duly appointed representative during construction are set forth in the Contract Documents. 00 72 00 GENERAL CONDITIONS Page 39 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 B. City’s Project Manager for these Contract Documents is as set forth in the Supplementary Conditions. City will establish a duly authorized representative at the Preconstruction Meeting in accordance with Section 01 31 19 of the General Requirements. 10.02 Visits to Site A. City will make visits to the Site at intervals appropriate to the various stages of construction as City deems necessary in order to observe the progress that has been made and the quality of the various aspects of Contractor’s executed Work. Based on information obtained during such visits and observations, City will determine, in general, if the Work is proceeding in accordance with the Contract Documents. City will not be required to make exhaustive or continuous inspections on the Site to check the quality or quantity of the Work. City’s efforts will be directed toward providing City a greater degree of confidence that the completed Work will conform generally to the Contract Documents. B. City’s visits and observations are subject to all the limitations on City’s responsibility set forth in Paragraph 99.07. Particularly, but without limitation, during or as a result of City’s visits or observations of Contractor’s Work, City will not supervise, direct, control, or have authority over or be responsible for Contractor’s means, methods, techniques, sequences, or procedures of construction, or the safety precautions and programs incident thereto, or for any failure of Contractor to comply with Laws and Regulations applicable to the performance of the Work. 10.03 Determinations for Work Performed A. As applicable, Contractor will determine the actual quantities and classifications of Work performed.. City’s Project Manager or duly authorized representative will review with Contractor the preliminary determinations on such matters before rendering a written recommendation. City’s written decision will be final (except as modified to reflect changed factual conditions or more accurate data). 10.04 Decisions on Requirements of Contract Documents and Acceptability of Work A. City will be the interpreter of the requirements of the Contract Documents and judge the acceptability of the Work thereunder. B. City will render a written decision on any issue referred. C. City’s written decision on the issue referred will be final and binding on the Contractor, subject to the provisions of Paragraph 11.07. ARTICLE 11 – CHANGES ININ THE WORK; CLAIMS; EXTRA WORK 11.01 Amending and Supplementing the Contract A. The Contract may be amended toto provide for additions, deletions, and revisions in the Work or to modify the terms and conditions thereof, including in the Contract Price or Contract Time, but such amendment will be made by Change Order only. B. The requirements of the Contract Documents may be supplemented, and minor variations and deviations in the Work not involving a change in Contract Price or Contract Time, may be authorized, by one of the following ways: 1. A Field Order; or 2. City’s review of a Submittal (subject to the provisions of Paragraph 7.18.C); or 00 72 00 GENERAL CONDITIONS Page 40 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 3. City’s written interpretation or clarification. 11.02 Execution of Change Orders A. City and Contractor shall execute appropriate Change Orders covering: 1. Changes in the Contract Price or Contract Time which are agreed to by the parties, including any undisputed sum or amount of time for Work actually performed.. 2. Changes in the Work which are: (a) ordered by City pursuant to Paragraph 11.04, (b) required because of City’s acceptance of defective Work under Paragraph 13.05 or City’s correction of defective Work under Paragraph 13.08, or (c) as otherwise agreed to by the parties. 11.03 Field Orders A. City may authorize minor variations and deviations in changes in the Work if the changes do not involve an adjustment in the Contract Price or the Contract Time and are compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. Such changes will be accomplished by a Field Order and will be binding on both the City and Contractor, which shall perform the Work involved promptly. 11.04 Authorized Changes in the Work – Extra Work A. Without invalidating the Contract and without notice to any surety, City may, at any time or from time to time, order Extra Work. Upon notice of such Extra Work, Contractor shall proceed with the Work involved only upon receiving written notice from City. Extra Work will be performed under the applicable conditions of the Contract Documents (except as otherwise specifically provided). Extra Work shall be memorialized by a Change Order which may or may not precede an order of Extra Work. B. For minor changes of Work not requiring changes to Contract Time or Contract Price, a Field Order may be issued by City. 11.05 Unauthorized Changes in the Work A. Contractor shall not be entitled to an increase in the Contract Price or an extension of the Contract Time with respect to any work performed that is not required by the Contract Documents, as amended, modified, or supplemented as allowed herein, except in certain cases of an emergency as provided in Paragraph 7.17.A. 11.06 Dispute of Extra Work A. Should a difference arise as to what does or does not constitute Extra Work, or as to the payment for such Extra Work, and the City requires its performance, the Contractor shall proceed with the Extra Work after making written request for a Change Order and shall keep accurate account of the actual reasonable cost thereof. Contract Claims regarding Extra Work shall be made pursuant to Paragraph 11.07. B. The Contractor shall furnish the City such records of all deviations from the original Contract Documents as may be necessary to enable the City to prepare for permanent record a corrected set of plans showing the actual work performed. C. The compensation agreed upon for Extra Work whether or not initiated by a Change Order shall be the full, complete and final payment for all charges, fees and costs Contractor incurs as a result of or relating to the Extra Work, whether said charges, fees or costs are known, 00 72 00 GENERAL CONDITIONS Page 41 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 unknown, foreseen or unforeseen at that time, including without limitation, any charges, fees or costs for delay, extended overhead, ripple or impact cost, or any other effect on changed or unchanged work as a result of the Extra Work. 11.07 Contract Claims Process A. City’s Decision Required: All Contract Claims, except those waived pursuant to Paragraph 14.08, shall be referred to the City for decision. A decision by City shall be required as a condition precedent to any exercise by Contractor of any rights or remedies he may otherwise have under the Contract Documents or by Laws and Regulations in respect of such Contract Claims. B. Notice: 1. Written notice stating the general nature of each Contract Claim shall be delivered by the Contractor to City no later than 15 days after the start of the event giving rise thereto. The responsibility to substantiate a Contract Claim shall rest with the party making the Contract Claim. 2. Notice of the amount or extent of the Contract Claim, with supporting data shall be delivered to the City no later than 45 days after the start of the event giving rise thereto (unless the City notifies Contractor in writing that City will allow additional time for Contractor to submit additional or more accurate data in support of such Contract Claim). 3. A Contract Claim for an adjustment in Contract Price shall be prepared in accordance with the provisions of Paragraph 11.08. 4. A Contract Claim for an adjustment in Contract Time shall be prepared in accordance with the provisions of Paragraph 11.09. 5. Each Contract Claim shall be accompanied by Contractor’s written statement that the adjustment claimed is the entire adjustment to which the Contractor believes it is entitled as a result of said event. 6. The City shall submit any response to the Contractor within 30 days after receipt of the Contractor’s last submittal (unless in connection with the Contract Claim (unless Contractor allows the City additional time to submit a response). C. City’s Action: City will review each Contract Claim and, within 30 days after receipt of the last submittal of the Contractor unless action by City’s Council is required, take one of the following actions in writing: 1. deny the Contract Claim in whole or in part; 2. approve the Contract Claim; or 3. notify the Contractor that the City is unable to resolve the Contract Claim if, in the City’s sole discretion, it would be inappropriate for the City to do so. For purposes of further resolution of the Contract Claim, such notice shall be deemed a denial. D. City’s written action under this Paragraph 11.07 will be final and binding, unless City or Contractor invoke the dispute resolution procedure set forth in Article 16 within 30 days of such action or denial. E. No Contract Claim for an adjustment in Contract Price or Contract Time will be valid if not submitted in accordance with this Paragraph 11.07. 00 72 00 GENERAL CONDITIONS Page 42 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 F. If the City fails to take any action pursuant to this Paragraph 11.07, the Contract Claim is considered to have been denied by the City. 11.08 Change of Contract Price A. The Contract Price may only be changed by a Change Order. B. TheThe value of any Work covered by a Change Order will be determined as follows: 1. Where the Work involved is covered by unit prices contained in the Contract Documents, then by application of such unit prices to the quantities of the items involved (subject to the provisions of Paragraph 12.03); 2. Where the Work involved is not covered by unit prices contained in the Contract Documents, then by a mutually agreed lump sum or unit price (which may include an allowance for overhead and profit not necessarily in accordance with Paragraph 11.08.C.2), and shall include the cost of any secondary impacts that are foreseeable at the time of pricing the cost of Extra Work; or 3. Where the Work involved is not covered by unit prices contained in the Contract Documents and the parties do not reach mutual agreement to a lump sum or unit price, then on the basis of the Cost of the Work (determined as provided in Paragraph 12.01) plus a Contractor’s fee for overhead and profit (determined as provided in Paragraph 11.08.C). C. Contractor’s Fee: The Contractor’s fee for overhead and profit will be determined as follows: 1. A mutually acceptable fixed fee; or 2. If a fixed fee is not agreed upon, then a fee based on the following percentages of the various portions of the Cost of the Work: a. For costs incurred under Paragraphs 12.01.B.1, 12.01.B.2, and 12.01.B.3, the Contractor’s fee will be 15 percent except for: 1) rental fees for Contractor’s own equipment; and 2) bonds and insurance; b. For costs incurred under Paragraph 12.01.B.4, the Contractor’s fee will be 5 percent; 1) Where one or more tiers of subcontracts are on the basis of Cost of the Work plus a fee and no fixed fee is agreed upon, the intent of Paragraphs 11.08.C.2.a and 11.08.C.2.b is that the Contractor’s fee will be based on: (1) a fee of 15 percent of the costs incurred under Paragraphs 12.01.B.1, 12.01.B.2, and 12.01.B.3 by the Subcontractor that actually performs the Work, at whatever tier, and (2) with respect to Contractor itself and to any Subcontractors of a tier higher than that of the Subcontractor that actually performs the Work, a fee of 5 percent of the amount (fee plus underlying costs incurred) attributable to the next lower tier Subcontractor; provided, however, in no case shall the cumulative total of fees paid be in excess of 25% of the Cost of the Work; c. No fee will be payable on the basis of costs itemized under Paragraphs 12.01.B.5, 12.01.B.6, and 12.01.C; d. The amount of credit to be allowed by Contractor to City for any change which results in a net decrease in Cost of the Work will be the amount of the actual net 00 72 00 GENERAL CONDITIONS Page 43 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 decrease in Cost of the Work and a deduction of an additional amount equal to 5 percent of such actual net decrease in Cost of the Work; and 11.09 Change of Contract Time A. The Contract Time may only be changed by a Change Order. B. No extension of the Contract Time will be allowed under a Change Order for Extra Work or for claimed delay unless the Extra Work contemplated or claimed delay is shown to be on the critical path of the Project Schedule or Contractor can show by critical path method analysis how the Extra Work or claimed delay adversely affects the critical path. C. Delay, disruption, and interference in the Work, and any related changes in Contract Time, are addressed in and governed by Paragraph 4.03. 11.10 Notification to Surety A. If the provisions of any bond require notice to be given to a surety of any change affecting the general scope of the Work or the provisions of the Contract Documents (including, but not limited to, Contract Price or Contract Time), the giving of any such notice will be Contractor’s responsibility. The amount of each applicable bond will be adjusted by the Contractor to reflect the effect of any such change. ARTICLE 12 – COST OF THE WORK; ALLOWANCES; UNIT PRICE WORK; PLANS QUANTITY MEASUREMENT 12.01 Cost of the Work A. Purposes for Determination of Cost of the Work: The term “Cost of the Work” means the sum of all costs necessary for the proper performance of the Work at issue, as further defined below. The provisions of this Paragraph 12.01 are used for two distinct purposes: 1. To determine Cost of the Work when Cost of the Work is a component of the Contract Price, under cost-plus-fee, time-and-materials, or other cost-based terms; or 2. When needed to determine the value of a Change Order. When the value of any such adjustment is determined on the basis of Cost of the Work, Contractor is entitled only to those additional or incremental costs required because of the change in the Work or because of the event giving rise to the adjustment. B. Costs Included: The term, “Cost of the Work” means the sum of all costs, except those excluded in Paragraph 12.01.C, necessarily incurred and paid by Contractor in the proper performance of the Work. When the value of any Work is covered by a Change Order, the costs reimbursed to Contractor will be only those additional or incremental costs required because of the change in the Work. Such costs shall be in amounts no higher than those calculated based on the prevailing wage rates contained in the Contract Documents, shall not include any of the costs itemized in Paragraph 12.01.C, and may include as applicable, but not be limited to the following items: 1. Payroll costs for employees in the direct employ of Contractor in the performance of the Work under schedules of job classifications agreed upon by City and Contractor. Such employees shall include, without limitation, superintendents, foremen, safety managers, safety representatives, and other personnel employed full time on the Work. Payroll costs for employees not employed full time on the Work will be apportioned on the basis of 00 72 00 GENERAL CONDITIONS Page 44 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 their time spent on the Work. Payroll costs shall include, salaries and wages plus the cost of fringe benefits, which include social security contributions, unemployment, excise, and payroll taxes, workers’ compensation, health and retirement benefits, sick leave, and vacation and holiday pay applicable thereto. The expenses of performing Work outside of regular working hours on Business Days, during Weekend Working Hours, or on a state or federal holiday observed by the City, shall be included in the above to the extent authorized by City. 2. Cost of all materials and equipment furnished and incorporated in the Work, including costs of transportation and storage thereof, and Suppliers’ field services required in connection therewith. 3. Rentals of all construction equipment and machinery and the parts thereof, whether rented from Contractor or others, in accordance with rental agreements approved in writing by City, and the costs of transportation, loading, unloading, assembly, dismantling, and removal thereof. All such costs shall be in accordance with the terms of said rental agreements. and the Contract Documents. The rental of any such equipment, machinery, or parts shall cease when the use thereof is no longer necessary for the Work. 4. Payments made by Contractor to Subcontractors for Work performed by Subcontractors. If required by City, Contractor shall obtain competitive bids from subcontractors acceptable to City . Contractor shall deliver such bids to City, which will then determine, which bids, if any, will be acceptable. If any subcontract provides that the Subcontractor is to be paid on the basis of Cost of the Work plus a fee, the Subcontractor’s Cost of the Work and fee will be determined in the same manner as Contractor’s Cost of the Work and fee as provided in this Paragraph 12.01 and Paragraph 11.08.C. 5. Costs of special consultants (including but not limited to engineers, architects, testing laboratories, surveyors, attorneys, and accountants) employed or retained for services specifically related to the Work and specifically included in the agreed upon schedule of job classifications referred to in Paragraph 12.01.B.1 or otherwise specifically included in the Contract. 6. Supplemental costs consisting of the following: a. The proportion of necessary transportation, travel, and subsistence expenses of Contractor’s employees incurred in discharge of duties connected with the Work. b. Cost, including transportation and maintenance, of all materials, supplies, equipment, machinery, appliances, and temporary office or facilities at the Site, which are consumed in the performance of the Work, and cost, less market value, of such items used but not consumed which remain the property of Contractor. c. Sales, consumer, use, and other similar taxes related to the Work, and for which Contractor is liable, as imposed by Laws and Regulations, excluding those taxes for which an exemption is available as described in Paragraph 7.12. d. Deposits lost for causes other than the negligence or willful misconduct of Contractor, any Subcontractor, or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable, and royalty payments and fees for permits and licenses. e. Losses and damages (and related expenses) caused by damage to the Work, not compensated by insurance or otherwise, sustained by Contractor in connection with 00 72 00 GENERAL CONDITIONS Page 45 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 the performance of the Work, provided such losses and damages have resulted from causes other than the negligence or willful misconduct of Contractor, any Subcontractor, or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable. Such losses include settlements made with the written consent and approval of City. No such losses, damages, and expenses will be included in the Cost of the Work for the purpose of determining Contractor’s fee. f. The cost of utilities, fuel, and sanitary facilities at the Site. g. Minor expenses such as communication service at the Site, express and courier services, and similar petty cash items in connection with the Work. h. The costs of premiums for all bonds and insurance that Contractor is required by the Contract Documents to purchase and maintain. C. Costs Excluded: The term Cost of the Work does not include any of the following items: 1. Payroll costs and other compensation of Contractor’s officers, executives, principals, general managers, engineers, architects, estimators, attorneys, auditors, accountants, purchasing and contracting agents, expediters, timekeepers, clerks, and other personnel employed by Contractor, whether at the Site or in Contractor’s principal or branch office for general administration of the Work and not specifically included in the agreed upon schedule of job classifications referred to in Paragraph 12.01.B.1 or otherwise specifically covered in the Contract. The payroll costs and other compensation excluded here are to be considered administrative costs covered by the Contractor’s fee. 2. Expenses of Contractor’s principal and branch offices other than Contractor’s office at the Site. 3. Any part of Contractor’s capital expenses, including interest on Contractor’s capital employed for the Work and charges against Contractor for delinquent payments. 4. Costs due to the acts, omissions, negligence or willful misconduct of Contractor, any Subcontractor, or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable, including but not limited to, the correction of defective Work, disposal of materials or equipment wrongly supplied, and making good any damage to property. 5. Other overhead or general expense costs of any kind. D. Contractor’s Fee 1. When the Work as a whole is performed on the basis of cost-plus-a-fee, then: a. Contractor’s fee for the Work set forth in the Contract Documents as of the Effective Date of the Agreement will be determined as set forth in the Contract. b. for any Work covered by a Change Order for an adjustment in Contract Price on the basis of Cost of the Work, Contractor’s fee will be determined as set forth in Paragraph 11.08.C. 2. When the Work as a whole is performed on the basis of a stipulated sum, or any other basis other than cost-plus-a-fee, then Contractor’s fee for any Work covered by a Change Order for an adjustment in Contract Price on the basis of Cost of the Work will be determined in accordance with Paragraph 11.08.C.2. 00 72 00 GENERAL CONDITIONS Page 46 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 E. Documentation and Audit: Whenever the Cost of the Work for any purpose is to be determined pursuant to this Article 12, Contractor and pertinent Subcontractors will establish and maintain records of the costs in accordance with generally accepted accounting practices, and submit in a form acceptable to City an itemized cost breakdown together with supporting data. Subject to prior written notice, City will be afforded reasonable access, during normal business hours, to all Contractor’s accounts, records, books, correspondence, instructions, drawings, receipts, vouchers, memoranda, and similar data relating to the Cost of the Work and Contractor’s fee. Contractor shall preserve all such documents for a period of three years after the final payment by City. Contractor will be responsible for ensuring that pertinent Subcontractors will afford such access to City, and preserve such documents, to the same extent as is required of Contractor. 12.02 Allowances A. Specified Allowance: It is understood that Contractor has included in the Contract Price all allowances so named in the Contract Documents and shall cause the Work so covered to be performed for such sums and by such persons or entities as may be acceptable to City. B. Cash Allowances: Contractor agrees that: 1. the cash allowances include the cost to Contractor (less any applicable trade discounts) of materials and equipment required by the allowances to be delivered at the Site, and all applicable taxes; and 2. Contractor’s costs for unloading and handling on the Site, labor, installation, overhead, profit, and other expenses contemplated for the cash allowances, have been included in the Contract Price and not in the allowances, and no demand for additional payment for any of the foregoing will be valid. C. Contingency Allowance: Contractor agrees that a contingency allowance, if any, is for the sole use of City. D. Prior to final payment, an appropriate Change Order will be issued to reflect actual amounts due Contractor for Work covered by allowances, and the Contract Price will be correspondingly adjusted. 12.03 Unit Price Work A. Where the Contract Documents provide that all or part of the Work is to be Unit Price Work, initially the Contract Price will be deemed to include for all Unit Price Work an amount equal to the sum of the unit price for each separately identified item of Unit Price Work multiplied by the estimated quantity of each item as indicated in the Agreement. B. The estimated quantities of items of Unit Price Work are not guaranteed and are solely for the purpose of comparison of Bids and determining an initial Contract Price. Determinations of the actual quantities and classifications of Unit Price Work performed by Contractor will be made by City subject to the provisions of Paragraph 10.03. C. Each unit price will be deemed to include an amount considered by Contractor to be adequate to cover Contractor’s overhead and profit for each separately identified item. Work described in the Contract Documents, or reasonably inferred as required for a functionally complete installation, but not identified in the listing of unit price items shall be considered incidental to Unit Price Work listed and the cost of incidental work included as part of the unit price. D. Adjustments in Contract Price 00 72 00 GENERAL CONDITIONS Page 47 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 1. City may make an adjustment in the Contract Price in accordance with Paragraph 11.08 if: a. the quantity of the item of Work performed by Contractor differs materially and significantly from the estimated quantity of such item indicated in the Agreement; and b. there is no corresponding adjustment with respect to any other item of Work. 2. Adjusted unit prices will apply to all units of that item. E. Increased or Decreased Quantities: The City reserves the right to order Extra Work in accordance with Paragraph 11.04. 1. If the changes in quantities or the alterations do not significantly change the character of the Work under the Contract Documents, the altered Work will be paid for at the Contract unit price. 2. If the changes in quantities or alterations materially and significantly change the character of the Work, the Contract will be amended by a Change Order. 3. If no unit prices exist, thisany increase or decrease in quantities will be considered Extra Work and the Contract will be amended by a Change Order in accordance with Article 11. 4. A significant change in the character of Work occurs when: a. the character of work for any Item as altered differs materially or significantly in kind or nature from that in the Contract; or b. a Major Item of work varies by more than 25% from the original Contract quantity. 5. When the quantity of work to be done under any Major Item of the Contract is more than 125% of the original quantity stated in the Contract, then either party to the Contract may request an adjustment to the unit price on the portion of the work that is above 125%. 6. When the quantity of work to be done under any Major Item of the Contract is less than 75% of the original quantity stated in the Contract, then either party to the Contract may request an adjustment to the unit price. 12.04 Plans Quantity Measurement for Unclassified Excavation or Embankment A. Plans quantities may or may not represent the exact quantity of Work performed or material moved, handled, or placed during the term of the Contract. The estimated bid quantities are designated as final payment quantities, unless revised in accordance with the Contract. B. If the total actual quantity measured for an individual item varies by more than 25% (or as stipulated under “Price and Payment Procedures” for specific Items) from the total estimated quantity for an individual Item originally shown in the Contract Documents, an adjustment may be made to the quantity of authorized Work done for payment purposes. The party to the Contract requesting the adjustment will provide field measurements and calculations showing the final quantity for which payment will be made. Payment for revised quantity will be made at the unit price bid for that Item, except as provided for in Article 11. C. When quantities are revised by a change in design approved by the City, by Change Order, or to correct an error, or to correct an error on the plans, the plans quantity will be increased or 00 72 00 GENERAL CONDITIONS Page 48 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 decreased by the amount identified in the approved change, and the 25% variance provisions of Paragraph 12.04.B will apply to the new plans quantity. D. If the total Contract quantity multiplied by the unit price bid for an individual Item is less than $250 and the Item is not originally a plans quantity Item, then the Item may be paid as a plans quantity Item if the City and Contractor agree in writing to fix the final quantity as a plans quantity. E. For callout work or non-site specific Contracts, the plans quantity measurement requirements are not applicable. ARTICLE 13 – TESTS AND INSPECTIONS; CORRECTION, REMOVAL, OR ACCEPTANCE OF DEFECTIVE WORK 13.01 Access to Work A. City and its Engineer, consultants, representatives, employees, and independent testing laboratories, and authorities having jurisdiction shall have access to the Site and the Work at reasonable times for their observation, inspection, and testing. Contractor shall provide them proper and safe conditions for such access and advise them of Contractor’s safety procedures and programs so that they may comply with such procedures and programs as applicable. 13.02 Tests and Inspections A. Contractor shall give City timely notice of readiness of the Work (or specific parts thereof) for all required inspections and tests and shall cooperate with inspection and testing personnel to facilitate required inspections and tests. B. If the Contract Documents or any Laws and Regulations of any public body having jurisdiction require any Work (or part thereof) specifically to be inspected, tested, or approved, Contractor shall assume full responsibility for arranging and obtaining such inspections, tests, or approvals, pay all costs in connection therewith, and furnish City the required certificates of inspection, testing or approval, except that those fees specifically identified in the Supplementary Conditions or any Texas Department of Licensure and Regulation (TDLR) inspections, which shall will be paid as described in the Supplementary Conditions. C. Contractor shall be responsible for arranging, obtaining, and paying for all inspections, tests, re-tests, and approvals required: 1. by the Contract Documents, unless the Contract Documents expressly allocate responsibility for a specific inspection or test to City; 2. to attain City’s acceptance of materials or equipment to be incorporated in the Work; 3. by manufacturers of equipment furnished under the Contract Documents; 4. for testing, adjusting, and balancing of mechanical, electrical, and other equipment to be incorporated into the Work; and 5. for acceptance of materials, mix designs, or equipment submitted for approval prior to Contractor’s purchase thereof for incorporation in the Work. Such inspections and tests will be performed by independent inspectors, testing laboratories, or other qualified individuals or entities acceptable to City. 00 72 00 GENERAL CONDITIONS Page 49 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 D. City may arrange for the services of an independent testing laboratory (“Testing Lab”) to perform any inspections or tests (“Testing”) for any part of the Work, as determined solely by City. 1. City will coordinate such Testing to the extent possible, with Contractor; 2. Should any Testing under this Section 13.03.D result in a “fail”, “did not pass” or other similar negative result, the Contractor shall be responsible for paying for any and all retests. Contractor’s cancellation without cause of City initiated Testing shall be deemed a negative result and require a retest. 3. Any amounts owed for any retest under this Section 13.02.D shall be paid directly to the Testing Lab by Contractor. City will forward all invoices for retests to Contractor. 4. If Contractor fails to pay the Testing Lab, City will not issue Final Payment until the Testing Lab is paid. E. If the Contract Documents require the Work (or part thereof) to be approved by City or another designated individual or entity, then Contractor shall assume full responsibility for seeking and obtaining such approvals. F. If any Work (or the work of others) that is to be inspected, tested, or approved is covered by Contractor without the written approval of City, Contractor shall, if requested by City, uncover such Work for observation. Such uncovering and the recovering of such Work will be at Contractor’s expense. 13.03 Defective Work A. Contractor’s Obligation: It is Contractor’s obligation to assure that the Work is not defective. B. City’s Authority: City has the authority to determine whether Work is defective, and to reject defective Work. C. Notice of Defects: Written notice of all defective Work of which City has actual knowledge will be given to Contractor. D. Correction, or Removal and Replacement: Promptly after receipt of written notice of defective Work, Contractor shall correct all such defective Work, whether or not fabricated, installed, or completed, or, if City has rejected the defective Work, shall remove the defective Work from the Project and replace it with Work that is not defective. Failure to require the removal of any defective Work shall not constitute acceptance of such Work. E. Preservation of Warranties: When correcting defective Work, Contractor shall take no action that would void or otherwise impair City’s warranty and guarantee, if any, on said Work. F. Costs and Damages: In addition to its correction, removal, and replacement obligations with respect to defective Work, Contractor shall pay all claims, costs, losses, and damages arising out of or relating to defective Work, including but not limited to the cost of the inspection, testing, correction, removal, replacement, or reconstruction of such defective Work, fines levied against Contractor or City by governmental authorities because the Work is defective, and the costs of repair, replacement or reconstruction of work of others resulting from defective Work. 00 72 00 GENERAL CONDITIONS Page 50 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 13.04 Rejecting Defective Work A. City will have authority to reject Work which City believes to be defective or will not produce a completed Project that conforms to the Contract Documents or that will prejudice the integrity of the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. City will have authority to conduct special inspection or testing of the Work as provided in this Article 13, whether or not the Work is fabricated, installed, or completed. 13.05 Acceptance of Defective Work A. If, instead of requiring correction or removal and replacement of defective Work, City prefers to accept it, City may do so. Contractor shall pay all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) attributable to City’s evaluation of and determination to accept such defective Work, and for the diminished value of the Work to the extent not otherwise paid by Contractor. If any such acceptance occurs prior to Final Acceptance, a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work, and City shall be entitled to an appropriate decrease in the Contract Price, reflecting the diminished value of the Work so accepted. 13.06 Uncovering Work A. City has the authority to require additional inspection or testing of the Work, whether or not the Work is fabricated, installed, or completed. B. If any Work is covered contrary to the Contract Documents or specific instructions of City and if requested by City, Contractor shall uncover such Work for City’s observation, inspection or testing and then replace the covering, all at Contractor’s expense. C. If City considers it necessary or advisable that covered Work be observed by City or inspected or tested by others, then Contractor, at City’s request, shall uncover, expose, or otherwise make available for observation, inspection, or testing as City may require, that portion of the Work in question, and provide all necessary labor, material, and equipment. 1. If it is found that the uncovered Work is defective, Contractor shall be responsible for all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or dispute resolution costs) arising out of or relating to such uncovering, exposure, observation, inspection, and testing, and of satisfactory replacement or reconstruction (including but not limited to all costs of repair or replacement of work of others). City shall be entitled to accept defective Work in accordance with Paragraph 13.05 and in such case Contractor shall still be responsible for all costs associated with exposing, observing, and testing defective Work. 2. If the uncovered Work is not found to be defective, Contractor shall be allowed an extension of the Contract Time to the extent directly attributable to such uncovering, exposure, observation, inspection, testing, replacement, and reconstruction. 13.07 City May Stop the Work A. If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials or equipment, or Contractor fails to perform the Work in such a way that the completed Work will conform to the Contract Documents, then City may order Contractor to 00 72 00 GENERAL CONDITIONS Page 51 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 stop the Work, or any portion thereof, until the cause for such order has been corrected or eliminated; however, this right of City to stop the Work will not give rise to any duty on the part of City to exercise this right for the benefit of Contractor, any Subcontractor, any Supplier, any other individual or entity, or any surety for, or any employee or agent of, any of them. 13.08 City May Correct Defective Work A. If Contractor fails within a reasonable time after written notice from City to correct defective Work, or to remove and replace defective Work as required by City, or if Contractor fails to perform the Work in accordance with the Contract Documents, or if Contractor fails to comply with any other provision of the Contract Documents, then City may, after providing 7 days’ advance written notice to Contractor, correct or remedy any such deficiency. B. In connection with such corrective or remedial action, City may exclude Contractor from all or part of the Site, take possession of all or part of the Work and suspend Contractor’s services related thereto, and incorporate in the Work all materials and equipment stored at the Site or for which City has paid Contractor but which are stored elsewhere. Contractor shall allow City, City’s representatives, agents and employees, and City’s other contractors access to the Site to enable City to exercise the rights and remedies under this Paragraph 13.08. C. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court, or arbitration or other dispute resolution costs) incurred or sustained by City in exercising the rights and remedies under this Paragraph 13.08 will be the responsibility of and will be charged against Contractor. A Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work, and City shall be entitled to an appropriate decrease in the Contract Price. Such claims, costs, losses and damages will include, but not be limited to, all costs of repair or replacement of work of others destroyed or damaged by correction, removal, or replacement of Contractor’s defective Work. D. Contractor shall not be allowed an extension of the Contract Time because of any delay in the performance of the Work attributable to the exercise by City of City’s rights and remedies under this Paragraph 13.08. ARTICLE 14 – PAYMENTS TO CONTRACTOR; COMPLETION; CORRECTION PERIOD 14.01 Progress Payments A. Basis for Progress Payments: The Schedule of Values established as provided in Paragraph 2.03 will serve as the basis for progress payments and will be incorporated into a form of Application for Payment acceptable to City. Progress payments for Unit Price Work will be based on the number of units completed during the pay period, as determined under the provisions of Paragraph 12.03. Progress payments for cost-based Work will be based on Cost of the Work completed by Contractor during the pay period. B. Applications for Payments 1. Contractor is responsible for providing all information as required to become a vendor of the City. 2. At least 20 days before the date established in the General Requirements for each progress payment (but not more often than once a month), Contractor shall submit to City for review an Application for Payment filled out and signed by Contractor covering the Work 00 72 00 GENERAL CONDITIONS Page 52 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 completed as of the date of the Application and accompanied by such supporting documentation as is required by the Contract Documents. 3. If payment is requested on the basis of materials and equipment not incorporated in the Work but delivered and suitably stored at the Site or at another location agreed to in writing, the Application for Payment must also be accompanied by: (a) bill of sale, invoice, or purchase order payments, copies of cancelled checks or other documentation establishing full payment by Contractor for the materials and equipment; (b) at City’s request, documentation warranting that City has received the materials and equipment free and clear of all Liens; and (c) evidence that the materials and equipment are covered by appropriate property insurance, or other arrangements to protect City’s interest therein, all of which must be satisfactory to City. 4. Beginning with the second Application for Payment, each Application must include an affidavit of Contractor stating that all previous progress payments received on account of the Work by Contractor have been applied to discharge Contractor’s legitimate obligations associated with prior Applications for Payment. 5. The amount of retainage with respect to progress payments will be as stipulated in the Contract Documents. C. Review of Applications 1. City will, after receipt of each Application for Payment, either indicate in writing it will proceed to process the Application for Payment or return the Application to Contractor indicating reasons for refusing payment. In the latter case, Contractor may make the necessary corrections and resubmit the Application. 2. City’s processing of any payment requested in an Application for Payment will be based on City’s observations of the executed Work, and on City’s review of the Application for Payment and the accompanying data and schedules, that based City’s actual knowledge: a. the Work has progressed to the point indicated; and b. the quality and/or quantity of the Work is generally in accordance with the Contract Documents (subject to any subsequent evaluations of the Work, an evaluation of the Work as a functioning whole prior to or upon Final Acceptance, the results of any subsequent tests or inspections called for in the Contract Documents, a final determination of quantities and classifications for Unit Price Work under Paragraphs 10.05 and 12.03, and any other qualifications stated). 3. Processing any such payment will not thereby be deemed to have represented that: a. inspections made to check the quality or the quantity of the Work as it has been performed have been exhaustive, extended to every aspect of the Work in progress, or involved detailed inspections of the Work; or b. there are no other matters or issues between the parties that might entitle Contractor to be paid additionally by City or entitle City to withhold payment to Contractor; or c. Contractor has complied with Laws and Regulations applicable to Contractor’s performance of the Work. 4. City may refuse to process or pay the whole or any part of any payment because of subsequently discovered evidence or the results of subsequent inspections or tests, and 00 72 00 GENERAL CONDITIONS Page 53 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 may revise or revoke any such payment previously made, to such extent as may be necessary to protect City from loss because: a. the Work is defective, or the completed Work has been damaged by the Contractor or his subcontractors, requiring correction or replacement; b. there are discrepancies in quantities contained in previous applications for payment; c. the Contract Price has been reduced by Change Orders; d. City has been required to correct defective Work in accordance with Paragraph 1313.08, or has accepted defective Work pursuant to Paragraph 13.05; e. City has been required to remove or remediate a Hazardous Environmental Condition for which Contractor is responsible; or f. City has actual knowledge of the occurrence of any of the events enumerated in Paragraph 15.02.A that would constitute a default by Contractor and therefore justify termination for cause under the Contract Documents. D. Retainage: 1. For all contracts, retainage shall be five percent (5%). E. Liquidated Damages: For each calendar day that any work shall remain uncompleted after the time specified in the Contract Documents, the sum per day specified in the Agreement will be paid by the Contractor to the City, not as a penalty, but as liquidated damages suffered by the City. If feasible, the parties may agree to have the liquidated damages deducted from any amounts owned to Contractor by City instead of being paid directly to City by Contractor. F. Payment: Contractor will be paid pursuant to the requirements of this Article 14 and payment will become due in accordance with the Contract Documents. G. Reduction in Payment 1. City may refuse to make payment of the of the amount requested because: a. Claims have been made against City based on Contractor’s performance or furnishing of the Work, or City has incurred costs, losses, or damages resulting from Contractor’s performance or furnishing of the Work, including but not limited to claims, costs, losses, or damages from workplace injuries, adjacent property damage, non-compliance with Laws and Regulations, or patent infringement; b. Contractor has failed to take reasonable and customary measures to avoid damage, delay, disruption, and interference with other work at or adjacent to the Site; c. Contractor has failed to provide and maintain required bonds or insurance; d. City has been required to remove or remediate a Hazardous Environmental Condition for which Contractor is responsible; e. City has incurred extra charges or engineering costs related to submittal reviews, evaluations of proposed substitutes, tests and inspections, or return visits to manufacturing or assembly facilities; f. The Work is defective, requiring correction or replacement; 00 72 00 GENERAL CONDITIONS Page 54 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 g. City has been required to correct defective Work in accordance with Paragraph 13.08, or has accepted defective Work pursuant to Paragraph 13.05; h. The Contract Price has been reduced by Change Orders; i. An event has occurred that would constitute a default by Contractor and therefore justify a termination for cause; j. Liquidated or other damages have accrued as a result of Contractor’s failure to achieve Milestones or Final Acceptance of the Work; k. Liens have been filed in connection with the Work, except where Contractor has delivered a specific bond satisfactory to City to secure the satisfaction and discharge of such Liens; l. Other items entitle City to a set-off against the payment amount requested; or m. City has actual knowledge of the occurrence of any of the events enumerated in Paragraph 15.02. 2. If City refuses to make payment of the amount requested, City will give Contractor written notice stating the reasons for such action and promptly pay Contractor any amount remaining after deduction of the amount so withheld. City shall pay Contractor the amount so withheld, or any adjustment thereto agreed to by City and Contractor, within a reasonable time after Contractor remedies the reasons for such action to the satisfaction of City and City has confirmed such action. 14.02 Contractor’s Warranty of Title A. Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any Application for Payment, whether incorporated in the Project or not, will pass to City no later than the time of payment free and clear of all Liens. 14.03 Partial Utilization A. Prior to Final Acceptance of all the Work, City may use or occupy any substantially completed part of the Work which has specifically been identified in the Contract Documents, or which City determines constitutes a separately functioning and usable part of the Work that can be used by City for its intended purpose without significant interference with Contractor’s performance of the remainder of the Work. City at any time may notify Contractor in writing to of any such part of the Work which City determines to be ready for its intended use. In addition, City may request in writing that Contractor permit City to use or occupy any such part of the Work that City believes to be substantially complete, subject to the following conditions: 1. At any time, Contractor may notify City that Contractor considers any such part of the Work ready for its intended use. 2. Within a reasonable time after notification as enumerated in Paragraph 14.03, City and Contractor shall make an inspection of that part of the Work to determine its status of completion. If City does not consider that part of the Work to be substantially complete, City will notify Contractor in writing giving the reasons therefor. 3. Partial Utilization by City will not constitute Final Acceptance by City. 00 72 00 GENERAL CONDITIONS Page 55 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 14.04 Final Inspection A. Upon written notice from Contractor that the entire Work is complete in accordance with the Contract Documents: 1. City will promptly schedule a Final Inspection with Contractor. 2. City will notify Contractor in writing of all particulars in which this inspection reveals that the Work is incomplete or defective. Contractor shall immediately take such measures as are necessary to complete such Work or remedy such deficiencies. B. City reserves the right to deny request for Final Inspection if City determines that the entire Work is not sufficiently complete to warrant a Final Inspection. 14.05 Final Acceptance A. Upon completion by Contractor to City’s satisfaction, of any and all Work in accordance with the Contract Documents, including any corrections or additional Work identified in the Final Inspection and delivery of all maintenance and operating instructions, schedules, guarantees, bonds, certificates or other evidence of insurances, certificates of inspection, annotated record documents and other required documents in accordance with the Contract Documents, City will issue to Contractor a letter of Final Acceptance. 14.06 Final Payment A. Application for Payment 1. Upon receipt of a letter of Final Acceptance from City, Contractor may make application for Final Payment following the procedures for requesting payments in accordance with the Contract Documents. 2. The final Application for Payment must be accompanied (except as previously delivered) by: a. all documentation called for in the Contract Documents, including but not limited to the evidence of insurance required by Paragraph 6.03; b. consent of the surety, if any, to final payment; c. satisfactory evidence that all title issues have been resolved such that title to all Work, materials, and equipment has passed to City free and clear of any Liens or other title defects or will so pass upon final payment; d. a list of all Contract Claims or Damage Claims against City that Contractor believes are unsettled; e. affidavits of payments and complete and legally effective releases or waivers (satisfactory to City) of all Lien rights arising out of the Work, and of Liens filed in connection with the Work; and f. a completed subcontractor form identifying the subcontractor/supplier(s) and the description of Work and/or materials provided, if any. B. Payment Becomes Due: The final payment requested by Contractor, less previous payments made and less any sum to which City is entitled, including but not limited to liquidated damages, will become due and payable: 00 72 00 GENERAL CONDITIONS Page 56 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 1. After City’s acceptance of the Application for Payment and accompanying documentation; and 2. After all Damage Claims have been resolved: a. directly by the Contractor; or b. Contractor provides evidence that the Damage Claim has been reported to Contractor’s insurance provider for resolution. The making of the final payment by the City shall not relieve the Contractor of any guarantees or other requirements of the Contract that continue thereafter. 14.07 Final Completion Delayed and Partial Retainage Release A. If final completion of the Work is significantly delayed, and if City so confirms, City may, upon receipt of Contractor’s final Application for Payment, and without terminating the Contract, make payment of the balance due for that portion of the Work fully completed and accepted. If the remaining balance to be held by City for Work not fully completed or corrected is less than the retainage stipulated in Paragraph 14.01.D, and if bonds have been furnished as required in Paragraph 6.02, the written consent of the surety to the payment of the balance due for that portion of the Work fully completed and accepted shall be submitted by Contractor to City with the Application for such payment. Such payment shall be made under the terms and conditions governing final payment, except that it shall not constitute a waiver of Contract Claims. B. Partial Retainage Release. If the Contract provides for separate establishment and maintenance periods and/or test and performance periods following the completion of all other construction in the Contract Documents for all Work locations, the City may release a portion of the amount retained provided that all other work is completed as determined by the City. Before the release, all submittals and final quantities must be completed and accepted for all other work. An amount sufficient to ensure Contract compliance will be retained. 14.08 Waiver of Claims A. The acceptance of final payment will constitute a waiver and release by Contractor of all claims, rights, causes of action, or liabilities, including Contract Claims, against City arising out of, related to or under the Contract or for any act, omission or neglect of City. 14.09 Correction Period A. If within two (2) years after the date of Final Acceptance (or such longer period of time as may be prescribed by the Contract Documents) any Work has been found to be defective, or Contractor’s repair of any damages to the Site, adjacent areas, or areas made available for Contractor’s use by City has been found to be defective, then after receipt of City’s written notice of defect, Contractor shall promptly, without cost to City and in accordance with City’s written instructions: 1. correct the defective repairs to the Site or such adjacent areas, or areas made available for Contractor’s use by City; 2. correct such defective Work; 3. remove the defective Work from the Project and replace it with Work that is not defective, if the defective Work has been rejected by City, and 00 72 00 GENERAL CONDITIONS Page 57 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 4. satisfactorily correct or repair or remove and replace any damage to other Work, to the work of others, or to other land or areas resulting from the corrective measures. B. If Contractor does not promptly comply with the terms of City’s written instructions, or in an emergency where delay would cause serious risk of loss or damage, City may have the defective Work corrected or repaired or may have the rejected Work removed and replaced. Contractor shall pay all costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such correction or repair or such removal and replacement (including but not limited to all costs of repair or replacement of work of others). C. In special circumstances where a particular item of equipment is placed in continuous service before Final Acceptance of all the Work, the correction period for that item may start to run from an earlier date if so provided in the Specifications. D. Where defective Work (and damage to other Work resulting therefrom) has been corrected, repaired or removed and replaced under this Paragraph 14.09, the correction period hereunder with respect to such Work may be extended for an additional period of one year after the end of the initial correction period. E. Contractor’s obligations under this paragraph are in addition to all other obligations and warranties. The provisions of this Paragraph 14.09 are not to be construed as a substitute for, or a waiver of, the provisions of any applicable statute of limitation or repose. ARTICLE 15 – SUSPENSION OF WORK AND TERMINATION 15.01 City May Suspend Work A. At any time and without cause, City may suspend the Work or any portion thereof by written notice to Contractor. City may fix the date on which Work will be resumed in such notice, and Contractor shall resume the Work on the date so fixed. During a temporary suspension of the Work covered by these Contract Documents, for any reason, the City will make no extra payment for stand-by time of construction equipment and/or construction crews. B. Should the Contractor not be able to complete a portion of the Project due to causes beyond the control of and without the fault or negligence of the Contractor, and should it be determined by mutual consent of the Contractor and City that a solution to allow construction to proceed is not available within a reasonable period of time, Contractor may request an extension in Contract Time, directly attributable to any such suspension. C. If it should become necessary to suspend the Work for an indefinite period, the Contractor shall store all materials in such a manner that they will not obstruct or impede the public unnecessarily nor become damaged in any way; Contractor shall take every precaution to prevent damage or deterioration of the work performed; and Contractor shall provide suitable drainage about the work, and erect temporary structures where necessary. D. Contractor may be reimbursed for the cost of moving its equipment off the job and returning the necessary equipment to the job when it is determined by the City that construction may be resumed. Such reimbursement shall be based on actual cost to the Contractor of moving the equipment and no profit or overhead will be allowed. Reimbursement may not be allowed if the equipment is moved to another construction project for the City. 00 72 00 GENERAL CONDITIONS Page 58 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 15.02 City May Terminate for Cause A. The occurrence of any one or more of the following events by way of example, but not of limitation, may justify termination for cause: 1. Contractor’s persistent failure to perform the Work in accordance with the Contract Documents (including, but not limited to, failure to supply sufficient skilled workers or suitable materials or equipment, or failure to adhere to the Project Schedule established under Paragraph 2.06 as adjusted from time to time pursuant to Paragraph 7.05); 2. Failure of Contractor to perform or otherwise to comply with a material term of the Contract; or 3. Contractor’s disregard of Laws and Regulations of any public body having jurisdiction; or 4. Contractor’s repeated disregard of the authority of City; or 5. Contractor’s failure to promptly make good any defect in materials or workmanship, or defects of any nature, the correction of which has been directed in writing by the City; or 6. Substantial indication that the Contractor has made an unauthorized assignment of the Contract or any funds due therefrom for the benefit of any creditor or for any other purpose; or 7. Substantial indication that the Contractor has become insolvent or bankrupt, or otherwise financially unable to perform the Work satisfactorily; or 8. Contractor commences legal action in a court of competent jurisdiction against the City. B. If one or more of the events identified in Paragraph 15.02.A occurs, City will provide written notice to Contractor and Surety to arrange a conference with Contractor and Surety to address Contractor’s failure to perform the Work. The conference shall be held not later than 15 days after receipt of notice. by both Contractor and surety. 1. If the City, the Contractor, and the Surety do not agree to allow the Contractor to proceed to perform the Contract, the City may, to the extent permitted by Laws and Regulations, declare a Contractor default and formally terminate the Contractor's right to complete the Contract. Contractor default shall not be declared earlier than 20 days after the Contractor and Surety have received notice of the conference to address Contractor's failure to perform the Work. 2. If Contractor's services are terminated, Surety shall be obligated to take over and perform the Work. If Surety does not commence performance thereof within 15 consecutive calendar days after date of an additional written notice demanding Surety’s performance of its obligations, then City, without process or action at law, may take over any portion of the Work and complete it as described below. a. If City completes the Work, City may exclude Contractor and Surety from the Site and take possession of the Work, and all materials and equipment stored at the Site or for which City has paid Contractor, but which are stored elsewhere, and the Work as City may deem expedient. 3. Whether City or Surety completes the Work, Contractor shall not be entitled to receive any further payment until the Work is completed. If the unpaid balance of the Contract Price exceeds the cost to complete the Work, including all related claims, costs, losses, 00 72 00 GENERAL CONDITIONS Page 59 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals) sustained by City, such excess will be paid to Contractor. If the cost to complete the Work including such related claims, costs, losses, and damages exceeds such unpaid balance, Contractor shall pay the difference to City. Such claims, costs, losses, and damages incurred by City will be incorporated in a Change Order, provided that when exercising any rights or remedies under this Paragraph 15.02, City shall not be required to obtain the lowest price for the Work performed. 4. Neither City, nor any of its respective consultants, agents, officers, elected or appointed officials, directors or employees shall be in any way liable or accountable to Contractor or Surety for the method by which the completion of the said Work, or any portion thereof, may be accomplished or for the price paid therefor. 5. City, notwithstanding the method used in completing the Contract, shall not forfeit the right to recover damages from Contractor or Surety for Contractor's failure to timely complete the entire Contract. Contractor shall not be entitled to any claim, counterclaim or offset on account of the method used by City in completing the Contract. 6. Maintenance of the Work shall continue to be Contractor's and Surety's responsibilities as provided for in the bond requirements of the Contract Documents or any special guarantees provided for under the Contract Documents or any other obligations otherwise under the Contract or prescribed by law. C. Notwithstanding Paragraph 15.02.B, Contractor’s services will not be terminated if Contractor begins within seven days of receipt of notice of intent to terminate to correct its failure to perform and proceeds diligently to cure such failure within no more than 30 days of receipt of said notice. D. Where Contractor’s services have been so terminated by City, the termination will not affect any rights or remedies of City against Contractor then existing or which may thereafter accrue, or any rights or remedies of City against Contractor or Surety. Any retention or payment of money due Contractor by City will not release Contractor from liability. E. If and to the extent that Contractor has provided a performance bond under the provisions of Paragraph 6.02, the termination procedures of that bond shall not supersede the provisions of this Article 15. 15.03 City May Terminate for Convenience A. City may, without cause and without prejudice to any other right or remedy of City, terminate the Contract, in whole or in part. Any termination shall be affected by giving notice of the termination to the Contractor specifying the extent to which performance of Work under the contract is terminated, and the date upon which such termination becomes effective. Notice shall be deemed validly given if given in accordance with Paragraph 17.01.A. B. After a notice of termination, has been given, and except as otherwise directed by the City, the Contractor shall: 1. stop work under the Contract on the date and to the extent specified in the notice of termination; 2. place no further orders or subcontracts for materials, services or facilities except as may be necessary for completion of such portion of the Work under the Contract as is not terminated; 00 72 00 GENERAL CONDITIONS Page 60 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 3. terminate all orders and subcontracts to the extent that they relate to the performance of the Work terminated by notice of termination; 4. transfer title to the City and deliver in the manner, at the times, and to the extent, if any, directed by the City: a. the fabricated or unfabricated parts, Work in progress, completed Work, supplies and other material produced as a part of, or acquired in connection with the performance of, the Work terminated by the notice of the termination; and b. the completed, or partially completed plans, drawings, information and other property which, if the Contract had been completed, would have been required to be furnished to the City. 5. complete performance of such Work as shall not have been terminated by the notice of termination; and 6. take such action as may be necessary, or as the City may direct, for the protection and preservation of the property related to the Contract that is in the possession of the Contractor and in which the City has or may acquire the rest. C. At a time not later than 30 days after the termination date specified in the notice of termination, the Contractor may submit to the City a list, certified as to quantity and quality, of any or all items of termination inventory not previously disposed of in accordance with the Contract, exclusive of items the disposition of which has been directed or authorized by City. D. Not later than 15 days after Contractor’s submission of the certified list to City pursuant to Paragraph 15.03.C, the City shall accept title to such items, subject to verification of the list by the City upon removal of the items or,. If the items are stored, then City shall have 45 days after submission of the list, to verify the list submitted and accept title to such items. Any necessary adjustments to correct the list as submitted, shall be made prior to final settlement. E. Not later than 60 days after the notice of termination has been given, the Contractor shall submit hisits termination claim to the City in the form and with the certification prescribed by the City. Unless an extension request is made in writing within such 60-day period by the Contractor, and granted by the City, any and all such claims of Contractor that are not submitted to City within such 60-day period shall be conclusively deemed waived. F. Should a termination claim be timely submitted to the City, Contractor shall be paid for (without duplication of any items): 1. completed and acceptable Work executed in accordance with the Contract Documents prior to the effective date of termination, including fair and reasonable sums for overhead and profit on such Work calculated and determined in accordance with the Contract Documents; 2. expenses sustained prior to the effective date of termination in performing services and furnishing labor, materials, or equipment as required by the Contract Documents in connection with uncompleted Work, plus fair and reasonable sums for overhead and profit on such expenses calculated and determined in accordance with the Contract Documents; and 3. reasonable expenses directly attributable to reasonable and necessary wind-down and termination activities, without any overhead or profit. 00 72 00 GENERAL CONDITIONS Page 61 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 G. In the event of the failure of the Contractor and City to agree upon the whole amount to be paid to the Contractor by reason of the termination of the Work, the City shall determine, on the basis of information submitted and available to it, the amount, if any, due to the Contractor by reason of the termination and City shall pay to the Contractor the amounts so determined. Contractor shall not be paid on account of loss of anticipated profits or revenue or other economic loss arising out of, related to or resulting from such termination. ARTICLE 16 – RESOLUTION OF DISPUTES 16.01 Methods and Procedures A. Either City or Contractor may request mediation of any Contract Claim submitted for a decision under Paragraph 11.07 before such decision becomes final and binding. The request for mediation shall be submitted to the other party to the Contract. Timely submission of the request shall stay the effect of Paragraph 11.07.E. B. City and Contractor shall participate in the mediation process in good faith. The process shall be commenced within 60 calendar days of filing of the request. C. The parties shall agree on a mediator; however, if they cannot agree within 14 calendar days then the Denton County Alternative Dispute Resolution Program (“DCAP”) shall appoint a mediator. The mediation session shall be held within 45 days of the retention of the mediator, and last for at least one full mediation day, before any party has the option to withdraw from the process. The parties may agree to continue the mediation process beyond one day, until there is a settlement agreement, or one party, or the mediator, states that there is no reason to continue because of an impasse that cannot be overcome and sends a “notice of termination of mediation.” All reasonable efforts will be made to complete the mediation within 30 days of the first mediation session. All costs of mediation shall be borne equally by the parties. D. All communications, both written and oral, during Phases A and B are confidential and shall be treated as settlement negotiations for purposes of applicable rules of evidence; however, documents generated in the ordinary course of business prior to the Dispute, that would otherwise be discoverable, do not become confidential simply because they are used in the Negotiation and/or Mediation process. E. The process shall be confidential based on terms acceptable to the mediator and/or mediation service provider. F. If the Contract Claim is not resolved by mediation, City’s action under Paragraph 11.07.C or a denial pursuant to Paragraphs 11.07.C.3 or 11.07.D shall become final and binding 30 days after termination of the mediation unless, within that time period, City or Contractor: 1. elects in writing to invoke any other dispute resolution process provided for in the Supplementary Conditions; or 2. agrees with the other party to submit the Contract Claim to another dispute resolution process; or 3. gives written notice to the other party of the intent to submit the Contract Claim to a court of competent jurisdiction as set forth within the Contract Documents. 00 72 00 GENERAL CONDITIONS Page 62 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 ARTICLE 17 – MISCELLANEOUS 17.01 Giving Notice A. Whenever any provision of the Contract requires the giving of written notice, it will be deemed to have been validly given if delivered: 1. in person, by a commercial courier service or otherwise, if to City, to the duly authorized representative of City identified in the Contract Documents or to City’s Project Manager or, if to Contractor, to a member of the firm or to an officer of the corporation for whom it is intended; or 2. by registered or certified mail, postage prepaid, to the recipient’s place of business; or 3. by e-mail to the recipient. 17.02 Computation of Time A. When any period of time is referred to in the Contract by days, it will be computed to exclude the first and include the last day of such period. If the last day of any such period falls on a Saturday or Sunday or on a day that is a state or federal holiday observed by the City, the next Business Day shall become the last day of the period. 17.03 Cumulative Remedies A. The duties and obligations imposed by these General Conditions and the rights and remedies available hereunder to the parties hereto are in addition to, and are not to be construed in any way as a limitation of, any rights and remedies available to any or all of them which are otherwise imposed or available by Laws and Regulations, in equity, by special warranty or guarantee, or by other provisions of the Contract. The provisions of this Paragraph 17.03 will be as effective as if repeated specifically in the Contract Documents in connection with each particular duty, obligation, right, and remedy to which they apply. 17.04 Limitation of Damages A. With respect to any and all claims, disputes subject to final resolution, and other matters at issue, neither City, nor any of its officers, directors, elected or appointed officials, members, partners, employees, agents, consultants, or subcontractors, shall be liable to Contractor for any claims, costs, losses, or damages sustained by Contractor on or in connection with any other project or anticipated project. Further, the Contractor may only claim and the City may only be liable for those damages that are set forth in Subchapter I, Chapter 271 of the Texas Local Government Code and the City shall not be liable for any consequential damages, exemplary damages or damages for unabsorbed home office overhead. 17.05 No Waiver A. A party’s non-enforcement of any provision will not constitute a waiver of that provision, nor will it affect the enforceability of that provision or of the remainder of this Contract. B. The City has not waived its sovereign immunity except as expressly set forth in Subchapter I, Chapter 271 of the Texas Local Government Code or as expressly waived by other statute. 17.06 Survival of Obligations All representations, indemnifications, warranties, and guarantees made in, required by, or given in accordance with the Contract, as well as all continuing obligations indicated in the 00 72 00 GENERAL CONDITIONS Page 63 of 65 CITY OF DENTON STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised June 4, 2025 Contract, will survive final payment, completion, and Final Acceptance of the Work or termination of the Contract or of the services of Contractor. 17.07 Assignment of Contract A. Unless expressly agreed to elsewhere in the Contract, no assignment by a party to this Contract of any rights under or interests in the Contract will be binding on the other party without the written consent of the party sought to be bound; and, specifically but without limitation, money that may become due and money that is due may not be assigned without such consent (except to the extent that the effect of this restriction may be limited by law), and unless specifically stated to the contrary in any written consent to an assignment, no assignment will release or discharge the assignor from any duty or responsibility under the Contract. 17.08 Successors and Assigns A. City and Contractor each binds itself, its successors, assigns, and legal representatives to the other party hereto, its successors, assigns, and legal representatives in respect to all covenants, agreements, and obligations contained in the Contract Documents. 17.09 Governing Law A. The Contract shall be construed in accordance with the laws of the State of Texas without regard to conflicts of law principles. 17.10 Headings A. Article and paragraph headings are inserted for convenience only and do not constitute parts of these General Conditions. 00 73 00 SUPPLEMENTARY CONDITIONS Page 1 of 6 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised February 27, 2023 Effective February 27, 2023 SECTION 00 73 00 1 SUPPLEMENTARY CONDITIONS 2 TO 3 GENERAL CONDITIONS 4 5 Supplementary Conditions 6 7 These Supplementary Conditions modify and supplement Section 00 72 00 - General Conditions, and other 8 provisions of the Contract Documents as indicated below. All provisions of the General Conditions that are 9 modified or supplemented remain in full force and effect as so modified or supplemented. All provisions 10 of the General Conditions which are not so modified or supplemented remain in full force and effect. 11 12 Defined Terms 13 14 The terms used in these Supplementary Conditions which are defined in the General Conditions have the 15 meaning assigned to them in the General Conditions, unless specifically noted herein. 16 17 Modifications and Supplements 18 19 The following are instructions that modify or supplement specific paragraphs in the General Conditions and 20 other Contract Documents. 21 22 23 SC-5.01A 24 25 Easement limits shown on the Drawing are approximate and were provided to establish a basis for bidding. 26 Upon receiving the final easements descriptions, Contractor shall compare them to the lines shown on the 27 Contract Drawings. 28 29 SC-5.01A.1., “Availability of Lands” 30 31 The following is a list of known outstanding right-of-way, and/or easements to be acquired, if any as of 32 February 18, 2026: 33 34 35 36 37 Outstanding Right-Of-Way, and/or Easements to Be Acquired 38 PARCEL NUMBER OWNER TARGET DATE OF POSSESSION None The Contractor understands and agrees that the dates listed above are estimates only, are not guaranteed, 39 and do not bind the City. 40 41 If Contractor considers the final easements provided to differ materially from the representations on the 42 Contract Drawings, Contractor shall within five (5) Business Days and before proceeding with the Work, 43 notify City in writing associated with the differing easement line locations. 44 45 SC-5.01A.2, “Availability of Lands” 46 00 73 00 SUPPLEMENTARY CONDITIONS Page 2 of 6 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised February 27, 2023 Effective February 27, 2023 1 Utilities or obstructions to be removed, adjusted, and/or relocated 2 3 The following is list of utilities and/or obstructions that have not been removed, adjusted, and/or relocated 4 as of February 18, 2026 5 6 EXPECTED OWNER UTILITY AND LOCATION TARGET DATE OF ADJUSTMENT None The Contractor understands and agrees that the dates listed above are estimates only, are not guaranteed, 7 and do not bind the City. 8 9 SC-5.03A., “Subsurface and Physical Conditions” 10 11 The following are reports of explorations and tests of subsurface conditions at the site of the Work: 12 13 14 The following are drawings of physical conditions in or relating to existing surface and subsurface 15 structures (except Underground Facilities) which are at or contiguous to the site of the Work: 16 None 17 SC-5.05 A., “Underground Facilities 18 19 The following are additional resources for identification of Underground Facilities which are at or 20 contiguous to the site of the Work, and which are not necessarily shown in the Drawings: 21 None 22 23 SC-5.06A., “Hazardous Environmental Conditions at Site” 24 25 The following are reports and drawings of existing hazardous environmental conditions known to the City: 26 None 27 28 SC-6.02, “Performance, Payment, and Maintenance Bonds” 29 30 The “Contract Price” for Performance, Payment, and Maintenance Bonds will be the same as indicated 31 in Article 3 as listed in the Agreement. 32 33 SC-6.03A., “Certificates of Insurance” 34 35 The entities listed below are "additional insureds as their interest may appear" including their respective 36 officers, directors, agents and employees. 37 38 (1) City 39 (2) Consultant: None 40 (3) Other: None 41 42 43 SC-6.04A., “Contractor’s Insurance” 44 45 The limits of liability for the insurance required by Paragraph GC-6.04 shall provide the following 46 coverages for not less than the following amounts or greater where required by laws and regulations: 47 48 00 73 00 SUPPLEMENTARY CONDITIONS Page 3 of 6 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised February 27, 2023 Effective February 27, 2023 6.04A. Workers' Compensation, under Paragraph GC-6.04A. 1 2 Statutory limits 3 Employer's liability 4 $500,000 each accident/occurrence 5 $500,000 Disease - each employee 6 $500,000 Disease - policy limit 7 8 SC-6.04B., “Contractor’s Insurance” 9 10 6.04B. Commercial General Liability, under Paragraph GC-6.04B. Contractor's Liability Insurance 11 under Paragraph GC-6.04B., which shall be on a per project basis covering the Contractor with 12 minimum limits of: 13 14 $1,000,000 each occurrence 15 $2,000,000 aggregate limit 16 17 The policy must have an endorsement (Amendment – Aggregate Limits of Insurance) making the 18 General Aggregate Limits apply separately to each job site. 19 20 The Commercial General Liability Insurance policies shall provide “X”, “C”, and “U” coverage’s. 21 Verification of such coverage must be shown in the Remarks Article of the Certificate of Insurance. 22 23 SC 6.04C., “Contractor’s Insurance” 24 6.04C. Automobile Liability, under Paragraph GC-6.04C. Contractor’s Liability Insurance under 25 Paragraph GC-6.04C., which shall be in an amount not less than the following amounts: 26 27 (1) Automobile Liability - a commercial business policy shall provide coverage on "Any Auto", 28 defined as autos owned, hired and non-owned. 29 30 $1,000,000 each accident on a combined single limit basis. 31 32 SC-6.04D., “Contractor’s Insurance” 33 34 The Contractor’s construction activities will require its employees, agents, subcontractors, equipment, and 35 material deliveries to cross railroad properties and tracks, or perform work within 25 feet of the center line 36 of tracks None. 37 38 The Contractor shall conduct its operations on railroad properties in such a manner as not to interfere with, 39 hinder, or obstruct the railroad company in any manner whatsoever in the use or operation of its/their trains 40 or other property. Such operations on railroad properties may require that Contractor to execute a “Right of 41 Entry Agreement” with the particular railroad company or companies involved, and to this end the 42 Contractor should satisfy itself as to the requirements of each railroad company and be prepared to execute 43 the right-of-entry (if any) required by a railroad company. The requirements specified herein likewise relate 44 to the Contractor’s use of private and/or construction access roads crossing said railroad company’s 45 properties. 46 47 The Contractual Liability coverage required by Paragraph 5.04D of the General Conditions shall provide 48 coverage for not less than the following amounts, issued by companies satisfactory to the City and to the 49 Railroad Company for a term that continues for so long as the Contractor’s operations and work cross, 50 occupy, or touch railroad property: 51 52 (1) General Aggregate: $Confirm Limits with Railroad 53 54 00 73 00 SUPPLEMENTARY CONDITIONS Page 4 of 6 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised February 27, 2023 Effective February 27, 2023 (2) Each Occurrence: $Confirm Limits with Railroad 1 2 Required for this Contract X Not required for this Contract 3 4 With respect to the above outlined insurance requirements, the following shall govern: 5 6 1. Where a single railroad company is involved, the Contractor shall provide one insurance policy in 7 the name of the railroad company. However, if more than one grade separation or at-grade 8 crossing is affected by the Project at entirely separate locations on the line or lines of the same 9 railroad company, separate coverage may be required, each in the amount stated above. 10 11 2. Where more than one railroad company is operating on the same right-of-way or where several 12 railroad companies are involved and operated on their own separate rights-of-way, the Contractor 13 may be required to provide separate insurance policies in the name of each railroad company. 14 15 3. If, in addition to a grade separation or an at-grade crossing, other work or activity is proposed on a 16 railroad company’s right-of-way at a location entirely separate from the grade separation or at-17 grade crossing, insurance coverage for this work must be included in the policy covering the grade 18 separation. 19 20 4. If no grade separation is involved but other work is proposed on a railroad company’s right-of-21 way, all such other work may be covered in a single policy for that railroad, even though the work 22 may be at two or more separate locations. 23 24 No work or activities on a railroad company’s property to be performed by the Contractor shall be 25 commenced until the Contractor has furnished the City with an original policy or policies of the insurance 26 for each railroad company named, as required above. All such insurance must be approved by the City and 27 each affected Railroad Company prior to the Contractor’s beginning work. 28 29 The insurance specified above must be carried until all Work to be performed on the railroad right-of-way 30 has been completed and the grade crossing, if any, is no longer used by the Contractor. In addition, 31 insurance must be carried during all maintenance and/or repair work performed in the railroad right-of-way. 32 Such insurance must name the railroad company as the insured, together with any tenant or lessee of the 33 railroad company operating over tracks involved in the Project. 34 35 SC 6.04F., “Contractor’s Insurance” 36 Add Paragraph 6.04F. Environmental Impairment/Pollution 37 38 Environmental Impairment/Pollution Insurance to include coverage for the handling, receiving, dispensing, 39 removal, storage, testing, transportation, disposal, discharge, dispersal release or escape of any hazardous 40 material into or upon land, or any structure on land, the atmosphere or any watercourse or body of water, 41 including ground water, with a minimum combined bodily injury (including death) and property damage 42 limit of $2,000,000 per occurrence to be obtained upon substantial completion and acceptance of facility by 43 the City. 44 45 SC-7.08C., “Concerning Subcontractors and Suppliers” 46 47 The following subcontractors shall be required to be utilized by the Contractor for specific portions of the 48 Work as indicated below: 49 50 Required Subcontractors 51 SUBCONTRACTOR COMPANY NAME DESCRIPTION OF WORK TO BE PERFORMED None 00 73 00 SUPPLEMENTARY CONDITIONS Page 5 of 6 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised February 27, 2023 Effective February 27, 2023 SUBCONTRACTOR COMPANY NAME DESCRIPTION OF WORK TO BE PERFORMED 1 SC-7.11., “Permits and Utilities” 2 3 SC-7.11A., “Contractor obtained permits and licenses” 4 The following are known permits and/or licenses required by the Contract to be acquired by the Contractor: 5 6 None 7 8 SC-7.11B. “City obtained permits and licenses” 9 The following are known permits and/or licenses required by the Contract to be acquired by the City: 10 11 1. Texas Department of Transportation Permit Approval 12 13 SC-7.11C. “Outstanding permits and licenses” 14 15 The following is a list of known outstanding permits and/or licenses to be acquired, if any as of February 16 18, 2026: 17 18 Outstanding Permits and/or Licenses to Be Acquired 19 OWNER PERMIT OR LICENSE AND LOCATION TARGET DATE OF POSSESSION None 20 21 SC-8.02., “Coordination” 22 23 The individuals or entities listed below have contracts with the City for the performance of other work at 24 the Site: 25 26 Vendor Scope of Work Coordination Authority None 27 SC-9.01, “Communications to Contractor” 28 29 None 30 31 SC-10.01B., “City’s Project Manager” 32 33 The City’s Project Manager for this Contract is Sheldon Gatewood, or his/her successor pursuant to written 34 notification from the City Engineer. 35 36 SC-13.02B., “Tests and Inspections” 37 38 None 39 40 SC-14.01G, “Reduction in Payment” 41 42 Add Paragraph 14.01G.3: 43 00 73 00 SUPPLEMENTARY CONDITIONS Page 6 of 6 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised February 27, 2023 Effective February 27, 2023 1 3. City may reduce payments to the Contractor, if the number of Days that have passed after the date 2 listed on the Notice to Proceed exceeds the Contract Time for Substantial Completion. 3 4 SC-16.01C.1, “Methods and Procedures” 5 6 None 7 8 SC – 17.01, “Documents” 9 10 Any documents submitted to the City in electronic format shall be considered equivalent to an original of 11 such document. 12 13 14 15 END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 00 73 73 FORM 1295 - CERTIFICATE OF INTERESTED PARTIES Page 1 of 1 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective January 15, 2021 SECTION 00 73 73 1 FORM 1295 - CERTIFICATE OF INTERESTED PARTIES 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 END OF SECTION 23 01 11 00 SUMMARY OF WORK Page 1 of 3 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 SECTION 01 11 00 1 SUMMARY OF WORK 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Summary of Work to be performed in accordance with the Contract Documents 6 B. Deviations from this City of Denton Standard Specification 7 1. None. 8 C. Related Specification Sections include, but are not necessarily limited to: 9 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the Contract 10 2. Division 1 - General Requirements 11 1.2 PRICE AND PAYMENT PROCEDURES 12 A. Measurement and Payment 13 1. Work associated with this Item is considered incidental to the various items bid. 14 No separate payment will be allowed for this Item. 15 1.3 REFERENCES [NOT USED] 16 1.4 ADMINISTRATIVE REQUIREMENTS 17 A. Work Covered by Contract Documents 18 1. Work is to include furnishing all labor, materials, and equipment, and performing 19 all Work necessary for this construction project as detailed in the Drawings and 20 Specifications. 21 B. Incidental Work 22 1. Any and all Work specifically governed by documentary requirements for the 23 project, such as conditions imposed by the Contract Documents in which no 24 specific item for bid has been provided for in the Proposal, then the item shall be 25 considered as an incidental item of Work, the cost of which shall be included in the 26 price bid in the Proposal for various bid items. 27 C. Use of Premises 28 1. Coordinate uses of premises under direction of the City. 29 2. Assume full responsibility for protection and safekeeping of materials and 30 equipment stored on the Site. 31 3. Use and occupy only portions of the public streets and alleys, or other public places 32 or other rights-of-way as provided for in the ordinances of the City, as shown in the 33 Contract Documents, or as may be specifically authorized in writing by the City. 34 a. A reasonable amount of tools, materials, and equipment for construction 35 purposes may be stored in such space, but no more than is necessary to avoid 36 delay in the construction operations. 37 01 11 00 SUMMARY OF WORK Page 2 of 3 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 b. Excavated and waste materials shall be stored in such a way as not to interfere 1 with the use of spaces that may be designated to be left free and unobstructed 2 and so as not to inconvenience occupants of adjacent property. 3 c. If the street is occupied by railroad tracks, the Work shall be carried on in such 4 manner as not to interfere with the operation of the railroad. 5 1) All Work shall be in accordance with railroad requirements set forth in 6 Division 0 as well as the railroad permit. 7 D. Work within Easements 8 1. Do not enter upon private property for any purpose without having previously 9 obtained permission from the owner of such property. 10 2. Do not store equipment or material on private property unless and until the 11 specified approval of the property owner has been secured in writing by the 12 Contractor and a copy furnished to the City. 13 3. Unless specifically provided otherwise, clear all rights-of-way or easements of 14 obstructions which must be removed to make possible proper prosecution of the 15 Work as a part of the project construction operations. 16 4. Preserve and use every precaution to prevent damage to, all trees, shrubbery, plants, 17 lawns, fences, culverts, curbing, and all other types of structures or improvements, 18 to all water, sewer, and gas lines, to all conduits, overhead pole lines, or 19 appurtenances thereof, including the construction of temporary fences and to all 20 other public or private property adjacent to the Work. 21 5. Notify the proper representatives of the owners or occupants of the public or private 22 lands of interest in lands which might be affected by the Work. 23 a. Such notice shall be made at least 48 hours in advance of the beginning of the 24 Work. 25 b. Notices shall be applicable to both public and private utility companies and any 26 corporation, company, individual, or other, either as owners or occupants, 27 whose land or interest in land might be affected by the Work. 28 c. Be responsible for all damage or injury to property of any character resulting 29 from any act, omission, neglect, or misconduct in the manner or method or 30 execution of the Work, or at any time due to defective work, material, or 31 equipment. 32 6. Fence 33 a. Restore all fences encountered and removed during construction of the Work to 34 the original or a better than original condition. 35 b. Erect temporary fencing in place of the fencing removed whenever the Work is 36 not in progress and when the site is vacated overnight, and/or at all times to 37 provide site security. 38 c. The cost for all fence work within easements, including removal, temporary 39 closures and replacement, shall be incidental to the various items bid in the 40 project proposal, unless a bid item is specifically provided in the proposal. 41 01 11 00 SUMMARY OF WORK Page 3 of 3 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 1.5 SUBMITTALS [NOT USED] 1 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 2 1.7 CLOSEOUT SUBMITTALS [NOT USED] 3 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 4 1.9 QUALITY ASSURANCE [NOT USED] 5 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 6 1.11 FIELD [SITE] CONDITIONS [NOT USED] 7 1.12 WARRANTY [NOT USED] 8 PART 2 - PRODUCTS [NOT USED] 9 PART 3 - EXECUTION [NOT USED] 10 END OF SECTION 11 12 Revision Log DATE NAME SUMMARY OF CHANGE 13 01 25 00 SUBSTITUTION PROCEDURES Page 1 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 SECTION 01 25 00 1 SUBSTITUTION PROCEDURES 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. The procedure for requesting the approval of substitution of a product that is not 6 equivalent to a product which is specified by descriptive or performance criteria or 7 defined by reference to 1 or more of the following: 8 a. Name of manufacturer 9 b. Name of vendor 10 c. Trade name 11 d. Catalog number 12 2. Substitutions are not "or-equals". 13 B. Deviations from this City of Denton Standard Specification 14 1. None. 15 C. Related Specification Sections include, but are not necessarily limited to: 16 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 17 2. Division 1 – General Requirements 18 1.2 PRICE AND PAYMENT PROCEDURES 19 A. Measurement and Payment 20 1. Work associated with this Item is considered incidental to the various items bid. 21 No separate payment will be allowed for this Item. 22 1.3 REFERENCES [NOT USED] 23 1.4 ADMINISTRATIVE REQUIREMENTS 24 A. Request for Substitution - General 25 1. Within 30 days after award of Contract (unless noted otherwise), the City will 26 consider formal requests from Contractor for substitution of products in place of 27 those specified. 28 2. Certain types of equipment and kinds of material are described in Specifications by 29 means of references to names of manufacturers and vendors, trade names, or 30 catalog numbers. 31 a. When this method of specifying is used, it is not intended to exclude from 32 consideration other products bearing other manufacturer's or vendor's names, 33 trade names, or catalog numbers, provided said products are "or-equals," as 34 determined by City. 35 3. Other types of equipment and kinds of material may be acceptable substitutions 36 under the following conditions: 37 a. Or-equals are unavailable due to strike, discontinued production of products 38 meeting specified requirements, or other factors beyond control of Contractor; 39 or, 40 01 25 00 SUBSTITUTION PROCEDURES Page 2 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 b. Contractor proposes a cost and/or time reduction incentive to the City. 1 1.5 SUBMITTALS 2 A. See Request for Substitution Form (attached) 3 B. Procedure for Requesting Substitution 4 1. Substitution shall be considered only: 5 a. After award of Contract 6 b. Under the conditions stated herein 7 2. Submit one PDF copy via email to the Project Manager and their duly appointed 8 representative, including: 9 a. Documentation 10 1) Complete data substantiating compliance of proposed substitution with 11 Contract Documents 12 2) Data relating to changes in construction schedule, when a reduction is 13 proposed 14 3) Data relating to changes in cost 15 b. For products 16 1) Product identification 17 a) Manufacturer's name 18 b) Telephone number and representative contact name 19 c) Specification Section or Drawing reference of originally specified 20 product, including discrete name or tag number assigned to original 21 product in the Contract Documents 22 2) Manufacturer's literature clearly marked to show compliance of proposed 23 product with Contract Documents 24 3) Itemized comparison of original and proposed product addressing product 25 characteristics including, but not necessarily limited to: 26 a) Size 27 b) Composition or materials of construction 28 c) Weight 29 d) Electrical or mechanical requirements 30 4) Product experience 31 a) Location of past projects utilizing product 32 b) Name and telephone number of persons associated with referenced 33 projects knowledgeable concerning proposed product 34 c) Available field data and reports associated with proposed product 35 5) Samples 36 a) Provide at request of City. 37 b) Samples become the property of the City. 38 c. For construction methods: 39 1) Detailed description of proposed method 40 2) Illustration drawings 41 C. Approval or Rejection 42 1. Written approval or rejection of substitution given by the City 43 2. City reserves the right to require proposed product to comply with color and pattern 44 of specified product if necessary to secure design intent. 45 3. In the event the substitution is approved, the resulting cost and/or time reduction 46 will be documented by Change Order in accordance with the General Conditions. 47 01 25 00 SUBSTITUTION PROCEDURES Page 3 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 4. No additional contract time will be given for substitution. 1 5. Substitution will be rejected if: 2 a. Submittal is not through the Contractor with his stamp of approval 3 b. Request is not made in accordance with this Specification Section 4 c. In the City’s opinion, acceptance will require substantial revision of the original 5 design 6 d. In the City’s opinion, substitution will not perform adequately the function 7 consistent with the design intent 8 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 9 1.7 CLOSEOUT SUBMITTALS [NOT USED] 10 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 11 1.9 QUALITY ASSURANCE 12 A. In making request for substitution or in using an approved product, the Contractor 13 represents that the Contractor: 14 1. Has investigated proposed product, and has determined that it is adequate or 15 superior in all respects to that specified, and that it will perform function for which 16 it is intended 17 2. Will provide same guarantee for substitute item as for product specified 18 3. Will coordinate installation of accepted substitution into Work, to include building 19 modifications if necessary, making such changes as may be required for Work to be 20 complete in all respects 21 4. Waives all claims for additional costs related to substitution which subsequently 22 arise 23 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 24 1.11 FIELD [SITE] CONDITIONS [NOT USED] 25 1.12 WARRANTY [NOT USED] 26 PART 2 - PRODUCTS [NOT USED] 27 PART 3 - EXECUTION [NOT USED] 28 END OF SECTION 29 30 Revision Log DATE NAME SUMMARY OF CHANGE 31 01 25 00 SUBSTITUTION PROCEDURES Page 4 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 EXHIBIT A 1 REQUEST FOR SUBSTITUTION FORM: 2 3 TO: 4 PROJECT: DATE: 5 We hereby submit for your consideration the following product instead of the specified item for the 6 above project: 7 SECTION PARAGRAPH SPECIFIED ITEM 8 9 10 Proposed Substitution: 11 Reason for Substitution: 12 Include complete information on changes to Drawings and/or Specifications which proposed 13 substitution will require for its proper installation. 14 15 Fill in Blanks Below: 16 A. Will the undersigned contractor pay for changes to the building design, including engineering 17 and detailing costs caused by the requested substitution? 18 19 20 B. What effect does substitution have on other trades? 21 22 23 C. Differences between proposed substitution and specified item? 24 25 26 D. Differences in product cost or product delivery time? 27 28 29 E. Manufacturer's guarantees of the proposed and specified items are: 30 31 Equal Better (explain on attachment) 32 The undersigned states that the function, appearance and quality are equivalent or superior to the 33 specified item. 34 Submitted By: For Use by City 35 36 Signature Recommended Recommended 37 as noted 38 39 Firm Not recommended Received late 40 Address By 41 42 Date 43 Date Remarks 44 45 Telephone 46 47 48 For Use by City: 49 50 01 25 00 SUBSTITUTION PROCEDURES Page 5 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 Approved Rejected 1 City Date 2 3 01 29 76 STORED MATERIALS (MATERIALS ON HAND) Page 1 of 3 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 SECTION 01 29 76 1 STORED MATERIALS AND EQUIPMENT (MATERIALS ON HAND) 2 3 PART 1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. The procedure for requesting payment for stored materials and equipment 7 (materials on hand). 8 B. Deviations from this City of Denton Standard Specification: 9 1. None. 10 C. Related Specification Sections include but are not limited to: 11 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 12 Contract. 13 2. Division 1 - General Requirements. 14 1.2 PRICE AND PAYMENT PROCEDURES 15 A. Measurement and Payment 16 1. Work associated with this item is considered incidental to the various items bid. No 17 separate payment will be allowed for this item. 18 1.3 REFERENCES [NOT USED] 19 1.4 ADMINISTRATIVE REQUIREMENTS 20 A. Request for Payment of Stored Materials and Equipment 21 1. Provide written request to City, if payment is requested on the basis of approved 22 materials and equipment delivered and stored at the Site, or other agreed upon 23 location, in accordance with the Contract Documents, and which will not be 24 incorporated into the Work for a minimum of thirty (30) days from delivery. 25 B. Payment for Materials and Equipment 26 1. Payment will be made in accordance with Article 14 of the General Conditions, less 27 retainage. 28 2. Payment will not exceed the total estimated quantity required to complete the 29 Work. 30 3. The amounts advanced for stored materials and equipment will be deducted from 31 payments to the Contractor as the materials or equipment are incorporated into the 32 Work. 33 4. Payment for stored materials and equipment will not constitute acceptance of the 34 relevant portion of the Work which the materials will be incorporated into. 35 C. Allowed Materials and Equipment 36 01 29 76 STORED MATERIALS (MATERIALS ON HAND) Page 2 of 3 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 1. Payment for stored materials and equipment will be limited to major items 1 associated with the Work. Perishable articles and small warehouse items will not 2 be considered for payment for this item. Examples of major items associated with 3 the Work include the following items: 4 a. 21-Inch carrier pipe, 18-Inch carrier pipe, 36-Inch steel encasing pipe, 30-Inch 5 steel encasing pipe, and 5-foot manholes. 6 2. All items submitted for payment will be subject to approval for payment by relevant 7 City departments and the City Project Manager. 8 D. Returned Materials/Equipment 9 1. Should stored materials/equipment that have been paid for under this Section need 10 to be returned for any reason, the Contractor shall bear any fees associated with the 11 return. 12 E. Contractor shall save the City harmless in the event of loss or damage of 13 materials/equipment for which advance payments have been made in accordance with 14 this Section. 15 1.5 SUBMITTALS 16 A. Provide a certified inventory of the quantity of each stored item and accompanying 17 invoice. 18 B. Within thirty (30) days after the Contractor receives payment for stored materials or 19 equipment, provide a copy of a certified paid invoice statement for each item for which 20 payment has been made by Contractor. 21 1. If certification of payment is not presented within the thirty (30) day period, the 22 advanced payment will be deducted from the next progress payment. 23 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 24 1.7 CLOSEOUT SUBMITTALS [NOT USED] 25 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 26 1.9 QUALITY ASSURANCE [NOT USED] 27 1.10 DELIVERY, STORAGE, AND HANDLING 28 A. Delivery and Acceptance Requirements 29 B. Storage and Handling Requirements 30 1. Secure and maintain a location to store the materials and equipment in accordance 31 with Section 01 66 00. 32 01 29 76 STORED MATERIALS (MATERIALS ON HAND) Page 3 of 3 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 1.11 FIELD CONDITIONS [NOT USED] 1 1.12 WARRANTY [NOT USED] 2 PART 2 - PRODUCTS [NOT USED] 3 PART 3 - EXECUTION [NOT USED] 4 END OF SECTION 5 6 Revision Log DATE NAME SUMMARY OF CHANGE 7 01 31 19 PRECONSTRUCTION MEETING Page 1 of 3 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 SECTION 01 31 19 1 PRECONSTRUCTION MEETING 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Provisions for the preconstruction meeting to be held prior to the start of Work to 6 clarify construction contract administration procedures 7 B. Deviations from this City of Denton Standard Specification 8 1. None. 9 C. Related Specification Sections include, but are not necessarily limited to: 10 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 11 2. Division 1 – General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Work associated with this Item is considered incidental to the various items bid. 15 No separate payment will be allowed for this Item. 16 1.3 REFERENCES [NOT USED] 17 1.4 ADMINISTRATIVE REQUIREMENTS 18 A. Coordination 19 1. Attend preconstruction meeting. 20 2. Representatives of Contractor, subcontractors and suppliers attending meetings 21 shall be qualified and authorized to act on behalf of the entity each represents. 22 3. Meeting administered by City may be tape recorded. 23 a. If recorded, tapes will be used to prepare minutes and retained by City for 24 future reference. 25 4. Project Manager will establish their duly authorized representative(s) authorized to 26 make decisions as identified in the Contract Documents. 27 B. Preconstruction Meeting 28 1. A preconstruction meeting will be held within 14 days after the execution of the 29 Agreement and before Work is started. 30 a. The meeting will be scheduled and administered by the City. 31 2. The Project Manager will preside at the meeting, prepare the notes of the meeting 32 and distribute copies of same to all participants who so request by fully completing 33 the attendance form to be circulated at the beginning of the meeting. 34 3. Attendance shall include: 35 a. Project Manager 36 b. Project Manager’s duly authorized representative (if any) 37 c. Contractor's project manager 38 01 31 19 PRECONSTRUCTION MEETING Page 2 of 3 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 d. Contractor's superintendent 1 e. Any subcontractor or supplier representatives whom the Contractor may desire 2 to invite or the City may request 3 f. Other City representatives 4 g. Others as appropriate 5 4. Construction Schedule 6 a. Prepare baseline construction schedule in accordance with Section 01 32 16 and 7 provide at Preconstruction Meeting. 8 b. City will notify Contractor of any schedule changes upon Notice of 9 Preconstruction Meeting. 10 5. Preliminary Agenda may include: 11 a. Introduction of Project Personnel 12 b. General Description of Project 13 c. Status of right-of-way, utility clearances, easements or other pertinent permits 14 d. Contractor’s work plan and schedule 15 e. Contract Time 16 f. Notice to Proceed 17 g. Construction Staking 18 h. Progress Payments 19 i. Extra Work and Change Order Procedures 20 j. Field Orders 21 k. Disposal Site Letter for Waste Material 22 l. Insurance Renewals 23 m. Payroll Certification 24 n. Material Certifications and Quality Control Testing 25 o. Public Safety and Convenience 26 p. Documentation of Pre-Construction Conditions 27 q. Weekend Work Notification 28 r. Legal Holidays 29 s. Trench Safety Plans 30 t. Confined Space Entry Standards 31 u. Coordination with the City’s representative for operations of existing water 32 systems 33 v. Storm Water Pollution Prevention Plan 34 w. Coordination with other Contractors 35 x. Early Warning System 36 y. Contractor Evaluation 37 z. Special Conditions applicable to the project 38 aa. Damages Claims 39 bb. Submittal Procedures 40 cc. Substitution Procedures 41 dd. Correspondence Routing 42 ee. Record Drawings 43 ff. Temporary construction facilities 44 gg. Final Acceptance 45 hh. Final Payment 46 ii. Communications Plan 47 jj. Questions or Comments 48 01 31 19 PRECONSTRUCTION MEETING Page 3 of 3 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 1.5 SUBMITTALS [NOT USED] 1 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 2 1.7 CLOSEOUT SUBMITTALS [NOT USED] 3 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 4 1.9 QUALITY ASSURANCE [NOT USED] 5 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 6 1.11 FIELD [SITE] CONDITIONS [NOT USED] 7 1.12 WARRANTY [NOT USED] 8 PART 2 - PRODUCTS [NOT USED] 9 PART 3 - EXECUTION [NOT USED] 10 END OF SECTION 11 12 Revision Log DATE NAME SUMMARY OF CHANGE 13 01 31 20 PROJECT MEETINGS Page 1 of 3 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 SECTION 01 31 20 1 PROJECT MEETINGS 2 3 PART 1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Provisions for project meetings throughout the construction period to enable orderly 7 review of the progress of the Work and to provide for systematic discussion of 8 potential problems 9 B. Deviations this City of Denton Standard Specification 10 1. None. 11 C. Related Specification Sections include, but are not necessarily limited to: 12 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 13 2. Division 1 – General Requirements 14 1.2 PRICE AND PAYMENT PROCEDURES 15 A. Measurement and Payment 16 1. Work associated with this Item is considered incidental to the various items bid. 17 No separate payment will be allowed for this Item. 18 1.3 REFERENCES [NOT USED] 19 1.4 ADMINISTRATIVE REQUIREMENTS 20 A. Coordination 21 1. Schedule, attend and administer as specified, periodic progress meetings, and 22 specially called meetings throughout progress of the Work. 23 2. Representatives of Contractor, subcontractors and suppliers attending meetings 24 shall be qualified and authorized to act on behalf of the entity each represents. 25 3. Meetings administered by City may be recorded. 26 4. Meetings, in addition to those specified in this Section, may be held when requested 27 by the City, Engineer or Contractor. 28 B. Progress Meetings 29 1. Formal project coordination meetings will be held _________________. Meetings 30 will be scheduled and administered by Project Manager. 31 a. Additional meetings may be held at the request of the : 32 1) City 33 2) Engineer 34 3) Contractor 35 2. Additional progress meetings to discuss specific topics will be conducted on an as-36 needed basis. Such additional meetings shall include, but not be limited to: 37 a. Coordinating shutdowns 38 01 31 20 PROJECT MEETINGS Page 2 of 3 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 b. Installation of piping and equipment 1 c. Coordination between other construction projects 2 d. Resolution of construction issues 3 e. Equipment approval 4 3. The Project Manager will preside at progress meetings, prepare the notes of the 5 meeting and distribute copies of the same to all participants who so request by fully 6 completing the attendance form to be circulated at the beginning of each meeting. 7 4. Attendance shall include: 8 a. Contractor's project manager 9 b. Contractor's superintendent 10 c. Any subcontractor or supplier representatives whom the Contractor may desire 11 to invite or the City may request 12 d. Engineer's representatives 13 e. City’s representatives 14 f. Others, as requested by the Project Manager 15 5. Preliminary Agenda may include: 16 a. Review of Work progress since previous meeting 17 b. Field observations, problems, conflicts 18 c. Items which impede construction schedule 19 d. Review of off-site fabrication, delivery schedules 20 e. Review of construction interfacing and sequencing requirements with other 21 construction contracts 22 f. Corrective measures and procedures to regain projected schedule 23 g. Revisions to construction schedule 24 h. Progress, schedule, during succeeding Work period 25 i. Coordination of schedules 26 j. Review submittal schedules 27 k. Maintenance of quality standards 28 l. Pending changes and substitutions 29 m. Review proposed changes for: 30 1) Effect on construction schedule and on completion date 31 2) Effect on other contracts of the Project 32 n. Review Record Documents 33 o. Review monthly pay request 34 p. Review status of Requests for Information 35 6. Meeting Location 36 a. The City will establish a meeting location. 37 1) To the extent practicable, meetings will be held at the Site. 38 01 31 20 PROJECT MEETINGS Page 3 of 3 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 1.5 SUBMITTALS [NOT USED] 1 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 2 1.7 CLOSEOUT SUBMITTALS [NOT USED] 3 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 4 1.9 QUALITY ASSURANCE [NOT USED] 5 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 6 1.11 FIELD [SITE] CONDITIONS [NOT USED] 7 1.12 WARRANTY [NOT USED] 8 PART 2 - PRODUCTS [NOT USED] 9 PART 3 - EXECUTION [NOT USED] 10 END OF SECTION 11 12 Revision Log DATE NAME SUMMARY OF CHANGE 13 01 32 16 CONSTRUCTION PROGRESS SCHEDULE Page 1 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 SECTION 01 32 16 1 CONSTRUCTION PROGRESS SCHEDULE 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. General requirements for the preparation, submittal, updating, status reporting and 6 management of the Construction Progress Schedule 7 B. Deviations from this City of Denton Standard Specification 8 1. None. 9 C. Related Specification Sections include, but are not necessarily limited to: 10 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 11 2. Division 1 – General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Work associated with this Item is considered incidental to the various items bid. 15 No separate payment will be allowed for this Item. 16 1.3 REFERENCES 17 A. Definitions 18 1. Baseline Schedule - Initial schedule submitted before work begins that will serve 19 as the baseline for measuring progress and departures from the schedule. 20 2. Progress Schedule - Monthly submittal of a progress schedule documenting 21 progress on the project and any changes anticipated. 22 3. Schedule Narrative - Concise narrative of the schedule including schedule 23 changes, expected delays, key schedule issues, critical path items, etc 24 B. Reference Standards 25 1. None 26 1.4 ADMINISTRATIVE REQUIREMENTS 27 A. Baseline Schedule 28 1. General 29 a. Prepare a baseline Schedule using approved software and the Critical Path 30 Method (CPM). 31 b. Review the draft baseline Schedule with the City to demonstrate understanding 32 of the work to be performed and known issues and constraints related to the 33 schedule. 34 c. Designate an authorized representative (Project Scheduler) responsible for 35 developing and updating the schedule and preparing reports. 36 B. Progress Schedule 37 38 01 32 16 CONSTRUCTION PROGRESS SCHEDULE Page 2 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 1. Update the progress Schedule monthly. 1 2. Prepare the Schedule Narrative to accompany the monthly progress Schedule. 2 3. Change Orders 3 a. Incorporate approved change orders, resulting in a change of contract time, in 4 the baseline Schedule. 5 C. Responsibility for Schedule Compliance 6 1. Whenever it becomes apparent from the current progress Schedule and CPM Status 7 Report that delays to the critical path have resulted and the Contract completion 8 date will not be met, or when so directed by the City, make some or all of the 9 following actions at no additional cost to the City 10 a. Submit a Recovery Plan to the City for approval revised baseline Schedule 11 outlining: 12 1) A written statement of the steps intended to take to remove or arrest the 13 delay to the critical path in the approved schedule 14 2) Increase construction manpower in such quantities and crafts as will 15 substantially eliminate the backlog of work and return current Schedule to 16 meet projected baseline completion dates 17 3) Increase the number of working hours per shift, shifts per day, working 18 days per week, the amount of construction equipment, or any combination 19 of the foregoing, sufficiently to substantially eliminate the backlog of work 20 4) Reschedule activities to achieve maximum practical concurrency of 21 accomplishment of activities, and comply with the revised schedule 22 2. If no written statement of the steps intended to take is submitted when so requested 23 by the City, the City may direct the Contractor to increase the level of effort in 24 manpower (trades), equipment and work schedule (overtime, weekend and holiday 25 work, etc.) to be employed by the Contractor in order to remove or arrest the delay 26 to the critical path in the approved schedule. 27 a. No additional cost for such work will be considered. 28 D. The Contract completion time will be adjusted only for causes specified in this 29 Contract. 30 a. Requests for an extension of any Contract completion date must be 31 supplemented with the following: 32 1) Furnish justification and supporting evidence as the City may deem 33 necessary to determine whether the requested extension of time is entitled 34 under the provisions of this Contract. 35 a) The City will, after receipt of such justification and supporting 36 evidence, make findings of fact and will advise the Contractor, in 37 writing thereof. 38 2) If the City finds that the requested extension of time is entitled, the City's 39 determination as to the total number of days allowed for the extensions 40 shall be based upon the approved total baseline schedule and on all data 41 relevant to the extension. 42 a) Such data shall be included in the next updating of the Progress 43 schedule. 44 b) Actual delays in activities which, according to the Baseline schedule, 45 do not affect any Contract completion date shown by the critical path in 46 the network will not be the basis for a change therein. 47 01 32 16 CONSTRUCTION PROGRESS SCHEDULE Page 3 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 2. Submit each request for change in Contract completion date to the City within 30 1 days after the beginning of the delay for which a time extension is requested but 2 before the date of final payment under this Contract. 3 a. No time extension will be granted for requests which are not submitted within 4 the foregoing time limit. 5 b. From time to time, it may be necessary for the Contract schedule or completion 6 time to be adjusted by the City to reflect the effects of job conditions, weather, 7 technical difficulties, strikes, unavoidable delays on the part of the City or its 8 representatives, and other unforeseeable conditions which may indicate 9 schedule adjustments or completion time extensions. 10 1) Under such conditions, the City will direct the Contractor to reschedule the 11 work or Contract completion time to reflect the changed conditions and the 12 Contractor shall revise his schedule accordingly. 13 a) No additional compensation will be made to the Contractor for such 14 schedule changes except for unavoidable overall contract time 15 extensions beyond the actual completion of unaffected work, in which 16 case the Contractor shall take all possible action to minimize any time 17 extension and any additional cost to the City. 18 b) Available float time in the Baseline schedule may be used by the City 19 as well as by the Contractor. 20 3. Float or slack time is defined as the amount of time between the earliest start date 21 and the latest start date or between the earliest finish date and the latest finish date 22 of a chain of activities on the Baseline Schedule. 23 a. Float or slack time is not for the exclusive use or benefit of either the 24 Contractor or the City. 25 b. Proceed with work according to early start dates, and the City shall have the 26 right to reserve and apportion float time according to the needs of the project. 27 c. Acknowledge and agree that actual delays, affecting paths of activities 28 containing float time, will not have any effect upon contract completion times, 29 providing that the actual delay does not exceed the float time associated with 30 those activities. 31 E. Coordinating Schedule with Other Contract Schedules 32 1. Where work is to be performed under this Contract concurrently with or contingent 33 upon work performed on the same facilities or area under other contracts, the 34 Baseline Schedule shall be coordinated with the schedules of the other contracts. 35 a. Obtain the schedules of the other appropriate contracts from the City for the 36 preparation and updating of Baseline schedule and make the required changes 37 in his schedule when indicated by changes in corresponding schedules. 38 2. In case of interference between the operations of different contractors, the City will 39 determine the work priority of each contractor and the sequence of work necessary 40 to expedite the completion of the entire Project. 41 a. In such cases, the decision of the City shall be accepted as final. 42 b. The temporary delay of any work due to such circumstances shall not be 43 considered as justification for claims for additional compensation. 44 1.5 SUBMITTALS 45 A. Baseline Schedule 46 1. Submit Schedule in native file format and pdf format. 47 01 32 16 CONSTRUCTION PROGRESS SCHEDULE Page 4 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 a. Native file format shall be: 1 1) Microsoft Project 2 2. Submit draft baseline Schedule to City prior to the pre-construction meeting and 3 bring in hard copy to the meeting for review and discussion. 4 B. Progress Schedule 5 1. Submit progress Schedule in native file format and pdf format. 6 2. Submit progress Schedule monthly no later than the 25th day of the month. 7 C. Schedule Narrative 8 1. Submit the schedule narrative in pdf format. 9 2. Submit schedule narrative monthly no later than the 25th day of the month. 10 D. Submittal Process 11 1. 12 2. Contractor shall submit one (1) hard copy of documents to the Project Manager’s 13 duly appointed representative. 14 3. Contractor shall submit documents via email to the Project Manager and their duly 15 appointed representative. 16 4. Once the project has been completed and Final Acceptance has been issued by the 17 City, no further progress schedules are required. 18 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 19 1.7 CLOSEOUT SUBMITTALS [NOT USED] 20 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 21 1.9 QUALITY ASSURANCE 22 A. The person preparing and revising the construction Progress Schedule shall be 23 experienced in the preparation of schedules of similar complexity. 24 B. Schedule and supporting documents addressed in this Specification shall be prepared, 25 updated and revised to accurately reflect the performance of the construction. 26 C. Contractor is responsible for the quality of all submittals in this section meeting the 27 standard of care for the construction industry for similar projects. 28 01 32 16 CONSTRUCTION PROGRESS SCHEDULE Page 5 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1 1.11 FIELD [SITE] CONDITIONS [NOT USED] 2 1.12 WARRANTY [NOT USED] 3 PART 2 - PRODUCTS [NOT USED] 4 PART 3 - EXECUTION [NOT USED] 5 6 END OF SECTION 7 Revision Log DATE NAME SUMMARY OF CHANGE 8 01 32 33 PRECONSTRUCTION VIDEO Page 1 of 2 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 SECTION 01 32 33 1 PRECONSTRUCTION VIDEO 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Administrative and procedural requirements for: 6 a. Preconstruction Videos 7 B. Deviations from this City of Denton Standard Specification 8 1. None. 9 C. Related Specification Sections include, but are not necessarily limited to: 10 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 11 2. Division 1 – General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Work associated with this Item is considered incidental to the various items bid. 15 No separate payment will be allowed for this Item. 16 1.3 REFERENCES [NOT USED] 17 1.4 ADMINISTRATIVE REQUIREMENTS 18 A. Preconstruction Video 19 1. Produce a preconstruction video of the site/alignment, including all areas in the 20 vicinity of and to be affected by construction. 21 a. Provide digital copy of video upon request by the City. 22 2. Retain a copy of the preconstruction video until the end of the maintenance surety 23 period. 24 1.5 SUBMITTALS [NOT USED] 25 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 26 1.7 CLOSEOUT SUBMITTALS [NOT USED] 27 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 28 1.9 QUALITY ASSURANCE [NOT USED] 29 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 30 1.11 FIELD [SITE] CONDITIONS [NOT USED] 31 1.12 WARRANTY [NOT USED] 32 PART 2 - PRODUCTS [NOT USED] 33 01 32 33 PRECONSTRUCTION VIDEO Page 2 of 2 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 PART 3 - EXECUTION [NOT USED] 1 END OF SECTION 2 3 Revision Log DATE NAME SUMMARY OF CHANGE 4 01 33 00 SUBMITTALS Page 1 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENT Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 SECTION 01 33 00 1 SUBMITTALS 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. General methods and requirements of submissions applicable to the following 6 Work-related submittals: 7 a. Shop Drawings 8 b. Product Data (including Project Material Submittal Checklist submittals) 9 c. Samples 10 d. Mock Ups 11 B. Deviations from this City of Denton Standard Specification 12 1. None. 13 C. Related Specification Sections include, but are not necessarily limited to: 14 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 15 2. Division 1 – General Requirements 16 1.2 PRICE AND PAYMENT PROCEDURES 17 A. Measurement and Payment 18 1. Work associated with this Item is considered incidental to the various items bid. No 19 separate payment will be allowed for this Item. 20 1.3 REFERENCES [NOT USED] 21 1.4 ADMINISTRATIVE REQUIREMENTS 22 A. Coordination 23 1. Notify the City in writing, at the time of submittal, of any deviations in the 24 submittals from the requirements of the Contract Documents. 25 2. Coordination of Submittal Times 26 a. Prepare, prioritize and transmit each submittal sufficiently in advance of 27 performing the related Work or other applicable activities, or within the time 28 specified in the individual Work Sections, of the Specifications. 29 b. Contractor is responsible such that the installation will not be delayed by 30 processing times including, but not limited to: 31 a) Disapproval and resubmittal (if required) 32 b) Coordination with other submittals 33 c) Testing 34 d) Purchasing 35 01 33 00 SUBMITTALS Page 2 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENT Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 e) Fabrication 1 f) Delivery 2 g) Similar sequenced activities 3 c. No extension of time will be authorized because of the Contractor's failure to 4 transmit submittals sufficiently in advance of the Work. 5 d. Make submittals promptly in accordance with approved schedule, and in such 6 sequence as to cause no delay in the Work or in the work of any other 7 contractor. 8 B. Submittal Numbering 9 1. When submitting shop drawings or samples, utilize a submittal cross-reference 10 identification numbering system in the following manner: 11 a. Use the applicable Specification Section Number. 12 b. For the next 2 digits number use numbers 01-99 to sequentially number each 13 initial separate item or drawing submitted under each specific Section number. 14 c. Last use a letter, A-Z, indicating the resubmission of the same drawing (i.e. 15 A=2nd submission, B=3rd submission, C=4th submission, etc.). A typical 16 submittal number would be as follows: 17 18 303-02-B 19 20 1) 303 is the Specification Section for Portland Cement Concrete Pavement 21 2) 02 is the second initial submittal under this Specification Section 22 3) B is the third submission (second resubmission) of that particular shop 23 drawing 24 C. Contractor Certification 25 1. Review shop drawings, product data and samples, including those by 26 subcontractors, prior to submission to determine and verify the following: 27 a. Field measurements 28 b. Field construction criteria 29 c. Catalog numbers and similar data 30 d. Conformance with the Contract Documents 31 2. Provide each shop drawing, sample and product data submitted by the Contractor 32 with a Certification Statement affixed including: 33 a. The Contractor's Company name 34 b. Signature of submittal reviewer 35 c. Certification Statement 36 1) “By this submittal, I hereby represent that I have determined and verified 37 field measurements, field construction criteria, materials, dimensions, 38 catalog numbers and similar data and I have checked and coordinated each 39 item with other applicable approved shop drawings." 40 D. Submittal Format 41 01 33 00 SUBMITTALS Page 3 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENT Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 1. Fold shop drawings larger than 8 ½ inches x 11 inches to 8 ½ inches x 11inches. 1 2. Bind shop drawings and product data sheets together. 2 3. Order 3 a. Cover Sheet 4 1) Description of Packet 5 2) Contractor Certification 6 b. List of items / Table of Contents 7 c. Product Data /Shop Drawings/Samples /Calculations 8 E. Submittal Content 9 1. The date of submission and the dates of any previous submissions 10 2. The Project title and number 11 3. Contractor identification 12 4. The names of: 13 a. Contractor 14 b. Supplier 15 c. Manufacturer 16 5. Identification of the product, with the Specification Section number, page and 17 paragraph(s) 18 6. Field dimensions, clearly identified as such 19 7. Relation to adjacent or critical features of the Work or materials 20 8. Applicable standards, such as ASTM or Federal Specification numbers 21 9. Identification by highlighting of deviations from Contract Documents 22 10. Identification by highlighting of revisions on resubmittals 23 11. An 8-inch x 3-inch blank space for Contractor and City stamps 24 F. Shop Drawings 25 1. As specified in individual Work Sections includes, but is not necessarily limited to: 26 a. Custom-prepared data such as fabrication and erection/installation (working) 27 drawings 28 b. Scheduled information 29 c. Setting diagrams 30 d. Actual shopwork manufacturing instructions 31 e. Custom templates 32 f. Special wiring diagrams 33 g. Coordination drawings 34 h. Individual system or equipment inspection and test reports including: 35 1) Performance curves and certifications 36 i. As applicable to the Work 37 2. Details 38 01 33 00 SUBMITTALS Page 4 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENT Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 a. Relation of the various parts to the main members and lines of the structure 1 b. Where correct fabrication of the Work depends upon field measurements 2 1) Provide such measurements and note on the drawings prior to submitting 3 for approval. 4 G. Product Data 5 1. For submittals of product data for products included on the City’s Product Material 6 Submittal Checklist, highlight each item selected for use on the Project. 7 2. For submittals of product data for products not included on the City’s Product 8 Material Submittal Checklist, submittal data may include, but is not necessarily 9 limited to: 10 a. Standard prepared data for manufactured products (sometimes referred to as 11 catalog data) 12 1) Such as the manufacturer's product specification and installation 13 instructions 14 2) Availability of colors and patterns 15 3) Manufacturer's printed statements of compliances and applicability 16 4) Roughing-in diagrams and templates 17 5) Catalog cuts 18 6) Product photographs 19 7) Standard wiring diagrams 20 8) Printed performance curves and operational-range diagrams 21 9) Production or quality control inspection and test reports and certifications 22 10) Mill reports 23 11) Product operating and maintenance instructions and recommended 24 spare-parts listing and printed product warranties 25 12) As applicable to the Work 26 3. Submittals of product data for products not included on the City’s Product Material 27 Submittal Checklist may be considered a Substitution in accordance with Section 28 01 25 00. 29 4. All deviations from City’s Product Material Submittal Checklist shall require 30 approval by the Engineer of Record for the Project. 31 H. Samples 32 1. As specified in individual Sections, include, but are not necessarily limited to: 33 a. Physical examples of the Work such as: 34 1) Sections of manufactured or fabricated Work 35 2) Small cuts or containers of materials 36 3) Complete units of repetitively used products color/texture/pattern swatches 37 and range sets 38 4) Specimens for coordination of visual effect 39 01 33 00 SUBMITTALS Page 5 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENT Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 5) Graphic symbols and units of Work to be used by the City for independent 1 inspection and testing, as applicable to the Work 2 I. Do not start Work requiring a shop drawing, sample or product data nor any material to 3 be fabricated or installed prior to the approval or qualified approval of such item. 4 1. Fabrication performed, materials purchased or on-site construction accomplished 5 which does not conform to approved shop drawings and data is at the Contractor's 6 risk. 7 2. The City will not be liable for any expense or delay due to corrections or remedies 8 required to accomplish conformity. 9 3. Complete project Work, materials, fabrication, and installations in conformance 10 with approved shop drawings, applicable samples, and product data. 11 J. Submittal Distribution 12 1. Electronic Distribution 13 a. Provide all submittals in electronic form via email to Project Manager and their 14 duly appointed representative. 15 b. Shop Drawings 16 1) Email submittal to Project Manager and their duly appointed representative. 17 2) Hard Copies 18 a) Not required 19 c. Product Data 20 1) Email submittal to Project Manager and their duly appointed representative. 21 2) Hard Copies 22 a) Not required 23 d. Samples 24 1) Distributed to the Project Manager 25 K. Submittal Review 26 1. The review of shop drawings, data and samples will be for general conformance 27 with the design concept and Contract Documents. This is not to be construed as: 28 a. Permitting any departure from the Contract requirements 29 b. Relieving the Contractor of responsibility for any errors, including details, 30 dimensions, and materials 31 c. Approving departures from details furnished by the City, except as otherwise 32 provided herein 33 2. The review and approval of shop drawings, samples or product data by the City 34 does not relieve the Contractor from his/her responsibility with regard to the 35 fulfillment of the terms of the Contract. 36 a. All risks of error and omission are assumed by the Contractor, and the City will 37 have no responsibility therefore. 38 01 33 00 SUBMITTALS Page 6 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENT Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 3. The Contractor remains responsible for details and accuracy, for coordinating the 1 Work with all other associated work and trades, for selecting fabrication processes, 2 for techniques of assembly and for performing Work in a safe manner. 3 4. If the shop drawings, data or samples as submitted describe variations and show a 4 departure from the Contract requirements which City finds to be in the interest of 5 the City and to be so minor as not to involve a change in Contract Price or time for 6 performance, the City may return the reviewed drawings without noting an 7 exception. 8 5. Submittals will be returned to the Contractor under 1 of the following codes: 9 a. Code 1 10 1) "NO EXCEPTIONS TAKEN" is assigned when there are no notations or 11 comments on the submittal. 12 a) When returned under this code the Contractor may release the 13 equipment and/or material for manufacture. 14 b. Code 2 15 1) "EXCEPTIONS NOTED". This code is assigned when a confirmation of 16 the notations and comments IS NOT required by the Contractor. 17 a) The Contractor may release the equipment or material for manufacture; 18 however, all notations and comments must be incorporated into the 19 final product. 20 c. Code 3 21 1) "EXCEPTIONS NOTED/RESUBMIT". This combination of codes is 22 assigned when notations and comments are extensive enough to require a 23 resubmittal of the package. 24 a) This resubmittal is to address all comments, omissions and 25 non-conforming items that were noted. 26 b) Resubmittal is to be received by the City within 15 Calendar Days of 27 the date of the City's transmittal requiring the resubmittal. 28 d. Code 4 29 1) "NOT APPROVED" is assigned when the submittal does not meet the 30 intent of the Contract Documents. 31 a) The Contractor must resubmit the entire package revised to bring the 32 submittal into conformance. 33 b) It may be necessary to resubmit using a different manufacturer/vendor 34 to meet the Contract Documents. 35 6. Resubmittals 36 a. Handled in the same manner as first submittals 37 1) Corrections other than requested by the City 38 2) Marked with revision triangle or other similar method 39 a) At Contractor’s risk if not marked 40 01 33 00 SUBMITTALS Page 7 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENT Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 b. Submittals for each item will be reviewed no more than twice at the City’s 1 expense. 2 1) All subsequent reviews will be performed at times convenient to the City 3 and at the Contractor's expense, based on the City's or City Representative’s 4 then prevailing rates. 5 2) Provide Contractor reimbursement to the City within 30 Calendar Days for 6 all such fees invoiced by the City. 7 c. The need for more than 1 resubmission or any other delay in obtaining City's 8 review of submittals, will not entitle the Contractor to an extension of Contract 9 Time. 10 7. Partial Submittals 11 a. City reserves the right to not review submittals deemed partial, at the City’s 12 discretion. 13 b. Submittals deemed by the City to be not complete will be returned to the 14 Contractor, and will be considered "Not Approved" until resubmitted. 15 c. The City may at its option provide a list or mark the submittal directing the 16 Contractor to the areas that are incomplete. 17 8. If the Contractor considers any correction indicated on the shop drawings to 18 constitute a change to the Contract Documents, then written notice must be 19 provided thereof to the City at least 7 Calendar Days prior to release for 20 manufacture. 21 9. When the shop drawings have been completed to the satisfaction of the City, the 22 Contractor may carry out the construction in accordance therewith and no further 23 changes therein except upon written instructions from the City. 24 10. Each submittal, appropriately coded, will be returned within 30 Calendar Days 25 following receipt of submittal by the City. 26 L. Mock ups 27 1. Mock Up units as specified in individual Sections, include, but are not necessarily 28 limited to, complete units of the standard of acceptance for that type of Work to be 29 used on the Project. Remove at the completion of the Work or when directed. 30 M. Qualifications 31 1. If specifically required in other Sections of these Specifications, submit a P.E. 32 Certification for each item required. 33 N. Request for Information (RFI) 34 1. Contractor Request for additional information 35 a. Clarification or interpretation of the contract documents 36 b. When the Contractor believes there is a conflict between Contract Documents 37 c. When the Contractor believes there is a conflict between the Drawings and 38 Specifications 39 01 33 00 SUBMITTALS Page 8 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENT Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 1) Identify the conflict and request clarification 1 d. When the Contractor encounters an unknown condition in the field 2 2. Use the Request for Information (RFI) form provided by the City (attached). 3 3. Numbering of RFI 4 a. Prefix with “RFI” followed by series number, “-xxx”, beginning with “01” and 5 increasing sequentially with each additional transmittal. 6 4. Sufficient information shall be attached to permit a written response without further 7 information. 8 5. The City will log each request and will review the request. 9 a. If review of the project information request indicates that a change to the 10 Contract Documents is required, the City will issue a Field Order or Change 11 Order, as appropriate. 12 1.5 SUBMITTALS [NOT USED] 13 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 14 1.7 CLOSEOUT SUBMITTALS [NOT USED] 15 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 16 1.9 QUALITY ASSURANCE [NOT USED] 17 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 18 1.11 FIELD [SITE] CONDITIONS [NOT USED] 19 1.12 WARRANTY [NOT USED] 20 PART 2 - PRODUCTS [NOT USED] 21 PART 3 - EXECUTION [NOT USED] 22 END OF SECTION 23 Revision Log DATE NAME SUMMARY OF CHANGE 24 01 33 00 SUBMITTALS Page 9 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENT Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 REQUEST FOR INFORMATION 1 2 Project: RFI #: Engineering Project No.: Date Sent: Sender: Receiver: Copies To: 3 Subject: Request: Sender’s Proposed Answer/Solution: 4 THE PROPOSED ANSWER/SOLUTION IS, IS NOT, INCLUDED IN THE 5 CONTRACT. 6 7 Receiver’s Response: 8 Response By: Company: Date: 01 33 00 SUBMITTALS Page 10 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENT Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 1 DISTRIBUTION: 2 01 35 13 SPECIAL PROJECT PROCEDURES Page 1 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 SECTION 01 35 13 1 SPECIAL PROJECT PROCEDURES 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. The procedures for special project circumstances that includes, but is not limited to: 6 a. Coordination with the Texas Department of Transportation 7 b. Work near High Voltage Lines 8 c. Confined Space Entry Program 9 d. Excavation Protection 10 e. Air Pollution Watch Days 11 f. Use of Explosives, Drop Weight, Etc. 12 g. Water Utilities Notification 13 h. Public Notification Prior to Beginning Construction 14 i. Coordination with United States Army Corps of Engineers 15 j. Coordination within Railroad permits areas 16 k. Dust Control 17 l. Employee Parking 18 m. Coordination with North Central Texas Council of Governments Clean 19 Construction Specification 20 n. Tree Protection 21 B. Deviations from this City of Denton Standard Specification 22 1. None. 23 C. Related Specification Sections include, but are not necessarily limited to: 24 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 25 2. Division 1 – General Requirements 26 1.2 PRICE AND PAYMENT PROCEDURES 27 A. Measurement and Payment 28 1. Coordination within Railroad permit areas 29 a. Measurement 30 1) Measurement for this Item will be by lump sum. 31 b. Payment 32 1) The work performed and materials furnished in accordance with this Item 33 will be paid for at the lump sum price bid for Railroad Coordination. 34 c. The price bid shall include: 35 1) Mobilization 36 2) Inspection 37 3) Safety training 38 4) Additional Insurance 39 5) Insurance Certificates 40 01 35 13 SPECIAL PROJECT PROCEDURES Page 2 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 6) Other requirements associated with general coordination with Railroad, 1 including additional employees required to protect the right-of-way and 2 property of the Railroad from damage arising out of and/or from the 3 construction of the Project. 4 2. Railroad Flagmen 5 a. Measurement 6 1) Measurement for this Item will be per working day. 7 b. Payment 8 1) The work performed and materials furnished in accordance with this Item 9 will be paid for each working day that Railroad Flagmen are present at the 10 Site. 11 c. The price bid shall include: 12 1) Coordination for scheduling flagmen 13 2) Flagmen 14 3) Other requirements associated with Railroad 15 3. All other items 16 a. Work associated with these Items is considered incidental to the various Items 17 bid. No separate payment will be allowed for this Item. 18 1.3 REFERENCES 19 A. Reference Standards 20 1. Reference standards cited in this Specification refer to the current reference 21 standard published at the time of the latest revision date logged at the end of this 22 Specification, unless a date is specifically cited. 23 2. Health and Safety Code, Title 9. Safety, Subtitle A. Public Safety, Chapter 752. 24 High Voltage Overhead Lines. 25 3. North Central Texas Council of Governments (NCTCOG) – Clean Construction 26 Specification 27 4. Occupational Health and Safety Administration (OSHA) Standards – 29 CFR Part 28 1910.146 – Permit-Required Confined Spaces 29 1.4 ADMINISTRATIVE REQUIREMENTS 30 A. Coordination with the Texas Department of Transportation 31 1. When work in the right-of-way which is under the jurisdiction of the Texas 32 Department of Transportation (TxDOT): 33 a. Notify the Texas Department of Transportation prior to commencing any work 34 therein in accordance with the provisions of the permit 35 b. All work performed in the TxDOT right-of-way shall be performed in 36 compliance with and subject to approval from the Texas Department of 37 Transportation 38 B. Work near High Voltage Lines 39 1. Regulatory Requirements 40 a. All Work near High Voltage Lines (more than 600 volts measured between 41 conductors or between a conductor and the ground) shall be in accordance with 42 Health and Safety Code, Title 9, Subtitle A, Chapter 752. 43 2. Warning sign 44 a. Provide sign of sufficient size meeting all OSHA requirements. 45 01 35 13 SPECIAL PROJECT PROCEDURES Page 3 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 3. Equipment operating within 10 feet of high voltage lines will require the following 1 safety features 2 a. Insulating cage-type of guard about the boom or arm 3 b. Insulator links on the lift hook connections for back hoes or dippers 4 c. Equipment must meet the safety requirements as set forth by OSHA and the 5 safety requirements of the owner of the high voltage lines 6 4. Work within 6 feet of high voltage electric lines 7 a. Notification shall be given to: 8 1) The power company (example: Denton Municipal Electric) 9 a) Maintain an accurate log of all such calls to power company and record 10 action taken in each case. 11 b. Coordination with power company 12 1) After notification coordinate with the power company to: 13 a) Erect temporary mechanical barriers, de-energize the lines, or raise or 14 lower the lines 15 c. No personnel may work within 6 feet of a high voltage line before the above 16 requirements have been met. 17 C. Confined Space Entry Program 18 1. Provide and follow approved Confined Space Entry Program in accordance with 19 OSHA 29 CFR Part 1910.146 requirements. 20 2. Confined Spaces include: 21 a. Manholes 22 b. All other confined spaces in accordance with OSHA’s Permit Required for 23 Confined Spaces 24 D. Air Pollution Watch Days 25 1. General 26 a. Observe the following guidelines relating to working on City construction sites 27 on days designated as “AIR POLLUTION WATCH DAYS”. 28 b. Typical Ozone Season 29 1) May 1 through October 31. 30 c. Critical Emission Time 31 1) 6:00 a.m. to 10:00 a.m. 32 2. Watch Days 33 a. The Texas Commission on Environmental Quality (TCEQ), in coordination 34 with the National Weather Service, will issue the Air Pollution Watch by 3:00 35 p.m. on the afternoon prior to the WATCH day. 36 b. Requirements 37 1) Begin work after 10:00 a.m. whenever construction phasing requires the 38 use of motorized equipment for periods in excess of 1 hour. 39 2) However, the Contractor may begin work prior to 10:00 a.m. if: 40 a) Use of motorized equipment is less than 1 hour, or 41 b) If equipment is new and certified by EPA as “Low Emitting“, or 42 equipment burns Ultra Low Sulfur Diesel (ULSD), diesel emulsions, or 43 alternative fuels such as CNG. 44 E. TCEQ Air Permit 45 1. Obtain TCEQ Air Permit for construction activities per requirements of TCEQ. 46 F. Use of Explosives, Drop Weight, Etc. 47 01 35 13 SPECIAL PROJECT PROCEDURES Page 4 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 1. When Contract Documents permit on the project the following will apply: 1 a. Public Notification 2 1) Submit notice to City and proof of adequate insurance coverage, 24 hours 3 prior to commencing. 4 2) Minimum 24-hour public notification in accordance with paragraph 1.4.H 5 of this Section. 6 G. Water Utilities Coordination 7 1. During the construction of this project, it may be necessary to deactivate, for a 8 period of time, existing lines. The Contractor shall be required to coordinate with 9 Water Utilities to determine the best times for deactivating and activating those 10 lines. 11 2. Coordinate any event that will require connecting to or the operation of an existing 12 City water line system with the City’s representative. 13 a. If needed, obtain a hydrant water meter from Water Utilities for use during the 14 life of named project. 15 b. In the event that a water valve on an existing live system is required to be 16 turned off or on to accommodate the construction of the project is required, 17 coordinate this activity through the appropriate City representative. 18 1) Do not operate water line valves of existing water system. 19 a) Failure to comply will render the Contractor in violation of Texas Penal 20 Code Title 7, Chapter 28.03 (Criminal Mischief) and the Contractor 21 will be prosecuted to the full extent of the law. 22 b) In addition, the Contractor will assume all liabilities and 23 responsibilities as a result of these actions. 24 H. Public Notification Prior to Beginning Construction 25 1. Prior to beginning construction on any block in the project, on a block-by-block 26 basis, prepare and deliver a notice or flyer of the pending construction to the front 27 door of each residence or business that will be impacted by construction. The notice 28 shall be prepared as follows: 29 a. Post notice or flyer 7 days prior to beginning any construction activity on each 30 block in the project area. 31 1) Prepare flyer on the Contractor’s letterhead and include the following 32 information: 33 a) Name of Project 34 b) Engineering Project Number (EPN) 35 c) Scope of Project (i.e. type of construction activity) 36 d) Actual construction duration within the block 37 e) Name of the contractor’s foreman and phone number 38 f) Name of the City’s inspector and phone number 39 g) City’s after-hours phone number 40 2) A sample of the ‘pre-construction notification’ flyer is attached as Exhibit 41 A. 42 3) Submit schedule showing the construction start and finish time for each 43 block of the project to the inspector. 44 4) Deliver flyer to the City Inspector for review prior to distribution. 45 b. No construction will be allowed to begin on any block until the flyer is 46 delivered to all residents of the block. 47 I. Public Notification of Temporary Water Service Interruption during Construction 48 01 35 13 SPECIAL PROJECT PROCEDURES Page 5 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 1. In the event it becomes necessary to temporarily shut down water service to 1 residents or businesses during construction, prepare and deliver a notice or flyer of 2 the pending interruption to the front door of each affected resident. 3 2. Prepared notice as follows: 4 a. The notification or flyer shall be posted 24 hours prior to the temporary 5 interruption. 6 b. Prepare flyer on the contractor’s letterhead and include the following 7 information: 8 1) Name of the project 9 2) Date of the interruption of service 10 3) Period the interruption will take place 11 4) Name of the contractor’s foreman and phone number 12 5) Name of the City’s inspector and phone number 13 c. A sample of the temporary water service interruption notification is attached as 14 Exhibit B. 15 d. Deliver a copy of the temporary interruption notification to the City inspector 16 for review prior to being distributed. 17 e. No interruption of water service can occur until the flyer has been delivered to 18 all affected residents and businesses. 19 f. Electronic versions of the sample flyers can be obtained from the Project 20 Construction Inspector. 21 J. Coordination with United States Army Corps of Engineers (USACE) 22 1. At locations in the Project where construction activities occur in areas where 23 USACE permits are required, meet all requirements set forth in each designated 24 permit. 25 K. Coordination within Railroad Permit Areas 26 1. At locations in the project where construction activities occur in areas where 27 railroad permits are required, meet all requirements set forth in each designated 28 railroad permit. This includes, but is not limited to, provisions for: 29 a. Flagmen 30 b. Inspectors 31 c. Safety training 32 d. Additional insurance 33 e. Insurance certificates 34 f. Other employees required to protect the right-of-way and property of the 35 Railroad Company from damage arising out of and/or from the construction of 36 the project. Proper utility clearance procedures shall be used in accordance 37 with the permit guidelines. 38 2. Obtain any supplemental information needed to comply with the railroad’s 39 requirements. 40 3. Railroad Flagmen 41 a. Submit receipts to City for verification of working days that railroad flagmen 42 were present on Site. 43 L. Dust Control 44 1. Use acceptable measures to control dust at the Site. 45 a. If water is used to control dust, capture and properly dispose of waste water. 46 b. If wet saw cutting is performed, capture and properly dispose of slurry. 47 01 35 13 SPECIAL PROJECT PROCEDURES Page 6 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 M. Employee Parking 1 1. Provide parking for employees at locations approved by the City. 2 N. Coordination with North Central Texas Council of Governments (NCTCOG) Clean 3 Construction Specification 4 1. Equipment Requirements 5 a. All construction equipment being used to perform work on the Contract shall 6 meet EPA emissions standards of Tier 3 or equivalent, or cleaner. Model Form 7 A.14. Schedule for Phase-In of Tier 1-Tier 4 Non-Road Engines is included in 8 Appendix A. Compliance may be achieved through the use of equipment 9 powered by an EPA-certified engine, through engine repowers, or through the 10 use of retrofits which have been verified by the EPA and/or California Air 11 Resources Board. A list of available retrofits is available online at EPA’s 12 website “Verified Technologies List for Clean Diesel.” 13 b. Equipment that meets one or more of the following conditions may be exempt 14 from these requirements: 15 1) Equipment powered by an engine that is less than or equal to ten (10) years 16 old. 17 2) Equipment that must be used to fulfill use or reporting requirements for a 18 grant program or other clean air initiative. Documentation of such 19 obligations must be submitted to City for verification. 20 3) Equipment that is designated as low-use equipment, which is defined as 21 any piece of construction equipment which is used for less than ten (10) 22 hours per week on a single public works contract. A Low-Use Exemption 23 Weekly Reporting Form will be required for all equipment for which this 24 exemption is claimed. 25 4) Equipment that is being used to address a critical or emergency public 26 works need, including, but not limited to, broken water mains or sanitary 27 sewer lines. This exemption is limited to work performed in a situation in 28 which the procurement of construction services is performed on an 29 emergency basis, as provided for by State law. 30 2. Operational Requirements 31 a. All diesel fuel used to perform work on the public works contract shall be 32 Ultra-Low Sulfur Diesel (ULSD) fuel which also complies with Texas Low 33 Emission Diesel (TxLED) program requirements. This may include TxLED- 34 compliant Biodiesel blends. 35 b. The Contractor shall limit idling of equipment to no more than five (5) 36 minutes, unless the idling is applicable to one or more of the following 37 exceptions: 38 1) is being used for emergency response purposes; 39 2) is idling as a necessary component of mechanical operation, maintenance, 40 or diagnostic purposes; or 41 3) is idling for the health or safety of the equipment operator. 42 c. To the greatest extent possible, Contractor shall stage equipment away from, 43 and minimize operation near, sensitive receptors including, but not limited to, 44 fresh air intakes, hospitals, schools, licensed day care facilities, and residences. 45 3. Reporting Requirements 46 01 35 13 SPECIAL PROJECT PROCEDURES Page 7 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 a. On or before the day construction activity commences, the Contractor shall 1 submit to the City an inventory report containing identifying data for each piece 2 of equipment to be used on the worksite. A form for submitting such 3 information will be provided by the City. This inventory may be used by the 4 City to conduct site inspections and/or verify compliance with specification 5 elements. 6 b. If additional equipment is brought on-site after construction begins, the 7 Contractor shall provide this same inventory information to the City for the new 8 equipment on or before the day it begins work on-site. 9 c. Reports shall be provided for all equipment used on-site. 10 4. Enforcement Requirements 11 a. All construction equipment used at the Site is subject to inspection by the City 12 at random. Contractor is responsible for ensuring that all subcontractors meet 13 the requirements of this specification. 14 O. Tree Protection 15 1. Install tree protection in accordance with the Drawings, if applicable. 16 2. Coordinate with City Building Inspections prior to commencing and earthwork 17 activities to perform an initial tree protection inspection. 18 1.5 SUBMITTALS 19 A. Submittals shall be in accordance with Section 01 33 00. 20 B. All submittals shall be approved by the City prior to delivery. 21 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 22 A. Construction Notice Flyer 23 B. Notice of Temporary Water Service Interruption 24 1.7 CLOSEOUT SUBMITTALS [NOT USED] 25 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 26 1.9 QUALITY ASSURANCE [NOT USED] 27 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 28 1.11 FIELD [SITE] CONDITIONS [NOT USED] 29 1.12 WARRANTY [NOT USED] 30 PART 2 - PRODUCTS [NOT USED] 31 PART 3 - EXECUTION [NOT USED] 32 33 01 35 13 SPECIAL PROJECT PROCEDURES Page 8 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 END OF SECTION 1 2 Revision Log DATE NAME SUMMARY OF CHANGE 3 01 35 13 SPECIAL PROJECT PROCEDURES Page 9 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 EXHIBIT A 1 (To be printed on Contractor’s Letterhead) 2 3 4 5 Date: 6 7 EPN No.: 8 Project Name: 9 Limits of Construction: 10 11 NOTICE OF CONSTRUCTION 12 13 14 15 THIS IS TO INFORM YOU THAT UNDER A CONTRACT WITH THE CITY OF 16 DENTON, OUR COMPANY WILL WORK ON UTILITY LINES ON OR AROUND YOUR 17 PROPERTY. 18 19 CONSTRUCTION WILL BEGIN APPROXIMATELY SEVEN DAYS FROM THE DATE 20 OF THIS NOTICE. 21 22 IF YOU HAVE QUESTIONS ABOUT ACCESS, SECURITY, SAFETY OR ANY OTHER 23 ISSUE, PLEASE CALL: 24 25 26 <CONTRACTOR’S SUPERINTENDENT> AT <TELEPHONE NO.> 27 28 OR 29 30 <CITY INSPECTOR> AT < TELEPHONE NO.> 31 32 33 PLEASE KEEP THIS FLYER HANDY WHEN YOU CALL 34 35 01 35 13 SPECIAL PROJECT PROCEDURES Page 10 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 EXHIBIT B 1 2 Date: 3 4 EPN No.: 5 6 Project Name:_____________________ 7 8 9 NOTICE OF 10 TEMPORARY WATER SERVICE 11 INTERRUPTION 12 13 14 Due to utility improvements in your neighborhood, your water service will be 15 interrupted on ___________________________________________________ 16 between the hours of __________________ and _______________________. 17 18 19 IF YOU HAVE QUESTIONS ABOUT THIS DISRUPTION, PLEASE CALL: 20 21 22 <CONTRACTOR’S SUPERINTENDENT> AT <TELEPHONE NO.> 23 24 OR 25 26 <CITY INSPECTOR> AT < TELEPHONE NO.> 27 28 THIS SERVICE INTERRUPTION WILL BE AS SHORT AS POSSIBLE 29 30 Thank you, 31 _________________________, Contractor 32 01 45 23 TESTING AND INSPECTION SERVICES Page 1 of 2 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 SECTION 01 45 23 1 TESTING AND INSPECTION SERVICES 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Testing and inspection services procedures and coordination 6 B. Deviations from this City of Denton Standard Specification 7 1. None 8 C. Related Specification Sections include, but are not necessarily limited to: 9 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 10 2. Division 1 – General Requirements 11 1.2 PRICE AND PAYMENT PROCEDURES 12 A. Measurement and Payment 13 1. Work associated with this Item is considered incidental to the various Items bid. 14 No separate payment will be allowed for this Item. 15 a. In accordance with Article 13 of the General Conditions, Contractor is 16 responsible for performing, coordinating, and payment of all inspections, tests, 17 re-tests, or approvals. 18 b. In accordance with Article 13 of the General Conditions, City is responsible for 19 performing and payment for first set additional independent testing chosen by 20 the City to be performed. 21 1) If the first independent test performed by the City fails, the Contractor is 22 responsible for payment of subsequent testing until a passing test occurs. 23 a) Final acceptance will not be issued by City until all required payments 24 for testing by Contractor have been paid in full. 25 1.3 REFERENCES [NOT USED] 26 1.4 ADMINISTRATIVE REQUIREMENTS 27 A. Testing 28 1. Complete testing in accordance with the Contract Documents. 29 2. Coordination 30 a. When testing is required to be performed by the City, notify City, sufficiently in 31 advance, when testing is needed. 32 b. When testing is required to be completed by the Contractor, notify City, 33 sufficiently in advance, that testing will be performed. 34 3. Distribution of Testing Reports 35 a. Electronic Distribution 36 1) Provide all reports to Project Manager and their duly appointed 37 representative electronically via email. 38 39 40 01 45 23 TESTING AND INSPECTION SERVICES Page 2 of 2 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 4. Provide Project Manager’s duly appointed representative with trip tickets for each 1 delivered load of Concrete or Lime material including the following information: 2 a. Name of pit 3 b. Date of delivery 4 c. Material delivered 5 B. Inspection 6 1. Inspection or lack of inspection does not relieve the Contractor from obligation to 7 perform work in accordance with the Contract Documents. 8 1.5 SUBMITTALS 9 A. Submittals shall be in accordance with Section 01 33 00. 10 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 11 A. Materials Testing Reports sealed by a Professional Engineer or Professional 12 Geoscientist licensed in the State of Texas. 13 1.7 CLOSEOUT SUBMITTALS [NOT USED] 14 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 15 1.9 QUALITY ASSURANCE [NOT USED] 16 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 17 1.11 FIELD [SITE] CONDITIONS [NOT USED] 18 1.12 WARRANTY [NOT USED] 19 PART 2 - PRODUCTS [NOT USED] 20 PART 3 - EXECUTION [NOT USED] 21 END OF SECTION 22 23 Revision Log DATE NAME SUMMARY OF CHANGE 24 01 50 00 TEMPORARY FACILITIES AND CONTROLS Page 1 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 SECTION 01 50 00 1 TEMPORARY FACILITIES AND CONTROLS 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Provide temporary facilities and controls needed for the Work including, but not 6 necessarily limited to: 7 a. Temporary utilities 8 b. Sanitary facilities 9 c. Storage Sheds and Buildings 10 d. Dust control 11 e. Temporary fencing of the construction site 12 B. Deviations from this City of Denton Standard Specification 13 1. None. 14 C. Related Specification Sections include, but are not necessarily limited to: 15 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 16 2. Division 1 – General Requirements 17 1.2 PRICE AND PAYMENT PROCEDURES 18 A. Measurement and Payment 19 1. Work associated with this Item is considered incidental to the various Items bid. 20 No separate payment will be allowed for this Item. 21 1.3 REFERENCES [NOT USED] 22 1.4 ADMINISTRATIVE REQUIREMENTS 23 A. Temporary Utilities 24 1. Obtaining Temporary Service 25 a. Make arrangements with utility service companies for temporary services. 26 b. Abide by rules and regulations of utility service companies or authorities 27 having jurisdiction. 28 c. Be responsible for utility service costs until Work is approved for Final 29 Acceptance. 30 1) Included are fuel, power, light, heat and other utility services necessary for 31 execution, completion, testing and initial operation of Work. 32 2. Construction Water 33 a. Contractor to provide water required for and in connection with Work to be 34 performed and for specified tests of piping, equipment, devices or other use as 35 required for the completion of the Work. 36 b. Provide and maintain adequate supply of potable water for domestic 37 consumption by Contractor, if required. 38 c. Coordination 39 1) Contact City 1 week before water for construction is desired 40 01 50 00 TEMPORARY FACILITIES AND CONTROLS Page 2 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 d. Metering and Payment for Construction Water 1 1) For water system improvements: 2 a) Obtain construction water meter from City to track water usage. Water 3 will be provided at no cost to Contractor. 4 2) For all other projects: 5 a) Obtain construction water meter from City for payment as billed by 6 City’s established rates. 7 3. Electricity and Lighting 8 a. Provide and pay for electric powered service as required for Work, including 9 testing of Work. 10 1) Provide power for lighting, operation of equipment, or other use. 11 b. Electric power service includes temporary power service or generator to 12 maintain operations during scheduled shutdown. 13 4. Telephone 14 a. Provide emergency telephone service at Site for use by Contractor personnel 15 and others performing work or furnishing services at Site. 16 5. Temporary Heat and Ventilation 17 a. Provide temporary heat as necessary for protection or completion of Work. 18 b. Provide temporary heat and ventilation to assure safe working conditions. 19 B. Sanitary Facilities 20 1. Provide and maintain sanitary facilities for persons on Site. 21 a. Comply with regulations of State and local departments of health. 22 2. Enforce use of sanitary facilities by construction personnel at job site. 23 a. Enclose and anchor sanitary facilities. 24 b. No discharge will be allowed from these facilities. 25 c. Collect and store sewage and waste so as not to cause nuisance or health 26 problem. 27 d. Haul sewage and waste off-site at no less than weekly intervals and properly 28 dispose in accordance with applicable regulation. 29 3. Locate facilities near Work Site and keep clean and maintained throughout Project. 30 4. Remove facilities at completion of Project 31 C. Storage Sheds and Buildings 32 1. Provide adequately ventilated, watertight, weatherproof storage facilities with floor 33 above ground level for materials and equipment susceptible to weather damage. 34 2. Storage of materials not susceptible to weather damage may be on blocks off 35 ground. 36 3. Store materials in a neat and orderly manner. 37 a. Place materials and equipment to permit easy access for identification, 38 inspection and inventory. 39 4. Equip building with lockable doors and lighting, and provide electrical service for 40 equipment space heaters and heating or ventilation as necessary to provide storage 41 environments acceptable to specified manufacturers. 42 5. Fill and grade site for temporary structures to provide drainage away from 43 temporary and existing buildings. 44 6. Remove building from site prior to Final Acceptance. 45 01 50 00 TEMPORARY FACILITIES AND CONTROLS Page 3 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 D. Temporary Fencing 1 1. Provide and maintain for the duration or construction when required in contract 2 documents 3 E. Dust Control 4 1. Contractor is responsible for maintaining dust control through the duration of the 5 project. 6 a. Contractor remains on-call at all times 7 b. Must respond in a timely manner 8 F. Temporary Protection of Construction 9 1. Contractor or subcontractors are responsible for protecting Work from damage due 10 to weather. 11 1.5 SUBMITTALS [NOT USED] 12 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 13 1.7 CLOSEOUT SUBMITTALS [NOT USED] 14 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 15 1.9 QUALITY ASSURANCE [NOT USED] 16 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 17 1.11 FIELD [SITE] CONDITIONS [NOT USED] 18 1.12 WARRANTY [NOT USED] 19 PART 2 - PRODUCTS [NOT USED] 20 PART 3 - EXECUTION [NOT USED] 21 3.1 INSTALLERS [NOT USED] 22 3.2 EXAMINATION [NOT USED] 23 3.3 PREPARATION [NOT USED] 24 3.4 INSTALLATION 25 A. Temporary Facilities 26 1. Maintain all temporary facilities for duration of construction activities as needed. 27 01 50 00 TEMPORARY FACILITIES AND CONTROLS Page 4 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 3.5 [REPAIR] / [RESTORATION] 1 3.6 RE-INSTALLATION 2 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 3 3.8 SYSTEM STARTUP [NOT USED] 4 3.9 ADJUSTING [NOT USED] 5 3.10 CLEANING [NOT USED] 6 3.11 CLOSEOUT ACTIVITIES 7 A. Temporary Facilities 8 1. Remove all temporary facilities and restore area after completion of the Work, to a 9 condition equal to or better than prior to start of Work. 10 3.12 PROTECTION [NOT USED] 11 3.13 MAINTENANCE [NOT USED] 12 3.14 ATTACHMENTS [NOT USED] 13 END OF SECTION 14 15 Revision Log DATE NAME SUMMARY OF CHANGE 16 01 57 13 STORM WATER POLLUTION PREVENTION Page 1 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 SECTION 01 57 13 1 STORMWATER POLLUTION PREVENTION 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Procedures for Stormwater Pollution Prevention Plans 6 B. Deviations from this City of Denton Standard Specification 7 1. None. 8 C. Related Specification Sections include, but are not necessarily limited to: 9 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the 10 Contract 11 2. Division 1 – General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Construction Activities resulting in less than 1 acre of disturbance 15 a. Work associated with this Item is considered subsidiary to the various Items 16 bid. No separate payment will be allowed for this Item. 17 2. Construction Activities resulting in greater than 1 acre of disturbance 18 a. Measurement for this Item shall be by lump sum. 19 b. Payment 20 1) The work performed and the materials furnished in accordance with this 21 item shall be paid for at the lump sum price bid for “Stormwater Pollution 22 Prevention Plan”, and made in partial payments as follows: 23 a) When 1% of the Contract amount is earned, 15% of the SWPPP lump 24 sum bid will be paid. 25 b) When 10% of the Contract amount is earned, 25% of the SWPPP lump 26 sum bid will be paid. Previous payments under the item will be 27 deducted from this amount. 28 c) When 25% of the Contract amount is earned, 30% of the SWPPP lump 29 sum bid will be paid. Previous payments under the item will be 30 deducted from this amount. 31 d) When 50% of the Contract is earned, 50% of the SWPPP lump sum bid 32 will be paid. Previous payments under the item will be deducted from 33 this amount. 34 e) When 75% of the Contract is earned, 75% of the SWPPP lump sum bid 35 will be paid. Previous payments under the item will be deducted from 36 this amount. 37 f) When 100% of the Contract is earned and final stabilization has been 38 achieved, 100% of the SWPPP lump sum bid will be paid. Previous 39 payments under the item will be deducted from this amount. 40 c. The price bid shall include: 41 1) Preparation of Stormwater Pollution Prevention Plan 42 01 57 13 STORM WATER POLLUTION PREVENTION Page 2 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 2) Implementation 1 3) Permitting fees 2 4) Final Stabilization 3 1.3 REFERENCES 4 A. Abbreviations and Acronyms 5 1. Notice of Intent: NOI 6 2. Notice of Termination: NOT 7 3. Stormwater Pollution Prevention Plan: SWPPP 8 4. Texas Commission on Environmental Quality: TCEQ 9 5. Notice of Change: NOC 10 A.Reference Standards 11 1. Reference standards cited in this Specification refer to the current reference 12 standard published at the time of the latest revision date logged at the end of this 13 Specification, unless a date is specifically cited. 14 2. Integrated Stormwater Management (iSWM) Technical Manual for Construction 15 Controls 16 1.4 ADMINISTRATIVE REQUIREMENTS 17 A. General 18 1. Contractor is responsible for resolution and payment of any fines issued associated 19 with compliance to Stormwater Pollution Prevention Plan. 20 2. As a condition of approval, applicants conducting land disturbing activities will 21 complete the online construction site survey. This survey can be found at 22 https://www.surveymonkey.com/r/dentonconstruction. 23 3. Refer to TCEQ website for further information about stormwater permits at 24 https://www.tceq.texas.gov/permitting/stormwater/construction/TXR15_AIR.html. 25 B. Construction Activities resulting in: 26 1. Less than 1 acre of disturbance 27 a. Provide erosion and sediment control in accordance with Section 31 25 14. 28 2. 1 to less than 5 acres of disturbance 29 a. Texas Pollutant Discharge Elimination System (TPDES) General Construction 30 Permit is required 31 b. Complete SWPPP in accordance with TCEQ requirements 32 1) Indicate City is a Secondary Operator 33 2) TCEQ Small Construction Site Notice Required under general permit 34 TXR150000 35 a) Post at job site 36 b) Prior to Preconstruction Meeting, send 1 copy to City Watershed 37 Protection Division, Watershed@cityofdenton.com. 38 3) Provide erosion and sediment control in accordance with Section 31 25 14. 39 4) Project Site Operator must contact Watershed Protection Division for initial 40 inspection prior to commencing land disturbing activities to ensure 41 compliance with stormwater regulations and proper installation of 42 appropriate BMPs, Watershed@cityofdenton.com. 43 01 57 13 STORM WATER POLLUTION PREVENTION Page 3 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 5) Once the project has been completed and all the closeout requirements of 1 TCEQ have been met, send copy of signed Small Construction Site Notice 2 to Watershed Protection division, Watershed@cityofdenton.com. 3 3. 5 acres or more of Disturbance 4 a. Texas Pollutant Discharge Elimination System (TPDES) General Construction 5 Permit is required 6 b. Complete SWPPP in accordance with TCEQ requirements 7 1) Prepare a TCEQ NOI form and submit to TCEQ along with required fee 8 a) Send copy to City Watershed Protection Division, 9 Watershed@cityofdenton.com. 10 2) TCEQ Notice of Change required if making changes or updates to NOI 11 3) Provide erosion and sediment control in accordance with Section 31 25 14. 12 4) Project Site Operator must contact Watershed Protection Division for initial 13 inspection prior to commencing land disturbing activities to ensure 14 compliance with stormwater regulations and proper installation of 15 appropriate BMPs, Watershed@cityofdenton.com. 16 5) Once the project has been completed and all the closeout requirements of 17 TCEQ have been met a TCEQ Notice of Termination can be submitted. 18 a) Send copy to City Watershed Protection Division, 19 Watershed@cityofdenton.com. 20 C. Sites adjacent to or encroaching into Environmentally Sensitive Areas (ESAs): 21 1. Provide tree protective fencing at the boundary of any identified onsite ESAs and 22 approved construction activities that would result in land disturbances. 23 2. Provide signs identifying the area as an ESA and prohibiting construction activity. 24 1.5 SUBMITTALS 25 A. SWPPP 26 1. Submit in accordance with Section 01 33 00, except as stated herein. 27 a. Prior to the Preconstruction Meeting, submit a draft copy of SWPPP to the City 28 as follows: 29 1) 1 copy to the Project Manager 30 a) Project Manager will forward to the City Watershed Protection 31 Department, Watershed@cityofdenton.com. 32 B. Modified SWPPP 33 1. If the SWPPP is revised during construction, resubmit modified SWPPP to the City 34 in accordance with Section 01 33 00. 35 01 57 13 STORM WATER POLLUTION PREVENTION Page 4 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1 1.7 CLOSEOUT SUBMITTALS [NOT USED] 2 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 3 1.9 QUALITY ASSURANCE [NOT USED] 4 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 5 1.11 FIELD [SITE] CONDITIONS [NOT USED] 6 1.12 WARRANTY [NOT USED] 7 PART 2 - PRODUCTS [NOT USED] 8 PART 3 - EXECUTION [NOT USED] 9 END OF SECTION 10 Revision Log DATE NAME SUMMARY OF CHANGE 6/14/2024 Removed specific City of Denton personnel names from contact information under Section 1.4 11 01 58 13 TEMPORARY PROJECT SIGNAGE Page 1 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 25, 2024 Effective July 1, 2024 SECTION 01 58 13 1 TEMPORARY PROJECT SIGNAGE 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Temporary Project Signage Requirements 6 B. Deviations from this City of Denton Standard Speciflcation 7 1. None. 8 C. Related Speciflcation Sections include, but are not necessarily limited to: 9 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the 10 Contract 11 2. Division 1 – General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Temporary Project Sign 15 a. Measurement 16 1) Measurement for this Item will be per each project sign installed. 17 b. Payment 18 1) The work performed and materials furnished in accordance with this 19 Item and measured as provided under “Measurement” shall be paid for 20 at the unit price bid per each “Temporary Project Sign.” 21 c. The price bid shall include: 22 1) Installation of Temporary Project Sign 23 2) Excavation 24 3) Hauling 25 4) Disposal of excess Materials 26 5) Maintenance and Repair of Signs During Construction 27 6) Removal and Disposal of Temporary Project Sign 28 1.3 REFERENCES [NOT USED] 29 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 30 1.5 SUBMITTALS [NOT USED] 31 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 32 01 58 13 TEMPORARY PROJECT SIGNAGE Page 2 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 25, 2024 Effective July 1, 2024 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 2 1.9 QUALITY ASSURANCE [NOT USED] 3 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 4 1.11 FIELD [SITE] CONDITIONS [NOT USED] 5 1.12 WARRANTY [NOT USED] 6 PART 2 - PRODUCTS 7 2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIEDPRODUCTS [NOT USED] 8 2.2 EQUIPMENT, PRODUCT TYPES, AND MATERIALS 9 A. Design Criteria 10 1. Provide free standing Project Designation Sign as indicated below: 11 12 01 58 13 TEMPORARY PROJECT SIGNAGE Page 3 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 25, 2024 Effective July 1, 2024 The fiag shall resemble the Texas Flag. The background of the stars and the “City of 1 Denton” lettering shall be blue. The lower bar of the fiag shall be red, and the 2 upper bar shall be white. The dimensions, from the 3 farthest ends, shall be 12-inches vertically and 23.5-4 inches horizontally. The fiag shall appear in the 5 dimensions shown. The contractor may request a digital 6 copy in either .jpg or .tif format. 7 8 2. The Project Designation Sign shall be placed at strategic points with lettering 9 as needed to adequately describe the work. 10 3. Signs shall be painted white with blue letters and symbols. Letter size shall 11 conform to dimensions shown on sign drawing. Exceptions or variations from 12 the sign shown above shall not be allowed. 13 B. Materials 14 1. Sign 15 a. Constructed of ¾-inch flr plywood, grade A-C (exterior) or better 16 2.3 ACCESSORIES [NOT USED] 17 2.4 SOURCE QUALITY CONTROL [NOT USED] 18 PART 3 - EXECUTION 19 3.1 INSTALLERS [NOT USED] 20 3.2 EXAMINATION [NOT USED] 21 3.3 PREPARATION [NOT USED] 22 3.4 INSTALLATION 23 A. General 24 1. Provide vertical installation at extents of project. 25 2. Signs shall be placed prior to beginning the Work and maintained until the end 26 of the project. 27 3. Relocate sign as needed, upon request of the City. 28 B. Mounting options 29 a. Skids 30 b. Posts 31 c. Barricade 32 01 58 13 TEMPORARY PROJECT SIGNAGE Page 4 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 25, 2024 Effective July 1, 2024 3.5 -- 3.12 [NOT USED] 1 3.6 MAINTENANCE 2 A. General 3 1. Maintenance will include painting and repairs as needed or directed by the 4 City. 5 3.7 ATTACHMENTS [NOT USED] 6 7 8 9 10 END OF SECTION 11 12 Revision Log DATE NAME SUMMARY OF CHANGE 13 01 66 00 PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 1 of 3 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 13, 2022 Effective July 1, 2024 SECTION 01 66 00 1 PRODUCT STORAGE AND HANDLING REQUIREMENTS 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Scheduling of product delivery 6 2. Packaging of products for delivery 7 3. Protection of products against damage from: 8 a. Handling 9 b. Exposure to elements or harsh environments 10 B. Deviations from this City of Denton Standard Specification 11 1. None. 12 C. Related Specification Sections include, but are not necessarily limited to: 13 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 14 2. Division 1 – General Requirements 15 1.2 PRICE AND PAYMENT PROCEDURES 16 A. Measurement and Payment 17 1. Work associated with this Item is considered incidental to the various Items bid. 18 No separate payment will be allowed for this Item. 19 1.3 REFERENCES [NOT USED] 20 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 21 1.5 SUBMITTALS [NOT USED] 22 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 23 1.7 CLOSEOUT SUBMITTALS [NOT USED] 24 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 25 1.9 QUALITY ASSURANCE [NOT USED] 26 1.10 DELIVERY AND HANDLING 27 A. Delivery Requirements 28 1. Schedule delivery of products or equipment as required to allow timely installation 29 and to avoid prolonged storage. 30 2. Provide appropriate personnel and equipment to receive deliveries. 31 3. Delivery trucks will not be permitted to wait extended periods of time on the Site 32 for personnel or equipment to receive the delivery. 33 01 66 00 PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 2 of 3 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 13, 2022 Effective July 1, 2024 4. Deliver products or equipment in manufacturer's original unbroken cartons or other 1 containers designed and constructed to protect the contents from physical or 2 environmental damage. 3 5. Clearly and fully mark and identify as to manufacturer, item and installation 4 location. 5 6. Provide manufacturer's instructions for storage and handling. 6 B. Handling Requirements 7 1. Handle products or equipment in accordance with these Contract Documents and 8 manufacturer’s recommendations and instructions. 9 C. Storage Requirements 10 1. Store materials in accordance with manufacturer’s recommendations and 11 requirements of these Specifications. 12 2. Make necessary provisions for safe storage of materials and equipment. 13 a. Place loose soil materials and materials to be incorporated into Work in a 14 manner that prevents damage to any part of Work or existing facilities and that 15 maintains free access at all times to all parts of Work and to utility service 16 company installations in vicinity of Work. 17 3. Keep materials and equipment neatly and compactly stored in locations that will 18 cause minimum inconvenience to other contractors, public travel, adjoining owners, 19 tenants and occupants. 20 a. Arrange storage to provide easy access for inspection. 21 4. Restrict storage to areas available on construction site for storage of material and 22 equipment as shown on Drawings, or approved by Project Manager or their duly 23 authorized representative. 24 5. Provide off-site storage and protection when on-site storage is not adequate. 25 a. Provide addresses of and access to off-site storage locations for inspection by 26 Project Manager or their duly authorized representative. 27 6. Do not use lawns, grass plots or other private property for storage purposes without 28 written permission of owner or other person in possession or control of premises. 29 7. Store in manufacturers’ unopened containers. 30 8. Neatly, safely and compactly stack materials delivered and stored along line of 31 Work to avoid inconvenience and damage to property owners and general public 32 and maintain at least 3 feet from fire hydrant. 33 9. Keep public and private driveways and street crossings open. 34 10. Repair or replace damaged lawns, sidewalks, streets or other improvements to 35 satisfaction of Project Manager or their duly authorized representative. 36 a. Total length which materials may be distributed along route of construction at 37 one time is 1,000 linear feet, unless otherwise approved in writing by Project 38 Manager. 39 01 66 00 PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 3 of 3 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 13, 2022 Effective July 1, 2024 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1 1.12 WARRANTY [NOT USED] 2 PART 2 - PRODUCTS [NOT USED] 3 PART 3 - EXECUTION 4 3.1 [NOT USED] 5 3.2 FIELD [OR] SITE QUALITY CONTROL 6 A. Tests and Inspections 7 1. Inspect all products or equipment delivered to the site prior to unloading. 8 B. Non-Conforming Work 9 1. Reject all products or equipment that are damaged, used or in any other way 10 unsatisfactory for use on the project. 11 3.3 SYSTEM STARTUP [NOT USED] 12 3.4 ADJUSTING [NOT USED] 13 3.5 CLEANING [NOT USED] 14 3.6 CLOSEOUT ACTIVITIES [NOT USED] 15 3.7 PROTECTION 16 A. Protect all products or equipment in accordance with manufacturer's written directions. 17 B. Store products or equipment in location to avoid physical damage to items while in 18 storage. 19 C. Protect equipment from exposure to elements and keep thoroughly dry if required by 20 the manufacturer. 21 3.8 MAINTENANCE [NOT USED] 22 3.9 ATTACHMENTS [NOT USED] 23 END OF SECTION 24 Revision Log DATE NAME SUMMARY OF CHANGE 25 01 70 00 MOBILIZATION AND REMOBILIZATION Page 1 of 3 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 13, 2022 Effective July 1, 2024 SECTION 01 70 00 1 MOBILIZATION AND REMOBILIZATION 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Mobilization and Demobilization 6 a. Mobilization 7 1) Transportation of Contractor’s personnel, equipment, and operating supplies 8 to the Site 9 2) Establishment of necessary general facilities for the Contractor’s operation 10 at the Site 11 3) Premiums paid for performance and payment bonds 12 4) Transportation of Contractor’s personnel, equipment, and operating supplies 13 to another location within the designated Site 14 5) Relocation of necessary general facilities for the Contractor’s operation 15 from 1 location to another location on the Site. 16 b. Demobilization 17 1) Transportation of Contractor’s personnel, equipment, and operating supplies 18 away from the Site including disassembly 19 2) Site Clean-up 20 3) Removal of all buildings and/or other facilities assembled at the Site for this 21 Contract 22 c. Mobilization and Demobilization do not include activities for specific items of 23 work that are for which payment is provided elsewhere in the contract. 24 2. Remobilization 25 26 a. Remobilization for Suspension of Work specifically required in the Contract 27 Documents or as required by City includes: 28 1) Demobilization 29 a) Transportation of Contractor’s personnel, equipment, and operating 30 supplies from the Site including disassembly or temporarily securing 31 equipment, supplies, and other facilities as designated by the Contract 32 Documents necessary to suspend the Work. 33 b) Site Clean-up as designated in the Contract Documents 34 2) Remobilization 35 a) Transportation of Contractor’s personnel, equipment, and operating 36 supplies to the Site necessary to resume the Work. 37 01 70 00 MOBILIZATION AND REMOBILIZATION Page 2 of 3 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 13, 2022 Effective July 1, 2024 b) Establishment of necessary general facilities for the Contractor’s 1 operation at the Site necessary to resume the Work. 2 3) No Payments will be made for: 3 a) Mobilization and Demobilization from one location to another on the 4 Site in the normal progress of performing the Work. 5 b) Stand-by or idle time 6 c) Lost profits 7 B. Deviations from this City of Denton Standard Specification 8 1. None. 9 C. Related Specification Sections include, but are not necessarily limited to: 10 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 11 2. Division 1 – General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Mobilization and Demobilization 15 a. Measurement 16 1) This Item will be measured by the lump sum as the work progresses. 17 b. Payment 18 1) For this Item, the adjusted Contract amount will be calculated as the total 19 Contract amount less the lump sum for mobilization. Mobilization shall be 20 made in partial payments as follows: 21 a) When 1% of the adjusted Contract amount for construction Items is 22 earned, 25% of the mobilization lump sum bid will be paid. 23 b) When 25% of the adjusted Contract amount for construction Items is 24 earned, 50% of the mobilization lump sum bid will be paid. Previous 25 payments under the Item will be deducted from this amount. 26 c) When 50% of the adjusted Contract amount for construction Items is 27 earned, 75% of the mobilization lump sum bid will be paid. Previous 28 payments under the Item will be deducted from this amount. 29 d) When 75% of the adjusted Contract amount for construction Items is 30 earned, 100% of the mobilization lump sum bid will be paid. Previous 31 payments under the Item will be deducted from this amount. 32 e) A bid containing a total for “Mobilization” in excess of 10% of total 33 contract shall be considered unbalanced and a cause for 34 consideration of rejection. 35 c. The price bid shall include: 36 1) Mobilization of equipment to Site 37 2) Performance Bond 38 01 70 00 MOBILIZATION AND REMOBILIZATION Page 3 of 3 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 13, 2022 Effective July 1, 2024 3) Payment Bond 1 4) Maintenance Bond 2 5) Remobilization as identified in the Contract Documents 3 6) Demobilization 4 d. No payments will be made for standby, idle time, or lost profits associated this 5 Item. 6 2. Remobilization for suspension of Work not identified in the Contract Documents, as 7 required by City 8 a. Measurement and Payment 9 1) This shall be submitted as a Contract Claim in accordance with Article 11 10 of Section 00 72 00. 11 2) No payments will be made for standby, idle time, or lost profits associated 12 with this Item. 13 1.3 REFERENCES [NOT USED] 14 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 15 1.5 SUBMITTALS [NOT USED] 16 1.6 INFORMATIONAL SUBMITTALS [NOT USED] 17 1.7 CLOSEOUT SUBMITTALS [NOT USED] 18 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 19 1.9 QUALITY ASSURANCE [NOT USED] 20 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 21 1.11 FIELD [SITE] CONDITIONS [NOT USED] 22 1.12 WARRANTY [NOT USED] 23 PART 2 - PRODUCTS [NOT USED] 24 PART 3 - EXECUTION [NOT USED] 25 END OF SECTION 26 Revision Log DATE NAME SUMMARY OF CHANGE 27 01 71 23 CONSTRUCTION STAKING AND SURVEY Page 1 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 SECTION 01 71 23 1 CONSTRUCTION STAKING AND SURVEY 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Requirements for construction staking to be provided by the Contractor. 6 2. Requirements for coordination with City to allow performance of as-built survey at 7 the Site. 8 B. Deviations from this City of Denton Standard Specification 9 1. None 10 C. Related Specification Sections include, but are not necessarily limited to: 11 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 12 2. Division 1 – General Requirements 13 1.2 PRICE AND PAYMENT PROCEDURES 14 A. Measurement and Payment 15 1. Construction Staking 16 a. Measurement and Payment 17 1) Work associated with this Item is considered incidental to the various Items 18 bid. No separate payment will be allowed for this Item. 19 2. As-Built Survey 20 a. Measurement and Payment 21 1) Work associated with this Item is considered incidental to the various Items 22 bid. No separate payment will be allowed for this Item. 23 1.3 REFERENCES [NOT USED] 24 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 25 1.5 SUBMITTALS 26 A. Submittals, if required, shall be in accordance with Section 01 33 00. 27 B. All submittals shall be approved by the City prior to delivery. 28 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 29 A. Certificates 30 1. Provide certificate certifying that elevations and locations of improvements are in 31 conformance or non-conformance with requirements of the Contract Documents. 32 a. Certificate must be sealed by a registered professional land surveyor in the 33 State of Texas. 34 B. Field Quality Control Submittals 35 1. Documentation verifying accuracy of field engineering work. 36 C. As-built Survey Submittal: 37 01 71 23 CONSTRUCTION STAKING AND SURVEY Page 2 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 1. AutoCAD (.dwg) 1 2. ESRI Shapefile (.shp) 2 3. CSV file (.csv), formatted with X and Y coordinates in separate columns 3 4. Include vertical and horizontal data tied to original project control and benchmarks, 4 and feature descriptions 5 1.7 CLOSEOUT SUBMITTALS [NOT USED] 6 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 7 1.9 QUALITY ASSURANCE 8 A. Construction Staking 9 1. Construction staking will be performed by the Contractor. 10 2. Coordination 11 a. It is the Contractor’s responsibility to coordinate staking such that construction 12 activities are not delayed or negatively impacted. 13 3. General 14 a. Contractor is responsible for preserving and maintaining staking. 15 b. If in the opinion of the City, a sufficient number of stakes or markings have 16 been lost, destroyed or disturbed, by Contractor’s neglect, such that the 17 contracted Work cannot take place, then the Contractor will be required to re-18 stake the deficient areas. 19 B. As-built Survey 20 1. As-built Survey will be performed by the Contractor. 21 2. Coordination 22 a. Contractor to verify that control data established in the design survey and 23 required for construction remains intact. 24 b. It is the Contractor’s responsibility to coordinate As-built Survey such that 25 construction activities are not delayed or negatively impacted. 26 c. Contractor shall restore or replace all necessary control data damaged during 27 construction operations. 28 d. For sewer mains and water lines 12-inch and smaller in diameter, if permitted 29 by City in writing, Contractor may physically measure depth and mark the 30 location during the progress of construction and perform As-built Survey after 31 the facility has been buried. The Contractor is responsible for the quality 32 control required to ensure accuracy if this approach is permitted. 33 3. General 34 a. As-built survey will be performed in order to maintain complete and accurate 35 logs of control and survey work as it progresses for Project Records. 36 b. The Contractor perform as-built survey to obtain construction features 37 including, but not limited to, the following: 38 1) All Utility Lines 39 a) Rim and flowline elevations and coordinates for each manhole or 40 junction structure 41 2) Water Lines 42 a) Top of pipe elevations and coordinates for water lines at the following 43 locations: 44 (1) Every 250 linear feet 45 01 71 23 CONSTRUCTION STAKING AND SURVEY Page 3 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 (2) Horizontal and vertical points of inflection, curvature, etc. (All 1 Fittings) 2 (3) Cathodic protection test stations 3 (4) Sampling stations 4 (5) Meter boxes/vaults (All sizes) 5 (6) Fire lines 6 (7) Fire hydrants and valves 7 (8) Gate valves and Butterfly Valves 8 (9) Plugs, stubouts, dead-end lines 9 (10) Air Release valves (Manhole rim and vent pipe) 10 (11) Blow off valves (Manhole rim and valve lid) 11 (12) Pressure plane valves 12 (13) Cleaning wyes 13 (14) Casing pipe (each end) 14 b) Storm Sewer 15 (1) Top of pipe elevations and coordinates at the following locations: 16 (a) Every 250 linear feet 17 (b) Horizontal and vertical points of inflection, curvature, etc. 18 c) Sanitary Sewer 19 (1) Top of pipe elevations and coordinates for sanitary sewer lines at 20 the following locations: 21 (a) Every 250 linear feet 22 (b) Horizontal and vertical points of inflection, curvature, etc. 23 (c) Cleanouts 24 c. As-built survey will be performed in order to maintain complete and accurate 25 logs of control and survey work associated with meeting or exceeding the line 26 and grade required by these Specifications. 27 1) The Contractor remains fully responsible for the accuracy of the work and 28 the correction of it, as required. 29 2) Monitor line and grade continuously during construction. 30 3) Record deviation with respect to design line and grade once at each pipe 31 joint and submit daily records to City. 32 4) If the installation does not meet the specified tolerances, immediately notify 33 the City and correct the installation in accordance with the Contract 34 Documents. 35 d. Submit to the City copies of field notes, if requested, used to establish all lines 36 and grades and allow the City to check guidance system setup prior to 37 beginning each tunneling drive. 38 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 39 1.11 FIELD [SITE] CONDITIONS [NOT USED] 40 1.12 WARRANTY [NOT USED] 41 PART 2 - PRODUCTS [NOT USED] 42 PART 3 - EXECUTION 43 3.1 INSTALLERS [NOT USED] 44 01 71 23 CONSTRUCTION STAKING AND SURVEY Page 4 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 3.2 EXAMINATION [NOT USED] 1 3.3 PREPARATION [NOT USED] 2 3.4 APPLICATION 3 3.5 REPAIR / RESTORATION [NOT USED] 4 3.6 RE-INSTALLATION [NOT USED] 5 3.7 FIELD [OR] SITE QUALITY CONTROL 6 A. It is the Contractor’s responsibility to maintain all stakes and control data in accordance 7 with this Specification. 8 B. Do not change or relocate stakes or control data without approval from the City. 9 3.8 SYSTEM STARTUP [NOT USED] 10 3.9 ADJUSTING [NOT USED] 11 3.10 CLEANING [NOT USED] 12 3.11 CLOSEOUT ACTIVITIES [NOT USED] 13 3.12 PROTECTION [NOT USED] 14 3.13 MAINTENANCE [NOT USED] 15 3.14 ATTACHMENTS [NOT USED] 16 END OF SECTION 17 18 Revision Log DATE NAME SUMMARY OF CHANGE 19 01 74 23 CLEANING Page 1 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 SECTION 01 74 23 1 CLEANING 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Intermediate and final cleaning for Work not including special cleaning of closed 6 systems specified elsewhere 7 B. Deviations from this City of Denton Standard Specification 8 1. None. 9 C. Related Specification Sections include, but are not necessarily limited to: 10 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 11 2. Division 1 – General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Work associated with this Item is considered incidental to the various Items bid. 15 No separate payment will be allowed for this Item. 16 1.3 REFERENCES [NOT USED] 17 1.4 ADMINISTRATIVE REQUIREMENTS 18 A. Scheduling 19 1. Schedule cleaning operations so that dust and other contaminants disturbed by 20 cleaning process will not fall on newly painted surfaces. 21 2. Schedule final cleaning upon completion of Work and immediately prior to final 22 inspection. 23 1.5 SUBMITTALS [NOT USED] 24 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 25 1.7 CLOSEOUT SUBMITTALS [NOT USED] 26 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 27 1.9 QUALITY ASSURANCE [NOT USED] 28 1.10 STORAGE, AND HANDLING 29 A. Storage and Handling Requirements 30 1. Store cleaning products and cleaning wastes in containers specifically designed for 31 those materials. 32 01 74 23 CLEANING Page 2 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1 1.12 WARRANTY [NOT USED] 2 PART 2 - PRODUCTS 3 2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIEDPRODUCTS [NOT USED] 4 2.2 MATERIALS 5 A. Cleaning Agents 6 1. Compatible with surface being cleaned 7 2. New and uncontaminated 8 3. For manufactured surfaces 9 a. Material recommended by manufacturer 10 2.3 ACCESSORIES [NOT USED] 11 2.4 SOURCE QUALITY CONTROL [NOT USED] 12 PART 3 - EXECUTION 13 3.1 INSTALLERS [NOT USED] 14 3.2 EXAMINATION [NOT USED] 15 3.3 PREPARATION [NOT USED] 16 3.4 APPLICATION [NOT USED] 17 3.5 REPAIR / RESTORATION [NOT USED] 18 3.6 RE-INSTALLATION [NOT USED] 19 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 20 3.8 SYSTEM STARTUP [NOT USED] 21 3.9 ADJUSTING [NOT USED] 22 3.10 CLEANING 23 A. General 24 1. Prevent accumulation of wastes that create hazardous conditions. 25 2. Conduct cleaning and disposal operations to comply with laws and safety orders of 26 governing authorities. 27 3. Do not dispose of volatile wastes such as mineral spirits, oil or paint thinner in 28 storm or sanitary drains or sewers. 29 4. Dispose of degradable debris at an approved solid waste disposal site. 30 5. Dispose of nondegradable debris at an approved solid waste disposal site or in an 31 alternate manner approved by City and regulatory agencies. 32 01 74 23 CLEANING Page 3 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 6. Transport and deposit vegetative material removed as a result of work operations 1 off-site at a legal site in accordance with all applicable federal, state, and local laws 2 and regulations. 3 a. Removed vegetation will not be allowed to remain in piles or mounds on the 4 easement or surrounding property. 5 7. Handle materials in a controlled manner with as few handlings as possible. 6 8. Thoroughly clean, sweep, wash and polish all Work and equipment associated with 7 this project. 8 9. Remove all signs of temporary construction and activities incidental to construction 9 of required permanent Work. 10 10. If project is not cleaned to the satisfaction of the City, the City reserves the right to 11 have the cleaning completed at the expense of the Contractor. 12 11. Do not burn on-site. 13 B. Intermediate Cleaning during Construction 14 1. Keep Work areas clean so as not to hinder health, safety or convenience of 15 personnel in existing facility operations. 16 2. At maximum weekly intervals, dispose of waste materials, debris and rubbish. 17 3. Confine construction debris daily in strategically located container(s): 18 a. Cover to prevent blowing by wind 19 b. Store debris away from construction or operational activities 20 c. Haul from site at a minimum of once per week 21 4. Vacuum clean interior areas when ready to receive finish painting. 22 a. Continue vacuum cleaning on an as-needed basis, until Final Acceptance. 23 5. Prior to storm events, thoroughly clean site of all loose or unsecured items, which 24 may become airborne or transported by flowing water during the storm. 25 C. Interior Final Cleaning 26 1. Remove grease, mastic, adhesives, dust, dirt, stains, fingerprints, labels and other 27 foreign materials from sight-exposed surfaces. 28 2. Wipe all lighting fixture reflectors, lenses, lamps and trims clean. 29 3. Wash and shine glazing and mirrors. 30 4. Polish glossy surfaces to a clear shine. 31 5. Ventilating systems 32 a. Clean permanent filters and replace disposable filters if units were operated 33 during construction. 34 b. Clean ducts, blowers and coils if units were operated without filters during 35 construction. 36 6. Replace all burned out lamps. 37 7. Broom clean process area floors. 38 8. Mop office and control room floors. 39 D. Exterior (Site or Right of Way) Final Cleaning 40 1. Remove trash and debris containers from site. 41 a. Re-seed areas disturbed by location of trash and debris containers. 42 2. Sweep roadway to remove all rocks, pieces of asphalt, concrete or any other object 43 that may hinder or disrupt the flow of traffic along the roadway. 44 01 74 23 CLEANING Page 4 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised September 20, 2018 Effective July 1, 2024 3. Clean any interior areas including, but not limited to, vaults, manholes, structures, 1 junction boxes and inlets. 2 4. If no longer required for maintenance of erosion facilities, and upon approval by 3 City, remove erosion control from site. 4 5. Clean signs, lights, signals, etc. 5 3.11 CLOSEOUT ACTIVITIES [NOT USED] 6 3.12 PROTECTION [NOT USED] 7 3.13 MAINTENANCE [NOT USED] 8 3.14 ATTACHMENTS [NOT USED] 9 END OF SECTION 10 11 Revision Log DATE NAME SUMMARY OF CHANGE 12 01 77 19 CLOSEOUT REQUIREMENTS Page 1 of 3 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 SECTION 01 77 19 1 CLOSEOUT REQUIREMENTS 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. The procedure for closing out a contract 6 B. Deviations from this City of Denton Standard Specification 7 1. None. 8 C. Related Specification Sections include, but are not necessarily limited to: 9 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 10 2. Division 1 – General Requirements 11 3. Section 33 01 30 – Post Construction Closed Circuit Television (CCTV) Inspection 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Work associated with this Item is considered incidental to the various Items bid. 15 No separate payment will be allowed for this Item. 16 1.3 REFERENCES [NOT USED] 17 1.4 ADMINISTRATIVE REQUIREMENTS 18 A. Guarantees, Bonds and Affidavits 19 1. No application for final payment will be accepted until all guarantees, bonds, 20 certificates, licenses and affidavits required for Work or equipment as specified are 21 satisfactorily filed with the City. 22 B. Release of Liens or Claims 23 1. No application for final payment will be accepted until satisfactory evidence of 24 release of liens has been submitted to the City. 25 1.5 SUBMITTALS 26 A. Submit all required documentation to Project Manager. 27 1.6 INFORMATIONAL SUBMITTALS [NOT USED] 28 1.7 CLOSEOUT SUBMITTALS [NOT USED] 29 PART 2 - PRODUCTS [NOT USED] 30 01 77 19 CLOSEOUT REQUIREMENTS Page 2 of 3 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 PART 3 - EXECUTION 1 3.1 INSTALLERS [NOT USED] 2 3.2 EXAMINATION [NOT USED] 3 3.3 PREPARATION [NOT USED] 4 3.4 CLOSEOUT PROCEDURE 5 A. Prior to requesting Final Inspection, submit: 6 1. Project Record Documents in accordance with Section 01 78 39 7 2. Operation and Maintenance Data, if required, in accordance with Section 01 78 23 8 B. Prior to requesting Final Inspection, perform final cleaning in accordance with Section 9 01 74 23. 10 C. Final Inspection 11 1. After final cleaning, provide notice to the Project Manager and their duly appointed 12 representative that the Work is completed. 13 a. City reserves the right to deny request for Final Inspection if City determines 14 that the entire Work is not sufficiently complete to warrant a Final Inspection 15 b. The City will make an initial Final Inspection with the Contractor present. 16 c. Upon completion of this inspection, the City will notify the Contractor, in 17 writing within 10 business days, of any particulars in which this inspection 18 reveals that the Work is defective or incomplete. 19 2. Upon receiving written notice from the City, immediately undertake the Work 20 required to remedy deficiencies and complete the Work to the satisfaction of the 21 City. 22 3. Upon completion of Work associated with the items listed in the City's written 23 notice, inform the City, that the required Work has been completed. Upon receipt 24 of this notice, the City, in the presence of the Contractor, will make a subsequent 25 Final Inspection of the project. 26 4. Provide all special accessories required to place each item of equipment in full 27 operation. These special accessory items include, but are not limited to: 28 a. Specified spare parts 29 b. Adequate oil and grease as required for the first lubrication of the equipment 30 c. Initial fill up of all chemical tanks and fuel tanks 31 d. Light bulbs 32 e. Fuses 33 f. Vault keys 34 g. Handwheels 35 h. Other expendable items as required for initial start-up and operation of all 36 equipment 37 D. Supporting Documentation 38 1. Coordinate with the City Project Representative to complete the following 39 additional forms: 40 a. Final Payment Request 41 b. Statement of Contract Time 42 c. Affidavit of Payment and Release of Liens 43 01 77 19 CLOSEOUT REQUIREMENTS Page 3 of 3 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 d. Consent of Surety to Final Payment 1 E. Letter of Final Acceptance 2 1. When City has deemed the Work has been completed, and upon receiving all 3 Supporting Documentation, in accordance with General Conditions, City will issue 4 Letter of Final Acceptance and release the final payment request for payment. 5 F. Warranty Inspection for Wastewater Mains 6 1. A second television inspection conforming to the standards laid out in Section 33 7 01 30 shall be started by the Contractor no sooner than 630 calendar days and 8 finished no later than 690 calendar days after the date of issuance of the Letter of 9 Final Acceptance for the project by the City of Denton. 10 2. The second inspection shall include a complete televised inspection of each 11 manhole interior constructed or installed on the project (including cored manholes). 12 a. Should the second inspection indicate repairs that need to be made, these will 13 be performed by the Contractor at no cost to the City. 14 3. Failure of the Contractor to perform the second inspection or to make repairs 15 indicated by the second inspection shall be sufficient grounds for the City to take 16 action through the terms of the Maintenance Bond for the project to perform the 17 second inspection and make any repairs indicated. 18 3.5 REPAIR / RESTORATION [NOT USED] 19 3.6 RE-INSTALLATION [NOT USED] 20 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 21 3.8 SYSTEM STARTUP [NOT USED] 22 3.9 ADJUSTING [NOT USED] 23 3.10 CLEANING [NOT USED] 24 3.11 CLOSEOUT ACTIVITIES [NOT USED] 25 3.12 PROTECTION [NOT USED] 26 3.13 MAINTENANCE [NOT USED] 27 3.14 ATTACHMENTS [NOT USED] 28 END OF SECTION 29 30 Revision Log DATE NAME SUMMARY OF CHANGE 31 01 78 23 OPERATION AND MAINTENANCE DATA Page 1 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 SECTION 01 78 23 1 OPERATION AND MAINTENANCE DATA 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Product data and related information appropriate for City's maintenance and 6 operation of products furnished under Contract 7 2. Such products may include, but are not limited to: 8 a. Traffic Controllers 9 b. Irrigation Controllers (to be operated by the City) 10 c. Butterfly Valves 11 B. Deviations from this City of Denton Standard Specification 12 1. None. 13 C. Related Specification Sections include, but are not necessarily limited to: 14 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 15 2. Division 1 – General Requirements 16 1.2 PRICE AND PAYMENT PROCEDURES 17 A. Measurement and Payment 18 1. Work associated with this Item is considered incidental to the various Items bid. 19 No separate payment will be allowed for this Item. 20 1.3 REFERENCES [NOT USED] 21 1.4 ADMINISTRATIVE REQUIREMENTS 22 A. Schedule 23 1. Submit manuals in final form to the City within 30 calendar days of product 24 shipment to the project site. 25 1.5 SUBMITTALS 26 A. Submittals shall be in accordance with Section 01 33 00. All submittals shall be 27 approved by the City prior to delivery. 28 1.6 INFORMATIONAL SUBMITTALS 29 A. Submittal Form 30 1. Prepare data in form of an instructional manual for use by City personnel. 31 2. Format 32 a. Size: 8 ½ inches x 11 inches 33 b. Paper 34 1) 40 pound minimum, white, for typed pages 35 2) Holes reinforced with plastic, cloth or metal 36 c. Text: Manufacturer’s printed data, or neatly typewritten 37 01 78 23 OPERATION AND MAINTENANCE DATA Page 2 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 d. Drawings 1 1) Provide reinforced punched binder tab, bind in with text 2 2) Reduce larger drawings and fold to size of text pages. 3 e. Provide fly-leaf for each separate product, or each piece of operating 4 equipment. 5 1) Provide typed description of product, and major component parts of 6 equipment. 7 2) Provide indexed tabs. 8 f. Cover 9 1) Identify each volume with typed or printed title "OPERATING AND 10 MAINTENANCE INSTRUCTIONS". 11 2) List: 12 a) Title of Project 13 b) Identity of separate structure as applicable 14 c) Identity of general subject matter covered in the manual 15 3. Binders 16 a. Commercial quality 3-ring binders with durable and cleanable plastic covers 17 b. When multiple binders are used, correlate the data into related consistent 18 groupings. 19 4. Provide an electronic form of the O&M Manual. 20 B. Manual Content 21 1. Neatly typewritten table of contents for each volume, arranged in systematic order 22 a. Contractor, name of responsible principal, address and telephone number 23 b. A list of each product required to be included, indexed to content of the volume 24 c. List, with each product: 25 1) The name, address and telephone number of the subcontractor or installer 26 2) A list of each product required to be included, indexed to content of the 27 volume 28 3) Identify area of responsibility of each 29 4) Local source of supply for parts and replacement 30 d. Identify each product by product name and other identifying symbols as set 31 forth in Contract Documents. 32 2. Product Data 33 a. Include only those sheets which are pertinent to the specific product. 34 b. Annotate each sheet to: 35 1) Clearly identify specific product or part installed 36 2) Clearly identify data applicable to installation 37 3) Delete references to inapplicable information 38 3. Drawings 39 a. Supplement product data with drawings as necessary to clearly illustrate: 40 1) Relations of component parts of equipment and systems 41 2) Control and flow diagrams 42 b. Coordinate drawings with information in Project Record Documents to assure 43 correct illustration of completed installation. 44 c. Do not use Project Record Drawings as maintenance drawings. 45 4. Written text, as required to supplement product data for the particular installation: 46 a. Organize in consistent format under separate headings for different procedures. 47 b. Provide logical sequence of instructions of each procedure. 48 01 78 23 OPERATION AND MAINTENANCE DATA Page 3 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 5. Copy of each warranty, bond and service contract issued 1 a. Provide information sheet for City personnel giving: 2 1) Proper procedures in event of failure 3 2) Instances which might affect validity of warranties or bonds 4 C. Manual for Materials and Finishes 5 1. Submit 5 hard copies and 1 digital copy of complete manual in final form. 6 2. Content, for architectural products, applied materials and finishes: 7 a. Manufacturer's data, giving full information on products 8 1) Catalog number, size, composition 9 2) Color and texture designations 10 3) Information required for reordering special manufactured products 11 b. Instructions for care and maintenance 12 1) Manufacturer's recommendation for types of cleaning agents and methods 13 2) Cautions against cleaning agents and methods which are detrimental to 14 product 15 3) Recommended schedule for cleaning and maintenance 16 3. Content, for moisture protection and weather exposure products: 17 a. Manufacturer's data, giving full information on products 18 1) Applicable standards 19 2) Chemical composition 20 3) Details of installation 21 b. Instructions for inspection, maintenance and repair 22 D. Manual for Equipment and Systems 23 1. Submit 5 hard copies and 1 digital copy of complete manual in final form. 24 2. Content, for each unit of equipment and system, as appropriate: 25 a. Description of unit and component parts 26 1) Function, normal operating characteristics and limiting conditions 27 2) Performance curves, engineering data and tests 28 3) Complete nomenclature and commercial number of replaceable parts 29 b. Operating procedures 30 1) Start-up, break-in, routine and normal operating instructions 31 2) Regulation, control, stopping, shut-down and emergency instructions 32 3) Summer and winter operating instructions 33 4) Special operating instructions 34 c. Maintenance procedures 35 1) Routine operations 36 2) Guide to "trouble shooting" 37 3) Disassembly, repair and reassembly 38 4) Alignment, adjusting and checking 39 d. Servicing and lubrication schedule 40 1) List of lubricants required 41 e. Manufacturer's printed operating and maintenance instructions 42 f. Description of sequence of operation by control manufacturer 43 1) Predicted life of parts subject to wear 44 2) Items recommended to be stocked as spare parts 45 g. As installed control diagrams by controls manufacturer 46 h. Each contractor's coordination drawings 47 1) As installed color coded piping diagrams 48 01 78 23 OPERATION AND MAINTENANCE DATA Page 4 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 i. Charts of valve tag numbers, with location and function of each valve 1 j. List of original manufacturer's spare parts, manufacturer's current prices, and 2 recommended quantities to be maintained in storage 3 k. Other data as required under pertinent Sections of Specifications 4 3. Content, for each electric and electronic system, as appropriate: 5 a. Description of system and component parts 6 1) Function, normal operating characteristics, and limiting conditions 7 2) Performance curves, engineering data and tests 8 3) Complete nomenclature and commercial number of replaceable parts 9 b. Circuit directories of panelboards 10 1) Electrical service 11 2) Controls 12 3) Communications 13 c. As installed color coded wiring diagrams 14 d. Operating procedures 15 1) Routine and normal operating instructions 16 2) Sequences required 17 3) Special operating instructions 18 e. Maintenance procedures 19 1) Routine operations 20 2) Guide to "trouble shooting" 21 3) Disassembly, repair and reassembly 22 4) Adjustment and checking 23 f. Manufacturer's printed operating and maintenance instructions 24 g. List of original manufacturer's spare parts, manufacturer's current prices, and 25 recommended quantities to be maintained in storage 26 h. Other data as required under pertinent Sections of Specifications 27 4. Prepare and include additional data when the need for such data becomes apparent 28 during instruction of City's personnel. 29 1.7 CLOSEOUT SUBMITTALS [NOT USED] 30 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 31 1.9 QUALITY ASSURANCE 32 A. Provide operation and maintenance data by personnel with the following criteria: 33 1. Trained and experienced in maintenance and operation of described products 34 2. Skilled as technical writer to the extent required to communicate essential data 35 3. Skilled as draftsman competent to prepare required drawings 36 01 78 23 OPERATION AND MAINTENANCE DATA Page 5 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1 1.11 FIELD [SITE] CONDITIONS [NOT USED] 2 1.12 WARRANTY [NOT USED] 3 PART 2 - PRODUCTS [NOT USED] 4 PART 3 - EXECUTION [NOT USED] 5 END OF SECTION 6 7 Revision Log DATE NAME SUMMARY OF CHANGE 8 01 78 39 PROJECT RECORD DOCUMENTS Page 1 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 SECTION 01 78 39 1 PROJECT RECORD DOCUMENTS 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A.Section Includes: 5 1. Work associated with the documenting the project and recording changes to project 6 documents, including: 7 a. Record Drawings 8 B. Deviations from this City of Denton Standard Specification 9 1. None. 10 C. Related Specification Sections include, but are not necessarily limited to: 11 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 12 2. Division 1 – General Requirements 13 1.2 PRICE AND PAYMENT PROCEDURES 14 A. Measurement and Payment 15 1. Work associated with this Item is considered incidental to the various Items bid. 16 No separate payment will be allowed for this Item. 17 1.3 REFERENCES [NOT USED] 18 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 19 1.5 SUBMITTALS 20 A. Prior to submitting a request for Final Inspection, deliver Project Record Documents to 21 Project Manager. 22 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 23 1.7 CLOSEOUT SUBMITTALS [NOT USED] 24 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 25 1.9 QUALITY ASSURANCE 26 A.Accuracy of Records 27 1. Thoroughly coordinate changes within the Record Documents, making adequate 28 and proper entries on each page of Specifications and each sheet of Drawings and 29 other Documents where such entry is required to show the change properly. 30 2. Accuracy of records shall be such that future search for items shown in the Contract 31 Documents may rely reasonably on information obtained from the approved Project 32 Record Documents. 33 3. To facilitate accuracy of records, make entries within 24 hours after receipt of 34 information that the change has occurred. 35 36 01 78 39 PROJECT RECORD DOCUMENTS Page 2 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 4. Provide factual information regarding all aspects of the Work, both concealed and 1 visible, to enable future modification of the Work to proceed without lengthy and 2 expensive site measurement, investigation and examination. 3 1.10 STORAGE AND HANDLING 4 A.Storage and Handling Requirements 5 1. Maintain the job set of Record Documents, which shall include the Drawings and 6 the Project Manual, completely protected from deterioration and from loss and 7 damage until completion of the Work and transfer of all recorded data to the final 8 Project Record Documents. 9 2. In the event of loss of recorded data, use means necessary to again secure the data 10 to the City's approval. 11 a. In such case, provide replacements to the standards originally required by the 12 Contract Documents. 13 1.11 FIELD [SITE] CONDITIONS [NOT USED] 14 1.12 WARRANTY [NOT USED] 15 PART 2 - PRODUCTS 16 2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIED PRODUCTS [NOT USED] 17 2.2 RECORD DOCUMENTS 18 A.Job set 19 1. Promptly following receipt of the Notice to Proceed, secure from the City, at no 20 charge to the Contractor, 1 complete set of all Documents comprising the Contract. 21 B. Final Record Documents 22 1. At a time nearing the completion of the Work and prior to Final Inspection, provide 23 the City 1 complete set of all Final Record Drawings in the Contract. 24 2.3 ACCESSORIES [NOT USED] 25 2.4 SOURCE QUALITY CONTROL [NOT USED] 26 PART 3 - EXECUTION 27 3.1 INSTALLERS [NOT USED] 28 3.2 EXAMINATION [NOT USED] 29 3.3 PREPARATION [NOT USED] 30 3.4 MAINTENANCE DOCUMENTS 31 A.Maintenance of Job Set 32 1. Immediately upon receipt of the job set, identify each of the Documents with the 33 title, "RECORD DOCUMENTS - JOB SET". The Job set shall include the 34 Drawings and the Project Manual. 35 01 78 39 PROJECT RECORD DOCUMENTS Page 3 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 2. Preservation 1 a. Considering the Contract completion time, the probable number of occasions 2 upon which the job set must be taken out for new entries and for examination, 3 and the conditions under which these activities will be performed, devise a 4 suitable method for protecting the job set. 5 b. Do not use the job set for any purpose except entry of new data and for review 6 by the City, until start of transfer of data to final Project Record Documents. 7 c. Maintain the job set at the site of work. 8 3. Coordination with Construction Survey 9 a. At a minimum, in accordance with the intervals set forth in Section 01 71 23, 10 clearly mark any deviations from Contract Documents associated with 11 installation of the infrastructure. 12 4. Making entries on Drawings and Specifications 13 a. Record any deviations from Contract Documents on Drawings and in the 14 Specifications if applicable. 15 b. Use an erasable colored pencil (not ink or indelible pencil), clearly describe the 16 change by graphic line and note as required. 17 c. Date all entries. 18 d. Call attention to the entry by a "cloud" drawn around the area or areas affected. 19 e. In the event of overlapping changes, use different colors for the overlapping 20 changes. 21 5. Conversion of schematic layouts 22 a. In some cases on the Drawings, arrangements of conduits, circuits, piping, 23 ducts, and similar items, are shown schematically and are not intended to 24 portray precise physical layout. 25 1) Final physical arrangement is determined by the Contractor, subject to the 26 City's approval. 27 2) However, design of future modifications of the facility may require 28 accurate information as to the final physical layout of items which are 29 shown only schematically on the Drawings. 30 b. Show on the job set of Record Drawings, by dimension accurate to within 1 31 inch, the centerline of each run of items. 32 1) Final physical arrangement is determined by the Contractor, subject to the 33 City's approval. 34 2) Show, by symbol or note, the vertical location of the Item ("under slab", "in 35 ceiling plenum", "exposed", and the like). 36 3) Make all identification sufficiently descriptive that it may be related 37 reliably to the Specifications. 38 c. The City may waive the requirements for conversion of schematic layouts 39 where, in the City's judgment, conversion serves no useful purpose. However, 40 do not rely upon waivers being issued except as specifically issued in writing 41 by the City. 42 B. Final Project Record Documents 43 1. Transfer of data to Drawings and Specifications 44 a. Carefully transfer change data shown on the job set of Record Drawings and 45 Project Manual if applicable, to the corresponding final documents, 46 coordinating the changes as required. 47 01 78 39 PROJECT RECORD DOCUMENTS Page 4 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 b. Clearly indicate at each affected detail and other Drawing a full description of 1 changes made during construction, and the actual location of items. 2 c. Call attention to each entry by drawing a "cloud" around the area or areas 3 affected. 4 d. Make changes neatly, consistently and with the proper media to assure 5 longevity and clear reproduction. 6 e. Provide GPS coordinates for all underground utility appurtenances, bends, 7 fittings, valves, manholes, junction boxes or other structures. This requirement 8 shall encompass all water, sanitary sewer, or drainage improvements. 9 f. Record Drawing documents shall be submitted in an electronic format (.pdf). 10 11 2. Transfer of data to other Documents 12 a. If the Documents, other than Drawings, have been kept clean during progress of 13 the Work, and if entries thereon have been orderly to the approval of the City, 14 the job set of those Documents, other than Drawings, will be accepted as final 15 Record Documents. 16 b. If any such Document is not so approved by the City, secure a new copy of that 17 Document from the City at the City's usual charge for reproduction and 18 handling, and carefully transfer the change data to the new copy to the approval 19 of the City. 20 3.5 REPAIR / RESTORATION [NOT USED] 21 3.6 RE-INSTALLATION [NOT USED] 22 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 23 3.8 SYSTEM STARTUP [NOT USED] 24 3.9 ADJUSTING [NOT USED] 25 3.10 CLEANING [NOT USED] 26 3.11 CLOSEOUT ACTIVITIES [NOT USED] 27 3.12 PROTECTION [NOT USED] 28 3.13 MAINTENANCE [NOT USED] 29 3.14 ATTACHMENTS [NOT USED] 30 END OF SECTION 31 32 Revision Log DATE NAME SUMMARY OF CHANGE 6/14/2024 Added GPS and electronic format requirements to Record Drawings under 3.4.B. 33 02 41 13 SELECTIVE SITE DEMOLITION Page 1 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 02 41 13 1 SELECTIVE SITE DEMOLITION 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Removal and disposal of: 6 a. Steps 7 b. Fence 8 c. Guardrail 9 d. Mailbox 10 e. Riprap 11 f. Stormwater Structure 12 g. Retaining Walls Less Than 4 Feet 13 h. Retaining Walls Greater Than 4 Feet 14 B. Deviations from this City of Denton Standard Specification: 15 1. None. 16 C. Related Specification Sections include but are not limited to: 17 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 18 Contract. 19 2. Division 1 - General Requirements. 20 3. Section 02 41 14 – Utility Removal/Abandonment. 21 4. Section 02 41 15 – Paving Removal. 22 1.2 PRICE AND PAYMENT PROCEDURES 23 A. Measurement and Payment 24 1. Removal of Stairs 25 a. Measurement 26 1) Measured per square foot of horizontal surfaces only of Removal of Stairs. 27 b. Payment 28 1) The work performed and materials furnished in accordance with this item 29 and measured as provided under “Measurement” will be paid for at the unit 30 price bid per square foot of horizontal surfaces only for Removal of Stairs. 31 c. The price bid shall include: 32 1) Removal of stairs constructed of any material (i.e. concrete, wood, metal, 33 etc) 34 2) Sawing 35 3) Loading 36 4) Unloading 37 5) Storing 38 6) Hauling 39 7) Disposal 40 8) Clean-up 41 02 41 13 SELECTIVE SITE DEMOLITION Page 2 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 9) Repair adjacent sidewalk or pavement damaged by the removal of steps 1 2. Removal of Fence 2 a. Measurement 3 1) Measured per linear foot of Removal of Fence. 4 b. Payment 5 1) The work performed and materials furnished in accordance with this item 6 and measured as provided under “Measurement” will be paid for at the unit 7 price bid per linear foot for Removal of Fence. 8 c. The price bid shall include: 9 1) Removal of all post types 10 2) Removal of all fence types 11 3) Removal of all gate types 12 4) Removal of post foundations 13 5) Loading 14 6) Unloading 15 7) Storing 16 8) Hauling 17 9) Disposal 18 10) Clean-up 19 3. Removal of Guardrail 20 a. Measurement 21 1) Measured per linear foot of Removal of Guardrail. 22 b. Payment 23 1) The work performed and materials furnished in accordance with this item 24 and measured as provided under “Measurement” will be paid for at the unit 25 price bid per linear foot for Removal of Guardrail. 26 c. The price bid shall include: 27 1) Removal of all post types 28 2) Removal of all guardrail types 29 3) Removal of post foundations 30 4) Removal of concrete mow strip 31 5) Removal of all end terminal types 32 6) Loading 33 7) Unloading 34 8) Storing 35 9) Hauling 36 10) Disposal 37 11) Clean-up 38 4. Removal of Mailbox 39 a. Measurement 40 1) Measured per each Removal of Mailbox. 41 b. Payment 42 1) The work performed and materials furnished in accordance with this item 43 and measured as provided under “Measurement” will be paid for at the unit 44 price bid per each for Removal of Mailbox. 45 c. The price bid shall include: 46 1) Removal of all post types 47 2) Removal of post foundations 48 02 41 13 SELECTIVE SITE DEMOLITION Page 3 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3) Removal of all mailbox types 1 4) Removal of mailbox bank 2 5) Removal of all brick, concrete block, stone façade, or any other decorative 3 and structural material used to construct a mailbox 4 6) Temporary mailbox, mailbox bank, or other form of mail access 5 7) Coordination with USPS and property owner 6 8) Loading 7 9) Unloading 8 10) Storing 9 11) Hauling 10 12) Salvaging or disposal 11 13) Clean-up 12 5. Removal of Riprap 13 a. Measurement 14 1) Measured per square yard of Removal of Riprap 15 b. Payment 16 1) The work performed and materials furnished in accordance with this item 17 and measured as provided under “Measurement” will be paid for at the unit 18 price bid per square yard for Removal of Riprap. 19 c. The price bid shall include: 20 1) Removal of all rock at all sizes and types 21 2) Removal of concrete at all depths 22 3) Removal of reinforcing 23 4) Removal of grout 24 5) Removal of bedding material and filter fabric 25 6) Loading 26 7) Unloading 27 8) Storing 28 9) Hauling 29 10) Salvaging or disposal 30 11) Clean-up 31 6. Removal of Stormwater Structure 32 a. Measurement 33 1) Measured per each Removal of Stormwater Structure 34 b. Payment 35 1) The work performed and materials furnished in accordance with this item 36 and measured as provided under “Measurement” will be paid for at the unit 37 price bid per each for Removal of Stormwater Structure. 38 c. The price bid shall include: 39 1) Removal of all headwalls, wingwalls, and end treatments at all sizes and 40 types 41 2) Removal of concrete at all depths 42 3) Removal of reinforcing 43 4) Removal of grout 44 5) Removal of bedding material and filter fabric 45 6) Temporary shoring 46 7) Loading 47 8) Unloading 48 02 41 13 SELECTIVE SITE DEMOLITION Page 4 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 9) Storing 1 10) Hauling 2 11) Backfilling 3 12) Salvaging or disposal 4 13) Clean-up 5 7. Removal of Retaining Wall Less Than 4 Feet 6 a. Measurement 7 1) Measured per linear foot of Removal of Retaining Wall Less Than 4 Feet. 8 b. Payment 9 1) The work performed and materials furnished in accordance with this item 10 and measured as provided under “Measurement” will be paid for at the unit 11 price bid per linear foot for Removal of Retaining Wall Less Than 4 Feet. 12 c. The price bid shall include: 13 1) Removal of footings of all types and depths 14 2) Removal of wall 15 3) Removal of reinforcing 16 4) Shoring wall construction and design (if needed) 17 5) Loading 18 6) Unloading 19 7) Storing 20 8) Hauling 21 9) Salvaging or disposal 22 10) Clean-up 23 8. Removal of Retaining Wall Greater Than 4 Feet 24 a. Measurement 25 1) Measured per linear foot of Removal of Retaining Wall Greater Than 4 26 Feet. 27 b. Payment 28 1) The work performed and materials furnished in accordance with this item 29 and measured as provided under “Measurement” will be paid for at the unit 30 price bid per linear foot for Removal of Retaining Wall Greater Than 4 31 Feet. 32 c. The price bid shall include: 33 1) Removal of footings of all types and depths 34 2) Removal of wall 35 3) Removal of reinforcing 36 4) Shoring wall construction and design (if needed) 37 5) Loading 38 6) Unloading 39 7) Storing 40 8) Hauling 41 9) Salvaging or disposal 42 10) Clean-up 43 1.3 REFERENCES 44 A. Abbreviations and Acronyms 45 1. TMUTCD – Texas Manual on Uniform Traffic Control Devices 46 1.4 ADMINISTRATIVE REQUIREMENTS 47 02 41 13 SELECTIVE SITE DEMOLITION Page 5 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 A. Sequencing 1 2 1. Sidewalk Construction 3 a. Where existing sidewalks are to be closed during Paving Removal activities: 4 1) Utilize pedestrian/sidewalk detour route specified in the Drawings 5 a) If no detour route is provided, submit a pedestrian/sidewalk detour 6 route that has been signed and sealed by a registered professional 7 engineer to City for review. 8 2) The pedestrian/sidewalk detour route will be subsidiary to pertinent Traffic 9 Control items included with the project. 10 b. Install all sidewalk detours and closures in accordance with the TMUTCD, 11 State, and local guidelines. 12 c. Provide any traffic control devices in accordance with Section 34 71 13. 13 1.5 SUBMITTALS 14 A. Submittals shall be in accordance with Section 01 33 00. 15 B. All submittals shall be approved by the City prior to delivery. 16 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 17 A. Shop Drawings 18 1. Temporary Shoring Design 19 a. Submit a temporary shoring design for review and approval prior to removal of 20 retaining walls or any other removal activities requiring a shoring wall. 21 b. The design of a shoring wall is considered subsidiary to the appropriate bid 22 item. 23 c. Provide a signed and sealed shoring wall design by an engineer licensed in the 24 state of Texas for all shoring walls unless otherwise specified in the Drawings 25 or directed by City. 26 B. Informational Submittal 27 1. Equipment Information 28 a. Submittal for all major equipment to include: 29 1) Equipment name 30 2) Size 31 3) Intended use 32 1.7 CLOSEOUT SUBMITTALS [NOT USED] 33 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 34 1.9 QUALITY ASSURANCE [NOT USED] 35 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 36 1.11 FIELD CONDITIONS [NOT USED] 37 1.12 WARRANTY [NOT USED] 38 02 41 13 SELECTIVE SITE DEMOLITION Page 6 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 PART 2 - PRODUCTS [NOT USED] 1 2.1 CITY-SUPPLIED PRODUCTS [NOT USED] 2 2.2 MATERIALS [NOT USED] 3 2.3 ACCESSORIES [NOT USED] 4 2.4 SOURCE QUALITY CONTROL [NOT USED] 5 PART 3 - EXECUTION 6 3.1 INSTALLERS [NOT USED] 7 3.2 EXAMINATION [NOT USED] 8 3.3 PREPARATION 9 A. Surface Preparation 10 1. Verify all removal limits prior to construction unless otherwise directed by the City. 11 3.4 SITE DEMOLITION 12 A. Disposal of materials 13 1. Accept ownership and dispose of all materials removed. 14 2. Dispose of all material in accordance with Federal, State, and local laws and 15 regulations. 16 3. The disposal of any material removed as part of Selective Site Demolition is 17 considered subsidiary to the applicable items. 18 B. Removal of Stairs 19 1. Sawing 20 a. Perform sawing activities for concrete paving and sidewalk in accordance with 21 Section 02 41 15. 22 2. Minimum Limits of Stair Removal 23 a. If adjacent stairs are to remain, remove stair to the nearest whole stair. Do not 24 saw cut an existing stair. 25 b. If stairs to be removed are adjacent to a sidewalk, remove stairs to the nearest 26 sidewalk joint. 27 C. Removal of Fence 28 1. Remove all fence components above and below ground. 29 2. Backfill holes with acceptable fill material. 30 3. Compact per Drawings. 31 4. Use caution in removing any fence material. 32 5. Coordinate with property owners as needed to maintain a fenced area at all times 33 especially when animals are kept within the fencing. 34 6. Contractor is responsible for maintaining fencing and installing temporary fencing 35 as needed during construction. 36 02 41 13 SELECTIVE SITE DEMOLITION Page 7 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 7. Contractor is responsible for providing fencing at all times. 1 8. Installing and removing temporary fencing when necessary is subsidiary to 2 Removal of Fence. 3 D. Removal of Guardrail 4 1. Remove rail elements in original lengths. 5 2. Remove fittings from the posts and the metal rail prior to removing the posts. Once 6 the fittings and metal railing is removed, remove the posts. 7 3. Remove and replace any guardrail to remain that is damaged during construction 8 activities at no cost to the City. 9 4. Completely remove posts and any paving material surrounding the posts. 10 5. Backfill any holes with acceptable fill material. 11 E. Removal of Mailbox 12 1. Advance Coordination: 13 a. Coordinate with property owner prior to removal of mailbox. 14 b. Coordinate with local post office prior to removal. Provide approach and access 15 space in accordance to post office requirements. 16 c. Provide the City and the property owner with a written confirmation of the 17 timeframe. 18 2. For non-custom or decorative postal mailboxes, salvage existing materials for 19 reuse. 20 3. For all custom and/or decorative mailboxes: 21 a. Replace the custom mailbox with a standard post office approved mailbox. No 22 custom mailboxes will be constructed unless specified in the Drawings or 23 directed by the City. 24 b. If property owner wishes to remove or salvage a custom mailbox, determine an 25 agreed upon timeframe with the City, the Contractor, and the property owner 26 for removal. 27 4. The Contractor is responsible for providing a temporary mailbox during 28 construction for any mailbox that is proposed to be removed and relocated, 29 reinstalled, or replaced. 30 5. Maintain mailbox and/or mail delivery for duration of project. No separate pay will 31 be provided. 32 F. Removal of Riprap 33 1. Remove concrete riprap to the nearest joint. 34 2. Conform to concrete sawing requirements in Section 02 41 15. 35 G. Removal of Stormwater Structure 36 1. Remove entire structure or to the nearest joint as specified in the Drawings. 37 2. Removal includes all components of the stormwater structure including footings, 38 toe walls, and mitered RCP ends. 39 a. In accordance with concrete sawing requirements in Section 02 41 15. 40 b. In accordance with utility pipe removal requirements in Section 02 41 14. 41 02 41 13 SELECTIVE SITE DEMOLITION Page 8 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3. Provide temporary erosion control protection for adjacent side slopes, drainage 1 channels, and ditches. Temporary erosion control is considered subsidiary to the 2 Removal of Stormwater Structures. 3 4. Provide temporary shoring, if required. 4 5. Repair any portion of remaining structure that is damaged as a result of removal 5 activities. 6 6. Do not use explosives to remove portions of the existing structure. 7 7. Do not use a demolition ball, other swinging weight, or impact equipment unless 8 approved in writing by City. 9 8. Use pneumatic or hydraulic tools for final removal of concrete at the removal 10 limits. 11 9. Use removal equipment that will not damage any remaining portion of the 12 stormwater structure. 13 H. Removal of Retaining Wall Less Than 4 Feet 14 1. Any decorative or landscape retaining wall within the City’s right-of-way will not 15 be replaced unless required for grading purposes. 16 2. A retaining wall is required if the slope to tie back to existing ground within the 17 City’s right-of-way is steeper than 4:1. 18 3. If a retaining wall is required: 19 a. Determine if a retaining wall is required before removing any decorative or 20 landscape retaining walls. 21 b. Request approval from City before removing decorative or landscape retaining 22 wall. 23 4. If a retaining wall is not required: 24 a. Remove any decorative or landscape retaining wall within the City’s right-of-25 way and re-grade to a maximum of 4:1 slope. 26 b. Do not replace the decorative or landscape retaining wall. 27 5. Remove wall to the nearest existing joint where possible. If not possible, obtain 28 approval from the City for removal limits. 29 6. In accordance with concrete sawing requirements in Section 02 41 15. 30 7. Removal includes all components of the retaining wall. 31 8. Do not use explosives to remove portions of the existing structure. 32 9. Do not use a demolition ball, other swinging weight, or impact equipment unless 33 approved in writing. 34 10. Use pneumatic or hydraulic tools for final removal of concrete at the removal 35 limits. 36 11. Use removal equipment that will not damage any remaining portion of the retaining 37 wall. 38 12. Construct an approved shoring wall when necessary to provide a safe environment 39 for workers and the travelling public. 40 I. Removal of Retaining Wall Greater Than 4 Feet 41 1. Remove wall to the nearest existing joint. 42 2. In accordance with concrete sawing requirements in Section 02 41 15. 43 02 41 13 SELECTIVE SITE DEMOLITION Page 9 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3. Removal includes all components of the retaining wall including footings. 1 4. Do not use explosives to remove portions of the existing structure. 2 5. Do not use a demolition ball, other swinging weight, or impact equipment unless 3 approved in writing. 4 6. Use pneumatic or hydraulic tools for final removal of concrete at the removal 5 limits. 6 7. Use removal equipment that will not damage any remaining portion of the retaining 7 wall. 8 8. Construct an approved shoring wall when necessary to provide a safe environment 9 for workers and the travelling public. 10 3.5 REPAIR 11 A. Repair the following at no cost to the City if any damage is caused due to Selective Site 12 Demolition activities: 13 1. Adjacent concrete or asphalt pavement 14 2. Adjacent sidewalk 15 3. Adjacent curb or curb and gutter 16 4. Remaining portions of stormwater structures 17 5. Remaining portions of retaining walls 18 6. Subgrade or base material 19 7. Utility piping, structures, and appurtenances 20 8. Irrigation systems including but not limited to sprinkler heads, conduit, and pipe. 21 9. Landscape beds or planters 22 10. Decorative hardscape or landscape features 23 3.6 RE-INSTALLATION [NOT USED] 24 3.7 SITE QUALITY CONTROL [NOT USED] 25 3.8 SYSTEM STARTUP [NOT USED] 26 3.9 ADJUSTING [NOT USED] 27 3.10 CLEANING [NOT USED] 28 3.11 CLOSEOUT ACTIVITIES [NOT USED] 29 3.12 PROTECTION [NOT USED] 30 3.13 MAINTENANCE [NOT USED] 31 3.14 ATTACHMENTS [NOT USED] 32 02 41 13 SELECTIVE SITE DEMOLITION Page 10 of 10 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1 END OF SECTION 2 3 Revision Log DATE NAME SUMMARY OF CHANGE 4 02 41 14 UTILITY REMOVAL AND ABANDONMENT Page 1 of 13 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 02 41 14 1 UTILITY REMOVAL AND ABANDONMENT 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Removal, abandonment, or salvaging of the following utilities: 6 a. General Utility Items: 7 1) Utility Line Abandonment by Grout Fill – Water, Sanitary Sewer, 8 Stormwater 9 2) Utility Line Removal, Separate Trench – Water, Sanitary Sewer, 10 Stormwater 11 3) Utility Line Removal, Same Trench – Water, Sanitary Sewer, Stormwater 12 4) Utility Manhole Abandonment – Water, Sanitary Sewer, Stormwater 13 5) Utility Manhole Removal – Water, Sanitary Sewer, Stormwater 14 6) Plugging of Utility Lines – Water, Sanitary Sewer, Stormwater 15 7) Utility Junction Structure Removal – Sanitary Sewer, Stormwater 16 b. Water Specific Items: 17 1) Water Valve Removal 18 2) Water Valve Removal and Salvage 19 3) Water Valve Abandonment 20 4) Fire Hydrant Removal and Salvage 21 5) Water Meter Removal and Salvage 22 6) Concrete Water Vault Removal 23 7) Cathodic Test Station Abandonment 24 c. Stormwater Specific Items: 25 1) Stormwater Inlet Removal 26 2) Headwall/SET Removal 27 3) Trench Drain Removal 28 B. Deviations from this City of Denton Standard Specification: 29 1. None. 30 C. Related Specification Sections include but are not limited to: 31 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 32 Contract. 33 2. Division 1 - General Requirements. 34 3. Section 33 05 05 – Utility Trench Excavation, Embedment, and Backfill. 35 4. Section 33 05 15 – Installation of Carrier Pipe in Casing or Tunnel Liner Plate. 36 5. Section 03 34 13 – Controlled Low Strength Material (CLSM). 37 6. Section 03 30 00 – Cast-In-Place Concrete. 38 7. Section 33 14 10 – Ductile Iron Pipe and Fittings. 39 8. Section 33 14 12 – Concrete Pressure Pipe, Bar-Wrapped Steel Cylinder Type. 40 9. Section 33 14 13 – Buried Steel Pipe 41 02 41 14 UTILITY REMOVAL AND ABANDONMENT Page 2 of 13 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1 1.2 PRICE AND PAYMENT PROCEDURES 2 A. Measurement and Payment 3 1. General Utility Items 4 a. Utility Line Abandonment by Grout Fill 5 1) Measurement 6 a) Measured horizontally along the ground surface of existing utility line 7 to be abandoned. 8 2) Payment 9 a) The work performed and materials furnished in accordance with this 10 item and measured as provided under “Measurement” will be paid for 11 at the unit price bid per linear foot for “Grout Fill Utility Line” for: 12 (1) Various Sizes. 13 3) The price bid shall include: 14 a) Dewatering (as required) 15 b) Disposal of sewage (as required) 16 c) Furnishing and installing low density cellular grout or CLSM 17 d) Water 18 e) Pavement Removal 19 f) Excavation 20 g) Hauling 21 h) Disposal of excess materials 22 i) Furnishing, placement, and compaction of backfill 23 j) Clean-up 24 b. Utility Line Removal, Separate Trench 25 1) Measurement 26 a) Measured horizontally along the ground surface of existing utility line 27 to be removed. 28 2) Payment 29 a) The work performed and materials furnished in accordance with this 30 item and measured as provided under “Measurement” will be paid for 31 at the unit price bid per linear foot for “Remove Utility Line” for: 32 (1) Various Sizes. 33 3) The price bid shall include: 34 a) Dewatering (as required) 35 b) Disposal of sewage (as required) 36 c) Pavement Removal 37 d) Excavation 38 e) Hauling 39 f) Disposal of excess materials 40 g) Furnishing, placement, and compaction of backfill 41 h) Clean-up 42 c. Utility Line Removal, Same Trench 43 1) Measurement 44 a) This item is considered subsidiary to the proposed utility line being 45 installed. 46 2) Payment 47 02 41 14 UTILITY REMOVAL AND ABANDONMENT Page 3 of 13 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 a) The work performed and materials furnished in accordance with this 1 item are subsidiary to the unit price bid per linear foot of utility pipe 2 installed. 3 d. Utility Manhole Abandonment 4 1) Measurement 5 a) Measured per each manhole to be abandoned. 6 2) Payment 7 a) The work performed and materials furnished in accordance with this 8 item and measured as provided under “Measurement” will be paid for 9 at the unit price bid per each “Abandon Utility Manhole” for: 10 (1) Various diameters. 11 3) The price bid shall include: 12 a) Disposal of sewage (as required) 13 b) Removal and disposal of manhole cone 14 c) Removal and disposal of frame and cover 15 d) Cutting and plugging of existing utility lines 16 e) Concrete 17 f) Sand 18 g) Pavement removal 19 h) Excavation 20 i) Hauling 21 j) Disposal of excess materials 22 k) Furnishing, placement, and compaction of backfill 23 l) Surface restoration 24 m) Clean-up 25 e. Utility Manhole Removal 26 1) Measurement 27 a) Measured per each manhole to be removed. 28 2) Payment 29 a) The work performed and materials furnished in accordance with this 30 item and measured as provided under “Measurement” will be paid for 31 at the unit price bid per each “Remove Utility Manhole” for: 32 (1) Various diameters. 33 3) The price bid shall include: 34 a) Disposal of sewage (as required) 35 b) Removal and disposal of manhole 36 c) Removal and disposal of frame and cover 37 d) Cutting and plugging of existing utility lines 38 e) Pavement removal 39 f) Excavation 40 g) Hauling 41 h) Disposal of excess materials 42 i) Furnishing, placement, and compaction of backfill 43 j) Surface restoration 44 k) Clean-up 45 f. Plugging of Utility Lines 46 1) Measurement 47 a) Measurement for this item shall be by lump sum. 48 2) Payment 49 02 41 14 UTILITY REMOVAL AND ABANDONMENT Page 4 of 13 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 a) The work performed and the materials furnished in accordance with 1 this item shall be paid for at the lump sum price bid for all “Utility Line 2 Plugging”. 3 4 3) The price bid shall include: 5 a) Furnishing and installing all utility line pressure plugs 6 b) Furnishing and installing all utility line abandonment plugs 7 c) Ductile iron fittings (for pressure plugs) 8 d) Gaskets (for pressure plugs) 9 e) Nuts and bolts (for pressure plugs) 10 f) Pavement removal 11 g) Excavation 12 h) Hauling 13 i) Disposal of excess material 14 j) Furnishing, placement, and compaction of embedment 15 k) Furnishing, placement, and compaction of backfill 16 l) Disinfection (for pressure plugs) 17 m) Testing (for pressure plugs) 18 n) CLSM (for abandonment plugs) 19 o) Clean-up 20 g. Utility Junction Structure Removal 21 1) Measurement 22 a) Measured per each junction structure to be removed. 23 2) Payment 24 a) The work performed and materials furnished in accordance with this 25 item and measured as provided under “Measurement” will be paid for 26 at the unit price bid per each “Remove Utility Junction Structure”. 27 3) The price bid shall include: 28 a) Disposal of sewage (as required) 29 b) Removal and disposal of junction structure 30 c) Removal and disposal of frames and covers 31 d) Removal and disposal of hatches 32 e) Cutting and plugging of existing utility lines 33 f) Pavement removal 34 g) Excavation 35 h) Hauling 36 i) Disposal of excess materials 37 j) Furnishing, placement, and compaction of backfill 38 k) Surface restoration 39 l) Clean-up 40 2. Water Specific Items 41 a. Water Valve Removal 42 1) Measurement 43 a) Measured per each water valve to be removed. 44 2) Payment 45 a) The work performed and materials furnished in accordance with this 46 item and measured as provided under “Measurement” will be paid for 47 at the unit price bid per each “Remove Water Valve” for: 48 (1) Various sizes. 49 02 41 14 UTILITY REMOVAL AND ABANDONMENT Page 5 of 13 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3) The price bid shall include: 1 a) Removal and disposal of valve 2 b) Removal and disposal of valve box 3 c) Removal and disposal of water sampling station (if required) 4 d) Removal and disposal of water manhole, frame, cover, and grade rings 5 (if required) 6 e) CLSM 7 f) Pavement removal 8 g) Excavation 9 h) Hauling 10 i) Disposal of excess materials 11 j) Furnishing, placement, and compaction of backfill 12 k) Clean-up 13 b. Water Valve Removal and Salvage 14 1) Measurement 15 a) Measured per each water valve to be removed and salvaged. 16 2) Payment 17 a) The work performed and materials furnished in accordance with this 18 item and measured as provided under “Measurement” will be paid for 19 at the unit price bid per each “Salvage Water Valve” for: 20 (1) Various sizes. 21 3) The price bid shall include: 22 a) Removal and salvage of valve 23 b) Removal and disposal of valve box 24 c) Removal and disposal of water sampling station (if required) 25 d) Removal and disposal of water manhole, frame, cover, and grade rings 26 (if required) 27 e) CLSM 28 f) Delivery to City 29 g) Pavement removal 30 h) Excavation 31 i) Hauling 32 j) Disposal of excess materials 33 k) Furnishing, placement, and compaction of backfill 34 l) Clean-up 35 c. Water Valve Abandonment 36 1) Measurement 37 a) Measured per each water valve to be abandoned. 38 2) Payment 39 a) The work performed and materials furnished in accordance with this 40 item and measured as provided under “Measurement” will be paid for 41 at the unit price bid per each “Abandon Water Valve” for: 42 (1) Various sizes. 43 3) The price bid shall include: 44 a) Abandonment of valve 45 b) Removal and disposal of valve box 46 c) Removal and disposal of water sampling station (if required) 47 d) CLSM 48 e) Pavement removal 49 02 41 14 UTILITY REMOVAL AND ABANDONMENT Page 6 of 13 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 f) Excavation 1 g) Hauling 2 h) Disposal of excess materials 3 i) Furnishing, placement, and compaction of backfill 4 j) Clean-up 5 d. Fire Hydrant Removal and Salvage 6 1) Measurement 7 a) Measured per each fire hydrant to be removed and salvaged. 8 2) Payment 9 a) The work performed and materials furnished in accordance with this 10 item and measured as provided under “Measurement” will be paid for 11 at the unit price bid per each “Salvage Fire Hydrant”. 12 3) The price bid shall include: 13 a) Removal of fire hydrant 14 b) Salvage of fire hydrant (if required) 15 c) Delivery to City (if required) 16 d) Disposal of fire hydrant (if required) 17 e) Pavement removal 18 f) Excavation 19 g) Hauling 20 h) Disposal of excess materials 21 i) Furnishing, placement, and compaction of backfill 22 j) Clean-up 23 e. Water Meter Removal and Salvage 24 1) Measurement 25 a) Measured per each water meter to be removed and salvaged. 26 2) Payment 27 a) The work performed and materials furnished in accordance with this 28 item and measured as provided under “Measurement” shall be paid for 29 at the unit price bid per each “Salvage Water Meter”. 30 3) The price bid shall include: 31 a) Coordination with City for City performed disconnection, removal, and 32 salvage of water meter 33 b) Removal of existing water meter box 34 c) Salvage of existing water meter lid and delivery to City 35 d) Pavement removal 36 e) Excavation 37 f) Hauling 38 g) Disposal of excess materials 39 h) Furnishing, placement, and compaction of backfill 40 i) Clean-up 41 f. Concrete Water Vault Removal 42 1) Measurement 43 a) Measured per each junction structure to be removed. 44 2) Payment 45 a) The work performed and materials furnished in accordance with this 46 item and measured as provided under “Measurement” will be paid for 47 at the unit price bid per each “Remove Concrete Water Vault”. 48 3) The price bid shall include: 49 02 41 14 UTILITY REMOVAL AND ABANDONMENT Page 7 of 13 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 a) Coordination with City for City performed disconnection, removal, and 1 salvage of water meter (if applicable) 2 b) Removal, salvage, and delivery of valves/meters to City (if applicable) 3 c) Removal and disposal of all piping, fittings, and other appurtenances (if 4 applicable) 5 d) Removal and disposal of manhole 6 e) Removal and disposal of vault 7 f) Removal and disposal of hatches 8 g) Cutting and plugging of existing utility lines 9 h) Pavement removal 10 i) Excavation 11 j) Hauling 12 k) Disposal of excess materials 13 l) Furnishing, placement, and compaction of backfill 14 m) Surface restoration 15 n) Clean-up 16 g. Cathodic Test Station Abandonment 17 1) Measurement 18 a) Measured per each cathodic test station to be abandoned. 19 2) Payment 20 a) The work performed and materials furnished in accordance with this 21 item and measured as provided under “Measurement” shall be paid for 22 at the unit price bid per each “Abandon Cathodic Test Station”. 23 3) The price bid shall include: 24 a) Abandon cathodic test station 25 b) CLSM 26 c) Pavement removal 27 d) Excavation 28 e) Hauling 29 f) Disposal of excess materials 30 g) Furnishing, placement, and compaction of backfill 31 h) Clean-up 32 3. Stormwater Specific Items 33 a. Stormwater Inlet Removal 34 1) Measurement 35 a) Measured per each stormwater inlet to be removed. 36 2) Payment 37 a) The work performed and materials furnished in accordance with this 38 item and measured as provided under “Measurement” shall be paid for 39 at the unit price bid per each “Remove Storm Inlet”. 40 3) The price bid shall include: 41 a) Removal and disposal of inlet 42 b) Pavement removal 43 c) Excavation 44 d) Hauling 45 e) Disposal of excess materials 46 f) Furnishing, placement, and compaction of backfill 47 g) Clean-up 48 b. Headwall/SET Removal 49 02 41 14 UTILITY REMOVAL AND ABANDONMENT Page 8 of 13 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1) Measurement 1 a) Measured per each headwall or safety end treatment (SET) to be 2 removed. 3 2) Payment 4 a) The work performed and materials furnished in accordance with this 5 item and measured as provided under “Measurement” shall be paid for 6 at the unit price bid per each “Remove Headwall/SET”. 7 3) The price bid shall include: 8 a) Removal and disposal of Headwall/SET 9 b) Pavement removal 10 c) Excavation 11 d) Hauling 12 e) Disposal of excess materials 13 f) Furnishing, placement, and compaction of backfill 14 g) Clean-up 15 c. Trench Drain Removal 16 1) Measurement 17 a) Measured horizontally along the ground surface of existing trench drain 18 to be removed. 19 2) Payment 20 a) The work performed and materials furnished in accordance with this 21 item and measured as provided under “Measurement” shall be paid for 22 at the unit price bid per linear foot of “Remove Trench Drain”. 23 3) The price bid shall include: 24 a) Removal and disposal of trench drain 25 b) Pavement removal 26 c) Excavation 27 d) Hauling 28 e) Disposal of excess materials 29 f) Furnishing, placement, and compaction of backfill 30 g) Clean-up 31 1.3 REFERENCES 32 A. Abbreviations 33 1. CLSM – Controlled Low Strength Material 34 B. Definitions 35 1. Pressure Plug – Plugging of an existing pressurized pipeline to remain in service 36 with fitting, blind flange, or welded plug, as applicable. 37 2. Abandonment Plug – Plugging of an existing gravity or pressurized pipeline to be 38 abandoned with CLSM. 39 1.4 ADMINISTRATIVE REQUIREMENTS 40 A. Coordination 41 1. Contact Project Manager and Water Utilities for coordination of salvaged material 42 return. 43 02 41 14 UTILITY REMOVAL AND ABANDONMENT Page 9 of 13 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1.5 SUBMITTALS 1 A. Submittals shall be in accordance with Section 01 33 00. 2 B. All submittals shall be approved by the City prior to delivery. 3 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 4 A. Special Procedure Submittals 5 1. Utility Abandonment by Grout Fill Plan: 6 a. Grout fill narrative 7 b. Grout port locations 8 c. Calculations demonstrating proposed volume of grout 9 1.7 CLOSEOUT SUBMITTALS [NOT USED] 10 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 11 1.9 QUALITY ASSURANCE [NOT USED] 12 1.10 DELIVERY, STORAGE, AND HANDLING 13 A. Delivery and Acceptance Requirements 14 1. Protect and salvage all materials such that no damage occurs during delivery to 15 City. 16 1.11 FIELD CONDITIONS [NOT USED] 17 1.12 WARRANTY [NOT USED] 18 PART 2 - PRODUCTS [NOT USED] 19 2.1 CITY-SUPPLIED PRODUCTS [NOT USED] 20 2.2 MATERIALS [NOT USED] 21 2.3 ACCESSORIES [NOT USED] 22 2.4 SOURCE QUALITY CONTROL [NOT USED] 23 PART 3 - EXECUTION 24 3.1 INSTALLERS [NOT USED] 25 3.2 EXAMINATION [NOT USED] 26 3.3 PREPARATION 27 A. Coordinate with Water Utilities prior to abandonment of existing water or sanitary 28 sewer lines to determine whether all existing services have been removed. 29 3.4 REMOVAL, SALVAGE, AND ABANDONMENT 30 A. General Utility Items 31 02 41 14 UTILITY REMOVAL AND ABANDONMENT Page 10 of 13 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1. Utility Line Abandonment by Grout Fill 1 a. Excavate and backfill in accordance with Section 33 05 05. 2 b. Dewater existing line to be grouted. 3 c. Dispose of any sewage from existing line to be grouted for sanitary sewer lines. 4 d. Fill line with Low Density Cellular Grout in accordance with Section 33 05 15 5 or CLSM in accordance with Section 03 34 13. 6 e. Dispose of any excess material. 7 2. Utility Line Removal, Separate Trench 8 a. Excavate and backfill in accordance with Section 33 05 05. 9 b. Dewater existing line to be removed. 10 c. Dispose of any sewage from existing line to be removed for sanitary sewer 11 lines. 12 d. Cut any service, lateral, or main connections prior to removal. 13 e. Remove existing utility line and properly dispose of as approved by City. 14 3. Utility Manhole Abandonment 15 a. Excavate and backfill in accordance with Section 33 05 05. 16 b. Remove and dispose of existing frame, cover, grade rings, and manhole cone 17 section. 18 c. Cut and plug existing service, lateral, and main lines with 2000 psi concrete in 19 accordance with Section 03 30 00. 20 d. Backfill manhole with utility sand in accordance with Section 33 05 05. 21 4. Utility Manhole Removal 22 a. Excavate and backfill in accordance with Section 33 05 05. 23 b. Remove and dispose of existing frame, cover, and grade rings. 24 c. Dispose of any sewage from existing manhole for sanitary sewer manholes. 25 d. Demolish and remove entire concrete manhole. 26 e. Plug existing service, lateral, and main lines with abandonment plugs. 27 5. Plugging of Utility Lines 28 a. Water Line Pressure Plugs 29 1) Ductile Iron and PVC C900 Water Lines 30 a) Excavate, embed, and backfill in accordance with Section 33 05 05. 31 b) Plug line with MJ Plug with mechanical restraint and blocking in 32 accordance with Section 33 14 10. 33 2) Concrete Pressure Pipe, Bar Wrapped, Steel Cylinder Type Water Lines 34 a) Excavate, embed, and backfill in accordance with Section 33 05 05. 35 b) Plug line using: 36 (1) Fabricated plug restrained by welding in accordance with Section 37 33 14 12; or 38 (2) Blind flange in accordance with Section 33 14 12. 39 3) Buried Steel Water Lines 40 a) Excavate, embed, and backfill in accordance with Section 33 05 05. 41 b) Plug line using: 42 (1) Fabricated plug restrained by welding in accordance with Section 43 33 14 13; or 44 (2) Blind flange in accordance with Section 33 14 13. 45 b. Utility Line Abandonment Plugs 46 1) Excavate and backfill in accordance with Section 33 05 05. 47 2) Dispose of any sewage for sanitary sewer lines. 48 02 41 14 UTILITY REMOVAL AND ABANDONMENT Page 11 of 13 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3) Install bulkhead sufficient to retain CLSM plug before it has cured. 1 4) Backfill trench adjacent to pipe plug with CLSM to top of pipe. 2 5) Plug minimum 2 feet of existing pipe with CLSM in accordance with 3 Section 03 34 14. 4 a) Pressure plugs may be used for water line abandonment plugs as an 5 acceptable alternative. 6 6. Utility Junction Structure Removal 7 a. Excavate and backfill in accordance with Section 33 05 05. 8 b. Remove and dispose of existing frame, cover, hatch, and grade rings. 9 c. Dispose of any sewage from existing manhole for sanitary sewer manholes. 10 d. Demolish and remove entire concrete structure. 11 e. Plug existing service, lateral, and main lines with abandonment plugs. 12 B. Water Items 13 1. Water Valve Removal 14 a. Excavate and backfill in accordance with Section 33 05 05. 15 b. Remove and dispose of valve box. 16 c. Remove and dispose of valve bonnet, wedge, and stem. 17 d. Fill valve body with CLSM in accordance with Section 03 34 13. 18 2. Water Valve Removal and Salvage 19 a. Excavate and backfill in accordance with Section 33 05 05. 20 b. Remove and dispose of valve box. 21 c. Remove valve bonnet, wedge, and stem, and deliver to the City as directed by 22 City Inspector. 23 d. Protect salvaged materials from damage. 24 e. Fill valve body with CLSM in accordance with Section 03 34 13. 25 3. Water Valve Abandonment 26 a. Excavate and backfill in accordance with Section 33 05 05. 27 b. Remove the top 2 feet of the valve stack and any valve extensions. 28 c. Fill the remaining valve stack with CLSM in accordance with Section 03 34 13. 29 4. Fire Hydrant Removal and Salvage 30 a. Excavate and backfill in accordance with Section 33 05 05. 31 b. Remove fire hydrant. 32 c. Install abandonment plug on fire hydrant lead line. 33 d. Deliver salvaged fire hydrant to the City as directed by City. 34 e. Protect salvaged materials from damage. 35 5. Water Meter Removal and Salvage 36 a. Coordinate with City to have City remove and salvage water meter. 37 1) Contractor shall not remove water meter. 38 b. Remove and dispose of curb stop, and meter boxes. 39 c. Remove and salvage meter box lid and deliver to City as directed by City 40 Inspector. 41 d. Crimp abandoned service lines. 42 e. Backfill in accordance with Section 33 05 05. 43 6. Concrete Water Vault Removal 44 a. Excavate and backfill in accordance with Section 33 05 05. 45 b. Coordinate with City to have City remove and salvage water meter if 46 applicable. 47 02 41 14 UTILITY REMOVAL AND ABANDONMENT Page 12 of 13 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1) Contractor shall not remove water meter. 1 c. Remove and salvage valve, if applicable. 2 d. Remove and salvage vault lid. 3 e. Remove and salvage test stations. 4 f. Protect salvaged materials from damage. 5 g. Remove and dispose of piping and other appurtenances. 6 h. Deliver salvaged material to City as directed by City Inspector. 7 i. Demolish and remove entire concrete water vault. 8 j. Plug existing service and main lines with abandonment plugs. 9 k. Dispose of excess materials. 10 7. Cathodic Test Station Abandonment 11 a. Excavate and backfill in accordance with Section 33 05 05. 12 b. Remove top 2 feet of the cathodic test station stack and contents. 13 c. Fill any remaining voids with CLSM in accordance with Section 03 34 13. 14 C. Stormwater Items 15 1. Stormwater Inlet Removal 16 a. Excavate and backfill in accordance with Section 33 05 05. 17 b. Demolish and remove entire concrete inlet. 18 c. Plug existing lateral and main lines with abandonment plugs. 19 2. Headwall/SET Removal 20 a. Excavate and backfill in accordance with Section 33 05 05. 21 b. Demolish and remove concrete headwall/SET. 22 c. Plug existing lateral and main lines with abandonment plugs. 23 3. Trench Drain Removal 24 a. Excavate and backfill in accordance with Section 33 05 05. 25 b. Remove and dispose of existing pipe. 26 3.5 REPAIR [NOT USED] 27 3.6 RE-INSTALLATION [NOT USED] 28 3.7 FIELD QUALITY CONTROL [NOT USED] 29 3.8 SYSTEM STARTUP [NOT USED] 30 3.9 ADJUSTING [NOT USED] 31 3.10 CLEANING [NOT USED] 32 3.11 CLOSEOUT ACTIVITIES [NOT USED] 33 3.12 PROTECTION [NOT USED] 34 3.13 MAINTENANCE [NOT USED] 35 3.14 ATTACHMENTS [NOT USED] 36 37 38 02 41 14 UTILITY REMOVAL AND ABANDONMENT Page 13 of 13 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 END OF SECTION 1 2 Revision Log DATE NAME SUMMARY OF CHANGE 3 02 41 15 PAVING REMOVAL Page 1 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 02 41 15 1 PAVING REMOVAL 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Construction methods for 6 a. Remove Concrete Pavement 7 b. Remove Concrete Curb and Gutter 8 c. Remove Concrete Valley Gutter 9 d. Remove Sidewalk 10 e. Remove Curb Ramp 11 f. Remove Asphalt Pavement 12 g. Remove Driveway 13 h. Remove Brick Pavers 14 i. Remove Permeable Pavers 15 j. Wedge Milling 16 k. Surface Milling 17 l. Butt Joint Milling 18 m. Pavement Pulverization 19 n. Obliterate Abandoned Road 20 o. Pavement Removal for Utility Trenching 21 B. Deviations from this City of Denton Standard Specification: 22 1. None. 23 C. Related Specification Sections include but are not limited to: 24 1. Division 0 – Bidding Requirements, Contract Forms, and Conditions of the 25 Contract. 26 2. Division 1 – General Requirements. 27 3. Section 31 25 14 – Erosion and Sedimentation Control. 28 4. Section 32 01 17 – Flexible Pavement Repair. 29 5. Section 32 01 29 – Rigid Paving Repair. 30 6. Section 32 11 33 – Cement Treated Base Courses. 31 7. Section 34 71 13 – Traffic Control. 32 1.2 PRICE AND PAYMENT PROCEDURES 33 A. Measurement and Payment 34 1. Remove Concrete Pavement 35 a. Measurement 36 1) Measured per square yard from back of curb to back of curb or edge of 37 concrete to edge of concrete for existing concrete pavement for all 38 thicknesses. 39 b. Payment 40 02 41 15 PAVING REMOVAL Page 2 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1) The work performed and materials furnished in accordance with this item 1 and measured as provided under “Measurement” will be paid for at the unit 2 price bid per square yard for “Remove Concrete Pavement.” 3 c. The price bid shall include: 4 1) Sawing and breaking the material 5 2) Removal of monolithic concrete curb and concrete pavement 6 3) Loading 7 4) Unloading 8 5) Storing 9 6) Hauling 10 7) Salvaging or disposing 11 8) Repair adjacent pavement damaged by the removal of concrete 12 2. Remove Concrete Curb and Gutter 13 a. Measurement 14 1) Measured per linear foot of “Remove Curb and Gutter.” 15 b. Payment 16 1) The work performed and materials furnished in accordance with this item 17 and measured as provided under “Measurement” will be paid for at the unit 18 price bid per linear foot for “Remove Curb and Gutter.” 19 c. The price bid shall include: 20 1) Sawing and breaking the material 21 2) Removal of concrete curb and gutter 22 3) Cleaning 23 4) Loading 24 5) Unloading 25 6) Storing 26 7) Hauling 27 8) Salvaging or disposing 28 9) Repair adjacent pavement and curb and gutter damaged by the removal of 29 curb and gutter 30 3. Remove Concrete Valley Gutter 31 a. Measurement 32 1) Measured per square yard of “Remove Concrete Valley Gutter.” 33 b. Payment 34 1) The work performed and materials furnished in accordance with this item 35 and measured as provided under “Measurement” will be paid for at the unit 36 price bid per square yard for “Remove Concrete Valley Gutter.” 37 c. The price bid shall include: 38 1) Sawing and breaking the material 39 2) Removal of concrete valley gutter 40 3) Cleaning 41 4) Loading 42 5) Unloading 43 6) Storing 44 7) Hauling 45 8) Salvaging or disposing 46 9) Repair adjacent pavement damaged by the removal of concrete valley 47 gutter 48 49 02 41 15 PAVING REMOVAL Page 3 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 4. Remove Sidewalk 1 a. Measurement 2 1) Measured per square foot of “Remove Sidewalk.” 3 b. Payment 4 1) The work performed and materials furnished in accordance with this item 5 and measured as provided under “Measurement” will be paid for at the unit 6 price bid per square foot for “Remove Sidewalk.” 7 c. The price bid shall include: 8 1) The removal of integral sidewalk walls 9 2) The removal of landscape walls adjacent to sidewalk less than 3 feet in 10 height 11 3) Sawing and breaking the material 12 4) Cleaning 13 5) Loading 14 6) Unloading 15 7) Storing 16 8) Hauling 17 9) Salvaging or disposing 18 10) Repair to adjacent curb or curb and gutter damaged by the removal of 19 sidewalk 20 5. Remove Curb Ramp 21 a. Measurement 22 1) Measured per each of “Remove Curb Ramp.” 23 b. Payment 24 1) The work performed and materials furnished in accordance with this item 25 and measured as provided under “Measurement” will be paid for at the unit 26 price bid per each for “Remove Curb Ramp” for: 27 a) Various types. 28 c. The price bid shall include: 29 1) Removal of curb ramp, curb ramp curbs, flares, and detectable warning tiles 30 2) Sawing and breaking the material 31 3) Loading 32 4) Unloading 33 5) Storing 34 6) Hauling 35 7) Salvaging or disposing 36 8) Repair to adjacent curb, curb and gutter, or sidewalk damaged by the 37 removal of curb ramp 38 6. Remove Asphalt Pavement 39 a. Measurement 40 1) Measured per square yard from gutter edge to gutter edge or edge to edge 41 of existing asphalt pavement for all thicknesses. 42 b. Payment 43 1) The work performed and materials furnished in accordance with this item 44 and measured as provided under “Measurement” will be paid for at the unit 45 price bid per square yard for “Remove Asphalt Pavement.” 46 c. The price bid shall include: 47 1) Sawing 48 02 41 15 PAVING REMOVAL Page 4 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2) Breaking the material 1 3) Removal of asphalt pavement 2 4) Loading 3 5) Unloading 4 6) Storing 5 7) Hauling 6 8) Salvaging or disposing 7 9) Repair adjacent pavement damaged by the removal of asphalt 8 7. Remove Driveway 9 a. Measurement 10 1) Measured per square foot of “Remove Driveway.” 11 b. Payment 12 1) The work performed and materials furnished in accordance with this item 13 and measured as provided under “Measurement” will be paid for at the unit 14 price bid per square foot for “Remove Driveway” for: 15 a) Various pavement types (gravel, concrete, asphalt, pavers). 16 c. The price bid shall include: 17 1) Sawing 18 2) Breaking the material 19 3) Removal of driveway material 20 4) Loading 21 5) Unloading 22 6) Storing 23 7) Hauling 24 8) Salvaging or disposing 25 9) Repair adjacent pavement damaged by the removal of the driveway 26 8. Remove Brick Pavers 27 a. Measurement 28 1) Measured per square foot of “Remove Brick Pavers.” 29 b. Payment 30 1) The work performed and materials furnished in accordance with this item 31 and measured as provided under “Measurement” will be paid for at the unit 32 price bid per square foot for “Remove Brick Pavers.” 33 c. The price bid shall include: 34 1) Full-depth removal of bricks and any brick base material to existing 35 subgrade. 36 2) Sawing 37 3) Breaking the material 38 4) Removal of brick pavers 39 5) Cleaning 40 6) Loading 41 7) Unloading 42 8) Storing 43 9) Hauling 44 10) Disposal 45 11) Salvage and delivery to City, if required 46 12) Repair adjacent pavement damaged by the removal of bricks 47 9. Remove Permeable Pavers 48 02 41 15 PAVING REMOVAL Page 5 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 a. Measurement 1 1) Measured per square foot of “Remove Permeable Pavers.” 2 b. Payment 3 1) The work performed and materials furnished in accordance with this item 4 and measured as provided under “Measurement” will be paid for at the unit 5 price bid per square foot for “Remove Permeable Pavers.” 6 c. The price bid shall include: 7 1) Full-depth removal of any permeable pavers and paver base material to 8 existing subgrade or compacted soil. 9 2) Sawing 10 3) Breaking the material 11 4) Removal of permeable pavers 12 5) Cleaning 13 6) Loading 14 7) Unloading 15 8) Storing 16 9) Hauling 17 10) Disposal 18 11) Salvage and delivery to City, if required 19 12) Repair adjacent pavement damaged by the removal of permeable pavers 20 10. Wedge Milling 21 a. Measurement 22 1) Measured per square yard of “Wedge Milling.” 23 b. Payment 24 1) The work performed and materials furnished in accordance with this item 25 and measured as provided under “Measurement” will be paid for at the unit 26 price bid per square yard for “Wedge Milling.” 27 c. The price bid shall include: 28 1) Milling 29 2) Rolling 30 3) Sweeping and cleaning remaining pavement 31 4) Cleaning 32 5) Surface treatments as specified in the Drawings 33 6) Loading 34 7) Unloading 35 8) Storing 36 9) Hauling 37 10) Salvaging or disposing 38 11) Repair to adjacent pavement damaged by wedge milling 39 11. Surface Milling 40 a. Measurement 41 1) Measured square yard of “Surface Milling.” 42 b. Payment 43 1) The work performed and materials furnished in accordance with this item 44 and measured as provided under “Measurement” will be paid for at the unit 45 price bid per square yard for “Surface Milling.” 46 c. The price bid shall include: 47 1) Milling 48 02 41 15 PAVING REMOVAL Page 6 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2) Rolling 1 3) Sweeping and cleaning remaining pavement 2 4) Cleaning 3 5) Surface treatments as specified in the Drawings 4 6) Loading 5 7) Unloading 6 8) Storing 7 9) Hauling 8 10) Salvaging or disposing 9 11) Repair to adjacent pavement damaged by surface milling 10 12. Butt Joint Milling 11 a. Measurement 12 1) Measured per linear foot of “Butt Milling.” 13 b. Payment 14 1) The work performed and materials furnished in accordance with this item 15 and measured as provided under “Measurement” will be paid for at the unit 16 price bid per linear feet for “Butt Milling.” 17 c. The price bid shall include: 18 1) Milling 19 2) Rolling 20 3) Sweeping and cleaning remaining pavement 21 4) Cleaning 22 5) Surface treatments as specified in the Drawings 23 6) Loading 24 7) Unloading 25 8) Storing 26 9) Hauling 27 10) Salvaging or disposing 28 11) Repair to adjacent pavement damaged by butt milling 29 13. Pavement Pulverization 30 a. Measurement 31 1) Measured per square yard of “Pavement Pulverization.” 32 b. Payment 33 1) The work performed and materials furnished in accordance with this item 34 and measured as provided under “Measurement” will be paid for at the unit 35 price bid per square yard for “Pavement Pulverization.” 36 c. The price bid shall include: 37 1) Pulverization 38 2) Base undercutting 39 3) Mixing and compaction 40 4) Surface treatments as specified in the Drawings 41 5) Sweeping and cleaning remaining pavement 42 6) Temporary removal and stockpiling of pulverized material 43 7) Loading 44 8) Unloading 45 9) Storing 46 10) Hauling 47 11) Salvaging or disposing 48 02 41 15 PAVING REMOVAL Page 7 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 12) Repair to adjacent pavement damaged by pavement pulverization 1 14. Obliterate Abandoned Road 2 a. Measurement 3 1) Measured per square yard of “Obliterate Abandoned Road.” 4 b. Payment 5 1) The work performed and materials furnished in accordance with this item 6 and measured as provided under “Measurement” will be paid for at the unit 7 price bid per square yard for “Obliterate Abandoned Road.” 8 c. The price bid shall include: 9 1) Salvaging and replacing topsoil 10 2) Furnishing and installing any new topsoil 11 3) Removal of abandoned structures within the roadway 12 4) Scarifying, mixing, and shaping abandoned roadway 13 5) Sodding 14 6) Removal of any material or items specified under Obliterate 15 7) Loading 16 8) Unloading 17 9) Storing 18 10) Hauling 19 11) Salvaging or disposing 20 12) Clean-up 21 15. Pavement Removal for Utility Trenching 22 a. Measurement 23 1) This item is considered subsidiary to the installation of water, wastewater, 24 or stormwater piping. 25 b. Payment 26 1) The work performed and materials furnished in accordance with this item 27 are subsidiary to the unit price bid per linear foot of water, wastewater, or 28 stormwater piping installed. 29 1.3 REFERENCES 30 A. Abbreviations 31 1. HMA – Hot-mix Asphalt 32 B. Reference Standards 33 1. Reference standards cited in this Section refer to the current reference standard 34 published at the time of the latest revision date logged at the end of this Section 35 unless a date is specifically cited. 36 2. Texas Manual on Uniform Traffic Control Devices (TMUTCD). 37 1.4 ADMINISTRATIVE REQUIREMENTS 38 A. Sequencing 39 1. Sidewalk Construction 40 a. Where existing sidewalks are to be closed during Paving Removal activities: 41 1) Utilize pedestrian/sidewalk detour route specified in the Drawings 42 a) If no detour route is provided, submit a pedestrian/sidewalk detour 43 route that has been signed and sealed by a registered professional 44 engineer to the City for review. 45 02 41 15 PAVING REMOVAL Page 8 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 b. The pedestrian/sidewalk detour route will be subsidiary to pertinent Traffic 1 Control items included with the project. 2 c. Install all sidewalk detours and closures in accordance with the TMUTCD, 3 State, and local guidelines. 4 d. Provide any traffic control devices in accordance with Section 34 71 13. 5 2. Pavement Removal 6 a. Install traffic control devices prior to removal of pavement per the Drawings. 7 b. If no traffic control plan is provided, submit a traffic control plan that has been 8 signed and sealed by a registered professional engineer to the City for review. 9 B. Pre-removal Meeting 10 1. Hold a preinstallation meeting prior to performing any tasks included under Paving 11 Removal. Invite the City and appropriate representatives. The following items will 12 be reviewed and discussed at the meeting: 13 a. All removal limits for any pavement to be removed 14 b. Concrete paving removal method 15 1.5 SUBMITTALS 16 A. Submittals shall be in accordance with Section 01 33 00. 17 B. All submittals shall be approved by the City prior to delivery. 18 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 19 A. Informational Submittal: 20 1. Equipment Information 21 a. Submittal for all major equipment to include: 22 1) Equipment name 23 2) Size 24 3) Intended use 25 1.7 CLOSEOUT SUBMITTALS [NOT USED] 26 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 27 1.9 QUALITY ASSURANCE [NOT USED] 28 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 29 1.11 FIELD CONDITIONS [NOT USED] 30 1.12 WARRANTY [NOT USED] 31 PART 2 - PRODUCTS [NOT USED] 32 2.1 CITY-SUPPLIED PRODUCTS [NOT USED] 33 2.2 MATERIALS [NOT USED] 34 2.3 ACCESSORIES [NOT USED] 35 2.4 SOURCE QUALITY CONTROL [NOT USED] 36 02 41 15 PAVING REMOVAL Page 9 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 PART 3 - EXECUTION 1 3.1 INSTALLERS [NOT USED] 2 3.2 EXAMINATION [NOT USED] 3 3.3 PREPARATION 4 A. Site Preparation 5 1. Mark all pavement removal limits prior to construction. 6 2. City will review and provide direction to Contractor, regarding proposed limits 7 prior to saw cutting, milling, or any other pavement removal activities. 8 3. For maintenance projects, the City will mark the limits of Paving Removal prior to 9 construction. 10 3.4 PAVEMENT REMOVAL 11 A. Sawing 12 1. Full-depth saw cut all pavement to be removed. 13 2. Make a clean, smooth cut producing a groove 1/8 inch to 1/4 inch wide and full 14 depth. 15 3. Any saw cut wider than 1/4 inch will not be accepted. 16 4. Re-saw pavement edge after pavement is removed as many times as necessary to 17 provide a smooth, neat, straight pavement edge free from chips or gouges. 18 Contractor to re-saw a minimum of one time. 19 5. If a saw cut falls within 5 feet of an existing joint, pavement edge, or edge of gutter, 20 remove paving to the nearest joint, pavement edge, or gutter edge. 21 6. Minimize dust and residue from entering the atmosphere by using water, vacuums, 22 or other approved dust reducing measures. 23 7. Utilize erosion control measures to prevent dust and residue from entering the 24 storm drain system in accordance with Section 31 25 14. 25 8. Use care to prevent fracturing or spalling of adjacent existing pavement. Repair any 26 damage done to the existing pavement due to saw cutting or pavement removal in 27 accordance with Sections 32 01 17 or 32 01 29 at no cost to the City. 28 B. Remove Concrete Paving 29 1. Saw Cut 30 a. In accordance with this Section. 31 2. Minimum Limits of Removal 32 a. Parallel to the Centerline 33 1) Minimum cut along street path is: 34 a) 5 feet in total length 35 b) 1 foot from the edge of the trench 36 b. Perpendicular to the Center Line – Multiple Lanes 37 1) Remove full panel of one lane width if trench or repairs are contained 38 within the lane. 39 2) For locations where two or more lanes are affected, remove the full width 40 of affected lanes. 41 02 41 15 PAVING REMOVAL Page 10 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3) Maintain minimum gutter width of 2 feet from back of curb at all times. 1 c. Perpendicular to the Center Line – Single Lane 2 1) General: 3 a) 1 foot from the edge of the trench 4 b) Minimum gutter width is 2 feet from back of curb. 5 c) Remove curb if trench edge or repair is closer than 2 feet from back of 6 curb. 7 2) Concrete alley or residential street less than 30 feet wide: 8 a) Remove pavement from centerline to back of curb. Curb will be 9 considered subsidiary to removal of pavement. 10 3) Concrete alley or residential street greater than 30 feet wide: 11 a) Maintain a minimum of 10 feet from center line or gutter to trench edge 12 or repair. 13 b) Remove pavement starting at the centerline if trench edge or repair is 14 less than 10 feet from centerline. 15 c) If the trench edge or repair is within 10 feet of the back of curb, remove 16 pavement from trench edge or repair to back of curb. Curb will be 17 considered subsidiary to removal of pavement. 18 3. Construction 19 a. A drop hammer or guillotine-style concrete breaker is not allowed without prior 20 approval by City. 21 b. Pavement removal method to be discussed and approved by City during the 22 pre-removal Meeting. 23 c. Preferred method: 24 1) Saw cut sections of the concrete pavement. 25 2) Vertically lift concrete pavement section in whole pieces in a way that does 26 not damage existing features. 27 d. If pavement can’t be removed utilizing the preferred method, utilize a 28 jackhammer to break-up concrete and remove using a front-end loader or 29 backhoe. 30 C. Remove Concrete Curb and Gutter 31 1. Saw Cut 32 a. In accordance with this Section 33 2. Minimum Limits of Removal 34 a. Minimum width of 2-feet from back of curb 35 b. Minimum length of 30-inches 36 c. Removal shall be to the nearest construction joint (not necessarily centered on 37 the trench) 38 D. Remove Concrete Valley Gutter 39 1. Saw Cut 40 a. In accordance with this Section 41 2. Minimum Limits of Removal 42 a. Minimum width of 5 feet 43 b. Remove from gutter edge to gutter edge or from centerline to gutter edge 44 c. Remove concrete in accordance with Remove Concrete Paving 45 E. Remove Sidewalk and Curb Ramp 46 02 41 15 PAVING REMOVAL Page 11 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1. Saw Cut 1 a. In accordance with Sawing 2 2. Minimum Limits of Sidewalk Removal 3 a. Minimum sidewalk removal width and length of 5 feet 4 b. Remove to the nearest sidewalk joint if nearest sidewalk joint is within 3 feet of 5 specified removal limits. 6 c. Remove to the edge of sidewalk if the edge of sidewalk is within 5 feet of 7 specified removal limits. 8 d. Remove curb ramp to the nearest joint. Do not saw cut and leave in place any 9 portion of the existing curb ramp unless specified in the Drawings. 10 F. Remove Asphalt Paving 11 1. Saw Cut 12 a. In accordance with this Section 13 b. Protect asphalt edges to prevent spalling or damage. 14 c. If damage or spalling occurs, obtain direction from the City for repairs, if 15 necessary. 16 2. Minimum Limits of Removal 17 a. Parallel to the Centerline 18 1) Minimum cut along the street path is: 19 a) 5 feet in total length 20 b) 1 foot from the edge of the trench if the trench width is wider than 5 21 feet 22 b. Perpendicular to the Center Line – Multiple Lanes 23 1) If the trench or repairs occur between the center line and the inside lane 24 line, remove the full lane width. 25 2) If the trench or repairs occur between the gutter edge and the outside lane, 26 remove from the lane line to the gutter edge. 27 3) If the trench or repairs occur between two lanes, remove half-lane-width to 28 half-lane-width. 29 c. Perpendicular to the Center Line – Single Lane 30 1) General: 31 a) 2 feet from the edge of the trench 32 b) Minimum width from repair to gutter edge is 10 feet. 33 c) Remove pavement to gutter edge if distance from trench or repair to 34 gutter edge is less than 10 feet 35 2) Concrete alley or residential street less than 30 feet wide: 36 a) Remove pavement from centerline to gutter edge. 37 3) Concrete alley or residential street greater than 30 feet wide: 38 a) Maintain a minimum of 10 feet from center line or gutter edge to trench 39 edge or repair. 40 b) Remove pavement starting at the center line if trench edge or repair is 41 less than 10 feet from centerline. 42 c) Remove pavement from trench edge or repair to gutter if distance from 43 trench edge or repair to the face of curb is less than 10 feet. 44 3. Construction 45 a. Utilize a milling machine to remove pavement where possible in accordance 46 with this Section. 47 02 41 15 PAVING REMOVAL Page 12 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 b. Obtain approval prior to construction to utilize alternative equipment for 1 asphalt pavement removal. 2 G. Remove Driveway 3 1. Saw Cut 4 a. In accordance with this Section 5 2. Minimum Limits of Removal 6 a. If the driveway is concrete, remove to nearest driveway joint. 7 1) Only driveway joints required by City design standards are considered, and 8 existing patches will not be considered as joints. 9 H. Remove Brick Pavers and Permeable Pavers 10 1. Saw Cut 11 a. In accordance with Sawing 12 b. Saw cut 2 feet beyond the limits of the pavers if the adjacent pavement is 13 concrete or asphalt. 14 2. Remove pavers to the limits specified in the Drawings. 15 3. If salvaging pavers for re-use, remove, palletize and either deliver to specified 16 location in Drawings or stockpile for re-use on the Project. 17 I. Milling 18 1. General 19 a. Mill surfaces to the depth specified in the Drawings. 20 b. Milled surface should be rough. If necessary, grind or mill the surface again to 21 make the surface rough. 22 c. If the milled surface is going to be opened to traffic: 23 1) Install a temporary transition section. 24 2) An acceptable transition is 2 inches over 5 feet. 25 3) A different transition may be approved by City prior to opening the milled 26 surface to traffic. 27 d. Remove excess material and clean milled surfaces 28 e. Stockpiling of milled material will not be permitted within the right of way 29 unless otherwise approved by City. 30 2. Milling Equipment 31 a. Provide equipment that meets the following criteria. 32 1) Power operated milling machine capable of removing the specified 33 pavement thickness in maximum of two passes 34 2) Self-propelled with sufficient power, traction, and stability to maintain 35 accurate depth of cut and slope 36 3) Able to immediately remove material cut from the surface of the roadway 37 and discharge the cuttings into a truck utilizing an integral loading and 38 reclaiming system 39 4) Equipped with a dust control system 40 5) Equipped with a manual system that provides uniform varying depths of cut 41 while the machine is in motion. 42 3. Wedge and Surface Milling 43 a. Only used for roadway maintenance. Only utilized with prior approval by City 44 or as specified in Drawings. 45 02 41 15 PAVING REMOVAL Page 13 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 b. Wedge Mill existing asphalt or concrete from the gutter edge at a minimum 1 depth of 2 inches and transition to match the existing pavement within a 5 foot 2 width. 3 c. Surface Mill existing asphalt to the depth specified on Drawings. 4 d. Provide a uniform milled surface free from gouges, ridges, oil film, and other 5 irregularities. 6 e. Wedge milling includes the portion of HMA pavement that covers the existing 7 concrete curb and gutter. This depth is estimated to vary from 2 inches to the 8 full height of the curb. This additional depth would be milled prior to milling 9 the minimum 2 inches previously specified. 10 f. Perform wedge or surface milling operations in a continuous manner for the 11 length specified in the Drawings. 12 4. Butt Joint Milling 13 a. Butt joint will be full width of overlay operation 14 b. Typical locations for butt joints are at the beginning and ending of streets where 15 asphalt paving is removed or where a street is being overlaid. Butt joints may 16 be required in other locations as specified in the Drawings. 17 c. Butt joints at a minimum of 20 feet wide (perpendicular to the center line) for 18 the width specified in the Drawings. 19 d. Taper the butt joint from 2 inches to 0 inches adjacent to existing pavement at 20 the start or end of the project limits or as specified in the Drawings. 21 e. Provide a temporary asphalt transition in accordance with this Section. 22 J. Pavement Pulverization 23 1. Pulverization 24 a. Pulverize the existing pavement to a depth of 8 inches. In accordance with 25 Section 32 11 33. 26 b. Temporarily remove and stockpile pulverized material. 27 c. After temporary removal, cut subgrade or base material down 2 inches. 28 2. Cement Application 29 a. Use 3.5 percent Portland cement 30 b. In accordance with Section 32 11 33. 31 3. Mixing 32 a. In accordance with Section 32 11 33 33 4. Compaction 34 a. In accordance with Section 32 11 33 35 5. Finishing 36 a. In accordance with Section 32 11 33 37 6. Curing 38 a. In accordance with Section 32 11 33 39 7. If the existing pavement has a combination of 10 inches of HMA pavement and 40 crushed stone or gravel 41 a. 2 inch cutting is not required 42 b. Pulverize existing pavement 2 inches deep 43 c. Temporarily remove and stockpile pulverized material 44 K. Obliterating Abandoned Roadway 45 1. Strip and windrow existing topsoil before shaping operations 46 02 41 15 PAVING REMOVAL Page 14 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2. Remove asphalt or concrete pavement in accordance with this Section. 1 3. Remove any abandoned structures within the roadway unless otherwise specified in 2 the Drawings. 3 4. Scarify and mix the abandoned roadbed with soil and blade to produce a smooth, 4 uniform appearance. 5 5. Fill, cut, and shape the abandoned road to blend into the surrounding terrain. 6 6. Eliminate or re-align existing ditches as appropriate to maintain positive drainage. 7 7. Cover disturbed areas with topsoil after shaping operations. 8 8. Install sod within the limits of disturbance after topsoil is installed. 9 10 L. Disposal, Salvaging, and Recycling Removed Pavement 11 1. Contractor is responsible for any material removed during Paving Removal 12 activities. 13 2. Dispose of all material in accordance with Federal, State, and local laws and 14 regulations. 15 3. The disposal, salvaging, and recycling of any material removed as part of Paving 16 Removal is considered subsidiary to the applicable items. 17 4. Contractor is encouraged, but not required, to salvage and recycle as much material 18 as possible. Any recycled material used on a City project shall be in accordance 19 with the requirements of the appropriate Section based on the intended use. 20 3.5 REPAIR 21 A. Repair the following items to remain if any damage is caused due to pavement removal 22 activities at no cost to the City: 23 1. Adjacent concrete or asphalt pavement 24 2. Adjacent sidewalk 25 3. Adjacent curb or curb and gutter 26 4. Subgrade or base material 27 5. Utility piping, structures, and appurtenances 28 6. Irrigation systems including but not limited to sprinkler heads, conduit, and pipe 29 7. Landscape beds or planters 30 8. Sod 31 9. Decorative hardscape or landscape features 32 10. Decorative/stamped concrete 33 11. Sidewalk 34 12. Curb ramps 35 13. Traffic control signage 36 14. Pavement markings 37 15. Retaining walls 38 3.6 RE-INSTALLATION [NOT USED] 39 3.7 SITE QUALITY CONTROL [NOT USED] 40 02 41 15 PAVING REMOVAL Page 15 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3.8 SYSTEM STARTUP [NOT USED] 1 3.9 ADJUSTING [NOT USED] 2 3.10 CLEANING [NOT USED] 3 3.11 CLOSEOUT ACTIVITIES [NOT USED] 4 3.12 PROTECTION [NOT USED] 5 6 3.13 MAINTENANCE [NOT USED] 7 3.14 ATTACHMENTS [NOT USED] 8 END OF SECTION 9 10 Revision Log DATE NAME SUMMARY OF CHANGE 11 03 00 00 CONCRETE AND CONCRETE REINFORCING Page 1 of 18 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 25, 2024 Effective July 1, 2024 SECTION 03 00 00 1 CONCRETE AND CONCRETE REINFORCING 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Material requirements for concrete and concrete reinforcing. 6 B. Deviations from this City of Denton Standard Specification: 7 1. None. 8 C. Related Specification Sections include but are not limited to: 9 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 10 Contract. 11 2. Division 1 - General Requirements. 12 3. Section 03 30 00 – Cast-in-Place Concrete 13 4. Section 03 80 00 – Modifications to Existing Concrete Structures 14 5. Section 31 37 00 – Riprap 15 6. Section 32 05 16 – Aggregates for Exterior Improvements 16 7. Section 32 13 13 – Concrete Paving 17 8. Section 32 13 16 – Decorative Concrete Paving 18 9. Section 32 16 00 – Curbs, Gutters, Sidewalks, and Driveways 19 10. Section 32 32 00 – Retaining Walls 20 11. Section 33 05 61 – Cast-in-Place Concrete Manholes 21 12. Section 33 42 11 – Stormwater Pipe and Boxes 22 13. Section 33 42 23 – Stormwater Headwalls, Wingwalls, and End Treatments 23 14. Section 33 42 30 – Stormwater Junction Boxes 24 15. Section 33 42 33 – Stormwater Curb Inlets and Area Drains 25 16. Section 41 14 00 – Batching Equipment 26 1.2 PRICE AND PAYMENT PROCEDURES 27 A. Measurement and Payment 28 1. Measurement 29 a. Concrete and concrete reinforcing materials, equipment, tools, testing, and 30 incidentals are subsidiary to the installation of various items. 31 2. Payment 32 a. The work performed and materials furnished in accordance with this item are 33 subsidiary to the unit prices bid for various items which require the use of 34 concrete and concrete reinforcing, and will not be measured or paid for 35 separately. 36 37 03 00 00 CONCRETE AND CONCRETE REINFORCING Page 2 of 18 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 25, 2024 Effective July 1, 2024 1.3 REFERENCES 1 A. Reference Standards 2 1. Reference standards cited in this Section refer to the current reference standard 3 published at the time of the latest revision date logged at the end of this Section 4 unless a date is specifically cited. 5 2. American Concrete Institute (ACI): 6 a. 211, Proportioning of Concrete Mixes 7 b. 301, Specifications for Structural Concrete 8 c. 318, Building Code Requirements for Structural Concrete 9 3. ASTM International (ASTM): 10 a. A36, Standard Specification for Carbon Structural Steel 11 b. A615, Standard Specification for Deformed and Plain Carbon-Steel Bars for 12 Concrete Reinforcement 13 c. A675, Standard Specification for Steel Bars, Carbon, Hot-Wrought, Special 14 Quality, Mechanical Properties 15 d. A955, Standard Specification for Deformed and Plan Stainless Steel Bars for 16 Concrete Reinforcement 17 e. A996, Standard Specification for Rail-Steel and Axle-Steel Deformed Bars for 18 Concrete Reinforcement 19 f. A1064, Standard Specification for Carbon-Steel Wire and Welded Wire 20 Reinforcement, Plain and Deformed, for Concrete 21 g. C33, Standard Specification for Concrete Aggregates 22 h. C94, Standard Specification for Ready-Mixed Concrete 23 i. C150, Standard Specification for Portland Cement 24 j. C260, Standard Specification for Air-Entraining Admixtures for Concrete 25 k. C494, Standard Specification for Chemical Admixtures for Concrete 26 l. C595, Standard Specification for Blended Hydraulic Cements 27 m. C1116, Standard Specification for Fiber-Reinforced Concrete 28 n. C1399, Standard Test Method for Obtaining Average Residual-Strength of 29 Fiber-Reinforced Concrete 30 4. Texas Department of Transportation (TxDOT) Departmental Material 31 Specifications (DMS) 32 a. DMS-4515, Multiple Piece Tie Bars for Concrete Pavements 33 b. DMS-4550, Fibers for Concrete 34 c. DMS-4600, Hydraulic Cement 35 d. DMS-4610, Fly Ash 36 e. DMS-4640, Chemical Admixtures for Concrete 37 f. DMS-4650, Hydraulic Cement Concrete Curing Materials and Evaporation 38 Retardants 39 g. DMS-6100, Epoxies and Adhesives 40 5. TxDOT Test Procedures: 41 a. Tex-401-A, Sieve Analysis of Fine and Coarse Aggregate 42 b. Tex-409-A, Free Moisture and Water Absorption in Aggregate for Concrete 43 c. Tex-470-A, Optimized Aggregate Gradation for Hydraulic Cement Concrete 44 Mix Designs 45 d. Tex-425-A, Determining Moisture Content in Fine Aggregate by the “Speedy” 46 Moisture Method 47 03 00 00 CONCRETE AND CONCRETE REINFORCING Page 3 of 18 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 25, 2024 Effective July 1, 2024 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 1 1.5 SUBMITTALS 2 A. Submittals shall be in accordance with Section 01 33 00. 3 B. All submittals shall be approved by the City prior to delivery. 4 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 5 A. Shop Drawing 6 1. Concrete Mix Design – Submit a design of the concrete mix at least 4 weeks prior 7 to the start of construction activities requiring concrete unless approved otherwise 8 by the City. Provide the mix design in accordance with the class of concrete or 9 concrete mix design specified in the Drawings including: 10 a. Concrete Material Source Information 11 1) Concrete supplier name 12 2) Project name and address 13 3) Contractor name 14 4) Mixture Identification Number 15 b. Design Requirements and Design Summary Including: 16 1) The combined aggregate gradation, source, and material testing results in 17 accordance with Section 32 05 16. 18 2) Maximum slump 19 3) Concrete intended use (sidewalk, roadway, etc) and class designation 20 4) Design water to cement (w/c) ratio 21 5) Design Target Strength 22 6) 7-Day and 28-Day compressive strengths in accordance with ACI 301 and 23 318 24 7) Batch weights, specific gravity, and type/class information for: 25 a) Cement 26 b) Supplementary cementing materials (if used) 27 c) Coarse Aggregate 28 d) Fine Aggregate 29 e) Water 30 8) Chemical admixtures – Type and amount used 31 9) Product Data for all chemical admixtures, cement, and fly ash used. 32 c. Statement from the concrete supplier verifying concrete has been tested and 33 handled in accordance with ASTM C94. 34 2. Product Data 35 a. Provide electronic product data from each manufacturer that is supplying curing 36 compounds, evaporation retardant, joint fillers, or chemical additives to be used 37 on the project. 38 b. Product data sheets for all products other than epoxy to include: 39 1) Manufacturer name 40 2) Date 41 3) Material description 42 4) Point of delivery 43 5) Data and test results as required in this Section 44 03 00 00 CONCRETE AND CONCRETE REINFORCING Page 4 of 18 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 25, 2024 Effective July 1, 2024 6) Material Safety Data Sheets (if applicable, required for Epoxy and Curing 1 Compounds) 2 7) Manufacturer Recommended Storing Data (if applicable) 3 8) Application Recommendations (if applicable) 4 9) Manufacturer’s Recommended Storage and Handling instructions 5 c. Epoxy Product Data Sheet Additional Requirements: 6 1) Resin or hardener components 7 2) Brand name 8 3) Name of manufacturer 9 4) Lot or batch number 10 5) Temperature range for storage 11 6) Date of manufacture 12 7) Expiration date 13 8) Quantity contained 14 d. Fiber Reinforcing Submittal Requirements 15 1) Product data sheet 16 2) Letter of certification stating compliance with the requirements of this 17 Section and other applicable standards. 18 3) Report that provides test results for Fiber Testing in accordance with DMS-19 4550, Fibers for Concrete 20 4) Delivery, storage, and handling instructions 21 5) Dosage requirements to provide concrete reinforcing in accordance with the 22 requirements of this Section and any other applicable related Sections. 23 6) Installation and mixing instructions 24 7) Provide the City with test results in accordance with this Section and DMS-25 4550, Fibers for Concrete. 26 B. Informational Submittals 27 1. Source Locations 28 a. Provide the location of all material sources 29 1.7 CLOSEOUT SUBMITTALS [NOT USED] 30 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 31 1.9 QUALITY ASSURANCE [NOT USED] 32 1.10 DELIVERY, STORAGE, AND HANDLING 33 A. Storage and Handling Requirements 34 1. Secure and maintain a location to store the material in accordance with Section 01 35 66 00. 36 B. Storage and Stockpiling 37 1. Cement and Supplementary Cementitious Material (SCM) 38 a. Store all cement and SCM in weatherproof enclosures to protect them from 39 dampness or absorption of moisture. 40 2. Steel Reinforcement 41 a. Store reinforcement above ground surface on skids, platforms, or other support. 42 b. Protect reinforcement from mechanical damage and surface deterioration caused 43 by exposure to conditions that could cause rust. 44 03 00 00 CONCRETE AND CONCRETE REINFORCING Page 5 of 18 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 25, 2024 Effective July 1, 2024 1.11 FIELD CONDITIONS [NOT USED] 1 1.12 WARRANTY [NOT USED] 2 PART 2 - PRODUCTS 3 2.1 CITY-SUPPLIED PRODUCTS [NOT USED] 4 2.2 MATERIALS 5 A. Concrete Production Materials 6 1. Cementitious Material 7 a. Defined as the cement and supplementary cementing materials used in concrete. 8 b. Cement 9 1) Furnish cement Type I, II, or I/II in accordance with ASTM C150 Portland 10 Cement or Type IL in accordance with ASTM C595. 11 2) Provide cement from sources that are in accordance with DMS-4600 and 12 listed on TxDOT’s Material Producer List (MPL) entitled “Hydraulic 13 Cement”. 14 c. Supplementary Cementing Materials (SCM) 15 1) Fly Ash 16 a) Refer to DMS – 4610 for types of Fly Ash 17 b) Acceptable Fly Ash includes: 18 (1) Class C and Class F 19 (2) Ultra-Fine (UFFA) 20 (3) Modified Class F (MFFA) 21 c) Provide fly ash in accordance with DMS-4610 and from sources listed 22 on TxDOT’s MPL entitled “Fly Ash”. 23 d) Refer to Table 2 for Concrete Classes and Mix Design Options. 24 2) Other SCMs 25 a) No other SCM will be approved for use. 26 2. Water 27 a. Provide mixing water and curing water free from oils, acids, organic matter, or 28 other deleterious substances. 29 b. Provide water from municipal supplies approved by the Texas Department of 30 Health. 31 c. Obtain approval from the City if using water not approved by the Texas 32 Department of Health prior to construction. 33 1) If approved to use water from a non-pre-approved source, water testing 34 may be required. The City will request tests and provide minimum criteria. 35 3. Aggregate 36 a. General 37 1) Recycled crushed concrete pavement may be used as coarse or fine 38 aggregate in Class A, B, E, and P concrete. 39 2) A maximum of 20 percent of the fine aggregate may consist of recycled 40 crushed concrete pavement. 41 b. Fine aggregate 42 1) In accordance with Section 32 05 16 43 03 00 00 CONCRETE AND CONCRETE REINFORCING Page 6 of 18 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 25, 2024 Effective July 1, 2024 c. Coarse Aggregates 1 1) Provide coarse aggregate consisting of clean, tough, durable fragments in 2 accordance with Section 32 05 16. 3 2) Provide coarse aggregates that meet the gradation shown in Table 1 when 4 tested in accordance with Tex-401-A. 5 3) Select aggregate gradation based on the allowable grade for the appropriate 6 concrete class shown in shown in Table 1. 7 Table 1 8 Coarse Aggregate Gradation Chart 9 Aggregate Grade No.1 Maximum Nominal Size Percent Passing on Each Sieve 2– 1/2” 2” 1– 1/2” 1” 3/4” 1/2” 3/8” #4 #8 1 2” 100 80– 100 50– 85 20– 40 0–5 2(467) 1-1/2” 100 95– 100 35– 70 10– 30 0–5 3 1-1/2” 100 95– 100 60– 90 25– 60 0–5 4 (57) 1” 100 95– 100 25– 60 0– 10 0– 5 5 (67) 3/4” 100 90– 100 20– 55 0– 10 0– 5 6 (7) 1/2” 100 90– 100 40– 70 0– 15 0– 5 7 3/8” 100 70– 95 0– 25 8 3/8” 100 95– 100 20– 65 0– 10 1. Corresponding ASTM C33 gradation shown in parentheses 10 4. Chemical Admixtures 11 a. General 12 1) Only water reducing and air-entraining admixtures are allowed. 13 2) Provide admixtures in accordance with DMS-4640, Chemical Admixtures 14 for concrete. 15 3) Do not use Type C, E, F, or G admixtures in Class S bridge deck concrete. 16 4) Do not use chemical admixtures containing calcium chloride in any 17 concrete. 18 b. Water Reducing Admixture 19 1) Provide water-reducing admixtures in accordance with ASTM C494. Types 20 A, D, F, and G will be allowed. 21 a) ASTM C494, Types “A” and “F”: 22 (1) Improves quality of concrete at lower cement content 23 (2) Increase slump without increasing water-cement ratio 24 b) ASTM C494, Types “D” and “G”: 25 (1) Maintains workability during hot weather placement 26 c. Air-Entraining Admixture 27 1) Provide air-entraining admixtures in accordance with ASTM C260. 28 03 00 00 CONCRETE AND CONCRETE REINFORCING Page 7 of 18 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 25, 2024 Effective July 1, 2024 2) Maintain a total air content between 3 and 7 percent. 1 3) Do not exceed the manufacturer’s recommended dosage. 2 B. Concrete Placement Materials 3 4 1. Reinforcing Steel 5 a. Provide type, size, grade, and quantity of steel reinforcement as specified in the 6 Drawings. 7 b. Provide Grade 60 or above steel bar reinforcing unless otherwise indicated in the 8 Drawings. 9 c. Provide reinforcement free from dirt, loose rust, painting, oil, or other foreign 10 material. 11 d. Provide corrosion protection if specified in the Drawings. 12 e. Provide deformed reinforcing steel in accordance with one of the following: 13 1) New Billet Steel in accordance with ASTM A615, Grades 60, 75, or 80 14 2) Axle Steel in accordance with ASTM A996, Type A, Grade 60 15 a) Provide as straight bars only and do not bend them. 16 3) Rail Steel in accordance with ASTM A996 Type R, Grade 60. 17 a) Rail steel only allowed in concrete pavement. Provide as straight bars 18 only and do not bend them. 19 f. Provide bars in accordance with the size and weight requirements for reinforcing 20 in ASTM A615. 21 g. Twisted bars are not considered deformed and will not be accepted by the City. 22 h. Steel Wire Reinforcement will not be accepted by the City. 23 i. Spiral Reinforcement 24 1) Provide smooth or deformed wire conforming to ASTM A1064. 25 2) Provide bars in accordance with ASTM A615, ASTM A996 Type A, or 26 ASTM A675 Grade 80 meeting dimensional requirements of ASTM A615. 27 j. Bending 28 1) Bend all bars cold in a shape true to the shapes specified in the Drawings. 29 2) Bend all bars used for stirrups and ties around a pin having a diameter at 30 least two times the minimum thickness of the bar. 31 3) Perform all other bends in accordance with the latest code of Standard 32 Practice of Reinforcing Steel Institute. 33 4) Bend stainless reinforcing steel in accordance with ASTM A955. 34 2. Fiber Reinforcing. 35 a. General 36 1) Fiber reinforcement is only allowed if specified on the Drawings by the 37 Engineer of record with written approval from the City. Do not use for 38 structures or roadway paving. 39 b. Material 40 1) Provide fibers in accordance with ASTM C1116, including alkali-proof, 41 non-absorptive synthetic fibers, resistant to deterioration due to long-term 42 exposure to moisture or substances present in admixtures, and do not 43 contribute to nor interfere with the air entrainment of the concrete. 44 2) Provide macrosynthetic fibers for reinforcing. Do not use natural, steel, 45 glass, or any other type without prior approval by the City. 46 03 00 00 CONCRETE AND CONCRETE REINFORCING Page 8 of 18 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 25, 2024 Effective July 1, 2024 3) Provide fibers that meet a minimum average residual strength of 115 psi 1 when tested in accordance with ASTM C1399 with the following 2 modifications: 3 a) Initial deflection for the initial crack of 0.02000 inches. 4 b) Sample tolerance of average residual strength not below 10 percent of 5 the specified required value. 6 c. Length and Size 7 1) Provide fibers maximum 1.5 inches in length. 8 d. Testing 9 1) The use of fiber reinforcing does not change the strength or fresh concrete 10 requirements per this specification. 11 e. Rejection 12 1) Any concrete installed with fiber reinforcing that is non-compliant with the 13 requirements of this Section or other applicable related Sections will be 14 removed and replaced at no cost to the City. 15 3. Tie Bars 16 a. Refer to pertinent Sections and City standard details for specific uses and 17 installation requirements for Multiple Piece Tie Bars and Single Piece Tie Bars. 18 b. Install bars in accordance with the size, type, and location specified in the 19 Drawings. 20 c. Provide straight deformed steel tie bars in accordance with ASTM A615. 21 d. Install tie bars per the size and spacing specified in the Drawings. 22 e. Do not bend or use bent tie bars. Tie bars should remain straight. 23 f. Multiple Piece Tie Bars 24 1) Provide multiple piece tie bars in accordance with DMS-4515, Multiple 25 Piece Tie Bars for Concrete Pavements. 26 4. Dowel Bars 27 a. General 28 1) Install bars in accordance with the size, type, and location shown on the 29 Drawings. 30 2) Refer to pertinent Sections and City standard details for uses and 31 installation requirements. 32 b. Dowel Bars 33 1) Provide smooth, straight dowel bars free of burrs with a yield strength of at 34 least 60 kilo-pound per square inch (ksi) as specified in the Drawings. 35 2) Provide steel in accordance with ASTM A615 or meet the physical 36 requirements of ASTM A36 for smooth bars that are larger than 3/8 inch in 37 diameter. 38 3) Coat dowels with a thin film of grease, wax, silicone, or other approved de-39 bonding material. 40 4) Designate smooth bars by diameter in inches. 41 c. Dowel Caps 42 1) Provide dowel caps on the lubricated end of each dowel bar used in an 43 expansion joint. 44 2) Provide dowel caps filled with a soft compressible material with enough 45 range of movement to allow complete closure of expansion joint. 46 03 00 00 CONCRETE AND CONCRETE REINFORCING Page 9 of 18 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 25, 2024 Effective July 1, 2024 3) Provide dowel caps to the length specified in the Drawings. The cap should 1 have sufficient length to allow at least a 1.25-inch gap between the end of the 2 bar and the edge of the cap. 3 4) Provide caps for dowel bars with an internal diameter sufficient to permit 4 the cap to freely slip over the bar, but do not have an internal diameter that 5 exceeds the bar diameter by more 1/8 inch. 6 5. Reinforcement Supporting Devices 7 a. Use reinforcement supporting devices for construction of sidewalks, driveways, 8 roadways, crosswalks, and any other concrete paving operation. 9 b. Provide positioning and supporting devices (baskets and chairs) capable of 10 securing and holding the reinforcing steel in proper position before and during 11 paving. 12 c. Do not allow construction personnel to walk on the reinforcement bars. Replace 13 any broken chairs prior to concrete placement. 14 d. Provide supporting devices (baskets and chairs) made of plastic or non-rusting 15 metal. 16 1) Supporting devices to show no visible indications of deterioration after 17 immersion in a 5-percent solution of sodium hydroxide for 120-hours. 18 2) Provide the City with test results or product data sheets proving devices are 19 in accordance with the requirements of this Section if requested. 20 6. Epoxy 21 a. Provide Type 3, Class C epoxy in accordance with DMS-6100. 22 b. City to approve all epoxy and adhesive products prior to use. Submit a Product 23 Data Sheet in accordance with this Section. 24 c. Do not use damaged or previously opened containers. 25 d. Do not use any material showing evidence of crystallization, lumps, skinning, 26 extreme thickening, or settling of pigments that cannot be readily dispersed with 27 normal agitation. 28 e. Follow sound environmental practices when disposing of epoxy and adhesive 29 wastes. 30 f. Dispose of all empty containers separately. Completely empty and mix the 31 epoxy before disposal. 32 7. Evaporation Retardant 33 a. Provide evaporation retardant in accordance with DMS-4650. 34 8. Curing 35 a. The use of mats, plastic, or film to be approved by the City prior to use. 36 b. Provide membrane curing compounds in accordance with this specification and 37 DMS-4650. 38 1) Provide curing material in accordance with the requirements of DMS-4650 39 unless otherwise specified in the Drawings or by the City. 40 2) Provide a curing compound that does not react deleteriously with concrete 41 or its compounds. 42 3) Curing compound to produce a firm, continuous uniform moisture-43 impermeable film free from pinholes and adhere to surface of damp concrete. 44 4) The City may reject any concrete not cured properly due to improperly 45 applied curing compound or faulty materials. 46 5) The City may reject the curing compound based on visual or odor defects. 47 03 00 00 CONCRETE AND CONCRETE REINFORCING Page 10 of 18 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 25, 2024 Effective July 1, 2024 6) Curing compound to be delivered to the job site in the manufacturer's 1 original containers only, with original label containing the following: 2 a) Manufacturer's name 3 b) Trade name of the material 4 c) Batch number or symbol with which test samples may be correlated 5 C. Concrete Mix Design 6 1. General 7 a. Furnish mix designs using ACI 211 or Tex-470-A. 8 b. Maintain mix design and maximum water to cement ratio once mix design is 9 approved by City. 10 c. Do not place concrete until the mix design has been approved by the City. The 11 City may require any concrete placed prior to approval to be removed and 12 replaced at no cost to the City. 13 d. Perform mix design proportioning by absolute volume method unless otherwise 14 approved. 15 e. Perform cement replacement using equivalent weight method unless otherwise 16 approved. 17 f. Do not exceed specified water to cement ratios listed in Table 2 for concrete 18 classes when designing the mixture. 19 g. Provide a mix design after the trial batch tests are complete in accordance with 20 the requirements in this Section. 21 2. Cementitious Material 22 a. Do not exceed 700 pounds of cementitious material per cubic yard of concrete 23 unless otherwise specified or approved by the City. 24 b. Use cement of the same type and from the same source for monolithic 25 placements. 26 3. Concrete Classes 27 a. General 28 1) Provide concrete mix designs in accordance with the requirements shown in 29 Table 2 for the class of concrete specified in the Drawings. 30 2) Refer to the Drawings and the General Usage column on Table 2 for 31 concrete class information. 32 3) For concrete classes not specified in Table 2 refer to the Drawings or 33 special project specifications for concrete mix design requirements. 34 b. Class P Concrete 35 1) Use air entraining admixture. 36 2) Class P1 Concrete 37 a) Use Class P1 concrete for machine paved concrete roadways and 38 alleyways unless otherwise specified in the Drawings or directed by City. 39 3) Class P2 Concrete 40 a) Provide Class P2 concrete for hand poured concrete roadways, 41 driveways, alleyways, and all other hand poured, vehicular trafficked 42 concrete pavement unless otherwise specified in the Drawings. 43 c. High Early Strength Concrete (HES) 44 1) Use air entraining admixture. 45 2) Provide HES concrete in accordance with the requirements of Table 2. 46 3) Use HES concrete only when specified in the Drawings or when directed 47 by City. 48 03 00 00 CONCRETE AND CONCRETE REINFORCING Page 11 of 18 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 25, 2024 Effective July 1, 2024 4) HES may be approved for use when a roadway or driveway needs to be 1 opened to traffic quickly. 2 5) Perform tests at 24 hours to verify compressive strength of HES concrete is 3 minimum 3,200 psi. 4 6) Maximum coarse aggregate size is 1–1/2 inches. 5 03 00 00 CONCRETE AND CONCRETE REINFORCING Page 12 of 18 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 25, 2024 Effective July 1, 2024 Table 2 1 Concrete Classes 2 Class of Concrete Design Strength1, Min f’c (psi) Maximum Water to Cementitious Material Ratio Coarse Aggregate Grades2,3 Cement Types Mix Design Options General Usage4 A 3,000 0.60 1 – 4, 8 I, II, I/II, IL 1 and 2 Sidewalks, sidewalk curbs, riprap, channel liners, flumes B 2,000 0.60 2 – 7 I, II, I/II, IL Traffic signal controller foundations, small roadside signs, anchors, blocking, utility pipe encasement C5 3,600 0.45 1 – 6 I, II, I/II, IL 1 – 3 Culverts (except top slab of direct traffic culverts) E 3,000 0.50 2 – 5 I, II, I/II, IL 1 – 3 Seal concrete H5 Note 6 0.45 3 – 6 I, II, I/II, IL 1 – 3 Precast concrete S5 4,000 0.45 2 – 5 I, II, I/II, IL 1 – 3 Top slabs of direct traffic culverts, approach slabs, headwalls, wingwalls, cast-in-place inlets, junction boxes and manholes P18 4,000 0.50 2 – 3 I, II, I/II, IL 1 – 3 Machine poured concrete pavement, monolithic curbs, non- monolithic curb and curb & gutter P28 4,500 0.45 2 – 3 I, II, I/II, IL 1 – 3 Hand poured concrete pavement, driveways, and decorative concrete pavement HES8 4,500 0.45 2 – 3 I, II, I/II, IL Note 7 Concrete pavement and concrete pavement repair 1. Design strength must be attained within 56 days. 3 2. Do not use Grade 1 coarse aggregate except in foundations with 4 inch minimum clear spacing between 4 reinforcing steel bars unless otherwise specified on the Drawings or approved by the City. Do not use Grade 1 5 aggregate in drilled shafts. 6 3. Use Grade 8 aggregate in extruded curbs unless otherwise approved by the City or specified on the Drawings. 7 4. For information only. 8 03 00 00 CONCRETE AND CONCRETE REINFORCING Page 13 of 18 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 25, 2024 Effective July 1, 2024 5. Structural concrete classes. 1 6. As shown on the Drawings or in the City Standard Details. 2 7. Mix design options do not apply. 700 pounds of cementitious material per cubic yard limit does not apply. 3 8. For machine poured concrete, use a minimum cementitious material content of 517 pounds per cubic yard. For 4 hand poured concrete, use a minimum cementitious material content of 564 pounds per cubic yard. 5 6 4. Slump 7 a. Provide concrete with a slump in accordance with Table 3 unless otherwise 8 specified in the Drawings. 9 b. Request approval to exceed the slump limits listed in Table 3 with the mix 10 design submittal as part of the Action Submittal. 11 c. Do not exceed maximum slump during production of the mix design or during 12 concrete placement. 13 d. Any concrete placed with a slump exceeding the limits shown in Table 3 will be 14 rejected and removed and replaced at no cost to the City. 15 Table 3 16 Concrete Pavement Slump Requirements 17 Concrete Use1 Slump Range2, Inch Walls (over 9 inches thick), caps, columns, piers, approach slabs 3 – 5 Bridge slabs, top slabs of direct traffic culverts 3 – 5 Inlets, manholes, walls (less than 9 inches thick), bridge railing, culverts, concrete traffic barrier 4 – 6 Precast concrete 4 – 9 Underwater concrete placements 6 – 8 Drilled shafts, slurry displaced and underwater drilled shafts Note 3 Machine Poured Paving (Class P1 Concrete) 1.5 – 3 Hand Poured Paving (Class P2 and HES Concrete) 3 – 5 Curb, gutter, curb and gutter, sidewalk, driveways, riprap, small roadside sign foundations, concrete pavement repair, concrete repair, concrete base material for trench repair. 1.5 – 4 1. For information only. 18 2. For fiber reinforced concrete, perform slump before addition of fibers. 19 3. As shown on the Drawings. 20 21 5. Mix Design Options 22 a. Option 1: Replace cement with at least the minimum dosage listed in the Fly 23 Ash MPL for the fly ash used in the mixture. Do not replace more than 50% of 24 the cement with fly ash. 25 b. Option 2: Replace 35 to 50 percent of the cement with slag cement. 26 c. Option 3: Replace 35 to 50 percent of the cement with a combination of fly ash, 27 slag cement, MFA, metakaolin, or at least 3% silica fume; however, no more 28 than 35% may be fly ash, and no more than 10% may be silica fume.. 29 6. Trial Batch Production and Testing 30 a. Trial Batch 31 03 00 00 CONCRETE AND CONCRETE REINFORCING Page 14 of 18 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 25, 2024 Effective July 1, 2024 1) Produce a trial batch of the mix design in accordance with the requirements 1 of the concrete class specified in the Drawings, using the same materials 2 proposed for the project. 3 2) Perform testing and provide the results verifying the concrete mix design is 4 in accordance with the requirements of this Section. Testing to include: 5 a) Fresh concrete tests for air content and slump 6 b) Strength testing at 7 days and 28 days 7 3) Do not modify the mix design after the City has approved it. 8 4) Submit a new mix design if a change is made to concrete supplier. 9 Table 4 10 Concrete Discharge Times 11 Fresh Concrete Temperature, Degrees Fahrenheit Max Time After Batching for Concrete Not Containing Type B or D Admixtures, Minimum Max Time After Batching for Concrete Containing Type B or D Admixtures2, Minimum 90 and Above 45 75 Between 75 and 90 60 90 Below 75 90 120 1. Admixture Types are defined in DMS-4640 2. Concrete must contain at least the minimum manufacturer’s recommended dosage of Type B or D admixture. 3. Batching can occur at a commercial concrete site or at a batch plant. 2.3 ACCESSORIES [NOT USED] 12 2.4 SOURCE QUALITY CONTROL 13 A. Concrete Mix Design and Verification 14 1. Any concrete installed using a non-conforming mix design is subject to removal 15 and replacement at no cost to the City. 16 B. Concrete Production Acceptance 17 1. During production and placement of concrete, perform testing to verify the concrete 18 is in accordance with the requirements in this Section for admixtures, mix design, 19 slump, and compressive strength. 20 C. Concrete Placement Acceptance 21 1. General 22 a. If concrete is suspected of having foreign material, City may reject at any time 23 and the concrete may be removed and replaced at no cost to the City. 24 b. Acceptance will be based on attaining the strength and the fresh concrete tests. 25 2. Placement Sampling 26 a. Perform all fresh and hardened concrete testing at the frequency shown on Table 27 5. 28 b. If any test comes back as non-conforming, stop production and placement of 29 concrete until the reason has been determined and resolved. 30 c. Any concrete that was placed is subject to further testing and removal and 31 replacement at no cost to the City. 32 03 00 00 CONCRETE AND CONCRETE REINFORCING Page 15 of 18 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 25, 2024 Effective July 1, 2024 Table 5 1 Testing Frequencies 2 Concrete Placements Frequency Bridge Deck Placements Test the first 3 loads, then every 60 cubic yards or a fraction thereof specified by the City. All Other Structural Class Concrete Placements One test every 60 cubic yards or a fraction thereof per class per day as specified by the City Non-Structural Class Concrete Placements One test every 180 cubic yards or a fraction thereof as specified by the City 3. Testing of Fresh Concrete 3 a. Sample and test fresh concrete for properties listed in Table 6. 4 b. Take the sample at the time of discharge from the delivery truck. 5 c. Concrete that is exhibiting segregation, excessive bleeding, or has a slump 6 below the minimum allowed per concrete type (per Table 3) after addition of all 7 water withheld will be rejected. Contractor will remove and replace at no cost to 8 the City. 9 Table 6 10 Fresh Concrete Tests 11 Tests Test Methods Slump Tex-415-A Temperature Tex-422-A Air Content 1 Tex-414-A, Tex-416-A, or ASTM C457 1. Only required when air-entraining admixtures are used. 4. Concrete Strength Test 12 a. General 13 1) Perform strength testing for all projects containing more than 60 cubic 14 yards of concrete. 15 2) Provide trained technicians during concrete paving to cast test cylinders in 16 accordance with ASTM C31. 17 3) Refer to Table 2 for required strength for each concrete class. 18 b. Sampling 19 1) Collect 6 test cylinders from a representative portion of concrete being 20 placed for each test, with no less than two sets of cylinders taken from any 21 one day’s paving activities. 22 2) After the cylinders have been cast by trained technicians, transport samples 23 to the lab and test in accordance with ASTM C31 and ASTM C39. Provide 24 test results to the City. 25 3) Test the 6 cylinders per the following: 26 a) 2 of the cylinders tested at 7 days, 27 b) 2 cylinders tested at 28 days, and 28 c) 2 cylinder held and tested at 56 days, if necessary. 29 30 03 00 00 CONCRETE AND CONCRETE REINFORCING Page 16 of 18 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 25, 2024 Effective July 1, 2024 c. Acceptance 1 1) If the 28-day test results for the cylinders taken indicate deficient strength, 2 the Contractor may, at their own expense, core the pavement in question and 3 have the cores tested by another approved laboratory, in accordance with 4 ASTM C42 and ACI 318 protocol. 5 2) Average of the 28-day test results of all cores within a designated area must 6 meet 100 percent of the minimum specified strength. 7 3) If any individual cylinder or core results in less than 90 percent of design 8 strength, additional cores will be taken to identify the limits of the non-9 compliant concrete at no cost to the City. 10 4) All concrete considered non-compliant will be removed and replaced at no 11 cost to the City. 12 5. Cracked Concrete Acceptance Policy 13 a. If cracks greater than 0.025-inches exist in concrete pavement upon completion 14 of the project and prior to the termination of the maintenance period, the City 15 may require corrective action that could include removal and replacement at no 16 cost to the City depending on the cause of the cracking. 17 b. Corrective Actions: 18 1) The City will determine whether the following options are viable. The City 19 will evaluate each crack greater than 0.025-inches during the final inspection 20 and prior to the end of the maintenance period. 21 2) Routing and Sealing: 22 a) Perform the routing and sealing work as directed by the Project 23 Inspector, at no cost to the City, regardless of the cause of the cracking. 24 3) If routing and sealing is not a viable solution due to the cause of the 25 cracking, or the size, remove and replace the concrete. 26 4) If the cause of the cracking is determined to be due to deficient subgrade, 27 remove and replace the subgrade with flexible base or another approved 28 subgrade within the limits of the deficient concrete. 29 6. Aggregate Moisture Testing 30 a. Perform testing and provide results in accordance with 32 05 16. 31 b. City may request this test to be performed at any time. 32 D. Non-Conforming Work 33 1. Concrete Mix Design and Production Materials 34 a. The City may reject the mix design if not in accordance with the requirements of 35 this Section. 36 1) Any concrete installed using a non-conforming mix design will be subject 37 to removal and replacement at no cost to the City. 38 b. If the trial batch fails to meet the requirements specified in this Section, the 39 Contractor will produce test results for trial batches until the trial batch meets 40 the requirements specified herein at no cost to the City. 41 c. The City may perform verification testing on all materials to verify the 42 conformance of the mixture. 43 PART 3 - EXECUTION 44 3.1 INSTALLERS [NOT USED] 45 03 00 00 CONCRETE AND CONCRETE REINFORCING Page 17 of 18 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 25, 2024 Effective July 1, 2024 3.2 EXAMINATION [NOT USED] 1 3.3 PREPARATION [NOT USED] 2 3.4 INSTALLATION 3 A. Batching Equipment 4 1. Batching equipment shall be in accordance with the requirements of Section 41 14 5 00. 6 B. Refer to the following Sections for all installation requirements: 7 1. Section 03 30 00 Cast-in-Place Concrete 8 2. Section 03 80 00 Modifications to Existing Concrete Structures 9 3. Section 31 37 00 for Riprap 10 4. Section 32 13 13 for Concrete Paving 11 5. Section 32 13 16 for Decorative Concrete Paving 12 6. Section 32 16 00 for Curbs, Gutters, Sidewalks, and Driveways 13 7. Section 32 32 00 for Retaining Walls 14 8. Section 33 05 61 for Cast-in-Place Concrete Manholes 15 9. Section 33 42 11 for Stormwater Pipe and Boxes 16 10. Section 33 42 23 for Stormwater Headwalls, Wingwalls, and End Treatments 17 11. Section 33 42 30 for Stormwater Junction Boxes 18 12. Section 33 42 33 for Stormwater Curb Inlets and Area Drains 19 3.5 REPAIR [NOT USED] 20 3.6 RE-INSTALLATION [NOT USED] 21 3.7 SITE QUALITY CONTROL [NOT USED] 22 3.8 SYSTEM STARTUP [NOT USED] 23 3.9 ADJUSTING [NOT USED] 24 3.10 CLEANING [NOT USED] 25 3.11 CLOSEOUT ACTIVITIES [NOT USED] 26 3.12 PROTECTION [NOT USED] 27 3.13 MAINTENANCE [NOT USED] 28 29 03 00 00 CONCRETE AND CONCRETE REINFORCING Page 18 of 18 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 25, 2024 Effective July 1, 2024 3.14 ATTACHMENTS [NOT USED] 1 END OF SECTION 2 3 Revision Log DATE NAME SUMMARY OF CHANGE 6/25/2024 Added ASTM C595 reference 6/25/2024 Added Type IL cement to allowable cement in 2.2.A.1.b and subsequent locations 6/25/2024 Modified air entrainment ranges under 2.2.A.4.C.2 6/25/2024 Modified fiber reinforcement requirements; 2.2.B.2 6/25/2024 Modified Table 2 “Concrete Classes” to allow for Type IL cement, altered General Usage types, and removed Classes D and F from the table 6/25/2024 Modified Table 3 “Concrete Pavement Slump Requirements” to give greater slump ranges 6/25/2024 Modified mix design options for replacement of cement with various substitute products; 2.2.C.5 6/25/2024 Altered test cylinder requirements; 2.4.C.4 4 03 30 00 CAST-IN-PLACE CONCRETE Page 1 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 03 30 00 1 CAST-IN-PLACE CONCRETE 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Cast-in-place concrete, including formwork, reinforcement, concrete materials, 6 mixture design, and placement procedures. 7 B. Deviations from this City of Denton Standard Specification: 8 1. None. 9 C. Related Specification Sections include but are not limited to: 10 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 11 Contract. 12 2. Division 1 - General Requirements. 13 3. Section 03 00 00 – Concrete and Concrete Reinforcing. 14 4. Section 32 01 29 – Rigid Paving Repair. 15 5. Section 32 05 16 – Aggregates for Exterior Improvements. 16 6. Section 32 13 13 – Concrete Paving. 17 7. Section 41 14 00 – Batching Equipment. 18 1.2 PRICE AND PAYMENT PROCEDURES 19 A. Measurement and Payment 20 1. Measurement 21 a. Cast-in-place concrete materials, equipment, tools, testing, and incidentals are 22 subsidiary to the installation of structures or item being installed. 23 2. Payment 24 a. The work performed and materials furnished in accordance with this item are 25 subsidiary to the unit prices bid for various items which require the use of cast-26 in-place concrete. 27 1.3 REFERENCES 28 A. Abbreviations and Acronyms 29 1. HPC – High Performance Concrete 30 2. PSI – Pounds per square inch 31 B. Definitions 32 1. Substructure 33 03 30 00 CAST-IN-PLACE CONCRETE Page 2 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 a. Structures that are below ground, partially below ground, or retain earth. 1 Substructures could include: footings, columns, caps, abutments, piers, culverts, 2 retaining walls, headwalls, wingwalls, riprap, other bridge substructure 3 elements, and other concrete structures as indicated, or not included as a 4 superstructure. 5 2. Superstructure 6 a. Structures that are elevated above ground. Superstructures could include: bridge 7 slabs, decks, flat slabs, slab and girder units, approach slabs, or other bridge 8 superstructure elements as indicated. 9 C. Reference Standards 10 1. Reference standards cited in this Section refer to the current reference standard 11 published at the time of the latest revision date logged at the end of this Section 12 unless a date is specifically cited. 13 2. American Association of State Highway and Transportation Officials (AASHTO). 14 3. American Concrete Institute (ACI): 15 a. ACI 207 – Mass Concrete. 16 4. Texas Department of Transportation, Standard Specifications for Construction and 17 Maintenance of Highways, Streets, and Bridges (TxDOT): 18 a. Item 420 – Concrete Substructures. 19 b. Item 422 – Concrete Superstructures. 20 c. Item 426 – Post-Tensioning. 21 d. Item 441 – Steel Structures. 22 e. Item 448 – Structural Field Welding. 23 5. Texas Department of Transportation (TxDOT) Departmental Material 24 Specifications (DMS): 25 a. DMS-4650 – Hydraulic Cement Concrete Curing Materials and Evaporation 26 Retardants. 27 b. DMS-4675 – Cementitious Grouts and Mortars for Miscellaneous Applications. 28 c. DMS-6100 – Epoxies and Adhesives. 29 d. DMS-6160 – Water Stops, Nylon-Reinforced Neoprene Sheet, and Elastometric 30 Pads. 31 e. DMS-6310 – Joint Sealants and Fillers. 32 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 33 1.5 SUBMITTALS 34 A. Submittals shall be in accordance with Section 01 33 00. 35 B. All submittals shall be approved by the City prior to delivery. 36 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 37 A. Shop Drawings 38 1. Concrete Mix Design 39 a. In accordance with Section 03 00 00. 40 2. Product Data 41 a. Provide a product data sheet from each manufacturer supplying the following in 42 accordance with Section 03 00 00: 43 03 30 00 CAST-IN-PLACE CONCRETE Page 3 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1) Curing compounds 1 2) Evaporation retardant 2 3) Joint fillers 3 4) Chemical additives 4 5) Epoxy 5 6) Fiber reinforcing 6 7) Bond breaker material 7 3. Curing Method, Equipment, and Materials 8 a. Provide the method of curing, list of materials, and list of equipment to be used 9 for review. Obtain approval prior to placing concrete. 10 b. If different methods, equipment, or materials will be used in various locations, 11 provide each method, equipment, and material used at each location using cast-12 in-place concrete. 13 4. Heat Control Plan 14 a. Provide a heat control plan for monolithic placements specified as mass 15 concrete in the Drawings. 16 b. Develop using TxDOT’s ConcreteWorks software, or another approved method 17 in accordance with ACI 207. 18 1) Use historical temperature ranges for the anticipated time of the mass 19 placement. 20 2) Re-create plan if the work schedule shifts by more than one month. 21 c. Provide a heat control plan including the following applicable elements: 22 1) Selection of concrete ingredients including aggregates, gradation, and 23 cement types to minimize heat of hydration; 24 2) Use of ice or other concrete cooling ingredients; 25 3) Use of liquid nitrogen dosing systems; 26 4) Controlling rate or time of concrete placement; 27 5) Use of insulation or supplemental external heat to control heat loss; 28 6) Use of supplementary cementing materials; 29 7) Use of a cooling system to control the core temperature; or 30 8) Variation of the duration formwork remains in place. 31 B. Informational Submittals: 32 1. Source Locations 33 a. Location of all material sources 34 1. Testing Laboratory 35 a. Submit for review and approval the following information for each testing 36 laboratory used on the project: 37 1) Testing Laboratory Name 38 2) Location 39 3) Tests performed 40 a) Summary of each test performed at each lab, if multiple labs are used. 41 4) ACI Certification 42 a) All labs and Contractor personnel performing concrete testing must be 43 ACI certified. 44 2. Falsework and Forms Drawings 45 a. Submit Drawings for falsework and forms for the following items: 46 1) Vertical forms for piers and single column bents; 47 03 30 00 CAST-IN-PLACE CONCRETE Page 4 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2) Load supporting forms for caps and tie-beams; 1 3) Form attachments for bridges to be widened; and 2 4) Other items specified in the Drawings or by the city. 3 b. Design and construct falsework to safely carry the maximum anticipated loads 4 and to provide the necessary rigidity. 5 c. Use AASHTO’s Guide Design Specifications for Bridge Temporary Works and 6 Construction Handbook for Bridge Temporary works for falsework and shoring 7 information. 8 d. Provide design calculations when requested and show all essential details of 9 proposed forms, falsework, and bracing signed and sealed by a licensed 10 professional engineer in the state of Texas. 11 e. The Contractor is responsible for the design and safety of all falsework and 12 forms. 13 f. Account for the weight of materials and live loading when designing forms. 14 3. Equipment Information 15 a. Submittal for all major equipment including: 16 1) Equipment name and description 17 2) Size 18 3) Intended use 19 1.7 CLOSEOUT SUBMITTALS [NOT USED] 20 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 21 1.9 QUALITY ASSURANCE [NOT USED] 22 1.10 DELIVERY, STORAGE, AND HANDLING 23 A. Secure and maintain a location to store the material in accordance with Section 01 66 24 00. 25 B. Storage and Stockpiling 26 1. Cement and Supplementary Cementitious Material 27 a. In accordance with Section 03 00 00. 28 2. Steel Reinforcement 29 a. In accordance with Section 03 00 00. 30 3. Chemical Admixture, Epoxy, Curing Compound, and Other Materials 31 a. Follow manufacturer’s instructions regarding storage and application at 32 temperatures of material. 33 4. Epoxy 34 a. In accordance with Section 32 13 13. 35 1.11 FIELD CONDITIONS 36 A. Weather Conditions 37 1. In accordance with Sections 03 00 00 and 32 13 13. 38 2. Do not place concrete in contact with any material coated with frost or with a 39 temperature of 32 degrees Fahrenheit or lower. 40 3. Do not place concrete when the ambient temperature in the shade is below 40 41 degrees Fahrenheit and falling unless approved. 42 03 30 00 CAST-IN-PLACE CONCRETE Page 5 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 4. Place concrete when the ambient temperature in the shade is at least 35 degrees 1 Fahrenheit and rising or above 40 degrees Fahrenheit. 2 1.12 WARRANTY [NOT USED] 3 PART 2 - PRODUCTS 4 2.1 CITY-SUPPLIED PRODUCTS [NOT USED] 5 2.2 MATERIALS 6 A. Concrete Production Materials 7 1. Concrete Class 8 a. As specified in the Drawings or in accordance with the usage stated in Section 9 03 00 00. 10 2. Provide cementitious materials, water, aggregate, chemical admixtures, reinforcing 11 materials, and evaporation retardant in accordance with Sections 03 00 00 and 32 12 13 13. 13 B. Concrete in Water 14 1. Design the mix in accordance with Section 03 00 00 with a minimum cement 15 content of 650 pounds per cubic yard for concrete to be placed under water. Include 16 an anti-washout admixture in the mix design as necessary. 17 C. Grout, Mortar, and Epoxy 18 1. Provide grout in accordance with DMS-4675. 19 2. For use with Anchor Bolts or Dowels 20 a. Provide grout, epoxy, or epoxy mortar as the binding agent unless otherwise 21 specified in the Drawings. 22 b. Neat Epoxy 23 1) Provide a Type 3 epoxy in accordance with DMS-6100. 24 c. Epoxy Mortar 25 1) Provide a Type 8 epoxy in accordance with DMS-6100. 26 D. Jointing Materials 27 1. Joint Fillers 28 a. Provide in accordance with Section 32 13 13 and DMS-6310. 29 b. Superstructures 30 1) Provide joint materials in accordance with TxDOT Standard Specification 31 Item 422 32 2. Joint Sealants 33 a. Provide in accordance with Section 32 13 73. 34 E. Waterstops 35 1. Provide rubber or polyvinyl chloride (PVC) waterstops in accordance with DMS-36 6160 unless otherwise specified in the Drawings. 37 F. Curing 38 1. Provide membrane curing compounds in accordance with Section 03 00 00 and 39 DMS-4650. 40 03 30 00 CAST-IN-PLACE CONCRETE Page 6 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2. Cotton Mats 1 a. Provide cotton mats consisting of a filling material of cotton “bat” or “bats” (at 2 least 12 ounces per square yard) completely covered with unsized cloth (at least 3 6 ounces per square yard) stitched longitudinally with continuous parallel rows 4 of stitching spaced at less than 4 inches or tuft both longitudinally and 5 transversely at intervals less than 3 inches. 6 b. Provide cotton mats free from tears and in good general condition. 7 c. Provide a flap at least 6 inches wide consisting of 2 thicknesses of the covering 8 and extending along 1 side of the mat. 9 d. When using cotton mats, provide a layer of polyethylene sheeting on top of the 10 cotton mats. 11 3. Burlap Mats 12 a. Provide burlap material which complies with AASHTO M 182, Class 3 (10 13 ounces per square yard) with the following additions: 14 1) Do not use burlap fabricated from bags. 15 2) Do not use burlap containing any water-soluble ingredient. 16 b. Provide burlap only previously used for curing concrete. 17 c. Provide burlap mats free from contamination with any substance foreign to the 18 concrete curing process, such as grease or oil. 19 d. Concrete will be rejected if cured with contaminated burlap mats. 20 e. When using burlap mats, provide a layer of polyethylene sheeting on top of the 21 burlap mats. 22 4. Polyethylene Sheeting 23 a. Provide polyethylene sheeting a minimum of 4 millimeters thick and free from 24 visible defects. 25 b. Provide only clear or opaque white sheeting when the ambient temperature 26 during curing exceeds 90 degrees Fahrenheit, or when applicable to control 27 temperature during mass pours. 28 5. Burlap-Polyethylene Mats 29 a. Provide mats made from burlap impregnated on one side with a film of opaque 30 white pigmented polyethylene. 31 b. Provide laminated mats with a minimum of one layer of an impervious material 32 such as polyethylene, vinyl plastic, or other acceptable material (either as a 33 solid sheet or impregnated into another fabric) 34 c. Provide mats free of visible defects. 35 G. Formwork Materials 36 1. Timber Forms 37 a. Provide properly seasoned, good-quality lumber free from imperfections that 38 compromise the material strength or impair the finished surface of the concrete. 39 b. Provide timber or lumber in accordance with the requirements for species and 40 grade in the submitted falsework and form drawings. 41 c. Maintain forms or form lumber to maintain a good, clean condition. 42 d. Do not use any split, warped, bulged, or marred lumber, or any lumber with 43 defects that will produce inferior work. 44 e. Provide form lining for all formed surfaces except: 45 1) The inside of culvert barrels, inlets, manholes, and box girders; 46 2) Surfaces that are subsequently covered by backfill materials, or are 47 completely enclosed; and 48 03 30 00 CAST-IN-PLACE CONCRETE Page 7 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3) Any surface formed by a single finished board or by plywood. 1 f. Provide form lining of an approved type, such as Masonite or plywood. Do not 2 provide thin membrane sheeting, such as polyethylene sheets, for form lining. 3 g. Use plywood a minimum of 3/4 inch thick. Place the grain of the face plies on 4 plywood forms parallel to the span between the supporting studs or joists unless 5 otherwise indicated on the submitted falsework and form drawings. 6 h. Use plywood for forming exposed surfaces in accordance with the requirements 7 for B-B Plyform Class 1 or Class 2 Exterior of the US Department of 8 Commerce Voluntary Product Standard PS 1. 9 i. Space studs and joists so the facing form material remains in true alignment 10 under the imposed loads. 11 j. Space wales close enough to hold forms securely to the designated lines and 12 scabbed at least 4 feet on each side of joints to provide continuity. Place a row 13 of wales near the bottom of each placement. 14 k. Place facing material with parallel and square joints, securely fastened to 15 supporting studs. 16 l. Place forms with the form panels symmetrical (long dimensions set in the same 17 direction) for surfaces exposed to view and receiving only an ordinary surface 18 finish. 19 m. Make molding for chamfer strips or other materials that will not split when 20 nailed and can be maintained to a true line without warping. 21 n. Fill forms at all sharp corners and edges with triangular chamfer strips 22 measuring 3/4 inches on the sides unless otherwise specified in the Drawings. 23 o. Remove metal and wooden spreaders separating the forms as the concrete is 24 being placed. 25 p. Provide adequate clean-out openings for narrow walls and other locations 26 where access to the bottom of the forms is not readily available. 27 2. Metal Forms 28 a. Requirements for timber forms also apply to metal forms. Metal forms do not 29 require lining unless otherwise specified in the Drawings or by the City. 30 b. Use form metal thick enough to maintain the true shape without warping or 31 bulging. 32 c. Countersink all bolt and rivet heads on the facing sides. 33 d. Design clamps, pins, or other connecting devices to hold the forms rigidly 34 together and to allow removal without damage to the concrete. 35 e. Use metal forms that present a smooth surface and line up properly. 36 H. Repair Materials 37 1. In accordance with Section 32 01 29. 38 2.3 ACCESSORIES [NOT USED] 39 2.4 SOURCE QUALITY CONTROL 40 A. Tests and Inspections 41 1. Material Source Testing and Submittals 42 a. Perform in accordance with Sections 03 00 00 and 32 13 13. 43 03 30 00 CAST-IN-PLACE CONCRETE Page 8 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 PART 3 - EXECUTION 1 3.1 INSTALLERS [NOT USED] 2 3.2 EXAMINATION [NOT USED] 3 4 3.3 PREPARATION 5 A. Hauling 6 1. Deliver concrete to the Site in accordance with Sections 41 14 00 and 03 00 00. 7 2. Maintain concrete delivery and placement rates to prevent cold joints and in 8 accordance with Section 03 00 00. 9 3. Any concrete not placed within the time limits specified under Section 03 00 00 10 will be rejected. 11 4. Protect concrete transported by conveyors from sun and wind to prevent loss of 12 slump and workability. Shade or wrap the pipes the concrete is pumped through, if 13 necessary. 14 a. Wrap pipes in wet burlap. 15 5. Adding Water or Chemical Admixtures 16 a. Water may be added to the truck until the slump test is conducted. Once the 17 slump test is conducted, the addition of water or admixtures is not permitted 18 unless the slump is too low or otherwise permitted. 19 b. When water or air entraining admixture is added, turn the drum or blades at 20 least 30 additional revolutions at mixing speed to ensure thorough and uniform 21 mixing of the concrete. 22 c. When water is added, do not exceed the approved mix design water to 23 cementitious material ratio. 24 d. Do not add water or chemical admixtures after any concrete has been 25 discharged. 26 B. Transport and Discharging 27 1. Arrange discharging equipment, such as chutes, troughs, conveyors, pipes, and 28 vertical downspouts, to prevent segregation of the concrete material. 29 2. Keep all transporting and discharging equipment clean and free from hardened 30 concrete coatings. 31 3. Discharge water used for cleaning clear of the concrete. 32 4. Discharging Time 33 a. In accordance with Section 03 00 00. 34 C. Concrete Temperature 35 1. Place concrete according to the following temperature limits for the classes of 36 concrete defined in Section 03 00 00. 37 a. Class C, F, or H 38 1) Concrete temperature at time of placement is between 50 and 95 degrees 39 Fahrenheit. 40 b. Class S Culvert Top Slabs 41 1) Concrete temperature at time of placement is between 50 and 85 degrees 42 Fahrenheit. 43 03 30 00 CAST-IN-PLACE CONCRETE Page 9 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 c. Class A and B 1 1) Concrete temperature at time of placement is greater than 50 degrees 2 Fahrenheit. 3 d. Mass Concrete 4 1) Concrete temperature at time of placement is between 50 and 75 degrees 5 Fahrenheit. 6 D. Surface Preparation 7 1. Thoroughly wet all forms and adjacent hardened concrete prior to placing concrete. 8 2. Remove any remaining puddles of excess water before placing concrete. 9 3. Provide surfaces in a moist, saturated surface-dry condition when concrete is placed 10 on them. 11 4. Ensure the subgrade or foundation is moist before placing concrete on grade. 12 3.4 INSTALLATION 13 A. Superstructure Construction 14 1. Construct all superstructures in accordance with TxDOT Standard Specification 15 Item 422. 16 B. Schedule Restrictions 17 1. Reducing Schedule Restrictions 18 a. The Contractor may request to perform additional testing to reduce the schedule 19 restrictions required. At the time of request, the City will provide additional 20 testing requirements based on the site conditions. 21 b. If the Contractor does not perform additional strength testing, the 7-day lab-22 cured tests will be used for strength determination unless otherwise specified in 23 the Drawings. 24 2. Setting Forms 25 a. Attain at least 3,000 psi compressive strength before erecting forms on concrete 26 footings supported by piling or drilled shafts, or on individual drilled shafts. 27 b. Erect forms on spread footings and culvert footings after the concrete has aged 28 at least 2 curing days. 29 c. Place concrete only after the forms and reinforcing steel have been inspected. 30 d. Support tie beam or cap forms by falsework on previously placed tie beams 31 only if the tie beam concrete has attained a compressive strength of 3,000 psi 32 and the member is properly supported. 33 e. Maintain curing as required until completion of the curing period. 34 f. Place superstructure forms or falsework on the substructure only if the 35 substructure concrete has attained a minimum compressive strength of 3,000 36 psi. 37 3. Placement of Superstructure Members 38 a. Place superstructure members or precast substructure members only after the 39 substructure concrete has attained a compressive strength of 3,000 psi. 40 4. Opening to Traffic 41 a. Direct traffic culverts may be opened to traffic when the design strength 42 specified in the Drawings or in Section 03 00 00 has been reached and after the 43 curing period has ended. 44 b. Obtain approval before opening direct traffic culverts to the traveling public. 45 03 30 00 CAST-IN-PLACE CONCRETE Page 10 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 5. Post-Tensioned Construction 1 a. Ensure strength requirements specified in the Drawings for structural element 2 designed to be post-tensioned are met for stressing and staged loading of 3 structural elements. 4 5 C. Falsework and Forms 6 1. Falsework 7 a. Provide falsework design and materials in accordance with TxDOT Standard 8 Specification Item 420. 9 2. Forms 10 a. Provide formwork design and materials in accordance with TxDOT Standard 11 Specification Item 420. 12 b. Provide bond-breaking layer on timber and metal forms. 13 D. Drains 14 1. Install and construct weep holes and roadway drains as specified in the Drawings. 15 E. Placing Reinforcement and Post-Tensioning 16 1. Place reinforcement in accordance with Section 03 00 00. 17 2. Do not weld reinforcing steel supports to other reinforcing steel unless specified in 18 the Drawings. 19 3. Place post-tensioning ducts, anchorages, and other hardware in accordance with the 20 approved prestressing details and TxDOT Standard Specification Item 426. Keep 21 ducts free of obstructions until all post-tensioning operations are complete. 22 F. Joints 23 1. Expansion Joints 24 a. Construct joints and devices in accordance with the Drawings. 25 b. Use light wire or nails to anchor any preformed fiber joint material to the 26 concrete on 1 side of the joint. 27 c. Ensure finished joints are in accordance with the Drawings with the concrete 28 sections completely separated by the specified opening or joint material. 29 d. Remove all concrete within the joint opening immediately after form removal 30 and again where necessary after surface finishing. 31 2. Construction Joints 32 a. Make construction joints of the type and at the locations specified in the 33 Drawings. 34 b. Additional joints in other members are not permitted without approval. 35 c. Place approved additional joints using details specified in the Drawings. 36 d. Make construction joints square and normal to the forms unless otherwise 37 specified in the Drawings or by the City. 38 e. Use bulkheads in the forms for all vertical joints. 39 f. Thoroughly roughen the top surface of a concrete placement terminating at a 40 horizontal construction joint as soon as possible after initial set is attained. 41 g. Thoroughly clean the hardened concrete surface of all loose material, laitance, 42 dirt, and foreign matter, and saturate with water. 43 h. Remove all free water and moisten the surface before concrete or bonding grout 44 is placed against it. 45 03 30 00 CAST-IN-PLACE CONCRETE Page 11 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 i. Ensure the surface of the existing concrete is in a saturated surface-dry 1 condition immediately before placing subsequent concrete. 2 1) A saturated surface-dry condition is achieved when the surface remains 3 damp when exposed to sunlight for 15 minutes. 4 5 j. Wet the existing concrete by ponding water on the surface for 24 hours before 6 placing subsequent concrete. 7 1) Use high-pressure water blasting if ponding is not possible to achieve a 8 saturated surface-dry condition 15 to 30 minutes before placing the 9 concrete. 10 k. Draw forms tight against the existing concrete. 11 l. Bonding agents are not required unless otherwise specified in the Drawings or 12 by the City. 13 m. Coat the joint surface with bonding mortar, grout, epoxy, or other material if a 14 bonding agent is required. 15 n. Provide Type V epoxy in accordance with DMS-6100 for bonding fresh 16 concrete to hardened concrete. 17 o. Place the bonding epoxy on a clean, dry surface, and place the fresh concrete 18 while the epoxy is still tacky. 19 p. Place bonding mortar or grout on a surface in a saturated surface-dry condition, 20 and place the concrete before the bonding mortar or grout dries. 21 q. Place other bonding agents in accordance with the manufacturer’s 22 recommendations. 23 G. Placing Concrete 24 1. General 25 a. Minimize segregation while placing concrete. 26 b. Produce and place a uniform, dense compact mass of concrete. 27 c. Ensure concrete free-falls no more than 5 feet except in the case of drilled 28 shafts, thin walls such as culverts, or as allowed by other items. 29 d. Fill the forms by depositing concrete as close to final position as possible. Do 30 not deposit large quantities of concrete in one location and move the concrete to 31 fill the forms. 32 e. Remove any hardened concrete splatter ahead of the plastic concrete. 33 f. Deposit concrete in layers no more than 36 inches deep unless otherwise 34 permitted. 35 g. Avoid cold joints in monolithic placement. Sequence successive layers or 36 adjacent portions of concrete so they can be vibrated into a homogeneous mass 37 with the previously placed concrete before it sets. 38 h. Re-Vibration 39 1) When re-vibrating between adjacent or successive placements of concrete, 40 verify approved time lapse between adjacent or successive placements with 41 the City. 42 2) The timeframe between adjacent or successive placements will be subject 43 to approval by the City. 44 3) General accepted timeframes include: 45 a) No more than 1 hour to elapse 46 b) If the concrete contains at least the minimum recommended dosage of 47 Type B or D admixture, the City may approve 1.5 hours to elapse. 48 03 30 00 CAST-IN-PLACE CONCRETE Page 12 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2. In Cold Weather 1 a. Provide and install recording thermometers, maturity meters, or other suitable 2 temperature measuring devices capable of determining the temperature of the 3 concrete to verify all concrete is in accordance with the following temperature 4 limits: 5 1) Maintain the temperature at all surfaces of concrete in bents, piers, culvert 6 walls, retaining walls, parapets, wingwalls, top slabs of non-direct traffic 7 culverts, and other similar formed concrete at or above 40 degrees 8 Fahrenheit for 72 hours from the time of placement. 9 2) Maintain the temperature of all other concrete, including the bottom slabs 10 (footings) of culverts placed on or in the ground above 32 degrees 11 Fahrenheit for 72 hours from the time of placement. 12 b. Use coverings, insulated forms, artificial heating, or other means until all 13 requirements for curing have been satisfied. Do not apply heat directly to 14 concrete surfaces. 15 c. Plan for cold weather and have all necessary heating and covering material 16 ready for use. If any concrete is damaged due to poor planning, remove and 17 replace concrete at no cost to the City. 18 d. In accordance with ambient temperature requirements of this Section and 19 Section 03 00 00. 20 3. In Hot Weather 21 a. Keep the concrete at or below the maximum temperature at the time of 22 placement. 23 b. To control the concrete temperature, use ice, liquid nitrogen, shade, or water on 24 aggregate stockpiles. 25 4. In Water 26 a. Deposit concrete in water only when specified in the Drawings or with 27 approval from the City. 28 b. Make forms or cofferdams tight enough to prevent any water current passing 29 through. 30 c. Do not pump water during or within 36 hours of concrete placement. 31 d. Place the concrete with a tremie, pump, or other approved method. 32 1) Do not allow the concrete to fall freely through the water and do not disturb 33 the concrete after it has been placed. 34 e. Keep the concrete surface level during placement. 35 f. Submerge the lower end of the tremie or pump hose in the concrete at all times. 36 g. Use continuous placing operations until the work is complete. 37 5. Mass Placements 38 a. Develop and obtain approval for a heat control plan for monolithic placements 39 specified in the Drawings as mass concrete. 40 b. Place in accordance with the following temperature limits during the heat 41 dissipation period for mass monolithic placements: 42 1) The temperature differential between the central core of the placement and 43 the exposed concrete surface does not exceed 35 degrees Fahrenheit 44 2) The temperature at the central core of the placement does not exceed 160 45 degrees Fahrenheit 46 3) Revise the heat control plan as necessary to maintain the temperature 47 limitations. 48 03 30 00 CAST-IN-PLACE CONCRETE Page 13 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 4) Repair any resulting cracking if the temperature differential between the 1 central core of the placement and the nearest concrete surface exceeds 35 2 degrees Fahrenheit, at no cost to the City. 3 c. Furnish and install enough temperature recording devices, maturity meters, or 4 other approved equivalent devices to monitor the heat dissipation. 5 d. Maintain temperature control methods for 4 days unless otherwise directed or 6 approved based on the heat control plan. 7 e. Install devices using the following parameters: 8 1) Measuring Surface Temperature 9 a) Install no more than 3 inches from the surface. 10 2) Measuring Core Temperature 11 a) Install mid-way between the point of maximum predicted heat to the 12 nearest surface. 13 f. Do not use maturity meters to predict strength. 14 g. If the core temperature exceeds 160 degrees Fahrenheit, the mass concrete will 15 be subject to removal and replacement at no cost to the City. 16 1) Do not move forward with subsequent construction until the City has 17 evaluated the mass concrete. 18 6. In Foundation and Substructure 19 a. Perform any pumping or bailing from a suitable sump located outside the 20 forms. 21 b. Construct or adjust all temporary wales or braces inside cofferdams as the work 22 proceeds to prevent unauthorized construction joints. 23 c. Footings 24 1) Do not place concrete in footings until the depth and formwork has been 25 inspected. 26 2) Place concrete footings upon seal concrete after the cofferdams are free 27 from water and the seal concrete is cleaned. 28 d. Columns 29 1) Place concrete in columns monolithically between construction joints 30 unless otherwise specified in the Drawings or by the City. 31 2) Place the column concrete to the lower level of the cap or tie beam and 32 delay placing the cap or tie beam on top of the column until the column 33 concrete has reached a compressive strength of 3,000 psi. 34 7. In Box Culverts 35 a. For locations where the culvert is more than 4 feet in clear height, delay placing 36 the top slab until the wall concrete has reached a compressive strength of 3,000 37 psi. 38 b. Finishing 39 1) Footing slab 40 a) Provide a smooth, uniform finish. 41 2) Direct traffic top slabs 42 a) Finish in accordance with TxDOT Standard Specification Item 422. 43 3) Other top slabs 44 a) Float finish 45 H. Extending Existing Substructures 46 1. Removal 47 03 30 00 CAST-IN-PLACE CONCRETE Page 14 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 a. Remove portions of the existing structure to the lines and dimensions specified 1 in the Drawings or as directed by the City. 2 b. Repair any minor damage to the existing structure in accordance with Section 3 32 01 29. 4 c. Do not use explosives to remove portions of the existing structure. 5 d. Do not use a demolition ball, other swinging weight, or impact equipment 6 unless directed to or approved by the City. 7 e. Use equipment that will not damage the remaining concrete. 8 2. Splicing Reinforcing Steel 9 a. Splice new reinforcing bars to exposed bars in the existing structure using lap 10 splices in accordance with Section 03 00 00. 11 b. Welded splices are permitted, perform welds in accordance with TxDOT 12 Standard Specification Item 448. 13 3. Concrete Preparation 14 a. Roughen and clean concrete surfaces in contact with new construction before 15 placing forms. 16 b. Prepare joint surfaces in accordance with this Section. 17 I. Consolidation 18 1. Consolidate concrete and flush mortar to the form surfaces with immersion type 19 vibrators. Do not use vibrators that operate by attachment to forms or 20 reinforcement, unless otherwise approved. 21 2. Vibrate the concrete immediately after deposit. Space points of vibration to ensure 22 complete consolidation and thorough working of the concrete around the 23 reinforcement, embedded fixtures, and into the corners and angles of the forms. 24 3. Insert the vibrators vertically where possible. 25 4. Vibrate the entire depth of each lift and penetrate the previous lift 2 to 3 inches 26 where applicable. 27 5. Do not use the vibrator to move the concrete to other locations in the forms. 28 6. Do not drag the vibrator through the concrete. 29 7. Thoroughly consolidate concrete along construction joints by operating the vibrator 30 along and close to the joint surface. Do not vibrate against the joint surface. 31 8. Continue vibration until the concrete surrounding reinforcements and fixtures is 32 completely consolidated. 33 9. Hand-space or rod the concrete if necessary to ensure flushing of mortar to the 34 surface of all forms. 35 J. Dowels and Anchor Bolts 36 1. Install dowels and anchor bolts by casting them in-place or by grouting with grout, 37 epoxy, or epoxy mortar, unless otherwise specified. 38 2. Form or drill holes for grouting. 39 3. Follow the manufacturer’s recommended installation procedures for pre-packaged 40 grout or epoxy anchor systems. 41 4. Test anchors if specified in the Drawings or required within applicable Sections. 42 5. Drill holes for anchor bolts to accommodate the bolt embedment specified in the 43 Drawings. 44 03 30 00 CAST-IN-PLACE CONCRETE Page 15 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 6. Make holes for dowels at least 12 inches deep unless otherwise specified in the 1 Drawings. 2 7. Hole Diameter Size 3 a. A minimum of twice the dowel or bolt diameter 4 b. When using cementitious grout or epoxy mortar, do not exceed the dowel or 5 bolt diameter plus 1.5 inches. 6 c. When using neat epoxy, make the hole diameter 1/16 to 1/4 inch greater than 7 the dowel or bolt diameter, unless otherwise specified by the epoxy 8 manufacturer. 9 8. Thoroughly clean holes of all loose material, oil, grease, or other bond-breaking 10 substance, and blow them clean with filtered compressed air. 11 9. Use a wire brush followed by oil-free compressed air to remove all loose material 12 from the holes, repeating as necessary until no more material is removed. 13 10. Ensure holes are in a surface-dry condition when epoxy type materials are used and 14 a surface-moist condition when cementitious grout is used. 15 11. Develop and demonstrate for approval a procedure for cleaning and preparing the 16 holes for installation of the dowels and anchor bolts. 17 12. Completely fill the void between the hole and dowel or bolt with grouting material. 18 13. Follow all product recommendations for pre-packaged systems. 19 K. Finishing of Surfaces 20 1. Standard Surfaces 21 a. Provide a consistent and uniform surface for all visible concrete surfaces. 22 b. Apply an ordinary smooth surface finish to all concrete surfaces unless a flat, 23 textured, broom, or trowel surface is specified in this Section, the Drawings, or 24 as directed by the City. 25 c. Repair defects and surface irregularities in accordance with this Section. 26 Remove and replace any visible surfaces with defects or irregularities that are 27 unable to be repaired. 28 d. Apply an ordinary smooth surface finish as the final finish to the following 29 exposed concrete surfaces, unless otherwise specified in the Drawings or by the 30 City: 31 1) Inside and top of inlets 32 2) Inside and top of manholes 33 3) Inside of sewer and appurtenances 34 4) Inside of culvert barrels 35 e. Form marks and chamfer edges do not need to be smoothed for the inside of 36 culvert barrels. 37 2. Horizontal Surfaces 38 a. Do not use mortar topping for surfaces, unless otherwise directed by the City. 39 b. Strike off to grade and finish all unformed upper surfaces and float the surface. 40 c. Slope the following to drain water from the surface 41 1) Tops of caps and piers between bearing areas from the center slightly 42 toward the edge 43 2) The tops of abutment and transition bent caps from the backwall to the edge 44 d. Construct bearing areas for steel units in accordance with TxDOT Standard 45 Specification Item 441. 46 03 30 00 CAST-IN-PLACE CONCRETE Page 16 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 e. Finish 1 1) Standard 2 a) Smooth trowel finish 3 2) Bearing area under the expansion ends of concrete slabs and slab and girder 4 spans 5 a) Steel-trowel finish to the grades specified 6 3) Bearing areas under elastomeric bearing pads or nonreinforced bearing seat 7 buildups 8 a) Textured, wood float finish 9 4) Do not allow the bearing area to vary from a level plane by more than 1/16 10 inch in all directions. 11 f. Cast bearing seat buildups or pedestals for concrete units integrally with the cap 12 or a construction joint. 13 g. Provide a latex-based mortar, an epoxy mortar, or an approved proprietary 14 bearing mortar for bearing seat buildups cast with a construction joint. 15 h. Construct pedestals of Class C concrete, reinforced as specified in the Drawings 16 or, for pedestals less than 12 inches in height, as indicated in Figure 1 and 2 17 03 30 00 CAST-IN-PLACE CONCRETE Page 17 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1 Figure 1 2 Section Through Bearing Seat Buildups 3 Figure 2 4 Section Through Bearing Seat Buildups 5 6 L. Curing 7 1. General 8 a. Perform curing in accordance with approved methods. 9 b. Curing Day 10 1) Standard 11 a) The temperature, taken in the shade, is above 50 degrees Fahrenheit for 12 at least 19 hours. 13 2) Cold Day 14 a) The temperature of all surfaces of the concrete is maintained above 40 15 degrees Fahrenheit for the entire 24 hours. 16 c. The curing period begins when all concrete has attained its initial set in 17 accordance with Tex-440-A, unless otherwise indicated in the Drawings. 18 d. Curing Locations 19 1) For vertical surfaces, use form or membrane curing unless otherwise 20 specified in the Drawings or by the City. 21 2) For horizontal surfaces of HPC or mass concrete, use only water curing. 22 3) For horizontal or unformed surfaces of all other concrete, use water or 23 membrane curing. 24 4) For the top surface of any concrete structure that additional concrete will be 25 placed and bonded onto at a later date, use water curing. Examples include, 26 but are not limited to stub walls, caps with backwalls, and risers. 27 5) Cure all other concrete as specified in other applicable Sections. 28 e. Curing Timeframes: 29 1) Standard 30 a) Cure all concrete for 4 consecutive days 31 03 30 00 CAST-IN-PLACE CONCRETE Page 18 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2) Vertical Surfaces 1 a) Form cure for 48 hours after placement followed by 4 days of form 2 curing. 3 b) Form cure for 12 hours after placement followed by membrane cure in 4 accordance with manufacturer recommendations, as specified by the 5 Drawings, or as directed by the City. 6 c) HPC concrete 7 (1) Form cure for 48 hours after placement followed by membrane 8 cure in accordance with manufacturer recommendations, as 9 specified by the Drawings, or as directed by the City . 10 3) Mass Concrete 11 a) If forms are removed prior to 4 days of curing, form cure as required by 12 the heat control plan and then membrane cure in accordance with 13 manufacturer recommendations, as specified by the Drawings, or as 14 directed by the City. 15 f. If using membrane curing, apply within 2 hours of form removal. 16 2. Form Curing 17 a. When forms are left in contact with the concrete, other curing methods are not 18 required except for exposed surfaces and for cold weather protection. 19 b. Use other approved curing methods if forms are removed prior to the 4 day 20 curing period. 21 3. Water Curing 22 a. Keep all exposed surfaces of the concrete continuously wet for the required 23 curing timeframe. 24 b. Use water in accordance with Section 03 00 00. Do not use water that stains or 25 leaves a residue. 26 4. Blankets 27 a. Keep the concrete continuously wet by maintaining wet cotton or burlap mats 28 in direct contact with the concrete for the required curing time. 29 b. Cover the cotton or burlap mats with a layer of polyethylene sheeting. 30 c. Weigh the mats adequately to provide continuous contact with all concrete. 31 d. Cover surfaces that cannot be cured by direct contact with mats by forming an 32 enclosure well anchored to the forms or ground so outside air cannot enter the 33 enclosure. 34 1) Provide sufficient moisture inside the enclosure to keep all surfaces of the 35 concrete wet. 36 5. Membrane Curing 37 a. Do not vary the type of curing compound throughout the project. 38 b. Apply membrane curing at a rate of approximately 180 square feet per gallon 39 unless otherwise specified in accordance with manufacturer recommendations, 40 as specified by the Drawings, or as directed by the City. 41 c. Do not spray curing compound on projecting reinforcing steel or concrete that 42 will later form a construction joint. 43 d. Do not apply membrane curing to dry surfaces. Follow the manufacturer’s 44 recommendations for what level of surface moisture to apply curing compound. 45 e. Leave the film unbroken for the minimum curing period specified by the 46 manufacturer. 47 f. Correct damaged membrane immediately by reapplication of membrane. 48 03 30 00 CAST-IN-PLACE CONCRETE Page 19 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 M. Removal of Falsework and Forms 1 1. Follow curing requirements when removing forms. 2 2. For mass placements, keep forms in place for 4 days following concrete placement 3 unless otherwise specified by the heat control plan, in the Drawings, or by the City. 4 3. Do not remove weight-supporting forms and falsework spanning more than 1 foot 5 for all bridge components and culvert slabs until the concrete has attained a 6 compressive strength of 3,000 psi. 7 4. Remove inside forms (walls and top slabs) for box culverts and sewers after 8 concrete has attained 75 percent of the design compressive strength. 9 5. If a form is not providing support, the form may be removed provided the removal 10 does not disturb other forms that are providing support. 11 6. Metal Appliances: 12 a. Remove all metal appliances used inside forms to a depth of at least one-half 13 inch from the concrete surface. 14 b. Remove appliances without chipping or spalling the concrete. 15 c. If the concrete is damaged, the City will decide if the concrete can be repaired, 16 or if it will need to be replaced. 17 d. Replace any concrete that has been damaged due to the removal of metal 18 appliances at no cost to the City. 19 7. Do not leave any forms or falsework in place unless otherwise specified in the 20 Drawings or as directed by the City. 21 3.5 REPAIR 22 A. Repair Surface Defects and Irregularities 23 1. Chip away all loose or broken material to sound concrete where porous, spalled, or 24 honeycombed areas are visible after form removal. 25 2. Repair spalls in accordance with Section 32 01 29. 26 3. Clean and fill holes or spalls caused by the removal of form and falsework with 27 latex grout, cement grout, or epoxy grout. Fill only the holes. Do not blend the 28 patch with the surrounding concrete. 29 4. Remove all fins, rust stains, runs, drips, or mortar from surfaces that will be 30 exposed. Smooth all form marks and chamfer edges by grinding or dry-rubbing. 31 5. Ensure all repairs are dense, well-bonded, and properly cured. Finish exposed large 32 repairs to blend with the surrounding concrete where a higher class of finish is not 33 specified. 34 3.6 RE-INSTALLATION [NOT USED] 35 3.7 SITE QUALITY CONTROL 36 A. Concrete Mix Design and Verification 37 1. Perform testing in accordance with Section 03 00 00. 38 B. Concrete Production and Placement Acceptance 39 1. Perform production and placement testing in accordance with Section 03 00 00. 40 C. Non-Conforming Work 41 03 30 00 CAST-IN-PLACE CONCRETE Page 20 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1. General 1 a. The City may at any time reject a material if it fails to meet the requirements 2 specified in this Section. 3 b. The City may require the Contractor at any time to remove and replace installed 4 concrete if any material is found to be non-conforming, at no additional cost to 5 the City. 6 c. Any rejection of materials or source locations will be at no cost to the City. 7 2. Aggregates 8 a. If the aggregates fail to meet the requirements specified in Section 32 05 16, the 9 City may reject the aggregates. 10 3. Concrete Mix Design and Production Materials 11 a. If the mix design fails to meet the requirements specified in this Section and 12 Section 03 00 00, the City may reject the mix design. 13 b. Any concrete installed using a non-conforming mix design will be subject to 14 removal and replacement at no cost to the City. 15 c. The City may perform verification testing on all materials to verify the 16 conformance of the mixture. 17 3.8 SYSTEM STARTUP [NOT USED] 18 3.9 ADJUSTING [NOT USED] 19 3.10 CLEANING [NOT USED] 20 3.11 CLOSEOUT ACTIVITIES [NOT USED] 21 3.12 PROTECTION [NOT USED] 22 3.13 MAINTENANCE [NOT USED] 23 3.14 ATTACHMENTS [NOT USED] 24 END OF SECTION 25 26 Revision Log DATE NAME SUMMARY OF CHANGE 27 03 34 13 CONTROLLED LOW STRENGTH MATERIAL (CLSM) Page 1 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 03 34 13 1 CONTROLLED LOW STRENGTH MATERIAL (CLSM) 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Controlled low strength material (CLSM) for use as flowable backfill. 6 B. Deviations from this City of Denton Standard Specification: 7 1. None. 8 C. Related Specification Sections include but are not limited to: 9 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 10 Contract. 11 2. Division 1 - General Requirements. 12 3. Section 03 00 00 – Concrete and Concrete Reinforcing. 13 1.2 PRICE AND PAYMENT PROCEDURES 14 A. Measurement and Payment 15 1. Measurement 16 a. This item is considered subsidiary to utility pipe installed. 17 2. Payment 18 a. The work performed and materials furnished in accordance with this item are 19 subsidiary to the unit price bid per linear foot of utility pipe installed. 20 1.3 REFERENCES 21 A. Acronyms 22 1. CLSM – Controlled Low Strength Material. 23 B. Reference Standards 24 1. Reference standards cited in this Section refer to the current reference standard 25 published at the time of the latest revision date logged at the end of this Section 26 unless a date is specifically cited. 27 2. American Society of Testing and Materials (ASTM): 28 a. C31 - Standard Practice for Making and Curing Concrete Test Specimens in the 29 Field. 30 b. C33 - Standard Specification for Concrete Aggregates. 31 c. C39 - Standard Test Method for Compressive Strength of Cylindrical Concrete 32 Specimens. 33 d. C143 - Standard Test Method for Slump of Hydraulic Cement Concrete. 34 e. C231 - Standard Test Method for Air Content of Freshly Mixed Concrete by 35 the Pressure Method. 36 f. C260 - Standard Specification for Air-Entraining Admixtures for Concrete. 37 03 34 13 CONTROLLED LOW STRENGTH MATERIAL (CLSM) Page 2 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 g. C618 - Standard Specification for Coal Fly Ash and Raw or Calcined Natural 1 Pozzolan for Use in Concrete. 2 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 3 1.5 SUBMITTALS 4 A. Submittals shall be in accordance with Section 01 33 00. 5 B. All submittals shall be approved by the City prior to delivery. 6 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 7 A. Sieve analysis 8 1. Analyses of fine and coarse aggregates proposed to be used. 9 a. Resubmit at any time there is a significant change in grading of materials. 10 2. Mix 11 a. Full details, including mix design calculations for proposed mix. 12 B. Trial batch test data 13 1. Data for each test cylinder. 14 2. Data identifying mix and slump for each test cylinder. 15 1.7 CLOSEOUT SUBMITTALS [NOT USED] 16 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 17 1.9 QUALITY ASSURANCE [NOT USED] 18 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 19 1.11 SITE CONDITIONS [NOT USED] 20 1.12 WARRANTY [NOT USED] 21 PART 2 - PRODUCTS 22 2.1 CITY-FURNISHED PRODUCTS [NOT USED] 23 2.2 MATERIALS 24 A. Materials 25 1. Portland Cement: 26 a. Type II low alkali Portland cement in accordance with Section 03 00 00. 27 2. Fly Ash in accordance with ASTM C618. 28 3. Water in accordance with Section 03 00 00. 29 4. Admixtures: 30 a. Air entrainer in accordance with ASTM C260. 31 5. Fine Aggregate: 32 a. Concrete sand (not required to be in accordance with ASTM C33). 33 b. No more than 12 percent of fine aggregate shall pass a No. 200 sieve. 34 c. No plastic fines shall be present. 35 03 34 13 CONTROLLED LOW STRENGTH MATERIAL (CLSM) Page 3 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 6. Coarse Aggregate: 1 a. Pea gravel no larger than 3/8-inch. 2 B. Mixes 3 1. Performance requirements 4 a. Total calculated air content 5 1) Not less than 8.0 percent or greater than 12.0 percent. 6 b. Minimum unconfined compressive strength 7 1) Not less than 50 psi measured at 28 days. 8 c. Maximum unconfined compressive strength 9 1) Not greater than 150 psi measured at 28 days. 10 2) Limit the long-term strength (90 days) to 200 psi such that material could 11 be re-excavated with conventional excavation equipment in the future if 12 necessary. 13 d. Slump 14 1) Greater than 9 inches and sufficient to allow the material to flow freely 15 during placement. 16 e. Wet density 17 1) No greater than 132 pounds per cubic foot. 18 f. Color 19 1) No coloration required unless noted. 20 2) Submit dye or other coloration means for approval. 21 2. Suggested mix design: 22 Material Weight Specific Gravity Absolute Volume Cubic Foot Cement 30 pounds 3.15 0.15 Fly Ash 300 pounds 2.30 2.09 Water 283 pounds 1.00 4.54 Coarse Aggregate 1,465 pounds 2.68 8.76 Fine Aggregate 1,465 pounds 2.68 8.76 Admixture 4-6 ounces - 2.70 TOTAL 3,543 pounds - 27.00 23 2.3 ACCESSORIES [NOT USED] 24 2.4 SOURCE QUALITY CONTROL 25 A. Trial Batch 26 1. After mix design has been accepted by City, have trial batch of the accepted mix 27 design prepared by testing laboratory acceptable to City. 28 2. Prepare trial batches using specified cementitious materials and aggregates 29 proposed to be used for the Work. 30 3. Prepare trial batch with sufficient quantity to determine slump, workability, 31 consistency, and to provide sufficient test cylinders. 32 03 34 13 CONTROLLED LOW STRENGTH MATERIAL (CLSM) Page 4 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1 B. Test Cylinders 2 1. Prepare test cylinders in accordance with ASTM C31 with the following 3 exceptions: 4 a. Fill the concrete test cylinders to overflowing and tap sides lightly to settle the 5 mix. 6 b. Do not rod the concrete mix. 7 c. Strike off the excess material. 8 2. Place test cylinders in a moist curing room. Exercise caution in moving and 9 transporting the cylinders since they are fragile and will withstand only minimal 10 bumping, banging, or jolting without damage. 11 3. Do not remove the test cylinder from mold until the cylinder is to be capped and 12 tested. 13 4. The test cylinders may be capped with standard sulfur compound or neoprene pads: 14 a. Perform the capping carefully to prevent premature fractures. 15 b. Use neoprene pads a minimum of 1/2 inch thick, and 1/2 inch larger in diameter 16 than the test cylinders. 17 c. Do not perform initial compression test until the cylinders reach a minimum 18 age of 3 days. 19 C. Compression test 8 test cylinders: Test 4 test cylinders at 3 days and 4 at 28 days in 20 accordance with ASTM C39 with the following exceptions: 21 1. The compression strength of the 4 test cylinders tested at 28 days shall be equal to 22 or greater than the minimum required compression strength, but not exceed 23 maximum compression strength. 24 D. If the trial batch tests do not meet the requirements for strength or density, revise and 25 resubmit the mix design, and prepare additional trial batch and tests. Repeat until an 26 acceptable trial batch is produced in accordance with the requirements of this Section. 27 1. All the trial batches and acceptability of materials shall be paid by Contractor. 28 2. After acceptance, do not change the mix design without submitting a new mix 29 design, trial batches, and test information. 30 E. Determine slump in accordance with ASTM C143 with the following exceptions: 31 1. Do not rod the concrete material. 32 2. Place material in slump cone in 1 semi-continuous filling operation, slightly 33 overfill, tap lightly, strike off, and then measure and record slump. 34 PART 3 - EXECUTION 35 3.1 INSTALLERS [NOT USED] 36 3.2 EXAMINATION [NOT USED] 37 3.3 PREPARATION [NOT USED] 38 39 03 34 13 CONTROLLED LOW STRENGTH MATERIAL (CLSM) Page 5 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3.4 INSTALLATION 1 A. Placement 2 1. Place CLSM by any method which preserves the quality of the material in terms of 3 compressive strength and density: 4 a. Limit lift heights of CLSM placed against structures and other facilities that 5 could be damaged due to the pressure from the CLSM to 4 feet or the lift height 6 indicated on the Drawings, whichever is less. 7 1) Do not place another lift of CLSM until the last lift of CLSM has set and 8 gained sufficient strength to prevent lateral load due to the weight of the 9 next lift of CLSM. 10 b. The basic requirement for placement equipment and placement methods is the 11 maintenance of its fluid properties. 12 c. Transport and place material so it flows easily around, beneath, or through 13 walls, pipes, conduits, or other structures. 14 d. Maintain slump developed for trial batch during construction at all times within 15 1-inch +/-. 16 e. Use a slump, consistency, workability, flow characteristics, and pumpability 17 (where required) such that when placed, the material is self-compacting, self 18 densifying, and has sufficient plasticity so compaction or mechanical vibration 19 is not required. 20 f. When using as embedment for pipe take appropriate measures to ensure line 21 and grade of pipe. 22 3.5 REPAIR [NOT USED] 23 3.6 RE-INSTALLATION [NOT USED] 24 3.7 SITE QUALITY CONTROL 25 A. Quality Control Testing 26 1. Perform testing to determine whether the CLSM, as being produced during the 27 process of construction, is in accordance with the requirements of this Section. 28 a. Make and deliver test cylinders to testing laboratory at the Contractor’s 29 expense. 30 2. Test cylinders 31 a. Prepare test cylinders in accordance with ASTM C31 with the following 32 exceptions: 33 1) Fill the concrete test cylinders to overflowing and tap sides lightly to settle 34 the mix. 35 2) Do not rod the concrete mix. 36 3) Strike off the excess material. 37 b. Place the cylinders in a safe location away from the construction activities. 38 Keep the cylinders moist by covering with wet burlap, or equivalent. Do not 39 sprinkle water directly on the cylinders. 40 c. After 2 days, place the cylinders in a protective container, such as a Styrofoam 41 or similar lining that will limit the jarring and bumping of the cylinders, for 42 transport to the laboratory for testing. 43 03 34 13 CONTROLLED LOW STRENGTH MATERIAL (CLSM) Page 6 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 d. Place test cylinders in a moist curing room. Exercise caution in moving and 1 transporting the cylinders since they are fragile and will withstand only 2 minimal bumping, banging, or jolting without damage. 3 e. Do not remove the test cylinder from mold until the cylinder is to be capped 4 and tested. 5 f. The test cylinders may be capped with standard sulfur compound or neoprene 6 pads: 7 1) Perform the capping carefully to prevent premature fractures. 8 2) Use neoprene pads a minimum of 1/2 inch thick and 1/2 inch larger in 9 diameter than the test cylinders. 10 3) Do not perform initial compression test until the cylinders reach a 11 minimum age of 3 days. 12 3. The number of cylinder specimens taken each day shall be determined by the City. 13 a. Test 1 cylinder at 3 days and 2 at 28 days in accordance with ASTM C39 14 except as modified herein. 15 b. The compression strength of the cylinders tested at 28 days shall be equal to or 16 greater than the minimum required compression strength, but not exceed 17 maximum compression strength. 18 4. Test the air content of the CLSM. Test will be made immediately after discharge 19 from the mixer in accordance with ASTM C231. 20 5. Test the slump of CLSM using a slump cone in accordance with ASTM C143 with 21 the following exceptions: 22 a. Do not rod the concrete material. 23 b. Place material in slump cone in 1 semi-continuous filling operation, slightly 24 overfill, tap lightly, strike off, and then measure and record slump. 25 6. If compressive strength of test cylinders does not meet requirements, make 26 corrections to the mix design to be in accordance with the requirements of this 27 Section. 28 3.8 SYSTEM STARTUP [NOT USED] 29 3.9 ADJUSTING [NOT USED] 30 3.10 CLEANING [NOT USED] 31 3.11 CLOSEOUT ACTIVITIES [NOT USED] 32 3.12 PROTECTION [NOT USED] 33 3.13 MAINTENANCE [NOT USED] 34 3.14 ATTACHMENTS [NOT USED] 35 36 37 38 03 34 13 CONTROLLED LOW STRENGTH MATERIAL (CLSM) Page 7 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 END OF SECTION 1 2 Revision Log DATE NAME SUMMARY OF CHANGE 3 03 80 00 MODIFICATIONS TO EXISTING CONCRETE STRUCTURES Page 1 of 6 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 29,2021 Effective July 1, 2024 SECTION 03 80 00 1 MODIFICATIONS TO EXISTING CONCRETE STRUCTURES 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Modifications to existing concrete structures, including manholes, junction boxes, 6 vaults, retaining walls, wingwalls, headwalls, and culverts. 7 B. Deviations from this City of Denton Standard Specification: 8 1. None. 9 C. Related Specification Sections include but are not limited to: 10 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 11 Contract. 12 2. Division 1 - General Requirements. 13 3. Section 03 00 00 – Concrete and Concrete Reinforcing. 14 4. Section 03 30 00 – Cast-in-Place Concrete. 15 5. Section 03 34 13 - Controlled Low Strength Material (CLSM). 16 6. Section 32 32 00 – Retaining Walls. 17 7. Section 33 05 05 - Utility Trench Excavation, Embedment, and Backfill. 18 1.2 PRICE AND PAYMENT PROCEDURES 19 A. Measurement and Payment 20 1. Measurement 21 a. Modifications to Existing Concrete Structures materials, equipment, tools, 22 testing, and incidentals are subsidiary to the structure or item being installed. 23 2. Payment 24 a. The work performed and materials furnished in accordance with this item are 25 subsidiary to the unit prices bid for various items which require the use of 26 Modifications to Existing Concrete Structures. 27 1.3 REFERENCES 28 A. Reference Standards 29 1. Reference standards cited in this Section refer to the current reference standard 30 published at the time of the latest revision date logged at the end of this Section 31 unless a date is specifically cited. 32 2. Texas Department of Transportation (TxDOT) Departmental Material 33 Specifications (DMS): 34 a. DMS-6100, Epoxies and Adhesives. 35 3. TxDOT Concrete Repair Manual. 36 03 80 00 MODIFICATIONS TO EXISTING CONCRETE STRUCTURES Page 2 of 6 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 29,2021 Effective July 1, 2024 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 1 1.5 SUBMITTALS 2 A. Submittals shall be in accordance with Section 01 33 00. 3 B. All submittals shall be approved by the City prior to delivery. 4 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 5 A. Product Data 6 1. Provide electronic product data from each manufacturer supplying curing 7 compounds, evaporation retardant, joint fillers, or chemical additives to be used on 8 the project. 9 2. Product data sheets for all products other than epoxy including: 10 a. Manufacturer name 11 b. Date 12 c. Material description 13 d. Point of delivery 14 e. Data and test results as required in this Section 15 f. Material Safety Data Sheets, if applicable, required for Epoxy and Curing 16 Compounds 17 g. Manufacturer Recommended Storing Data, if applicable 18 h. Application Recommendations, if applicable 19 i. Manufacturer’s Recommended Storage and Handling instructions 20 3. Epoxy Product Data Sheet Additional Requirements: 21 a. Resin or hardener components 22 b. Brand name 23 c. Name of manufacturer 24 d. Lot or batch number 25 e. Temperature range for storage 26 f. Date of manufacture 27 g. Expiration date 28 h. Quantity contained 29 B. Information Submittals 30 1. Equipment Information 31 a. Submittal for all major equipment including: 32 1) Equipment name and description 33 2) Size 34 3) Intended use 35 1.7 CLOSEOUT SUBMITTALS [NOT USED] 36 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 37 1.9 QUALITY ASSURANCE [NOT USED] 38 1.10 DELIVERY, STORAGE, AND HANDLING 39 A. Storage and Handling Requirements 40 03 80 00 MODIFICATIONS TO EXISTING CONCRETE STRUCTURES Page 3 of 6 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 29,2021 Effective July 1, 2024 1. Secure and maintain a location to store the material in accordance with Section 01 1 66 00. 2 1.11 FIELD CONDITIONS [NOT USED] 3 1.12 WARRANTY [NOT USED] 4 PART 2 - PRODUCTS 5 2.1 CITY-SUPPLIED PRODUCTS [NOT USED] 6 2.2 MATERIALS 7 A. Cast-in-Place Concrete 8 1. In accordance with Sections 03 00 00 and 03 30 00. 9 B. Controlled Low Strength Material 10 1. In accordance with Section 03 34 13. 11 C. Steel Reinforcement 12 1. In accordance with Section 03 00 00. 13 D. Epoxy Bonding Agent 14 1. Provide a two component, solvent-free, asbestos-free, moisture-insensitive epoxy 15 resin material used to bond plastic concrete to hardened concrete in accordance with 16 DMS-6100, Type V. 17 E. Backfill material 18 1. Trenches 19 a. In accordance with Section 33 05 05. 20 2. Retaining walls 21 a. In accordance with Section 32 32 00. 22 F. Repair Mortars 23 1. Provide an asbestos free, moisture insensitive, polymer-modified, Portland cement-24 based cementitious trowel grade mortar for repairs on horizontal or vertical 25 surfaces. 26 G. Pipe Penetration Sealants 27 1. Provide one component polyurethane, bentonite-free, extrudable swelling waterstop 28 that is chemically resistant, not soluble in water, and capable of withstanding 29 wet/dry cycling. 30 2.3 ACCESSORIES [NOT USED] 31 2.4 SOURCE QUALITY CONTROL [NOT USED] 32 PART 3 - EXECUTION 33 3.1 INSTALLERS [NOT USED] 34 35 03 80 00 MODIFICATIONS TO EXISTING CONCRETE STRUCTURES Page 4 of 6 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 29,2021 Effective July 1, 2024 3.2 EXAMINATION 1 A. Verification of Conditions 2 1. Examine existing structure to be modified for damage or defects that may affect 3 modification. 4 a. Report issue to City for review before beginning modification. 5 3.3 PREPARATION 6 A. Connection Surface Preparation 7 1. Remove all deteriorated materials, dirt, oil, grease, and all other bond inhibiting 8 materials from the surface by dry mechanical means such as sanding or grinding. 9 a. Irregular voids or surface stones do not need to be removed if they are sound, 10 free of laitance, and firmly embedded into parent concrete, subject to the City's 11 final inspection. 12 B. Reinforcing Steel Preparation 13 1. Clean reinforcing steel shown to be incorporated in new concrete of existing 14 demolished concrete by wire brush or other similar means to remove all loose 15 material and products of corrosion before proceeding with the repair. 16 2. If reinforcing steel is exposed, clean by wire brush or other similar means to 17 remove all contaminants. 18 3. If half of the diameter or more of the reinforcing steel is exposed, chip out a 19 minimum of 1 inch behind the steel. 20 4. Cut, bend, or lap to new reinforcing as specified in the Drawings and provide with 21 1-inch minimum cover all around. 22 3.4 INSTALLATION 23 A. General 24 1. When drilling holes for dowels or bolts at new or existing concrete, stop drilling if 25 rebar is encountered and relocate the hole to avoid rebar as approved by the City 26 and Engineer. 27 2. Do not cut rebar without prior approval by the City and Engineer. 28 B. Concrete Removal 29 1. Remove concrete designated to be removed to specific limits as shown on the 30 Drawings by chipping, jack-hammering, or saw-cutting as appropriate in areas 31 where concrete is to be taken out. 32 a. Do not jackhammer sanitary sewer manhole penetrations. 33 2. Remove concrete in such a manner that surrounding concrete or existing reinforcing 34 to be left in place and existing in place equipment is not damaged. 35 3. Where existing reinforcing is exposed due to saw cutting/core drilling and no new 36 material is to be placed on the sawcut surface, apply a coating or surface treatment 37 of epoxy to the entire cut surface to a thickness of 1/4 inch. 38 4. In all cases where the joint between new concrete or grout and existing concrete 39 will be exposed in the finished work, except as otherwise shown or specified, 40 provide a 1-inch deep saw cut on each exposed surface of the existing concrete at 41 the edge of concrete removal. 42 03 80 00 MODIFICATIONS TO EXISTING CONCRETE STRUCTURES Page 5 of 6 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 29,2021 Effective July 1, 2024 C. Modification 1 1. When doweling in new concrete to existing structure, drill a hole 1/4 inch larger 2 than the diameter of the dowel. 3 a. Thoroughly clean the hole of all loose particles and dust and blow clean with 4 filtered compressed air prior to installing epoxy. 5 2. Roughen the existing concrete surface by dry mechanical means such as sanding or 6 grinding prior to placing grout, epoxy, or new concrete. 7 3. Place concrete as specified in the Drawings and in accordance with Section 03 30 8 00. 9 D. Installation Specifics for Coring into an Existing Manhole 10 1. The new pipe connection shall be made using a coring method that utilizes a 11 mechanical saw or drill. The use of pipe hammers or jackhammers is not allowed. 12 2. The manhole wall shall be cored or cut to the elevation indicated on the plans. The cut 13 or cored area shall be of sufficient size to allow the insertion of the new pipe and the 14 pipe-to-manhole connector. If required, the bench area shall also be cut or cored to the 15 width of the new conduit to ensure a continuous grade from the new conduit invert 16 into the manhole invert. Care should be taken to minimize the hole size so that the 17 amount of grouting is kept to a minimum. 18 3. The Contractor shall keep debris from entering the wastewater flow stream in the 19 existing manhole. This shall be done by either using a flow-through plug on the 20 existing manhole pipe connections or by bypass pumping around the manhole. 21 4. A pipe-to-manhole connector shall be attached to the sanitary sewer pipe where the 22 sanitary sewer pipe and the manhole meet. 23 5. The new sanitary sewer shall not protrude more than one inch into the manhole. 24 6. The core hole and bench cut (if required) shall be thoroughly cleaned before the 25 application of grout around the new pipe connection. 26 7. Grout shall be applied to the full thickness of the manhole wall all around the new pipe 27 connection to produce a watertight seal. The pipe-to-manhole connector shall be 28 completely encapsulated within the grouted area. If a bench cut was required, the cut 29 area shall be smoothed with grout. 30 31 3.5 REPAIR 32 A. Repair damaged concrete specified to be left in place in accordance with the TxDOT 33 Concrete Repair Manual. 34 03 80 00 MODIFICATIONS TO EXISTING CONCRETE STRUCTURES Page 6 of 6 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 29,2021 Effective July 1, 2024 3.6 RE-INSTALLATION [NOT USED] 1 3.7 SITE QUALITY CONTROL [NOT USED] 2 3.8 SYSTEM STARTUP [NOT USED] 3 3.9 ADJUSTING [NOT USED] 4 3.10 CLEANING [NOT USED] 5 3.11 CLOSEOUT ACTIVITIES [NOT USED] 6 3.12 PROTECTION [NOT USED] 7 3.13 MAINTENANCE [NOT USED] 8 3.14 ATTACHMENTS [NOT USED] 9 END OF SECTION 10 11 Revision Log DATE NAME SUMMARY OF CHANGE 12 26 05 00 COMMON WORK RESULTS FOR ELECTRICAL Page 1 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 26 05 00 1 COMMON WORK RESULTS FOR ELECTRICAL 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. All labor, materials, and equipment required to install, test, and provide an 6 operational electrical system as specified in the Drawings 7 B. Deviations from this City of Denton Standard Specification: 8 1. None. 9 C. Related Specification Sections include but are not limited to: 10 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 11 Contract. 12 2. Division 1 - General Requirements. 13 3. Division 26 – Electrical. 14 1.2 PRICE AND PAYMENT PROCEDURES 15 A. Measurement and Payment 16 1. Furnish and Install Electrical Service 17 a. Measurement 18 1) Measured per each electrical service installed 19 b. Payment 20 1) The work performed and the materials furnished in accordance with this 21 item and measured as provided under “Measurement” will be paid for at the 22 unit price bid per each for “Furnish/Install Electrical Service” for: 23 a) Various types. 24 b) Various sizes. 25 c. The price bid shall include: 26 1) Furnishing and installing all the components of the electrical service as 27 specified by the Drawings 28 2) All necessary permits and fees and other costs 29 3) Coordinating with the utility company for all work and materials provided 30 by the utility company 31 4) Poles 32 5) Service supports 33 6) Foundations 34 7) Anchor bolts 35 8) Riprap 36 9) Enclosures 37 10) Switches 38 11) Breakers 39 12) Service conduit 40 13) Fittings 41 26 05 00 COMMON WORK RESULTS FOR ELECTRICAL Page 2 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 14) Service conductors 1 15) Brackets 2 16) Bolts 3 17) Hangers 4 18) Hardware 5 19) Equipment, labor, tools, and incidentals 6 20) Excavation 7 21) Disposal of excess material 8 22) Haul off 9 23) Cleanup 10 2. Relocate Electrical Service 11 a. Measurement 12 1) Measured per each electrical service relocated. 13 b. Payment 14 1) The work performed and the materials furnished in accordance with this 15 item and measured as provided under “Measurement” will be paid for at the 16 unit price bid per each for “Relocate Electrical Service” for: 17 a) Various types. 18 b) Various sizes. 19 c. The price bid shall include: 20 1) Disconnecting and isolating the existing electrical service as specified in 21 the Drawings 22 2) Relocating the service supports 23 3) New service support foundation 24 4) Furnishing and compacting of backfill 25 5) Paying all fees, permits, and other costs 26 6) Coordination with the utility company for all work and materials provided 27 by the utility company 28 7) Removal and disconnection of equipment and materials 29 8) Poles 30 9) Service supports 31 10) Foundations 32 11) Anchor bolts 33 12) Riprap 34 13) Enclosures 35 14) Switches 36 15) Breakers 37 16) Service conduit 38 17) Fittings 39 18) Service conductors 40 19) Brackets 41 20) Bolts 42 21) Hangers 43 22) Hardware 44 23) Equipment, labor, tools, and incidentals 45 24) Excavation 46 25) Disposal of excess material 47 26) Haul off 48 27) Cleanup 49 50 26 05 00 COMMON WORK RESULTS FOR ELECTRICAL Page 3 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3. Remove Electrical Service 1 a. Measurement 2 1) Measured per each of the electrical service removed 3 b. Payment 4 1) The work performed and the materials furnished in accordance with this 5 item and measured as provided under “Measurement” will be paid for at the 6 unit price bid of each for “Remove Electrical Service” for: 7 a) Various types. 8 b) Various sizes. 9 c. The price bid shall include: 10 1) Coordination with the utility company to disconnect and isolate the 11 electrical service 12 2) Removing the service supports 13 3) Furnishing and compaction of backfill 14 4) Materials, equipment, labor, tools, and incidentals 15 5) 16 1.3 REFERENCES 17 A. Reference Standards 18 1. Reference standards cited in this Section refer to the current reference standard 19 published at the time of the latest revision date logged at the end of this Section 20 unless a date is specifically cited. 21 1. Texas Department of Transportation (TxDOT), Standard Specifications for 22 Construction and Maintenance of Highways, Streets, and Bridges: 23 a. Item 441, “Steel Structures” 24 b. Item 445, “Galvanizing” 25 c. Item 449, “Anchor Bolts” 26 d. Item 618, “Conduit” 27 e. Item 620, “Electrical Conductors” 28 f. Item 627, “Treated Timber Poles” 29 g. Item 628, “Electrical Services” 30 h. Item 656, “Foundations for Traffic Control Devices” 31 2. Texas Department of Transportation (TxDOT) Departmental Material 32 Specifications (DMS): 33 a. DMS-11080, “Electrical Services” 34 3. TxDOT Material Producer List (MPL) 35 4. National Electrical Manufacturers Association (NEMA) 36 5. National Electrical Code (NEC) 37 6. Underwriters Laboratories, Inc. (UL) 38 7. Canadian Electrical Code (CSA) 39 1.4 ADMINISTRATIVE REQUIREMENTS 40 A. Coordination 41 26 05 00 COMMON WORK RESULTS FOR ELECTRICAL Page 4 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1. Where references are made to the Related Work paragraph in each Specification 1 Section, referring to other Sections and other Divisions of the Specifications, the 2 Contractor shall provide such information or Work as may be required in those 3 references, and include such information or Work as may be specified. 4 2. Division 26 requirements apply to electrical work provided under any division of 5 the Specifications. 6 B. Service and Metering 7 1. Obtain service from the electric service provider at 120/240 Volts, Single Phase, 8 Three Wire, 60 Hz from transformer equipment furnished and installed by the 9 power company. 10 2. Power company responsibilities: 11 a. Furnishing and installing the primary overhead conductors and pole line 12 b. Furnishing and installing the transformer or riser pole, primary cutouts, 13 lightning arresters and grounding 14 c. Furnishing and installing primary conduits and cables 15 d. Furnishing and installing the transformer pad and grounding (if pad-mounted 16 transformer) 17 e. Furnishing and installing transformer 18 f. Terminating underground primary cables 19 g. Furnishing metering current transformers (CT's), meter and meter wiring 20 h. Terminating secondary cables to the service transformer 21 i. Furnishing meter base and enclosure 22 3. Contractor responsibilities: 23 a. Furnishing and installing secondary conduits and cables 24 b. Furnishing and installing power company approved metering current 25 transformer enclosure (if required by power company) 26 c. Installing meter base 27 d. Furnishing and installing an empty conduit with pull line from the metering 28 current transformer enclosure to the meter enclosure. Conduit size and type 29 approved by the power company 30 e. Coordinating electrical service installation with power company 31 4. City responsibilities: 32 a. Negotiating with power company for the costs of new or revised services 33 b. Making payment directly to power company for such costs 34 C. Codes, Inspections and Fees 35 1. Obtain all necessary permits and pay all fees required for permits and inspections. 36 1.5 SUBMITTALS 37 A. Submittals shall be in accordance with Section 01 33 00. 38 B. All submittals shall be approved by the City prior to delivery. 39 1.6 ACTION SUBMITTALS [NOT USED] 40 1.7 CLOSEOUT SUBMITTALS [NOT USED] 41 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 42 26 05 00 COMMON WORK RESULTS FOR ELECTRICAL Page 5 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1.9 QUALITY ASSURANCE [NOT USED] 1 1.10 DELIVERY, STORAGE, AND HANDLING 2 A. Storage and Handling Requirements 3 1. Secure and maintain a location to store the material in accordance with Section 01 4 66 00. 5 1.11 FIELD CONDITIONS [NOT USED] 6 1.12 WARRANTY [NOT USED] 7 PART 2 - PRODUCTS 8 2.1 CITY-FURNISHED PRODUCTS [NOT USED] 9 2.2 MANUFACTURER / MATERIALS 10 A. Manufacturers 11 1. Provide material in accordance with TxDOT’s Traffic Material Producer List: 12 http://ftp.dot.state.tx.us/pub/txdot-info/cmd/mpl/qtrfsigeqp.pdf 13 a. Manufacturers on this list shall be in accordance with this Section and related 14 Sections. 15 2. Electrol Systems Meter Pedestal, Stainless Steel: 16 a. TY D (120/240)070(NS)SS(E)PS(U), or 17 b. Approved equal. 18 3. Substitution requests for manufacturers or models not indicated above shall be 19 processed in accordance with Section 01 25 00. 20 B. Materials 21 1. Provide materials that comply with the details shown on the plans, the requirements 22 of this Item, and the pertinent requirements of the following TxDOT specifications: 23 a. Item 441 24 b. Item 445 25 c. Item 449 26 d. Item 618 27 e. Item 620 28 f. Item 627 29 g. Item 656 30 2. Provide new materials, except where specified in the Drawings to be reused. 31 3. For the installation of electrical services, use new materials that meet the 32 requirements of the NEC, UL, CSA, and NEMA, and are in accordance with DMS-33 11080, “Electrical Services.” 34 4. Provide prequalified electrical services prequalified from TxDOT’s MPL. Notify 35 the City in writing of selected materials from the MPL intended for use on each 36 project. 37 5. Pedestal Service shall be custom made in accordance with the Contract Documents 38 a. Supplied with 100 amp main breaker 39 b. 1-50a/1p for traffic signal 40 26 05 00 COMMON WORK RESULTS FOR ELECTRICAL Page 6 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 c. 1-20a/2p for lighting 1 d. 1-15a/1p for control circuit interior photo cell with windows 2 e. Hand-off-Auto Selector Switch 3 f. 200 amp meter socket 4 6. Pedestal service type shall be used unless otherwise approved by the City. 5 7. Pedestal service enclosure shall be aluminum and light green in color. 6 2.3 ACCESSORIES [NOT USED] 7 2.4 SOURCE QUALITY CONTROL [NOT USED] 8 PART 3 - EXECUTION 9 3.1 INSTALLERS [NOT USED] 10 3.2 EXAMINATION 11 A. Interpretation of Drawings 12 1. Coordinate the conduit installation with other trades and the actual supplied 13 equipment. 14 2. Where circuits are shown as home runs: Provide fittings and boxes for complete 15 raceway installation. 16 3. Verify exact locations and mounting heights of lighting fixtures, switches and 17 receptacles prior to installation. 18 3.3 PREPARATION [NOT USED] 19 3.4 INSTALLATION 20 A. Installation 21 1. General 22 a. Perform work as specified in the Drawings an in accordance with the 23 requirements of this Section. 24 b. Use established industry and utility safety practices when installing, relocating, 25 or removing electrical services located near overhead or underground utilities. 26 1) Consult with the appropriate utility company before beginning work. 27 2. Installation 28 a. Furnish and install electrical service equipment. 29 b. Ensure components of the electrical service meet the requirements of the 30 Contract Documents. 31 c. Follow NEC and local utility company requirements when installing the 32 electrical equipment. 33 1) Coordinate the utility companies’ work for providing service. 34 3. Relocation 35 a. Coordinate relocation with the appropriate utility company before beginning 36 work. 37 b. Remove and reinstall existing electrical service in accordance with this Section. 38 1) Replace or add circuit breakers as specified in the Drawings. 39 40 26 05 00 COMMON WORK RESULTS FOR ELECTRICAL Page 7 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 4. Removal 1 a. Coordinate removal with the appropriate utility company before beginning 2 work. 3 1) Before the removal of the electrical service, disconnect and isolate any 4 existing electrical service equipment in accordance with the utility 5 company’s requirements. 6 b. Remove existing electrical service support a minimum of 2 feet below finished 7 grade unless otherwise specified in the Drawings. 8 c. Repair the remaining hole by backfilling with material equal in composition 9 and density to the surrounding area. 10 d. Replace any surfacing such as asphalt pavement or concrete riprap with like 11 material to equivalent condition. 12 e. Disconnect conductors and remove them from the conduit. 13 1) Cut off all protruding conduit 6 inches below finished grade. 14 2) Abandoned conduit need not be removed unless specified in the Drawings. 15 f. Reconnect conductors and conduit to be reused when specified in the Drawings. 16 1) Any necessary splices should be made in ground boxes, unless otherwise 17 specified in the Drawings, and approved by City. 18 g. Accept ownership of unsalvageable materials, and dispose of them in 19 accordance with Federal, State, and local regulations. 20 B. Phase Balancing 21 1. Connect circuits on motor control centers and panelboards to result in evenly 22 balanced loads across all phases. 23 3.5 REPAIR [NOT USED] 24 3.6 RE-INSTALLATION [NOT USED] 25 3.7 FIELD QUALITY CONTROL [NOT USED] 26 3.8 SYSTEM STARTUP 27 A. Tests and Settings 28 1. Test systems and equipment furnished under Division 26. 29 2. Repair or replace all defective work as directed by City. 30 3. Adjust the systems as specified and/or required in accordance with manufacturer 31 and utility requirements. 32 4. Prior to energizing electrical equipment, perform the following tests: 33 a. Submit a sample test form or procedure. 34 b. Submit test reports required by the utility comapny and data within 30 days 35 after the test. 36 c. Include names of all test personnel. 37 d. Initial each test. 38 5. Check wire and cable terminations for tightness. 39 6. Verify all terminations at transformers, equipment, capacitor connections, panels, 40 and enclosures by producing a 1-2-3 rotation on a phase sequence motor when 41 connected to A, B, and C phases. 42 26 05 00 COMMON WORK RESULTS FOR ELECTRICAL Page 8 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 7. Inspect, set, and test mechanical operation for circuit breakers, disconnect switches, 1 motor starters, and control equipment. 2 8. Check interlocking, control, and instrument wiring for each system and/or part of a 3 system to prove the system will function as specified in the Drawings. 4 9. Schedule and coordinate testing with the City a minimum of 2 weeks in advance. 5 10. Provide qualified test personnel, instruments, and test equipment. 6 3.9 ADJUSTING [NOT USED] 7 3.10 CLEANING [NOT USED] 8 3.11 CLOSEOUT ACTIVITIES [NOT USED] 9 3.12 PROTECTION [NOT USED] 10 3.13 MAINTENANCE [NOT USED] 11 3.14 ATTACHMENTS [NOT USED] 12 END OF SECTION 13 14 Revision Log DATE NAME SUMMARY OF CHANGE 15 26 05 10 DEMOLITION FOR ELECTRICAL SYSTEM Page 1 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 26 05 10 1 DEMOLITION FOR ELECTRICAL SYSTEM 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Installation and testing of all equipment, wiring, and appurtenances as may be 6 required to perform electrical demolition. 7 B. Deviations from this City of Denton Standard Specification: 8 1. None. 9 C. Related Specification Sections include but are not limited to: 10 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 11 Contract. 12 2. Division 1 - General Requirements. 13 1.2 PRICE AND PAYMENT PROCEDURES 14 A. Measurement and Payment 15 1. Demolition for Electrical System 16 a. Measurement 17 1) Measured per lump sum for removing and salvaging electrical system. 18 b. Payment 19 1) The work performed, and materials furnished in accordance with this item 20 and measured as provided under “Measurement” will be paid for at the unit 21 price bid per lump sum for “Remove and Salvage Electrical Equipment.” 22 c. The price bid shall include: 23 1) Removing and salvaging electrical equipment as specified by the Drawings 24 2) Excavation 25 3) Furnishing, placement, and compaction of backfill 26 4) Hauling 27 5) Clean-up 28 1.3 REFERENCES. 29 A. Reference Standards 30 1. Reference standards cited in this Section refer to the current reference standard 31 published at the time of the latest revision date logged at the end of this Section 32 unless a date is specifically cited. 33 1.4 ADMINISTRATIVE REQUIREMENTS 34 A. Coordination 35 1. Coordinate with the City or their designee 48 hours in advance of removals. 36 2. Coordinate with other Trades for removal of electrical services in conjunction with 37 the removal of the associated equipment. 38 26 05 10 DEMOLITION FOR ELECTRICAL SYSTEM Page 2 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1.5 SUBMITTALS 1 A. Submittals shall be in accordance with Section 01 33 00. 2 B. All submittals shall be approved by the City prior to delivery. 3 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 4 1.7 CLOSEOUT SUBMITTALS [NOT USED] 5 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 6 1.9 QUALITY ASSURANCE [NOT USED] 7 1.10 DELIVERY, STORAGE, AND HANDLING 8 A. Delivery and Acceptance Requirements 9 1. All salvage materials will be delivered by the Contractor to the City at a location 10 designated by the City. 11 a. The City will serve as the receiving agent for salvage material. 12 B. Storage and Handling Requirements 13 1. Secure and maintain a location to store the material in accordance with Section 01 14 66 00. 15 1.11 FIELD CONDITIONS [NOT USED] 16 1.12 WARRANTY [NOT USED] 17 PART 2 - PRODUCTS [NOT USED] 18 2.1 CITY-FURNISHED PRODUCTS [NOT USED] 19 2.2 MATERIALS [NOT USED] 20 2.3 ACCESSORIES [NOT USED] 21 2.4 SOURCE QUALITY CONTROL [NOT USED] 22 PART 3 - EXECUTION 23 3.1 INSTALLERS [NOT USED] 24 3.2 EXAMINATION 25 A. Verify field measurements and circuiting arrangements. 26 B. Verify abandoned wiring and equipment serve only abandoned facilities. 27 C. Report Drawing discrepancies to City before disturbing the existing installation. 28 29 26 05 10 DEMOLITION FOR ELECTRICAL SYSTEM Page 3 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3.3 PREPARATION 1 A. Disconnect electrical systems in walls, floors, and ceilings scheduled for removal. 2 B. Coordinate utility service outages with Utility Company to minimize length and number 3 of outages. 4 C. Provide temporary wiring and connections to maintain existing systems in service 5 during construction. 6 D. When work must be performed on energized equipment or circuits, use personnel 7 experienced in such operations. 8 E. Existing Electrical Service 9 1. Maintain existing system in service until new system is complete and ready for 10 service. 11 F. Disable system only to make switchovers and connections. 12 G. Obtain permission from City at least 1 week in advance before partially or completely 13 disabling the system. 14 3.4 REMOVAL 15 A. Remove, relocate, and extend existing installations to accommodate new construction. 16 B. Remove abandoned wiring to source of electrical supply. 17 C. Remove exposed abandoned conduit, including abandoned conduit above accessible 18 ceiling finishes. 19 1. Cut conduit flush with walls and floors and patch surfaces. 20 D. Disconnect abandoned outlets and remove devices. 21 1. Remove abandoned outlets if conduit serving them is abandoned and removed. 22 2. Provide blank cover for abandoned outlets which are not removed. 23 E. Disconnect and remove abandoned panelboards and distribution equipment. 24 F. Disconnect and remove electrical devices and equipment that has been removed. 25 G. Repair adjacent construction and finishes damaged during demolition and extension 26 work. 27 H. Maintain access to existing installations that are to remain active. Modify installation or 28 provide access to panels as appropriate. 29 I. If portions of raceway system are to be demolished or revised, remaining raceway 30 system shall be in accordance with this and all related Sections. 31 1. If necessary, provide and install equipment to ensure acceptable raceway system. 32 J. Extend existing installations using materials and methods as specified for new Work. 33 K. Minimize noise, dust, and vibration. Conduct the Work so as to avoid any damage to 34 the surroundings. 35 L. Salvaged Equipment and Materials 36 1. The City shall have the right to retain any or all electrical and instrumentation 37 equipment specified to be removed from the site. 38 26 05 10 DEMOLITION FOR ELECTRICAL SYSTEM Page 4 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2. Deliver the City’s equipment to a site designated by the City. 1 3. If the City refuses the salvage, the Contractor must claim ownership of the 2 materials and dispose of them properly. 3 4. Prior to starting demolition, the Contractor and City shall jointly visit the areas of 4 demolition and the City will designate which items are to remain the property of the 5 City. 6 a. Any material not designated to remain the property of the City, or removed 7 from the Site during demolition, shall become the property of the Contractor 8 and shall be promptly removed from the Site. 9 1) Any material removed from the Site during demolition shall also become 10 the property of the Contractor. 11 5. Take necessary precautions in removing City designated property to prevent 12 damage during the demolition process. 13 a. Remove steel structural members by unbolting, cutting welds, or cutting rivet 14 heads and punching shanks through holes. 15 b. Do not use a cutting torch to separate the City’s equipment or material. 16 6. Remove items in 1 piece or in a manner that does not impact their reuse. 17 a. Loose components may be removed separately. 18 b. Controls and electrical equipment may be removed from the equipment and 19 handled separately. 20 c. Large units may be handled separately. 21 d. Salvaged piping shall be taken apart at flanges or fittings and removed in 22 sections. 23 M. Refurbish and replace any existing facility to be left in place that is damaged by the 24 demolition operations. 25 1. Repair damaged parts to a condition equal to or better than that found at the start of 26 the work. 27 3.5 RESTORATION 28 A. Clean and repair existing materials and equipment that remain or are to be reused. 29 B. Panelboards 30 1. Clean exposed surfaces. 31 2. Check tightness of electrical connections. 32 3. Replace damaged circuit breakers. 33 4. Provide closure plates for vacant positions. 34 5. Provide typed circuit directory showing revised circuiting arrangement. 35 3.6 RE-INSTALLATION [NOT USED] 36 3.7 FIELD QUALITY CONTROL [NOT USED] 37 3.8 SYSTEM STARTUP [NOT USED] 38 3.9 ADJUSTING [NOT USED] 39 3.10 CLEANING [NOT USED] 40 26 05 10 DEMOLITION FOR ELECTRICAL SYSTEM Page 5 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3.11 CLOSEOUT ACTIVITIES [NOT USED] 1 3.12 PROTECTION [NOT USED] 2 3.13 MAINTENANCE [NOT USED] 3 3.14 ATTACHMENTS [NOT USED] 4 END OF SECTION 5 6 Revision Log DATE NAME SUMMARY OF CHANGE 7 26 05 13 ZINC COATED STEEL WIRE Page 1 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 26 05 13 1 ZINC COATED STEEL WIRE 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Zinc Coated Steel Wire. 6 B. Deviations from this City of Denton Standard Specification: 7 1. None. 8 C. Related Specification Sections include but are not limited to: 9 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 10 Contract. 11 2. Division 1 - General Requirements. 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Furnish and Install Zinc Coated Steel Wire 15 a. Measurement 16 1) Measured per linear foot of Zinc Coated Steel Wire installed. 17 b. Payment 18 1) The work performed and materials furnished in accordance with this item 19 and measured as provided under “Measurement” shall be paid for at the 20 unit price bid per linear foot of “Zinc Coated Steel Wire” installed for: 21 a) Various types. 22 b) Various sizes. 23 c. The price bid shall include: 24 1) Furnishing and installing Zinc Coated Cable 25 2) Testing wire strands 26 2. Remove Zinc Coated Steel Wire 27 a. Measurement 28 1) Measured per linear foot of Zinc Coated Steel Wires removed. 29 b. Payment 30 1) The work performed and materials furnished in accordance with this item 31 and measured as provided under “Measurement” shall be paid for at the 32 unit price bid per linear foot of “Zinc Coated Steel Wire Removal.” 33 c. The price bid shall include: 34 1) Removal and disposal of Zinc Coated Steel Wire 35 2) Clean-up 36 37 26 05 13 ZINC COATED STEEL WIRE Page 2 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1.3 REFERENCES 1 A. Reference Standards 2 1. Reference standards cited in this Section refer to the current reference standard 3 published at the time of the latest revision date logged at the end of this Section 4 unless a date is specifically cited. 5 2. ASTM International (ASTM): 6 a. A475, Standard Specification for Zinc-Coated Steel Wire Strand. 7 3. Texas Department of Transportation, Standard Specifications for Construction and 8 Maintenance of Highways, Streets, and Bridges (TxDOT). 9 a. Item 625, Zinc-Coated Steel Wire Strand. 10 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 11 1.5 SUBMITTALS 12 A. Submittals shall be in accordance with Section 01 33 00. 13 B. All submittals shall be approved by the City prior to delivery. 14 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 15 A. Product Data: 16 1. Zinc Coated Steel Wire. 17 1.7 CLOSEOUT SUBMITTALS [NOT USED] 18 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 19 1.9 QUALITY ASSURANCE [NOT USED] 20 1.10 DELIVERY, STORAGE, AND HANDLING 21 A. Storage and Handling Requirements 22 1. Secure and maintain a location to store the material in accordance with Section 01 23 66 00. 24 1.11 FIELD CONDITIONS [NOT USED] 25 1.12 WARRANTY [NOT USED] 26 PART 2 - PRODUCTS 27 2.1 CITY-SUPPLIED PRODUCTS 28 A. Refer to the Contract Documents to determine if any equipment and material will be 29 furnished by the City. 30 2.2 MATERIALS 31 A. Materials 32 1. Zinc Coated Steel Wire 33 26 05 13 ZINC COATED STEEL WIRE Page 3 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 a. Provide new materials in accordance with TxDOT Item 625 and ASTM A475, 1 Utilities Grade or better, class A coating. 2 b. Furnish 7 wires per strand. 3 c. In accordance with the following: 4 5 Nominal Diameter of Strand Nominal Diameter of Coated Wires Approx. Weight per 1,000 ft. Minimum Breaking Strength Minimum Zinc Coating Wt. Class A (in.) (in.) (lb.) (lb.) (oz./sq. ft.) 3/16 0.065 80 2,400 0.50 1/4 0.080 121 4,750 0.60 9/32 0.093 164 4,600 0.70 5/16 0.109 225 6,000 0.80 3/8 0.120 273 11,500 0.85 7/16 0.145 399 18,000 0.90 1/2 0.165 517 25,000 0.90 6 d. Supply new material. 7 e. Remove drips, runs, sharp points, voids, and damage from the zinc coating. 8 f. Samples from each roll of each diameter of strand will be taken. 9 1) Replace strands not in accordance with this Section. 10 2.3 ACCESSORIES [NOT USED] 11 2.4 SOURCE QUALITY CONTROL [NOT USED] 12 PART 3 - EXECUTION 13 3.1 INSTALLERS [NOT USED] 14 3.2 EXAMINATION [NOT USED] 15 3.3 PREPARATION [NOT USED] 16 3.4 INSTALLATION 17 A. Install strands as specified in the Drawings. 18 1. Splicing is not permitted. 19 B. Ground strand to the grounding conductor at each pole when used as a messenger cable 20 or span wire. 21 1. Metal poles may be used as the grounding conductor. 22 2. Ensure a resistance less than 1 ohm from the strand to the ground. 23 3.5 REPAIR / RESTORATION [NOT USED] 24 3.6 RE-INSTALLATION [NOT USED] 25 3.7 FIELD QUALITY CONTROL [NOT USED] 26 26 05 13 ZINC COATED STEEL WIRE Page 4 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3.8 SYSTEM STARTUP [NOT USED] 1 3.9 ADJUSTING [NOT USED] 2 3.10 CLEANING [NOT USED] 3 3.11 CLOSEOUT ACTIVITIES [NOT USED] 4 3.12 PROTECTION [NOT USED] 5 3.13 MAINTENANCE [NOT USED] 6 3.14 ATTACHMENTS [NOT USED] 7 END OF SECTION 8 9 Revision Log DATE NAME SUMMARY OF CHANGE 10 26 05 19 SIGNAL CABLES Page 1 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 26 05 19 1 SIGNAL CABLES 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Installation and Removal of Multi-conductor Cable. 6 B. Deviations from this City of Denton Standard Specification: 7 1. None. 8 C. Related Specification Sections include but are not limited to: 9 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 10 Contract. 11 2. Division 1 - General Requirements. 12 3. Section 26 05 34 – Conduit. 13 1.2 PRICE AND PAYMENT PROCEDURES 14 A. Measurement and Payment 15 1. Furnish and Install Multi-conductor Cable 16 a. Measurement 17 1) Measured per linear foot of Multi-conductor Cable furnished and installed. 18 b. Payment 19 1) The work performed and materials furnished in accordance with this item 20 and measured as provided under “Measurement” shall be paid for at the 21 unit price bid per linear foot of “Furnish/Install Multi-conductor Cable” for: 22 a) Various types. 23 b) Various sizes. 24 c. The price bid shall include: 25 1) Furnishing and installing Multi-conductor Cable as specified by the 26 Drawings 27 2. Remove Multi-conductor Cable 28 a. Measurement 29 1) Measured per linear foot of Multi-conductor Cable removed. 30 b. Payment 31 1) The work performed and materials furnished in accordance with this item 32 and measured as provided under “Measurement” shall be paid for at the 33 unit price bid per linear foot of “Remove Multi-conductor Cable” for: 34 a) Various types. 35 b) Various sizes. 36 c. The price bid shall include: 37 1) Removal of Multi-conductor Cable as specified by the Drawings 38 39 26 05 19 SIGNAL CABLES Page 2 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1.3 REFERENCES 1 A. Abbreviations and Acronyms 2 1. AWG: American wire gauge 3 2. PVC: polyvinyl chloride 4 B. Reference Standards 5 1. Reference standards cited in this Section refer to the current reference standard 6 published at the time of the latest revision date logged at the end of this Section 7 unless a date is specifically cited. 8 2. Texas Department of Transportation, Standard Specifications for Construction and 9 Maintenance of Highways, Streets and Bridges (TxDOT): 10 a. Item 684, Traffic Signal Cables. 11 3. TxDOT Departmental Materials Specification: 12 a. DMS-11110, Traffic Signal Cable. 13 4. Underwriters Laboratories, Inc. (UL). 14 5. International Municipal Signal Association (IMSA). 15 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 16 1.5 SUBMITTALS 17 A. Submittals shall be in accordance with Section 01 33 00. 18 B. All submittals shall be approved by the City prior to delivery. 19 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 20 A. Product Data Sheets are required for: 21 1. Multi-conductor cable. 22 2. Power lead-in cable. 23 1.7 CLOSEOUT SUBMITTALS [NOT USED] 24 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 25 1.9 QUALITY ASSURANCE [NOT USED] 26 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 27 A. Storage and Handling Requirements 28 1. Secure and maintain a location to store the material in accordance with Section 01 29 66 00. 30 1.11 FIELD [SITE] CONDITIONS [NOT USED] 31 1.12 WARRANTY [NOT USED] 32 PART 2 - PRODUCTS 33 2.1 CITY-FURNISHED PRODUCTS [NOT USED] 34 35 26 05 19 SIGNAL CABLES Page 3 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2.2 MATERIALS 1 A. Materials 2 1. In accordance with TxDOT Item 684. 3 2. All traffic signal cable conductors for both vehicle and pedestrian heads shall be 4 multi-conductor capable of operating at 600 volts maximum and suitable for use at 5 conductor temperatures not exceeding 75 degrees C (167 degrees F). 6 3. Multi-conductor cable shall be either stranded IMSA 19-1 or 20-1, #14 AWG, 7 stranded copper wire. 8 4. Ensure fillers are non-metallic, moisture resistant, non-wicking material. 9 5. Supply cables shall be clearly labeled with the name of the manufacturer and the 10 IMSA specification number in indent printing at 2 foot intervals to the outer surface 11 of the jacket. 12 6. All proprietary equipment cabling shall be manufacturer supplied and properly 13 installed in accordance with the manufacturer’s recommendations. 14 7. All electrical connectors for breakaway poles shall be breakaway (Buchannan 65U, 15 Bussman HEBW Littlefuse LEF, or equal). 16 8. All electrical connections for neutrals shall be breakaway, shall have a white color 17 marking, and shall have permanently installed solid neutral Buchannan 20U 18 Bussman HET Littlefuse LET or equal. 19 9. Breakaway fuse holders shall be 1-pole or 2-pole, watertight, breakaway, in-line 20 fused connector designed for used with breakaway pole bases that meet the 21 following requirements: 22 a. UL listed, 600-V-rated. 23 b. Prevent energized parts from being exposed after breaking away. 24 c. Have breakaway connector boots that fit multiple wire sizes (may be dual wire 25 “feed-in-feed-out type”). 26 d. Have neutral connectors marked white. 27 2.3 ACCESSORIES [NOT USED] 28 2.4 SOURCE QUALITY CONTROL [NOT USED] 29 PART 3 - EXECUTION 30 3.1 INSTALLERS [NOT USED] 31 3.2 EXAMINATION [NOT USED] 32 3.3 PREPARATION [NOT USED] 33 3.4 INSTALLATION 34 A. Special Techniques 35 1. Cables shall be installed in conduit unless indicated as an "overhead" cable run. 36 a. All conduits must be in accordance with Section 26 05 34. 37 b. Conduit must be continuous, reasonably dry, completely free of debris, and 38 without sharp projections, edges, or short bends. 39 26 05 19 SIGNAL CABLES Page 4 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2. If required by the City, the Contractor shall demonstrate the conduit is dry and free 1 of debris by pulling a swab and/or mandrel through the conduit. 2 a. The conductors shall be installed to ensure against harmful stretching of the 3 conductors or damage to the insulation. 4 3. Installation methods shall be in accordance with the recommendations of the cable 5 manufacturer. 6 4. At the request of the City, furnish a copy of the manufacturer's recommendations 7 which shall include methods of attaching pull cable, pulling tension per conductor 8 size and per radius of conduit bend, and the type of lubricant to be used. 9 5. All cables in a given conduit run shall be pulled at the same time and the 10 conductors shall be assembled to form 1 loop so the pulling tension is equally 11 distributed to all the cables. 12 a. Use pulling eyes for long, hard pulls. 13 b. For short runs, the cables may be gripped directly by the conductors by forming 14 them into a loop to which the pull wire or rope can be attached. 15 c. The insulation on each conductor shall be removed before the loop is formed. 16 d. The method used will depend on the anticipated maximum pulling tension in 17 each case. 18 6. If new cables are to replace existing cables within existing conduit, the existing 19 cables may be used to pull in the new cables. 20 7. Where new cables are to be added to existing cable runs: 21 a. Pull existing cables out of cable run. 22 b. Add new cables to existing cables such that the combined wires from 1 cable 23 pull. 24 8. Installation and removal shall be done in such a way as to prevent damage to the 25 existing and/or new cables. 26 a. In the event of damage, the Contractor shall repair and/or replace damaged 27 cables at no cost to the City. 28 9. All conduit runs shall be measured accurately and precisely for determining cable 29 lengths to be installed. 30 a. City shall be present for all conduit run measurements taken. 31 b. City shall record all cable measurements and include the distances on an as-32 built drawing. 33 10. Where new cables are to replace existing cables, removed cables may be used as a 34 measuring device to determine the lengths of the new cables to be installed. 35 a. Accurate measurements of all cable lengths. 36 11. Contractor shall keep in accordance with the manufacturer’s recommended 37 maximum pulling tensions at all times. 38 12. If required by the City, insert a dynamometer in the pull wire as the cables are being 39 pulled into the conduit to demonstrate that the maximum tensions are not being 40 exceeded. 41 13. The cable shall be fed freely off the reel into the conduit without making a reverse 42 curve. 43 14. At the pulling end, the pull wire and cables shall be drawn from the conduit in 44 direct line with the conduit. 45 26 05 19 SIGNAL CABLES Page 5 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 15. Sheaves or other suitable devices shall be used as required to reduce any hazards to 1 the cable during installation. 2 16. The cables shall be adequately lubricated to reduce friction and further minimize 3 possible damage. 4 a. Such lubricants shall not be the grease or oil type used on lead sheathed cables 5 but shall be one of several commercially available wire pulling compounds that 6 are suitable for PVC sheathed cables. 7 b. They shall consist of soap, talc, mica, or similar materials and shall be designed 8 to have no deleterious effect on the cables being used. 9 17. Cables shall be neatly trained to their destinations. 10 18. Keep cable in accordance with the cable manufacturer's recommended values for 11 the minimum bending radii to which cables may be bent for permanent training 12 during installation. 13 a. These limits do not apply to conduit bends, sheaves, or other curved surfaces 14 around which these cables may be pulled under tension while being installed. 15 b. Larger radius bends are required for such conditions. 16 B. Wire and Cable 17 1. All wire and cable shall be as specified in the Drawings, except wire and cable 18 specifically covered by other Sections of the Contract Documents. 19 2. Controller Cabinet Wiring 20 a. Wiring for the controller cabinet shall consist of connecting signal wires, 21 vehicle detection wires, power wires, ground wires, and pedestrian push button 22 wires to their respective terminals in the cabinet. 23 b. In the controller cabinet, stranded signal conductors from the field shall be 24 stripped back and a solderless terminal connector (spade lug) shall be attached 25 by means of a crimping tool. 26 c. These terminal Connectors shall be inserted under the binder head screw and 27 tightened securely. 28 d. Other wiring for the controller shall be completed as shown on the wiring 29 diagrams and in the instructions furnished with the controller by the 30 manufacturer. 31 e. All field wiring in cabinets shall be neatly installed. Incoming cables shall be 32 trained to their destination and neatly laced together. 33 1) All spare wires shall be trimmed and neatly coiled with the ends taped. 34 2) Detector lead-in cables shall have their insulation jackets removed from 35 their terminal strip connection to the bottom of the cabinet. 36 f. Pedestrian push buttons shall have a ground wire completely isolated and 37 independent from all other ground wires. 38 1) This wire shall be connected to the designated terminal in the controller 39 cabinet. 40 2) A pedestrian isolation board shall be in place. 41 g. Individual conductors between the controller and signal pole base shall be #14 42 AWG. 43 3. Signal Head Wiring 44 1) No splicing of cable shall be allowed. 45 26 05 19 SIGNAL CABLES Page 6 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2) Each cable shall be identified with permanent marking labels (Panduit type 1 PLM standard single marker tie, Thomas and Betts type 548M or 2 equivalent) at each ground box, pole base, and controller, as specified in the 3 Drawings. 4 3) Traffic signal cable within the signal poles and arms shall be #14 AWG. 5 4. Additional lengths of each wire are required. 6 a. The wire that passes through or terminates in: 7 1) A ground box – Minimum 6 feet 8 2) The cabinet – Minimum 15 feet, and/or 9 3) A steel mast arm vertical pole – Minimum 6 feet 10 b. For Span wire assemblies: 11 1) At each pole – 15 feet 12 2) At each signal head – 6 feet 13 c. Depending on local conditions, other lengths of wire not listed herein may be 14 required and will be determined on site by the City. 15 5. No splicing will be allowed for any type of wiring, unless approved by the City. 16 a. Exceptions are where manufacture’s supplied cable/wire requires continuation 17 for connection to applicable terminus. All splicing techniques shall be in 18 accordance with manufacture’s recommendations/requirements and approved in 19 writing by the City prior to beginning work. 20 6. Wiring hole locations are to be marked by the Contractor and approved by the City 21 prior to drilling for the item it is intended to serve. 22 7. All conductors shall be in accordance with manufacturer’s loading 23 standards/requirements. 24 8. Terminals 25 a. The ends of all stranded wires from the controller cabinet and from the signal 26 heads shall be twisted at least 3 turns and wire nut applied in the base of the 27 signal structure. 28 9. Identification of Signal Wires and Cables 29 a. IMSA color coded signal cable shall be used for all signal systems. 30 1) Colors shall be continuous from the point of origin to the point of 31 termination. 32 b. Each signal cable, detector lead-in cable and communication cable shall be 33 designated with permanent marking labels or (Panduit type PLM, Thomas and 34 Betta type 548M standard single marker type or equivalent) and color-coded 35 tape at each pull box and in the controller cabinet. 36 3.5 REPAIR [NOT USED] 37 3.6 RE-INSTALLATION [NOT USED] 38 3.7 FIELD QUALITY CONTROL 39 A. Field Tests and Inspections 40 1. The City may require all cables be checked for insulation resistance upon 41 installation and prior to termination. The tests shall be made with a test set 42 operating at a minimum of 500 volts DC applied to the conductors. 43 26 05 19 SIGNAL CABLES Page 7 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2. Each conductor in the multi-conductor signal cables shall be tested for insulation 1 resistance relative to each other and to the outer covering of the cable. The 2 minimum acceptance value for insulation resistance shall be 1 megohm. 3 3.8 SYSTEM STARTUP [NOT USED] 4 3.9 ADJUSTING [NOT USED] 5 3.10 CLEANING [NOT USED] 6 3.11 CLOSEOUT ACTIVITIES [NOT USED] 7 3.12 PROTECTION [NOT USED] 8 3.13 MAINTENANCE [NOT USED] 9 3.14 ATTACHMENTS [NOT USED] 10 END OF SECTION 11 12 Revision Log DATE NAME SUMMARY OF CHANGE 13 26 05 20 TRAY CABLES Page 1 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 26 05 20 1 TRAY CABLES 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Installation and Removal of Tray Cable. 6 B. Deviations from this City of Denton Standard Specification: 7 1. None. 8 C. Related Specification Sections include but are not limited to: 9 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 10 Contract. 11 2. Division 1 - General Requirements. 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Furnish and Install Tray Cable 15 a. Measurement 16 1) Measured per linear foot of tray cable installed. 17 b. Payment 18 1) The work performed and materials furnished in accordance with this item 19 and measured as provided under “Measurement” will be paid for at the unit 20 price bid per linear foot of “Tray Cable” installed for: 21 a) Various types. 22 b) Various sizes. 23 c. The price bid shall include: 24 1) Furnishing and installing tray cable as specified by the Drawings 25 2. Remove Tray Cable 26 a. Measurement 27 1) Measured per linear foot of Tray Cable removed. 28 b. Payment 29 1) The work performed and materials furnished in accordance with this item 30 and measured as provided under “Measurement” shall be paid for at the 31 unit price bid per linear foot of “Tray Cable” removed for: 32 a) Various types. 33 b) Various sizes. 34 c. The price bid shall include: 35 1) Removal of tray cable as specified by the Drawings 36 1.3 REFERENCES 37 A. Abbreviations and Acronyms 38 1. NRTL: nationally recognized testing laboratory 39 26 05 20 TRAY CABLES Page 2 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2. D/C: direct current 1 3. PVC: polyvinyl chloride 2 4. XHHW: cross linked polyethylene, high heat resistance, water resistance 3 B. Reference Standards 4 1. Reference standards cited in this Section refer to the current reference standard 5 published at the time of the latest revision date logged at the end of this Section 6 unless a date is specifically cited. 7 2. ASTM International (ASTM): 8 a. ASTM B3, Standard Specification for Soft or Annealed Copper Wire. 9 3. Texas Department of Transportation (TxDOT), Standard Specifications for 10 Construction and Maintenance of Highways, Streets and Bridges: 11 a. Item 621, Tray Cable. 12 4. Texas Department of Transportation (TxDOT), Departmental Materials 13 Specification: 14 a. DMS-11050, Tray Cable. 15 5. Institute of Electrical and Electronics Engineers (IEEE) 16 a. 383, Standard for Qualifying Electric Cables and Splices for Nuclear Facilities. 17 6. National Electrical Code (NEC). 18 7. National Electrical Manufacturers Association (NEMA). 19 8. Occupational Safety and Health Administration (OSHA). 20 9. Underwriters Laboratory (UL): 21 a. Subject 1277, Standard for Electrical Power and Control Tray Cables with 22 Optional Optical-Fiber Members. 23 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 24 1.5 SUBMITTALS 25 A. Submittals shall be in accordance with Section 01 33 00. 26 B. All submittals shall be approved by the City prior to delivery. 27 1.6 ACTION SUBMITTALS [NOT USED] 28 1.7 CLOSEOUT SUBMITTALS [NOT USED] 29 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 30 1.9 QUALITY ASSURANCE [NOT USED] 31 1.10 DELIVERY, STORAGE, AND HANDLING 32 A. Storage and Handling Requirements 33 1. Secure and maintain a location to store the material in accordance with Section 01 34 66 00. 35 1.11 FIELD CONDITIONS [NOT USED] 36 1.12 WARRANTY [NOT USED] 37 26 05 20 TRAY CABLES Page 3 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 PART 2 - PRODUCTS 1 2.1 CITY-FURNISHED PRODUCTS [NOT USED] 2 2.2 MATERIALS 3 A. General Requirements 4 1. Provide new materials listed for the intended use in accordance with the NEC and 5 NEMA standards. 6 a. Provide components in accordance with the UL. 7 b. When UL is referenced, consider materials certified by any current NRTL in 8 accordance with the OSHA website. 9 2. Faulty fabrication or poor workmanship in materials, equipment, or installation will 10 be justification for rejection. 11 3. Provide manufacturer’s warranties or guarantees when offered as a customary trade 12 practice. 13 4. Provide round tray cable with non-hygroscopic filler suitable for direct earth burial 14 in wet location, for installation outdoors in conduit, or as an aerial cable supported 15 by a messenger where sunlight-resistant rating is required. 16 5. Clearly and durably mark the outer surface of the jacket by permanent printing to 17 show the insulation type, rating, and manufacturer. 18 a. Apply markings at 2-foot maximum intervals. 19 B. Conductors 20 1. Provide new 3 or 4 individually insulated soft annealed copper conductors in 21 accordance with ASTM B 3 and as specified in the Drawings. 22 2. In accordance with UL Subject 1277 and NEC requirements. 23 3. Provide tray cable rated for a minimum of 600 V, 90°C dry and 75°C wet, unless 24 other insulation type or rating is specified in the Drawings. 25 4. In accordance with the 70,000-btu “Cable Tray Propagation Test” in IEEE 383 and 26 in accordance with the 210,000-btu flame test to show reserve capabilities. 27 5. Ensure the cable is in accordance with the following: 28 a. Provide individually insulated conductors with XHHW insulation and an 29 overall PVC jacket. 30 b. Clearly and durably mark the outer surface of the jacket at 2-foot maximum 31 intervals by indent printing to show the insulation type, rating, and 32 manufacturer. 33 c. Assemble round conductors and provide non-hygroscopic filler to prevent 34 flattening of cable. 35 d. Ensure cable is suitable for use outdoors under exposure to ultraviolet light and 36 in wet locations. 37 C. Insulation 38 1. Provide black, white, and green conductor insulation or black, red, and green 39 conductor insulation, as directed by the City, for three-conductor tray cable. 40 2. Provide black, red, white, and green conductor insulation, as directed by the City, 41 for four-conductor tray cable. 42 26 05 20 TRAY CABLES Page 4 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2.3 ACCESSORIES [NOT USED] 1 2.4 SOURCE QUALITY CONTROL [NOT USED] 2 PART 3 - EXECUTION 3 3.1 INSTALLERS [NOT USED] 4 3.2 EXAMINATION [NOT USED] 5 3.3 PREPARATION [NOT USED] 6 3.4 INSTALLATION 7 A. Special Techniques 8 1. Perform Work as specified in the Drawings and in accordance with requirements of 9 this Section. 10 2. Provide an additional 5 feet of cable coiled in each ground box when installing 11 cable in underground conduit. Splice tray cable conductors only as specified in the 12 Drawings. 13 3. Obtain the City’s written approval for each splice. Ensure allowed splices are 14 watertight. 15 4. Test the cable’s conductors after installation and before any connection. 16 a. Remove and replace tray cable exhibiting a D/C insulation resistance of less 17 than 5 megohms at 1,000 volts D/C at no additional cost to the City. 18 3.5 REPAIR [NOT USED] 19 3.6 RE-INSTALLATION [NOT USED] 20 3.7 FIELD QUALITY CONTROL 21 A. The City may require all cables to be checked for insulation resistance upon installation 22 and prior to termination. 23 1. The tests shall be made with a test set operating at a minimum of 500 volts D/C 24 applied to the conductors. 25 3.8 SYSTEM STARTUP [NOT USED] 26 3.9 ADJUSTING [NOT USED] 27 3.10 CLEANING [NOT USED] 28 3.11 CLOSEOUT ACTIVITIES [NOT USED] 29 3.12 PROTECTION [NOT USED] 30 3.13 MAINTENANCE [NOT USED] 31 32 26 05 20 TRAY CABLES Page 5 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3.14 ATTACHMENTS [NOT USED] 1 END OF SECTION 2 3 Revision Log DATE NAME SUMMARY OF CHANGE 4 26 05 26 GROUNDING CONDUCTORS, GROUND RODS, AND POWER LEAD-IN CABLES Page 1 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 26 05 26 1 GROUNDING CONDUCTORS, GROUND RODS, AND POWER LEAD-IN CABLES 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Grounding Conductors. 6 2. Ground Rod. 7 B. Deviations from this City of Denton Standard Specification: 8 1. None. 9 C. Related Specification Sections include but are not limited to: 10 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 11 Contract. 12 2. Division 1 - General Requirements. 13 1.2 PRICE AND PAYMENT PROCEDURES 14 A. Measurement and Payment 15 1. Grounding Conductors 16 a. Measurement 17 1) Measured per linear foot of grounding conductor installed. 18 b. Payment 19 1) The work performed and materials furnished in accordance with this Item 20 and measured as provided under “Measurement” shall be paid for at the 21 unit price bid per linear foot of “Bare Elec Conductor” installed for: 22 a) Various types. 23 b) Various sizes. 24 c. The price bid shall include: 25 1) Furnishing and installing Grounding Conductor as specified by the 26 Drawings 27 2. Ground Rod 28 a. Measurement 29 1) This item is considered subsidiary to the various Traffic Signal Structures 30 being installed. 31 b. Payment 32 1) The work performed and the materials furnished in accordance with this 33 Item are subsidiary to various Traffic Signal Structures being installed and 34 shall be subsidiary to the unit price bid per various Traffic Signal Structures 35 being installed, no other compensation will be allowed. 36 3. Power Lead-in Cable 37 a. Measurement 38 1) Measured per linear foot of power lead-in cable installed. 39 40 26 05 26 GROUNDING CONDUCTORS, GROUND RODS, AND POWER LEAD-IN CABLES Page 2 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 b. Payment 1 1) The work performed and materials furnished in accordance with this item 2 and measured as provided under “Measurement” shall be paid for at the 3 unit price bid per linear foot of “Insulated Elec Conductor” installed for: 4 a) Various types. 5 b) Various sizes. 6 c. The price bid shall include: 7 1) Furnishing and installing Power Lead-in Cable as specified by the 8 Drawings 9 1.3 REFERENCES 10 A. Abbreviations and Acronyms 11 1. AWG: American wire gauge 12 2. PVC: polyvinyl chloride 13 3. RHW: Rubber insulation, heat resistance of 75℃, water resistance 14 4. THHN: Thermoplastic, high heat resistance, nylon coated 15 5. A/C: alternating current 16 B. Reference Standards 17 1. Reference standards cited in this Section refer to the current reference standard 18 published at the time of the latest revision date logged at the end of this Section 19 unless a date is specifically cited. 20 2. Texas Department of Transportation (TxDOT), Standard Specifications for 21 Construction and Maintenance of Highways, Streets and Bridges: 22 a. Item 620, Electrical Conductors. 23 3. Texas Department of Transportation (TxDOT) Departmental Materials 24 Specification: 25 a. DMS-11040, Electrical Conductors. 26 4. Federal Specification A-A-59544 27 5. American Society for Testing and Materials (ASTM): 28 a. ASTM B33, Standard Specification for Tin-Coated Soft or Annealed Copper 29 Wire for Electrical Purposes. 30 b. ASTM B8, Standard Specification for Concentric-Lay-Stranded Copper 31 Conductors, Hard, Medium-Hard, or Soft. 32 6. International Municipal Signal Association (IMSA). 33 7. National Electric Code (NEC). 34 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 35 1.5 SUBMITTALS 36 A. Submittals shall be in accordance with Section 01 33 00. 37 B. All submittals shall be approved by the City prior to delivery. 38 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 39 A. Product Data Sheets are required for: 40 1. Grounding conductor. 41 26 05 26 GROUNDING CONDUCTORS, GROUND RODS, AND POWER LEAD-IN CABLES Page 3 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2. Grounding rod. 1 1.7 CLOSEOUT SUBMITTALS [NOT USED] 2 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 3 1.9 QUALITY ASSURANCE [NOT USED] 4 1.10 DELIVERY, STORAGE, AND HANDLING 5 A. Storage and Handling Requirements 6 1. Secure and maintain a location to store the material in accordance with Section 01 7 66 00. 8 1.11 FIELD CONDITIONS [NOT USED] 9 1.12 WARRANTY [NOT USED] 10 PART 2 - PRODUCTS 11 2.1 CITY-FURNISHED PRODUCTS [NOT USED] 12 2.2 MATERIALS 13 A. Materials 14 1. Grounding Conductor 15 a. Grounding Conductor shall be in accordance with TxDOT DMS-11040. 16 b. The grounding conductor shall be a #6 AWG solid copper wire. 17 c. The conductor shall be bonded to all ground rods. 18 2. Ground Rod 19 a. Ground rod electrodes shall be copper-bonded steel being at least 5/8 inch in 20 diameter. 21 b. All ground rods shall be a minimum of 8 feet, with a minimum of 6 feet buried. 22 3. Power lead-in cable 23 a. Power lead-in cable shall be stranded RHW copper wire and suitable for A/C 24 electric service. 25 b. The cable shall be capable of operating at 600 volts maximum and suitable for 26 use at conductor temperatures not exceeding 167 degrees Fahrenheit (75 degrees 27 Celsius). 28 c. Material and construction shall be in accordance with the applicable 29 requirements of IMSA and NEC standards. 30 d. Conductors shall be stranded, anneal coated copper. 31 e. Coated wire 32 1) Use copper wire in accordance with ASTM B33 before insulating or 33 stranding. 34 f. Stranding shall be class B, in accordance with the latest edition of ASTM B8. 35 g. Insulation shall be THHN and comply with Federal Specification A-A-59544 36 and all applicable ASTM standards. 37 2.3 ACCESSORIES [NOT USED] 38 26 05 26 GROUNDING CONDUCTORS, GROUND RODS, AND POWER LEAD-IN CABLES Page 4 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2.4 SOURCE QUALITY CONTROL [NOT USED] 1 PART 3 - EXECUTION 2 3.1 INSTALLERS [NOT USED] 3 3.2 EXAMINATION [NOT USED] 4 3.3 PREPARATION [NOT USED] 5 3.4 INSTALLATION 6 A. Special Techniques 7 1. Ground Conductors 8 a. Perform Work as specified in the Drawings. 9 2. Ground Rod 10 a. Properly install and connect a ground rod for each controller cabinet, power 11 drop, and signal pole pier to reduce any extraneous voltage to a safe level. 12 b. The ground rod shall be located to minimize the length of the grounding-13 conductor run. 14 c. For pole-mounted cabinets, a grounding rod and grounding conductor shall be 15 installed at the nearest foundation or ground box. 16 d. All grounding circuits shall be substantial, permanent, and electrically 17 continuous with an ohms-to-ground resistance not to exceed 10 ohms when 18 tested by volt-ohm-meter. 19 e. Illumination poles shall use concrete-grounded electrodes. 20 f. Grounding Connectors and Electrodes 21 1) When the location precludes driving a single ground rod to a depth of 8 feet 22 (2.4 m), or when a multiple ground rod matrix is used to obtain the required 23 resistance to ground, ground rods shall be spaced at least 6 feet apart and 24 bonded by a minimum No. 6 AWG copper wire. 25 2) Connection of grounding circuits to grounding electrodes shall be by 26 devices which will ensure a positive, fail-safe grip between the conductor 27 and the electrode. 28 a) No splice joint will be permitted in the grounding conductor. 29 3) Each grounding rod shall be driven into the ground to a depth sufficient to 30 provide the required resistance (10 ohms) between electrodes and ground. 31 3. Power Lead-in Cable 32 a. Perform work as specified in the Drawings. 33 3.5 REPAIR [NOT USED] 34 3.6 RE-INSTALLATION [NOT USED] 35 3.7 FIELD QUALITY CONTROL [NOT USED] 36 3.8 SYSTEM STARTUP [NOT USED] 37 3.9 ADJUSTING [NOT USED] 38 3.10 CLEANING [NOT USED] 39 26 05 26 GROUNDING CONDUCTORS, GROUND RODS, AND POWER LEAD-IN CABLES Page 5 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3.11 CLOSEOUT ACTIVITIES [NOT USED] 1 3.12 PROTECTION [NOT USED] 2 3.13 MAINTENANCE [NOT USED] 3 3.14 ATTACHMENTS [NOT USED] 4 END OF SECTION 5 6 Revision Log DATE NAME SUMMARY OF CHANGE 7 26 05 33 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS Page 1 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 26 05 33 1 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Furnish and install complete raceway systems as shown on the Drawings and as 6 specified herein. 7 B. Deviations from this City of Denton Standard Specification: 8 1. None. 9 C. Related Specification Sections include but are not limited to: 10 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 11 Contract. 12 2. Division 1 - General Requirements. 13 1.2 PRICE AND PAYMENT PROCEDURES 14 A. Measurement and Payment 15 1. Conduits and Related Hardware 16 a. Measurement 17 1) Measured horizontally along the ground surface from center line to center 18 line between ground boxes or poles, a combination of the two, or to the 19 termination point of conduit installed. 20 b. Payment 21 1) The work performed and materials furnished in accordance with this item 22 and measured as provided under “Measurement” will be paid for at the unit 23 price bid per linear foot of conduit installed for: 24 a) Various sizes. 25 b) Various types. 26 c) Various installation methods. 27 c. The price bid shall include: 28 1) Installation of Conduit and Related Hardware as specified by the Drawings 29 2) Elbows 30 3) Couplings 31 4) Weatherheads 32 2. Conduit Boxes 33 a. Measurement 34 1) Measured per each Conduit Box installed. 35 b. Payment 36 1) The work performed and materials furnished in accordance with this item 37 and measured as provided under “Measurement” will be paid for at the unit 38 price bid per each of conduit box installed. 39 c. The price bid shall include: 40 1) Furnishing and installing the Conduit Box as specified by the Drawings 41 26 05 33 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS Page 2 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2) Excavation 1 3) Furnishing, placement, and compaction of backfill 2 4) Clean-up 3 1.3 REFERENCES 4 A. Abbreviations and Acronyms 5 1. PVC: Polyvinyl chloride 6 2. HDPE: High Density Polyethylene 7 3. BX: Product B Experimental 8 4. AC: Armored cable 9 B. Reference Standards 10 1. Reference standards cited in this Section refer to the current reference standard 11 published at the time of the latest revision date logged at the end of this Section 12 unless a date is specifically cited. 13 2. American National Standards Institute, Inc. (ANSI): 14 a. ANSI C80.5, American National Standard for Electrical Rigid Aluminum 15 Conduit (ERAC). 16 3. National Electrical Manufacturers Association (NEMA): 17 a. 250, Enclosures for Electrical Equipment (1000 Volt Maximum). 18 b. C80.1, Electrical Rigid Steel Conduit. 19 c. TC-2, Electrical Polyvinyl Chloride (PVC) Tubing and Conduit. 20 d. TC-3, Polyvinyl Chloride (PVC) Fittings for Use with Rigid PVC Conduit and 21 Tubing. 22 e. TC-7, Smooth-Walled Coilable Electrical Polyethylene Conduit. 23 4. National Fire Protection Association (NFPA): 24 a. 70 – National Electrical Code (NEC). 25 1) Article 350, Liquidtight Flexible Metal Conduit: Type LFMC. 26 2) Chapter 9, Tables. 27 5. Underwriters Laboratories (UL) 28 a. 6, Electrical Rigid Metal Conduit – Steel. 29 b. 514B, Conduit, Tubing and Cable Fittings. 30 c. 651, Standard for Schedule 40 and 80 Rigid PVC Conduit. 31 C. All equipment components and completed assemblies specified in this Section of the 32 Specifications shall bear the appropriate label of UL. 33 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 34 1.5 SUBMITTALS 35 A. Submittals shall be in accordance with Section 01 33 00. 36 B. All submittals shall be approved by the City prior to delivery. 37 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 38 A. Product Data 39 1. Submit to the City, in accordance with Division 1, the manufacturers' names and 40 product designation or catalog numbers of all materials specified 41 26 05 33 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS Page 3 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 2 1.9 QUALITY ASSURANCE [NOT USED] 3 1.10 DELIVERY, STORAGE, AND HANDLING 4 A. Storage and Handling Requirements 5 1. Secure and maintain a location to store the material in accordance with Section 01 6 66 00. 7 1.11 FIELD CONDITIONS [NOT USED] 8 1.12 WARRANTY [NOT USED] 9 PART 2 - PRODUCTS [NOT USED] 10 2.1 CITY-FURNISHED PRODUCTS [NOT USED] 11 2.2 MATERIALS 12 A. Materials 13 1. Liquidtight Steel Flexible Metal Conduit 14 a. Interlocked steel core 15 b. PVC jacket rated for 80 degrees Celsius 16 c. In accordance with NEC Article 350 17 d. Fittings 18 e. Extruded from 6063 T-1 alloy 19 f. Maximum 0.1 percent copper content 20 g. In accordance with: 21 1) ANSI C80.5 22 2) UL-6 23 2. Rigid Steel Conduit 24 a. Hot dip galvanized 25 b. Threads: Hot galvanized after cutting 26 c. In accordance with: 27 1) NEMA C80.1 28 3. Rigid PVC Schedule 80 Conduit 29 a. Designed for use above ground and underground as described in the NEC 30 b. Resistant to sunlight 31 c. UL Labeled 32 d. In accordance with: 33 1) NEMA TC-2 34 2) UL 651 35 e. Fittings in accordance with: 36 1) NEMA TC-3 37 2) UL 514B 38 4. Rigid PVC Schedule 40 Conduit 39 a. Designed for use underground as described in the NEC 40 26 05 33 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS Page 4 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 b. Resistant to sunlight 1 c. UL Labeled. 2 d. In accordance with: 3 1) NEMA TC-2 4 2) UL 651 5 e. Fittings in accordance with: 6 1) NEMA TC-3 7 2) UL 514B 8 5. HDPE Conduit 9 a. Designed for use underground as described in the NEC 10 b. Resistant to sunlight 11 c. UL Labeled 12 d. In accordance with: 13 1) UL 651A 14 2) UL 651B 15 3) NEMA TC-7 16 6. Raceway Boxes 17 a. For use on exposed raceway systems only. 18 b. Boxes for underground systems shall be in accordance with Section 26 05 43. 19 c. Box size 20 1) Distance between each raceway entry inside the box and the opposite wall 21 shall be no less than 6 times the trade size of the largest raceway in a row. 22 2) Distance shall be increased for additional entries by the amount of the sum 23 of the diameters of all other raceway entries in the same row on the same 24 wall of the box. 25 3) Each row calculated individually, and the single row that provides the 26 maximum distance used to size box. 27 2.3 ACCESSORIES 28 A. Conduit Outlet Bodies 29 1. Up to and including 2-1/2 inches 30 a. Galvanized steel 31 b. Captive screw-clamp cover 32 c. Neoprene gasket 33 d. Stainless steel screws and clamps 34 2. Larger than 2-1/2 inches 35 a. Use junction boxes. 36 B. Conduit Hubs 37 1. Watertight 38 2. Threaded galvanized steel 39 3. Insulated throat 40 4. Stainless steel grounding screw 41 C. Grounding Bushings 42 1. Insulated lay-in lug grounding bushings 43 2. Tin-plated copper grounding path 44 26 05 33 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS Page 5 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3. Integrally molded noncombustible phenolic insulated surfaces rated 150 degrees 1 Celsius 2 4. Plastic insert cap each bushing 3 5. Lug size shall be sufficient to accommodate maximum ground wire size in 4 accordance with the NEC for the application 5 D. Raceway Sealant 6 1. Use for sealing of raceway hubs entering or terminating in boxes or enclosures 7 where specified in the Drawings. 8 E. Conduit Penetration Seals 9 1. Use for conduit wall and floor seals. 10 F. Conduit and related hardware 11 1. All PVC conduits, including elbows and couplings, shall be schedule 40 PVC 12 conduit, conforming to Federal Specification W-C-1094 and UL Standard UL-651. 13 All conduit sizes shall be as specified in the Drawings. 14 2. Rigid metal conduit shall be steel, hot-dipped galvanized inside and outside. 15 3. Weather heads shall be made of aluminum and may be the threaded or clamp-on. 16 G. Expansion/Deflection Fittings 17 1. Use: 18 a. Embedded in concrete 19 b. Exposed 20 2. Description: 21 a. Internal grounding 22 b. 4-inch movement 23 c. Stainless steel/cast iron 24 H. Expansion Fittings: 25 1. Galvanized steel 26 2. 8-inch movement 27 3. Internal grounding 28 2.4 SOURCE QUALITY CONTROL [NOT USED] 29 PART 3 - EXECUTION 30 3.1 INSTALLERS [NOT USED] 31 3.2 EXAMINATION [NOT USED] 32 3.3 PREPARATION [NOT USED] 33 3.4 APPLICATION 34 A. Interface with Other Work 35 1. Coordinate the placement of conduit and related components with other trades and 36 existing installations. 37 26 05 33 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS Page 6 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 B. Unless specified in the Drawings or directed by the City, the conduit type installed with 1 respect to the location shall be as follows: 2 1. Underground, 18 inches or more cover: 3 a. Rigid PVC Schedule 40 or HDPE 4 2. Underground, less than 18 inches cover: 5 a. Rigid PVC Schedule 80 or HDPE 6 3. Exposed: 7 a. Rigid galvanized steel 8 4. Final connection to equipment subject to vibration: 9 a. Liquidtight Steel Flexible Metal Conduit 10 C. Box Applications 11 1. Furnish raceway junction, pull, and terminal boxes with NEMA ratings for the 12 location in which they are installed. 13 2. Exposed switch, receptacle, and lighting outlet boxes and conduit fittings shall be 14 galvanized steel. 15 3. Furnish boxes with factory mounting lugs. Drilling through the back of any box or 16 enclosure is prohibited. 17 D. Conduit Outlet Bodies Applications 18 1. Conduits up to and including 2-1/2 inches: 19 a. Conduit outlet bodies may be used, except where junction boxes are specified 20 in the Drawings. 21 2. Conduits larger than 2-1/2 inches: Use junction boxes. 22 E. Conduit Hub Applications 23 1. Unless specifically stated herein or specified in the Drawings, all raceways shall 24 terminate at an outlet with a conduit hub. 25 a. Locknut or double locknut terminations will not be permitted. 26 F. Insulated Grounding Bushing Applications 27 1. Use: Terminate raceways at bottom entry to pad-mounted electrical equipment or 28 switchgear, if there is no wall or floor pan on which to anchor or terminate the 29 raceway. 30 2. Other raceways: Terminate on enclosures with a conduit hub. 31 3. Grounding bushing caps: Remain on the bushing until the wire is ready to be 32 pulled. 33 G. Conduit Fittings Applications 34 1. Combination expansion deflection fittings: Install where conduits cross structure 35 expansion joints, on conduit transitions from underground to above ground, and 36 where installed in exposed conduit runs such that the distance between expansion-37 deflection fittings does not exceed 150 feet of conduit run. 38 2. Expansion fittings: Install in lieu of a combination expansion-deflection fitting, on 39 the exposed side of conduit transitions from underground to above ground, where 40 the earth has been disturbed to a depth of more than 10 feet. 41 H. Conduit Penetration Seals Applications 42 26 05 33 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS Page 7 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1. Conduit wall seals: Use where underground conduits penetrate walls or at other 1 locations specified in the Drawings. 2 2. Conduit sealing bushings: Use to seal conduit ends exposed to the weather and at 3 other locations specified in the Drawings. 4 I. Conduit Tag Applications 5 1. Tag all conduits within 1 foot of the entry of equipment, and all wall and floor 6 penetrations. 7 2. Tag all underground conduits and ducts at all locations exiting and entering from 8 underground, including manholes and handholes. 9 J. Raceway Installation 10 1. No conduit smaller than 1¼ inch electrical trade size. 11 2. No more than the equivalent of 3 - 90-degree bends in any 1 run. 12 3. Do not pull wire until the conduit system is complete in all details. 13 4. Install all underground raceways in accordance with Section 26 05 43. 14 5. Where raceways enter or leave the system, where the raceway begins or ends, or 15 where the system could be subjected to the entry of moisture, rain, or liquid of any 16 type, the raceway shall be tightly sealed using watertight sealant (Duxseal or equal) 17 at the higher elevation, both before and after the installation of cables, to eliminate 18 entry of water or moisture to the raceway system at any time. 19 a. Any damage to new or existing equipment due to the entrance of moisture from 20 unsealed raceways shall be corrected by complete replacement of such 21 equipment at no cost to the City. 22 b. Cleaning or drying of such damaged equipment will not be acceptable. 23 6. Conduit supports, other than for underground raceways 24 a. Space at intervals of 8 feet or less as required to obtain rigid construction. 25 7. Single conduits: 26 a. Support with 1-hole pipe clamps in combination with 1 screw back plates, to 27 raise conduits from the surface. 28 8. Multiple runs of conduits 29 a. Supported on trapeze type hangers with horizontal members and threaded 30 hanger rods not less than 3/8 inch in diameter. 31 9. Surface mounted panel boxes, junction boxes, and conduit 32 a. Supported by strut to provide a minimum of 1/2 inch clearance between wall 33 and equipment. 34 10. Conduit hangers 35 a. Attach to structural steel by means of beam or channel clamps. Use concrete 36 inserts of the spot type where attached to concrete surfaces. 37 11. Conduits on exposed work 38 a. Install at right angles to and parallel with the surrounding wall. 39 b. Conform to the form of the ceiling. 40 c. No diagonal runs. 41 d. Provide concentric bends in parallel conduit runs. 42 e. Install conduit perfectly straight and true. 43 26 05 33 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS Page 8 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 12. Conduits terminated into enclosures: Install perpendicular to the walls where 1 flexible liquidtight or rigid conduits are required. 2 a. Do not use short sealtight elbow fittings for such terminations, except for 3 connections to instrumentation transmitters where multiple penetrations are 4 required. 5 13. Use insulated throat grounding bushings for conduits containing equipment 6 grounding conductors and terminating in boxes. Connect grounding conductors to 7 the box. 8 14. Install conduits using threaded fittings. Do not use running threads. 9 15. PVC conduit 10 a. Use glued type conduit fittings. 11 16. HDPE conduit 12 a. Use fittings by same manufacturer as conduit. 13 17. Liquidtight flexible steel conduit 14 a. Primary and secondary of transformers 15 b. Generator terminations 16 c. Other equipment where vibration is present 17 d. Connections to instrumentation transmitters, where multiple penetrations are 18 required 19 e. Do not use in other locations. 20 f. Maximum length: Not greater than that of a factory manufactured long radius 21 elbow of the conduit size being used 22 g. Maximum bending radius shall be in accordance with NEC Chapter 9, Table 2. 23 h. Do not use BX or AC type prefabricated cables. 24 18. Conduits passing through openings in walls or floor slabs 25 a. Seal remaining openings against the passage of flame and smoke. 26 19. Conduit ends exposed to the weather or corrosive gases 27 a. Seal with conduit sealing bushings. 28 20. Raceways terminating in Control Panels or boxes containing electrical equipment 29 a. Do not install to enter from the top of the panel or box. 30 b. Seal with a watertight sealant: Duxseal or equal. 31 21. Conduit 32 a. The Contractor will be required to coordinate with all local utility companies, 33 long distance communication companies, City utilities, railroad companies, and 34 Dig Tess, if applicable, to ascertain exact locations of conflicting underground 35 services. 36 b. The location of conduits and ground boxes are diagrammatic only and may be 37 shifted by the City to accommodate field conditions. 38 c. The maximum allowable overcut shall be 1 inch (25 mm) in diameter for bores. 39 d. The vertical and horizontal tolerances shall not exceed 18 inches (457 mm) as 40 measured from the intended target point for bores. 41 e. The use of a pneumatically driven device for punching holes beneath the 42 pavement (commonly known as a "missile") will not be permitted. 43 f. Conduit installed for future use shall have a non-metallic, nylon type pull string 44 and shall be capped using standard weather tight conduit caps, as approved by 45 the City. 46 26 05 33 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS Page 9 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 g. The Contractor shall place duct seal or foam at the ends of all conduit where 1 conductors and/or cables are present. 2 h. New Conduit 3 1) All underground conduit shall be schedule 40 PVC conduit. 4 2) All conduit or raceways above ground shall be rigid metal. 5 3) All conduit and fittings shall be of the sizes and types specified in the 6 Drawings. 7 4) Each section of conduit shall bear evidence of approval by UL. 8 5) Conduit terminating in posts or pedestal bases shall not extend vertically 9 more than 3 inches above the concrete foundation. 10 6) Field bends in conduit shall have a minimum radius of 12 diameters of the 11 nominal size of the conduit. 12 7) Exposed vertical conduit shall be galvanized rigid metal and reamed, with 13 couplings made tight. PVC conduit shall be joined by the solvent-weld 14 method in accordance with the conduit manufacturer's recommendations. 15 8) No reducer couplings shall be used unless specified in the Drawings. 16 9) Conduit and fittings shall have burrs and rough places smoothed and shall 17 be clean and free of obstructions before the cable is installed. 18 10) Field cuts shall be made with a hacksaw only and shall be square and true 19 so the ends will butt or come together for the full diameter thereof. 20 a) In no case shall a cutting torch be used to cut or join conduit. 21 11) Slip joints or running threads will not be permitted for coupling conduit 22 unless approved by the City. 23 12) When a standard coupling cannot be used, an approved union coupling 24 shall be used and shall provide a water-tight coupling between the conduit. 25 13) Couplings shall be properly installed to bring their ends of connected 26 conduit together to produce a good, rigid connection throughout the entire 27 length of the conduit run. 28 14) Where the coating on a rigid metal conduit run has been damaged in 29 handling or installation, such damaged parts shall be thoroughly painted 30 with rust preventive paint. 31 15) Ends of conduits shall be capped or plugged until installation of the wire is 32 complete. 33 16) Upon request by the City, the Contractor shall draw a full-size metal wire 34 brush, attached by swivel joint to a pull tape, through the metal conduit to 35 ensure the conduit is clean and free from obstructions. 36 17) Conduits shall be placed in an open trench at a minimum 24 inches (612 37 mm) depth below the curb grade in the sidewalk areas, or 18 inches (450 38 mm) below the finished street grade in the street area. 39 18) Conduit placed for concrete encasement shall be secured and supported in 40 such a manner the alignment will not be disturbed during placement of the 41 concrete. 42 a) No concrete shall be placed until all conduit ends have been capped and 43 all box openings closed. 44 19) PVC conduit placed under existing pavement, sidewalks, and driveways, 45 shall be placed by first providing a void through which the PVC conduit 46 shall be inserted. 47 a) The void may be made by boring. 48 26 05 33 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS Page 10 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 b) Use of water or other fluids in connection with the boring operation 1 will be permitted only to lubricate cuttings. 2 c) Water jetting will not be permitted. 3 20) If, as determined by the City, placing of conduit by boring is impractical, 4 written permission may be granted by the Traffic Services Manager or 5 designee for the Contractor to cut the existing pavement. 6 21) Pits for boring shall not be closer than 2 feet (612 mm) to the back of the 7 curb or the outside edge of the shoulder. 8 a) The boring method used shall not interfere with the operation of streets, 9 highways, or other facilities, and shall not weaken or damage any 10 embankment structure or pavement. 11 22) Backfill - Compaction & Density Test for All Ditch lines 12 a) All ditch lines within paving areas of existing and proposed streets and 13 within 2 feet (600 mm) of the back of curb are to be mechanically 14 tamped. 15 b) All tamping is to be density controlled to 90 percent standard proctor 16 density at optimum moisture content and no greater than 5 percent 17 optimum or less than 2 percent below optimum. 18 c) All backfill material is to be select native material with 6-inch (150 19 mm) diameter clods and smaller. 20 d) It is permissible to put backfill in 6 inches to 8 inches (150 mm to 400 21 mm) lifts with densities being taken for each foot (300 mm) of 22 compacted material on offsetting stations of 50 feet (15.9 M). 23 23) Provide adequately bent conduit and properly excavate so as to prevent 24 damage to the conduit or conductor by a bend radius too short. 25 24) All conduit runs shall be continuous and of the same material (metal only 26 or PVC only). 27 25) Where tying into existing conduit, the Contractor must continue with the 28 same material (metal to metal or PVC to PVC). 29 26) Each length of galvanized rigid metal conduit, where used, shall be reamed 30 and threaded on each end and couplings shall be made up tight. 31 27) White-lead paint or equal shall be used on threads of all joints. 32 28) Metal conduit and fittings shall have burrs and rough places smoothed. 33 29) Where the coating on a metal conduit run has been damaged in handling or 34 installation, such damaged parts shall be thoroughly painted with rust 35 preventive paint. 36 i. Existing Conduit 37 1) Prior to pulling cable in existing underground conduit, the conduit shall be 38 cleaned with a mandrel or cylindrical wire brush and blown out with 39 compressed air. 40 2) If conduit appears to be blocked, the Contractor shall make an attempt to 41 clear the conduit by rodding, at no additional cost to the City. 42 3) If the existing conduit cannot be used, the Contractor may be required to 43 repair and/or replace this conduit as directed by the Engineer. 44 a) Repair of this conduit will be paid for as "Extra Work" on a Change 45 Order. 46 4) The City shall be notified prior to disconnection or removal of any existing 47 cable. 48 26 05 33 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS Page 11 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 22. Conduits from external sources entering or leaving a multiple compartment 1 enclosure 2 a. Stub up into the bottom horizontal wireway or other manufacturer designated 3 area, directly below the vertical section in which the conductors are to be 4 terminated. 5 23. Conduits entering from cable tray 6 a. Stub into the upper section. 7 24. Install conduit sealing and drain fittings in areas designated as NEMA 4X or 8 NEMA 7. 9 25. Conduit identification plates 10 a. Install on all power, instrumentation, alarm, and control conduits at each end of 11 the run and at intermediate junction boxes and manholes. 12 b. Install conduit plates before conductors are pulled into conduits. 13 c. Coordinate exact identification plate location with the City at the time of 14 installation to provide uniformity of placement and ease of reading. 15 26. Pull mandrels through all existing conduits to be reused and through all new 16 conduits 2 inches in diameter and larger prior to installing conductors. 17 27. Install 3/16-inch polypropylene pull lines in all new conduits noted as spares or 18 designated for future equipment. 19 28. Install conduit to drain away from the equipment served. If conduit drainage is not 20 possible, use conduit seals to plug the conduits at the point of attachment to the 21 equipment. 22 29. Route conduits to avoid crossing pipe shafts, access hatches, or vent duct openings, 23 present or future, in floor or ceiling construction. 24 30. Do not use running threads. 25 31. Conduits passing from heated to unheated spaces, exterior spaces, refrigerated 26 spaces, or cold air plenums 27 a. Seal with watertight sealant (Duxseal or equal). 28 32. Locate conduits a minimum of 3 inches from steam or hot water piping. 29 a. Where crossings are unavoidable, locate conduit at least 1 inch from the 30 covering of the pipe crossed. 31 33. Conduits terminating at a cable tray 32 a. Support independently from the cable tray. 33 b. Provide conduit support within 1-feet of the cable tray. 34 c. Weight of the conduit not supported by cable tray. 35 3.5 REPAIR [NOT USED] 36 3.6 RE-INSTALLATION [NOT USED] 37 3.7 FIELD QUALITY CONTROL [NOT USED] 38 3.8 SYSTEM STARTUP [NOT USED] 39 3.9 ADJUSTING [NOT USED] 40 3.10 CLEANING [NOT USED] 41 3.11 CLOSEOUT ACTIVITIES [NOT USED] 42 26 05 33 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS Page 12 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3.12 PROTECTION [NOT USED] 1 3.13 MAINTENANCE [NOT USED] 2 3.14 ATTACHMENTS [NOT USED] 3 END OF SECTION 4 5 Revision Log DATE NAME SUMMARY OF CHANGE 6 26 05 35 GROUND BOXES Page 1 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 SECTION 26 05 35 1 GROUND BOXES 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Ground Boxes 6 2. Remove Ground Boxes 7 B. Deviations from this City of Denton Standard Specification: 8 1. None. 9 C. Related Specification Sections include but are not limited to: 10 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 11 Contract. 12 2. Division 1 - General Requirements. 13 3. Section 26 05 33 – Raceway and Boxes. 14 1.2 PRICE AND PAYMENT PROCEDURES 15 A. Measurement and Payment 16 1. Furnish and Install Ground Boxes 17 a. Measurement 18 1) Measured per each ground box installed for: 19 a) Various sizes. 20 b) Various types. 21 b. Payment 22 1) The work performed and materials furnished in accordance with this Item 23 and measured as provided under “Measurement” will be paid for at the unit 24 price bid per each “Ground Box” installed for: 25 a) Various sizes. 26 b) Various types. 27 c. The price bid shall include: 28 a) Furnishing and installing Ground Boxes as specified in the Drawings 29 b) Excavation and backfill 30 c) Enclosures 31 d) Covers 32 e) Bolts 33 f) Gravel 34 g) Concrete apron, if required 35 2. Remove Ground Boxes 36 a. Measurement 37 1) Measured per each ground box removed for: 38 a) Various sizes. 39 b) Various types. 40 26 05 35 GROUND BOXES Page 2 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 b. Payment 1 1) The work performed and materials furnished in accordance with this Item 2 and measured as provided under “Measurement” will be paid for at the unit 3 price bid per each “Ground Box” removed for: 4 a) Various sizes. 5 b) Various types. 6 c. The price bid shall include: 7 1) Removing Ground Boxes as specified in the Drawings 8 2) Excavation and backfill 9 1.3 REFERENCES 10 A. Reference Standards 11 1. Reference standards cited in this Section refer to the current reference standard 12 published at the time of the latest revision date logged at the end of this Section 13 unless a date is specifically cited. 14 2. Texas Department of Transportation (TxDOT), Standard Specifications for 15 Construction and Maintenance of Highways, Streets, and Bridges: 16 a. Item 624, Ground Boxes. 17 b. Item 421, Hydraulic Cement Concrete. 18 c. Item 432, Riprap. 19 d. Item 440, Reinforcement for Concrete. 20 e. Item 618, Conduit. 21 f. Item 620, Electrical Conductors. 22 3. Texas Department of Transportation (TxDOT) Departmental Material 23 Specifications (DMS): 24 a. DMS-11070, Ground Boxes. 25 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 26 1.5 SUBMITTALS 27 A. Submittals shall be in accordance with Section 01 33 00. 28 B. All submittals shall be approved by the City prior to delivery. 29 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 30 A. Product Data Sheets are required for: 31 1. Ground boxes 32 1.7 CLOSEOUT SUBMITTALS [NOT USED] 33 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 34 1.9 QUALITY ASSURANCE [NOT USED] 35 1.10 DELIVERY, STORAGE, AND HANDLING 36 A. Storage and Handling Requirements 37 1. Secure and maintain a location to store the material in accordance with Section 01 38 66 00. 39 26 05 35 GROUND BOXES Page 3 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 1.11 FIELD CONDITIONS [NOT USED] 1 1.12 WARRANTY [NOT USED] 2 PART 2 - PRODUCTS 3 2.1 CITY-FURNISHED PRODUCTS [NOT USED] 4 2.2 MATERIALS 5 A. Materials 6 1. Traffic Signal Ground boxes shall be as follows: 7 a. Martin Enterprises or equal, size 24x36x24 (TxDOT Type D) 8 1) Provide fabricated precast polymer concrete ground boxes in accordance 9 with DMS-11070. 10 2) Ground boxes shall have bolted down covers. 11 3) Cast iron covers are not allowed. 12 4) Covers will clearly contain the words “TRAFFIC SIGNAL”. 13 2. Fiber Ground Boxes shall be as follows: 14 a. Martin Enterprises or equal, size 24x36x36 (TxDOT ITS) 15 1) Provide fabricated precast polymer concrete ground boxes in accordance 16 with DMS-11070. 17 2) Ground boxes shall have bolted down covers. 18 3) Cast iron covers are not allowed. 19 4) Covers will clearly contain the words “DANGER HIGH VOLTAGE 20 TRAFFIC SIGNAL”. 21 2.3 ACCESSORIES [NOT USED] 22 2.4 SOURCE QUALITY CONTROL [NOT USED] 23 PART 3 - EXECUTION 24 3.1 INSTALLERS [NOT USED] 25 3.2 EXAMINATION [NOT USED] 26 3.3 PREPARATION [NO USED] 27 3.4 INSTALLATION 28 A. Special Techniques 29 1. Use established industry and utility safety practices when installing or removing 30 ground boxes located near underground utilities. Consult with the appropriate utility 31 company before beginning work. 32 2. Fabricate and install ground boxes as specified in the Drawings. Install ground box 33 to approved line and grade. 34 3. Utilize precast concrete ground boxes in accordance with this and related Sections. 35 26 05 35 GROUND BOXES Page 4 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 4. Construct concrete aprons as specified in the Drawings and in accordance with 1 TxDOT Item 421. 2 5. A minimum gravel fill of 9 inches shall be placed under each ground box and a 3 concrete skirt installed around each ground box as specified in the Drawings. 4 6. Lube the bolts, clean out the cover rim, and clean the ground box inside and out 5 prior to final inspection. 6 7. Removal 7 a. Remove existing ground boxes and concrete aprons to at least 6 in. below the 8 conduit level. 9 b. Uncover conduit to a sufficient distance so 90 degree bends can be removed, 10 and conduit reconnected. 11 c. Clean the conduit in accordance with Section 26 05 33. 12 d. Replace conduit within 5 ft. of the ground box. 13 e. Remove old conductors and install new conductors as specified in the 14 Drawings. 15 f. Backfill area with material equal in composition and density to the surrounding 16 area. Replace surfacing material with similar material to an equivalent 17 condition. 18 3.5 REPAIR [NOT USED] 19 3.6 RE-INSTALLATION [NOT USED] 20 3.7 FIELD QUALITY CONTROL [NOT USED] 21 3.8 SYSTEM STARTUP [NOT USED] 22 3.9 ADJUSTING [NOT USED] 23 3.10 CLEANING [NOT USED] 24 3.11 CLOSEOUT ACTIVITIES [NOT USED] 25 3.12 PROTECTION [NOT USED] 26 3.13 MAINTENANCE [NOT USED] 27 3.14 ATTACHMENTS [NOT USED] 28 END OF SECTION 29 30 Revision Log DATE NAME SUMMARY OF CHANGE 31 31 10 00 SITE CLEARING Page 1 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 SECTION 31 10 00 1 SITE CLEARING 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Site Preparation 6 a. Preparing the right-of-way and designated easements for construction 7 operations by the removal and disposal of obstructions within the project limits. 8 b. Removing trees and shrubs. 9 c. Pruning trees and shrubs. 10 d. Tree protection fence 11 e. Trunk protection 12 B. Deviations from this City of Denton Standard Specification: 13 1. None. 14 C. Related Specification Sections include but are not limited to: 15 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 16 Contract. 17 2. Division 1 - General Requirements. 18 3. Section 02 41 13 – Selective Site Demolition. 19 4. Section 02 41 15 – Paving Removal. 20 5. Section 31 23 16 – Unclassified Excavation. 21 6. Section 34 71 13 – Traffic Control 22 1.2 PRICE AND PAYMENT PROCEDURES 23 A. Measurement and Payment 24 1. Site Preparation 25 a. Measurement 26 1) Measured per lump sum of Site Preparation within the project limits, when 27 specifically required by the Contract Documents. Otherwise this item is 28 considered subsidiary to the various items bid. 29 b. Payment 30 1) The work performed and materials furnished in accordance with this item 31 and measured as provided under “Measurement” will be paid for at the unit 32 price bid for lump sum for “Site Preparation.” 33 c. The price bid shall include: 34 1) Full compensation for Site Preparation as specified by the Drawings 35 2) Tools, equipment, and labor and incidentals needed to execute work 36 3) Sawing 37 4) Grading and backfilling of holes 38 5) Excavation 39 31 10 00 SITE CLEARING Page 2 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 6) Topsoil and sod limits of tree removal disturbance unless quantified 1 separately under another bid item 2 7) Tree and shrub protection for trees and shrubs to remain 3 8) Replace any tree designated to remain that is damaged during tree removal 4 9) Tree wound treatment material 5 10) Tree and shrub pruning 6 11) Disposal of debris, tree clippings, limbs, leaves, and pine needles removed 7 as part of pruning 8 12) Trunk Protection 9 a) Closed cell foam pad 10 b) Wood planks 11 c) Steel straps 12 13) Tree protection fence 13 a) Woven wire fence 14 b) T-Bar posts 15 c) One strand barbed wire fence 16 d) Tundra weight orange flagging 17 14) Remove, haul-off, and dispose of: 18 a) Trees, shrubbery, grass and all other vegetation not designated to 19 remain 20 b) Stumps, roots, brush, and logs 21 c) Abandoned utility pipes or conduits 22 d) Fence and fence posts if Fence Removal bid item is not used 23 e) Gravel, stone, or boulders, not including removal of gravel or stone 24 driveways, roads, or other driving surfaces. 25 f) Scrap metal 26 g) All rubbish or debris 27 h) All obstructions and objectionable material not specifically included in 28 another bid item 29 1.3 REFERENCES 30 A. Abbreviations and Acronyms 31 1. SWPPP – Storm Water Pollution Prevention Plan 32 2. MUTCD – Manual on Uniform Traffic Control Devices 33 3. pH – Potential of Hydrogen 34 4. ESA – Environmentally Sensitive Areas 35 B. Reference Standards 36 1. Reference standards cited in this Section refer to the current reference standard 37 published at the time of the latest revision date logged at the end of this Section 38 unless a date is specifically cited. 39 2. Tree Care Industry Association (TCIA) / American National Standards Institute 40 (ANSI): 41 a. A300, Tree, Shrub, and Other Woody Plant Management – Standard Practices 42 (Pruning). 43 3. National Arborist Association Pruning Standards 44 4. Texas Manual on Uniform Traffic Control Devices (TMUTCD). 45 31 10 00 SITE CLEARING Page 3 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 5. City of Denton Development Code 1 2 1.4 ADMINISTRATIVE REQUIREMENTS 3 A. Disposal Letter 4 1. Provide the City with a Disposal Letter in accordance with Division 01. 5 B. Permits 6 1. For commercial and residential construction, a Clear and Grade Permit is required 7 to be obtained from City. 8 a. No excavation or embankment activities will be allowed without an executed 9 construction contract and an assigned City inspector. 10 b. Remove and replace any embanked soils if excavation and/or embankment 11 activities are performed prior to an executed construction contract and an 12 assigned City inspector at no cost to the City. 13 2. Tree Removal Permit in accordance with the City of Denton Development Code is 14 required. 15 3. Tree Inventory Plan prepared in accordance with the City of Denton Development 16 Code or as specified in the Drawings. 17 a. Provide Tree Inventory Plan sufficient for the purposes of obtaining a Tree 18 Removal Permit. 19 1) If insufficient, provide a Tree Inventory Plan that has been prepared by an 20 arborist or a registered landscape architect. 21 b. Provide the City with the correct documents for obtaining the Tree Removal 22 Permit. 23 4. SWPPP – Provide a SWPPP in accordance with Section 01 57 13. 24 5. ESA Compliance Review – Provide tree protective fencing in accordance with 01 25 57 13. 26 C. Sequencing 27 1. Sidewalk Construction 28 a. Where existing sidewalks are to be closed during Paving Removal activities: 29 1) Utilize pedestrian/sidewalk detour route specified in the Drawings 30 a) If no detour route is provided, submit a pedestrian/sidewalk detour 31 route that has been signed and sealed by a registered professional 32 engineer to the City for review. 33 b. The pedestrian/sidewalk detour route will be subsidiary to pertinent Traffic 34 Control items included with the project. 35 c. Install all sidewalk detours and closures in accordance with the TMUTCD, 36 State, and local guidelines. 37 d. Provide any traffic control devices in accordance with Section 34 71 13. 38 D. Pre-Site Clearing Meeting 39 1. Hold a site clearing meeting prior to performing any tasks included under Site 40 Clearing with City and appropriate representatives. 41 2. Clearly mark all: 42 a. Trees and shrubs to remain 43 b. Trees and shrubs to remove 44 31 10 00 SITE CLEARING Page 4 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 c. Trees and shrubs to be pruned pre and post construction as specified in the 1 Drawings. 2 3. Have the SWPPP in place and inspected by Watershed Protection prior to Site 3 Clearing activities. 4 4. Review Tree Inventory Plan as prepared for Tree Removal Permit or in the 5 Drawings. 6 5. Confirm approval of the Tree Removal Permit. 7 6. Confirm trees and shrubs to be removed during pre-site clearing meeting 8 7. Confirm limits for Site Preparation during pre-site clearing meeting. 9 1.5 SUBMITTALS 10 A. Submittals shall be in accordance with Section 01 33 00. 11 B. All submittals shall be approved by the City prior to delivery. 12 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 13 A. Product Data: 14 1. Tree wound treatment material product data 15 B. Informational Submittal 16 1. Certificates 17 a. Certified Arborist 18 1) A company with a certified arborist is required when performing Tree and 19 Shrub Pruning. Provide the certificate of the employee(s) from the 20 company performing the pruning. 21 2. Equipment Information 22 a. Submittal for all major equipment to include: 23 1) Equipment name 24 2) Size 25 3) Intended use 26 1.7 CLOSEOUT SUBMITTALS [NOT USED] 27 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 28 1.9 QUALITY ASSURANCE 29 A. Certifications 30 1. Tree and Shrub Pruning 31 a. A company with a certified arborist is required. 32 b. Provide the certificate of the employee(s) from the company performing the 33 proposed pruning. 34 2. Tree Inventory Plan or Tree Removal Permit 35 a. A certified arborist or a registered landscape architect is required. 36 b. Provide the certificate or license information of the employee(s) from the 37 company preparing the plan and/or permit. 38 31 10 00 SITE CLEARING Page 5 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1 1.11 FIELD CONDITIONS 2 A. An ISA Certified Arborist is required to be on site during all pruning activities. 3 4 B. Avoid pruning between February and July. 5 1. When pruning activities need to occur between February and July, use an approved 6 wound treatment material. 7 1.12 WARRANTY [NOT USED] 8 PART 2 - PRODUCTS 9 2.1 CITY-SUPPLIED PRODUCTS [NOT USED] 10 2.2 PRODUCTS 11 A. Tree Wound Treatment 12 B. Root Barrier 13 1. Century Products, or 14 2. Approved equal. 15 2.3 ACCESSORIES [NOT USED] 16 2.4 SOURCE QUALITY CONTROL [NOT USED] 17 PART 3 - EXECUTION [NOT USED] 18 3.1 INSTALLERS [NOT USED] 19 3.2 EXAMINATION [NOT USED] 20 3.3 PREPARATION [NOT USED] 21 3.4 EXECUTION 22 A. General 23 1. Removal 24 a. Notify the City in writing when items required to be removed are: 25 1) Buried and not easily detected from the surface 26 2) Not specified in the Drawings. 27 2. Accept ownership and dispose of all materials removed within project limits. 28 3. Plug remaining ends of abandoned underground utilities over 3 inches in diameter 29 with concrete to form a tight closure. 30 4. Backfill, compact, and restore areas where items have been removed unless 31 otherwise specified in the Drawings. 32 5. Do not remove any trees unless directed by City or as specified in the Drawings. 33 31 10 00 SITE CLEARING Page 6 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 6. Dispose of all trees within 24 hours of removal. 1 7. Dispose of all material in accordance with Federal, State, and local laws and 2 regulations. 3 B. Hazardous Material 4 1. This item does not include the removal and disposal of hazardous material. 5 2. Notify the City immediately if any hazardous or questionable materials not shown 6 in the Drawings are encountered. 7 3. Test, remove, and dispose of hazardous material in accordance with Division 01. 8 C. Tree and Shrub Protection 9 1. General 10 a. Perform all excavation and earthwork within the drip line of trees by hand. 11 b. Do not park or service equipment, store materials, or disturb the root area under 12 the branches of trees designated to remain. 13 c. Protect trees designated to remain during construction activity from: 14 1) Compaction of root area by material storage 15 2) Compaction by driving or parking within the drip-line 16 3) Trunk damage by moving equipment, material storage, nailing, or bolting 17 4) Girding by tying constrictive material to trees 18 5) Poisoning by pouring solvents, gas, paint, etc. on or around trees and roots 19 6) Cutting of roots 1.5 inch in diameter or more. 20 7) Changes of soil pH factor by disposal of lime based material such as 21 concrete within the drip line. 22 8) Deformation or permanent damage to the trunk or limbs 23 d. Treatment of Damaged Limbs 24 1) Saw clean all damaged areas and damaged limbs over 1 inch in diameter 25 and treat with an approved wound treatment material. 26 2) Treat with an approved wound treatment within 20 minutes of damaging 27 the tree. 28 2. Tree Protection Fence 29 a. Install tree protection fence at the drip line around trees designated to be 30 protected in Drawings. 31 b. If field conditions do not allow fencing to be installed at the drip line, obtain 32 City approval to install tree protection fencing at a minimum of 8 feet from the 33 trunk. 34 c. Provide “Keep Out. Tree Preservation” signs for protected trees. 35 d. Use the following to construct the Tree Protection Fence unless otherwise 36 specified in Drawings 37 1) Woven wire fence installed with T-Bar posts 38 2) Space T-Bar posts at 10 feet on center 39 3) Place one strand barbed wire along the top of poses. 40 4) Tie tundra weight orange flagging that is 2 feet in length at 3 feet on center 41 along the woven wire. 42 e. Do not install mulch within 12 inches of tree trunk. 43 f. Maintain existing grade within the tree protection fence unless otherwise 44 specified in Drawings. 45 3. Trunk Protection 46 31 10 00 SITE CLEARING Page 7 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 a. Install Trunk Protection as specified in Drawings. 1 b. Use the following to construct the Trunk Protection unless otherwise specified 2 in Drawings 3 1) Closed cell foam pad around trunk 4 a) Extend the foam pad 6 inches above and 6 inches below the wood 5 planks. 6 2) 4-foot-long planks that are 4 inches wide and 2 inches thick. Staple planks 7 together using steel straps on top of the foam pad and around the trunk. 8 c. Mulch: 9 1) Provide a 2-foot-wide mulch barrier around the tree trunk. 10 d. Provide “Caution. Tree Protection Area” orange tape around protected tree 11 trunks. 12 D. Tree and Shrub Removal 13 1. Remove tree stumps: 14 a. To 12 inches or more below the finished grade when tree is outside of the limits 15 of additional construction activities 16 b. To natural ground when area will be covered by 3 feet or more of embankment 17 c. Completely remove all stumps and roots when the area will be used as borrow 18 or embankment within the project limits. 19 2. Backfill holes with acceptable material and compact flush with surrounding area. 20 3. Install top soil and sod within limits of tree and shrub removal unless topsoil and 21 sod will be installed as part of the project. 22 E. Tree and Shrub Pruning 23 1. Equipment: 24 a. Use a Vermeer V-1550 RC root pruner or equal to perform all root pruning 25 operations. 26 2. Use tree wound treatment when pruning trees or shrubs during the months of 27 February to July. 28 3. Perform all tree, shrub, and root pruning under the supervision of a certified 29 arborist. 30 4. Prune lower limbs to prevent breakage and to permit access by construction 31 machinery during grading, field/site preparation, and clearing and grubbing 32 operations. 33 5. Prune limbs in accordance with ANSI A300 and National Arborist Association 34 Pruning Standards. 35 6. Prune shade trees in accordance with Class IV National Arborist Association 36 Pruning Standards 37 7. Make cuts as close as possible to the trunk or parent limb without cutting into the 38 limb collar or leaving a protruding stub. 39 8. Remove suckers to the height of the lowest main branch. 40 9. Disinfect tools with 70 percent methyl alcohol, benzalkonium chloride, cholerine 41 solution, or other approved disinfectant prior to: 42 a. Pruning oak trees 43 b. Cutting any tree of different type than previous tree pruned 44 10. Tree pruning on 2-inch diameter or larger trees: 45 31 10 00 SITE CLEARING Page 8 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 a. Undercut one-third through the limb 8 to 12 inches from the main stem 1 b. Remove limb 4 to 6 inches outside the first cut. 2 c. Remove stub with an even flush cut so that the limb collar protrudes 3 approximately 0.5 inch 4 d. Do not allow limb to fall free if it could damage any other limbs or items 5 e. Treat exposed cuts with wound treatment within 20 minutes of the cut 6 3.5 REPAIR 7 A. Repair the following at no cost to the City if any damaged due to Site Clearing 8 activities: 9 1. Adjacent concrete or asphalt pavement 10 2. Adjacent sidewalk 11 3. Adjacent curb or curb and gutter 12 4. Subgrade or base material 13 5. Utility piping, structures, and appurtenances 14 6. Irrigation systems including but not limited to sprinkler heads, conduit, and pipe. 15 7. Landscape beds or planters 16 8. Decorative hardscape or landscape features 17 9. Retaining walls 18 10. Trees, shrubs, sodding, and topsoil 19 11. Erosion control devices and ESA fences 20 B. Tree Replacement 21 1. Replace any existing tree permanently damaged by construction activities at no cost 22 to the City. Replace tree with an equal or larger caliper tree. 23 3.6 RE-INSTALLATION [NOT USED] 24 3.7 FIELD QUALITY CONTROL [NOT USED] 25 3.8 SYSTEM STARTUP [NOT USED] 26 3.9 ADJUSTING [NOT USED] 27 3.10 CLEANING [NOT USED] 28 3.11 CLOSEOUT ACTIVITIES [NOT USED] 29 3.12 PROTECTION [NOT USED] 30 3.13 MAINTENANCE [NOT USED] 31 3.14 ATTACHMENTS [NOT USED] 32 33 34 35 31 10 00 SITE CLEARING Page 9 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised November 23, 2020 Effective July 1, 2024 END OF SECTION 1 2 Revision Log DATE NAME SUMMARY OF CHANGE 3 31 23 16 UNCLASSIFIED EXCAVATION Page 1 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 31 23 16 1 UNCLASSIFIED EXCAVATION 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Excavation for general site grading, street grading, and channel excavation. 6 B. Deviations from this City of Denton Standard Specification: 7 1. None. 8 C. Related Specification Sections include but are not limited to: 9 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 10 Contract. 11 2. Division 1 - General Requirements. 12 3. Section 02 41 13 – Selective Site Demolition. 13 4. Section 02 41 15 – Paving Removal. 14 5. Section 31 00 00 – Site Clearing. 15 6. Section 31 24 00 – Embankments. 16 7. Section 31 25 14 – Erosion and Sedimentation Controls. 17 1.2 PRICE AND PAYMENT PROCEDURES 18 A. Measurement and Payment 19 1. Unclassified Excavation 20 a. Measurement 21 1) Measured per cubic yard in its final position using the average end area 22 method of Excavation performed. Limits of measurement shown in the 23 Drawings. 24 b. Payment 25 1) The work performed and materials furnished in accordance with this item 26 and measured as provided under “Measurement” will be paid for at the unit 27 price bid per cubic yard for “Unclassified Excavation.” 28 c. The price bid shall include: 29 1) Shrinkage and/or swelling factors. Contractor is responsible for 30 determining factors and will not be compensated separately. 31 2) Excavation of all materials within excavation limits 32 3) Finishing parkways and medians 33 4) Excavation 34 5) Safety 35 6) Dewatering 36 7) Temporary drainage 37 8) Drying 38 9) Dust control 39 10) Reworking or replacing over excavated material in rock cuts 40 31 23 16 UNCLASSIFIED EXCAVATION Page 2 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 11) Placement 1 12) Compaction 2 13) Loading, hauling, and unloading 3 14) Disposal of unsuitable and excess materials not used elsewhere on the job 4 site 5 15) Finishing slopes, ditches, and channels 6 16) Maintenance blading or scarifying the ground surface 7 17) Equipment 8 18) Tools, equipment, and labor and incidentals needed to execute work 9 1.3 REFERENCES 10 A. Abbreviations and Acronyms 11 1. ROW: Right-of-Way 12 2. SWPPP: Storm Water Pollution Prevention Plan 13 B. Classification: 14 1. All authorized excavation is considered unclassified and involves removal of all 15 materials necessary to complete excavation of the site. Any reference to rock, 16 limestone, or other material on the Drawings and/or this specification is solely for 17 the City and the Contractor’s information and is not to be taken as an indication or 18 guarantee of classification of excavation. Payment will not be separated based on 19 classification of excavation unless expressly noted in the Drawings. 20 C. Reference Standards 21 1. Reference standards cited in this Section refer to the current reference standard 22 published at the time of the latest revision date logged at the end of this Section 23 unless a date is specifically cited. 24 a. Occupational Safety and Health Administration (OSHA): 25 1) Technical Manual Section 5. 26 2) Laws and Regulations Standard 1926, Safety and Health Regulations for 27 Construction. 28 b. City of Denton Development Code 29 1.4 ADMINISTRATIVE REQUIREMENTS 30 A. Permits 31 1. For commercial and residential construction, a Clear and Grade Permit is required. 32 a. No excavation or embankment activities will be allowed without an executed 33 construction contract and an assigned City inspector. 34 b. If the City determines or suspects excavation and/or embankment activities 35 have occurred prior to an executed contract and a City inspector assigned, all 36 construction activities could be suspended for at least 30 days pending the 37 results of the Pre-Earthwork meeting. 38 c. Any damages caused by early clearing and grading activities will be repaired at 39 no cost to the City. 40 B. Sequencing 41 1. Sidewalk Construction 42 a. Where existing sidewalks are to be closed during Paving Removal activities: 43 1) Utilize pedestrian/sidewalk detour route specified in the Drawings 44 31 23 16 UNCLASSIFIED EXCAVATION Page 3 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 a) If no detour route is provided, submit a pedestrian/sidewalk detour 1 route to City for review. 2 b. The pedestrian/sidewalk detour route will be subsidiary to pertinent Traffic 3 Control items included with the project. 4 c. Install all sidewalk detours and closures in accordance with the TMUTCD, 5 State, and local guidelines. 6 d. Provide any traffic control devices in accordance with Section 34 71 13. 7 C. Pre-Earthwork Meeting 8 1. Hold a Pre-Earthwork meeting at the same time as the Pre-Site Clearing Meeting. 9 Invite the City and appropriate representatives. 10 2. Clearly mark all the following items prior to the meeting: 11 a. All requirements for pre-site clearing meeting in accordance with 31 00 00. 12 b. Excavation limits 13 c. Cut/fill stakes 14 3. Submit means and methods for any rock cutting for review prior to the Pre-15 Earthwork Meeting. 16 4. Have the SWPPP in place and inspected by Watershed Protection in accordance 17 with Section 01 57 13 prior to excavation activities. 18 5. Determine any site-specific constraints or concerns prior to meeting for review. 19 1.5 SUBMITTALS 20 A. Submittals shall be in accordance with Section 01 33 00. 21 B. All submittals shall be approved by the City prior to delivery. 22 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 23 A. Informational Submittal 24 1. Equipment Information 25 a. Submittal for all major equipment to include: 26 1) Equipment name 27 2) Size 28 3) Intended use 29 2. Explosives, Blasting, and Rock Ripping 30 a. Submit storage locations and guidelines for using explosives. 31 b. For rock ripping and blasting, submit means and methods prior to Pre-32 Earthwork meeting for review. 33 c. Provide a list of personnel and employer who will be handling and using 34 explosives. Provide reference information including previous projects and 35 certifications proving explosive qualifications. 36 1.7 CLOSEOUT SUBMITTALS [NOT USED] 37 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 38 1.9 QUALITY ASSURANCE 39 A. Excavation Safety 40 1. Perform all excavations in a safe manner. 41 31 23 16 UNCLASSIFIED EXCAVATION Page 4 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2. Comply with the requirements of OSHA 29 CFR part 1926 and state requirements 1 when performing excavation, sheeting, and bracing. 2 1.10 DELIVERY, STORAGE, AND HANDLING 3 A. Storage and Handling Requirements 4 1. Secure and maintain a location to store the material prior to any excavation 5 activities beginning in accordance with Section 01 66 00. 6 2. Store excavated material to be used in other areas within the right-of-way (ROW) 7 or easement limits unless specifically disallowed in the Contract Documents. 8 a. If the Contract Documents do not allow the storage of excavated materials 9 within ROW or easements, secure and maintain an adequate storage location 10 off-site. 11 3. Store material and equipment in approved areas that are at least 30 feet from edge 12 of road limits. Install erosion control fencing around staging areas. 13 4. For urban areas with limited staging areas, designate offsite location for storing and 14 staging of materials and equipment. If this is not feasible, obtain approval from the 15 City to stage and store materials within project site. 16 5. All offsite staging areas to be in accordance with SWPPP and Watershed Protection 17 requirements. Offsite staging areas are considered part of the project site and will 18 need to be included with the SWPPP and Watershed Protection review. 19 6. If excavated material is stored off-site: 20 a. Provide an authorized letter from property owner approving the storage of 21 excavated materials. 22 b. Contractor is responsible for negotiating and coordinating with the property 23 owner. 24 c. The City is not responsible for establishing an off-site location. 25 d. The City is not liable for any damage resulting in off-site storage of excavated 26 materials. 27 7. Remove any excavated material not used in other areas within 48 hours of 28 excavation activities. 29 8. Do not block drainage ways, inlets, or driveways with excavation activities or 30 materials. 31 9. Provide erosion control in accordance with Section 31 25 14. 32 10. Store materials only in areas barricaded as provided in the traffic control plans or as 33 approved by the City if excavation is performed during active traffic. 34 11. Do not store material within the drip line of any tree or in landscaped areas. 35 12. Install tree protection in accordance with Section 31 10 00. 36 1.11 FIELD CONDITIONS 37 A. Existing Conditions 38 1. Any data provided regarding subsurface conditions of excavated material is not 39 intended as a representation or warranty of accuracy or continuity of proposed 40 excavated material. 41 2. The City is not responsible for interpretations or conclusions made by the 42 Contractor regarding the existing material to be excavated. 43 31 23 16 UNCLASSIFIED EXCAVATION Page 5 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1.12 WARRANTY [NOT USED] 1 PART 2 - PRODUCTS [NOT USED] 2 2.1 CITY-FURNISHED [NOT USED] 3 2.2 MATERIALS [NOT USED] 4 2.3 ACCESSORIES [NOT USED] 5 2.4 SOURCE QUALITY CONTROL [NOT USED] 6 PART 3 - EXECUTION 7 3.1 INSTALLERS [NOT USED] 8 3.2 EXAMINATION [NOT USED] 9 3.3 PREPARATION 10 A. Surface Preparation 11 1. If needed, provide temporary drainage to maintain positive drainage throughout 12 excavation activities. Any temporary drainage construction will be considered 13 subsidiary to excavation. 14 2. Dewatering and temporary storm drain activities will be considered part of the 15 SWPPP and Watershed Protection review and are required to be in accordance with 16 all requirements listed therein. 17 B. Demolition / Removal 18 1. Remove any existing pavement in accordance with Section 02 41 15 and 02 41 13. 19 3.4 EXCAVATION 20 A. General 21 1. Accept ownership of unsuitable or excess material and dispose of material off-site 22 in accordance with Federal, State, and local regulations. City is not responsible for 23 any disposed material or disposal activities. 24 2. Perform excavations while material to be excavated is dry aside from water applied 25 for dust control. 26 3. Contractor is responsible for the condition of the subgrade until the pavement is in 27 place. 28 4. Over-excavate and replace any portion of subgrade that becomes damaged or 29 unstable due to weather or construction activities prior to stabilizing the subgrade, 30 installing base material, or placing the pavement. This will be at no cost to the City. 31 5. Separate, remove, and dispose of unacceptable fill material as defined in Section 31 32 24 00 in accordance with Federal, State, and local regulations. 33 6. Maintain positive drainage in the excavated area to avoid damage to any existing 34 structures, proposed structures, and the roadway. 35 31 23 16 UNCLASSIFIED EXCAVATION Page 6 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 7. Shape slopes to avoid loosening material below or outside the proposed grade. 1 8. Remove and dispose of slides as directed. 2 3 B. Earth Cut 4 1. Excavate to finish grade or subgrade within acceptable subgrade tolerances. 5 2. Use approved embankment material compacted in accordance with 31 24 00 to 6 replace over-excavated material at no cost to City. Anticipated reasons for over 7 excavation can include, but are not limited to: 8 a. Excavation below an acceptable subgrade tolerance 9 b. Soils damaged due to weather or construction activities 10 3. Shape and compact subgrade in accordance with Section 31 24 00. 11 4. Subgrade Tolerances 12 a. Excavate to within 0.1 foot in all directions. 13 b. In areas of over excavation, provide fill material approved by the City at no cost 14 to City. 15 C. Rock Cut 16 1. Do not use dynamite or rock ripping within 500 feet of residences or commercial 17 development. 18 2. Blasting 19 a. Obtain City approval prior to any blasting. 20 b. Send notification at least 15 days in advance to all property owners within 21 1,000 feet of the blasting site. 22 c. Follow all OSHA regulations for explosives and blasting agents, including but 23 not limited to requirements in the OSHA Technical Manual Section 5, and 24 OSHA Laws and Regulations Standard 1926, Safety and Health Regulations for 25 Constructions. 26 d. Use only authorized workers with training, knowledge, or experience in the 27 field of transporting, storing, handling, and use of explosives. 28 1) Authorized workers also need to have working knowledge of State and 29 local laws and regulations pertaining to explosives. 30 e. If there are concerns that seismic vibrations may cause damage to adjacent 31 structures, provide: 32 1) A structural engineer to determine safe limits to prevent any damage. 33 2) All equipment, monitors, tools, and engineering design necessary at no cost 34 to the City. 35 f. Use blasting mats or other approved containment equipment to ensure that no 36 rocks or debris will be thrown into the air. 37 g. Comply with all City of Denton noise ordinances when blasting. 38 3. Excavate to finish grade or subgrade within acceptable subgrade tolerances. 39 4. For small pockets or thin layers, remove rock to at least 12-inches below subgrade. 40 5. Use approved embankment material compacted in accordance with 31 24 00 to 41 replace over excavated material at no cost to City. 42 D. Water for Construction 43 31 23 16 UNCLASSIFIED EXCAVATION Page 7 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1. Provide water as needed for site preparation, compaction, dust control, and other 1 incidental activities in accordance with local requirements in accordance with 2 Section 01 35 13. 3 4 E. Dewatering 5 1. Dewatering is subsidiary to excavation and includes the installation and operation 6 of all pumping, bailing, well-pointing, sumps, and draining necessary to keep the 7 excavation free from groundwater, seepage water, water from storm drains, 8 wastewater collection systems, ditches, creeks, ponds, and other sources. 9 2. Keep channels, trenches, pits, and other low point excavations drained as much as 10 practical during construction at no cost to the City. 11 3. Construction will not be permitted in standing water. 12 4. Conform all discharge from dewatering activities to Federal, State, and local 13 requirements in a manner approved by the City. 14 5. Control outlet velocities from dewatering discharges to prevent erosion. 15 F. Excavated Material 16 1. Maintain safe and convenient access to private and public properties adjacent to 17 excavation activities unless specified in the Drawings. Obtain approval from the 18 City for maintenance of access methods. 19 2. Acceptable fill material may be used for embankment in accordance with 31 24 00. 20 3. Stockpile acceptable excavated materials on-site in accordance with Sections 31 10 21 00 and 31 24 00. Proper erosion control and BMPs to be utilized in accordance with 22 the Drawings, local guidelines, and approved by the City. 23 G. Methods of Excavation 24 1. Submit means and methods for review by the City prior for any method of 25 excavation that is not using traditional excavation methods. 26 2. Comply with all Federal, State, and local regulations when developing and 27 submitting for approval any alternative method. 28 3. If an alternative method is requested and approved after contract execution, perform 29 excavation at no additional cost to the City beyond the stated excavation unit price 30 in the bid form. 31 3.5 REPAIR 32 A. Repair the following at no cost to the City if any damage is caused due to excavation 33 activities: 34 1. Adjacent concrete or asphalt pavement to remain 35 2. Adjacent sidewalk to remain 36 3. Adjacent curb or curb and gutter to remain 37 4. Adjacent subgrade or base material to remain 38 5. Utility piping, structures, and appurtenances 39 6. Irrigation systems including but not limited to sprinkler heads, conduit, and pipe. 40 7. Landscape beds or planters 41 8. Decorative hardscape or landscape features 42 31 23 16 UNCLASSIFIED EXCAVATION Page 8 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 9. Retaining walls 1 3.6 RE-INSTALLATION [NOT USED] 2 3.7 SITE QUALITY CONTROL [NOT USED] 3 3.8 SYSTEM STARTUP [NOT USED] 4 3.9 ADJUSTING [NOT USED] 5 3.10 CLEANING [NOT USED] 6 3.11 CLOSEOUT ACTIVITIES [NOT USED] 7 3.12 PROTECTION [NOT USED] 8 3.13 MAINTENANCE [NOT USED] 9 3.14 ATTACHMENTS [NOT USED] 10 END OF SECTION 11 12 Revision Log DATE NAME SUMMARY OF CHANGE 13 31 24 00 EMBANKMENT Page 1 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 SECTION 31 24 00 1 EMBANKMENT 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Furnishing, placing, and compacting approved soils for construction. 6 B. Deviations from this City of Denton Standard Specification: 7 1. None. 8 C. Related Specification Sections include but are not limited to: 9 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 10 Contract. 11 2. Division 1 - General Requirements. 12 3. Section 31 10 00 – Site Clearing. 13 4. Section 31 25 14 – Erosion and Sedimentation Controls. 14 1.2 PRICE AND PAYMENT PROCEDURES 15 A. Measurement and Payment 16 1. Embankment 17 a. Measurement 18 1) Measured per cubic yard in its final position using the average end area 19 method of Embankment performed. Limits of measurement shown in the 20 Drawings. 21 b. Payment 22 1) The work performed in accordance with this item and measured as 23 provided under “Measurement” will be paid for at the unit price bid per 24 cubic yard for “Embankment.” 25 c. The price bid shall include: 26 1) Transporting or hauling material 27 2) Placing, compacting, and finishing Embankment 28 3) Construction Water 29 4) Dust Control 30 5) Proof Rolling 31 6) Disposal of excess materials 32 7) Reworking or replacement of undercut material 33 2. Select Fill Embankment 34 a. Measurement 35 1) Measured cubic yard in its final position using the average end area method 36 of Select Fill Embankment performed. Limits of measurement shown in the 37 Drawings. 38 39 31 24 00 EMBANKMENT Page 2 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 b. Payment 1 1) The work performed in accordance with this item and measured as 2 provided under “Measurement” will be paid for at the unit price bid per 3 cubic yard for “Select Fill Embankment”. 4 c. The price bid shall include: 5 1) Transporting or hauling material 6 2) Placing, compacting, and finishing Embankment 7 3) Construction Water 8 4) Dust Control 9 5) Clean-up 10 6) Proof Rolling 11 7) Disposal of excess materials 12 8) Reworking or replacement of undercut material 13 1.3 REFERENCES 14 A. Reference Standards 15 1. Reference standards cited in this Section refer to the current reference standard 16 published at the time of the latest revision date logged at the end of this Section 17 unless a date is specifically cited. 18 2. ASTM Standards: 19 a. D2487, Standard Practice for Classification of Soils for Engineering Purposes 20 (Unified Soil Classification System). 21 b. D4318, Test Procedure for Determining Liquid Limit, Plastic Limit, and 22 Plasticity Index of Soils. 23 c. D698, Standard Test Methods for Laboratory Compaction Characteristics of 24 Soil Using Standard Effort. 25 3. TEX-115-E, FIELD METHOD FOR DETERMINING IN-PLACE DENSITY OF 26 SOILS AND BASE MATERIALS 27 1.4 ADMINISTRATIVE REQUIREMENTS 28 A. Permits 29 1. For commercial and residential construction, a Clear and Grade Permit is required. 30 a. No excavation or embankment activities will be allowed without an executed 31 construction contract and an assigned City inspector. 32 b. Any excavation or embankment activities performed prior to an executed 33 construction contract and an assigned City inspector is subject to additional 34 testing, compaction, and site requirements at no cost to the City. 35 B. Sequencing 36 1. Install all erosion control measures in accordance with Section 31 25 14 prior to 37 commencing any earthwork activities. 38 2. Complete all site clearing in accordance with Section 31 10 00 prior to commencing 39 any earthwork activities. 40 C. Pre-Earthwork Meeting 41 1. A Pre-Earthwork Meeting is not required for Capital Improvement projects. 42 2. Hold a Pre-Earthwork meeting at the same time as the Pre-Site Clearing Meeting. 43 Invite the City and appropriate representatives. 44 45 31 24 00 EMBANKMENT Page 3 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 3. Clearly mark all the following items prior to the meeting: 1 a. All requirements for pre-site clearing meeting in accordance with 31 10 00. 2 b. Excavation limits 3 c. Cut/fill stakes 4 4. Have the SWPPP in place and inspected by Watershed Protection in accordance 5 with Section 01 57 13 prior to Excavation activities. 6 5. Determine any site-specific constraints or concerns prior to meeting for review. 7 1.5 SUBMITTALS 8 A. Submittals shall be in accordance with Section 01 33 00. 9 B. All submittals shall be approved by the City prior to commencement of any lime 10 treating activities. 11 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 12 A. Information Submittal 13 1. Equipment Information 14 a. Submittal for all major equipment to include: 15 1) Equipment name 16 2) Size 17 3) Intended use 18 1.7 CLOSEOUT SUBMITTALS 19 A.Test and Evaluation Reports 20 1. All test reports generated during testing. 21 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 22 1.9 QUALITY ASSURANCE [NOT USED] 23 1.10 DELIVERY, STORAGE, AND HANDLING 24 A. Storage and Handling Requirements 25 1. Secure and maintain a location to store the material in accordance with Section 01 26 66 00. 27 2. Within Existing Rights-of-Way (ROW) 28 a. Store soil within existing ROW, easements, or temporary construction 29 easements, unless specifically disallowed in the Contract Documents. 30 b. Do not block drainage ways, inlets, or driveways. 31 c. When the Work is performed in active traffic areas, store materials only in 32 areas barricaded as provided in the traffic control plans. 33 d. In non-paved areas, do not store material on the root zone of any trees or in 34 landscaped areas. 35 3. Designated Storage Areas 36 a. If the Contract Documents do not allow the storage within the ROW, easement 37 or temporary construction easement, secure and maintain an adequate storage 38 location. 39 b. Provide an affidavit verifying rights have been secured to store the materials on 40 private property. 41 31 24 00 EMBANKMENT Page 4 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 c. Do not block drainage ways. 1 1.11 FIELD CONDITIONS 2 A. Ambient Conditions 3 1. Surface temperature must be at least 40°F and the ambient temperature must be 4 45°F and rising. 5 2. Do not install embankment during or shortly after rain events which prevent proper 6 work placement of the material and compaction. 7 a. Prior to resuming compaction operations: 8 1) Let soil dry to optimal density. 9 2) Remove muddy material off the surface to expose firm and compacted 10 materials. 11 1.12 WARRANTY [NOT USED] 12 PART 2 - PRODUCTS 13 2.1 CITY-FURNISHED PRODUCTS [NOT USED] 14 2.2 MATERIALS 15 A. General 16 1. Furnish material capable of forming a stable embankment. 17 2. Furnish material free from trees, stumps, roots, vegetation, or other deleterious 18 materials. 19 B. Acceptable Fill Material 20 1. In-situ or imported soils classified as CL, CH, SC, or GC in accordance with ASTM 21 D2487. 22 2. Free from deleterious materials, boulders over 6 inches in size, shale and organics. 23 3. Can be placed free from voids. 24 4. Has 20 percent passing the number 200 sieve. 25 5. Meets the requirements of Table 1. 26 Table 1 – Acceptable Fill Material Requirements 27 Property Test Method Specification Limit Liquid Limit (LL) Tex-104-E ≤ 50 Plasticity Index (PI) Tex-106-E ≤ 35 Sulfate Limit Tex-145-E ≤ 3000 ppm Bar Linear Shrinkage Tex-107-E ≥ 2 C. Blended Fill Material 28 1. In-situ soils classified as SP, SM, GP, or GM in accordance with ASTM D2487. 29 2. Blended with in-situ or imported Acceptable Fill material in accordance with the 30 requirements of this Section. 31 31 24 00 EMBANKMENT Page 5 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 3. Free from deleterious materials, boulders over 6 inches in size, shale and organics. 1 4. Has 20 percent passing the number 200 sieve. 2 5. Final blended product meets the requirements of Table 1. 3 D. Unacceptable Fill Material 4 1. In-situ soils classified as ML, MH, PT, OL, or OH in accordance with ASTM 5 D2487 6 E. Select Fill Material 7 1. Classified as SC or CL in accordance with ASTM D2487 8 2. Free from deleterious materials, boulders over 6 inches in size, shale and organics. 9 3. Can be placed free from voids. 10 4. Has 20 percent passing the number 200 sieve. 11 5. Meets the requirements of Table 2. 12 13 Table 2 – Select Fill Material Requirements 14 Property Test Method Specification Limit Liquid Limit (LL) Tex-104-E ≤ 35 Plasticity Index (PI) Tex-106-E 8< PI ≤ 20 Sulfate Limit Tex-145-E ≤ 2000 ppm Bar Linear Shrinkage Tex-107-E ≥ 2 15 2.3 ACCESSORIES [NOT USED] 16 2.4 SOURCE QUALITY CONTROL 17 A. Borrow material shall be tested prior to delivery to the Site. 18 1. Provide Proctor Test results, Gradation, and Atterberg Limits for Borrow material 19 from each source. 20 a. All testing listed above shall be performed in accordance with ASTM D698, 21 D6913, and D4318 respectively. 22 PART 3 - EXECUTION 23 3.1 INSTALLERS [NOT USED] 24 3.2 EXAMINATION [NOT USED] 25 3.3 PREPARATION 26 A. Protection of In-Place Conditions 27 1. Pavement 28 a. Conduct activities in such a way that does not damage existing pavement 29 designated to remain. 30 31 24 00 EMBANKMENT Page 6 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 b. Repair or replace any pavement damaged due to the negligence of the 1 contractor outside the limits designated for pavement removal at no additional 2 cost. 3 2. Trees 4 a. Flag and protect all trees designated to remain in accordance with Section 31 10 5 00. 6 b. Conduct embankments in a manner such that there is no damage to the tree 7 canopy. 8 c. Prune or trim tree limbs as specified in the Drawings or as directed by City. 9 1) Pruning or trimming may only be accomplished with equipment 10 specifically designed for tree pruning or trimming. 11 3. Above ground Structures 12 a. Protect all above ground structures adjacent to the construction. 13 B. Surface Preparation 14 1. Backfill stump holes or other small incidental excavations due to site clearing with 15 material of same properties as in-situ material. 16 2. Scarify base soil surface on which the embankment will be constructed to a 17 minimum depth of 6 inches. 18 3. Bench slopes before placing new material. 19 3.4 EMBANKMENT 20 A. General 21 1. Provide material type as specified in the Drawings. 22 2. Begin filling in the lowest section or the toe of the work area. 23 3. When fill is placed directly or upon older fill, remove debris and any loose material 24 and proof roll existing surface. 25 4. After spreading the loose lifts to required thickness and adjusting its moisture 26 content as necessary, simultaneously recompact scarified material with the placed 27 embankment material. 28 5. Compact material in loose lifts no greater than 8 inches. 29 6. Roll with enough passes to achieve the minimum required compaction. 30 7. Provide water sprinkled as necessary to achieve required moisture levels for 31 specified compaction. 32 8. Do not add additional lifts until the entire previous lift is properly compacted. 33 B. Surface Water Control 34 1. Grade surface horizontally but provide with sufficient longitudinal and transverse 35 slope to allow for runoff of surface water from every point. 36 2. Conduct fills so no obstruction to drainage from any other sections of fill is created. 37 3. Install temporary dewatering sumps in low areas during filling where excess 38 amounts of runoff collect. 39 4. Compact uniformly throughout. Keep surfaces of fill reasonably smooth and free 40 from humps and hollows that would prevent proper uniform compaction. 41 C. Earth Embankments 42 31 24 00 EMBANKMENT Page 7 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 1. Construct embankments in successive layers, evenly distributing materials in 1 lengths suited for sprinkling and rolling. 2 2. Move the material dumped in piles or windrows by blading or by similar methods 3 and incorporate it into uniform layers. 4 3. Construct embankments in layers approximately parallel to the finished grade of the 5 street. 6 4. Featheredge or mix abutting layers of dissimilar material for at least 100 feet to 7 ensure no abrupt changes in the material. 8 5. Break down clods or lumps of material and mix embankment until a uniform 9 material is attained. 10 6. Establish grade and shape to the typical sections specified in the Drawings. 11 7. Maintain finished sections of embankment to the grade and compaction 12 requirements until the project is accepted. 13 D. Rock Embankments 14 1. Rock Embankments for roadways are only allowed when specified in the Drawings. 15 2. Construct rock embankments in successive layers for the full width of the roadway 16 cross-section with a depth of 18 inches or less. 17 3. The layer depth for large rock sizes shall not exceed a depth of 18 inches in any 18 case. 19 4. Fill voids created by the large stone matrix with smaller stones during the 20 placement and filling operations. 21 5. Ensure the depth of the embankment layer is greater than the maximum dimension 22 of any rock. 23 6. Do not place rock greater than 18 inches in its maximum dimension. 24 7. Do not place rock embankments in any location where future utilities are 25 anticipated. 26 8. Construct the final layer with graded material so the density and uniformity is in 27 accordance with compaction requirements. 28 E. Density Control 29 1. Determine maximum dry density and moisture content using ASTM D698 and 30 submit moisture-density curves to City for review. 31 2. Compact each lift to meet the following requirements: 32 a. For soils with a PI less than 35, compact to 98% of maximum dry density, plus 33 or minus 2%. 34 b. For soils with a PI greater than 35, compact to at least 98% of maximum dry 35 density. 36 F. Maintenance of Moisture and Reworking 37 1. Maintain the density and moisture content once all requirements are met. 38 2. For soils with a PI greater than 15, maintain the moisture content no lower than 4 39 percentage points below optimum. 40 3. Rework the material to obtain specified compaction when the material loses the 41 required stability, density, moisture, or finish. 42 31 24 00 EMBANKMENT Page 8 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 4. Alter the compaction methods and procedures on subsequent work to obtain 1 specified density as directed by City. 2 3.5 REPAIR 3 A. Repair the following at no cost to the City if any damage is caused due to Embankment 4 activities: 5 1. Adjacent concrete or asphalt pavement to remain 6 2. Adjacent sidewalk to remain 7 3. Adjacent curb or curb and gutter to remain 8 4. Adjacent subgrade or base material to remain 9 5. Utility pipes 10 6. Irrigation systems including but not limited to sprinkler heads, conduit, and pipe. 11 7. Landscape beds or planters 12 8. Decorative hardscape or landscape features 13 9. Retaining walls 14 3.6 RE-INSTALLATION [NOT USED] 15 3.7 FIELD QUALITY CONTROL 16 A. Field Tests and Inspections 17 1. Proctors 18 a. Perform Proctor Tests in accordance with ASTM D698. 19 b. Notify the City if the characteristic of the soil changes. 20 c. Perform new Proctors for varying soils: 21 1) When indicated in the geotechnical investigation in the Appendix 22 2) If notified by the Engineer 23 3) At the convenience of the City 24 d. For Embankments where different soil types are present and are blended, the 25 Proctors shall be based on the mixture of those soils. 26 2. Proof Rolling 27 a. City must be on-site during proof rolling operations. 28 b. Make at least two passes with the proof roller, offsetting each trip by at most 29 one tire width. 30 c. Correct areas of rutting or pumping and unstable or non-uniform areas in 31 accordance with this Section. 32 3. Density Testing of Embankments 33 a. Density Testing shall be in accordance with ASTM D6938. 34 b. City must be on site during density testing. 35 c. For Embankments under future pavement: 36 1) Perform density testing twice per working day when compaction operations 37 are being conducted. 38 2) Measure density every 100’ along corridor. 39 3) City to determine density testing locations. 40 d. For Embankments not under future pavement or structures: 41 1) The City will perform density testing once per working day when 42 compaction operations are being conducted. 43 31 24 00 EMBANKMENT Page 9 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 2) Measure density every 250’ along embankment. 1 3) City to determine density testing locations. 2 e. Test reports shall include: 3 1) Location of test by station number 4 2) Time and date of test 5 3) Depth of testing 6 4) Field moisture 7 5) Dry density 8 6) Proctor identifier 9 7) Percent Proctor Density 10 B. Non-Conforming Work 11 1. All non-conforming work shall be removed and replaced at no additional cost to the 12 City. 13 3.8 SYSTEM STARTUP [NOT USED] 14 3.9 ADJUSTING [NOT USED] 15 3.10 CLEANING [NOT USED] 16 3.11 CLOSEOUT ACTIVITIES [NOT USED] 17 3.12 PROTECTION [NOT USED] 18 3.13 MAINTENANCE [NOT USED] 19 3.14 ATTACHMENTS [NOT USED] 20 END OF SECTION 21 22 Revision Log DATE NAME SUMMARY OF CHANGE 6/14/2024 Added TXDOT reference standard TEX-115-E 6/14/2024 Excluded shale material from all backfill options 23 31 25 14 EROSION AND SEDIMENT CONTROL Page 1 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 SECTION 31 25 14 1 EROSION AND SEDIMENT CONTROL 2 3 PART 1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Installation and maintenance of temporary control measures necessary to prevent 7 and control soil erosion, sedimentation, and water pollution. 8 2. Preparation and implementation of Contractor produced Erosion Control Plan. 9 B. Deviations from this City of Denton Standard Specification: 10 1. None. 11 C. Related Specification Sections include but are not limited to: 12 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 13 Contract. 14 2. Division 1 - General Requirements. 15 3. Section 32 05 26 – Aggregates for Exterior Improvements. 16 1.2 PRICE AND PAYMENT PROCEDURES 17 A. Measurement and Payment 18 1. Silt Fence 19 a. Measurement 20 1) Measured per linear foot of Silt Fence installed. 21 b. Payment 22 1) The work performed and materials furnished in accordance with this item 23 and measured as provided under “Measurement” will be paid for at the unit 24 price bid per linear foot for “Silt Fence” installed. 25 c. The price bid shall include: 26 1) Furnishing and installing Silt Fence as specified by the Drawings 27 2) Posts 28 3) Filter fabric 29 4) Net reinforcement 30 5) Fasteners 31 6) Stone overflows 32 7) Safety caps 33 8) Cleaning 34 9) Disposal of silt 35 10) Repair of damaged Silt Fence 36 2. Check Dam 37 a. Measurement 38 1) Measured per linear foot of Check Dam installed. 39 b. Payment 40 31 25 14 EROSION AND SEDIMENT CONTROL Page 2 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 1) The work performed and materials furnished in accordance with this item 1 and measured as provided under “Measurement” will be paid for at the unit 2 price bid per linear foot for “Check Dam” installed. 3 c. The price bid shall include: 4 1) Furnishing and installing Check Dam as specified by the Drawings 5 2) Aggregate, wire reinforcement, and filter fabric 6 3) Excavation 7 4) Loading, unloading, hauling, and storing 8 5) Cleaning 9 6) Disposal of silt 10 7) Repair of damaged Check Dam 11 3. Organic Filter Tube 12 a. Measurement 13 1) Measured per linear foot of Organic Filter Tube installed. 14 b. Payment 15 1) The work performed and materials furnished in accordance with this item 16 and measured as provided under “Measurement” will be paid for at the unit 17 price bid per linear foot for “Organic Filter Tube” installed. 18 c. The price bid shall include: 19 1) Furnishing and installing Organic Filter Tube as specified by the Drawings 20 2) Containment mesh 21 3) Core material 22 4) Posts 23 5) Rock bags 24 6) Cleaning 25 7) Disposal of silt 26 8) Repair of damaged Organic Filter Tube 27 4. Inlet Protection 28 a. Measurement 29 1) Measured per each of Inlet Protection installed. 30 b. Payment 31 1) The work performed and materials furnished in accordance with this item 32 and measured as provided under “Measurement” will be paid for at the unit 33 price bid per each for “Inlet Protection” installed. 34 c. The price bid shall include: 35 1) Furnishing and installing Inlet Protection as specified by the Drawings 36 2) All items pertaining to hog wire for erosion control as needed 37 3) Loading, unloading, hauling, and storing 38 4) Cleaning 39 5) Disposal of silt 40 6) Repair of damaged Inlet Protection items 41 5. Erosion Control Blanket 42 a. Measurement 43 1) Measured per square yard of Erosion Control Blanket installed. 44 b. Payment 45 1) The work performed and materials furnished in accordance with this item 46 and measured as provided under “Measurement” will be paid for at the unit 47 price bid per square yard for “Erosion Control Blanket” installed. 48 31 25 14 EROSION AND SEDIMENT CONTROL Page 3 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 c. The price bid shall include: 1 1) Furnishing and installing Erosion Control Blanket as specified by the 2 Drawings 3 2) Blanket and staples 4 3) Loading, unloading, hauling, and storing 5 4) Cleaning 6 5) Disposal of silt 7 6) Repair of damaged Erosion Control Blanket 8 6. Stabilized Construction Exit 9 a. Measurement 10 1) This item is considered subsidiary to the various items bid. 11 b. Payment 12 1) The work performed and the materials furnished in accordance with this 13 item are subsidiary to the various items bid and no other compensation will 14 be allowed. 15 7. Mulching 16 a. Measurement 17 1) Measured square yard of Mulching installed. 18 b. Payment 19 1) The work performed and materials furnished in accordance with this item 20 and measured as provided under “Measurement” will be paid for at the unit 21 price bid per square yard for “Mulching” installed. 22 c. The price bid shall include: 23 1) Furnishing and installing Mulching as specified by the Drawings 24 2) Loading, unloading, hauling, and storing 25 8. Pipe Inlet Sediment Trap 26 a. Measurement 27 1) Measured per each Pipe Inlet Sediment Trap installed. 28 b. Payment 29 1) The work performed and materials furnished in accordance with this item 30 and measured as provided under “Measurement” will be paid for at the unit 31 price bid per each for “Pipe Inlet Sediment Trap” installed. 32 c. The price bid shall include: 33 1) Furnishing and installing Pipe Inlet Sediment Trap as specified by the 34 Drawings 35 2) Filter stone 36 3) Loading, unloading, hauling, and storing 37 4) Cleaning 38 5) Disposal of silt 39 6) Repair of damaged Pipe Inlet Sediment Traps 40 9. Stone Outlet Sediment Trap 41 a. Measurement 42 1) Measured per each Stone Outlet Sediment Trap installed. 43 b. Payment 44 1) The work performed and materials furnished in accordance with this item 45 and measured as provided under “Measurement” will be paid for at the unit 46 price bid per each for “Stone Outlet Sediment Trap” installed. 47 c. The price bid shall include: 48 31 25 14 EROSION AND SEDIMENT CONTROL Page 4 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 1) Furnishing and installing Stone Outlet Sediment Trap as specified by the 1 Drawings 2 2) Filter stone 3 3) Loading, unloading, hauling, and storing 4 4) Cleaning 5 5) Disposal of silt 6 6) Repair of damaged Stone Outlet Sediment Traps 7 10. Turf Reinforcement Mat 8 a. Measurement 9 1) Measured square yard of Turf Reinforcement Mat installed. 10 b. Payment 11 1) The work performed and materials furnished in accordance with this item 12 and measured as provided under “Measurement” will be paid for at the unit 13 price bid per square yard for “Turf Reinforcement Mat” installed. 14 c. The price bid shall include: 15 1) Furnishing and installing Turf Reinforcement Mat as specified by the 16 Drawings 17 2) Loading, unloading, hauling, and storing 18 3) Cleaning 19 4) Disposal of silt 20 5) Repair of damaged Pipe Inlet Sediment Traps items 21 11. Dewatering Controls 22 a. Measurement 23 1) This item is considered subsidiary to the various items bid. 24 b. Payment 25 1) The work performed and the materials furnished in accordance with this 26 item are subsidiary to the various items bid and no other compensation will 27 be allowed. 28 12. Stormwater Pollution Prevention Device Installation 29 a. Measurement 30 1) Measurement for this item shall be by lump sum. 31 b. Payment 32 1) The work performed and materials furnished in accordance with this item 33 shall be paid for at the lump sum price bid for all “Stormwater Pollution 34 Prevention Device Installation”. 35 c. The price bid shall include: 36 1) Furnishing and installing all items under Stormwater Pollution Prevention 37 Device Installation as specified by the Drawings 38 2) Excavation 39 3) Loading, unloading, hauling, and storing 40 4) Cleaning 41 5) Disposal of silt 42 6) Repair of damaged Storm Water Pollution Prevention Devices 43 13. Remove Stormwater Pollution Prevention Devices 44 a. Measurement 45 1) Measurement for this item shall be by lump sum. 46 b. Payment 47 31 25 14 EROSION AND SEDIMENT CONTROL Page 5 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 1) The work performed and materials furnished in accordance with this item 1 shall be paid for at the lump sum price bid for all “Remove Stormwater 2 Pollution Prevention Devices.” 3 c. The price bid shall include: 4 1) Removing all items previously installed as part of the Stormwater Pollution 5 Prevention Plan as specified by the Drawings 6 2) Loading, unloading, and hauling 7 3) Cleaning 8 4) Disposal of silt 9 14. Erosion Control Plan Preparation 10 a. Measurement 11 1) Measurement for this item shall be by lump sum. 12 b. Payment 13 1) The work performed in accordance with this item shall be paid for at the 14 lump sum price bid for all “Erosion Control Plan Preparation.” 15 c. The price bid shall include: 16 1) Creation, submittal and approval of an erosion control plan as specified by 17 the Drawings 18 2) Revisions or updates to the erosion control plan as required by Watershed 19 Protection inspectors throughout project implementation 20 15. Erosion Control Plan Implementation 21 a. Measurement 22 1) Measurement for this item shall be by lump sum. 23 b. Payment 24 1) The work performed in accordance with this item shall be paid for at the 25 lump sum price bid for all “Erosion Control Plan Implementation.” 26 2) 75% of the lump sum price shall be payable after initial installation and 27 approval by the Watershed Protection department 28 3) The remaining 25% of the lump sum price shall be payable after vegetative 29 cover requirements have been met and all erosion and sediment control 30 measures have been removed. 31 c. The price bid shall include: 32 1) Installation, maintenance, and repair of all erosion or sediment control 33 measures indicated in the approved Erosion Control Plan 34 2) Modifications to the approved erosion and sediment control measures 35 required to comply with performance requirements during the project 36 3) Removal of all erosion or sediment control measures once vegetative cover 37 requirements have been met. 38 1.3 REFERENCES 39 A. Abbreviations and Acronyms 40 1. Environmentally Sensitive Area: ESA 41 B. Reference Standards 42 1. Reference standards cited in this Section refer to the current reference standard 43 published at the time of the latest revision date logged at the end of this Section 44 unless a date is specifically cited. 45 2. City of Denton, Stormwater Design Criteria Manual 46 31 25 14 EROSION AND SEDIMENT CONTROL Page 6 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 3. North Central Texas Council of Governments (NCTCOG) Integrated Stormwater 1 Management (iSWM) Technical Manual. 2 4. Texas Department of Transportation, Standard Specifications for Construction and 3 Maintenance of Highways, Streets, and Bridges (TxDOT): 4 a. Item 169, Soil Retention Blankets. 5 5. Texas Department of Transportation (TxDOT), Departmental Material 6 Specifications (DMS): 7 a. DMS-6200, Filter Fabric. 8 b. DMS-6230, Temporary Sediment Control Fence Fabric. 9 c. DMS-6370, Erosion Control Blankets. 10 1.4 ADMINISTRATIVE REQUIREMENTS 11 A. Sequencing 12 1. Ensure erosion control measures are fully installed prior to the commencement of 13 any earth disturbing activities. 14 2. If required, ensure ESA protection measures are fully installed prior to the 15 commencement of any earth disturbing activities. 16 3. Contact Watershed Protection division for initial inspection of installed erosion 17 control or ESA protection measures prior to the commencement of any earth 18 disturbing activities. Watershed@cityofdenton.com 19 4. On phased projects, final stabilization shall be completed and Erosion and Sediment 20 Control devices removed from each phase as construction is completed. 21 1.5 SUBMITTALS 22 A. Submittals shall be in accordance with Section 01 33 00. 23 B. All submittals shall be approved by the City prior to delivery. 24 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 25 A. Storm Water Pollution Prevention Plan (SWPPP) submittals in accordance with Section 26 01 57 13 where land disturbance exceeds 1 acre. 27 B. Erosion Control Plan submittal when Contractor is responsible for creating site specific 28 erosion control plan. 29 1. Plan content and requirements as specified in the Drawings 30 2. Plan to adhere to the general standards of the City of Denton’s Development Code 31 Section 7.3.5 32 C. Product Data 33 1. Provide product data from each manufacturer supplying Erosion and Sediment 34 Control devices and accessories. 35 2. Product data sheets for all products to include: 36 a. Manufacturer name 37 b. Date 38 c. Material description 39 d. Point of delivery 40 e. Data and test results as specified in this Section 41 f. Manufacturer Recommended Storing Data, if applicable 42 31 25 14 EROSION AND SEDIMENT CONTROL Page 7 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 g. Application Recommendations, if applicable 1 1.7 CLOSEOUT SUBMITTALS [NOT USED] 2 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 3 1.9 QUALITY ASSURANCE [NOT USED] 4 1.10 DELIVERY, STORAGE, AND HANDLING 5 A. Storage and Handling Requirements 6 1. Secure and maintain a location to store the material in accordance with Section 01 7 66 00. 8 2. Store all storm water pollution prevention materials in accordance with 9 manufacturer’s recommendations. 10 1.11 SITE CONDITIONS [NOT USED] 11 1.12 WARRANTY [NOT USED] 12 PART 2 - PRODUCTS 13 2.1 CITY-SUPPLIED PRODUCTS [NOT USED] 14 2.2 MATERIALS 15 A. Silt Fence 16 1. Fabric 17 a. Provide fabric in accordance with the following criteria: 18 19 Property Test Method Specification Limit Tensile Strength ASTM D4632 90-lbs Puncture Rating ASTM D4833 60-lbs Mullen Burst Rating ASTM D3796 280-psi Apparent Opening Size ASTM D4751 Sieve No. 30 to No. 100 Ultraviolet Resistance ASTM D4355 70 percent min 20 2. Posts 21 a. Provide steel T-section or L-section posts, 1.3 pounds per linear foot, and 4 feet 22 in length minimum. 23 b. Provide plastic caps on all steel posts in areas exposed to pedestrian traffic. 24 c. Wood posts may be approved by City if project duration is expected to be less 25 than 90 days. 26 3. Net Reinforcement 27 a. Provide net reinforcement of at least 12 gauge galvanized welded wire mesh, 28 with a maximum opening size of 2x2 inches. 29 4. Stone Overflows 30 a. Provide 1 1/2 inch washed stone aggregate in accordance with Section 32 05 31 26. 32 31 25 14 EROSION AND SEDIMENT CONTROL Page 8 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 B. Check Dam 1 1. Aggregate 2 a. Provide 3 to 6 inch aggregate in accordance with Section 32 05 26 for check 3 dam heights of 24 inches or less. 4 b. Provide 4 to 8 inch aggregate in accordance with Section 32 05 26 for check 5 dam greater than 24 inches in height. 6 2. Wire 7 a. If required, provide mesh consisting of minimum 20 gauge galvanized wire. 8 3. Fabric 9 a. For check dams greater than 18 inches in height, provide filter fabric in 10 accordance with the following criteria: 11 12 Property Test Method Specification Limit Tensile Strength ASTM D4632 250-lbs Puncture Rating ASTM D4833 135-lbs Mullen Burst Rating ASTM D3796 420-psi Apparent Opening Size ASTM D4751 Sieve No. 20 max Ultraviolet Resistance ASTM D4355 20 percent min 13 C. Organic Filter Tube 14 1. Containment Mesh 15 a. Provide biodegradable, photodegradable, or recyclable containment mesh with 16 a minimum rated life of one year under normal site conditions, such as burlap, 17 twine, UV photodegradable plastic, or polyester. 18 1) Obtain approval from the City for use of any other material. 19 b. Provide recyclable containment mesh for temporary organic filter tube 20 installation. 21 c. Provide biodegradable or photodegradable containment mesh when organic 22 filter tube will remain in place as part of vegetative system. 23 2. Core Material 24 a. Provide biodegradable or recyclable core material such as compost, mulch, or 25 coir. 26 1) Obtain approval from the City for use of any other material. 27 3. Posts 28 a. Provide steel T-section or L-section posts, 1.3 pounds per linear foot or 2 29 inches by 2 inches wooden posts. 30 b. Provide posts at least 6 inches longer than the outside diameter of the Organic 31 Filter Tube. 32 D. Inlet Protection 33 1. Provide Inlet Protection comprised of Organic Filter Tubes or rock bags for erosion 34 control in accordance with this Section. 35 E. Erosion Control Blanket 36 1. Blanket 37 a. In accordance with DMS 6370. 38 2. Staples 39 31 25 14 EROSION AND SEDIMENT CONTROL Page 9 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 a. In accordance with the Erosion Control Blanket manufacturer 1 recommendations. 2 F. Stabilized Construction Exit 3 1. Aggregate 4 a. Provide 3 to 6 inch aggregate in accordance with Section 32 05 26. 5 G. Mulching 6 1. Provide type of organic mulching as specified in the Drawings. 7 H. Pipe Inlet Sediment Trap 8 1. Riprap 9 a. Provide 6 to 12 inch Dry Stone Riprap in accordance with Section 31 37 00. 10 2. Filter Stone 11 a. Provide 1 1/2 inch washed stone aggregate in accordance with Section 32 05 12 26. 13 3. Wire 14 a. Provide mesh consisting of minimum 20 gauge galvanized wire with 1/2 inch 15 by 1/2 inch openings. 16 4. Fabric 17 a. Provide Filter Fabric meeting the following criteria: 18 19 Property Test Method Specification Limit Tensile Strength ASTM D4632 250-lbs Puncture Rating ASTM D4833 135-lbs Mullen Burst Rating ASTM D3796 420-psi Apparent Opening Size ASTM D4751 Sieve No. 20 max Ultraviolet Resistance ASTM D4355 20 percent min 20 5. Concrete Block 21 a. Provide standard 8-inch x 8-inch x 16-inch concrete masonry units in 22 accordance with ASTM C139. 23 I. Stone Outlet Sediment Trap 24 1. Riprap 25 a. Provide 6 to 12 inch Dry Stone Riprap in accordance with Section 31 37 00. 26 2. Filter Stone 27 a. Provide 1 1/2 inch washed stone aggregate in accordance with Section 32 05 28 26. 29 3. Fabric 30 a. Provide Filter Fabric in accordance with the following criteria: 31 32 Property Test Method Specification Limit Tensile Strength ASTM D4632 250-lbs Puncture Rating ASTM D4833 135-lbs Mullen Burst Rating ASTM D3796 420-psi Apparent Opening Size ASTM D4751 Sieve No. 20 max Ultraviolet Resistance ASTM D4355 20 percent min 31 25 14 EROSION AND SEDIMENT CONTROL Page 10 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 1 J. Turf Reinforcement Mat 2 1. Provide Turf Reinforcement Mats in accordance with TxDOT Item 169 Approved 3 Products List, Erosion Control Approved Products and in accordance with the 4 following criteria: 5 6 Property Test Method Specification Limit Minimum Thickness ASTM D6525 0.25 in Ultraviolet Resistance ASTM D4355 80 percent Tensile Strength ASTM D6818 175 lbs/ft 7 K. Dewatering Controls 8 1. Sediment Filter Bag 9 a. Provide sediment filter bags made of non-woven, needle-punched, geotextile 10 that meets the following criteria: 11 12 Property Test Method Specification Limit Tensile Strength ASTM D4632 250-lbs Puncture Rating ASTM D4833 135-lbs Mullen Burst Rating ASTM D3796 420-psi Ultraviolet Resistance ASTM D4355 20 percent min Water Flow Rate ASTM D4491 85 to 110 gpm/ft2 13 2. Temporary Sediment Tank 14 a. Provide compartmented container with a storage volume equal to 1 cubic foot 15 for each gallon per minute of pump discharge capacity. 16 2.3 ACCESSORIES [NOT USED] 17 2.4 SOURCE QUALITY CONTROL [NOT USED] 18 PART 3 - EXECUTION 19 3.1 INSTALLERS [NOT USED] 20 3.2 EXAMINATION [NOT USED] 21 3.3 PREPARATION 22 A. General 23 1. Remove trees, brush, stumps, and other objectionable material that will interfere 24 with the construction of the erosion control measure. 25 B. Erosion Control Blanket 26 1. Remove rocks, dirt clods, stumps, and other objectionable material that will prevent 27 the mat from lying in direct contact with the soil. 28 C. Mulching 29 31 25 14 EROSION AND SEDIMENT CONTROL Page 11 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 1. Fertilize and treat soil prior to mulching installation when used with final 1 vegetation. 2 a. Fertilization and soil treatment are not required when using mulching with 3 hydroseeding or when seed is spread during winter months. 4 D. Turf Reinforcement Mat 5 1. Remove rocks, dirt clods, stumps, and other objectionable material that will prevent 6 the mat from lying in direct contact with the soil. 7 3.4 INSTALLATION 8 A. Silt Fence 9 1. Provide silt fence near the downstream perimeter of a disturbed area to intercept 10 sediment from sheet flow. 11 2. Install posts 18 inches deep, maximum 6 feet on center. 12 3. Dig 6-inch x 6-inch trench on uphill side of fence and embed fabric and wire mesh. 13 Backfill the trench. 14 4. Attach net reinforcement to posts with clips for steel posts or staples for wood posts 15 in at least four equally spaced locations per post. 16 5. Fasten fabric to top of net reinforcement at a maximum spacing of 15 inches. 17 6. Locate splices in fabric at a post and provide a 3-foot overlap ensuring no leakage 18 or bypass. 19 7. Install stone overflow structures at low points or spaced at approximately 300 feet if 20 there is no apparent low point. 21 8. Turn last 10 feet of Silt Fence slightly uphill to prevent bypass. 22 9. Repair or replace any posts, net reinforcement, or fabric that are bent, torn, or 23 otherwise unable to function as intended in accordance with this Section. 24 B. Check Dam 25 1. Place the aggregate to the lines, height, and slopes specified in the Drawings. 26 2. Place Check Dams perpendicular to the direction of flow. 27 C. Organic Filter Tube 28 1. Install Organic Filter Tubes near the downstream perimeter of a disturbed area to 29 intercept sediment from sheet flow. 30 2. When placed on soil, excavate a 1-inch to 2-inch deep bedding trench along the 31 length of the Organic Filter Tubes. 32 3. Secure Organic Filter Tubes using posts to prevent displacement as a result of 33 normal rain events, damage to the logs, and flow from penetrating under the logs. 34 a. Rock bags may be used in place of posts on paved surfaces. 35 4. Overlap ends of Organic Filter Tubes by at least 18 inches and secure ends together 36 preventing gaps from forming. 37 5. Turn last 10 feet of Organic Filter Tubes slightly uphill to prevent bypass. 38 D. Inlet Protection 39 1. Install prefabricated inlet protection systems in accordance with manufacturer’s 40 instructions. 41 31 25 14 EROSION AND SEDIMENT CONTROL Page 12 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 2. Install filter fabric as specified in the Drawings and in accordance with this Section. 1 3. Install inlet protection systems to provide 2-inch overflow capability to allow storm 2 water overflow during extreme storm events or when filter media on protection 3 device clogs. 4 E. Erosion Control Blanket 5 1. Use an Erosion Control Blanket anywhere seeding is to be used and the slope is 6 steeper than a 6:1 slope. 7 2. Use Turf Reinforcement Mat when stabilizing slopes of 2:1 or steeper. 8 3. Provide blanket on sod locations only when specified in the Drawings. 9 4. Dig 6 inch trench along the entire perimeter of the installation area. 10 5. Lay Erosion Control Blanket into trench and backfill with compacted soil. 11 6. Fasten Erosion Control Blanket in accordance with manufacturer’s instructions. 12 7. Ensure staples are installed parallel to the direction of flow. 13 8. Overlap ends of Erosion Control Blanket by a minimum of 3 feet, and longitudinal 14 edges by 6 inches. 15 9. Staple Erosion Control Blanket at all critical channel points and all overlaps. 16 10. ECBs shall be installed vertically down slope (across contours) on cut/fill slopes 17 and embankments and along contours (parallel to flow) in swales and drainage 18 ditches. 19 11. Unless the ECB is seeded to establish vegetation, perimeter applications shall be 20 limited to thirty feet wide drainage areas (I.e. linear construction projects) for an 8 21 feet width of ECB. 22 F. Stabilized Construction Exit 23 1. Install stabilized construction exit as specified in the Drawings. 24 2. Install stabilized construction exits at any point where traffic will be leaving a 25 construction site to or from a street, alley, sidewalk, or parking area. 26 3. Slope stabilized construction exit away from offsite paved surfaces or incorporate a 27 drainage swale to prevent runoff from leaving the construction site. 28 4. Do not place stabilized construction exits at the lowest point on the construction site 29 or on top of utility lines. 30 5. Minimum width of 15 feet for one-way and 20 feet for two-way. 31 G. Mulching 32 1. Spread organic mulch by hand or mechanical means providing complete, uniform 33 coverage of the specified area. 34 2. Install mulching to a thickness between 1 to 2 inches. 35 3. Anchor mulching by application of fiber mulch binder, synthetic mulch binder, 36 using a tractor-drawn crimper to punch into the soil, or by placing netting above the 37 mulch and stapled into the ground when placed on slopes of 3:1 or steeper. 38 4. Do not use mulching on slopes of 1.5:1 or steeper. 39 H. Pipe Inlet Sediment Trap 40 1. Install pipe inlet sediment trap as specified in the Drawings. 41 31 25 14 EROSION AND SEDIMENT CONTROL Page 13 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 2. Provide a stormwater and sediment storage area upslope of the pipe inlet sediment 1 trap to a minimum volume equal to the runoff calculated from the temporary 2 control design storm. 3 3. Provide side slopes surrounding the storage area at 2:1 or flatter. 4 4. Install the pipe inlet sediment trap to a maximum height of half the inlet pipe 5 diameter. 6 5. Install pipe inlet sediment trap to provide 2-inch overflow capability to allow storm 7 water overflow during extreme storm events or when filter media on protection 8 device clogs. 9 I. Stone Outlet Sediment Trap 10 1. Install stone outlet sediment trap as specified in the Drawings. 11 2. Provide a stormwater and sediment storage area upslope of the pipe inlet sediment 12 trap to a minimum volume equal to the runoff calculated from the temporary 13 control design storm. 14 3. Install the pipe inlet sediment trap to a maximum height of half the inlet pipe 15 diameter. 16 4. Grade side slopes surrounding the storage area at 2:1 or flatter. 17 5. Install pipe inlet sediment trap to provide 2-inch overflow capability to allow storm 18 water overflow during extreme storm events or when filter media on protection 19 device clogs. 20 J. Turf Reinforcement Mat 21 1. Install turf reinforcement mats as specified in the Drawings and manufacturer’s 22 recommendations. 23 2. Install turf reinforcement mats immediately after completing grading of the slope or 24 channel, and at most within 14 days after completing the grading. 25 3. Install turf reinforcement mats vertically down slope on steep cut/fill slopes, 26 embankments, and steep channel slopes above the water surface level. 27 4. Install turf reinforcement mats horizontally (parallel to flow) for channel slopes 28 below the water surface level. 29 5. Dig 6 inch trench along the entire perimeter of the installation area. 30 6. Lay turf reinforcement mat into trench and backfill with compacted soil. 31 7. Fasten turf reinforcement mat in accordance with manufacturer’s instructions. 32 8. Ensure staples are installed parallel to the direction of flow. 33 9. Overlap ends of turf reinforcement mat by a minimum of 3 feet, and longitudinal 34 edges by 6 inches. 35 10. Staple turf reinforcement mat at all critical channel points and all overlaps. 36 3.5 REPAIR 37 1. Repair any controls determined to no longer be functioning as intended in 38 accordance with this Section. 39 2. Repair devices as soon as exposed ground has dried sufficiently to prevent further 40 damage from equipment operations needed for repairs. 41 3.6 RE-INSTALLATION [NOT USED] 42 31 25 14 EROSION AND SEDIMENT CONTROL Page 14 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 3.7 FIELD QUALITY CONTROL 1 A. Field Inspections 2 1. Inspect all storm water pollution prevention controls at least once every 7 calendar 3 days. 4 2. Inspect dewatering pumps and sediment controls hourly while pumps are in 5 operation. 6 3.8 SYSTEM STARTUP [NOT USED] 7 3.9 ADJUSTING [NOT USED] 8 3.10 CLEANING [NOT USED] 9 3.11 CLOSEOUT ACTIVITIES [NOT USED] 10 3.12 PROTECTION [NOT USED] 11 3.13 MAINTENANCE 12 A. General 13 1. If a storm water pollution prevention control ceases to function as intended, repair 14 and replace the device or any portions necessary. Repeated failure indicates a 15 device is insufficient and additional or different Erosion and Sediment Control 16 devices must be selected. 17 2. Remove sediment, debris, and litter from all devices as necessary to maintain 18 intended operation. 19 3. Continue maintenance of all erosion and sediment control devices until vegetative 20 cover reaches 70 percent density, as determined by the City. 21 B. Check Dam 22 1. Remove silt when it reaches a depth equal to one-third the height of the dam or one 23 foot, whichever is less. 24 C. Dewatering Controls 25 1. Repair areas eroded due to dewatering pumping and install erosion control devices 26 to prevent further erosion. 27 2. Clean sediment tanks when they become half full of sediment. 28 3.14 ATTACHMENTS [NOT USED] 29 30 31 END OF SECTION 32 33 Revision Log 31 25 14 EROSION AND SEDIMENT CONTROL Page 15 of 15 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 14, 2024 Effective July 1, 2024 DATE NAME SUMMARY OF CHANGE 6/14/24 Added ESA protection measures to Section 1.4; Removed Watershed Protection individual contact information from Section 1.4 6/14/24 Removed organic filter tubes and rock bags from inlet protection under 3.4.D 6/14/24 Removed presence of Watershed Protection from inspection requirement under 3.7 1 31 34 19 GEOSYNTHETIC SOIL REINFORCEMENT Page 1 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 31 34 19 1 GEOSYNTHETIC SOIL REINFORCEMENT 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Geosynthetic Soil Reinforcements. 6 B. Deviations from this City of Denton Standard Specification: 7 1. None. 8 C. Related Specification Sections include but are not limited to: 9 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 10 Contract. 11 2. Division 1 - General Requirements. 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Geosynthetic Soil Reinforcement 15 a. Measurement 16 1) Measured per the square yard of Geosynthetic Soil Reinforcement installed. 17 b. Payment 18 1) The work performed and materials furnished in accordance with this item 19 and measured as provided under “Measurement” will be paid for at the unit 20 price bid per square yard for “Geosynthetic Soil Reinforcement” installed. 21 c. The price bid shall include: 22 1) Furnishing and installing Geosynthetic Soil Reinforcement 23 2) Loading 24 3) Unloading 25 4) Hauling 26 5) Disposal of excess materials 27 6) Clean-up 28 1.3 REFERENCES 29 A. Reference Standards 30 1. Reference standards cited in this Section refer to the current reference standard 31 published at the time of the latest revision date logged at the end of this Section 32 unless a date is specifically cited. 33 2. American Society for Testing and Materials (ASTM): 34 a. D4632, Grab Breaking Load and Elongation of Geotextiles 35 b. D276, Identification of Fibers in Textiles 36 c. D4355, Standard Test Method for Deterioration of Geotextiles by Exposure to 37 Light, Moisture and Heat in a Xenon Arc-Type Apparatus 38 3. TXDOT Test Procedures: 39 31 34 19 GEOSYNTHETIC SOIL REINFORCEMENT Page 2 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 a. Tex-616-J, Construction Fabrics 1 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 2 1.5 SUBMITTALS 3 A. Submittals shall be in accordance with Section 01 33 00. 4 B. All submittals shall be approved by the City prior to delivery. 5 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 6 A. Product Data 7 1. Name 8 2. Manufacturer 9 3. Chemical composition 10 4. Material Properties 11 1.7 CLOSEOUT SUBMITTALS [NOT USED] 12 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 13 1.9 QUALITY ASSURANCE [NOT USED] 14 1.10 DELIVERY, STORAGE, AND HANDLING 15 A. Storage and Handling Requirements 16 1. Secure and maintain a location to store the material in accordance with Section 01 17 66 00. 18 1.11 FIELD CONDITIONS 19 A. Ambient Conditions 20 1. Install Geosynthetic Soil Reinforcement under appropriate ambient and soil 21 conditions in accordance with manufacturer’s recommendations. 22 1.12 WARRANTY [NOT USED] 23 PART 2 - PRODUCTS 24 2.1 CITY-FURNISHED PRODUCTS [NOT USED] 25 2.2 MATERIALS 26 A. Manufacturers 27 1. Manufacturer List 28 a. Geosynthetic Soil Reinforcement 29 1) TriAx Geogrid by Tensar, or 30 2) Approved equal 31 2. Substitution requests for manufacturers or models not indicated above shall be 32 processed in accordance with Section 01 25 00. 33 B. Material Requirements 34 35 31 34 19 GEOSYNTHETIC SOIL REINFORCEMENT Page 3 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1. Provide Geosynthetic Soil Reinforcement meeting the following requirements: 1 2 Characteristic Test Method Average Roll Minimum Value Grab Strength ASTM D4632 80-lbs @ 12-in per minute Elongation at Break ASTM D4632 50% @ 12-in per minute Asphalt Retention Tex-616-J 0.5-oz per square foot Melting Point ASTM D276 300° F Resistance to UV Light ASTM D4355 70% 3 2.3 ACCESSORIES [NOT USED] 4 2.4 SOURCE QUALITY CONTROL [NOT USED] 5 PART 3 - EXECUTION 6 3.1 INSTALLERS [NOT USED] 7 3.2 EXAMINATION [NOT USED] 8 3.3 PREPARATION [NOT USED] 9 3.4 INSTALLATION 10 A. Install Geosynthetic Soil Reinforcement in accordance with manufacturer’s guidelines. 11 3.5 REPAIR [NOT USED] 12 3.6 RE-INSTALLATION [NOT USED] 13 3.7 FIELD QUALITY CONTROL [NOT USED] 14 3.8 SYSTEM STARTUP [NOT USED] 15 3.9 ADJUSTING [NOT USED] 16 3.10 CLEANING [NOT USED] 17 3.11 CLOSEOUT ACTIVITIES [NOT USED] 18 3.12 PROTECTION [NOT USED] 19 3.13 MAINTENANCE [NOT USED] 20 21 31 34 19 GEOSYNTHETIC SOIL REINFORCEMENT Page 4 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3.14 ATTACHMENTS [NOT USED] 1 END OF SECTION 2 3 Revision Log DATE NAME SUMMARY OF CHANGE 4 31 37 00 RIPRAP Page 1 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 31 37 00 1 RIPRAP 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A.Section Includes: 5 1. Provide and place concrete, stone, cement-stabilized, or special riprap. 6 B. Deviations from this City of Denton Standard Specification: 7 1. None. 8 C. Related Specification Sections include but are not limited to: 9 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 10 Contract. 11 2. Division 1 - General Requirements. 12 3. Section 03 00 00 - Concrete and Concrete Reinforcing. 13 4. Section 32 13 13 – Concrete Paving. 14 1.2 PRICE AND PAYMENT PROCEDURES 15 A.Measurement and Payment 16 1. Riprap 17 a. Measurement 18 1) Measured per square yard of Riprap installed. 19 b. Payment 20 1) The work performed and materials furnished in accordance with this item 21 and measured as provided under “Measurement” will be paid for at the unit 22 price bid per square yard for “Riprap” installed for: 23 a) Various depths. 24 b) Various types. 25 c. The price bid shall include: 26 1) Furnishing and installing Riprap as specified by the Drawings 27 2) Aggregate, filter fabric, expansion joint material, concrete, grout, mortar, 28 and reinforcing steel 29 3) Excavation for wingwalls and toe wall trenches 30 4) Excavation below natural ground or bottom of excavated channel, as 31 applicable 32 5) Loading, unloading, hauling, and storing 33 6) Shaping of slopes, as applicable 34 7) Bedding 35 8) Clean-up 36 37 31 37 00 RIPRAP Page 2 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1.3 REFERENCES 1 A.Reference Standards 2 1. Reference standards cited in this Section refer to the current reference standard 3 published at the time of the latest revision date logged at the end of this Section 4 unless a date is specifically cited. 5 2. American Society for Testing and Materials (ASTM) 6 a. D5519, Standard Test Methods for Particle Size Analysis of Natural and Man-7 Made Riprap Materials. 8 3. TxDOT Departmental Material Specifications (DMS): 9 a. DMS 6200, Filter Fabric. 10 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 11 1.5 SUBMITTALS [NOT USED] 12 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 13 1.7 CLOSEOUT SUBMITTALS [NOT USED] 14 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 15 1.9 QUALITY ASSURANCE [NOT USED] 16 1.10 DELIVERY, STORAGE, AND HANDLING 17 A.Storage and Handling Requirements 18 1. Secure and maintain a location to store the material in accordance with Section 01 19 66 00. 20 1.11 FIELD CONDITIONS 21 A.Ambient Conditions 22 1. Place mortar or grout only when the air temperature is above 35° F and rising. 23 2. For concrete riprap, follow all field condition requirements for concrete in 24 accordance with Sections 03 00 00 and 32 13 13. 25 1.12 WARRANTY [NOT USED] 26 PART 2 - PRODUCTS 27 2.1 CITY-FURNISHED PRODUCTS [NOT USED] 28 2.2 MATERIALS 29 A.Filter Fabric 30 1. Provide Type 2 filter fabric in accordance with DMS-6200, if required. 31 B. Concrete Riprap 32 1. Use concrete with a compressive strength of 4,000 psi at 28-days in accordance 33 with Section 03 30 00. 34 35 31 37 00 RIPRAP Page 3 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 C. Stone Riprap 1 1. Use durable natural stone with a bulk specific gravity of at least 2.50 and a 2 maximum weight loss of 18 percent after 5 cycles of magnesium sulfate solution. 3 2. Common 4 a. Use stones between 50 and 250 pounds. 5 b. Use stones at least 3 inches in their least dimension. 6 c. Use stones at least twice as wide as they are thick. 7 3. Protection 8 a. Use boulders or quarried rock that meets the gradation requirements of Table 1. 9 b. Both the width and the thickness of each piece of riprap must be a least 1/3 of 10 the length. 11 c. Provide bedding stone that in-place meets the gradation requirements shown in 12 Table 2 or as otherwise shown on the Drawings. 13 d. Determine the gradation of the finished, in-place, riprap stone under the direct 14 supervision of the City in accordance with ASTM D5519. 15 Table 1 16 Riprap Gradation Requirements 17 Thickness Maximum Size (lb.) 90 percent Size1 (lb.) 50 percent Size2 (lb.) 8 percent Size3, Minimum (lb.) 12 in. 200 80-180 30-75 3 15 in. 320 170-300 60-165 20 18 in. 530 290-475 105-220 22 21 in. 800 460-720 175-300 25 24 in. 1,000 550-850 200-325 30 30 in. 2,600 1,150-2.50 400-900 40 1. Defined such that 10% of the total riprap stone by weight is larger and 90% is smaller. 18 2. Defined such that 50% of the total riprap stone by weight is larger and 50% is smaller. 19 3. Defined such that 92% of the total riprap stone by weight is larger and 8% is smaller. 20 Table 2 21 Bedding Stone Gradation 22 Sieve Size (Square Mesh) Percent by Weight Passing 3 inches 100 1-1/2 inches 50-80 3/4 inches 20-60 No. 4 0-15 No. 10 0-5 D.Grout 23 1. Provide grout with a ratio of 1-part portland cement to 3-parts sand and mixed with 24 water until it achieves a consistency that will flow into and completely fill all voids. 25 2.3 ACCESSORIES [NOT USED] 26 2.4 SOURCE QUALITY CONTROL [NOT USED] 27 31 37 00 RIPRAP Page 4 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 PART 3 - EXECUTION 1 3.1 INSTALLERS [NOT USED] 2 3.2 EXAMINATION [NOT USED] 3 3.3 PREPARATION 4 A.Grading 5 1. Grade and compact the slopes and other areas to be protected with riprap to match 6 the line and grade shown on the plans. 7 3.4 INSTALLATION 8 A.Filter Fabric 9 1. Place filter fabric with the length running up and down the slope, if required. 10 2. Ensure fabric has a minimum overlap of 2 feet. 11 3. Secure fabric with nails at least 2 inches long or U-shaped pins with legs at least 9 12 inches long. 13 4. Space nails or pins at a maximum 10 feet in each direction and 5 feet along seams. 14 B. Concrete Riprap 15 1. Reinforcement 16 a. Reinforce concrete riprap with No. 3 reinforcing bars spaced at a maximum of 17 18 inches in each direction unless otherwise specified in the Drawings. 18 b. Provide a minimum 6-inch lap at all splices. 19 c. Place the first parallel bar no more than 6 inches from the edge of concrete and 20 ensure between 1 and 3 inches of horizontal cover at the edge of riprap. 21 d. Use approved supports to hold the reinforcement approximately equidistant 22 from the top and bottom surface of the slab. 23 e. Adjust reinforcement during concrete placement to maintain correct position. 24 f. Provide 2-inch weep holes on 10-foot centers located 2 feet above finished 25 grade backed by 1 cubic foot of gravel and galvanized hardware cloth. 26 g. Provide additional rows of 2-inch weep holes for each 20 feet of riprap height, 27 offset by 5 feet from the first row. 28 2. Subgrade 29 a. Sprinkle and consolidate the subgrade before the concrete is placed ensuring all 30 surfaces are moist. 31 b. Compact each layer to a minimum of 98 percent standard proctor density with a 32 moisture content not to exceed plus or minus 2 percent of optimum. 33 3. Compact and shape the concrete once it has been placed in accordance with the 34 dimensions shown on the plans. 35 4. Finish the surface with a wood float after it has set sufficiently. 36 5. Provide a smooth surface or broom finish, as approved. 37 6. Cure the riprap immediately after the finishing operation in accordance with 38 Section 32 13 13. 39 40 31 37 00 RIPRAP Page 5 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 C. Stone Riprap 1 1. Provide the following types of stone riprap as specified in the Drawings: 2 a. Dry Riprap 3 1) Stone riprap with voids filled entirely with only spalls or small stones. 4 2) Use spalls and small stones lighter than 25 pounds to fill open joints and 5 voids in stone riprap, and place to a tight fit. 6 3) Do not exceed a 6-inch variation between the tops of adjacent stones. 7 4) Replace, embed deeper, or chip away stones that project more than the 8 allowable amount above the finished surface. 9 b. Grouted Riprap 10 1) Common stone riprap with voids grouted after all stones are in place. 11 2) Prevent earth, sand, or foreign material from filling the spaces between the 12 stones. 13 3) Wet the stones thoroughly after they are in place, fill the spaces between 14 the stones with grout, and pack. 15 4) Sweep the surface of the riprap with a stiff broom after grouting. 16 5) Protect work from rapid drying for at least 3 days after placement. 17 2. Common 18 a. Construct riprap as shown in Figure 1. 19 b. Place stones on a bed excavated for the base course. 20 c. Bed the base course of stone well into the ground with the edges in contact. 21 d. Bed and place each succeeding course in even contact with the preceding 22 course. 23 3. Protection 24 a. Construct riprap as shown in Figure 2. 25 b. Place riprap stone on the slopes within the limits specified in the Drawings. 26 c. Place stone for riprap on the bedding material to produce a reasonably well-27 graded mass of riprap with the minimum practicable percentage of voids. 28 d. Place riprap to its full thickness in a single operation. 29 e. Avoid displacing the bedding material. 30 f. Ensure the entire mass of stones in their final position is free from 31 objectionable pockets of small stones and clusters of larger stones. 32 g. Do not place riprap in layers, and do not place by dumping into chutes, 33 dumping from the top of the slope, pushing from the top of the slope, or any 34 method likely to cause segregation of the various sizes. 35 h. Obtain the desired distribution of the various sizes of stones throughout the 36 mass by selective loading of material at the quarry or other source or by other 37 methods of placement that will produce the specified results. 38 i. Rearrange individual stones by mechanical equipment or by hand if necessary 39 to obtain a reasonably well-graded distribution of stone sizes. 40 3.5 REPAIR [NOT USED] 41 3.6 RE-INSTALLATION [NOT USED] 42 3.7 FIELD QUALITY CONTROL 43 A.Field Tests and Inspections 44 31 37 00 RIPRAP Page 6 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1. Perform a size verification test in accordance with ASTM D5519 at least once per 1 5,000 square yards of finished riprap for all types of stone. 2 2. For installations greater than 5,000 square yards, do not place additional riprap until 3 the initial size verification test has been approved. 4 3.8 SYSTEM STARTUP [NOT USED] 5 3.9 ADJUSTING [NOT USED] 6 3.10 CLEANING [NOT USED] 7 3.11 CLOSEOUT ACTIVITIES [NOT USED] 8 3.12 PROTECTION [NOT USED] 9 3.13 MAINTENANCE [NOT USED] 10 3.14 ATTACHMENTS 11 12 13 Figure 1 – Common Stone Riprap, dry or grouted 14 31 37 00 RIPRAP Page 7 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1 Figure 2 – Protection Stone Riprap 2 3 END OF SECTION 4 5 Revision Log DATE NAME SUMMARY OF CHANGE 6 32 31 00 FENCES AND GATES Page 1 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 32 31 00 1 FENCES AND GATES 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Furnishing and installing, removing, or replacing wooden, metal, chain link, or wire 6 fences and gates. 7 B. Deviations from this City of Denton Standard Specification: 8 1. None. 9 C. Related Specification Sections include but are not limited to: 10 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 11 Contract. 12 2. Division 1 - General Requirements. 13 3. Section 02 41 13 – Selective Site Demolition. 14 4. Section 03 00 00 – Concrete and Concrete Reinforcing 15 1.2 PRICE AND PAYMENT PROCEDURES 16 A. Measurement and Payment 17 1. Fence 18 a. Measurement 19 1) Measured per linear foot of Fence installed. 20 b. Payment 21 1) The work performed and materials furnished in accordance with this item 22 and measured as provided under “Measurement” will be paid for at the unit 23 price bid per linear foot for “Fence” installed for: 24 a) Various Types. 25 b) Various Heights. 26 c. The price bid shall include: 27 1) Furnishing and installing Fence as specified by the Drawings 28 2) Posts, fencing material, and all accessories 29 3) Excavation and embankment 30 4) Loading 31 5) Unloading 32 6) Hauling 33 7) Storing 34 8) Mow strip, if required 35 2. Gate 36 a. Measurement 37 1) Measured per each Gate installed. 38 39 32 31 00 FENCES AND GATES Page 2 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 b. Payment 1 1) The work performed and materials furnished in accordance with this item 2 and measured as provided under “Measurement” will be paid for at the unit 3 price bid per each “Gate” installed for: 4 a) Various Types. 5 b) Various Heights. 6 c) Various Widths. 7 c. The price bid shall include: 8 1) Furnishing and installing Gates as specified by the Drawings 9 2) Posts, fencing material, and all accessories 10 3) Excavation and embankment 11 4) Loading 12 5) Unloading 13 6) Hauling 14 7) Storing 15 8) Mow strip, if required. 16 3. Cattle Guard 17 a. Measurement 18 1) Measured per each Cattle Guard installed. 19 b. Payment 20 1) The work performed and materials furnished in accordance with this item 21 and measured as provided under “Measurement” will be paid for at the unit 22 price bid per each “Cattle Guard” installed for: 23 a) Various Widths. 24 c. The price bid shall include: 25 1) Furnishing and installing Cattle Guards as specified by the Drawings 26 2) Excavation and embankment 27 3) Loading 28 4) Unloading 29 5) Hauling 30 6) Storing 31 1.3 REFERENCES 32 A. Reference Standards 33 1. Reference standards cited in this Section refer to the current reference standard 34 published at the time of the latest revision date logged at the end of this Section 35 unless a date is specifically cited. 36 2. ASTM International (ASTM): 37 a. A116, Standard Specification for Metallic-Coated, Steel-Woven Wire Fence 38 Fabric 39 b. A121, Standard Specification for Metallic-Coated Carbon Steel Barbed Wire 40 c. A392, Standard Specification for Zinc-Coated Steel Chain-Link Fence Fabric 41 d. A491, Standard Specification for Aluminum-Coated Steel Chain-Link Fence 42 Fabric 43 e. A702, Standard Specification for Steel Fence Posts, Hot Wrought 44 f. F626, Standard Specification for Fence Fittings 45 g. F668, Standard Specification for Polyvinyl Chloride (PVC), Polyolefin and 46 Other Polymer-Coated Steel Chain Link Fence Fabric 47 32 31 00 FENCES AND GATES Page 3 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 h. F934, Standard Specification for Standard Colors for Polymer-Coated Chain 1 Link Fence Materials 2 i. F1083, Standard Specification for Pipe, Steel, Hot-Dipped Zinc-Coated 3 (Galvanized) Welded, for Fence Structures 4 3. American Wood-Preservers’ Association (APWA). 5 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 6 1.5 SUBMITTALS 7 A. Submittals shall be in accordance with Section 01 33 00. 8 B. All submittals shall be approved by the City prior to delivery. 9 1.6 ACTION SUBMITTALS 10 A.Product Data 11 1. Provide product data from each manufacturer that is supplying fence, gate, or cattle 12 guard materials and accessories. 13 2. Product data sheets for all products to include: 14 a. Manufacturer name 15 b. Date 16 c. Material description 17 d. Data and test results as required in this Section 18 e. Manufacturer Recommended Storing Data, if applicable 19 f. Installation Recommendations, if applicable 20 B. Shop Drawings 21 1. Provide shop drawings for all fence, gates, and cattle guards showing: 22 a. Installation layout with details and dimensions 23 b. Material type 24 c. Material finish 25 1.7 CLOSEOUT SUBMITTALS [NOT USED] 26 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 27 1.9 QUALITY ASSURANCE [NOT USED] 28 1.10 DELIVERY, STORAGE, AND HANDLING 29 A. Storage and Handling Requirements 30 1. Secure and maintain a location to store the material in accordance with Section 01 31 66 00. 32 32 31 00 FENCES AND GATES Page 4 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1.11 SITE CONDITIONS [NOT USED] 1 1.12 WARRANTY [NOT USED] 2 PART 2 - PRODUCTS 3 2.1 CITY-SUPPLIED PRODUCTS [NOT USED] 4 2.2 MATERIALS 5 A. General 6 1. Provide only new materials of the size, weight, and material specified in the 7 Drawings. 8 2. Provide materials of good commercial quality and design. 9 B. Posts 10 1. Metal 11 a. Do not use rerolled or open-seam material. 12 b. Provide steel pipe in accordance with ASTM F1083. 13 c. Provide T-posts in accordance with ASTM A702. 14 d. Paint all non-galvanized posts with an anti-corrosive paint approved by the 15 City. 16 2. Wood 17 a. Provide posts free of all decay, shakes, splits, or other defects that would 18 weaken or otherwise make the posts unsuitable for the purposes intended. 19 b. Ensure all knots are sound, tight, trimmed flush, and not exceeding 1/3 the 20 small dimension of the post. 21 c. Ensure posts are straight, such that a line drawn between the center of each end 22 does not fall outside the center of the post at any point by more than 2 inches. 23 d. For untreated posts use cedar, redwood, cypress, or live oak. 24 e. For treated posts use pine, spruce, or fir preservative treated in accordance with 25 all applicable AWPA standards. 26 3. Concrete 27 a. Provide concrete with a minimum 28 day compressive strength of 3,000 psi in 28 accordance with Section 03 00 00. 29 b. Bagged concrete is allowed. 30 C. Chain Link Fabric 31 1. Provide chain link fabric made of at least 9 gauge steel wire in accordance with 32 ASTM A392 or ASTM A491. 33 2. Provide knuckled selvages at the top and bottom edge of fabric. 34 3. Provide 7 gauge steel tension wire with a minimum breaking strength of 1,950 35 pounds for the bottom edge, and top edge when railing is not used, of all chain link 36 fence. 37 4. When directed provide PVC vinyl coated fabric in accordance with ASTM F668 38 and colored in accordance with ASTM F934. 39 40 32 31 00 FENCES AND GATES Page 5 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 D. Wire Mesh Fabric 1 1. Provide wire mesh fabric made of at least 10 gauge wire for the top and bottom 2 wires and at least 12-1/2 gauge wire for the intermediate wire and vertical stays in 3 accordance with ASTM A116. 4 E. Barbed Wire 5 1. Provide barbed wire made of 2 strands 12-1/2 gauge wire, twisted with 2-point 14 6 gauge barbs spaced no more than 5 inches apart in accordance with ASTM A121, 7 Class 1. 8 F. Wood Slats 9 1. Provide redwood or cedar slats free from all decay, shakes, splits, or other defects 10 that would weaken or otherwise make the slats unsuitable for the purposes intended. 11 G. Gates 12 1. Provide gates of the same material used in the adjacent fence, unless otherwise 13 specified in the Drawings. 14 2. Provide all gate materials in accordance with the Section. 15 H. Cattle Guards 16 1. Provide cattle guards of the dimensions and materials specified in the Drawings. 17 2.3 ACCESSORIES 18 A. Miscellaneous 19 1. Provide galvanized bolts, nuts, washers, staples, screws, braces, straps, and other 20 suitable devices needed to erect fence. 21 2. For metal posts, provide fittings from pressed or rolled steel, forged steel, malleable 22 iron, or wrought iron. 23 3. Paint all non-galvanized metal accessories with anti-corrosive paint approved by 24 the City. 25 B. Post Caps 26 1. Provide malleable iron post caps designed to exclude all moisture. 27 C. Chain Link Accessories 28 1. Provide fittings and other appurtenances in accordance with ASTM F626. 29 2.4 SOURCE QUALITY CONTROL [NOT USED] 30 PART 3 - EXECUTION 31 3.1 INSTALLERS [NOT USED] 32 3.2 EXAMINATION [NOT USED] 33 34 32 31 00 FENCES AND GATES Page 6 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3.3 PREPARATION 1 A. Clearing 2 1. Remove all stumps, brush, rocks, trees, or other obstructions that would interfere 3 with construction of the fence to a minimum width of 2 feet on each side of the 4 centerline of the fence. 5 2. Grub or excavate any stumps in fence clearing area. 6 3. Remove any existing fence in a position to interfere with the new fence location in 7 accordance with Section 02 41 13. 8 4. Backfill and compact all holes remaining after post and stump removal with 9 suitable soil. 10 3.4 INSTALLATION 11 A. General 12 1. Stake the locations for corner, pull, gate, and end posts as specified in the 13 Drawings, for City approval. 14 2. Follow the finished ground elevations for fencing panels between corner, pull, gate, 15 and end posts. 16 3. Level off minor ground elevation irregularities in the path of the fencing. 17 B. Post Installation 18 1. Space fence posts as specified in the Drawings, to match existing, or to meet the 19 minimum requirements below. 20 21 Post Type Required Spacing or Placement Line posts Max 8 feet on centers Pull posts Max 500 feet on centers; Each horizontal change between 15° and 30°; Each vertical change greater than 20° Corner posts Each horizontal change greater than 30° 22 2. Post Holes 23 a. T-posts for wire fence may be hand driven. For all other posts, drill holes for 24 concrete footings. 25 b. Set posts at a minimum depth of 2 feet for line posts, and 4 feet or 1/3 the 26 length of the post, whichever is greater, for corner and pull posts under tension. 27 c. Drill holes to provide a minimum 3 inches of space between the post and drilled 28 hole on all sides, including the bottom. 29 d. Place concrete to fill all voids around post in a continuous pour. Maintain 30 plumbness and post position as concrete is poured. 31 e. Trowel finish around post sloping to direct water away from post. 32 f. Allow concrete footing to cure for 3 days prior to hanging gates or tensioning 33 cables. 34 g. If bagged concrete is used pull emptied bags from post holes before curing. 35 3. Plumb and permanently position posts with anchorages firmly set. 36 32 31 00 FENCES AND GATES Page 7 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 4. Brace corner and pull posts in two directions. 1 5. Brace end and gate posts in one direction. 2 6. Set end, corner, pull, and gate posts prior to stretching wire or wire mesh fabric 3 between posts. 4 7. Gate Posts 5 a. Set gate posts such that the line between both tops is level, regardless of the 6 grade at the groundline. 7 b. When the grade at the groundline is not level, set posts such that the minimum 8 height requirement is met for the downgrade post. 9 C. Chain Link Fence 10 1. Fasten fabric to corner, pull, end, and gate posts using steel stretcher bars. 11 2. Fasten one end of fabric and apply tension to the other end to remove all slack 12 before making attachments. 13 3. Place bottom of fabric approximately 2 inches above the finished grade. 14 4. Grade uneven areas so the maximum distance between the bottom of the fabric and 15 ground is 6 inches. 16 5. Fasten fabric to the tension wires, top rail, and intermediate line posts at 16-inch 17 intervals using 9 gauge galvanized steel ties. 18 6. Connect existing fence to new fence at existing or newly installed corner post. 19 D. Wire Mesh Fabric and Wire Fence 20 1. Fasten wire mesh fabric or wire fence to posts using galvanized ties or staples while 21 drawing the fencing taut. 22 2. Guy Wire 23 a. Secure fencing with guy wire at the critical point of grade depressions where 24 tension tends to pull posts out of the ground with a double 9 gauge galvanized 25 wire. 26 b. Connect the guy wire to the top and bottom wire of wire mesh fabric or each 27 strand of wire fence and to a deadman weighing at least 100 pounds, buried in 28 the ground. 29 c. Stretch the wire fence prior to guying. 30 3. Connect existing cross fences to new fences and corner posts at junction with 31 existing fences. 32 E. Wood Fence 33 1. Place wood fence slats approximately 2 inch above the finished grade and on a 34 straight grade between posts. 35 2. Grade uneven areas so the maximum distance between the bottom of the slats and 36 ground is 6 inches. 37 3. Attach slats to rails using galvanized screws. 38 F. Gates 39 1. Install horizontal stiffeners on gates 7 feet or taller, and vertical stiffeners on 40 maximum 8-foot centers. 41 2. Install swing gates to open 180 degrees from the closed position. 42 32 31 00 FENCES AND GATES Page 8 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3.5 REPAIR [NOT USED] 1 3.6 RE-INSTALLATION [NOT USED] 2 3.7 SITE QUALITY CONTROL [NOT USED] 3 3.8 SYSTEM STARTUP [NOT USED] 4 3.9 ADJUSTING [NOT USED] 5 3.10 CLEANING [NOT USED] 6 3.11 CLOSEOUT ACTIVITIES [NOT USED] 7 3.12 PROTECTION [NOT USED] 8 3.13 MAINTENANCE [NOT USED] 9 3.14 ATTACHMENTS [NOT USED] 10 END OF SECTION 11 12 Revision Log DATE NAME SUMMARY OF CHANGE 13 32 93 00 PLANTINGS Page 1 of 24 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 32 93 00 1 PLANTINGS 2 3 PART 1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Material, installation, and maintenance requirements for: 7 a. Plantings (Tree, Shrub, Ground Cover, and Miscellaneous Plantings) 8 b. Topsoil, Seeding, and Sodding (Grass and Wildflowers) 9 c. Landscape Edging 10 d. Landscape Restoration 11 e. General Site Landscaping 12 f. Subsidiary Planting Items (Fertilizer, Mulch, Plant Supports, Mulch Tacking, 13 and Water) 14 B. Deviations from this City of Denton Standard Specification: 15 1. None. 16 C. Related Specification Sections include but are not limited to: 17 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 18 Contract. 19 2. Division 1 - General Requirements. 20 3. Section 03 00 00 – Concrete and Concrete Reinforcement. 21 4. Section 03 30 00 – Cast-in-Place Concrete. 22 5. Section 31 25 14 – Erosion and Sediment Control. 23 6. Section 32 13 13 – Concrete Paving. 24 7. Section 32 13 16 – Decorative Concrete Paving. 25 1.2 PRICE AND PAYMENT PROCEDURES 26 A. Measurement and Payment 27 1. Tree 28 a. Measurement 29 1) Measured per each Tree planted. 30 b. Payment 31 1) The work performed and materials furnished in accordance with this item 32 and measured as provided under “Measurement” will be paid for at the unit 33 price bid per each for Tree planted for: 34 2) Various caliper inches. 35 c. The price bid shall include: 36 1) Furnishing and installing Tree as specified by the Drawings 37 2) Preparing excavation pit 38 3) Topsoil, fertilizer, mulch, and planting mix 39 4) Plant supports 40 32 93 00 PLANTINGS Page 2 of 24 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 5) Loading 1 6) Unloading 2 7) Storing 3 8) Hauling 4 9) Handling all materials 5 10) Placing 6 11) All maintenance activities 7 2. Shrub 8 a. Measurement 9 1) Measured per each Shrub planted. 10 b. Payment 11 1) The work performed and materials furnished in accordance with this item 12 and measured as provided under “Measurement” will be paid for at the unit 13 price bid per each of Shrub planted for: 14 a) Various sizes. 15 c. The price bid shall include: 16 1) Furnishing and installing Shrub as specified by the Drawings 17 2) Preparing excavation pit 18 3) Topsoil, fertilizer, mulch, and planting mix 19 4) Plant supports 20 5) Loading 21 6) Unloading 22 7) Storing 23 8) Hauling 24 9) Handling all materials 25 10) Placing 26 11) All maintenance activities 27 3. Ground Cover 28 a. Measurement 29 1) Measured per square foot of Ground Cover planted. 30 b. Payment 31 1) The work performed and materials furnished in accordance with this item 32 and measured as provided under “Measurement” will be paid for at the unit 33 price bid per square foot for Ground Cover planted. 34 c. The price bid shall include: 35 1) Furnishing and installing Ground Cover as specified by the Drawings 36 2) Preparing excavation pit 37 3) Topsoil, fertilizer, mulch, and planting mix 38 4) Plant supports 39 5) Loading 40 6) Unloading 41 7) Storing 42 8) Hauling 43 9) Handling all materials 44 10) Placing 45 11) All maintenance activities 46 4. Miscellaneous Planting 47 a. Measurement 48 32 93 00 PLANTINGS Page 3 of 24 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1) Measured per square foot of Miscellaneous Planting planted. 1 b. Payment 2 1) The work performed and materials furnished in accordance with this item 3 and measured as provided under “Measurement” will be paid for at the unit 4 price bid per square foot for Miscellaneous Planting installed. 5 c. The price bid shall include: 6 1) Furnishing and installing Miscellaneous Planting as specified by the 7 Drawings 8 2) Preparing excavation pit 9 3) Topsoil, fertilizer, mulch, and planting mix 10 4) Plant supports 11 5) Loading 12 6) Unloading 13 7) Storing 14 8) Hauling 15 9) Handling all materials 16 10) Placing 17 11) Tools 18 12) Equipment 19 13) All maintenance activities 20 5. Landscape Edging 21 a. Measurement 22 1) Measured per linear foot of Landscape Edging installed. 23 b. Payment 24 1) The work performed and materials furnished in accordance with this item 25 and measured as provided under “Measurement” will be paid for at the unit 26 price bid per linear foot for Landscape Edging installed for: 27 a) Concrete Landscape Edging, various widths and depths 28 (1) 6” wide, 12” depth, 6”x12” 29 (2) 12” wide, 12” depth, 12”x12” 30 (3) 12” wide, 24” depth, 12”x24” 31 b) Decorative Concrete Landscape Edging, 12”x12” 32 c) Plastic Landscape Edging 33 d) Metal Landscape Edging 34 c. The price bid shall include: 35 1) Furnishing and installing Landscape Edging as specified by the Drawings 36 2) Loading 37 3) Unloading 38 4) Storing 39 5) Hauling 40 6) Handling all materials 41 7) Placing 42 8) All maintenance activities 43 6. Topsoil 44 a. Measurement 45 1) Measured per cubic yards of Topsoil installed. 46 b. Payment 47 32 93 00 PLANTINGS Page 4 of 24 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1) The work performed and materials furnished in accordance with this item 1 and measured as provided under “Measurement” will be paid for at the unit 2 price bid per cubic yard for Topsoil installed. 3 4 c. The price bid shall include: 5 1) Furnishing and installing Topsoil as specified by the Drawings 6 2) Salvaging existing topsoil 7 3) Loading 8 4) Unloading 9 5) Storing 10 6) Hauling 11 7) Handling all materials 12 8) Placing 13 9) All maintenance activities 14 7. Seeding 15 a. Measurement 16 1) Measured per square yard of Seed installed. 17 b. Payment 18 1) The work performed and materials furnished in accordance with this item 19 and measured as provided under “Measurement” will be paid for at the unit 20 price bid per square yard of Seeding installed for: 21 a) Grass Seeding. 22 b) Wildflower Seeding. 23 c. The price bid shall include: 24 1) Furnishing and installing Seeding as specified by the Drawings 25 2) Rolling and tamping 26 3) Loading 27 4) Unloading 28 5) Storing 29 6) Hauling 30 7) Handling all materials 31 8) Placing 32 9) Mulching and tacking, if required 33 10) Fertilizer, if required 34 11) Watering, until established 35 12) All maintenance activities 36 8. Sodding 37 a. Measurement 38 1) Measured per square yard of Sodding installed. 39 b. Payment 40 1) The work performed and materials furnished in accordance with this item 41 and measured as provided under “Measurement” will be paid for at the unit 42 price bid per square yard of Sodding installed. 43 c. The price bid shall include: 44 1) Furnishing and installing Sodding as specified by the Drawings 45 2) Rolling and tamping 46 3) Loading 47 4) Unloading 48 32 93 00 PLANTINGS Page 5 of 24 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 5) Storing 1 6) Hauling 2 7) Handling all materials 3 8) Placing 4 9) Mulching and tacking, if required 5 10) Fertilizer, if required 6 11) Watering, until established 7 12) All maintenance activities 8 9. Landscape Restoration 9 a. Measurement 10 1) Measured lump sum of Landscape Restoration installed 11 b. Payment 12 1) The work performed and materials furnished in accordance with this item 13 and measured as provided under “Measurement” will be paid for at the unit 14 price bid per lump sum for Landscape Restoration. 15 c. The price bid shall include: 16 1) Furnishing and installing Landscape Restoration as specified by the 17 Drawings 18 2) Preparing excavation pit 19 3) Topsoil, fertilizer, mulch, and planting mix 20 4) Plant supports 21 5) Loading 22 6) Unloading 23 7) Storing 24 8) Hauling 25 9) Handling all materials 26 10) Placing 27 11) All maintenance activities 28 10. General Site Landscaping 29 a. Measurement 30 1) Measured lump sum of General Site Landscaping installed 31 b. Payment 32 1) The work performed and materials furnished in accordance with this item 33 and measured as provided under “Measurement” will be paid for at the unit 34 price bid per lump sum for General Site Landscaping installed. 35 c. The price bid shall include: 36 1) Furnishing and installing General Site Landscaping as specified by the 37 Drawings 38 2) Preparing excavation pit 39 3) Topsoil, fertilizer, mulch, and planting mix 40 4) Plant supports 41 5) Loading 42 6) Unloading 43 7) Storing 44 8) Hauling 45 9) Handling all materials 46 10) Placing 47 11) All maintenance activities 48 32 93 00 PLANTINGS Page 6 of 24 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1.3 REFERENCES 1 A. Abbreviations and Acronyms 2 1. PSF – Pounds per Square Foot 3 2. PSI – Pounds per Square Inch 4 3. B&B – Balled and Burlapped 5 B. Definitions 6 Figure 1 7 Limits of excavation, embankment, salvaged topsoil and replaced topsoil 8 9 10 C. Reference Standards 11 1. Reference standards cited in this Section refer to the current reference standard 12 published at the time of the latest revision date logged at the end of this Section 13 unless a date is specifically cited. 14 2. American Joint Committee on Horticultural Nomenclature 15 a. Standardized Plant Names 16 3. American National Standard Institute ANSI: 17 a. ANSI Z60.1 – American Standard for Nursery Stock 18 32 93 00 PLANTINGS Page 7 of 24 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1 4. Texas Department of Agriculture Standards: 2 a. Texas Seed Law 3 b. Texas Fertilizer Law 4 5. Texas Department of Transportation, Standard Specifications for Construction and 5 Maintenance of Highways, Streets, and Bridges (TxDOT): 6 a. Item 7, Article 7, “Preservation of Cultural and Natural Resources and the 7 Environment” 8 6. TxDOT Test Procedures: 9 a. Tex-128-E, Determining Soil pH. 10 1.4 ADMINISTRATIVE REQUIREMENTS 11 A. Coordination 12 1. Coordinate with irrigation installation to ensure plantings receive required amount 13 of water. The Contractor is responsible for all watering required in accordance with 14 this Section. 15 B. Pre-Planting Meetings 16 1. Coordinate with the current owners of any existing landscape areas 1 week prior to 17 holding the pre-planting meeting. 18 2. Hold a pre-planting meeting 1 week prior to performing any tasks included under 19 Plantings. A second pre-planting meeting may be required if seeding/sodding 20 activities are performed more than 3 weeks apart from planting activities. Invite the 21 City and the current owner (if other than the City) of any existing landscape areas 22 along with any appropriate representatives. Prior to the pre-planting meeting, the 23 following needs to be prepared or conducted: 24 a. Landscape Plan: 25 1) Provide a landscape plan prepared, signed, and sealed by a licensed 26 landscape architect. 27 2) Document existing landscape areas during the growing and blooming 28 season. Documentation to include at a minimum quantity, location, and 29 condition of all existing landscape areas. 30 1.5 SUBMITTALS [NOT USED] 31 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 32 A. Submittals shall be in accordance with Section 01 33 00. 33 B. All submittals shall be approved by the City prior to delivery. 34 C. Shop Drawings 35 1. Product Data 36 a. Provide product data for the following products to be used during Planting 37 activities. 38 1) Tacking Agents 39 2) Fertilizer 40 3) Tree Trunk Protection 41 4) Landscape Edging 42 5) Insect, Disease, and Animal Treatment 43 32 93 00 PLANTINGS Page 8 of 24 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 a. Product data sheets will include: 1 1) Manufacturer name or source location 2 2) Date 3 3) Product description 4 4) Verification that the product meets the required standards stated in this 5 specification. 6 5) Produce data and test results as required in this specification 7 6) Material Safety Data Sheets, if applicable 8 7) Manufacturer Recommended Storing Data, if applicable 9 8) Usage and Installation Recommendations 10 9) Maintenance recommendations, if applicable 11 2. Plantings 12 a. Provide the following information for any plantings: 13 1) Nursery Name and Location 14 2) Date 15 3) Plant description 16 4) Certification that the plants meet the specification requirements 17 5) Produce data and test results as required in this specification 18 6) Planting recommendations 19 7) Maintenance recommendations 20 3. Plastic and Metal Landscape Edging 21 a. Provide a shop drawing of the product data for the plastic and/or metal 22 landscape edging material being used. . 23 4. Topsoil 24 a. Provide any offsite source location for topsoil and soil testing results. 25 5. Sod 26 a. Provide source location and proposed grass type for all sod used on project site. 27 6. Seed 28 a. Provide source location for seeding and seed type for all grass and wildflower 29 seeding. 30 7. Mulch 31 a. Provide no float cypress mulch or approved equal for use in landscape areas. 32 b. For all other types of mulch, provide source location, type of mulch, and 33 composition for all mulch used on site. 34 8. Concrete 35 a. Provide concrete mix design, integral color, stamp pattern, and sealant for all 36 concrete and decorative concrete landscape edging in accordance with Sections 37 03 00 00, 32 13 13, and 32 13 16. 38 D. Informational Submittals 39 1. Licensed Landscaper 40 a. Provide information and applicable certifications for the licensed landscape 41 architect or a landscaper of sufficient experience in project specific plantings. 42 2. Equipment Submittals: 43 a. Submittal for all major equipment to include: 44 1) Equipment name and description 45 2) Size 46 32 93 00 PLANTINGS Page 9 of 24 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3) Intended use 1 2 1.7 CLOSEOUT SUBMITTALS 3 A. Maintenance Recommendations 4 1. Provide any nursery or supplier recommendations for care and maintenance of 5 plants and plant materials to the City. 6 B. Warranty Documentation 7 1. Provide any nursery or supplier warranty information to the City. 8 2. Transfer any nursery or supplier warranties to the City if applicable. 9 1.8 MAINTENANCE MATERIAL SUBMITTALS 10 A. Maintain all plantings for 1 year. No separate pay will be provided for maintenance 11 period. 12 1.9 QUALITY ASSURANCE 13 A. Qualifications 14 1. Licensed Professionals 15 a. Provide a landscape architect or qualified landscaper during planting. 16 2. Planting Substitutions 17 a. No substitutions will be allowed without written approval by the City. The 18 following is required when requesting a plant substitution: 19 1) Submit proof of non-availability together with proposal for use of 20 equivalent material. 21 2) Substitutions of larger size or better grade than specified will be allowed 22 upon approval by the City. No additional payment or increase in unit price 23 will be given. 24 1.10 DELIVERY, STORAGE, AND HANDLING 25 A. Delivery and Acceptance Requirements 26 1. Plants 27 a. General: 28 1) Notify City at least 48 hours prior to delivering plants to the site. 29 2) Coordinate with the City for inspection and approval of materials upon 30 delivery. 31 3) Remove rejected plants from the workplace and replace as directed. 32 b. When planting is delayed more than 6 hours after delivery 33 1) Set plants in the shade 34 2) Protect from weather and mechanical damage 35 3) Keep roots moist by covering with mulch, burlap, or other acceptable 36 means of retaining moisture. Water as needed. 37 2. Trees 38 a. Ship trees with Certificates of Inspection as required by governing authorities. 39 b. Label each tree and shrub with securely attached waterproof tag bearing legible 40 designation of botanical and common name. 41 c. Use protective covering during delivery. 42 32 93 00 PLANTINGS Page 10 of 24 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 d. Deliver packaged materials in fully labeled original containers showing weight, 1 analysis, and name of nursery. 2 3 B. Storage and Handling Requirements 4 1. Secure and maintain a location to store the material in accordance with Section 01 5 66 00. 6 2. Trees 7 a. Protect trees from deterioration during delivery and while being stored on-site. 8 b. Do not prune prior to planting. 9 c. Do not bend or bind-tie trees or shrubs in a way that will damage the bark, 10 break branches, or alter the natural shape. 11 C. Stockpiling 12 1. Topsoil 13 a. Stockpile topsoil, when necessary, in a windrow in approved locations within 14 the right of way or easements. 15 b. Keep source and stockpile areas drained. 16 c. Once topsoil has been removed from stockpiled location, restore stockpile site 17 to existing conditions or better. 18 2. Seed 19 a. If using native grass or wildflower seed, provide seed harvested within 100 20 miles of the site. 21 b. Provide each seed species in separate containers labeled with seed variety. 22 3. Sod 23 a. Protect sod from exposure to wind, sun, and freezing. 24 b. Keep stacked sod moist. 25 4. Fertilizer 26 a. Provide fertilizer in acceptable distribution condition and in containers labeled 27 with the analysis. 28 1.11 SITE CONDITIONS 29 A. Ambient Conditions 30 1. Follow all nursery and/or supplier recommendations for optimal weather conditions 31 for installation. 32 2. Comply with all requirements of this specification for planting, seeding, and 33 sodding timeframes. 34 B. Existing Conditions 35 1. Prior to performing work: 36 a. Locate all existing utility lines in accordance with Federal, State, and local 37 requirements. 38 b. Verify power source for existing and proposed irrigation systems. 39 c. Document existing irrigation system in accordance with Administrative 40 Requirements, if applicable. 41 d. Locate all existing irrigation structures which may include, but are not limited 42 to water lines, controllers, sprinkler heads, and drip lines. 43 1.12 WARRANTY [NOT USED] 44 32 93 00 PLANTINGS Page 11 of 24 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 PART 2 - PRODUCTS 1 2.1 CITY-SUPPLIED PRODUCTS [NOT USED] 2 2.2 MATERIALS 3 A. Plants 4 1. General: 5 a. Planting bid items are generic based on plant types. Refer to Drawings for 6 planting schedule and locations. 7 b. Provide nursery-grown plants unless otherwise specified in the Drawings. 8 c. Provide plants with the following characteristics: 9 1) vigorous, healthy, well-rooted plants 10 2) with well-formed crowns 11 3) true to sizes and of typical shape and characteristic of the species 12 d. Refer to Source Quality Control for non-conforming plants. 13 2. Plant Supports: 14 a. Provide a minimum 8-foot long steel T-stakes and 1-inch wide plastic tree 15 chains with protecting chain cover to interface with tree trunk or ArborTie or 16 similar product. 17 b. Deadman Anchoring System: 18 1) Where applicable for anchoring trees, obtain written approval for products 19 and installation method prior to planting trees. 20 c. Provide an ArborGard tree truck protector or similar product. 21 3. Trees 22 a. Tree characteristics: 23 1) True to species and variety specified 24 2) Straight and symmetrical 25 3) Grown under climatic conditions similar to those in the locality of the 26 project for at least 2 years 27 4) Freshly dug during the most recent favorable harvest season 28 5) Grown and harvested in accordance with the American Standard for 29 Nursery Stock 30 6) From a nursery within 200 miles of the project unless otherwise approved 31 7) Compatible with the cold hardiness zone of the project location 32 b. Mark the tree’s north orientation in the nursery for all deciduous trees grown in 33 the field with a 1-inch diameter spot of white paint on the tree trunk within the 34 bottom twelve inches of the trunk. 35 c. Provide a tree with a crown in good overall proportion to entire height of the 36 tree with branching configuration as recommended by ANSI Z60.1 for the tree 37 specified. 38 d. Balled and Burlapped Trees 39 1) Provide trees balled and burlapped or in the container that the tree was 40 grown in. 41 2) Dig a size and shape conforming to the American Standard for Nursery 42 Stock. 43 3) Ensure the balls contain soil with as many fibrous roots as possible. 44 4) Wrap balls firmly with non-synthetic, rottable burlap and secure the burlap 45 using nails and heavy non-synthetic rottable twine. 46 32 93 00 PLANTINGS Page 12 of 24 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 5) Ensure the root collar is apparent (first lateral root visible) at the surface of 1 the ball after wrapping. 2 6) Trees with loose, broken, processed, or manufactured root balls will not be 3 accepted. 4 e. Caliper Measuring: 5 1) For trunks up to 4 inches or less in diameter: Measure the caliper 6 inches 6 above the top of root ball. 7 2) For trunks that are more than 4 inches in diameter: Measure the caliper 12 8 inches above the top of root ball. 9 3) Caliper Measurements: 10 a) By diameter tape measure 11 b) Indicated calipers on Drawings are minimum 12 c) Averaging of plant caliper is not permitted. 13 4. Backfill and Plant Soil Mix: 14 a. Use soil excavated from the plant pits or beds or provide a loose, friable soil 15 mix as specified in the Drawings. 16 b. Provide a mix free of: 17 1) reproductive parts of weeds and grasses 18 2) harmful substances and detrimental amounts of foreign matter 19 c. Use fertilizer when specified in the Drawings. 20 B. Landscape Edging 21 1. Concrete 22 a. Concrete Class: Class A 23 2. Decorative Concrete 24 a. Concrete Class: Class A 25 b. Provide the amount of color to be added to the concrete during production with 26 the concrete mix design. 27 c. Provide color in accordance with the requirements of the Drawings and Section 28 32 13 16. 29 3. Plastic and Metal 30 a. Plastic and metal landscape edging are not permitted unless otherwise specified 31 in the Drawings or approved in writing by the City. 32 b. Plastic and metal landscape edging will be permitted only in locations where 33 the proposed landscape edging is matching existing. 34 c. Provide the City with a shop drawing to review prior to purchasing the 35 landscape edging. 36 C. Topsoil 37 1. Approved Topsoil Sources: 38 a. Within the Right of Way: 39 1) Obtain topsoil from the right of way at sites of proposed excavation or 40 embankment when specified in the Drawings, or as directed by the City. 41 b. Outside the Right of Way: 42 1) Obtain topsoil from approved sources in accordance with Article 7.7 43 “Preservation of Cultural and Natural Resources and the Environment”. 44 2. Topsoil characteristics: 45 a. Easily cultivated and fertile 46 32 93 00 PLANTINGS Page 13 of 24 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 b. Free of objectionable material including subsoil, weeds, clay lumps, non-soil 1 materials, roots, stumps, or stones larger than 1 inch in diameter 2 c. Resists erosion 3 d. Able to support plant growth 4 e. When tested: 5 1) pH: 5.5 to 8.5 per Tex-128-E 6 2) Liquid Limit: 50 or less 7 3) Plasticity Index: 20 or less 8 4) Gradation: Maximum of 10 percent passing the No. 200 sieve 9 D. Seeding 10 1. General 11 a. Provide seed from the previous season’s crop in accordance with Texas Seed 12 Law including the testing and labeling for pure live seed (PLS=Purity x 13 Germination). 14 b. Furnish Seed of the designated species in unopened and labeled bags or 15 containers. 16 c. Use within 12 months from the date of the analysis. 17 d. When Buffalograss is specified, use seed treated with potassium nitrate 18 (KNO3). 19 2. Availability of Seed 20 a. The City may permit the use of an alternative seed variety if the specified seed 21 is not available. 22 b. Receive approval in writing before using an alternative seed variety. 23 3. Unacceptable Seed Varieties 24 a. Johnson Grass 25 b. Nut Grass 26 c. Use a seed product that does not contain more than 10 percent by weight of the 27 total of pure live seed of weed seed. 28 4. Approved Seed Varieties 29 a. Do not plant wildflower seed mixes: 30 1) within 10 feet of a road or parking lot 31 2) within 3 feet of a sidewalk, trail, or other walkway 32 b. Ditch, Channel, and Rural Area Seeding: 33 1) Plant between February 1 and May 15 34 35 32 93 00 PLANTINGS Page 14 of 24 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 Table 1 1 Ditch, Channel, and Rural Area Seed Mix 2 Clay Soils Species and Rates (pound PLS per acre) Sandy Soils Species and Rates (pound PLS per acre) Green Sprangletop (Van Horn) Sideoats Grama (Haskell) Texas Grama (Atascosa) Hairy Grama (Chaparral) Shortspike Windmillgrass (Welder) Little Bluestem (OK Select) 1.0 1.0 1.0 0.4 0.2 0.8 Green Sprangletop (Van Horn) Hooded Windmillgrass (Mariah) Shortspike Windmillgrass (Welder) Hairy Grama (Chaparral) Slender Grama (Dilley) Sand Lovegrass (Mason) Sand Dropseed (Borden County) Little Bluestem (OK Select) 1.0 0.2 0.2 0.4 1.0 0.2 0.2 0.8 Wildflower Seed Mixes Purple Prairie Clover (Cuero) Englemann Daisy (Eldorado) Illinois Bundleflower Awnless Bushsunflower (Plateau) 0.6 0.75 1.3 0.2 Partridge Pea (Comanche) Englemann Daisy (Eldorado) Purple Prairie Clover 0.6 0.75 0.3 c. Urban Area Seeding 3 1) Plant between February 1 and May 15 4 Table 2 5 Urban Area Seed Mix 6 Clay Soils Species and Rates (pound PLS per acre) Sandy Soils Species and Rates (pound PLS per acre) Green Sprangletop Sideoats Grama (El Reno) Buffalograss (Texoka) Bermudagrass 0.3 3.6 1.6 2.4 Green Sprangletop (Van Horn) Buffalograss (Texoka) Bermudagrass Sand Dropseed (Borden County) 0.3 1.6 3.6 0.4 d. Cool Weather Seeding 7 1) Plant between September 1 and November 30 8 Table 3 9 Cool Weather Seed Mix 10 Species and Rates (pound PLS per acre) Tall Fescue Western Wheatgrass Wheat (Red, Winter) 4.5 5.6 34 e. Warm Weather Seeding 11 1) Plant between May 1 and August 31 12 Table 4 13 Warm Weather Seed Mix 14 Species and Rates (pound PLS per acre) 32 93 00 PLANTINGS Page 15 of 24 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 Foxtail Millet 34 E. Sodding 1 1. Do not use sod from areas where the grass is thinned out. 2 2. Approved Sod Varieties 3 a. St. Augustine grass 4 b. Common Bermudagrass 5 c. Buffalograss 6 d. Approved varieties of Bermudagrass and Zoysia Grass 7 e. Match existing grass varieties where possible. 8 3. Acceptable Growing Bed Properties: 9 a. St. Augustine: 10 1) Clay or Clay Loam topsoil 11 b. Bermudagrass and Zoysia Grass: 12 1) Sandy or Sandy Loam soils 13 4. Sod characteristics: 14 a. Block, rolled, or solid 15 b. Free from insects, noxious weeds, Johnson grass, other grasses, stones, or any 16 matter deleterious to the growth and subsistence of the sod 17 c. Alive and growing grass and is of the type specified in the Drawings 18 d. Contains stolons, leaf blades, rhizomes, and dense matted roots throughout the 19 soil of the sod for a minimum of 1 inch 20 5. Acceptable Sod Dimensions 21 a. Machine cut to uniform soil thickness. 22 b. Has a uniform width and can be easily lifted, handled, and rolled without 23 breaking. 24 c. Minimum Sod Thickness: 3/4 inch 25 d. Maximum Grass Height: 2 inches 26 6. Keep sod material moist from the time it is dug until it is planted. Grass sod with 27 dried roots will be considered non-conforming. Any grass installed with dried roots 28 will be removed and replaced at no cost to the City. 29 7. Mulch sod is not approved for use. 30 8. Any broken or torn sod or sod with uneven ends will be considered non-conforming 31 and will be rejected. Remove any non-conforming sod at no cost to the City. 32 F. Landscape Restoration 33 1. Inventory all existing plantings prior to any construction activity. 34 2. Contractor to replace any existing plantings that have been damaged due to 35 construction activities and restore the landscape site to the existing condition or 36 better. 37 G. Water 38 1. Provide clean water free of industrial wastes and other substances harmful to the 39 growth of vegetation. 40 H. Fertilizer 41 32 93 00 PLANTINGS Page 16 of 24 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1. Provide fertilizer in accordance with the requirements of the Texas Fertilizer Law 1 and passes testing by the Texas A&M Feed and Fertilizer Control Service. 2 2. Acceptable Nitrogen, Phosphorus, and Potassium Composition 3 a. 16 percent Nitrogen, 20 percent Phosphorus, and 0 percent Potassium 4 b. 16 percent Nitrogen, 8 percent Phosphorus, and 8 percent Potassium 5 c. Ensure that 50 percent of the nitrogen component is a slow-release sulfur-6 coated urea. 7 I. Mulch 8 1. For Use on Seeding: 9 a. Straw Mulch: 10 1) Oat, wheat, or rice straw 11 b. Hay Mulch: 12 1) Hay mulch of either Bermudagrass or prairie grasses. 13 c. Characteristics: 14 1) Free of Johnson grass and other noxious and foreign materials. 15 2) Dry and free from molded or rotted material. 16 2. For Use on Landscape Areas: 17 a. Provide no float cypress mulch or approved equal. 18 b. Mulch characteristics: 19 1) is free from growth or germination inhibiting qualities; and 20 2) contains no more than 10 percent moisture. 21 J. Tacking Materials 22 1. Use a tacking agent applied in accordance with manufacturer’s recommendations or 23 a crimping method on all straw or hay mulch operations. 24 2. Use tacking agents as approved or as specified in the Drawings. 25 2.3 ACCESSORIES [NOT USED] 26 2.4 SOURCE QUALITY CONTROL 27 A. Tests and Inspections 28 B. Non-Conforming Work 29 1. Rejection of Plants 30 a. Plants with any of the following characteristics are subject to rejection: 31 1) Disease or insect infestation, including eggs and larvae 32 2) Dried or damaged root system or crown 33 3) Excessive abrasion of the bark 34 4) Prematurely opened or damaged buds 35 5) Disfiguring knots 36 6) Evidence of heat, freeze, windburn, mold, sub scale, or similar conditions 37 7) Damaged, pruned, crooked, or multiple leaders, unless multiple leaders are 38 specified or are normal for the species 39 8) Cut limbs over 3/4 inch in diameter that have not completely callused 40 9) Dry, soggy, loose, cracked, broken, misshapen, or undersized root balls 41 10) Processed balled roots (bench balled) 42 11) Root balls encased in impervious material 43 12) Overgrown or root-bound plants 44 32 93 00 PLANTINGS Page 17 of 24 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 13) Undersized or unsound containers 1 14) Containers with less than ¾ planting medium depth 2 15) An abnormal balance between height and spread for the species 3 16) Missing or broken serialized locking tags, when specified 4 17) Any condition not in accordance with the Drawings or nursery stock 5 standards 6 18) Conditions that would prevent thriving growth or cause an unacceptable 7 appearance 8 C. Manufacturer Services 9 D. Coordination of Other Tests and Inspections 10 PART 3 - EXECUTION 11 3.1 INSTALLERS [NOT USED] 12 3.2 EXAMINATION [NOT USED] 13 3.3 PREPARATION 14 A. Surface Preparation 15 1. Plants 16 a. Mark Plant Locations and Bed Outlines 17 1) Provide and install markings such as wooden stakes to mark the locations, 18 types of plants, and the outline of planting beds. 19 2) Obtain approval from the City and any applicable landscape bed owners of 20 the plant and bed locations before any planting activities begin. 21 2. Plant Bed Preparation 22 a. Prepare the bed and install the planting soil mix, vegetation barrier, and other 23 materials as specified in the Drawings. 24 3. Plant Soil Preparation 25 a. Clean topsoil of roots, plants, sod, stones, clay lumps, and other foreign 26 materials. 27 b. Mix fertilizer in with topsoil within 48 hours of planting. 28 4. Erosion Control Blanket 29 a. Prepare the site in accordance with the manufacturer’s recommendations and 30 Section 31 25 14. 31 3.4 INSTALLATION 32 A. Finishing of Parkways 33 1. Finishing of parkways is considered subsidiary to pertinent items and will not be 34 paid for separately. 35 2. Smoothly shape parkways, shoulders, slopes, and ditches. 36 3. Grade parkways to finished slopes and elevations prior to the placement of any 37 Plantings within the site. 38 4. Standard Parkway Slopes 39 a. Minimum: 1 percent 40 32 93 00 PLANTINGS Page 18 of 24 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 b. Maximum: 4:1 1 c. Use standard parkway slopes unless otherwise specified in the Drawings or 2 directed by the City. 3 4 d. Where sidewalk is present, maintain the minimum parkway slope in accordance 5 with the following criteria before transitioning to a steeper slope: 6 1) from the back of curb to the face of sidewalk edge 7 2) 2 feet from the back of sidewalk 8 e. If no sidewalk is present, maintain minimum parkway slope 2 feet from the 9 back of curb before transitioning to a steeper slope. 10 B. Plants 11 1. Plant Pit Excavation 12 a. Excavate the receiving pits for mechanically transplanted plants with the same 13 type and size equipment used to dig the plants. 14 b. Depth: 15 1) Excavate pits for container and balled and burlapped stock to the depth 16 specified in the Drawings or at least the depth of the root ball. 17 2) Excavate pits for bare root plants to the depth of the root system. 18 3) Excavate pits on slopes using measurements specified in the Drawings or at 19 least the depth of the root ball based on the uphill side of the pit. 20 c. Horizontal Dimensions: 21 1) Provide a minimum horizontal dimension of 12 inches between the root 22 ball and pit walls for the following, unless otherwise specified in the 23 Drawings: 24 a) 15 gallon or larger pots 25 b) 14 inch or larger boxes 26 c) Larger than 14-inch root balls of balled and burlapped plants 27 2) Provide a minimum horizontal dimension of 2 times the root ball diameter 28 across the pit for the following, unless otherwise specified in the Drawings: 29 a) Less than 15-gallon pots 30 b) 14 inch or smaller root balls of balled and burlapped plants. 31 3) Provide a minimum pit diameter for bare root plants in accordance with the 32 supplier’s recommendations and allows the roots to spread without 33 crowding or curving around the walls of the pit. 34 2. Plant Installation 35 a. General Plant Installation: 36 1) Install plants within 24 hours of excavating plant pits. Cover or barricade 37 any planting pit to remain open overnight. 38 2) Scarify the walls of pits as plant installation begins. 39 3) Lift plants only from the bottom of the root balls or with belts or lifting 40 harnesses that are wide enough to not damage the root balls. 41 4) Center all plants in a pit, except those mechanically collected, and back fill 42 in lifts using topsoil, fertilized topsoil, or planting mix as directed. 43 5) Backfill in lifts where each lift is 1/3 of the depth of the root ball. 44 6) Fill the pit with water after each lift to remove air pockets. 45 b. Containerized Plants: 46 1) Remove plastic, paper, or fibrous pots from the containerized plant material 47 before planting. 48 32 93 00 PLANTINGS Page 19 of 24 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2) Pull roots out of the root mat and cut circling roots with a knife. 1 3) Loosen the potting soil and shake away from the root mat. 2 4) Install the plant immediately after removing the container, install the plant. 3 4 c. Balled and Burlapped (B&B) Plants 5 1) Cut and remove ropes or strings from the top of root balls and trees after 6 plant has been set. 7 2) Remove burlap or cloth wrapping and any wire baskets. 8 a) If site conditions do not allow complete removal, remove a minimum 9 of the top two-thirds of balls. 10 3) Do not turn under and bury portions of burlap at top of ball. 11 d. For mechanically collected plants: 12 1) Prune protruding roots from the root ball to a point even with the cutting 13 blades. 14 2) Place the plant in the pit and work sand between the pit walls and the root 15 ball with water until the sand fills all the cavities. 16 e. Apply fertilizer where specified in the Drawings. 17 f. Ensure top of the root ball remains at the grade specified in the Drawings after 18 settlement. 19 3. Pruning: 20 a. Perform in accordance with Section 31 10 00. Provide all required submittals 21 and testing required in accordance with Section 31 10 00. 22 b. Limit pruning to removal of dead and broken branches and as needed to 23 improve the appearance and health of the plants. 24 c. Remove and dispose of pruning debris. 25 4. Plant Supports: 26 a. Install plant supports such as staking, guying, anchoring, and bracing as 27 specified in the Drawings. 28 b. Support and keep plants in a vertical position or as directed. 29 5. Trunk Protection: 30 a. Perform in accordance with Section 31 10 00. Provide all required submittals 31 and testing required in accordance with Section 31 10 00. 32 6. Landscape Edging Installation 33 a. Concrete Landscape Edging (Concrete Mow Strips) 34 1) Concrete Class: Class A, 12 inches wide, 6 inches thick 35 2) Finish: Trowel 36 3) Sawing: 1.5” deep sawcut spaced at 6’ on center 37 4) Jointing: If mow strip is adjacent to the back of curb or other pavement 38 structure, provide a doweled expansion joint between mow strip and 39 pavement. 40 b. Plastic or Metal Edging 41 1) Install landscape edging in accordance with the Drawings and 42 manufacturer’s recommendations. 43 7. Mulching 44 a. Mulch plant beds to a depth of 2 inches unless otherwise specified in the 45 Drawings. 46 C. Landscape Edging 47 32 93 00 PLANTINGS Page 20 of 24 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1. Concrete and Decorative Concrete 1 a. Install in accordance with Sections 03 30 00, 32 13 13, and 32 13 16. 2 2. Plastic and Metal 3 a. Install in accordance with manufacturer’s recommendations. 4 D. Topsoil 5 1. Remove and dispose of objectionable material from the topsoil source before 6 starting work. 7 2. Cultivate the area to a depth of 4 inches before placing topsoil unless sodding is 8 installed. Refer to this Section for topsoil depth requirements. 9 3. Spread 4 inches of topsoil to a uniform loose cover unless another depth is specified 10 in the Drawings. 11 4. Place and shape the topsoil as directed. 12 5. Water and roll the topsoil with a light roller or other suitable equipment. 13 E. Seeding 14 1. General: 15 a. In Areas Without Existing Grass: 16 1) Cultivate the area to a depth of 4 inches before placing the seed. 17 2) Smoothly distribute topsoil to a depth of 4 inches. 18 b. In Areas with Existing Grass: 19 1) Mow the area before placement of the permanent seed. 20 2. Broadcast Seeding: 21 a. Broadcast seed in 2 directions at right angles to each other. 22 b. After placing seeds, perform the following: 23 1) In large seeding areas along ditches, channels, or rural areas: 24 a) Roll the planted area with a light roller or other suitable equipment. 25 2) In urban seeding areas: 26 a) Harrow or lightly rake the area to cover the seed. 27 3) Avoid covering the seed with more soil than twice the seed’s diameter. 28 c. Wildflower Seeding: 29 1) Scalp any existing grass to 1 inch and remove all grass clippings before 30 spreading wildflower seeds. 31 3. Mechanically Seeding (Drilling): 32 a. Uniformly distribute seed over the areas specified in the Drawings. 33 b. All varieties of seed and fertilizer may be distributed at the same time provided 34 that each component is uniformly applied at the specified rate. 35 c. Drill seed at a depth of 1/4 inch to 1/3 inch utilizing a pasture or rangeland type 36 drill. 37 d. Plant seeds along the contour of slopes. 38 e. After planting: 39 1) Roll with a roller that is integral to the seed drill, or use a corrugated roller 40 referred to as a “Cultipacker.” 41 2) Roll sloped areas on the contour. 42 4. Hydromulching is not allowed. 43 5. Fertilize uniformly at the required rate over seeded area. 44 6. Watering and Finishing 45 32 93 00 PLANTINGS Page 21 of 24 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 a. Water soil to a minimum depth of 4 inches within 48 hours of seeding. 1 b. Water twice daily for 14 days after seeding. Take care to prevent washing of the 2 slopes or dislodgement of the seed. 3 1) If seed is washed away due to watering or rainfall, re-seed bare areas until 4 grass meets the required length for final acceptance at no cost to the City. 5 c. Continue watering until after final acceptance. 6 7. Final Turf Requirements 7 a. Continue seeding activities until seeded areas are free of bare areas. 8 b. Established Turf: 9 1) 100 percent growth to a height of 3 inches. 10 2) A minimum of 1 mow cycle has been completed. 11 c. Final acceptance won’t be given until turf has been established. 12 F. Sodding 13 1. General: 14 a. Plant the sod specified and mulch, if required, after the area has been completed 15 to lines and grades as specified in the Drawings. 16 b. Use grass sod of the same grass type as the adjacent grass or existing lawn 17 unless otherwise specified in the Drawings or by the City. 18 c. Plant between the average date of the last freeze in the Spring and 6 weeks 19 before the average date for the first freeze in the Fall according to the Texas 20 Almanac for the project area. 21 d. Use care to retain native soil on the roots of the sod during the process of 22 excavating, hauling, and planting. 23 e. Keep sod material moist from the time it is dug until planted. 24 2. Installation: 25 a. Cultivate the area to a depth of 6 inches before placing the sod. 26 b. Place 4 inches of topsoil in accordance with the type of sod grass being 27 installed. 28 c. Apply fertilizer uniformly over the entire area and water, if required in 29 accordance with the Drawings. 30 d. Place sod so the entire area designated for sodding is covered. 31 e. Fill voids left in the sodding with additional sod and tamp. 32 f. Roll and tamp sod so sod is in complete contact with topsoil at a uniform slope. 33 g. Peg sod with either wooden pegs or wire staples driven through the sod block to 34 the firm earth in areas that may slide. 35 h. Remove portions of dead sod as necessary to provide a uniform established turf 36 before final acceptance. Removal and replacement of dead sod will be done at 37 no cost to the City. 38 i. Ensure top of sod is 1-inch below the top of curb, sidewalk, concrete edging, or 39 any other adjacent structure. 40 3. Watering and Finishing 41 a. Coordinate irrigation installation with planting to ensure plants and grass are 42 receiving adequate water. Contractor is responsible for watering all plantings 43 during construction until final acceptance. 44 b. Thoroughly water sod immediately after planting. 45 c. Continue watering until after final acceptance. 46 d. Established Turf: 47 1) 100 percent growth to a height of 3 inches. 48 32 93 00 PLANTINGS Page 22 of 24 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2) A minimum of 1 mow cycle has been completed. 1 3) Roots have started to peg down 2 4) There are no dead blocks of sod. 3 e. Final acceptance won’t be given until turf has been established. 4 5 G. Erosion Control Blanket 6 1. Install erosion control blanket in accordance with manufacturer’s recommendations 7 and Section 31 25 14. 8 2. Install the erosion control blanket within 24 hours after seeding or sodding has 9 occurred unless otherwise directed. 10 H. Mulching 11 a. Ensure top of sod is 1-inch below the top of curb, sidewalk, concrete edging, or 12 any other adjacent structure. 13 2. For Use on Grass Sod: 14 a. Apply straw or hay mulch uniformly in areas as specified in the Drawings. 15 b. Use an approved tacking method over the mulched area. 16 c. Application Rate: 17 1) Straw Mulch: 18 a) Apply at 2 to 2.5 tons per acre 19 2) Hay Mulch: 20 a) Apply at 1.5 to 2 tons per acre 21 I. Fertilizer 22 1. Apply uniformly at the specified rate over required areas. 23 2. Apply fertilizer as a dry material and do not mix with water to form a slurry. 24 3. Fertilizer Rate: 25 a. Seeding: 26 1) Incorporate during seedbed preparation. 27 2) Not required for wildflower seeding. 28 3) Grass Seeding: 29 a) Newly Established – 100 pounds of nitrogen per acre 30 b) Established Seeding Areas – 150 pounds of nitrogen per acre 31 b. Sod: 32 1) Only required when directed by the City or specified in the Drawings. 33 3.5 REPAIR [NOT USED] 34 3.6 RE-INSTALLATION [NOT USED] 35 3.7 SITE QUALITY CONTROL [NOT USED] 36 3.8 SYSTEM STARTUP [NOT USED] 37 3.9 ADJUSTING [NOT USED] 38 3.10 CLEANING [NOT USED] 39 3.11 CLOSEOUT ACTIVITIES [NOT USED] 40 3.12 PROTECTION [NOT USED] 41 32 93 00 PLANTINGS Page 23 of 24 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3.13 MAINTENANCE 1 A. Maintenance 2 1. Perform maintenance on all plantings until final acceptance of the project. 3 2. Maintenance is considered subsidiary to applicable planting items and will not be 4 paid for separately. 5 3. Mowing, Trimming, and Edging 6 a. Mow, trim, and edge all planting areas within the project limits. 7 b. Mow, trim, and edge at a minimum every 15 days during the growing season 8 unless otherwise directed. 9 c. Mow to a height of 3 to 4 inches in height. 10 d. Keep cord trimmers at least 1 foot from plants to prevent damage. 11 e. Remove and replace all plants damaged during maintenance work. 12 4. Plant Bed and Site Maintenance 13 a. Chemically control weeds and unwanted grasses in plant beds, along structures, 14 and around existing plants within the project side every 15 days unless 15 otherwise directed. 16 b. Reshape plant beds every 30 days as necessary. 17 c. Maintain mulch in plant beds as needed. 18 d. Ensure that herbicides and pesticides do not damage any proposed or existing 19 desirable plants. 20 e. Follow the manufacturer’s recommendations for herbicides and pesticides. 21 5. Plant Supports 22 a. Replace, repair, and adjust supports as needed to meet the requirements of the 23 Drawings. 24 b. Adjust staking and guying to prevent girdling of plant trunks. 25 c. Remove or dispose of support material as directed. 26 6. Insect, Disease, and Animal Treatment 27 a. Inspect plants and planting areas every 15 days. 28 b. Notify the City of concerns, problems, and recommended corrective measures 29 in writing for approval. 30 c. Treat the plants and planting areas in accordance with TDA or TSPCB laws and 31 regulations. 32 d. Follow the manufacturer’s instructions for handling and applying pesticides. 33 7. Plant Replacement 34 a. Remove and dispose of dead and damaged plants from the site as directed. 35 b. Replace plants as originally specified within 10 days of notification. 36 c. Plant replacement must be completed and approved prior to final acceptance. 37 3.14 ATTACHMENTS [NOT USED] 38 39 40 41 32 93 00 PLANTINGS Page 24 of 24 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 END OF SECTION 1 2 Revision Log DATE NAME SUMMARY OF CHANGE 3 33 01 30 POST CONSTRUCTION CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION Page 1 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 13, 2021 Effective July 1, 2024 SECTION 33 01 30 1 POST CONSTRUCTION CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Requirements and procedures for Closed Circuit Television (CCTV) Inspection of 6 all new sanitary sewer mains and services or storm sewer mains prior to: 7 a. Pre-Construction (sanitary sewer mains and services only) 8 b. Final Acceptance 9 c. At the end of the warranty period 10 B. Deviations from this City of Denton Standard Specification: 11 1. None. 12 C. Related Specification Sections include but are not limited to: 13 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 14 Contract. 15 2. Division 1 - General Requirements. 16 3. Section 33 01 32 – Cleaning of Sewer Mains. 17 1.2 PRICE AND PAYMENT PROCEDURES 18 A. Measurement and Payment 19 1. Measurement 20 a. Measurement for this item will be by the linear foot of line televised for CCTV 21 Inspection performed following repair or installation determined from the 22 distance recorded on the video log. 23 2. Payment 24 a. The work performed and materials furnished in accordance with this item and 25 measured as provided under “Measurement” will be paid for at the unit price 26 bid per linear foot for “Post-CCTV Inspection”. 27 1) Contractor will not be paid for unaccepted video. 28 3. The price bid shall include: 29 a. Mobilization 30 b. Cleaning 31 c. Digital file 32 1.3 REFERENCES 33 A. Reference Standards 34 1. Reference standards cited in this Section refer to the current reference standard 35 published at the time of the latest revision date logged at the end of this Section 36 unless a date is specifically cited. 37 2. Pipeline Assessment and Certification Program (PACP) 38 33 01 30 POST CONSTRUCTION CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION Page 2 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 13, 2021 Effective July 1, 2024 3. National Association of Sewer Service Companies (NASSCO) 1 1.4 ADMINISTRATIVE REQUIREMENTS 2 A. Coordination – Coordinate with Inspector 48 hours in advance of work. 3 B. Scheduling: 4 1. CCTV cannot be performed until final surface repair and manhole adjustments are 5 completed. 6 2. CCTV cannot be performed until all items listed in Paragraph 3.3 A have been 7 completed. 8 1.5 SUBMITTALS 9 A. Submittals shall be in accordance with Section 01 33 00. 10 B. All submittals shall be approved by the City prior to delivery. 11 C. Log sheet report must utilize PACP reporting standards. 12 D. Video submittal shall be a digital mpeg file unless otherwise directed by the City and 13 must be compatible with the City’s equipment. 14 E. All information gathered must be legible, easily read or viewed, and of high definition 15 color in accordance with NASSCO. 16 F. Inspection Report shall include: 17 1. Asset 18 a. Date and Time 19 b. City 20 c. Address and/or Project Name 21 d. Main Number – GIS ID (If Available) or Station 22 e. Upstream Manhole GIS ID (If Available) or Station 23 f. Downstream Manhole GIS ID (If Available) or Station 24 g. Pipe Diameter 25 h. Material 26 i. Pipe Length 27 2. Inspection 28 a. Inspection Number (i.e. 1st,2nd, etc…) 29 b. Crew Number 30 c. Operator Name 31 d. Operator Comments 32 e. Reason for Inspection 33 f. Equipment Number 34 g. Camera Travel Direction (Upstream/Downstream) 35 h. Inspected Length (feet) 36 i. City Contract Name and Number 37 j. Contractor Company Name 38 k. Contractor Contact Name 39 l. Contractor Contact Phone Number 40 1.6 INFORMATIONAL SUBMITTALS [NOT USED] 41 1.7 CLOSEOUT SUBMITTALS 42 33 01 30 POST CONSTRUCTION CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION Page 3 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 13, 2021 Effective July 1, 2024 A. Post-CCTV submittals 1 1. Provide PDF copies of CCTV video and Inspection Reports on 2 USB drives. 2 2. Provide 2 hard copies of CCTV Inspection Report. 3 3. Submit to the City for review prior to scheduling a project final walk through. 4 4. The City maintains the right to reject CCTV submittals if the submittals fail to 5 conform to the quality or administrative requirements as specified in this Section 6 (e.g., obstructions on lens, foggy lens, insufficient data, etc.). 7 a. Any additional CCTV inspections performed by the Contractor due to a 8 rejected submittal will be the responsibility of the Contractor. 9 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 10 1.9 QUALITY ASSURANCE [NOT USED] 11 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 12 1.11 FIELD CONDITIONS [NOT USED] 13 1.12 WARRANTY 14 A. A second television inspection by the Contractor shall be started no sooner than 15 630 calendar days after date of Final Acceptance and finished no later than 690 calendar 16 days after the date of Final Acceptance. 17 B. Should the Contractor fail to provide a second original television inspection video with 18 proper documentation to the City by the 690th calendar day, written notice to perform a 19 second television inspection shall be given by the City to the Contractor and the Surety. 20 C. If the Contractor or Surety fail to perform a second televised inspection within 10 21 calendar days of notification, City shall have the right to perform a second television 22 inspection or cause the same to be done, either by contract or otherwise, and to pay for 23 the cost of the second television inspection. 24 1. If such cost of repairs, so made, shall not be paid by the Contractor or Surety upon 25 receipt of notice of the amount thereof: 26 a. City shall have the right of action on the Performance Bond; or 27 b. In case the second television inspection shall not actually be made by City after 28 such failure on the part of the Contractor or Surety: 29 1) City shall have the right to ascertain and determine the cost of such repairs 30 and to maintain an action against the Contractor or Surety; or both under 31 said bond, to recover the amount so determined in any court of competent 32 jurisdiction, and the amount so determined shall be conclusive upon the 33 Contractor and Surety in any action upon said bond. 34 PART 2 - PRODUCTS 35 2.1 EQUIPMENT 36 37 33 01 30 POST CONSTRUCTION CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION Page 4 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 13, 2021 Effective July 1, 2024 A. Closed Circuit Television Camera 1 1. One specifically designed and constructed for sewer inspection 2 2. Be operative in 100 percent humidity/submerged conditions 3 3. Capable of tilting at right angles along the axis of the pipe while panning the 4 camera lens through a full circle about the circumference of the pipe. 5 4. Solid state color and have remote control of the rotational lens. 6 5. Capable of viewing the complete circumference of the pipe and manhole structure, 7 including the cone-section or corbel. 8 6. Lens shall be an auto-iris type with remote controlled manual override. 9 7. Equipment will provide a view of the pipe ahead of the equipment and of features 10 to the side of the equipment through turning and rotation of the lens. 11 8. Lighting for camera shall be suitable to allow a clear picture of the entire periphery 12 of the pipe. 13 a. Lights shall be capable of panning 90-degrees to the axis of the pipe. 14 B. Video Capture System 15 1. The video and audio recordings of the CCTV inspections shall be made using 16 digital video equipment. A video enhancer may be used in conjunction with, but 17 not in lieu of, the required equipment. The digital recording equipment shall 18 capture CCTV inspection on USB drive, with each segment (from upstream 19 manhole to downstream manhole) inspection recorded as an individual file in 20 .MPEG format. 21 2. Capable of printing pipeline inspection reports with captured images of defects or 22 other related significant visual information on a standard color printer. 23 3. Store digitized color picture images and be saved in digital format on a USB drive. 24 4. Able to produce data reports to include, at a minimum, all observation points and 25 pertinent data. 26 5. Camera footage, date, main number, and manhole numbers shall be maintained in 27 real time and shall be displayed on the video monitor as well as the video character 28 generators illuminated footage display at the control console. 29 2.2 EQUIPMENT, PRODUCT TYPES, MATERIALS [NOT USED] 30 2.3 ACCESSORIES [NOT USED] 31 2.4 SOURCE QUALITY CONTROL [NOT USED] 32 PART 3 - EXECUTION 33 3.1 INSTALLERS [NOT USED] 34 3.2 EXAMINATION [NOT USED] 35 3.3 PREPARATION 36 A. General 37 33 01 30 POST CONSTRUCTION CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION Page 5 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 13, 2021 Effective July 1, 2024 1. Prior to inspection obtain pipe and manhole asset identification numbers from the 1 plans or City to be used during inspections, if available. 2 a. If identification numbers are not available at the time of inspection: 3 1) Use pipe and manhole stations corresponding with the design plans. 4 2) Pipe and manhole identification numbers are to be included at the time of 5 the warranty inspection. 6 2. Inspection shall not commence until the sewer section to be televised has been 7 completely cleaned in accordance with Section 33 01 32. 8 a. Sewer system should be connected to existing sewer system and should be 9 active; or 10 b. Sewer may be flooded with clean water, not jetted, in lieu of active sewer. 11 3. Inspection of newly installed sewers not yet in service shall not begin prior to 12 completion of the following: 13 a. Pipe testing 14 b. Completion of all manhole work 15 c. Installation of all lateral services 16 d. Vacuum test of manholes 17 e. Final surface repair 18 4. Temporary Bypass Pumping in accordance with Section 33 32 11, if required. 19 3.4 INSPECTION (CCTV) 20 A. General 21 1. Begin inspection immediately after cleaning of the main. 22 2. Video shall start at the manhole and include a pan video of the starting Manhole. 23 3. Move camera through line in either direction at a moderate rate, stopping when 24 necessary to permit proper documentation of the main’s condition. 25 4. Do not move camera at a speed greater than 30 feet per minute. 26 5. Use manual winches, power winches, TV cable, and power rewinds that do not 27 obstruct camera view, allowing for proper evaluation. 28 6. During investigation, stop camera at each defect along the main. 29 a. Record the nature, location, and orientation of the defect or infiltration location. 30 7. Pan and tilt the camera to provide additional detail at: 31 a. Manholes 32 1) Pan camera around to see condition of manhole including installation of 33 epoxy liner, if applicable. 34 a) Visual confirmation does not relieve the Contractor from performing 35 Quality Control on epoxy liners in accordance with Section 33 01 40. 36 b. Service connections 37 1) Pan camera to get a complete overview of service connection including 38 zooming into service connection, include location (i.e. 3 o’clock, 9 o’clock, 39 etc.) 40 c. Joints 41 1) Include comment on condition, signs of damage, etc. 42 d. Visible pipe defects 43 1) Including but not limited to cracks, broken or deformed pipe, holes, offset 44 joints, obstructions or debris (show as % of pipe diameter). 45 33 01 30 POST CONSTRUCTION CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION Page 6 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 13, 2021 Effective July 1, 2024 a) If debris has been found in the pipe during the post-CCTV inspection, 1 additional cleaning is required and pipe shall be re-televised. 2 e. Infiltration/Inflow locations 3 f. Pipe material transitions 4 g. Other locations that do not appear to be typical for normal pipe conditions 5 h. Note locations where camera is underwater and level as a % of pipe diameter. 6 8. Provide accurate distance measurement. 7 a. The meter device is to be accurate to the nearest 1/10 foot. 8 9. CCTV inspections are to be continuous. 9 a. Do not provide a single segment of main on more than 1 USB drive. 10 b. A single segment is defined from manhole to manhole. 11 3.5 REPAIR 12 A. Make repairs or clean the line if the City notes problems, including but not limited to 13 the following: 14 1. Pulled or slipped joints. 15 2. Rolled gaskets. 16 3. Water infiltration. 17 4. Cracked or damaged pipe. 18 5. Sagging or deformed pipe. 19 6. In pipes with gradients less than 0.7 percent, a maximum one-half inch of standing 20 water will be allowed in 6" through 24" diameter pipes. 21 7. In pipes with gradients 0.7 percent or greater, no standing water is allowed. 22 a. The depths of standing water allowable for mains that are greater than 24" in 23 diameter will be evaluated by the City. 24 8. Structural damage to the pipe. 25 9. Services coming into the main at an angle other than according to the Drawings. 26 10. Services not installed on lots indicated by plans. 27 11. Pipe or manhole invert has debris, soil or residue. 28 12. Failed manhole liners. 29 B. After any repairs, another televised inspection is to be run at no additional cost is 30 required. 31 3.6 RE-INSTALLATION [NOT USED] 32 3.7 FIELD QUALITY CONTROL [NOT USED] 33 3.8 SYSTEM STARTUP [NOT USED] 34 3.9 ADJUSTING [NOT USED] 35 3.10 CLEANING 36 A. Cleaning of sewer mains: 37 1. Clean the mains in accordance with Section 33 01 32. 38 3.11 CLOSEOUT ACTIVITIES [NOT USED] 39 33 01 30 POST CONSTRUCTION CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION Page 7 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 13, 2021 Effective July 1, 2024 3.12 PROTECTION [NOT USED] 1 3.13 MAINTENANCE [NOT USED] 2 3 3.14 ATTACHMENTS [NOT USED] 4 END OF SECTION 5 6 Revision Log DATE NAME SUMMARY OF CHANGE 7 33 01 31 SEWER AND MANHOLE TESTING Page 1 of 6 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 33 01 31 1 SEWER AND MANHOLE TESTING 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Testing for sanitary sewer pipe and manholes prior to placing in service 6 a. Low Pressure Air Test and Deflection (Mandrel) Test for 36-inch and smaller 7 sanitary sewer mains 8 1) Excludes pipe with flow. 9 2) Hydrostatic Testing is not allowed. 10 b. Individual Joint Test for greater than 36-inch sanitary sewer mains 11 1) Excludes pipe with flow. 12 2) Hydrostatic Testing is not allowed. 13 c. Vacuum Testing for sanitary sewer manholes 14 1) Non-standard manholes or manholes installed over an existing sewer main 15 may not require vacuum testing. 16 2. All newly constructed sanitary sewer pipe and manholes shall be cleaned and tested 17 prior being placed into service. 18 B. Deviations from this City of Denton Standard Specification: 19 1. None. 20 C. Related Specification Sections include but are not limited to: 21 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 22 Contract. 23 2. Division 1 - General Requirements. 24 3. Section 03 80 00 – Modifications to Existing Concrete Structures. 25 4. Section 33 01 32 – Cleaning of Sewer Mains. 26 5. Section 33 05 05 – Utility Trench Excavation, Embedment, and Backfill. 27 1.2 PRICE AND PAYMENT PROCEDURES 28 A. Measurement and Payment 29 1. Pipe Testing 30 a. Measurement 31 1) This item is considered subsidiary to the sanitary sewer main (pipe) 32 completed in place. 33 b. Payment 34 1) The work performed and the materials furnishing in accordance with this 35 item are subsidiary to the unit price bid per linear foot of sanitary sewer 36 main (pipe) complete in place, and no other compensation will be allowed. 37 2. Manhole Testing 38 a. Measurement 39 1) This item is considered subsidiary to the manhole completed in place. 40 33 01 31 SEWER AND MANHOLE TESTING Page 2 of 6 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1 b. Payment 2 1) The work performed and the materials furnished in accordance with this 3 item are subsidiary to the unit price bid per each manhole complete in 4 place, and no other compensation will be allowed. 5 1.3 REFERENCES [NOT USED] 6 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 7 1.5 SUBMITTALS 8 A. Submittals shall be in accordance with Section 01 33 00. 9 B. All submittals shall be approved by the City prior to delivery. 10 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 11 1.7 CLOSEOUT SUBMITTALS 12 A. Test and Evaluation Reports 13 1. All test reports generated during testing (pass and fail) 14 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 15 1.9 QUALITY ASSURANCE 16 A. Certifications 17 1. Mandrel Equipment 18 a. If requested by City, provide Quality Assurance certification verifying the 19 equipment used has been designed and manufactured in accordance to the 20 required specifications. 21 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 22 1.11 FIELD CONDITIONS [NOT USED] 23 1.12 WARRANTY [NOT USED] 24 PART 2 - PRODUCTS 25 2.1 CITY-FURNISHED PRODUCTS [NOT USED] 26 2.2 MATERIALS 27 A. Materials 28 1. Mandrel used for deflection test 29 a. Use of an uncertified mandrel or a mandrel altered or modified after certification 30 will invalidate the deflection test. 31 b. Mandrel requirements 32 1) Odd number of legs with minimum of 9 legs 33 2) Effective length not less than its nominal diameter 34 3) Fabricated of rigid and nonadjustable steel 35 33 01 31 SEWER AND MANHOLE TESTING Page 3 of 6 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 4) Fitted with pulling rings at each end 1 5) Stamped or engraved on some segment other than a runner indicating the 2 following: 3 a) Pipe material specification 4 b) Nominal size 5 c) Mandrel outside diameter (OD) 6 6) Mandrel diameter must be 95 percent of inside diameter (ID) of pipe. 7 2.3 ACCESSORIES [NOT USED] 8 2.4 SOURCE QUALITY CONTROL [NOT USED] 9 PART 3 - EXECUTION 10 3.1 INSTALLERS [NOT USED] 11 3.2 EXAMINATION [NOT USED] 12 3.3 PREPARATION 13 A. Low Pressure Air Test (Pipe) 14 1. Clean the sewer main before testing, in accordance with Section 33 01 32. 15 2. Plug ends of all branches, laterals, tees, wyes, and stubs to be included in test. 16 B. Deflection (mandrel) test (Pipe) 17 1. Perform as last work item before final inspection. 18 2. Clean the sewer main and inspect for offset and obstruction prior to testing. 19 C. Individual Joint test (Pipe) 20 1. Perform as pipe installation progresses. 21 2. Clean the sewer main and inspect for offset and obstruction prior to testing. 22 D. Vacuum test (Manhole) 23 1. Plug lifting holes and exterior joints. 24 2. Plug pipes and stub-outs entering the manhole. 25 3. Secure stub-outs, manhole boots, and pipe plugs to prevent movement while 26 vacuum is drawn. 27 4. Plug pipes with drop connections beyond drop. 28 5. Place test head inside the frame at the top of the manhole. 29 3.4 INSTALLATION 30 A. Low pressure air test (Pipe) 31 1. Install plug with inlet tap. 32 2. Connect air hose to inlet tap and a portable air control source. 33 3. Start the stop watch after the stabilization period (3.5 psig minimum pressure). 34 35 33 01 31 SEWER AND MANHOLE TESTING Page 4 of 6 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 4. Determine the time in seconds required for the internal air pressure to reach 2.5 1 psig. Minimum permissible pressure holding time per diameter per length of pipe 2 is computed from the following equation: 3 4 T = (0.0850*D*K) 5 Q 6 Where: 7 T = shortest time, seconds, allowed for air pressure to drop to 1.0 psig 8 K = 0.000419*D*L, but not less than 1.0 9 D = nominal pipe diameter, inches 10 L = length of pipe being tested (by pipe size), feet 11 Q = 0.0015, cubic feet per minute per square foot of internal surface 12 5. UNI-B-6, Table 1 provides required time for given lengths of pipe for sizes 4-inch 13 through 60-inch based on the equation above. 14 6. Stop test if no pressure loss has occurred during the first 25 percent of the 15 calculated testing time. 16 B. Deflection (mandrel) test (Pipe) 17 1. The mandrel is pulled through the pipe by hand to ensure maximum allowable 18 deflection is not exceeded. 19 2. Maximum percent deflection by pipe size is as follows: 20 21 Nominal Pipe Size Inches Percent Deflection Allowed 12 and smaller 5.0 15 through 30 4.0 Greater than 30 3.0 C. Individual Joint test (Pipe) 22 1. Follow procedures in Section 3.4.A, but each individual joint to be 100% tested. 23 The time allowed for the pressure drop from 3.5 psig to 2.5 psig is 10-seconds. 24 2. No joint shall be air tested until the pipe has been backfilled. Perform air testing as 25 pipe installation progresses. Pipe installation shall not exceed 100-feet from the 26 last joint tested. 27 3. Perform visual inspection of each joint immediately after testing. 28 4. If the joint fails to pass the joint air test, necessary repairs as recommended by the 29 pipe manufacturer may be made if approved by City, and the joint retested. 30 a. Failure to pass the air test after repairs have been made may be cause for 31 rejection. 32 D. Vacuum test (Manhole) (prior to backfill) 33 1. Draw a vacuum of 10 inches of mercury and turn off the pump. 34 2. With the valve closed, read the level vacuum level after the required test time. 35 36 33 01 31 SEWER AND MANHOLE TESTING Page 5 of 6 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3. Minimum time required for vacuum drop of 1 inch of mercury is as follows: 1 2 Depth of Manhole, feet 4-foot Dia Seconds 5-foot Dia Seconds 6-foot Dia Seconds 8 20 26 33 10 25 33 41 12 30 39 49 14 35 45 57 16 40 52 67 18 40 59 73 ** T=5 T=6.5 T=8 ** - For manholes over 18-feet deep, add “T” seconds as shown for each respective 3 diameter for each 2 feet of additional depth of manhole to the time shown for 18-foot 4 depth. (Example: A 30-foot deep, 4-foot diameter. Total test time would be 70 seconds. 5 40+6(5) = 70 seconds) 6 4. Manhole vacuum levels observed to drop greater than 1 inch of mercury, fail the 7 test. 8 3.5 REPAIR 9 A. Non-Conforming Work 10 1. Low pressure air test 11 a. Should the air test fail, find and repair leak(s) and retest. 12 2. Deflection (mandrel) test (Pipe) 13 a. Should the mandrel fail to pass, the pipe is considered over-deflected. 14 b. Uncover over-deflected pipe and allow pipe to recover. Reinstall and compact 15 backfill and embedment in accordance with Section 33 05 05 if pipe is not 16 permanently deformed or otherwise damaged. 17 c. If damaged, remove and replace. 18 3. Vacuum test (Manhole) 19 a. Should the vacuum test fail, repair suspect area and retest. 20 1) External repairs required for leaks at pipe connection to manhole. 21 a) Shall be in accordance with Section 03 80 00. 22 2) Leaks within the manhole structure may be repaired internally or 23 externally. 24 3.6 RE-INSTALLATION [NOT USED] 25 3.7 FIELD QUALITY CONTROL [NOT USED] 26 3.8 SYSTEM STARTUP [NOT USED] 27 3.9 ADJUSTING [NOT USED] 28 3.10 CLEANING 29 A. Cleaning of sewer mains: 30 1. Clean the mains in accordance with Section 33 01 32. 31 33 01 31 SEWER AND MANHOLE TESTING Page 6 of 6 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3.11 CLOSEOUT ACTIVITIES [NOT USED] 1 3.12 PROTECTION [NOT USED] 2 3.13 MAINTENANCE [NOT USED] 3 3.14 ATTACHMENTS [NOT USED] 4 END OF SECTION 5 6 Revision Log DATE NAME SUMMARY OF CHANGE 7 33 01 32 CLEANING OF SEWER MAINS Page 1 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 33 01 32 1 CLEANING OF SEWER MAINS 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Procedures for cleaning sanitary sewer mains to remove all debris, solids, sand, 6 grease, grit, etc. from the pipelines and manholes prior to television inspection. 7 B. Related Specification Sections include but are not limited to: 8 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 9 Contract. 10 2. Division 1 - General Requirements. 11 1.2 PRICE AND PAYMENT PROCEDURES 12 A. Measurement and Payment 13 1. Measurement 14 a. This item is considered subsidiary to the sanitary sewer main being cleaned. 15 2. Payment 16 a. The work performed and the materials furnished in accordance with this item 17 are subsidiary to the unit price bid per linear foot of sewer pipe complete in 18 place, and no other compensation will be allowed. 19 1.3 REFERENCES [NOT USED] 20 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 21 1.5 SUBMITTALS [NOT USED] 22 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 23 1.7 CLOSEOUT SUBMITTALS [NOT USED] 24 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 25 1.9 QUALITY ASSURANCE [NOT USED] 26 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 27 1.11 FIELD CONDITIONS [NOT USED] 28 1.12 WARRANTY [NOT USED] 29 PART 2 - PRODUCTS 30 2.1 CITY-FURNISHED PRODUCTS [NOT USED] 31 32 33 01 32 CLEANING OF SEWER MAINS Page 2 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2.2 MATERIALS 1 A. Materials 2 1. Use only the type of cleaning material which will not create hazards to health or 3 property or affect treatment plant processes. 4 2.3 ACCESSORIES [NOT USED] 5 2.4 SOURCE QUALITY CONTROL [NOT USED] 6 PART 3 - EXECUTION 7 3.1 INSTALLERS [NOT USED] 8 3.2 EXAMINATION [NOT USED] 9 3.3 PREPARATION [NOT USED] 10 3.4 INSTALLATION [NOT USED] 11 3.5 REPAIR [NOT USED] 12 3.6 RE-INSTALLATION [NOT USED] 13 3.7 FIELD QUALITY CONTROL [NOT USED] 14 3.8 SYSTEM STARTUP [NOT USED] 15 3.9 ADJUSTING [NOT USED] 16 3.10 CLEANING 17 A. General 18 1. All materials, equipment, and personnel necessary to complete the cleaning of the 19 sanitary sewer main and manholes must be present on the jobsite prior to isolating 20 the sewer manhole or line segment and beginning the cleaning process. 21 2. Maintain clean work and surrounding premises within the work limits so as to 22 comply with Federal, State, and local environmental and anti-pollution laws, 23 ordinances, codes, and regulations when cleaning and disposing of waste materials, 24 debris, and rubbish. 25 3. Keep the work and surrounding premises within work limits free of accumulations 26 of dirt, dust, waste materials, debris, and rubbish. 27 4. Suitable containers for storage of waste materials, debris, and rubbish shall be 28 provided until time of disposal. 29 a. It is the sole responsibility of the Contractor to secure a licensed legal dump site 30 for the disposal of this material. 31 b. Under no circumstances shall sewage or solids removed from the main or 32 manhole be dumped onto streets or into ditches, catch basins, storm drains, or 33 sanitary sewers. 34 5. The cleaning process shall remove all grease, sand, silts, solids, rags, debris, etc. 35 from each sewer segment, including the manhole(s). 36 33 01 32 CLEANING OF SEWER MAINS Page 3 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 6. Selection of cleaning equipment and the method for cleaning shall be based on the 1 condition of the sanitary sewer mains at the time work commences and will be 2 subject to approval by the City. 3 7. All cleaning equipment and devices shall be operated by experienced personnel. 4 8. Satisfactory precautions shall be taken to protect the sanitary sewer mains and 5 manholes from damage that might be inflicted by the improper use of the cleaning 6 process or equipment. 7 9. Any damages done to a sewer main and/or structure by the Contractor shall be 8 repaired by the Contractor at no additional cost and to the satisfaction of the City. 9 10. Cleaning shall also include washing the manhole wall by high pressure water jet. 10 11. The Contractor may be required to demonstrate the performance capabilities of the 11 cleaning equipment proposed for use on the project. 12 a. If the results obtained by the proposed sanitary sewer cleaning equipment are 13 not satisfactory, the Contractor shall use different equipment and/or 14 attachments, as required, to meet City satisfaction. 15 b. More than 1 type of equipment/attachments may be required at a location. 16 12. When high velocity cleaning equipment is used, a suitable sand trap, weir, dam, or 17 suction shall be constructed in the downstream manhole to trap all solids and debris 18 for removal. 19 13. Any damage of property, as a result of flooding, shall be the liability and 20 responsibility of the Contractor. 21 14. The flow of wastewater present in the sanitary sewer main shall be utilized to 22 provide necessary fluid for hydraulic cleaning devices whenever possible. 23 15. When additional quantities of water from fire hydrants are necessary to avoid delay 24 in normal working procedures, the water shall be conserved and not used 25 unnecessarily. 26 a. No fire hydrant shall be obstructed or used when there is a fire in the area. 27 b. It is the responsibility of the Contractor to obtain a fire hydrant water meter and 28 establish responsibility for all related charges for the set-up, including the water 29 usage bills from respective water purveyor agency. 30 c. All expenses shall be considered incidental to the cleaning of the existing 31 sanitary sewer mains. 32 B. Methods 33 1. High-Velocity Cleaning 34 a. Cleaning equipment that uses a high velocity water jet for removing debris shall 35 be capable of producing a minimum volume of 50 gpm, with a pressure of 36 1,500 psi, for the sanitary sewer line and 3,500 psi for the (manhole) structure 37 at the pump. 38 1) Any variations to this pumping rate must be approved in advance by the 39 City. 40 2) To prevent damage to older sewer mains and property, a pressure less than 41 1,500 psi can be used with City approval. 42 3) A working pressure gauge shall be used on the discharge of all high 43 pressure water pumps. 44 33 01 32 CLEANING OF SEWER MAINS Page 4 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 4) For sewers 18 inches and larger in diameter, in addition to conventional 1 nozzles, use a nozzle which directs the cleaning force to the bottom of the 2 pipe. 3 5) Operate the equipment so the pressurized nozzle continues to move at all 4 times. 5 6) The pressurized nozzle shall be turned off or reduced anytime the hose is 6 on hold or delayed in order to prevent damage to the line. 7 2. Mechanical Cleaning 8 a. Mechanical cleaning, in addition to normal cleaning when required, shall be 9 with equipment and accessories typically used for this application driven by 10 power winching devices. 11 b. Submit the equipment manufacturer's operational manual and guidelines to the 12 City, which shall be followed strictly unless modified by the City. 13 c. All equipment and devices shall be operated by experienced operators to ensure 14 no damage to the pipe occurs in the process of cleaning. 15 d. Buckets, scrapers, scooters, porcupines, kites, heavy duty brushes, and other 16 debris-removing equipment/accessories shall be used as appropriate and 17 necessary in the field, in conjunction with the approved power machines. 18 e. The use of cleaning devices such as rods, metal pigs, porcupines, root saws, 19 snakes, scooters, sewer balls, kites, and other approved equipment, in 20 conjunction with hand winching device, and/or gas, electric rod propelled 21 devices, shall be considered normal cleaning equipment. 22 3. Hydraulic Cleaning (pipe flooding) is not allowed. 23 3.11 CLOSEOUT ACTIVITIES [NOT USED] 24 3.12 PROTECTION [NOT USED] 25 3.13 MAINTENANCE [NOT USED] 26 3.14 ATTACHMENTS [NOT USED] 27 END OF SECTION 28 29 Revision Log DATE NAME SUMMARY OF CHANGE 30 33 01 33 PIPE BURSTING Page 1 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 33 01 33 1 SANITARY SEWER PIPE BURSTING 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Requirements to rehabilitate existing sanitary sewers by the pipe enlargement 6 system, herein called Pipe Bursting (Pipe Bursting/Crushing). 7 a. Sizes range from 6-inch through 20-inch for the new pipe. 8 1) Pipe larger than 20-inch will require City approval. 9 b. The system includes splitting or bursting the existing pipe to install a new high-10 density polyethylene (HDPE) pipe and reconnecting existing sewer service 11 connections. 12 B. Deviations from this City of Denton Standard Specification: 13 1. None. 14 C. Related Specification Sections include but are not limited to: 15 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 16 Contract. 17 2. Division 1 - General Requirements. 18 3. Section 33 01 30 – Closed Circuit Television (CCTV) Inspection. 19 4. Section 33 05 62 – Cast-in-Place Concrete Manholes. 20 5. Section 33 14 14 – High Density Polyethylene (HDPE) Pipe. 21 6. Section 33 31 16 – Sanitary Sewer Service Connections and Service Line. 22 7. Section 33 32 11 – Bypass Pumping of Existing Sewer Systems. 23 1.2 PRICE AND PAYMENT PROCEDURES 24 A. Measurement and Payment 25 1. Pipe Installation by Pipe Bursting 26 a. Measurement 27 1) Measured horizontally along the ground surface from center line to center 28 line of the manhole or appurtenance of HDPE Pipe installed by Pipe 29 Bursting. 30 b. Payment 31 1) The work performed and materials furnished in accordance with this item 32 and measured as provided under “Measurement” will be paid for at the unit 33 price bid per linear foot for “Pipe Bursting” installed for: 34 a) Various sizes. 35 c. The price bid shall include: 36 1) Furnishing and installing pipe as specified by the Drawings 37 2) Pre-CCTV 38 3) Pavement removal 39 4) Excavation 40 33 01 33 PIPE BURSTING Page 2 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 5) Hauling 1 6) Launching pit 2 7) Receiving pit 3 8) Obstruction removal and disposal 4 9) Bypass Pumping for pipes 12-inch and smaller 5 10) Disposal of excess material 6 11) Furnishing, placement, and compaction of embedment 7 12) Furnishing, placement, and compaction of backfill 8 13) Fittings or couplings if necessary 9 14) Reinstatement of benches/inverts 10 15) Anchoring new pipe and sealing manholes 11 16) Clean-up 12 17) Cleaning 13 18) Testing 14 2. Point Repair 15 a. Measurement 16 1) Measured horizontally along the ground surface following the pipe 17 centerline for the length identified during the Pre-CCTV inspection and 18 directed by the City. 19 b. Payment 20 1) The work performed and materials furnished in accordance with this item 21 and measured as provided under “Measurement” will be paid for at the unit 22 price bid per linear foot for “Sewer Pipe, Point Repair” installed for: 23 a) Various sizes. 24 c. The price bid shall include: 25 1) Furnishing and installing pipe as specified by the Drawings 26 2) Pre-CCTV 27 3) Repair clamps or couplings 28 4) Pavement removal 29 5) Excavation 30 6) Hauling 31 7) Bypass Pumping for pipes 12-inch and smaller 32 8) Disposal of excess material 33 9) Furnishing, placement, and compaction of embedment 34 10) Furnishing, placement, and compaction of backfill 35 11) Clean-up 36 12) Cleaning 37 13) Testing 38 3. Service Reinstatement, Pipe Bursting 39 a. Measurement 40 1) Measured per each service to be reinstated. 41 b. Payment 42 1) The work performed and materials furnished in accordance with this Item 43 and measured as provided under “Measurement” shall be paid for at the 44 unit price bid per each “Service Reinstatement, Pipe Bursting.” 45 c. The price bid shall include: 46 1) Furnishing and installing pipe as specified by the Drawings 47 2) Repair clamps or couplings 48 33 01 33 PIPE BURSTING Page 3 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3) Pre-CCTV 1 4) Pavement removal 2 5) Excavation 3 6) Hauling 4 7) Launching pit, if necessary 5 8) Receiving pit, if necessary 6 9) Bypass Pumping for pipes 12-inch and smaller 7 10) Disposal of excess material 8 11) Furnishing, placement, and compaction of embedment 9 12) Furnishing, placement, and compaction of backfill 10 13) Clean-up 11 14) Cleaning 12 15) Testing 13 1.3 REFERENCES 14 A. Abbreviations and Acronyms 15 1. HDPE – High Density Polyethylene 16 2. CCTV – Closed Circuit Television 17 B. Definitions 18 1. Pipe Bursting/Crushing/Enlargement 19 a. The reconstruction of gravity sewer pipe by installing an approved pipe 20 material by use of a static, hydraulic or pneumatic hammer “moling” device, 21 suitably sized to break out the old pipe or by using a modified boring “knife” 22 with a flared plug that implodes and crushes the existing sewer pipe. 23 b. Forward progress of the "mole" or the "knife" may be aided by the use of 24 hydraulic equipment or other apparatus. 25 c. The replacement pipe is either pulled or pushed into the bore. 26 d. The method allows for replacement of pipe sizes from 6-inches through 20-27 inches and/or upsizing in varying increments up to 20-inches. 28 e. No other Pipe Enlargement system, other than those listed in this Section, is 29 acceptable. 30 1.4 ADMINISTRATIVE REQUIREMENTS 31 A. Coordination 32 1. Coordinate with City, franchise utilities, etc. as specified in the Drawings. 33 2. Provide advanced notice prior to commencing actual pipe enlargement activities, as 34 specified in the Drawings, in order to allow the City to provide appropriate 35 advanced notice to affected residents. 36 3. Review the location and number of insertion or access pits with the City Inspector 37 prior to excavation. 38 B. Sequencing 39 1. Provide a bypass pumping plan, for existing 15-inch and larger sewer lines, 40 detailing collection and discharge locations and method of bypass pumping in 41 accordance with Section 33 32 11, prior to the start of construction. 42 2. Provide a phasing plan with the sequence of construction prior to the start of 43 construction. 44 33 01 33 PIPE BURSTING Page 4 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1 1.5 SUBMITTALS 2 A. Submittals shall be in accordance with Section 01 33 00. 3 B. All submittals shall be approved by the City prior to delivery. 4 1.6 ACTION SUBMITTALS 5 A. Special Procedure Submittals 6 1. Provide a bypass pumping plan for existing 15-inch and larger sewer lines, in 7 accordance with Section 33 32 11. 8 2. Provide a phasing plan with the sequence of construction prior to the start of 9 construction. 10 B. Submit Contractor and personnel experience records in accordance with this Section 11 1.7 CLOSOUT SUBMITTALS 12 A. Record Documentation 13 1. Provide Post-Construction CCTV inspection reports in accordance with Section 33 14 01 30. 15 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 16 1.9 QUALITY ASSURANCE 17 A. Qualifications 18 1. The Contractor shall be certified by the particular Pipe Enlargement system 19 manufacturer that such firm is a licensed installer of their system. 20 2. The Contractor shall be able to show that the personnel directly involved with Pipe 21 Enlargement have adequate experience with similar work and shall have performed 22 a minimum of 50,000 feet of successful installation in the United States. 23 B. Pre-construction and Post-Construction Testing 24 1. Inspection and payment for any Pre-Construction CCTV Inspection will be the sole 25 responsibility of the Contractor. 26 2. Provide Post-Construction CCTV Inspection of the pipeline to be replaced and/or 27 enlarged in accordance with Section 33 01 30. 28 1.10 DELIVERY, STORAGE, AND HANDLING 29 A. Storage and Handling Requirements 30 1. Secure and maintain a location to store the material in accordance with Section 01 31 66 00. 32 1.11 SITE CONDITIONS [NOT USED] 33 1.12 WARRANTY [NOT USED] 34 33 01 33 PIPE BURSTING Page 5 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 PART 2 - PRODUCTS 1 2.1 CITY-FURNISHED [NOT USED] 2 2.2 MATERIALS 3 A. HDPE Pipe in accordance with Section 33 14 14. 4 B. Service Saddles/lateral connections in accordance with Section 33 31 16. 5 C. Repair Clamps in accordance with Section 33 14 14. 6 D. Manhole Inverts and Benches requiring replacement in accordance with Section 33 05 7 62. 8 2.3 ACCESSORIES [NOT USED] 9 2.4 SOURCE QUALITY CONTROL [NOT USED] 10 PART 3 - EXECUTION 11 3.1 INSTALLERS [NOT USED] 12 3.2 EXAMINATION 13 A. Verification of Conditions 14 1. Perform Pre-Construction CCTV Inspection of the pipeline to be replaced/enlarged. 15 a. Inspection of the pipelines shall be performed by experienced personnel trained 16 in locating breaks, obstacles, and service connections by Closed Circuit Color 17 Television. 18 B. Evaluation and Assessment 19 1. Identify, by location, the presence of line obstructions in the existing sewer (heavy 20 solids, dropped joints, protruding service taps, or collapsed pipe) which will prevent 21 completion of the pipe bursting/crushing process and which cannot be removed by 22 conventional sewer cleaning equipment. 23 2. Identify, by location, the presence of sags in the sewer line(s) by the following 24 procedure: 25 a. Perform CCTV inspection. 26 b. Provide CCTV inspection results to the City. 27 c. The City Inspector will review the Pre-CCTV to determine if any excessive 28 sags exist and will inform the Contractor which segments of pipe are to be 29 replaced by point repair. 30 3.3 PREPARATION 31 A. Bypassing Sewage 32 1. Bypass pump sewage in accordance with Section 33 32 11. 33 B. Line Obstructions 34 1. If identified in the CCTV inspection, remove line obstruction. 35 a. Removal of obstruction is considered subsidiary to pipe bursting. 36 33 01 33 PIPE BURSTING Page 6 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 C. Point Repairs 1 1. Perform point repair as specified in the Drawings and at the discretion of the City 2 including: 3 1) Pipe replacement 4 2) Digging a sag elimination pit and bringing the bottom of the pipe trench to 5 a uniform grade in line with the existing pipe invert 6 3.4 INSTALLATION 7 A. Site Organization 8 1. Locate insertion or access pits to minimize the total number required and to 9 maximize the length of replacement pipe installed in a single pull. 10 a. Use existing manholes wherever practical. 11 1) Manhole inverts and bottoms may be removed to permit access for 12 installation equipment. 13 2. Locate equipment used to perform the Work away from buildings so as to minimize 14 noise impact. 15 a. Provide silencers or other devices to reduce machine noise as needed in 16 accordance with City noise ordinance. 17 3. Insertion pits shall be of sufficient length to allow the bursting head and new HDPE 18 pipe to enter the host pipe at an angle that will maintain the grade of the existing 19 sanitary sewer. 20 B. Schedule 21 1. Do not begin pipe bursting/enlargement operations if segment cannot be completed 22 before the end of the same work day. 23 C. Finished Pipe 24 1. The installed replacement pipe shall be continuous over the entire length of each 25 pipe segment from manhole to manhole and free from visual defects such as foreign 26 inclusions, concentrated ridges, discoloration, pitting, varying wall thickness, pipe 27 separation, and other deformities. 28 2. Carefully cut out the replacement pipe passing through or terminating in a manhole 29 in manner approved by the City. 30 3. Streamline and improve the manhole invert and benches to ensure smooth flow. 31 4. The installed pipe shall meet the leakage requirements of the pressure test specified 32 herein. 33 D. Pipe Jointing 34 1. Assemble and join sections of HDPE replacement pipe on the job site above 35 ground. 36 2. Use the heating and butt-fusion system for jointing in strict accordance with the 37 manufacturer's printed instructions and in accordance to Section 33 14 14. 38 3. Ensure butt-fusion joints have a smooth, uniform, double rolled back bead made 39 while applying the proper melt, pressure, and alignment. 40 4. Make all joints available for inspection by City prior to insertion. 41 5. Join the replacement pipe on site in appropriate working lengths near the insertion 42 pit. 43 33 01 33 PIPE BURSTING Page 7 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 a. Limit the maximum length of continuous replacement pipe assembled above 1 ground and pulled on the job site at any one time to 500 linear feet. 2 6. For situations where the replacement pipe is not pulled all the way to the manhole, 3 utilize a repair clamp to connect segments of the HDPE pipe, as approved by the 4 City. 5 E. New Pipe Installation 6 1. Install new pipe in accordance with the manufacturer’s recommendations. 7 F. Anchoring New Pipe and Sealing Manholes 8 1. After the new pipe has been installed in the entire length of the sewer section, 9 anchor the pipe at manholes. 10 a. The new pipe shall protrude in the manholes for enough distance to allow 11 sealing and trimming, but not less than 4 inches. 12 2. Wait a minimum of 10 hours after installation before sealing the new pipe at 13 manholes. 14 3. Provide a flexible gasket connector in the manhole wall at the end of the new pipe, 15 centered in the existing manhole wall. 16 4. Grout flexible connector in the manhole, filling all voids the full thickness of the 17 manhole wall. 18 5. Restore manhole bottom and invert if required, in accordance with Section 33 05 19 62. 20 G. Sewer Service Connections 21 1. Install service connections in accordance with Section 33 31 16. 22 H. Rescue 23 1. The cost for rescue of static, hydraulic, or pneumatic hammer “moling” devices or 24 modified boring “knives” that become stuck or excessively buried and require 25 additional excavation to retrieve shall be the sole responsibility of the Contractor. 26 I. Surface Restoration 27 1. Any damage caused to paving structures or any surface fracture resulting from the 28 pipe enlargement shall be repaired or replaced to the same condition, or better, at 29 the expense of the Contractor. 30 3.5 REPAIR [NOT USED] 31 3.6 RE-INSTALLATION [NOT USED] 32 3.7 SITE QUALITY CONTROL 33 A. Post-Construction Closed Circuit Television (CCTV) Inspection 34 1. Video Inspection 35 a. Conduct a Post-Construction CCTV Inspection in accordance with Section 33 36 01 30. 37 3.8 SYSTEM STARTUP [NOT USED] 38 3.9 ADJUSTING [NOT USED] 39 33 01 33 PIPE BURSTING Page 8 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3.10 CLEANING [NOT USED] 1 3.11 CLOSEOUT ACTIVITIES [NOT USED] 2 3.12 PROTECTION [NOT USED] 3 3.13 MAINTENANCE [NOT USED] 4 5 3.14 ATTACHMENTS [NOT USED] 6 END OF SECTION 7 8 Revision Log DATE NAME SUMMARY OF CHANGE 9 33 01 40 LINERS FOR SANITARY SEWER STRUCTURES Page 1 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 33 01 40 1 LINERS FOR SANITARY SEWER STRUCTURES 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Application of a lining system to concrete utility structures such as manholes, lift 6 station wet wells, junction boxes, or other concrete facilities that may require 7 protection from corrosive materials. 8 a. This covers rehabilitation of existing sanitary sewer structures and newly 9 installed sanitary sewer structures. 10 2. Structures to be lined include all force main discharge manholes, pre-cast manholes, 11 junction structures, lift station wet wells, the manhole preceding a wet well, and any 12 other manhole or structure as specified in the Drawings. 13 B. Related Specification Sections include but are not limited to: 14 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 15 Contract. 16 2. Division 1 - General Requirements. 17 3. Section 33 01 31 – Sewer and Manhole Testing. 18 1.2 PRICE AND PAYMENT PROCEDURES 19 A. Measurement and Payment 20 1. Manholes 21 a. Measurement 22 1) Measured per vertical foot of lining, as measured from the benching to the 23 bottom of the grade rings for new Cast-in-Place manhole installation and 24 from the benching to the bottom of the frame for all types of manhole 25 rehabilitations. 26 b. Payment 27 1) The work performed and materials furnished in accordance with this item 28 and measured as provided under “Measurement” will be paid for at the unit 29 price bid per vertical foot of “Manhole Liner” applied for: 30 a) Various sizes. 31 b) Various types. 32 c. The price bid shall include: 33 1) Removal of roots 34 2) Removal of existing liner 35 3) Eliminating any leaks 36 4) Removal of steps 37 5) Repair/seal connection of the existing frame to chimney 38 6) Repairs of any cracks in the existing structure chimney, corbel (cone), wall, 39 bench, including any replacement of damaged rebar, and pipe 40 7) Surface cleaning and preparation 41 33 01 40 LINERS FOR SANITARY SEWER STRUCTURES Page 2 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 8) Furnishing and installing liner as specified by the Drawings 1 9) Hauling 2 10) Disposal of excess material 3 11) Site Clean-up 4 12) Manhole and Invert Cleaning 5 13) Testing 6 2. New Precast Concrete Manholes 7 a. Measurement 8 1) This item is considered subsidiary to Precast Concrete Manhole 9 installation. 10 b. Payment 11 1) The work performed and materials furnished in accordance with this item 12 are subsidiary to the unit price bid per each Precast Concrete Manhole, and 13 per vertical foot of extra depth Precast Concrete Manhole installed. 14 3. Non-Manhole Structures 15 a. Measurement 16 1) Measured per square foot of area where the liner is applied. 17 b. Payment 18 1) The work performed and materials furnished in accordance with this item 19 and measured as provided under “Measurement” will be paid for at the unit 20 price bid per square foot of “Structure Liner” applied. 21 c. The price bid shall include: 22 1) Removal of roots 23 2) Removal of existing liner 24 3) Eliminating any leaks 25 4) Removal of steps 26 5) Repair/seal connection of the existing frame to chimney 27 6) Repairs of any cracks in the existing structure chimney, corbel (cone), wall, 28 bench, including any replacement of damaged rebar, and pipe 29 7) Surface cleaning and preparation 30 8) Furnishing and installing Liner as specified by the Drawings 31 9) Lining of wet well floor in new applications only 32 10) Hauling 33 11) Disposal of excess material 34 12) Site Clean-up 35 13) Manhole and Invert Cleaning 36 14) Testing 37 1.3 REFERENCES 38 A. Definitions 39 1. Lining and coating may be used interchangeably. 40 B. Reference Standards 41 1. Reference standards cited in this Section refer to the current reference standard 42 published at the time of the latest revision date logged at the end of this Section 43 unless a date is specifically cited. 44 2. ASTM International (ASTM): 45 33 01 40 LINERS FOR SANITARY SEWER STRUCTURES Page 3 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 a. D543, Standard Practices for Evaluating the Resistance of Plastics to Chemical 1 Reagents. 2 b. D638, Standard Test Method for Tensile Properties of Plastics. 3 c. D695, Standard Test Method for Compressive Properties of Rigid Plastics. 4 d. D790, Standard Test Methods for Flexural Properties of Unreinforced and 5 Reinforced Plastics and Electrical Insulating Materials. 6 e. D4060, Standard Test Method for Abrasion Resistance of Organic Coatings by 7 the Taber Abraser. 8 f. D4414, Standard Practice for Measurement of Wet Film Thickness by Notch 9 Gages. 10 3. The Society for Protective Coatings/NACE International (SSPC/NACE): 11 a. SP 13/NACE No. 6, Surface Preparation of Concrete. 12 b. SP0188, Discontinuity (Holiday) Testing of New Protective Coatings on 13 Conductive Substrates. 14 1.4 ADMINISTRATIVE REQUIREMENTS 15 A. Sequencing 16 1. All paving activities, including any final grade adjustments for manholes outside 17 pavement, shall be completed before Contractor begins lining work. 18 2. After liner installation, Contractor shall wait a minimum of 48 hours to allow the 19 liner material to fully cure before returning the system to normal service. 20 1.5 SUBMITTALS 21 A. Submittals shall be in accordance with Section 01 33 00. 22 B. All submittals shall be approved by the City prior to delivery. 23 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 24 A. Product Data 25 1. Technical data sheet on each product used. 26 2. Material Safety Data Sheet (MSDS) for each product used. 27 3. Technical data sheet and project specific data for repair materials to be top-coated 28 with the lining product including application, cure time, and surface preparation 29 procedures. 30 4. Material and method for repair of leaks or cracks in the structure. This applies to 31 repair work on both existing structures, manholes, and newly installed manholes 32 (including Developer projects) that have been identified with cracks, voids, signs of 33 infiltration, other structural defects, or other related construction damage. 34 B. Certification 35 1. Current documentation from lining product manufacturer certifying Contractor’s 36 training (and/or licensure) as an approved installer and equipment compliance with 37 the Quality Assurance requirements. 38 1.7 CLOSEOUT SUBMITTALS 39 A. Testing Documentation 40 1. Provide test results required in Article 3.7 to City. 41 33 01 40 LINERS FOR SANITARY SEWER STRUCTURES Page 4 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 a. Include the following manhole or structure location information: 1 1) Station number. 2 2) GIS ID number, if provided during construction. 3 b. Inspection report of each manhole/structure tested. 4 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 5 1.9 QUALITY ASSURANCE 6 A. Qualifications 7 1. Contractor 8 a. Trained by, or have training approved and certified by, the lining product 9 manufacturer for the handling, mixing, application, and inspection of the lining 10 product(s) to be used. 11 b. Initiate and enforce quality control procedures consistent with the lining 12 product(s) manufacturer recommendations and applicable NACE or SSPC 13 standards. 14 1.10 DELIVERY, STORAGE, AND HANDLING 15 A. Storage and Handling Requirements 16 1. Secure and maintain a location to store the material in accordance with Section 01 17 66 00. 18 2. Keep materials dry, protected from weather, and stored under cover. 19 3. Store lining materials between 50 degrees F and 90 degrees F. 20 4. Do not store near flame, heat, or strong oxidants. 21 5. Handle lining materials according to their material safety data sheets. 22 1.11 FIELD CONDITIONS 23 A. Provide confined space entry, flow diversion, and/or bypass plans as necessary to 24 perform the specified work. Active flows shall be diverted with flow through plugs as 25 required to ensure that flow is maintained off the surfaces to be lined. 26 1.12 WARRANTY [NOT USED] 27 PART 2 - PRODUCTS 28 2.1 CITY-FURNISHED PRODUCTS [NOT USED] 29 2.2 EQUIPMENT, PRODUCT TYPES, MATERIALS 30 A. Manufacturers 31 1. Manufacturer List 32 a. SprayWall by Sprayroq, Inc. 33 b. SpectraShield 34 B. Repair and Resurfacing Products 35 1. Compatible with the specified lining product(s) in order to bond effectively, thus 36 forming a composite system 37 2. Used and applied in accordance with the manufacturer’s recommendations 38 33 01 40 LINERS FOR SANITARY SEWER STRUCTURES Page 5 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3. The repair and resurfacing products must meet the following: 1 a. 100 percent solids, solvent-free epoxy grout specifically formulated for epoxy 2 top coating compatibility 3 b. Factory blended, rapid setting, high early strength, fiber reinforced, non-shrink 4 repair mortar that can be toweled or pneumatically spray applied and 5 specifically formulated to be suitable for top coating with the specified lining 6 product used 7 C. Lining Product 8 1. Capable of being installed and curing properly within a manhole or other concrete 9 structure. 10 2. Resistant to all forms of chemical or bacteriological attack found in municipal 11 sanitary sewer systems, and capable of adhering to typical manhole structure 12 substrates. 13 D. 100 Percent Solids, Rigid, Ultra High-build Polyurethane Lining System: 14 1. Application Temperature – 50 degrees F, minimum 15 2. Thickness – 125 mils minimum for newly installed structures. 16 3. Color – Beige 17 4. Compressive Strength, in accordance with ASTM D695 – 19,000 psi minimum 18 5. Tensile Strength, in accordance with ASTM D638 – 7,400 psi minimum 19 6. Hardness, Shore D, in accordance with ASTM D4541 – 90 minimum 20 7. Abrasion Resistance, in accordance with ASTM D4060 CS 17F Wheel – 17.7 mg 21 loss maximum 22 8. Flexural Modulus, in accordance with ASTM D790 – 529,000 psi minimum 23 9. Flexural Strength, in accordance with ASTM D790 – 14,000 psi minimum 24 10. Adhesion to Concrete, mode of failure, in accordance with ASTM D4541 – 25 Substrate (concrete) failure 26 11. Chemical Resistance, in accordance with ASTM D543/G20, all types of service for: 27 a. Municipal sanitary sewer environment 28 b. Sulfuric acid, 70 percent 29 c. Sodium hydroxide, 20 percent 30 E. Multi-layer Modified Polyurea and Polyurethane Lining System: 31 1. Application Temperature – 50 degrees F, minimum 32 2. Thickness – SpectraSheild, 500 mils minimum 33 3. Moisture Barrier and Final Corrosion Barrier 34 a. Color – Pink 35 b. Tensile Strength, in accordance with ASTM D412 – 2550 psi minimum 36 c. Hardness, Shore D, in accordance with ASTM D2240 – 56 minimum 37 d. Abrasion Resistance, in accordance with ASTM D4060 – 20 mg loss maximum 38 e. Percent Elongation, in accordance with ASTM D412 – 269 39 4. Surfacer 40 a. Compressive Strength, in accordance with ASTM D1621 – 100 psi minimum 41 b. Density, in accordance with ASTM D1622 – 5 lbs/cu ft minimum 42 c. Shear Strength, in accordance with ASTM C273 – 230 psi minimum 43 33 01 40 LINERS FOR SANITARY SEWER STRUCTURES Page 6 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 d. Closed Cell Content, in accordance with ASTM D1940 – >95% 1 F. Lining Application Equipment 2 1. Manufacturer approved, heated, plural component spray equipment. 3 2. Hard to reach areas, primer application, and touch-up may be performed using hand 4 tools. 5 3. Applicator shall use approved specialty equipment adequate in size, capacity, and 6 number sufficient to accomplish the work in a timely manner. 7 2.3 ACCESSORIES [NOT USED] 8 2.4 SOURCE QUALITY CONTROL [NOT USED] 9 PART 3 - EXECUTION 10 3.1 INSTALLERS 11 A. All installers shall be certified applicators approved by the manufacturers. Applicator 12 shall use adequate number of skilled, trained, experienced workmen for the approved 13 product. 14 3.2 EXAMINATION [NOT USED] 15 3.3 PREPARATION 16 A. Manhole Preparation 17 1. Stop active flows via damming, plugging, or diverting as required to ensure all 18 liquids are maintained below or away from the surfaces to be coated. 19 2. Maintain temperature of the surface to be coated between 40 and 120 degrees F. 20 3. Shield specified surfaces to avoid exposure of direct sunlight or other intense heat 21 source. 22 a. Where varying surface temperatures do exist, lining installation should be 23 scheduled when the temperature is falling versus rising. 24 B. Surface Preparation 25 1. Remove oils, roots, grease, incompatible existing linings, waxes, form release, 26 curing compounds, efflorescence, sealers, salts or other contaminants which may 27 affect the performance and adhesion of the lining to the substrate. 28 2. Remove any steps found in the structure. 29 3. Remove concrete and/or mortar damaged by corrosion, chemical attack, or other 30 means of degradation so only sound substrate remains. 31 4. Surface preparation method, or combination of methods, to be used are high 32 pressure water cleaning, high pressure water jetting, abrasive blasting, shotblasting, 33 grinding, scarifying, detergent water cleaning, hot water blasting, and others in 34 accordance with SSPC SP 13/NACE No. 6. 35 5. All methods used shall be performed in a manner that provides a uniform, sound, 36 clean, neutralized, surface suitable for the specified lining product. 37 6. After completion of surface preparation, inspect for leaks, cracks, holes, exposed 38 rebar, ring and cover condition, invert condition, and inlet/outlet pipe condition. 39 33 01 40 LINERS FOR SANITARY SEWER STRUCTURES Page 7 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 7. After defects in the structure have been identified, seal cracks, repair exposed rebar 1 with new rebar to match existing, repair leaks and cracks with grout or other 2 methods approved by the Manufacturer. 3 a. All new rebar shall be embedded in 1 1/2-inch epoxy mastic. 4 b. Replace/seal connection between existing frame and chimney if found loose or 5 not attached. 6 3.4 INSTALLATION 7 A. General 8 1. Perform lining after the sewer line installation/repairs, grade adjustments, and 9 grouting are complete. 10 2. Perform application procedures in accordance with the recommendations of the 11 lining product manufacturer, including environmental controls, product handling, 12 mixing, and application. 13 B. Temperature 14 1. Only perform application if surface temperature is between 40 and 120 degrees F. 15 2. Make no application if freezing is expected to occur inside the manhole within 24 16 hours after application. 17 C. Lining 18 1. Spray apply in accordance with the manufacturer’s recommendation at a minimum 19 film thickness as noted in Section 2.2. 20 2. Apply lining from and including the bench to the bottom of the grade rings for new 21 installations and to the bottom of the frame for rehab projects. 22 3. After walls are coated, remove bench covers and spray bench/trough to at a 23 minimum the same thickness as the walls. 24 4. Apply any topcoat or additional coats within the product’s recoat window. 25 a. Additional surface preparation is required if the recoat window is exceeded. 26 5. Allow a minimum of 3 hours of cure time or be hard to touch before reactivating 27 flow. 28 3.5 REPAIR [NOT USED] 29 3.6 RE-INSTALLATION [NOT USED] 30 3.7 FIELD QUALITY CONTROL 31 A. Each structure will be visually inspected by the City the same day following the 32 application. 33 B. Groundwater infiltration of the system shall be zero. 34 C. All pipe connections shall be open and clear. 35 D. The inspector will check for deficiencies, pinholes, voids, cracks, uncured spots, 36 delamination, and thin spots. Any deficiencies in the liner shall be marked and repaired 37 according to the procedures outlined by the Manufacturer. 38 E. If leaks are detected they will be chipped back, plugged, and coated immediately with 39 protective epoxy resin lining. 40 33 01 40 LINERS FOR SANITARY SEWER STRUCTURES Page 8 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1. Make repair 24 hours after leak detection. 1 F. Lining Thickness Testing 2 1. Wet Film Thickness Testing 3 a. Take wet film thickness gauge measurements in accordance with ASTM D4414 4 at 3 locations within the manhole, 2 spaced equally apart along the wall and 1 5 on the bench. 6 1) Document and attest measurements and provide to the City. 7 2. Thickness Testing for modified polymer liner system 8 a. Upon installation of the Final Corrosion Barrier, insert probe into substrate for 9 depth of system measurement at 3 locations within the manhole, 2 spaced 10 equally apart along the wall and 1 on the bench. 11 1) Document and attest measurements and provide to the City. 12 G. Post Installation Lining Tests 13 1. Holiday Detection Testing 14 a. Holiday Detection test the liner in accordance with NACE SP0188. Mark all 15 detected holidays. Repair all holidays in accordance to coating manufacturer’s 16 recommendations. 17 1) Document and attest all test results and repairs made, and provide to the 18 City. 19 2) Contractor shall mark any location that shows a spark or potential for a 20 pinhole and repair these locations in accordance with manufacturer 21 recommendations. 22 H. Non-Conforming Work 23 1. City reserves the right to require additional testing depending on the rate of failure. 24 a. City will select testing locations. 25 2. Repair all defects according to the manufacturer’s recommendations. 26 3.8 SYSTEM STARTUP [NOT USED] 27 3.9 ADJUSTING [NOT USED] 28 3.10 CLEANING [NOT USED] 29 3.11 CLOSEOUT ACTIVITIES [NOT USED] 30 3.12 PROTECTION [NOT USED] 31 3.13 MAINTENANCE [NOT USED] 32 3.14 ATTACHMENTS [NOT USED] 33 34 35 36 37 33 01 40 LINERS FOR SANITARY SEWER STRUCTURES Page 9 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 END OF SECTION 1 2 Revision Log DATE NAME SUMMARY OF CHANGE 3 33 01 50 ADJUSTING MANHOLES, INLETS, VALVE BOXES, AND OTHER STRUCTURES TO GRADE Page 1 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 33 01 50 1 ADJUSTING MANHOLES, INLETS, VALVE BOXES, AND OTHER STRUCTURES TO 2 GRADE 3 4 PART 1 - GENERAL 5 1.1 SUMMARY 6 A. Section Includes: 7 1. Vertical adjustments to manholes, inlets, valve boxes, cathodic protection test 8 stations, and other miscellaneous structures to a new grade. 9 B. Deviations from this City of Denton Standard Specification: 10 1. None. 11 C. Related Specification Sections include but are not limited to: 12 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 13 Contract. 14 2. Division 1 - General Requirements. 15 3. Section 03 00 00 – Concrete and Concrete Reinforcing 16 4. Section 03 30 00 – Cast-In-Place Concrete. 17 5. Section 03 34 13 – Controlled Low Strength Material (CLSM). 18 6. Section 03 80 00 – Modifications to Existing Concrete Structures. 19 7. Section 32 01 17 – Flexible Paving Repair. 20 8. Section 32 01 29 – Rigid Paving Repair. 21 9. Section 33 05 81 – Frame, Cover and Grade Rings. 22 10. Section 33 05 05 – Utility Trench Excavation, Embedment, and Backfill. 23 11. Section 33 14 20 – Resilient Seated Gate Valve. 24 12. Section 33 14 40 – Fire Hydrants. 25 13. Section 33 05 61 – Cast-in-Place Concrete Manholes. 26 14. Section 33 05 62 – Precast Concrete Manholes. 27 15. Section 33 05 76 – Fiberglass Manholes. 28 1.2 PRICE AND PAYMENT PROCEDURES 29 A. Measurement and Payment 30 1. Manhole – Minor Adjustment 31 a. Measurement 32 1) Measured per each manhole to be adjusted less than 6 inches to the grade 33 specified in the Drawings. 34 b. Payment 35 1) The work performed and materials furnished in accordance with this item 36 and measured as provided under “Measurement” will be paid for at the unit 37 price bid per each “Manhole Adjustment, Minor” completed. 38 33 01 50 ADJUSTING MANHOLES, INLETS, VALVE BOXES, AND OTHER STRUCTURES TO GRADE Page 2 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1 c. The price bid shall include: 2 1) Pavement removal 3 2) Excavation 4 3) Hauling 5 4) Disposal of excess material 6 5) Grade rings 7 6) Reuse of the existing manhole frame and cover 8 7) Furnishing, placement, and compaction of embedment and backfill 9 8) Concrete base material 10 9) Permanent asphalt patch or concrete paving repair, as required 11 10) Clean-up 12 2. Manhole – Major Adjustment 13 a. Measurement 14 1) Measured per each manhole to be adjusted greater than 6 inches and 15 requiring structural modification to the grade specified in the Drawings. 16 b. Payment 17 1) The work performed and materials furnished in accordance with this item 18 and measured as provided under “Measurement” will be paid for at the unit 19 price bid per each “Manhole Adjustment, Major” completed. 20 c. The price bid shall include: 21 1) Pavement removal 22 2) Excavation 23 3) Hauling 24 4) Disposal of excess material 25 5) Structural modifications and grade rings 26 6) Reuse of the existing manhole frame and cover 27 7) Furnishing, placement, and compaction of embedment and backfill 28 8) Concrete base material 29 9) Permanent asphalt patch or concrete paving repair, as required 30 10) Clean-up 31 3. Manhole – Major Adjustment with Frame and Cover 32 a. Measurement 33 1) Measured per each manhole to be adjusted greater than 6 inches, requiring 34 structural modification, and a new frame and cover to the grade specified in 35 the Drawings. 36 b. Payment 37 1) The work performed and materials furnished in accordance with this item 38 and measured as provided under “Measurement” will be paid for at the unit 39 price bid per each “Manhole Adjustment, Major with Frame and Cover” 40 completed. 41 c. The price bid shall include: 42 1) Pavement removal 43 2) Excavation 44 3) Hauling 45 4) Disposal of excess material 46 5) Structural modifications and grade rings 47 6) Frame and cover 48 33 01 50 ADJUSTING MANHOLES, INLETS, VALVE BOXES, AND OTHER STRUCTURES TO GRADE Page 3 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 7) Furnishing, placement, and compaction of embedment and backfill 1 8) Concrete base material 2 9) Permanent asphalt patch or concrete paving repair, as required 3 10) Clean-up 4 4. Inlet Adjustment 5 a. Measurement 6 1) Measured per each adjustment of an inlet requiring structural modifications 7 to the grade specified in the Drawings. 8 b. Payment 9 1) The work performed and materials furnished in accordance with this item 10 and measured as provided under “Measurement” will be paid for at the unit 11 price bid per each “Inlet Adjustment” completed. 12 c. The price bid shall include: 13 1) Pavement removal 14 2) Excavation 15 3) Hauling 16 4) Disposal of excess material 17 5) Structural modifications 18 6) Reuse of frame and covers (if applicable) 19 7) Furnishing, placement, and compaction of embedment and backfill 20 8) Concrete base material, as required 21 9) Surface restoration, permanent asphalt patch, or concrete paving repair, as 22 required 23 10) Clean-up 24 5. Valve Box Adjustment 25 a. Measurement 26 1) Measured per each valve box adjustment to the grade specified in the 27 Drawings. 28 b. Payment 29 1) The work performed and materials furnished in accordance with this item 30 and measured as provided under “Measurement” will be paid for at the unit 31 price bid per each “Valve Box Adjustment” completed. 32 c. The price bid shall include: 33 1) Pavement removal 34 2) Excavation 35 3) Hauling 36 4) Disposal of excess material 37 5) Adjustment device 38 6) Furnishing, placement, and compaction of embedment and backfill 39 7) Concrete base material, as required 40 8) Surface restoration, permanent asphalt patch, or concrete paving repair, as 41 required 42 9) Clean-up 43 6. Cathodic Protection Test Station Adjustment 44 a. Measurement 45 1) Measured per each adjustment of a cathodic protection test station to the 46 grade specified in the Drawings. 47 48 33 01 50 ADJUSTING MANHOLES, INLETS, VALVE BOXES, AND OTHER STRUCTURES TO GRADE Page 4 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 b. Payment 1 1) The work performed and materials furnished in accordance with this item 2 and measured as provided under “Measurement” will be paid for at the unit 3 price bid per each “Cathodic Protection Test Station Adjustment” 4 completed. 5 c. The price bid shall include: 6 1) Pavement removal 7 2) Excavation 8 3) Hauling 9 4) Disposal of excess material 10 5) Adjustment device 11 6) Furnishing, placement, and compaction of embedment and backfill 12 7) Concrete base material, as required 13 8) Surface restoration, permanent asphalt patch, or concrete paving repair, as 14 required 15 9) Clean-up 16 7. Fire Hydrant Adjustment 17 a. Measurement 18 1) Measured per each fire hydrant adjustment, requiring stem extensions, to 19 the grade specified in the Drawings. 20 b. Payment 21 1) The work performed and materials furnished in accordance with this item 22 and measured as provided under “Measurement” will be paid for at the unit 23 price bid per each “Fire Hydrant Stem Extension” completed. 24 c. The price bid shall include: 25 1) Pavement removal 26 2) Excavation 27 3) Hauling 28 4) Disposal of excess material 29 5) Adjustment materials 30 6) Furnishing, placement, and compaction of embedment and backfill 31 7) Concrete base material, as required 32 8) Surface restoration, permanent asphalt patch, or concrete paving repair, as 33 required 34 9) Clean-up 35 1.3 REFERENCES 36 A. Abbreviations 37 1. CLSM – Controlled Low Strength Material 38 B. Definitions 39 1. Minor Adjustment 40 a. Refers to a small elevation change, less than 6 inches, performed on an existing 41 manhole which does not require structural modifications. 42 2. Major Adjustment 43 a. Refers to a significant elevation change, greater than 6 inches, performed on an 44 existing manhole which requires structural modification. 45 33 01 50 ADJUSTING MANHOLES, INLETS, VALVE BOXES, AND OTHER STRUCTURES TO GRADE Page 5 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 1 1.5 SUBMITTALS [NOT USED] 2 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 3 1.7 CLOSEOUT SUBMITTALS [NOT USED] 4 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 5 1.9 QUALITY ASSURANCE [NOT USED] 6 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 7 1.11 FIELD CONDITIONS [NOT USED] 8 1.12 WARRANTY [NOT USED] 9 PART 2 - PRODUCTS 10 2.1 CITY-SUPPLIED PRODUCTS [NOT USED] 11 2.2 MATERIALS 12 A. Cast-in-Place Concrete 13 1. In accordance with Sections 03 00 00 and 03 30 00 14 B. Controlled Low Strength Material (CLSM) 15 1. In accordance with Section 03 34 13 16 C. Modifications to Existing Concrete Structures 17 1. In accordance with Section 03 80 00 18 19 D. Grade Rings 20 1. In accordance with Section 33 05 81 21 E. Frame and Cover 22 1. In accordance with Section 33 05 81 23 F. Backfill material 24 1. In accordance with Section 33 05 05 25 G. Water valve box extension 26 1. In accordance with Section 33 14 20 27 H. Fire Hydrant Adjustment 28 1. In accordance with Section 33 14 40 29 I. Cast-in-Place Concrete Manholes 30 1. In accordance with Section 33 05 61 31 J. Precast Concrete Manholes 32 1. In accordance with Section 33 05 62 33 33 01 50 ADJUSTING MANHOLES, INLETS, VALVE BOXES, AND OTHER STRUCTURES TO GRADE Page 6 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 K. Fiberglass Manholes 1 1. In accordance with Section 33 05 76 2 2.3 ACCESSORIES [NOT USED] 3 2.4 SOURCE QUALITY CONTROL [NOT USED] 4 PART 3 - EXECUTION 5 3.1 INSTALLERS [NOT USED] 6 3.2 EXAMINATION 7 A. Verification of Conditions 8 1. Examine existing structure to be adjusted for damage or defects that may affect 9 grade adjustment. 10 a. Report issue to City for consideration before beginning adjustment. 11 3.3 PREPARATION 12 A. Grade Verification 13 1. For major adjustments, confirm the grade change noted on Drawings is consistent 14 with field measurements. 15 a. If not consistent, coordinate with City to verify final grade before beginning 16 adjustment. 17 3.4 ADJUSTMENT 18 A. Manholes, Inlets, and Miscellaneous Structures 19 1. For sanitary sewer adjustments, replace all 24-inch frame and cover assemblies 20 with 30-inch frame and cover assemblies. 21 2. Protect the bottom of structures using wood forms shaped to fit the structure to 22 prevent debris falling into the invert, inlet, or outlet piping during adjustments. 23 a. Do not use any more than a 2-piece bottom. 24 3. Use the least number of grade rings necessary to meet required grade. 25 a. The maximum height of proposed and existing grade rings shall be no more 26 than 12-inches for any combination of grade rings. 27 b. Use least amount of grade rings necessary. 28 1) For example, use 3, 4-inch rings in lieu of 6, 2-inch rings. 29 c. Adjustments which result in 12-inches or more of grade rings will be 30 considered major adjustments and will require structural modifications to 31 existing structure to accommodate this requirement. 32 B. Valve Boxes 33 1. Utilize standard 3-piece adjustable valve box for adjusting to final grade as shown 34 on the Drawings. 35 C. Fire Hydrants 36 1. Limit vertical adjustments to an increase of 2 vertical feet. 37 33 01 50 ADJUSTING MANHOLES, INLETS, VALVE BOXES, AND OTHER STRUCTURES TO GRADE Page 7 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2. Decreasing grade for fire hydrants is not permitted and requires a complete 1 replacement of fire hydrant assembly in accordance with Section 33 14 40. 2 D. Backfill and Grading 3 1. Backfill area of excavation surrounding each adjustment in accordance with Section 4 33 05 05. 5 E. Pavement Repair 6 1. If required, perform pavement repair in accordance with Section 32 01 17 or 7 Section 32 01 29. 8 3.5 REPAIR [NOT USED] 9 3.6 RE-INSTALLATION [NOT USED] 10 3.7 FIELD QUALITY CONTROL [NOT USED] 11 3.8 SYSTEM STARTUP [NOT USED] 12 3.9 ADJUSTING [NOT USED] 13 3.10 CLEANING [NOT USED] 14 3.11 CLOSEOUT ACTIVITIES [NOT USED] 15 3.12 PROTECTION [NOT USED] 16 3.13 MAINTENANCE [NOT USED] 17 18 33 01 50 ADJUSTING MANHOLES, INLETS, VALVE BOXES, AND OTHER STRUCTURES TO GRADE Page 8 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3.14 ATTACHMENTS [NOT USED] 1 END OF SECTION 2 Revision Log DATE NAME SUMMARY OF CHANGE 3 33 05 05 UTILITY TRENCH EXCAVATION, EMBEDMENT, AND BACKFILL Page 1 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 17, 2024 Effective July 1, 2024 SECTION 33 05 05 1 UTILITY TRENCH EXCAVATION, EMBEDMENT, AND BACKFILL 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Excavation, Embedment, and Backfill for: 6 a. Pressure Applications 7 1) Water Distribution Mains 8 2) Sanitary Sewer Force Mains 9 3) Reclaimed Water Mains 10 b. Gravity Applications 11 1) Sanitary Sewer Gravity Mains 12 2) Storm Sewer Pipe and Culverts 13 3) Storm Sewer Precast Box and Culverts 14 2. Including: 15 a. Excavation of all material encountered, including rock and unsuitable materials 16 b. Disposal of excess unsuitable material 17 c. Site specific trench safety 18 d. Pumping and dewatering 19 e. Clay Dams 20 f. Embedment 21 g. Concrete encasement for utility lines 22 h. Backfill 23 i. Compaction 24 B. Deviations from this City of Denton Standard Specification: 25 1. None. 26 C. Related Specification Sections include but are not limited to: 27 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 28 Contract. 29 2. Division 1 - General Requirements. 30 3. Section 02 41 13 – Selective Site Demolition. 31 4. Section 02 41 15 – Paving Removal. 32 5. Section 03 00 00– Concrete and Concrete Reinforcing. 33 6. Section 03 30 00– Cast-In-Place Concrete. 34 7. Section 03 34 13 – Controlled Low Strength Material (CLSM). 35 8. Section 31 10 00 – Site Clearing. 36 9. Section 31 25 14 – Erosion and Sediment Control. 37 10. Section 33 05 97 – Utility Markers/Locators. 38 11. Division 34 - Transportation. 39 40 33 05 05 UTILITY TRENCH EXCAVATION, EMBEDMENT, AND BACKFILL Page 2 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 17, 2024 Effective July 1, 2024 1.2 PRICE AND PAYMENT PROCEDURES 1 A. Measurement and Payment 2 1. Trench Excavation, Embedment, and Backfill associated with the installation of an 3 underground utility 4 a. Measurement 5 1) This item is considered subsidiary to utility pipe installed. 6 b. Payment 7 1) The work performed and materials furnished in accordance with this item 8 are subsidiary to the unit price bid per linear foot of utility pipe installed. 9 2. Imported Embedment or Backfill 10 a. Measurement 11 1) Measured by cubic yard per plan quantity. 12 b. Payment 13 1) The work performed and materials furnished in accordance with this item 14 and measured as provided under “Measurement” will be paid for at the unit 15 price bid per cubic yard of “Imported Embedment/Backfill” per plan 16 quantity for: 17 a) Various embedment/backfill materials. 18 c. The price bid shall include 19 1) Furnishing of backfill or embedment in accordance with this Section 20 2) Hauling to the Site 21 3) Placement and compaction of backfill or embedment 22 3. Concrete Encasement for Utility Lines 23 a. Measurement 24 1) Measured by cubic yard per plan quantity. 25 b. Payment 26 1) The work performed and materials furnished in accordance with this item 27 and measured as provided under “Measurement” will be paid for at the unit 28 price bid per cubic yard of “Concrete Encasement for Utility Lines” per 29 plan quantity. 30 c. The price bid shall include 31 1) Furnishing, hauling, placing, and finishing concrete in accordance with 32 Section 03 30 00 33 2) Clean-up 34 4. Groundwater Control 35 a. Measurement 36 1) Measurement shall be lump sum when a groundwater control plan is 37 specifically required by the Contract Documents. Otherwise this item is 38 considered subsidiary to the various items bid. 39 b. Payment 40 1) The work performed and the materials furnished in accordance with this 41 item shall be paid for at the lump sum price bid for “Groundwater Control”. 42 43 33 05 05 UTILITY TRENCH EXCAVATION, EMBEDMENT, AND BACKFILL Page 3 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 17, 2024 Effective July 1, 2024 c. The price bid shall include: 1 a) Submittals 2 b) Additional Testing 3 c) Groundwater control system installation 4 d) Groundwater control system operations and maintenance 5 e) Disposal of water 6 f) Removal of groundwater control system 7 5. Clay Dams 8 a. Measurement 9 1) This item is considered subsidiary to utility pipe installed where indicated 10 in the Drawings. 11 b. Payment 12 1) The work performed and materials furnished in accordance with this item 13 are subsidiary to the unit price bid per linear foot of utility pipe installed. 14 6. Trench Safety 15 a. Measurement 16 1) Measured per linear foot of excavation for all trenches that require trench 17 safety in accordance with OSHA excavation safety standards (29 CFR Part 18 1926 Subpart P Safety and Health Regulations for Construction). 19 b. Payment 20 1) The work performed and materials furnished in accordance with this item 21 and measured as provided under “Measurement” will be paid for at the unit 22 price bid per linear foot of excavation to comply with OSHA excavation 23 safety standards (29 CFR Part 1926 Subpart P Safety and Health 24 Regulations for Construction). 25 c. The price bid shall include: 26 1) Submittals 27 2) Conformance with trench safety plan 28 1.3 REFERENCES 29 A. Abbreviations 30 1. CSS – Cement Stabilized Sand 31 2. CLSM – Controlled Low Strength Material 32 B. Definitions 33 1. General – Definitions used in this section are in accordance with Terminologies 34 ASTM F412 and ASTM D8 and Terminology ASTM D653, unless otherwise 35 noted. 36 37 33 05 05 UTILITY TRENCH EXCAVATION, EMBEDMENT, AND BACKFILL Page 4 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 17, 2024 Effective July 1, 2024 2. Definitions for trench width, backfill, embedment, initial backfill, pipe zone, 1 haunching bedding, springline, pipe zone, and foundation are defined as shown in 2 the following schematic: 3 4 3. Deleterious materials – Harmful materials such as clay lumps, silts, and organic 5 material 6 4. Excavated Trench Depth – Distance from the surface to the bottom of the bedding 7 or the trench foundation 8 5. Final Backfill Depth 9 a. Unpaved Areas – The depth of the final backfill measured from the top of the 10 initial backfill to the surface 11 b. Paved Areas – The depth of the final backfill measured from the top of the 12 initial backfill to bottom of permanent or temporary pavement repair 13 C. Reference Standards 14 1. Reference standards cited in this Section refer to the current reference standard 15 published at the time of the latest revision date logged at the end of this Section, 16 unless a date is specifically cited. 17 2. ASTM Standards: 18 a. C33, Standard Specification for Concrete Aggregates. 19 b. C40, Standard Test Method for Organic Impurities in Fine Aggregates for 20 Concrete. 21 33 05 05 UTILITY TRENCH EXCAVATION, EMBEDMENT, AND BACKFILL Page 5 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 17, 2024 Effective July 1, 2024 c. C88, Standard Test Method for Soundness of Aggregate by Use of Sodium 1 Sulfate or Magnesium Sulfate. 2 d. C94, Standard Specification for Ready-Mixed Concrete. 3 e. C123, Standard Test Method for Lightweight Particles in Aggregate. 4 f. C131, Standard Test Method for Resistance to Degradation of Small-Size 5 Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine. 6 g. C136, Standard Test Method for Sieve Analysis of Fine and Coarse Aggregate. 7 h. C142, Standard Test Method for Clay Lumps and Friable Particles in 8 Aggregates. 9 i. D448, Standard Classification for Sizes of Aggregate for Road and Bridge 10 Construction. 11 j. C535, Standard Test Method for Resistance to Degradation of Large-Size 12 Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine. 13 k. D698, Test Methods for Laboratory Compaction Characteristics of Soil Using 14 Stand and Effort (12,400 ft-lb/ft3 600 Kn-m/M3)). 15 l. D1632, Standard Practice for Making and Curing Soil-Cement Compression 16 and Flexure Test Specimens in the Laboratory. 17 m. D1633, Standard Test Methods for Compressive Strength of Molded Soil-18 Cement Cylinders. 19 n. D1556, Standard Test Method for Density and Unit Weight of Soils in Place by 20 Sand Cone Method. 21 o. D2487, Standard Practice for Classification of Soils for Engineering Purposes 22 (Unified Soil Classification System). 23 p. D6938, Standard Test Methods for In-Place Density and Water Content of Soil 24 and Soil-Aggregate by Nuclear Methods (Shallow Depth). 25 q. D4318, Standard Test Methods for Liquid Limit, Plastic Limit, and Plasticity 26 Index of Soils. 27 3. Occupational Safety and Health Administration (OSHA) 28 a. 29 CFR, Part 1926-Safety Regulations for Construction, Subpart P: 29 Excavations. 30 1.4 ADMINISTRATIVE REQUIREMENTS 31 A. Coordination 32 1. Utility Company Notification 33 a. Notify area utility companies at least 48 hours in advance, excluding weekends 34 and holidays, before starting excavation. 35 b. Request the location of buried lines and cables in the vicinity of the proposed 36 work. 37 B. Sequencing 38 1. Sequence work for each section of the pipe installed to complete the embedment 39 and backfill placement on the day the pipe foundation is complete. 40 2. Sequence work such that Proctors are complete in accordance with ASTM D698 41 prior to commencement of construction activities. 42 C. Excavation Protection 43 1. Excavation protection shall be in strict compliance with OSHA excavation safety 44 standards (29 CFR Part 1926 Subpart P Safety and Health regulations for 45 Construction). 46 33 05 05 UTILITY TRENCH EXCAVATION, EMBEDMENT, AND BACKFILL Page 6 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 17, 2024 Effective July 1, 2024 2. Submit three (3) copies of a site-specific trench safety plan prepared by a licensed 1 Professional Engineer in the State of Texas to the City prior to construction in 2 accordance with Section 01 33 00. 3 a. The City will not review the submittal. Receipt of submittal is confirmation 4 that the Contractor has prepared a trench safety plan as required by state and 5 federal law. 6 b. The City assumes no responsibility for trench safety and shall be held harmless 7 under the indemnification clause of the General Conditions. 8 3. Any changes in the trench excavation plan after initiation of construction will not 9 be cause for an extension of time and will require a new submittal to the City. 10 4. The Contractor accepts sole responsibility for compliance with all applicable safety 11 requirements. 12 1.5 SUBMITTALS 13 A. Submittals shall be in accordance with Section 01 33 00. 14 B. All submittals shall be approved by the City prior to delivery. 15 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 16 A. Submittals 17 1. Designated storage area affidavit for storage on private property, if applicable. 18 B. Shop Drawings 19 1. Provide detailed drawings and explanation for groundwater and surface water 20 control, if required. 21 2. Trench Safety Plan in accordance with Article 1.4. 22 3. Stockpiled excavation and/or backfill material 23 a. Provide a description of the storage of the excavated material only if the 24 Contract Documents do not allow storage of materials in the right-of-way or the 25 easement. 26 1.7 CLOSEOUT SUBMITTALS 27 A. Test and Evaluation Reports 28 1. All test reports generated during testing. 29 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 30 1.9 QUALITY ASSURANCE [NOT USED] 31 1.10 DELIVERY, STORAGE, AND HANDLING 32 A. Storage Requirements 33 1. Secure and maintain a location to store the material in accordance with Section 01 34 66 00. 35 2. Within Existing Rights-of-way (ROW) 36 a. Spoils and imported embedment and backfill materials may be stored within 37 existing ROW, easements, or temporary construction easements, unless 38 specifically disallowed in the Contract Documents or the City’s Right-of-Way 39 Ordinance. 40 33 05 05 UTILITY TRENCH EXCAVATION, EMBEDMENT, AND BACKFILL Page 7 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 17, 2024 Effective July 1, 2024 b. Do not block drainage ways, inlets, or driveways. 1 c. Provide erosion control in accordance with Section 31 25 14. 2 d. Store materials only in areas barricaded as provided in the traffic control plans. 3 e. In non-paved areas, do not store material on the root zone of any trees or in 4 landscaped areas. 5 3. Designated Storage Areas 6 a. If the Contract Documents do not allow the storage of spoils, embedment or 7 backfill materials within the ROW, easement, or temporary construction 8 easements, secure and maintain an adequate storage location. 9 b. Provide an affidavit that rights have been secured to store the materials on 10 private property. 11 c. Provide erosion control in accordance with Section 31 25 14. 12 d. Do not block drainage ways, inlets, or driveways. 13 e. Only materials used for 1 working day will be allowed to be stored in the work 14 zone. 15 1.11 FIELD CONDITIONS 16 A. Existing Conditions 17 1. Any data which has been or may be provided on subsurface conditions is not 18 intended as a representation or warranty of accuracy or continuity between soils. It 19 is expressly understood that neither the City nor the Engineer will be responsible 20 for interpretations or conclusions drawn by the Contractor, in accordance with 21 Section 00 72 00. 22 a. Data is made available for the convenience of the Contractor. 23 1.12 WARRANTY [NOT USED] 24 PART 2 - PRODUCTS 25 2.1 CITY-FURNISHED PRODUCTS [NOT USED] 26 2.2 MATERIALS 27 A. Materials 28 1. Utility Sand 29 a. Granular and free flowing 30 b. Generally, meets or exceeds the limits on deleterious substances per Table 2 of 31 ASTM C33 for fine aggregate 32 c. Reasonably free of organic material 33 d. Gradation tested in accordance with ASTM C136: 34 Sieve Size Percent Retained 1 inch 0 3/8 inch 0-10 #30 40-75 #100 95 2. Crushed Rock 35 a. Durable crushed rock or recycled concrete 36 b. In accordance with the gradation of ASTM D448 size numbers 56, 57 or 67 37 33 05 05 UTILITY TRENCH EXCAVATION, EMBEDMENT, AND BACKFILL Page 8 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 17, 2024 Effective July 1, 2024 c. May be unwashed 1 d. Free from significant silt clay or unsuitable materials 2 e. Percentage of wear not more than 40 percent in accordance with ASTM C131 3 or C535 4 f. Not more than a 12 percent maximum loss when subjective to 5 cycles of 5 sodium sulfate soundness per ASTM C88 6 3. Pea Gravel 7 a. Durable particles composed of small, smooth, rounded stones or pebbles 8 b. In accordance with the gradation of ASTM D448 size number 8 9 4. Fine Crushed Rock (Chat) 10 a. Durable crushed rock 11 b. In accordance with the gradation of ASTM D448 size numbers 8 or 89 12 c. May be unwashed 13 d. Free from significant silt clay or unsuitable materials. 14 e. Percentage of wear not more than 40 percent in accordance with ASTM C131 15 or C535 16 f. Not more than a 12 percent maximum loss when subjective to 5 cycles of 17 sodium sulfate soundness in accordance with ASTM C88 18 5. Ballast Stone 19 a. Stone ranging from 3 inches to 6 inches in greatest dimension. 20 b. May be unwashed 21 c. Free from significant silt clay or unsuitable materials 22 d. Percentage of wear not more than 40 percent per ASTM C131 or C535 23 e. Not more than a 12 percent maximum loss when subjected to 5 cycles of 24 sodium sulfate soundness in accordance with ASTM C88 25 6. Native Backfill Material 26 a. In-situ or imported soils classified as CL, CH, SC, or GC in accordance with 27 ASTM D2487 28 b. Free from deleterious materials, boulders over 6 inches in size, and organics 29 c. Free from voids 30 d. Must have 20 percent passing the number 200 sieve 31 7. Blended Backfill Material 32 a. In-situ soils classified as SP, SM, GP, or GM in accordance with ASTM D2487 33 b. Blended with in-situ or imported backfill material in accordance with the 34 requirements of Native Backfill Material 35 c. Free from deleterious materials, boulders over 6 inches in size and organics 36 d. Must have 20 percent passing the number 200 sieve 37 8. Unacceptable Backfill Material 38 a. In-situ soils classified as ML, MH, PT, OL, or OH in accordance with ASTM 39 D2487 40 9. Select Fill 41 a. Classified as SC or CL in accordance with ASTM D2487 42 b. Free from deleterious materials, boulders over 6 inches in size, and organics. 43 c. Can be placed free from voids. 44 d. Has 20 percent passing the number 200 sieve. 45 e. Meets the requirements of the following table: 46 Property Test Method Specification Limit 33 05 05 UTILITY TRENCH EXCAVATION, EMBEDMENT, AND BACKFILL Page 9 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 17, 2024 Effective July 1, 2024 Liquid Limit (LL) Tex-104-E ≤ 35 Plasticity Index (PI) Tex-106-E 8< PI ≤ 20 Sulfate Limit Tex-145-E ≤ 2000 ppm Bar Linear Shrinkage Tex-107-E ≥ 2 1 10. Cement Stabilized Sand (CSS) 2 a. Sand 3 1) Clean and durable, in accordance with grading requirements for fine 4 aggregates of ASTM C33 and the following requirements: 5 a) Classified as SW, SP, or SM by the United Soil Classification System 6 of ASTM D2487 7 b) Deleterious materials 8 (1) Clay lumps, ASTM C142, less than 0.5 percent 9 (2) Lightweight pieces, ASTM C123, less than 5.0 percent 10 (3) Organic impurities, ASTM C40, color no darker than standard 11 color 12 (4) Plasticity index of 4 or less when tested in accordance with ASTM 13 D4318. 14 b. Minimum of 4 percent cement content of Type I/II portland cement 15 c. Water 16 1) Potable water, free of soils, acids, alkalis, organic matter or other 17 deleterious substances, in accordance with the requirements of ASTM C94 18 d. Mix in a stationary pug mill, weigh-batch, or continuous mixing plant. 19 e. Strength 20 1) 50 to 150 psi compressive strength at 2 days in accordance with ASTM 21 D1633, Method A 22 2) 200 to 250 psi compressive strength at 28 days in accordance with ASTM 23 D1633, Method A 24 3) The maximum compressive strength in 7 days shall be 400 psi. 25 a) Backfill that exceeds the maximum compressive strength shall be 26 removed by the Contractor for no additional compensation. 27 f. Random samples of delivered product will be taken in the field at point of 28 delivery for each day of placement in the work area. Specimens will be 29 prepared in accordance with ASTM D1632. 30 11. Controlled Low Strength Material (CLSM) 31 a. Conform to Section 03 34 13 32 12. Trench Geotextile Fabric 33 a. Soils other than ML or OH in accordance with ASTM D2487 34 1) Needle punch, nonwoven geotextile composed of polypropylene fibers 35 2) Fibers shall retain their relative position 36 3) Inert to biological degradation 37 4) Resist naturally occurring chemicals 38 5) UV Resistant 39 6) Mirafi 140N by Tencate, or approved equal 40 b. Soils Classified as ML or OH in accordance with ASTM D2487 41 1) High-tenacity monofilament polypropylene woven yarn 42 33 05 05 UTILITY TRENCH EXCAVATION, EMBEDMENT, AND BACKFILL Page 10 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 17, 2024 Effective July 1, 2024 2) 8 to10 percent open area 1 3) Fibers shall retain their relative position 2 4) Inert to biological degradation 3 5) Resist naturally occurring chemicals 4 6) UV Resistant 5 7) Mirafi FW402 by Tencate, or approved equal 6 13. Concrete Encasement 7 a. In accordance with Sections 03 00 00 and 03 30 00. 8 14. Clay Dam 9 a. Provide clay (SC, CL, or CH) with a plasticity index of no less than 18. 10 2.3 ACCESSORIES [NOT USED] 11 2.4 SOURCE QUALITY CONTROL [NOT USED] 12 PART 3 - EXECUTION 13 3.1 INSTALLERS [NOT USED] 14 3.2 EXAMINATION 15 A. Verification of Conditions 16 1. Review all known, identified, or marked utilities, whether public or private, prior to 17 excavation. 18 2. Locate and protect all known, identified, or marked utilities or underground 19 facilities as excavation progresses. 20 3. Notify all utility owners within the project limits 48 hours prior to beginning 21 excavation. 22 4. The information and data shown in the Drawings with respect to utilities is 23 approximate and based on record information or on physical appurtenances 24 observed within the project limits. 25 5. Coordinate with the owner(s) of underground facilities. 26 6. Immediately notify any utility owner of damages to underground facilities resulting 27 from construction activities. 28 7. Repair any damages resulting from the construction activities. 29 B. Differing Site Conditions 30 1. Notify the City immediately of any differing site condition in accordance with 31 Section 00 72 00. 32 3.3 PREPARATION 33 A. Protection of In-Place Conditions 34 1. Pavement 35 a. Conduct activities in such a way that does not damage existing pavement 36 designated to remain. 37 33 05 05 UTILITY TRENCH EXCAVATION, EMBEDMENT, AND BACKFILL Page 11 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 17, 2024 Effective July 1, 2024 1) Where desired to move equipment not licensed for operation on public 1 roads or across pavement, provide means to protect the pavement from all 2 damage. 3 b. Repair or replace any pavement damaged due to the negligence of the 4 Contractor outside the limits designated for pavement removal at no additional 5 cost to the City. 6 2. Drainage 7 a. Maintain positive drainage during construction and re-establish drainage for all 8 swales and culverts affected by construction. 9 3. Trees 10 a. When operating outside of existing right-of-way (ROW), stake permanent and 11 temporary construction easements. 12 b. Restrict all construction activities to the designated easements and ROW. 13 c. Flag and protect all trees designated to remain in accordance with Section 31 10 14 00. 15 d. Conduct excavation, embedment, and backfill in a manner such that there is no 16 damage to the tree canopy. 17 e. Prune or trim tree limbs as specifically allowed by the Drawings or as 18 specifically allowed by the City. 19 1) Pruning or trimming may only be accomplished with equipment 20 specifically designed for tree pruning or trimming. 21 f. Remove trees specifically designated to be removed in the Drawings in 22 accordance with Section 31 10 00. 23 4. Above ground Structures 24 a. Protect all above ground structures adjacent to the construction. 25 b. Remove above ground structures designated for removal in the Drawings in 26 accordance with Sections 02 41 13, 02 41 15, and 31 10 00. 27 5. Traffic 28 a. Maintain existing traffic in accordance with Division 34, except as modified by 29 the traffic control plan. 30 b. Do not block access to driveways or alleys for extended periods of time unless: 31 1) Alternative access has been provided; 32 2) Proper notification has been provided to the property owner or resident; 33 3) It is specifically allowed in the traffic control plan. 34 c. Use traffic rated plates to maintain access until access is restored. 35 6. Traffic Signal – Poles, Mast Arms, Pull boxes, Detector loops 36 a. Notify the City a minimum of 48 hours prior to any excavation that could 37 impact the operations of an existing traffic signal. 38 b. Protect all traffic signal poles, mast arms, pull boxes, traffic cabinets, conduit, 39 and detector loops. 40 c. Notify the City immediately of damage to any component of the traffic signal 41 due to the construction activities. 42 d. Repair any damage to the traffic signal poles, mast arms, pull boxes, traffic 43 cabinets, conduit, and detector loops as a result of the construction activities in 44 accordance with Division 34. 45 7. Fences 46 a. Protect all fences designated to remain. 47 b. Leave fence in the equal or better condition as prior to construction. 48 33 05 05 UTILITY TRENCH EXCAVATION, EMBEDMENT, AND BACKFILL Page 12 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 17, 2024 Effective July 1, 2024 3.4 INSTALLATION 1 A. Excavation 2 1. Excavate to the depth indicated on the Drawings. 3 2. Trench excavations are defined as unclassified. No additional payment shall be 4 granted for rock or other in-situ materials encountered in the trench. 5 3. Excavate to a width sufficient for laying the pipe in accordance with the Drawings 6 and bracing in accordance with the Trench Safety Plan. 7 4. The bottom of the excavation shall be firm and free from standing water. 8 a. Notify the City immediately if the water and/or the in-situ soils do not provide 9 for a firm trench bottom. 10 b. The City will determine if any changes are required in the pipe foundation or 11 bedding. 12 5. Unless otherwise permitted by the Drawings or City, the limits of the excavation 13 shall not advance beyond the pipe placement so the trench may be backfilled in the 14 same day. 15 6. Unless otherwise indicated on the Drawings, no benching or sloping shall be 16 allowed under a paved surface (roadways, parking areas, etc.). Excavation trenches 17 shall be vertical utilizing appropriate shoring, bracing or shielding. 18 7. Benching or sloping will be allowed under unpaved surface areas up to the extent of 19 the public right-of-way and/or public easement. 20 B. Over Excavation 21 1. Fill over excavated areas with bedding material specified for pipe installation. 22 2. No additional payment will be made for over excavation or additional bedding 23 material. 24 C. Unacceptable Backfill Materials 25 1. Separate in-situ soils classified as unacceptable backfill material from acceptable 26 backfill materials. 27 2. If the unacceptable backfill material is to be blended in accordance with this 28 Section, store material in a suitable location until the material is blended. 29 3. Remove all unacceptable material from the project site that is not intended to be 30 blended or modified. 31 D. Shoring, Sheeting and Bracing 32 1. Furnish, install, and maintain a trench safety system in accordance with the Trench 33 Safety Plan and as required by Federal, State, or local safety requirements. 34 2. If soil or water conditions are encountered that are not addressed by the current 35 Trench Safety Plan, engage a Professional Engineer Licensed in the State of Texas 36 to modify the Trench Safety Plan and provide a revised submittal to the City. 37 3. Do not allow soil, or water containing soil, to migrate through the Trench Safety 38 System in quantities of sufficient amount to adversely affect the suitability of the 39 Trench Protection System. 40 4. Movable bracing, shoring plates, or trench boxes used to support the sides of the 41 trench excavation shall not: 42 a. Disturb the embedment located in the pipe zone or lower, 43 33 05 05 UTILITY TRENCH EXCAVATION, EMBEDMENT, AND BACKFILL Page 13 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 17, 2024 Effective July 1, 2024 b. Alter the pipe’s line and grade after the Trench Protection System is removed, 1 or 2 c. Compromise the compaction of the embedment located below the spring line of 3 the pipe and in the haunching. 4 E. Water Control 5 1. Surface Water 6 a. Furnish all materials and equipment and perform all incidental work required to 7 direct surface water away from the excavation. 8 2. Groundwater 9 a. Furnish all materials and equipment to dewater groundwater by a method which 10 preserves the undisturbed state of the subgrade soils. 11 b. Do not allow submergence of pipe within 24 hours after placement. 12 c. Do not allow water to flow over concrete until it has sufficiently cured. 13 d. Engage a Professional Engineer Licensed in the State of Texas to prepare a 14 Groundwater Control Plan if any of the following conditions are encountered: 15 1) A Groundwater Control Plan is specifically required by the Contract 16 Documents 17 2) If in the sole judgment of the City, groundwater is so severe that an 18 Engineered Groundwater Control Plan is required to protect the trench or 19 the installation of the pipe. Such situations may include, but are not limited 20 to: 21 a) Groundwater levels in the trench are unable to be maintained below the 22 top of the bedding. 23 b) A firm trench bottom cannot be maintained due to groundwater. 24 c) Groundwater entering the excavation undermines the stability of the 25 excavation. 26 d) Groundwater entering the excavation is transporting unacceptable 27 quantities of soils through the Trench Safety System. 28 e. In the event that there is no bid item for a Groundwater Control Plan and the 29 City requires an Engineered Groundwater Control Plan due to conditions 30 discovered at the site, the Contractor will be eligible to submit a Contract 31 Claim. 32 f. Control of groundwater shall be considered subsidiary to the excavation when: 33 1) No Groundwater Control Plan is specifically identified and required in the 34 Contract Documents. 35 g. Groundwater Control Plan installation, operation, and maintenance 36 1) Furnish all materials and equipment necessary to implement, operate, and 37 maintain the Groundwater Control Plan. 38 2) Once the excavation is complete, remove all groundwater control 39 equipment not called to be incorporated into the work. 40 h. Water Disposal 41 1) Dispose of groundwater in accordance with City policy or Ordinance. 42 2) Do not discharge groundwater onto or across private property without 43 written permission. 44 3) Permission from City is required prior to disposal into the sanitary sewer 45 system. 46 4) Disposal shall not violate any Federal, State, or local regulations. 47 F. Embedment and Pipe Placement 48 33 05 05 UTILITY TRENCH EXCAVATION, EMBEDMENT, AND BACKFILL Page 14 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 17, 2024 Effective July 1, 2024 1. Water Lines less than or equal to 12 inches in diameter (non-HDPE): 1 a. Embedment zone shall be of uniform material. 2 b. Utility sand shall be generally used for embedment. 3 c. If groundwater is in sufficient quantity to cause sand to pump, use crushed 4 rock, fine crushed rock, or pea gravel as embedment. 5 d. Place evenly spread bedding material on a firm trench bottom. 6 e. Provide firm, uniform bedding a minimum of 6 inches below the pipe. 7 f. Place pipe on the bedding in accordance with the alignment of the Drawings. 8 g. Place embedment, including initial backfill, to 12 inches above the pipe. 9 h. Where gate valves are present, extend initial backfill to 6 inches above the 10 elevation of the valve nut. 11 i. Form all blocking against undisturbed trench wall to the dimensions in the 12 Drawings. 13 j. Compact embedment and initial backfill. 14 k. Place marker tape on top of the initial trench backfill in accordance with 15 Section 33 05 97. 16 2. Water Lines 16-inches through 24-inches in diameter (non-HDPE): 17 a. The entire embedment zone shall be of uniform material. 18 b. Use crushed rock or fine crushed rock for embedment. 19 c. Place evenly spread bedding material on a firm trench bottom. 20 d. Provide firm, uniform bedding a minimum of 6 inches below the pipe. 21 1) Additional bedding may be required if groundwater is present in the trench. 22 e. Place pipe on the bedding according to the alignment shown on the Drawings. 23 f. The pipe line shall be within: 24 1) ±3 inches of the elevation on the Drawings 25 g. Place and compact embedment material to adequately support haunches in 26 accordance with the pipe manufacturer’s recommendations. 27 h. Place remaining embedment, including initial backfill, to 12 inches above the 28 pipe. 29 i. Where valves are present and not placed within a vault or manhole, extend 30 initial backfill up to the valve nut. 31 j. Compact the embedment and initial backfill to a minimum of 95 percent of 32 Standard Proctor density in accordance with ASTM D698. 33 k. Place trench geotextile fabric on top of the initial backfill. 34 l. Place marker tape on top of the trench geotextile fabric in accordance with 35 Section 33 05 97. 36 3. Water Lines 30-inches and greater in diameter (non-HDPE): 37 a. Embedment zone shall be of uniform material. 38 b. Use crushed rock for embedment. 39 c. Place evenly spread bedding material on a firm trench bottom. 40 d. Provide firm, uniform bedding a minimum of 6 inches below the pipe. 41 1) Additional bedding may be required if groundwater is present in the trench. 42 e. Place pipe on the bedding according to the alignment shown on the Drawings. 43 f. The pipe line shall be within: 44 1) ±1 inch of the elevation on the Drawings 45 g. Place and compact embedment material to adequately support haunches in 46 accordance with the pipe manufacturer’s recommendations. 47 33 05 05 UTILITY TRENCH EXCAVATION, EMBEDMENT, AND BACKFILL Page 15 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 17, 2024 Effective July 1, 2024 h. For steel pipe, the initial embedment lift shall not exceed the spring line prior to 1 compaction. 2 i. Place remaining embedment, including initial backfill, to 12 inches above the 3 pipe. 4 j. Where valves are present and not placed within a vault or manhole, extend 5 initial backfill up to the valve nut. 6 k. Compact the embedment and initial backfill to a minimum of 95 percent of 7 Standard Proctor density in accordance with ASTM D698. 8 l. Wrap trench geotextile fabric around entirety of pipe embedment. 9 m. Place marker tape on top of the trench geotextile fabric in accordance with 10 Section 33 05 97. 11 4. HDPE Pipe (All Uses), Gravity Sanitary Sewer Pipe (All Materials), and Force 12 Mains (All Materials) by Open Cut: 13 a. Embedment zone shall be of uniform material. 14 b. Use crushed rock for embedment. 15 c. Place evenly spread bedding material on a firm trench bottom. 16 d. Spread bedding so that lines and grades are maintained and that there are no 17 sags in the sanitary sewer pipe line. 18 e. Provide firm, uniform bedding a minimum of 6 inches below the pipe. 19 1) Additional bedding may be required if groundwater is present in the trench. 20 f. Place pipe on the bedding according to the alignment shown in the Drawings. 21 g. The pipe line shall be within: 22 1) ±3 inches of the elevation on the Drawings for 24-inch and smaller water 23 lines and force mains 24 2) ±1 inch of the elevation on the Drawings for 30-inch and larger water lines 25 and force mains 26 3) ±0.1 inches of the elevation, and consistent with the grade shown on the 27 Drawings for gravity sanitary sewer. 28 h. Place and compact embedment material to adequately support haunches in 29 accordance with the pipe manufacturer’s recommendations. 30 i. For lines 30 inches and greater in diameter, the embedment lift shall not exceed 31 the spring line prior to compaction. 32 j. Place remaining embedment, including initial backfill, to 12 inches above the 33 pipe. 34 k. Compact the embedment and initial backfill to a minimum of 95 percent of 35 Standard Proctor density in accordance with ASTM D698. 36 l. Place trench geotextile fabric on top of the initial backfill. 37 m. Place marker tape on top of the trench geotextile fabric in accordance with 38 Section 33 05 97. 39 5. Storm Sewer (RCP) 40 a. The bedding and the pipe zone up to the spring line shall be of uniform 41 material. 42 b. Use crushed rock for embedment up to the spring line. 43 c. The specified backfill material may be used above the spring line. 44 d. Place evenly spread bedding material on a firm trench bottom. 45 e. Spread bedding so lines and grades are maintained and there are no sags in the 46 storm sewer pipe line. 47 f. Provide firm, uniform bedding a minimum of 6 inches below the pipe. 48 33 05 05 UTILITY TRENCH EXCAVATION, EMBEDMENT, AND BACKFILL Page 16 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 17, 2024 Effective July 1, 2024 1) Additional bedding may be required if groundwater is present in the trench. 1 g. Place pipe on the bedding according to the alignment of the Drawings. 2 h. The pipe line shall be within ±0.1 inches of the elevation and consistent with 3 the grade shown on the Drawings. 4 i. Place embedment material up to the spring line. 5 1) Place embedment to ensure adequate support is obtained in the haunch. 6 j. Compact the embedment and initial backfill to a minimum of 95 percent of 7 Standard Proctor density in accordance with ASTM D698. 8 k. Place trench geotextile fabric on top of pipe and crushed rock. 9 6. Storm Sewer Reinforced Concrete Box 10 a. Crushed rock shall be used for bedding. 11 b. The pipe zone and the initial backfill shall be: 12 1) Crushed rock, or 13 2) Native backfill material compacted to a minimum of 95 percent of Standard 14 Proctor density in accordance with ASTM D698 15 c. Place evenly spread compacted bedding material on a firm trench bottom. 16 d. Spread bedding so lines and grades are maintained and there are no sags in the 17 storm sewer pipe line. 18 e. Provide firm, uniform bedding a minimum of 6 inches below the box. 19 1) Additional bedding may be required if groundwater is present in the trench. 20 f. Fill the annular space between multiple boxes with crushed rock or CLSM in 21 accordance with 03 34 13. 22 g. Place pipe on the bedding according to the alignment of the Drawings. 23 h. The pipe shall be within ±0.1 inches of the elevation and consistent with the 24 grade shown on the Drawings. 25 i. Compact the embedment initial backfill to a minimum of 95 percent of 26 Standard Proctor density in accordance with ASTM D698. 27 7. Water Services (2 inches and smaller in Diameter) 28 a. The entire embedment zone shall be of uniform material. 29 b. Utility sand shall be generally used for embedment. 30 c. Place evenly spread bedding material on a firm trench bottom. 31 d. Provide firm, uniform bedding a minimum of 1 inch below the service line. 32 e. Place pipe on the bedding according to the alignment of the Drawings. 33 f. Place remaining embedment, including initial backfill, to 1-inch minimum 34 above the service line. 35 g. Compact the initial backfill. 36 8. Sanitary Sewer Services 37 a. The entire embedment zone shall be of uniform material. 38 b. Crushed rock or fine crushed rock shall be used for embedment. 39 c. Place evenly spread bedding material on a firm trench bottom. 40 d. Spread bedding so that lines and grades are maintained and that there are no 41 sags in the sanitary sewer pipe line. 42 e. Provide firm, uniform bedding, a minimum of 2 inches below the service line. 43 1) Additional bedding may be required if groundwater is present in the trench. 44 f. Place pipe on the bedding according to the alignment of the Drawings. 45 g. Place remaining embedment, including initial backfill, to 2 inches above the 46 service line. 47 33 05 05 UTILITY TRENCH EXCAVATION, EMBEDMENT, AND BACKFILL Page 17 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 17, 2024 Effective July 1, 2024 h. Compact the initial backfill to a minimum of 95 percent of Standard Proctor 1 density in accordance with ASTM D698. 2 G. Trench Backfill 3 1. At a minimum, place backfill in such a manner that the required in-place density 4 and moisture content is obtained, and so that there will be no damage to the surface, 5 pavement or structures due to any trench settlement or trench movement. 6 a. Meeting the requirements of this Section does not relieve the responsibility to 7 damages associated with the Work. 8 2. Backfill Material 9 a. Final backfill depth less than 15 feet 10 1) Backfill with: 11 a) Native backfill material, 12 b) Blended backfill material, or 13 c) Select backfill material, CSS, or CLSM when specifically required. 14 b. Final backfill depth 15 feet or greater: (under pavement or future pavement) 15 a) Backfill with: 16 (1) Native backfill material, 17 (2) Blended backfill material, or 18 (3) Select backfill material, CSS, or CLSM when specifically required. 19 20 c. Final backfill depth 15 feet or greater: (not under pavement or future pavement) 21 1) Backfill with: 22 a) Native backfill material, or 23 b) Blended backfill material. 24 d. Backfill for water and sewer service lines: 25 1) Match backfill requirement of the main being tapped. 26 3. Required Compaction and Density 27 a. Final backfill (depths less than 15 feet) 28 1) Compact native backfill material, blended backfill material or select 29 backfill to a minimum of 98 percent of Standard Proctor density in 30 accordance with ASTM D698 at moisture content within -2 to +4 31 percentage points of the optimum moisture. 32 2) CSS or CLSM requires no compaction. 33 b. Final backfill (depths 15 feet and greater/under existing or future pavement) 34 1) Compact select backfill to a minimum of 98 percent Standard Proctor in 35 accordance with ASTM D698 at moisture content within -2 to +4 36 percentage points of optimum moisture. 37 2) CSS or CLSM requires no compaction. 38 c. Final backfill (depths 15 feet and greater/not under existing or future pavement) 39 1) Compact native backfill material, blended backfill material, or select 40 backfill to a minimum of 98 percent Standard Proctor in accordance with 41 ASTM D698 at moisture content within -2 to +4 percentage points of 42 optimum moisture. 43 4. Saturated Soils 44 a. If in-situ soils consistently demonstrate that they are greater than 4 percentage 45 points over optimum moisture content, the soils are considered saturated. 46 b. Flooding the trench or water jetting is strictly prohibited. 47 33 05 05 UTILITY TRENCH EXCAVATION, EMBEDMENT, AND BACKFILL Page 18 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 17, 2024 Effective July 1, 2024 c. If saturated soils are identified in the Drawings or Geotechnical Report in the 1 Appendix, Contractor shall proceed with Work following all backfill 2 procedures outlined in the Drawings for areas of soil saturation greater than 4 3 percentage points above optimum moisture content.. 4 d. If saturated soils are encountered during Work but not identified in Drawings or 5 Geotechnical Report in the Appendix: 6 1) The Contractor shall: 7 a) Immediately notify the City. 8 b) Submit a Contract Claim for Extra Work associated with direction from 9 City. 10 2) The City shall: 11 a) Investigate soils and determine if Work can proceed in the identified 12 location. 13 b) Direct the Contractor of changed backfill procedures associated with 14 saturated soils that may include: 15 (1) Imported backfill 16 (2) A site specific backfill design 17 5. Placement of Backfill 18 a. Use only compaction equipment specifically designed for compaction of a 19 particular soil type and within the space and depth limitation experienced in the 20 trench. 21 b. Flooding the trench or water setting is strictly prohibited. 22 c. Place in loose lifts not to exceed 8 inches. 23 d. Compact to specified densities. 24 e. Compact only on top of initial backfill, undisturbed trench, or previously 25 compacted backfill. 26 f. Remove any loose materials due to the movement of any trench box, shoring, 27 or sloughing of the trench wall. 28 g. Install appropriate markers for water and sanitary sewer trenches in accordance 29 with Section 33 05 97. 30 6. Backfill Means and Methods Demonstration 31 a. Demonstration will be required to be performed at the City’s discretion. 32 b. Notify the City in writing with sufficient time for the City to obtain samples 33 and perform Standard Proctor test in accordance with ASTM D698. 34 c. The results of the Standard Proctor 35 d. Test must be received prior to beginning excavation. 36 e. Upon commencing of backfill placement for the project, demonstrate means 37 and methods to obtain the required densities. 38 f. Demonstrate Means and Methods for compaction including: 39 1) Depth of lifts for backfill which shall not exceed 8 inches 40 2) Method of moisture control for excessively dry or wet backfill 41 3) Placement and moving trench box, if used 42 4) Compaction techniques in an open trench 43 5) Compaction techniques around structure 44 g. Provide a testing trench box to provide access to the recently backfilled 45 material. 46 h. The Contractor will provide a qualified testing lab full time during backfill 47 operations to randomly test density and moisture continent. 48 33 05 05 UTILITY TRENCH EXCAVATION, EMBEDMENT, AND BACKFILL Page 19 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 17, 2024 Effective July 1, 2024 1) The testing lab will provide results as available on the job site. 1 7. Varying Ground Conditions 2 a. Notify the City of varying ground conditions and the need for additional 3 Proctors. 4 b. Request additional Proctors when soil conditions change. 5 c. Significant changes in soil conditions will require an additional Means and 6 Methods demonstration. 7 H. Trench Dam 8 1. Place controlled low-strength material (CLSM) or cement stabilized sand (CSS) 9 across the full width of the trench with a minimum thickness of 2 feet at the 10 locations indicated on the plans. 11 2. Install Trench Dam to whichever option is reached first: a minimum of four feet 12 above the pipe, bottom of pavement subgrade, or bottom of topsoil. 13 3. Key Trench Dam a minimum of 12 inches into the bottom of trench. 14 3.5 REPAIR [NOT USED] 15 3.6 RE-INSTALLATION [NOT USED] 16 3.7 FIELD QUALITY CONTROL 17 A. Field Tests and Inspections 18 1. Proctors 19 a. Perform Proctors in accordance with ASTM D698. 20 b. Make test results available within 4 calendar days and distributed to: 21 1) City Project Manager 22 2) City Inspector 23 3) Engineer 24 c. Notify the City if the characteristic of the soil changes. 25 d. Perform new Proctors for varying soils: 26 1) When indicated in the geotechnical investigation in the Appendix 27 2) If notified by the City 28 e. Trenches where different soil types are present at different depths: 29 1) Base Proctors on the mixture of the soils. 30 2. Density Testing of Backfill 31 a. In accordance with ASTM D6938. 32 b. Provide testing trench protection for trench depths in excess of 5 feet. 33 c. Place, move and remove testing trench protection as necessary to facilitate any 34 City performed tests. 35 d. For final backfill depths less than 15 feet and trenches of any depth not under 36 existing or future pavement: 37 1) Perform density testing twice per working day when backfilling operations 38 are being conducted. 39 2) The testing lab shall take a minimum of 3 density tests of the current lift in 40 the available trench. 41 e. For final backfill depths 15 feet and greater deep and under existing or future 42 pavement: 43 33 05 05 UTILITY TRENCH EXCAVATION, EMBEDMENT, AND BACKFILL Page 20 of 20 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 17, 2024 Effective July 1, 2024 1) Perform density testing twice per working day when backfilling operations 1 are being conducted. 2 2) The testing lab shall take a minimum of 3 density tests of the current lift in 3 the available trench. 4 3) The testing lab will remain onsite sufficient time to test 2 additional lifts. 5 f. Make the excavation available for City performed tests. 6 g. Provide results to the City’s Inspector upon completion of the testing. 7 h. Provide a formal report to the City within 48 hours including: 8 1) Location of test by station number 9 2) Time and date of test 10 3) Depth of testing 11 4) Field moisture 12 5) Dry density 13 6) Proctor identifier 14 7) Percent Standard Proctor density 15 16 3. Density of Embedment 17 a. Storm sewer boxes that are embedded with native backfill material, blended 18 backfill material, cement modified backfill material or select material will 19 follow the same testing procedure as backfill. 20 b. Test fine crushed rock or crushed rock embedment in accordance with ASTM 21 D6938 or ASTM D1556. 22 B. Non-Conforming Work 23 1. Remove and replace all non-conforming work. 24 3.8 SYSTEM STARTUP [NOT USED] 25 3.9 ADJUSTING [NOT USED] 26 3.10 CLEANING [NOT USED] 27 3.11 CLOSEOUT ACTIVITIES [NOT USED] 28 3.12 PROTECTION [NOT USED] 29 3.13 MAINTENANCE [NOT USED] 30 3.14 ATTACHMENTS [NOT USED] 31 END OF SECTION 32 33 Revision Log DATE NAME SUMMARY OF CHANGE 6/17/2024 Added restrictions on benching and sloping; 3.4.A 34 33 05 07 STEEL CASING PIPE Page 1 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 33 05 07 1 STEEL CASING PIPE 2 3 PART 1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Minimum requirements for manufacturing, furnishing, and transporting Steel 7 Casing Pipe to be installed by Open Cut or by Other than Open Cut at the locations 8 specified in the Drawings. 9 B. Deviations from this City of Denton Standard Specification: 10 1. None. 11 C. Related Specification Sections include but are not limited to: 12 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 13 Contract. 14 2. Division 1 - General Requirements. 15 3. Section 33 05 05 – Utility Trench Excavation, Embedment and Backfill. 16 4. Section 33 05 10 – Auger Boring. 17 5. Section 33 05 11 – Hand Tunneling. 18 6. Section 33 05 15 – Installation of Carrier Pipe in Casing or Tunnel Liner Plate. 19 1.2 PRICE AND PAYMENT PROCEDURES 20 A. Measurement and Payment 21 1. Open Cut 22 a. Measurement 23 1) Measured horizontally along the ground surface for Steel Casing Pipe 24 installed. 25 b. Payment 26 1) The work performed and materials furnished in accordance with this item 27 and measured as provided under “Measurement” will be paid for at the unit 28 price bid per linear foot for “Casing by Open Cut” installed for: 29 a) Various Sizes. 30 c. The price bid shall include: 31 1) Furnishing and installing Steel Casing Pipe by Open Cut as specified by the 32 Drawings 33 2) Pavement Removal 34 3) Excavation 35 4) Hauling 36 5) Disposal of excess material 37 6) Furnishing, placement, and compaction of embedment 38 7) Furnishing, placement, and compaction of backfill 39 8) Clean-up 40 33 05 07 STEEL CASING PIPE Page 2 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1 2. By Other than Open Cut 2 a. Measurement 3 1) Measured horizontally along the ground surface of Steel Casing Pipe 4 installed. 5 b. Payment 6 1) The work performed and materials furnished in accordance with this item 7 and measured as provided under “Measurement” will be paid for at the unit 8 price bid per linear foot for “Casing or Tunnel Liner Plate by Other than 9 Open Cut” installed for: 10 a) Various Sizes. 11 2) The work performed and materials furnished in accordance with this item 12 and measured as provided under “Measurement” will be paid for at the unit 13 price bid per linear foot for “Casing by Other than Open Cut” installed for: 14 a) Various Sizes. 15 c. The price bid shall include: 16 1) Furnishing and installing Steel Casing Pipe by Other than Open Cut as 17 specified by the Drawings 18 2) Launching Shaft 19 3) Receiving Shaft 20 4) Contact grouting, if required 21 5) Pavement Removal 22 6) Excavation 23 7) Hauling 24 8) Disposal of excess material 25 9) Furnishing, placement, and compaction of backfill 26 10) Clean-up 27 B. In-House Design Measurement and Payment [Used only when approved by the City on 28 projects where geotechnical information is not available, encountered rock shall be as 29 dictated in this Section. If not used delete this Paragraph B and all subparagraphs.] 30 1. In-House Design By Other than Open Cut (Common Excavation) 31 a. Measurement 32 1) Measured horizontally along the ground surface of Steel Casing Pipe 33 installed 34 b. Payment 35 1) The work performed, and materials furnished in accordance with this item 36 and measured as provided under “Measurement” will be paid for at the unit 37 price bid per linear foot for “In-House Design Casing by Other than Open 38 Cut (Common Excavation)” installed for: 39 a) Various Sizes 40 c. The price bid shall include: 41 1) Furnishing and installing Steel Casing Pipe by Other than Open Cut for 42 City In-House Design as specified by the Drawings 43 2) Launching Shaft 44 3) Receiving Shaft 45 4) Contact grouting, if required 46 5) Pavement Removal 47 6) Excavation 48 33 05 07 STEEL CASING PIPE Page 3 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 7) Hauling 1 8) Disposal of excess material 2 9) Furnishing, placement, and compaction of backfill 3 10) Clean-up 4 2. In-House Design By Other than Open Cut Additive for Rock Excavation [The 5 quantity for this bid-item should be same as for “In-House Design By Other than 6 Open Cut (No Rock Encountered)”.] 7 a. Measurement 8 1) Measured horizontally along the ground surface of Steel Casing Pipe 9 installed 10 b. Payment 11 1) The work performed, and materials furnished in accordance with this item 12 and measured as provided under “Measurement” will be paid for at the unit 13 price bid per linear foot for “In-House Design by Other than Open Cut 14 Additive for Rock Excavation” performed, only if the Contractor 15 successfully demonstrates that rock was excavated in accordance with this 16 Section for: 17 a) Various Sizes 18 c. The price bid shall include: 19 1) Auger boring or hand tunneling through rock 20 2) Excavation 21 3) Hauling 22 4) Disposal of excess material 23 1.3 REFERENCES 24 A. Definitions 25 1. Common Excavation – All excavation not included as rock excavation or 26 excavation otherwise classified. Soils included in common excavation are clays, 27 silts, sands, and gravels. 28 2. Rock Excavation – Includes firm, rigid and unweathered sedimentary, igneous and 29 metamorphic rock that is naturally in-place. Boulders or detached stones with a 30 volume of 1/2 cubic yard or more are classified as rock excavation. When common 31 excavation is interlayered with the rock excavation, and the common excavation 32 makes up 25 percent or less of the volume, the entire volume is classified as rock 33 excavation. 34 B. Reference Standards 35 1. Reference standards cited in this Section refer to the current reference standard 36 published at the time of the latest revision date logged at the end of this Section 37 unless a date is specifically cited. 38 2. ASTM International (ASTM): 39 a. A139, Standard Specification for Electric-Fusion (Arc)-Welded Steel Pipe 40 (NPS Sizes 4 and Over). 41 3. American Water Works Association (AWWA): 42 a. C210, Liquid-Epoxy Coatings and Linings for Steel Water Pipe and Fittings. 43 1.4 ADMINISTRATIVE REQUIREMENTS 44 45 33 05 07 STEEL CASING PIPE Page 4 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 A. Rock Excavation 1 1. If the City determines that the excavation can be defined as Rock Excavation as 2 defined above, the Contractor shall be entitled to full payment in accordance with 3 the Additive Rock Excavation bid item. Otherwise the Contractor will not be 4 entitled to additional payment beyond the Common Excavation bid item. 5 1.5 SUBMITTALS 6 A. Submittals shall be in accordance with Section 01 33 00. 7 B. All submittals shall be approved by the City prior to delivery. 8 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 9 A. Product Data 10 1. Exterior Coating 11 a. Material data 12 b. Field touch-up procedures 13 2. Interior Coating 14 a. Material data 15 b. Field touch-up procedures 16 B. Shop Drawings 17 1. Shop drawings are not required for installation of steel casing pipe by open cut. 18 2. Provide the following shop drawings for installation of steel casing pipe by other 19 than open cut: 20 a. Furnish details for Steel Casing Pipe outlining the following: 21 1) Grout/lubrication ports 22 2) Joint details 23 3) Other miscellaneous items for furnishing and fabricating pipe 24 b. Submit calculations in a neat, legible format sealed by a Professional Engineer 25 Licensed in Texas, consistent with the information provided in the geotechnical 26 report (if applicable), including: 27 1) Calculations confirming pipe jacking capacity is adequate to resist 28 anticipated jacking loads for each crossing with a minimum safety factor of 29 2 30 2) Calculations confirming pipe capacity is adequate to safely support all other 31 anticipated loads, including earth and groundwater pressures, surcharge 32 loads, and handling loads 33 3) Calculations confirming jointing method will support all loading conditions 34 1.7 CLOSEOUT SUBMITTALS [NOT USED] 35 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 36 1.9 QUALITY ASSURANCE [NOT USED] 37 38 33 05 07 STEEL CASING PIPE Page 5 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1.10 DELIVERY, STORAGE, AND HANDLING 1 A. Delivery, Storage and Handling Requirements 2 1. Secure and maintain a location to store the material in accordance with Section 01 3 66 00. 4 2. Prior to delivery of the pipe, end/internal bracing shall be furnished and installed as 5 recommended by the manufacturer, for protection during shipping and storage. 6 3. Deliver, handle, and store pipe in accordance with the manufacturer’s 7 recommendations to protect coating systems. 8 1.11 FIELD CONDITIONS [NOT USED] 9 1.12 WARRANTY [NOT USED] 10 PART 2 - PRODUCTS 11 2.1 CITY-FURNISHED PRODUCTS [NOT USED] 12 2.2 MATERIALS 13 A. Performance / Design Criteria 14 1. Contractor is fully responsible for the design of steel casing pipe which must meet 15 or exceed the design requirements of this Section for the intended installation 16 method. 17 2. For steel casing pipe to be installed by other than open cut: 18 a. Design of the casing pipe shall account for all installation and service loads 19 including: 20 1) Jacking loads 21 2) External groundwater and earth loads 22 3) Traffic loads 23 4) Practical consideration for handling, shipping and other construction 24 operations 25 5) Any other live or dead loads reasonable anticipated. 26 b. Design shall be signed and sealed by a Professional Engineer Licensed in 27 Texas. 28 c. The allowable jacking capacity shall not exceed 50 percent of the minimum 29 yield 30 31 33 05 07 STEEL CASING PIPE Page 6 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3. Steel casing pipe shall have minimum wall thickness as follows. The Drawings or 1 other design criteria listed in this Section may require a higher wall thickness, but in 2 no case should the pipe wall thickness be less than the following: 3 Casing Pipe Diameter (inches) Minimum Wall Thickness All Other Locations (inches) 32 and smaller .5 (1/2) 36 – 42 .625 (5/8) 44 – 48 .6875 (11/16) Greater than 48 Project specific design Greater than 20-ft deep Project specific design 4. Provide steel casing pipe with inside diameter sufficient to install the required 4 carrier pipe with casing spacers and in accordance with the minimum casing 5 diameter requirements in Section 33 05 15. 6 5. Furnish in lengths that are compatible with Contractor’s shaft sizes and allowable 7 work areas. 8 6. Random segments of pipe will only be allowed for closing segments. 9 7. When required by installation method, provide grout/lubricant ports along the pipe 10 at intervals of 10 feet or less. 11 a. Attach ports and fittings to the pipe in a manner that will not materially affect 12 the strength of the pipe nor interfere with the installation of carrier pipe. 13 b. Provide plugs for sealing the fittings which are capable of withstanding all 14 external and internal pressures and loads without leaking. 15 B. Materials 16 1. Provide new, smooth-wall, carbon steel pipe in accordance with ASTM A139, 17 Grade B. 18 2. Allowed Dimensional Tolerances: 19 a. Minimum wall thickness (at any point): Minimum 87.5 percent of the nominal 20 wall thickness. 21 b. Outside circumference: Within 1.0 percent or 3/4 inch of the nominal 22 circumference, whichever is less. 23 c. Outside diameter: Within 1/8 inch of the nominal outside diameter. 24 d. Roundness (difference between the major and minor outside diameters): 25 Maximum 0.5 percent of the specified nominal outside diameter or 1/4 inch, 26 whichever is less. 27 e. Maximum allowable straightness deviation: 1/8 inch in any 10-foot length. 28 3. Provide square ends for all steel pipe. 29 a. Ensure pipe end section variations do not exceed 1/8 inch at any point from a 30 true plane perpendicular to the axis of the pipe and passing through the center 31 of the pipe at the end. 32 b. When pipe ends require a beveled edge for welding, bevel on the outside to an 33 angle of 35 degrees with a tolerance of ± 2½ degrees and with a width of root 34 face 1/16 inch ± 1/32 inch. 35 4. Fabricate steel casing pipe with longitudinal or spiral-welded seams. 36 33 05 07 STEEL CASING PIPE Page 7 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 a. Grind all girth weld seams flush. 1 C. Finishes 2 1. Clean and prepare steel casing pipe for coating and lining application in accordance 3 with the requirements of AWWA C210. 4 2. Coat and line steel casing pipe with a coal-tar epoxy in accordance with the 5 requirements of AWWA C210, meeting the following requirements: 6 a. Color: Black 7 b. Minimum Dry Film Thickness: 16 mils 8 c. Applied in accordance with manufacturer’s recommendations 9 2.3 ACCESSORIES [NOT USED] 10 2.4 SOURCE QUALITY CONTROL [NOT USED] 11 PART 3 - EXECUTION 12 3.1 INSTALLERS [NOT USED] 13 3.2 EXAMINATION [NOT USED] 14 3.3 PREPARATION [NOT USED] 15 3.4 INSTALLATION 16 A. Install steel casing pipe By Other Than Open Cut in accordance with Section 33 05 10 17 or Section 33 05 11 where specified in the Drawings. Install steel casing pipe By Open 18 Cut in accordance with Section 33 05 05 where specified in the Drawings. 19 1. Steel casing pipe connections shall be achieved by full penetration field butt 20 welding or an integral machine press-fit connection (Permalok or equal) prior to 21 installation of the pipe. 22 a. Install integral machined press-fit connections in accordance with the 23 manufacturer’s installation procedures and recommendations. 24 2. Butt welding a square end piece of steel pipe to a 35-degree beveled end of steel 25 pipe in the field is acceptable. 26 B. Install carrier pipe inside steel casing pipe in accordance with Section 33 05 15. 27 C. Perform contact grouting of the annulus outside the casing pipe in accordance with 28 Section 33 05 10 or Section 33 05 11. 29 3.5 REPAIR 30 A. Touch-up external coating after field welds in accordance with manufacturer’s 31 recommendations. 32 3.6 RE-INSTALLATION [NOT USED] 33 3.7 FIELD QUALITY CONTROL [NOT USED] 34 3.8 SYSTEM STARTUP [NOT USED] 35 3.9 ADJUSTING [NOT USED] 36 33 05 07 STEEL CASING PIPE Page 8 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3.10 CLEANING [NOT USED] 1 3.11 CLOSEOUT ACTIVITIES [NOT USED] 2 3.12 PROTECTION [NOT USED] 3 3.13 MAINTENANCE [NOT USED] 4 3.14 ATTACHMENTS [NOT USED] 5 END OF SECTION 6 7 Revision Log DATE NAME SUMMARY OF CHANGE 8 33 05 08 TUNNEL LINER PLATE Page 1 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 33 05 08 1 TUNNEL LINER PLATE 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Minimum requirements for manufacturing, furnishing, and transporting Tunnel 6 Liner Plate to be used for excavation support as installed by Hand Tunneling. 7 B. Deviations from this City of Denton Standard Specification: 8 1. None. 9 C. Related Specification Sections include but are not limited to: 10 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 11 Contract. 12 2. Division 1 - General Requirements. 13 3. Section 33 05 11 – Hand Tunneling. 14 4. Section 33 05 15 – Installation of Carrier Pipe in Casing or Tunnel Liner Plate. 15 1.2 PRICE AND PAYMENT PROCEDURES 16 A. Measurement and Payment 17 1. Tunnel Liner Plate 18 a. Measurement 19 1) Measured horizontally along the ground surface for Tunnel Liner Plate 20 installed. 21 b. Payment 22 1) The work performed and materials furnished in accordance with this item 23 and measured as provided under “Measurement” will be paid for at the unit 24 price bid per linear foot for “Casing or Tunnel Liner Plate by Other than 25 Open Cut” installed for: 26 a) Various Sizes. 27 2) The work performed and materials furnished in accordance with this item 28 and measured as provided under “Measurement” will be paid for at the unit 29 price bid per linear foot for “Tunnel Liner Plate by Hand Tunneling” 30 installed for: 31 a) Various Sizes. 32 c. The price bid shall include: 33 1) Furnishing and installing Tunnel Liner Plate as specified by the Drawings 34 2) Launching Shaft 35 3) Receiving Shaft 36 4) Contact grouting 37 5) Pavement Removal 38 6) Excavation 39 7) Hauling 40 8) Disposal of excess material 41 33 05 08 TUNNEL LINER PLATE Page 2 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 9) Furnishing, placement, and compaction of backfill 1 10) Clean-up 2 1.3 REFERENCES 3 A. Reference Standards 4 1. Reference standards cited in this Section refer to the current reference standard 5 published at the time of the latest revision date logged at the end of this Section 6 unless a date is specifically cited. 7 2. American Association of State Highway and Transportation Officials (AASHTO) 8 a. LRFD, Bridge Design Manual, Section 12.13. 9 b. M190, Bituminous-Coated Corrugated Metal Culvert Pipe and Pipe Arches. 10 3. American Society of Testing and Materials (ASTM): 11 a. A123, Standard Specification for Zinc (Hot- Dip Galvanized) Coating on Iron 12 and Steel Products. 13 b. A153, Standard Specification for Zinc Coating (Hot Dip) on Iron and Steel 14 Hardware. 15 c. A1011, Standard Specification for Steel, Sheet and Strip, Hot-Rolled, Carbon, 16 Structural, High-Strength Low-Alloy and High-Strength Low-Alloy with 17 Improved Formability, and Ultra-High Strength. 18 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 19 1.5 SUBMITTALS 20 A. Submittals shall be in accordance with Section 01 33 00. 21 B. All submittals shall be approved by the City prior to delivery. 22 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 23 A. Product Data 24 1. Tunnel liner plate fasteners 25 a. Material data 26 2. Exterior Coating 27 a. Material data 28 b. Field touch-up procedures 29 3. Annular Grout Mix 30 a. Material data 31 B. Shop Drawings 32 1. Calculations for design of the tunnel liner plate sealed by a Professional Engineer 33 Licensed in the State of Texas 34 2. Detailed plan for grouting the void space on the exterior of the tunnel liner plate 35 3. Grout coupling location and spacing 36 1.7 CLOSEOUT SUBMITTALS [NOT USED] 37 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 38 1.9 QUALITY ASSURANCE [NOT USED] 39 33 05 08 TUNNEL LINER PLATE Page 3 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1 1.10 DELIVERY, STORAGE, AND HANDLING 2 A. Delivery, Storage and Handling Requirements 3 1. Secure and maintain a location to store the material in accordance with Section 01 4 66 00. 5 2. Deliver, store, and handle tunnel liner plate in accordance with manufacturer’s 6 recommendations to protect coating systems. 7 1.11 FIELD CONDITIONS [NOT USED] 8 1.12 WARRANTY [NOT USED] 9 PART 2 - PRODUCTS 10 2.1 CITY-FURNISHED PRODUCTS [NOT USED] 11 2.2 MATERIALS 12 A. Manufacturers 13 1. 2-Flange Tunnel Liner Plate: 14 a. Contech Engineered Solutions, LLC. 15 B. Performance / Design Criteria 16 1. Manufacturer to design tunnel liner plate in accordance with the methods and 17 criteria specified in AASHTO LRFD, Bridge Design Manual, Section 12.13. 18 2. Soil parameters shall be determined by the tunnel liner plate manufacturer. 19 3. Allow a maximum deflection of 3 percent. 20 4. Design for H20 loading angle of 0. 21 C. Materials 22 1. Tunnel Liner Plate 23 a. Provide new, unused, corrugated metal tunnel liner plates made from steel 24 sheets suitable for their intended purpose in accordance with ASTM A1011. 25 1) Potable and Reclaimed Water, and Sewer Force Main Carrier Pipe 26 a) Galvanized and Coated 27 (1) Plate to be galvanized with zinc coating in accordance with ASTM 28 A123 with the following exception: 29 (a) Apply zinc at a rate of 2.0 ounces per square foot on each side. 30 (2) Plate to be coated with a bituminous coating in accordance with the 31 requirements of AASHTO M190 32 (a) Uniformly coat inside and outside of liner plate to minimum 33 thickness of 0.05 inches, measured on crests of corrugations. 34 2) Gravity Sanitary Sewer Carrier Pipe 35 a) Black Steel Plate 36 (1) Only allowed where annulus between plate and carrier pipe is grout 37 filled. Otherwise, provide galvanized steel plate as indicated above. 38 b. Provide tunnel liner plates and fasteners in accordance with AASHTO LRFD, 39 Bridge Design Manual, Section 12.13. 40 33 05 08 TUNNEL LINER PLATE Page 4 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 c. Punch liner plates for bolting on both longitudinal and circumferential seams. 1 Fabricate to permit complete erection from the inside of the tunnel. 2 d. Galvanize bolts and nuts in accordance with ASTM A153. 3 e. Use gasketed liner plates where groundwater is encountered. 4 f. Provide uniformly fabricated plates. 5 1) Plates intended for 1 size tunnel shall be interchangeable. 6 g. Field welding of tunnel liner plate, including grout couplings is not permitted. 7 h. Tunnel liner plate shall be 2-flanged. 8 1) 4-flanged tunnel liner plate is not permitted. 9 i. Wall Thickness: 10 1) 12-gauge minimum is applicable for: 11 a) 72-inches nominal diameter and smaller tunnel liner plate 12 b) Bury depths between 8 feet and 16 feet 13 c) Any application outside of these requirements will require a project 14 specific design for gauge thickness, but wall thickness shall be no less 15 than 12-gauge. 16 j. Provide tunnel liner plate with inside diameter sufficient to install the required 17 carrier pipe as specified in Section 33 05 15. 18 2.3 ACCESSORIES [NOT USED] 19 2.4 SOURCE QUALITY CONTROL [NOT USED] 20 PART 3 - EXECUTION 21 3.1 INSTALLERS [NOT USED] 22 3.2 EXAMINATION [NOT USED] 23 3.3 PREPARATION [NOT USED] 24 3.4 INSTALLATION 25 A. Install tunnel liner plate in accordance with the requirements of Section 33 05 11. 26 B. Install carrier pipe in accordance with Section 33 05 15. 27 C. Contact grout the annulus outside the tunnel liner plate in accordance with Section 33 28 05 11. 29 3.5 REPAIR [NOT USED] 30 3.6 RE-INSTALLATION [NOT USED] 31 3.7 FIELD QUALITY CONTROL [NOT USED] 32 3.8 SYSTEM STARTUP [NOT USED] 33 3.9 ADJUSTING [NOT USED] 34 3.10 CLEANING [NOT USED] 35 3.11 CLOSEOUT ACTIVITIES [NOT USED] 36 33 05 08 TUNNEL LINER PLATE Page 5 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3.12 PROTECTION [NOT USED] 1 3.13 MAINTENANCE [NOT USED] 2 3.14 ATTACHMENTS [NOT USED] 3 END OF SECTION 4 5 Revision Log DATE NAME SUMMARY OF CHANGE 6 33 05 10 AUGER BORING Page 1 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 33 05 10 1 AUGER BORING 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Minimum requirements for Auger Boring using 48-inch and smaller casing pipe 6 with lengths less than 300 feet at the locations as specified in the Drawings. 7 B. Deviations from this City of Denton Standard Specification: 8 1. None. 9 C. Related Specification Sections include but are not limited to: 10 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 11 Contract. 12 2. Division 1 - General Requirements. 13 3. Section 33 05 05 – Utility Trench Excavation, Embedment and Backfill. 14 4. Section 33 05 07 – Steel Casing Pipe. 15 5. Section 33 05 11 – Hand Tunneling. 16 1.2 PRICE AND PAYMENT PROCEDURES 17 A. Measurement and Payment 18 1. Measurement 19 a. This item is considered subsidiary to steel casing pipe construction. 20 2. Payment 21 a. The work performed and materials furnished in accordance with this item are 22 subsidiary to the unit price bid per linear foot of “Casing By Other Than Open 23 Cut” to be complete in place, and no other compensation will be allowed. 24 1.3 REFERENCES 25 A. Reference Standards 26 1. Reference standards cited in this Section refer to the current reference standard 27 published at the time of the latest revision date logged at the end of this Section 28 unless a date is specifically cited. 29 2. Occupational Safety and Health Administration (OSHA) 30 a. OSHA Regulations and Standards for Underground Construction, 29 CFR Part 31 1926, Subpart S, Underground Construction and Subpart P, Excavation. 32 1.4 ADMINISTRATIVE REQUIREMENTS 33 A. Preinstallation 34 1. Provide notice to the City a minimum of 3 workings days in advance of the planned 35 launch of Auger Boring operations. 36 37 33 05 10 AUGER BORING Page 2 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1.5 SUBMITTALS 1 A. Submittals shall be in accordance with Section 01 33 00. 2 B. All submittals shall be approved by the City prior to delivery. 3 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 4 A. Shop Drawings 5 1. Submit the following: 6 a. Detailed description of the methods and equipment to be used in completing 7 each reach of boring operation. 8 b. Description of intended survey methods to ensure the tunnel is advanced and 9 within the line and grade tolerances specified in the Drawings. 10 c. Shaft layout drawings 11 1) Detailing dimensions and locations of all equipment, including overall 12 work area boundaries, crane, front-end loader, forklift, spoil stockpiles, 13 spoil hauling equipment, pumps, generator, pipe storage area, tool trailer or 14 containers, fences, and staging area 15 2) Required for all shaft locations and shall be to scale or show correct 16 dimensions. 17 3) Layout such that all equipment and operations are completely contained 18 within the allowable construction areas specified in the Drawings. 19 d. Schedule in accordance with Division 1 to include the following activities as 20 independent items: 21 1) Mobilization 22 2) Shaft excavation and support 23 3) Water control at shafts 24 4) Working slab construction 25 5) Thrust wall construction 26 6) Auger Boring 27 7) Shaft backfill 28 8) Site restoration 29 9) Cleanup 30 10) Demobilization 31 B. Daily Records 32 1. Submit samples of the boring logs or records to be used a minimum of 7 days prior 33 to beginning Auger Boring. 34 2. Submit daily records to the City’s Inspector by noon on the day following any data 35 or records taken. 36 3. Daily records shall include: 37 a. Date 38 b. Time 39 c. Name of operator 40 d. Bore drive identification 41 e. Installed casing and corresponding tunnel length 42 f. Time required to bore each ring 43 g. Time required to set subsequent ring 44 h. Spoil volumes 45 33 05 10 AUGER BORING Page 3 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 i. Grout volumes and pressures (if required) 1 j. Soil conditions, including occurrences of unstable soils and estimated 2 groundwater inflow rates, if any 3 k. Line and grade offsets 4 l. Any movement of the guidance system 5 m. Problems encountered during boring 6 n. Durations and reasons for delays 7 o. Manually recorded observations made: 8 1) At intervals of not less than 2 every 5 feet 9 2) As conditions change 10 3) As directed by the City 11 1.7 CLOSEOUT SUBMITTALS [NOT USED] 12 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 13 1.9 QUALITY ASSURANCE 14 A. Qualifications 15 1. Contractor 16 a. All boring work shall be performed by an experienced Subcontractor or 17 Contractor who has at least 5 years of experience in performing auger boring 18 work and has completed at least 5 boring projects of similar diameter and 19 ground conditions. 20 1) At least 1 of the projects shall have an individual boring length equal to or 21 greater in length than the longest tunnel on this project. 22 2) Submit details of referenced projects including owner’s name and contact 23 information, project superintendent, and machine operators. 24 b. The project superintendent shall have at least 5 years of experience supervising 25 boring construction. 26 1) The Contractor may be required to submit details of any referenced project 27 including owner’s name, contact information, and project superintendent. 28 c. The site safety representative and personnel responsible for air quality 29 monitoring shall be experienced in tunnel construction and shall have current 30 certification by OSHA. 31 1.10 DELIVERY, STORAGE, AND HANDLING 32 A. Storage and Handling Requirements 33 1. Secure and maintain a location to store the material in accordance with Section 01 34 66 00. 35 1.11 FIELD CONDITIONS [NOT USED] 36 1.12 WARRANTY [NOT USED] 37 PART 2 - PRODUCTS 38 2.1 CITY-FURNISHED [NOT USED] 39 40 33 05 10 AUGER BORING Page 4 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2.2 MATERIALS 1 A. Description 2 1. Steel Casing Pipe in accordance with Section 33 05 07. 3 2. Tunnel Liner Plate is not permitted for use with Auger Boring. 4 B. Design Criteria 5 1. Design excavation methods and spoil conveyance system for the full range of 6 ground conditions described in the Geotechnical Reports. 7 2. Use methods and equipment to control ground movement (surface settlement and 8 heave) above the pipeline to prevent damage to existing utilities, facilities, and 9 improvements. 10 a. Limit any ground movements to values that shall not cause damage to adjacent 11 utilities or surface features. 12 b. Repair any damage caused by ground movements at no cost to the City. 13 c. Provide settlement monitoring to measure ground movement during Auger 14 Boring operations, as required by all applicable Federal, State, or local 15 requirements. 16 2.3 ACCESSORIES [NOT USED] 17 2.4 SOURCE QUALITY CONTROL [NOT USED] 18 PART 3 - EXECUTION 19 3.1 INSTALLERS [NOT USED] 20 3.2 EXAMINATION [NOT USED] 21 3.3 PREPARATION 22 A. Commence boring operations upon completion of the following: 23 1. Review available utility drawings and location of conduits and underground utilities 24 in all areas where excavation is to be performed. 25 a. Notify the applicable one-call system prior to any excavation to avoid 26 interference with the existing conduits and utilities in accordance with Division 27 1. 28 b. Repair damage to existing utilities resulting from excavation at no additional 29 cost to the City. 30 c. Provide and follow notification requirements of permit provider (ie TxDOT, 31 Railroad) if applicable. 32 2. Complete pit excavations and support systems for each drive in accordance with the 33 requirements of the Contract Documents. 34 3.4 INSTALLATION 35 A. General 36 1. Immediately notify the City if any problems are encountered with equipment or 37 materials or if the Contractor believes the conditions encountered are materially and 38 significantly different than those represented within the Contract Documents. 39 33 05 10 AUGER BORING Page 5 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2. Where pipe is required to be installed under railroad embankments or under 1 highways, streets, or other facilities, perform construction in such a manner to not 2 interfere with the operation of the railroad, street, highway, or other facility, and to 3 not weaken or damage any embankment or structure. 4 3. During construction operations, furnish and maintain barricades and lights to 5 safeguard traffic and pedestrians until the backfill has been completed. Once 6 complete, remove barricades and lights from the site. 7 4. Properly manage and dispose of groundwater inflows to the shafts in accordance 8 with requirements of applicable Sections and all permit conditions. 9 a. Discharge of groundwater inflow into sanitary sewers is not allowed without 10 approval in writing from City. 11 5. Furnish all necessary equipment, power, water, and utilities for tunneling, spoil 12 removal and disposal, grouting, and other associated work required for the methods 13 of construction. 14 6. Promptly clean up, remove, and dispose of any spoil or slurry spillage. 15 7. Do not disturb roadways, railroads, canal channels, adjacent structures, landscaped 16 areas, or existing utilities. 17 a. Immediately repair any damage caused to original or better condition and to the 18 satisfaction of the City, at no additional cost. 19 8. Whenever there is a condition that is likely to endanger the stability of the 20 excavation or adjacent structures, operate with a full crew 24 hours a day, including 21 weekends and holidays, without interruption, until those conditions no longer 22 jeopardize the stability of the Work. 23 9. Notify the Texas One Call system (800-245-4545) to request marking of utilities by 24 utility owners/operators that subscribe to One Call. Individually notify all other 25 known or suspected utilities to request marking of these utilities. 26 a. Confirm all requested locates are performed prior to commencing boring 27 operations. 28 b. Visually confirm and stake necessary existing lines, cables, or other 29 underground facilities. Expose necessary crossing utilities and utilities within 30 10 feet laterally of the designed tunnel. 31 c. Control drilling and grouting practices to prevent damage to existing utilities. 32 B. Boring Methods 33 1. Tunnel liner plate shall not be used for Auger Boring. 34 2. Limit boring slopes/grades to less than 8-percent where profiles are not included, or 35 otherwise approved by City. 36 3. The Contractor shall be fully responsible for insuring the methods used are 37 adequate for the protection of workers, pipe, property, and the public. 38 4. The Contractor shall be fully responsible for providing a finished product as 39 required. 40 5. Blasting is not allowed. 41 C. Pits and Trenches 42 1. If the grade of the pipe at the end is below the ground surface, excavate suitable pits 43 or trenches for the purpose of conducting the jacking operations and for placing end 44 joints of the pipe. 45 33 05 10 AUGER BORING Page 6 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2. Securely sheet and brace all areas of open excavation in a manner to prevent earth 1 from caving in where end trenches are cut in the sides of the embankment or 2 beyond it. 3 3. The location of the pit shall meet the approval of the City. 4 4. The pits of trenches excavated to facilitate these operations shall be backfilled in 5 accordance with Section 33 05 05 immediately after the casing and carrier pipe 6 installation has been completed. 7 D. Boring 8 1. Install steel casing pipe by boring hole with the earth auger and simultaneously 9 jacking pipe into place. 10 2. The boring shall proceed from a pit provided for the boring equipment and 11 workmen. 12 3. Pilot Hole 13 a. Required for Casing installed by bore for the following conditions: 14 1) Auger bore lengths exceeding 150-ft in length 15 2) Casing diameters exceeding 20-inches 16 b. Pilot bore approximate 2-inch hole the entire length of the crossing. Check for 17 line and grade on the opposite end of the bore from the work pit. 18 c. Pilot hole shall serve as the centerline of the larger diameter hole to be bored. 19 d. Place excavated material near the top of the working pit and dispose of as 20 required. 21 1) If sufficient room is unavailable, immediate haul-off is required. 22 e. In lieu of boring a pilot hole, auger shall be pulled, at a minimum, after every 23 40 linear feet of progress of steel casing pipe and line and grade shall be 24 evaluated. 25 1) Other methods of maintaining line and grade on the casing may be 26 acceptable, if approved by City. 27 4. The use of water or other fluids in connection with the boring operation will be 28 permitted only to the extent required to lubricate cuttings. 29 a. Jetting or sluicing will not be permitted. 30 5. In unconsolidated soil formations, a gel-forming colloidal drilling fluid consisting 31 of at least 10 percent of high grade carefully processed bentonite may be used to: 32 a. Consolidate cuttings of the bit 33 b. Seal the walls of the hole 34 c. Furnish lubrication for subsequent removal of cuttings and installation of the 35 pipe immediately thereafter 36 6. Allowable variation from the line and grade shall be as specified in this Section. 37 E. Contact Grouting 38 1. Contact grout any voids in excess of 2-inches caused by, or encountered during, the 39 boring or encountered outside of shafts. 40 a. Modify equipment and procedures as required to avoid recurrence of excessive 41 settlements or damage. 42 b. Perform contact grouting procedures in accordance with Section 33 05 11. 43 F. Control of Line and Grade 44 1. Tolerance 45 46 33 05 10 AUGER BORING Page 7 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 a. Pressurized Carrier pipe 1 1) Lateral or vertical variation in the final position of the pipe casing from the 2 line and grade established by the Drawings shall be permitted only to the 3 extent of 1 inch in 10 feet. 4 a) Variation allowed must be regular and only in the direction that will not 5 detrimentally affect the function of the carrier pipe and clearances from 6 other underground utilities or structures. 7 b. Gravity Carrier Pipe 8 1) Lateral variation in the final position of the pipe casing from the line and 9 grade established by the Drawings shall be permitted only to the extent of 1 10 inch in 10 feet. 11 a) Variation allowed must be regular and only in the direction that will not 12 detrimentally affect the function of the carrier pipe and clearances from 13 other underground utilities or structures. 14 2) Grades shown in Drawings must be maintained vertically with no allowable 15 variation. 16 2. Monitor line and grade continuously during boring operations. 17 a. Record deviation with respect to design line and grade once at each casing 18 joint. 19 3. If pipe installation does not meet the specified tolerances, correct the installation, 20 including any necessary redesign of the pipeline or structures and acquisition of 21 necessary easements. 22 4. See pilot bore requirements in this Section. 23 G. Obstructions 24 1. If the boring operations encounter an object or condition that impedes the forward 25 progress of the casing or adversely affects line and grade per this Section, notify the 26 City immediately. 27 2. Correct the condition and remove, clear, or otherwise make it possible for the 28 casing to advance past any objects or obstructions that impede forward progress. 29 3. Proceed with removal of the object or obstruction by methods submitted by the 30 Contractor and accepted by the City. 31 4. Compensation will be allowed by change order for removal of obstructions, as 32 defined as metallic debris, reinforced concrete, rocks, whole trees and other hard 33 objects with a maximum dimension larger than 40 percent of the outer diameter of 34 the casing pipe which: 35 a. Cannot be broken up by the cutting tools with diligent effort 36 b. Are located partially or wholly within the cross-sectional area of the bore 37 c. Contain utilities or ditch lines located longitudinally within the auger bore 38 horizon 39 5. No additional compensation will be allowed for removing, clearing or otherwise 40 making it possible for the casing to advance past objects consisting of cobbles, 41 boulders, wood, reinforced concrete, and other objects or debris with maximum 42 lateral dimensions less than 40 percent of the outer diameter of the casing. 43 6. Compensation 44 a. Payment will be negotiated with the Contractor on a case-by-case basis. 45 b. Provide the City an opportunity to view obstruction prior to removal. 46 33 05 10 AUGER BORING Page 8 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1) Any removal process that does not allow direct inspection of the nature and 1 position of the obstruction will not be considered for payment. 2 3.5 RESTORATION 3 A. After completion of the boring, all construction debris, spoils, oil, grease, and other 4 materials shall be removed from the pipe, pits, and all work areas. 5 1. Cleaning shall be incidental to the construction. 6 B. Plug ends of casing with plywood and place temporary backfill if carrier pipe is 7 installed at a later date. 8 C. Backfill bore pits within 48 hours of successful installation of carrier pipe 9 D. Restoration shall follow construction as the Work progresses. 10 1. Restore and repair any damage resulting from surface settlement caused by shaft 11 excavation or boring. 12 2. Any property damaged or destroyed shall be restored to a condition equal to or 13 better than existing condition prior to construction. 14 3. Restoration shall be completed no later than 14 days after boring is complete, or 15 earlier if required as part of a permit or easement agreement. 16 4. This provision for restoration shall include all property affected by the construction 17 operations. 18 3.6 RE-INSTALLATION [NOT USED] 19 3.7 SITE QUALITY CONTROL 20 A. Field Tests and Inspections 21 1. Allow access to the City and furnish necessary assistance and cooperation to aid in 22 the observations, measurements, data, and sample collection, including, but not 23 limited to the following: 24 a. The City shall have access to the boring system prior to, during, and following 25 all boring operations. 26 b. The City shall have access to the tunneling shafts prior to, during, and 27 following all boring operations. 28 1) This shall include, but not be limited to, visual inspection of installed pipe 29 and verification of line and grade. 30 2) The Contractor shall provide safe access in accordance with all safety 31 regulations. 32 c. The City shall have access to spoils removed from the boring excavation prior 33 to, during, and following all boring operations. 34 1) The City shall be allowed to collect soil samples from the muck buckets or 35 spoil piles a minimum of once every 10 feet and at any time when changes 36 in soil conditions or obstructions are apparent or suspected. 37 B. Safety 38 1. The Contractor is responsible for safety on the job site. 39 a. Perform all Work in accordance with the current applicable regulations of the 40 Federal, State and local agencies. 41 33 05 10 AUGER BORING Page 9 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 b. In the event of conflict, comply with the more restrictive applicable 1 requirement. 2 2. No gasoline powered equipment shall be permitted in receiving shafts/pits. 3 a. Diesel, electrical, hydraulic, and air powered equipment are acceptable, subject 4 to applicable Federal, State, and local regulations. 5 3. Furnish and operate a temporary ventilation system in accordance with applicable 6 safety requirements when personnel are underground. 7 a. Perform all required air and gas monitoring. 8 b. Ventilation system shall provide a sufficient supply of fresh air and maintain an 9 atmosphere free of toxic or flammable gasses in all underground work areas. 10 4. Perform all work in accordance with all current applicable regulations and safety 11 requirements of the Federal, State and local agencies. 12 5. Comply with all applicable provisions of OSHA 29 CFR Part 1926, Subpart S, 13 Underground Construction and Subpart P, Excavations. 14 a. In the event of conflict, comply with the more stringent requirements. 15 6. If personnel will enter the pipe during construction, develop an emergency response 16 plan for rescuing personnel trapped underground in a shaft excavation or pipe. 17 a. Keep all equipment required for emergency response at the Site in accordance 18 with all applicable Federal, State, and local requirements. 19 3.8 SYSTEM STARTUP [NOT USED] 20 3.9 ADJUSTING [NOT USED] 21 3.10 CLEANING [NOT USED] 22 3.11 CLOSEOUT ACTIVITIES [NOT USED] 23 3.12 PROTECTION [NOT USED] 24 3.13 MAINTENANCE [NOT USED] 25 3.14 ATTACHMENTS [NOT USED] 26 END OF SECTION 27 28 Revision Log DATE NAME SUMMARY OF CHANGE 29 33 05 11 HAND TUNNELING Page 1 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 33 05 11 1 HAND TUNNELING 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Minimum requirements for Hand Tunneling using tunnel liner plate or steel casing 6 pipe where specified in the Drawings. 7 B. Deviations from this City of Denton Standard Specification: 8 1. None. 9 C. Related Specification Sections include but are not limited to: 10 1. Division 0 – Bidding Requirements, Contract Forms, and Conditions of the 11 Contract. 12 2. Division 1 – General Requirements. 13 3. Section 33 05 07 – Steel Casing Pipe. 14 4. Section 33 05 08 – Tunnel Liner Plate. 15 1.2 PRICE AND PAYMENT PROCEDURES 16 A. Measurement and Payment 17 1. Measurement 18 a. This item is considered subsidiary to installation of Tunnel Liner Plate or Steel 19 Casing Pipe By Other than Open Cut. 20 2. Payment 21 a. The work performed and materials furnished in accordance with this item are 22 considered subsidiary the unit price bid per linear foot of installation of Tunnel 23 Liner Plate or Steel Casing Pipe By Other than Open Cut to be completed in 24 place, and no other compensation will be allowed. 25 1.3 REFERENCES 26 A. Definitions 27 1. Contact Grouting: Installation of grout in the annulus outside of casing pipe or 28 tunnel liner plate. 29 B. Reference Standards 30 1. Reference standards cited in this Section refer to the current reference standard 31 published at the time of the latest revision date logged at the end of this Section, 32 unless a date is specifically cited. 33 2. American Association of State Highway and Transportation Officials (AASHTO): 34 a. HB-17, Standard Specifications for Highway Bridges. 35 3. ASTM International (ASTM) 36 33 05 11 HAND TUNNELING Page 2 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 a. C39 - Standard Test Method for Compressive Strength of Cylindrical Concrete 1 Specimens. 2 b. C109 - Standard Test Method for Compressive Strength of Hydraulic Cement 3 Mortars 4 c. C150 - Standard Specification for Portland Cement 5 4. Occupational Safety and Health Administration (OSHA) 6 a. OSHA Regulations and Standards for Underground Construction, 29 CFR Part 7 1926, Subpart S, Underground Construction and Subpart P, Excavation. 8 1.4 ADMINISTRATIVE REQUIREMENTS 9 A. Pre-installation 10 1. Provide notice to the City at least 72 hours in advance of the planned launch of 11 tunneling operations. 12 1.5 SUBMITTALS 13 A. Submittals shall be in accordance with Section 01 33 00. 14 B. All submittals shall be approved by the City prior to delivery. 15 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 16 A. Shop Drawings 17 1. Submit the following: 18 a. Detailed description of the methods and equipment to be used in completing 19 each reach of tunnel. 20 b. Description of intended survey methods to ensure the tunnel is advanced and 21 within the line and grade tolerances specified in the Drawings. 22 c. Shaft layout drawings 23 1) Detailing dimensions and locations of all equipment, including overall 24 work area boundaries, crane, front-end loader, forklift, spoil stockpiles, 25 spoil hauling equipment, pumps, generator, pipe storage area, tool trailer or 26 containers, fences, and staging area 27 2) Required for all shaft locations and shall be to scale or show correct 28 dimensions. 29 3) Layout such that all equipment and operations are completely contained 30 within the allowable construction areas specified in the Drawings. 31 d. Tunneling schedule in accordance with Division 1 to include the following 32 activities as independent items: 33 1) Mobilization 34 2) Shaft excavation and support 35 3) Water control at shafts 36 4) Working slab construction 37 5) Thrust wall construction 38 6) Tunneling 39 7) Shaft backfill 40 8) Site restoration 41 9) Cleanup 42 10) Demobilization 43 33 05 11 HAND TUNNELING Page 3 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2. Contact Grouting: Provide the following: 1 a. Contact Grouting Work Plan and Methods including: 2 1) Grouting methods 3 2) Details of equipment 4 3) Grouting procedures and sequences including: 5 a) Injection methods 6 b) Injection pressures 7 c) Monitoring and recording equipment 8 d) Pressure gauge calibration data 9 e) Materials 10 4) Grout mix details including: 11 a) Proportions 12 b) Admixtures including: 13 (1) Manufacturer’s literature 14 (2) Laboratory test data verifying the strength of the proposed grout 15 mix 16 (3) Proposed grout densities 17 (4) Viscosity 18 (5) Initial set time of grout 19 (a) Data for these requirements shall be derived from trial batches 20 from an approved testing laboratory. 21 5) Reference projects: minimum of 3 other similar projects in which the 22 proposed grout mix design was used. 23 6) Grout volumes: calculations for anticipated volumes of grout to be pumped 24 for each application and reach grouted. 25 B. Daily Records 26 1. Submit samples of the tunneling logs or records to be used a minimum of 7 days 27 prior to beginning Hand Tunneling. 28 2. Submit daily records to the City’s Inspector by noon on the day following any data 29 or records taken. 30 3. Daily records shall include: 31 a. Date 32 b. Time 33 c. Name of operator 34 d. Tunnel drive identification 35 e. Installed liner ring and corresponding tunnel length 36 f. Time required to tunnel each ring 37 g. Time required to set subsequent ring 38 h. Spoil volumes (muck carts per liner ring and estimated volume of spoil in each 39 muck cart) 40 i. Grout volumes and pressures 41 j. Soil conditions, including occurrences of unstable soils and estimated 42 groundwater inflow rates, if any 43 k. Line and grade offsets 44 l. Any movement of the guidance system 45 m. Problems encountered during tunneling 46 n. Durations and reasons for delays 47 33 05 11 HAND TUNNELING Page 4 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 o. Manually recorded observations made: 1 1) At intervals of not less than 2 every 5 feet 2 2) As conditions change 3 3) As directed by the City 4 1.7 CLOSEOUT SUBMITTALS [NOT USED] 5 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 6 1.9 QUALITY ASSURANCE 7 A. Qualifications 8 1. Failure to meet the qualification requirements is failure to fulfill the Contract and 9 the Contractor will be required to obtain a Subcontractor that meets the 10 qualification requirements. 11 2. All tunneling work shall be performed by an experienced Subcontractor or 12 Contractor who has at least 5 years of experience in performing tunneling work and 13 has completed at least 5 projects of similar diameter in similar ground conditions. 14 3. All Work shall be performed in the presence of the City unless the City grants prior 15 written approval to perform such work in City’s absence. 16 1.10 DELIVERY, STORAGE, AND HANDLING 17 A. Storage and Handling Requirements 18 1. Secure and maintain a location to store the material in accordance with Section 01 19 66 00. 20 1.11 FIELD CONDITIONS [NOT USED] 21 1.12 WARRANTY [NOT USED] 22 PART 2 - PRODUCTS 23 2.1 CITY-FURNISHED [NOT USED] 24 2.2 MATERIALS 25 A. Description 26 1. Casing Pipe in accordance with Section 33 05 07. 27 2. Tunnel Liner Plate in accordance with Section 33 05 08. 28 B. Design Criteria 29 1. Design excavation methods and spoil conveyance system for the full range of 30 ground conditions described in the Geotechnical Reports. 31 2. Tolerance 32 a. Accurately maintain the face of the excavation inside the tunnel so as to allow 33 the absolute minimum amount of void space outside the casing/liner plate. 34 b. Maintain a maximum of ½ inch tolerance between the outside of the 35 casing/liner plate and the excavation wherever possible. 36 33 05 11 HAND TUNNELING Page 5 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 c. The tunnel diameter shall not be greater than 2 inches larger than the 1 casing/liner outer diameter (O.D.). 2 3. Use methods and equipment to control ground movement (surface settlement and 3 heave) above the pipeline to prevent damage to existing utilities, facilities, and 4 improvements. 5 a. Limit any ground movements to values that shall not cause damage to adjacent 6 utilities and surface features. 7 b. Repair any damage caused by ground movements at no cost to the City. 8 c. Provide settlement monitoring to measure ground movement during tunneling 9 operations, as required by a specific agency or entity. 10 C. Contact Grout: 11 1. Cement 12 a. Type II or Type V Portland cement in accordance with ASTM C150 13 2. Bentonite 14 a. Commercially processed powdered bentonite, Wyoming type, such as Imacco-15 gel, Black Hills, or equal 16 3. Fluidifier 17 a. Capable of holding the solid constituents of the grout in colloidal suspension 18 b. Compatible with the cement and water used in the grouting work 19 c. In accordance with the requirements of ASTM C 937 20 4. Other Admixtures 21 a. May be used subject to the written approval of the City to improve the 22 pumpability, control set time, and prevent segregation and bleeding. 23 5. Equipment: 24 a. Equipment for mixing and injecting grout shall be adequate to satisfactorily 25 mix and agitate the grout and force it into the grout ports, in a continuous flow 26 at the desired pressure. Provide pumps capable of continuously developing a 27 sustained pressure of 15 psi greater than existing groundwater pressures at the 28 grout port connection. 29 b. Provide two pressure gauges, one at the grout pump and one at the collar of 30 each port being grouted. Check accuracy of the gauges periodically with an 31 accurately calibrated pressure gauge. Make available a minimum of two spare 32 pressure gauges on the site at all times. 33 c. The grouting equipment shall be provided with a meter to determine the volume 34 of grout injected. The meter shall be calibrated in cubic feet to the nearest one-35 tenth of a cubic foot. 36 d. Maintain grouting equipment in satisfactory operating condition throughout the 37 course of the Work to ensure continuous and efficient performance during 38 grouting operations. 39 e. Provide suitable stop valves at the collar of each port for use in maintaining 40 pressure as required until the grout has set. 41 f. Provide grout hoses with an inside diameter not less than 1-1/2 inches and 42 capable of withstanding the maximum water and grout pressures to be used. 43 6. Grout Mixes: 44 33 05 11 HAND TUNNELING Page 6 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 a. Develop one or more grout mixes designed to completely fill the voids outside 1 the casing, product pipe, or shafts, and to provide acceptable strength to prevent 2 settlement. 3 b. Provide grout used outside shaft excavations of sufficient strength that allows 4 for efficient excavation by the tunneling equipment. 5 c. Determine 24-hour and 28-day strength of each grout mix in accordance with 6 ASTM C39 or C109. 7 d. All grout mix proportions shall be subject to review and acceptance by the City. 8 7. Grout Composition: 9 a. Grout Materials: Portland cement, bentonite, fluidifier as necessary, and water 10 in the proportions specified herein, or as approved by the City. 11 b. Sand may be added to the grout mix in instances of very high grout takes, as 12 approved in writing by the City. 13 1) The addition of sand may require additional water or fluidifier to be added 14 to the grout mix. 15 8. Compressive Strength: 16 a. 24-hour minimum compressive: 10 psi. 17 b. 28-day minimum compressive strength: 50 psi. 18 c. The grouting contractor shall coordinate with the trenchless subcontractor to 19 ensure the maximum anticipated grout strength can be efficiently excavated by 20 the tunneling equipment without damaging the equipment or causing excessive 21 wear of cutting tools. 22 2.3 ACCESSORIES [NOT USED] 23 2.4 SOURCE QUALITY CONTROL [NOT USED] 24 PART 3 - EXECUTION 25 3.1 INSTALLERS [NOT USED] 26 3.2 EXAMINATION [NOT USED] 27 3.3 PREPARATION 28 A. Commence tunneling upon completion of the following: 29 1. All required submittals have been reviewed and accepted by the City. 30 2. Review available utility drawings and location of conduits and underground utilities 31 in all areas where excavation is to be performed. 32 a. Notify the applicable one-call system prior to any excavation to avoid 33 interference with the existing conduits and utilities. 34 1) Repair damage to existing utilities resulting from excavation at no 35 additional cost to the City. 36 3. Shaft excavations and support systems for each drive completed in accordance with 37 the requirements of the Specifications. 38 4. Site safety representative has prepared a code of safe practices in accordance with 39 OSHA requirements. 40 a. Provide a copy to the City prior to starting shaft construction or tunneling. 41 33 05 11 HAND TUNNELING Page 7 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 b. Hold safety meetings and provide safety instruction for new employees as 1 required by OSHA. 2 5. All specified settlement monitoring points have been installed, approved, and 3 baselined in accordance with the Contract Documents. 4 B. Verification of Stability 5 1. Confirm the ground will remain stable without movement of soil or water while the 6 entry/exit location shoring is removed and while the tunnel is launched or received 7 into a shaft. 8 2. Demonstrate all soils have been stabilized at all tunnel portal locations to: 9 a. Prevent the inflow of weak, running, or flowing soils. 10 b. Prevent the inflow of loose rock. 11 c. Prevent and control groundwater inflows. 12 3.4 INSTALLATION 13 A. Tunnel Methods 14 1. Tunnel liner plate shall not be used where auger boring or jacking methods are 15 used, or where not allowed on the Drawings or permits. 16 2. Wood box tunneling is not allowed. 17 3. The Contractor shall be fully responsible to: 18 a. Ensure the methods used are adequate for the protection of workers, pipe, 19 property and the public 20 b. Provide a finished product as required. 21 B. General 22 1. Immediately notify the City if and when any problems are encountered with 23 equipment or materials, or if the Contractor believes the conditions encountered are 24 materially and significantly different than those represented within the Contract 25 Documents. 26 2. Properly manage and dispose of groundwater inflows to the shafts in accordance 27 with requirements of applicable Sections and all permit conditions. 28 a. Discharge of groundwater inflow into sanitary sewers is not allowed without 29 proper approval and permits. 30 3. Furnish all necessary equipment, power, water, and utilities for tunneling, spoil 31 removal and disposal, grouting, and other associated work required for the methods 32 of construction. 33 4. Promptly clean up, remove, and dispose of any spoil or slurry spillage. 34 5. Whenever there is a condition that is likely to endanger the stability of the 35 excavation or adjacent structures, operate with a full crew 24 hours a day, including 36 weekends and holidays, without interruption, until those conditions no longer 37 jeopardize the stability of the Work. 38 C. Installation with Steel Casing Pipe 39 1. Jack the pipe from the low or downstream end, unless specified otherwise. 40 a. Provide heavy duty jacks suitable for forcing the pipe through the embankment. 41 1) When operating jacks, apply pressure evenly. 42 33 05 11 HAND TUNNELING Page 8 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 b. Provide a suitable jacking head and bracing between jacks so that pressure will 1 be applied to the pipe uniformly around the ring of the pipe. 2 c. Provide a suitable jacking frame or back stop. 3 d. Set the pipe to be jacked on guides, properly braced together, to support the 4 section of the pipe and to direct it in the proper line and grade. 5 e. Place the whole jacking assembly so as to line up with the direction and grade 6 of the pipe. 7 f. In general, excavate embankment material just ahead of the pipe and remove 8 material through the pipe. 9 g. Force the pipe through the embankment with jacks into the space excavated. 10 2. Provide a clearance of at least 1/3 of the circumference of the pipe for the underside 11 of the pipe. Ensure clearance is in accordance with the contour and grade of the 12 pipe. 13 3. Provide a clearance of not more than 2 inches for the upper half of the pipe. 14 a. Taper clearance to 0 at the point where the excavation conforms to the contour 15 of the pipe. 16 4. Extend the distance of the excavation beyond the end of the pipe depending on the 17 character of the material, but do not exceed 2 feet in any case. 18 a. Decrease the distance if the character of the material being excavated makes it 19 desirable to keep the advance excavation closer to the end of the pipe. 20 5. If desired, use a cutting edge of steel plate around the head end of the pipe, 21 extending a short distance beyond the end of the pipe with inside angles or lugs, to 22 keep the cutting edge from slipping back onto pipe. 23 6. When jacking of pipe has begun, carry on the operation without interruption to 24 prevent the pipe from becoming firmly set in the embankment. 25 a. Remove and replace any pipe damaged in the jacking operations, at no cost to 26 the City. 27 b. No vertical deflection is allowed casing during installation. 28 D. Installation with Tunnel Liner Plate 29 1. Install the tunnel liner plates to the limits specified in the Drawings and in 30 AASHTO HB-17, Section II-26, Construction of Tunnels Using Steel Tunnel Liner 31 Plates. 32 a. Assemble liner plates into circumferential rings. 33 b. Liner plates shall be of the type to permit segments to be installed completely 34 from inside the tunnel. 35 2. Accurately maintain the face of the excavation inside the tunnel to allow the 36 absolute minimum of void space outside the casing/liner plate. 37 a. Maintain a maximum of ½ inch tolerance between the outside of the 38 casing/liner plate and the excavation wherever possible. 39 b. The tunnel diameter shall not be greater than 2 inches larger than the liner O.D. 40 3. Install liner plate as closely as possible behind the excavation. 41 a. Excavation shall at no time be more than 6 inches ahead of the required space 42 to install an individual tunnel liner plate. 43 b. Use breast plates, poling boards, or other suitable devices to maintain accurate 44 excavation with the minimum of unsupported excavation at any time. 45 33 05 11 HAND TUNNELING Page 9 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 c. No vertical deflection is allowed for tunnel liner plate during installation. 1 4. Control ground movement (surface settlement and heave) above the pipeline to 2 prevent damage to existing utilities, facilities, and improvements. 3 a. In no case shall ground movements cause damage to adjacent structures, 4 roadways, or utilities. 5 b. Repair any damage resulting from construction activities at no additional cost 6 to the City and without extensions of schedule for completion. 7 E. Contact Grouting 8 1. Grout any voids caused by or encountered during the tunneling or encountered 9 outside of shafts. 10 a. Modify equipment and procedures as required to avoid recurrence of excessive 11 settlements or damage. 12 2. Install contact grout in the void space between the outside of the casing/tunnel liner 13 plate and the excavation. 14 a. For tunnel liner plate, install pressure grout mix at the end of each work day or 15 more often, as conditions warrant. 16 3. Install grout through fittings for the casing/tunnel liner plate 42-inches in diameter 17 or larger. 18 a. Grout fittings shall be fabricated into tunnel liner plate at a maximum spacing 19 of 6 feet. 20 b. Remove and plug grout fittings after pressure grouting. 21 4. Install grout from the low end for all crossings where grout fittings are not used. 22 a. Seal the low end and install grout until grout is extruded from the opposite end. 23 5. Seal pipe grout fittings with screw type plugs upon completion of grouting. 24 F. Control of Line and Grade 25 1. Confirm all established benchmarks and control points provided for the 26 Contractor’s use are accurate. 27 a. Use these benchmarks to furnish and maintain all reference lines and grades for 28 tunneling. 29 b. Use lines and grades to establish the location of the pipe using a laser or 30 theodolite guidance system. 31 c. Submit to the City copies of field notes used to establish all lines and grades 32 and allow the City to check guidance system setup prior to beginning each 33 tunneling drive. 34 d. Provide access for the City to perform survey checks of the guidance system 35 and the line and grade of the carrier pipe on a daily basis during tunneling 36 operations. 37 e. The Contractor remains fully responsible for the accuracy of the work and the 38 correction of inaccurate work, as required. 39 2. The casing/tunnel liner shall be installed in accordance with the following 40 tolerances: 41 a. Variations from design line or grade: ± 2 inches maximum 42 1) If the installation is off line or grade, make the necessary corrections and 43 return to the design alignment and grade at a rate of not more than 1 inch 44 per 25 feet. 45 33 05 11 HAND TUNNELING Page 10 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3. Monitor line and grade continuously during tunneling operations. 1 a. Record deviation with respect to design line and grade once at each pipe joint 2 and submit records to City daily. 3 4. If pipe installation does not meet the specified tolerances, correct the installation, 4 including any necessary redesign of the pipeline or structures and acquisition of 5 necessary easements. 6 G. Obstructions 7 1. If the tunneling operations encounter an object or condition that impedes the 8 forward progress of the casing/liner plate or adversely affects line and grade per this 9 Section, notify the City immediately. 10 2. Correct the condition and remove, clear, or otherwise make it possible for the 11 casing to advance past any objects or obstructions that impede forward progress. 12 3. Proceed with removal of the object or obstruction by methods submitted by the 13 Contractor and accepted by the City. 14 4. Compensation will be allowed by change order for removal of obstructions, as 15 defined as metallic debris, reinforced concrete, rocks, whole trees and other hard 16 objects with a maximum dimension larger than 50 percent of the outer diameter of 17 the casing pipe which: 18 a. Cannot be broken up by the cutting tools with diligent effort 19 b. Are located partially or wholly within the cross-sectional area of the bore 20 c. Contain utilities or ditch lines located longitudinally within the tunnel horizon 21 5. No additional compensation will be allowed for removing, clearing or otherwise 22 making it possible for the casing to advance past objects consisting of cobbles, 23 boulders, wood, reinforced concrete, and other objects or debris with maximum 24 lateral dimensions less than 50 percent of the outer diameter of the casing or liner 25 plate. 26 6. Compensation 27 a. Payment will be negotiated with the Contractor on a case-by-case basis. 28 b. Provide the City an opportunity to view obstruction prior to removal. 29 1) Any removal process that does not allow direct inspection of the nature and 30 position of the obstruction will not be considered for payment. 31 3.5 RESTORATION 32 A. After completion of the tunneling, all construction debris, spoils, oil, grease, and other 33 materials shall be removed from the tunneling pipe, shafts, and all work areas. 34 1. Cleaning shall be incidental to the construction. 35 B. Plug ends of casing with plywood and place temporary backfill if carrier pipe is 36 installed at a later date. 37 C. Backfill pits/shafts within 48 hours of successful installation of carrier pipe 38 D. Restoration shall follow construction as the Work progresses and shall be completed as 39 soon as reasonably possible. 40 1. Restore and repair any damage resulting from surface settlement caused by shaft 41 excavation or tunneling. 42 33 05 11 HAND TUNNELING Page 11 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2. Any property damaged or destroyed, shall be restored to equal to or better than the 1 condition prior to construction. 2 3. Restoration shall be completed no later than 14 days after tunneling is complete, or 3 earlier if required as part of a permit or easement agreement. 4 4. This provision for restoration shall include all property affected by the construction 5 operations. 6 3.6 RE-INSTALLATION [NOT USED] 7 3.7 SITE QUALITY CONTROL 8 9 A. Field Test and Inspections 10 1. Allow access to the City and furnish necessary assistance and cooperation to aid in 11 the observations, measurements, and data and sample collection including, but not 12 limited to: 13 a. The City shall have access to the tunneling system prior to, during, and 14 following all tunneling operations. 15 b. The City shall have access to the tunneling shafts prior to, during, and 16 following all tunneling operations. 17 1) This shall include, but not be limited to, visual inspection of installed pipe 18 and verification of line and grade. 19 2) The Contractor shall provide safe access in accordance with all safety 20 regulations. 21 c. The City shall have access to spoils removed from the tunnel excavation prior 22 to, during, and following all tunneling operations. 23 1) The City shall be allowed to collect soil samples from the muck buckets or 24 spoil piles a minimum of once every 10 feet and at any time when changes 25 in soil conditions or obstructions are apparent or suspected. 26 B. Safety 27 1. The Contractor is responsible for safety on the job site. 28 a. Perform all Work in accordance with the current applicable regulations of the 29 Federal, State and local agencies. 30 b. In the event of conflict, comply with the more restrictive applicable 31 requirement. 32 2. No gasoline powered equipment shall be permitted in receiving shafts/pits. 33 a. Diesel, electrical, hydraulic and air powered equipment are acceptable, subject 34 to applicable Federal, State, and local regulations. 35 3. Furnish and operate a temporary ventilation system in accordance with applicable 36 safety requirements when personnel are underground. 37 a. Perform all required air and gas monitoring. 38 b. Ventilation system shall provide a sufficient supply of fresh air and maintain an 39 atmosphere free of toxic or flammable gasses in all underground work areas. 40 4. Perform all Work in accordance with all current applicable regulations and safety 41 requirements of the Federal, State, and local agencies. 42 5. Comply with all applicable provisions of OSHA 29 CFR Part 1926, Subpart S, 43 Underground Construction and Subpart P, Excavations. 44 33 05 11 HAND TUNNELING Page 12 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 a. In the event of conflict, comply with the more stringent requirements. 1 6. If personnel will enter the pipe during construction, develop an emergency response 2 plan for rescuing personnel trapped underground in a shaft excavation or pipe. 3 a. Keep on-site all equipment required for emergency response in accordance with 4 the agency having jurisdiction. 5 3.8 SYSTEM STARTUP [NOT USED] 6 3.9 ADJUSTING [NOT USED] 7 3.10 CLEANING [NOT USED] 8 3.11 CLOSEOUT ACTIVITIES [NOT USED] 9 3.12 PROTECTION [NOT USED] 10 3.13 MAINTENANCE [NOT USED] 11 3.14 ATTACHMENTS [NOT USED] 12 END OF SECTION 13 Revision Log DATE NAME SUMMARY OF CHANGE 14 33 05 15 INSTALLATION OF CARRIER PIPE IN CASING OR TUNNEL LINER PLATE Page 1 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 33 05 15 1 INSTALLATION OF CARRIER PIPE IN CASING OR TUNNEL LINER PLATE 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Requirements for the installation of carrier pipe into steel casing pipe or tunnel liner 6 plate at locations specified in the Drawings. 7 B. Deviations from this City of Denton Standard Specification: 8 1. None. 9 C. Related Specification Sections include but are not limited to: 10 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 11 Contract. 12 2. Division 1 - General Requirements. 13 3. Section 33 01 31 – Sewer and Manhole Testing. 14 4. Section 33 05 05 – Utility Trench Excavation, Embedment, and Backfill. 15 5. Section 33 14 10 – Ductile Iron Pipe and Fittings. 16 6. Section 33 14 11 – Polyvinyl Chloride (PVC) Pressure Pipe. 17 7. Section 33 14 12 – Concrete Pressure Pipe, Bar-Wrapped Steel Cylinder Type. 18 8. Section 33 14 13 – Buried Steel Pipe. 19 9. Section 33 14 14 – High Density Polyethylene (HDPE) Pipe. 20 10. Section 33 31 10 – Fiberglass Reinforced Pipe for Gravity Sanitary Sewers. 21 11. Section 33 31 14 – Polyvinyl Chloride (PVC) Gravity Sanitary Sewer Pipe. 22 1.2 PRICE AND PAYMENT PROCEDURES 23 A. Measurement and Payment 24 1. Installation of Sanitary Sewer Carrier Pipe in Casing/Tunnel Liner Plate 25 a. Measurement 26 1) Measured horizontally along the ground surface for Sanitary Sewer Carrier 27 Pipe installed. 28 b. Payment 29 1) The work performed and materials furnished in accordance with this item 30 and measured as provided under “Measurement” will be paid for at the unit 31 price bid per linear foot for “Sanitary Sewer Carrier Pipe” installed for: 32 a) Various Sizes. 33 b) Various Materials. 34 33 05 15 INSTALLATION OF CARRIER PIPE IN CASING OR TUNNEL LINER PLATE Page 2 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 c. The price bid shall include: 1 1) Furnishing and installing Sanitary Sewer Carrier Pipe in Casing/Tunnel 2 Liner Plate as specified by the Drawings 3 2) Annular grouting, if required 4 3) Casing spacers 5 4) End seals 6 5) Excavation 7 6) Hauling 8 7) Disposal of excess material 9 8) Clean-up 10 2. Installation of Force Main Carrier Pipe in Casing/Tunnel Liner Plate 11 a. Measurement 12 1) Measured horizontally along the ground surface for Force Main Carrier 13 Pipe installed. 14 b. Payment 15 1) The work performed and materials furnished in accordance with this item 16 and measured as provided under “Measurement” will be paid for at the unit 17 price bid per linear foot for “Force Main Carrier Pipe” installed for: 18 a) Various Sizes. 19 b) Various Materials. 20 c. The price bid shall include: 21 1) Furnishing and installing Force Main Carrier Pipe in Casing/Tunnel Liner 22 Plate as specified by the Drawings 23 2) Annular grouting, if required 24 3) Casing spacers 25 4) End seals 26 5) Excavation 27 6) Hauling 28 7) Disposal of excess material 29 8) Clean-up 30 3. Installation of Water Carrier Pipe in Casing/Tunnel Liner Plate 31 a. Measurement 32 1) Measured horizontally along the ground surface for Water Carrier Pipe 33 installed. 34 b. Payment 35 1) The work performed and materials furnished in accordance with this item 36 and measured as provided under “Measurement” will be paid for at the unit 37 price bid per linear foot for “Water Carrier Pipe” installed for: 38 a) Various Sizes. 39 b) Various Materials. 40 c. The price bid shall include: 41 1) Furnishing and installing Water Carrier Pipe in Casing/Tunnel Liner Plate 42 as specified by the Drawings 43 2) Annular grouting, if required 44 3) Joint restraint 45 4) Casing spacers 46 5) End seals 47 6) Excavation 48 33 05 15 INSTALLATION OF CARRIER PIPE IN CASING OR TUNNEL LINER PLATE Page 3 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 7) Hauling 1 8) Disposal of excess material 2 9) Clean-up 3 1.3 REFERENCES 4 A. Abbreviations 5 1. LDCC – Low Density Cellular Concrete (Grout) 6 2. PVC – Polyvinyl Chloride 7 3. DIP – Ductile Iron Pipe 8 4. HDPE – High Density Polyethylene 9 5. FRP – Fiberglass Reinforced Pipe 10 B. Definitions 11 1. Carrier Pipe – Permanent pipe for operational use that is used to convey flows. 12 2. Casing – A steel pipe or tunnel liner that supports the ground and provides a stable 13 underground excavation for installation of the carrier pipe. 14 3. Annular Grouting – Grouting of the space between the casing and carrier pipe. 15 C. Reference Standards 16 1. Reference standards cited in this Section refer to the current reference standard 17 published at the time of the latest revision date logged at the end of this Section 18 unless a date is specifically cited. 19 2. American Society of Testing and Materials (ASTM): 20 a. C39, Standard Test Method for Compressive Strength of Cylindrical Concrete 21 Specimens. 22 b. C109, Standard Test Method for Compressive Strength of Hydraulic Cement 23 Mortars (Using 2-in or [50 mm] Cube Specimens). 24 c. D2241, Standard Specification for Poly(Vinyl Chloride) (PVC) Pressure-Rated 25 Pipe (SDR Series). 26 3. International Organization for Standardization (ISO): 27 a. 9001, Quality Management Systems - Requirements. 28 4. Occupational Safety and Health Administration (OSHA): 29 a. OSHA Regulations and Standards for Underground Construction, 29 CFR Part 30 1926, Subpart S, Underground Construction and Subpart P, Excavation. 31 5. American Water Works Association (AWWA): 32 a. C200, Steel Water Pipe - 6 Inches and Larger. 33 b. C303, Concrete Pressure Pipe, Bar-Wrapped, Steel-Cylinder Type. 34 c. C900, Polyvinyl Chloride (PVC) Pressure Pipe, and Fabricated Fittings, 4 IN 35 through 60 IN, for Water Transmission and Distribution. 36 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 37 1.5 SUBMITTALS 38 A. Submittals shall be in accordance with Section 01 33 00. 39 B. All submittals shall be approved by the City prior to delivery. 40 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 41 33 05 15 INSTALLATION OF CARRIER PIPE IN CASING OR TUNNEL LINER PLATE Page 4 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1 A. Product Data 2 1. Casing Spacers 3 a. Material Data 4 2. Annular Grout Mix 5 a. Material Data 6 B. Shop Drawings 7 1. Casing Spacers 8 a. Detail drawings and manufacturer’s information for the casing spacers that will 9 be used. 10 1) Include dimensions, component materials, and documentation of 11 manufacturer’s ISO 9001:2000 certification. 12 b. Alternatives to casing spacers may be allowed by the City on a case-by-case 13 basis. 14 1) For consideration of an alternate method, submit a substitution request in 15 accordance with Section 01 25 00. 16 2. End seal or bulkhead designs and locations for casing/liners. 17 3. Annular Grouting Work Plan and Methods including: 18 a. Grouting methods 19 b. Details of equipment 20 c. Grouting procedures and sequences including: 21 1) Injection methods 22 2) Injection pressures 23 3) Monitoring and recording equipment 24 4) Pressure gauge calibration data 25 5) Materials 26 d. Grout mix details including: 27 1) Proportions 28 2) Admixtures including: 29 a) Manufacturer’s literature 30 b) Laboratory test data verifying the strength of the proposed grout mix 31 c) Proposed grout densities 32 d) Viscosity 33 e) Initial set time of grout 34 (1) Data for these requirements shall be derived from trial batches from 35 a qualified testing laboratory. 36 e. Submit a minimum of 3 other similar projects where the proposed grout mix 37 design was used. 38 f. Submit anticipated volumes of grout to be pumped for each application and 39 reach grouted. 40 4. Additional requirements for installations of carrier pipe 24-inch and larger: 41 a. Submit work plan describing the carrier pipe installation equipment, materials 42 and construction methods to be employed. 43 b. For installations without holding jacks or a restrained spacer, provide buoyant 44 force calculations for the pipe during grouting, and measures which will be 45 employed to prevent pipe flotation. 46 33 05 15 INSTALLATION OF CARRIER PIPE IN CASING OR TUNNEL LINER PLATE Page 5 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1) Calculations sealed by a Professional Engineer Licensed in the State of 1 Texas 2 c. Description of methods and devices to prevent buckling of carrier pipe during 3 annular grouting, if required. 4 1.7 CLOSEOUT SUBMITTALS [NOT USED] 5 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 6 1.9 QUALITY ASSURANCE 7 A. Certifications 8 1. Casing spacer manufacturer shall be certified in accordance with ISO 9001:2000. 9 1.10 DELIVERY, STORAGE, AND HANDLING 10 A. Storage and Handling Requirements 11 1. Secure and maintain a location to store the material in accordance with Section 01 12 66 00. 13 1.11 FIELD CONDITIONS [NOT USED] 14 1.12 WARRANTY [NOT USED] 15 PART 2 - PRODUCTS 16 2.1 CITY-FURNISHED PRODUCTS [NOT USED] 17 2.2 MATERIALS 18 A. Performance / Design Criteria 19 1. Install carrier pipe within the horizontal and vertical tolerances as indicated in Part 20 3 of this Section, incorporating all support/spacer dimensions required. 21 2. The following carrier pipe materials are permitted for installation in casing as 22 indicated: 23 Diameter (inches) Material Section Reference Water Line 6-12 DIP (Restrained) PVC (C900, Restrained) HDPE 33 14 10 33 14 11 33 14 14 16-30 DIP (Restrained) AWWA C303 (Restrained) HDPE 33 14 10 33 14 12 33 14 14 36 and greater DIP (Restrained) AWWA C303 (Restrained) AWWA C200 (Restrained) HDPE 33 14 10 33 14 12 33 14 13 33 14 14 24 33 05 15 INSTALLATION OF CARRIER PIPE IN CASING OR TUNNEL LINER PLATE Page 6 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1 Diameter (inches) Material Section Reference Gravity Sanitary Sewer 8-12 DIP (with Ceramic Epoxy) PVC (D2241 or D3034) PVC (C900) HDPE 33 14 10 33 31 14 33 14 11 33 14 14 14-16 DIP (with Ceramic Epoxy) PVC (C900) PVC (D3034) 33 14 10 33 14 11 33 31 14 18-24 DIP (with Ceramic Epoxy) FRP PVC (C900) PVC (D3034) 33 14 10 33 31 10 33 14 11 33 31 14 30 and greater DIP (with Ceramic Epoxy) FRP 33 14 10 33 31 10 Sewer Force Main All Sizes DIP (with Ceramic Epoxy, Restrained) HDPE 33 14 10 33 14 14 2 3. The minimum casing pipe or liner diameter required for nominal carrier pipe 3 diameters will be as indicated below: 4 Nominal Carrier Pipe Size, All Materials (inches) Minimum Casing Diameter (inches) Minimum Liner Plate Diameter (inches) 8 and Smaller 18 48 10 - 15 24 48 16 – 18 30 48 20 - 21 36 48 24 – 27 42 48 30 48 54 Greater than 30 Project Specific Design Project Specific Design 4. Annular Grouting 5 a. Water Line and Sewer Force Main 6 1) No annular grouting will be required. 7 b. Gravity Sanitary Sewer 8 1) Fill all voids between the carrier pipe and the casing or liner plate with low 9 density cellular concrete grout. 10 5. Grout Mixes 11 a. Low Density Cellular Concrete (Grout) 12 1) Portland cement based grout mix with the addition of a foaming agent for 13 the purpose of annular grouting. 14 2) Develop 1 or more grout mixes designed to completely fill the annular 15 space based on the following requirements: 16 33 05 15 INSTALLATION OF CARRIER PIPE IN CASING OR TUNNEL LINER PLATE Page 7 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 a) Provide adequate retardation to completely fill the annular space in 1 1 monolithic pour. 2 b) Provide less than 1 percent shrinkage by volume. 3 c) Minimum compressive strength of 10 psi in 24 hours, 300 psi in 28 4 days 5 d) Design grout mix with the proper density and use proper methods to 6 prevent floating of the carrier pipe. 7 e) Proportion grout to flow and to completely fill all void between the 8 carrier pipe and the casing or liner plate. 9 6. End Seals 10 a. Provide end seals at each end of the casing or liner plate to contain the grout 11 backfill and/or to close the casing/liner ends to prevent the inflow of water or 12 soil. 13 1) Water Piping and Sewer Force Mains less than 24-inch diameter: 14 a) Mortared brick with non-shrink grout, 15 b) Link Seal manufactured by GPT, or 16 c) Approved equal. 17 2) Water Piping and Sewer Force Mains 24-inch diameter and greater: 18 a) Use pull-on, 1/8 inch thick synthetic rubber end seals, Model C 19 manufactured by GPT, or 20 b) Approved equal. 21 3) Gravity Sanitary Sewer Piping: 22 a) No end seals are required if the annulus is grouted. 23 7. Casing Spacers (Insulators) 24 a. Provide casing spacers to support the carrier pipe during installation and 25 grouting (where grout is used). 26 1) For AWWA C303 and C200 pipe, mortar bands may be allowed in lieu of 27 casing spacers in accordance with Section 33 14 12 and Section 33 14 13. 28 b. Provide restrained-style casing spacers to hold carrier pipe stable during 29 grouting operations and prevent floating or movement. 30 c. Provide dielectric strength sufficient to electrically isolate each component 31 from one another and from casing/liner. 32 d. Carrier pipe less than 12-inch diameter and in casing or liner less than or equal 33 to 150 linear feet: 34 1) Provide high density polyethylene spacers manufactured by Raci Spacers 35 North America, Inc. 36 2) Provide sufficient height to allow a minimum clearance of 2 inches 37 between the outside of carrier pipe bells or external restraint system and the 38 inside of the casing/liner surface. 39 e. Carrier pipe 12-inch diameter and larger, or all piping in casing/liner greater 40 than 150 linear feet: 41 1) Minimum 14 gauge 42 2) Stainless steel for water line and sewer force main 43 3) Coated steel for gravity sanitary sewer 44 4) Suitable for supporting weight of carrier pipe without deformation or 45 collapse during installation 46 5) Risers: 47 a) Design for proposed loading 48 33 05 15 INSTALLATION OF CARRIER PIPE IN CASING OR TUNNEL LINER PLATE Page 8 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 b) 10 gauge steel 1 c) Stainless steel for water line and sewer force main 2 d) Provide sufficient height with attached runner to allow a minimum 3 clearance of 2 inches between the outside of carrier pipe bells or 4 couplings and the inside of the casing/liner surface. 5 6) Bands: 6 a) Stainless steel for water line and sewer force main 7 b) Provide polyvinyl chloride inner liner with: 8 (1) Minimum thickness of 0.09 inches 9 (2) Durometer “A” of 85-90 hardness 10 (3) Minimum dielectric strength of 58,000 volts 11 7) Runners: 12 a) Pressure-molded glass reinforced polymer or UHMW 13 b) Minimum 2 inches in width 14 c) Minimum 11 inches in length 15 d) Attach to the band or riser with minimum 3/8 inch welded steel or 16 stainless steel studs. 17 e) Recess runner studs and nuts well below wearing surface of the runner. 18 (1) Fill recess with corrosion inhibiting filler. 19 2.3 ACCESSORIES [NOT USED] 20 2.4 SOURCE QUALITY CONTROL [NOT USED] 21 PART 3 - EXECUTION 22 3.1 INSTALLERS [NOT USED] 23 3.2 EXAMINATION [NOT USED] 24 3.3 PREPARATION [NOT USED] 25 3.4 INSTALLATION 26 A. General 27 1. Carrier pipe installation may not begin until completion of the following tasks: 28 a. All required submittals have been provided, reviewed, and accepted. 29 b. All casing/liner joints are watertight and no water is entering casing or liner 30 from any sources. 31 c. All contact grouting is complete, if required. 32 d. Casing/liner alignment record drawings have been submitted and accepted by 33 City to document deviations due to casing/liner installation. 34 e. Site safety representative has prepared a code of safe practices and an 35 emergency plan in accordance with applicable requirements. 36 2. Install the carrier pipe within the casing or liner between the limits and to the lines 37 and grades specified in the Drawings. Utilize methods which include due regard for 38 safety of workers, adjacent structures and improvements, utilities, and the public. 39 B. Control of Line and Grade 40 1. Install carrier pipe inside the casing or liner within the following tolerances: 41 33 05 15 INSTALLATION OF CARRIER PIPE IN CASING OR TUNNEL LINER PLATE Page 9 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 a. Horizontally +/- 2 inches from design line 1 b. Vertically +/- 1 inch from design grade 2 2. Check line and grade set up prior to beginning carrier pipe installation. 3 3. Perform survey checks of line-and-grade of carrier pipe during installation 4 operations. 5 4. Contractor is fully responsible for the accuracy of the carrier pipe installation, and 6 correction of the installation, if required. 7 a. Where the carrier pipe installation does not satisfy specified tolerances, correct 8 the installation, including if necessary, redesign of the pipe or structures at no 9 additional cost to City. 10 C. Installation of Carrier Pipe 11 1. Pipe Installation 12 a. Remove all loose soil from casing or liner. 13 b. Grind smooth all rough welds at casing joints. 14 c. Install carrier pipe so that there is no metallic contact between the carrier pipe 15 and the casing or liner. 16 d. Install carrier pipe without sliding or dragging it on the ground or in the 17 casing/liner in a manner that could damage the pipe or coatings. 18 1) If guide rails are used, place cement mortar on both sides of the rails. 19 e. Electrically isolate the carrier pipe from the casing spacers and from the 20 casing/liner. 21 f. Grade the bottom of the trench adjacent to each end of the casing/liner to 22 provide firm, uniform, and continuous support for the pipe. If the trench 23 requires backfilling to establish the final trench bottom grade, place the backfill 24 in 6-inch lifts and compact in accordance with Section 33 05 05 prior to 25 installing the carrier pipe. 26 g. After the casing/liner has been placed, pump dry and maintain a dry surface 27 until the carrier pipe and end seals are installed. 28 2. Installation of Casing Spacers 29 a. Provide casing spacers, insulators, or other approved devices to prevent 30 flotation, movement, or damage to the pipe during installation and grout 31 backfill placement. 32 b. Assemble and securely fashion casing spacers to pipeline to be installed in 33 casing or liner. 34 c. Correctly assemble, evenly tighten, and prevent damage to pipe or casing 35 spacer during tightening and pipe insertion. 36 d. Install spacers in accordance with manufacturer’s recommendations. 37 e. Coat the casing spacer runners with a non-corrosive/environmentally safe 38 lubricant to minimize friction when installing the carrier pipe. 39 3. Casing Spacer Spacing 40 a. Maximum distance between spacers is 6 feet 6 inches. 41 b. For 18 and 20-foot-long joints, install a minimum of 5 spacers for PVC and 42 HDPE pipe, and 4 spacers for all other materials. 43 1) Install 2 spacers within 1 foot on each side of bell or flange. 44 2) Space remaining 2 or 3 spacers evenly between pipe ends. 45 c. If the casing or liner is angled or bent, add 1 additional spacer and adjust 46 spacing evenly. 47 33 05 15 INSTALLATION OF CARRIER PIPE IN CASING OR TUNNEL LINER PLATE Page 10 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 d. Provide 2 end spacers at each casing/liner end, within 6 inches of end of 1 casing/liner. 2 e. Install spacers on PVC pipe at the insertion line to prevent over-insertion of the 3 spigot into the bell. 4 4. After Carrier Pipe Installation 5 a. Mortar inside and outside of the joints, as applicable. 6 b. Verify electrical discontinuity between water carrier pipe and the casing/liner. 7 1) If continuity exists, remedy the short by all means necessary, including 8 removing and reinstalling the carrier pipe, prior to installing the annular 9 grout (if applicable). 10 c. If steel pipe is used and not welded prior to installing in casing/liner, welding of 11 pipe will only be allowed after annular grouting is complete (if applicable). 12 D. Installation of End Seals (Water and Sewer Force Main) 13 1. Pipe less than 24 inches in diameter: 14 a. Install mortared brick or Link Seal 15 2. Pipe 24-inches and greater in diameter: 16 a. Ground end of casing/liner minimum 6 inches and maximum 12 inches. 17 b. Place pull-on synthetic rubber end seals on the pipe and pull over the end 18 casing/liner. Securely fasten with stainless steel bands. 19 E. Annular Grouting (For Gravity Sewer Only) 20 1. Prepare pipe as necessary to prevent the pipe from floating during grouting 21 operations as necessary. 22 2. Mixing of Grout 23 a. Mix material in equipment of sufficient size to provide the desired amount of 24 grout material for each stage in a single operation. 25 1) The equipment shall be capable of mixing the grout at the required densities 26 for the approved procedure and shall be capable of changing the densities 27 as required by field conditions. 28 3. Backfill Annular Space with Grout 29 a. Prior to filling the annular space, test the gravity sewer carrier pipe in 30 accordance with Section 33 01 31. 31 b. Verify from the manufacturer, the maximum allowable external pressure the 32 carrier pipe may experience, and do not exceed this grout injection pressure. 33 c. After the installation of the carrier pipe, fill the remaining space (all voids) with 34 LDCC grout. 35 1) All exterior surfaces of the carrier pipe wall and interior surfaces of the 36 casing/liner shall be in contact with grout. 37 2) Pump grout through a pipe or hose. 38 3) Use grout pipes, or other appropriate materials, to avoid damage to carrier 39 pipe during grouting. 40 4. Injection of LDCC Grout 41 a. Grout injection pressure shall not exceed the carrier pipe manufacturer’s 42 recommendations, or 5 psi, whichever is lower. 43 b. Provide pumping equipment of a size sufficient to inject grout at a volume, 44 velocity, and pressure compatible with the size/volume of the annular space. 45 33 05 15 INSTALLATION OF CARRIER PIPE IN CASING OR TUNNEL LINER PLATE Page 11 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 c. Once grouting operations begin, proceed with uninterrupted grouting, unless 1 grouting procedures require multiple stages. 2 d. Grout placements shall not be terminated until the estimated volume of annular 3 grout has been injected. 4 5. Block the carrier pipe during grouting to prevent flotation during grout installation. 5 6. Protect and preserve the interior surfaces of the casing from damage during 6 grouting. 7 3.5 REPAIR [NOT USED] 8 3.6 RE-INSTALLATION [NOT USED] 9 3.7 FIELD QUALITY CONTROL 10 A. Grouting Reports and Records 11 1. Required for the following scenarios: 12 a. Carrier pipe 24-inch and greater 13 b. Carrier pipe of any size longer than 150 feet 14 2. Maintain and submit daily logs of grouting operations including: 15 a. Grouting locations 16 b. Pressures 17 c. Volumes 18 d. Grout mix pumped 19 e. Time of pumping 20 f. Any problems or unusual observations 21 B. Grout Strength Tests 22 1. Perform testing for 24-hour and 28 day compressive strength for the cylinder molds 23 (ASTM C39) or grout cubes (ASTM C109) obtained during grouting operations. 24 2. Provide and test at least 1 set of 4-cylinder molds or grout cutes for each 100 cubic 25 yards of grout injected, but not less than 1 set for each grouting shift. 26 3. Test remaining samples as directed by City. 27 C. Safety 28 1. Contractor is responsible for safety on the job site. 29 a. Perform all Work in accordance with the current applicable regulations of the 30 Federal, State and local agencies. 31 1) Comply with all applicable provisions of OSHA 29 CFR Part 1926, 32 Subpart S, Underground Construction and Subpart P, Excavations. 33 2) In the event of a conflict, comply with the more stringent requirement. 34 2. No gasoline powered equipment shall be permitted in jacking/launching shafts and 35 receiving shafts/pits. 36 a. Diesel, electrical, hydraulic, and air powered equipment is acceptable subject to 37 applicable Federal, State, and local regulations. 38 3. Methods of construction shall be such as to ensure the safety of the Work, 39 Contractor, subcontractor, other personnel on the Site, and the public. 40 4. Furnish and operate a temporary ventilation system in accordance with applicable 41 safety requirements when personnel are underground. 42 a. Perform all required air and gas monitoring. 43 33 05 15 INSTALLATION OF CARRIER PIPE IN CASING OR TUNNEL LINER PLATE Page 12 of 12 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 b. Ventilation system shall provide a sufficient supply of fresh air and maintain an 1 atmosphere free of toxic or flammable gasses in all underground work areas. 2 5. If personnel will enter the pipe during construction, develop an emergency response 3 plan for rescuing personnel trapped underground in a shaft excavation or pipe. 4 a. Keep all equipment required for emergency response at the Site in accordance 5 with all applicable Federal, State, and local requirements. 6 3.8 SYSTEM STARTUP [NOT USED] 7 3.9 ADJUSTING [NOT USED] 8 3.10 CLEANING [NOT USED] 9 3.11 CLOSEOUT ACTIVITIES [NOT USED] 10 3.12 PROTECTION [NOT USED] 11 3.13 MAINTENANCE [NOT USED] 12 3.14 ATTACHMENTS [NOT USED] 13 END OF SECTION 14 15 Revision Log DATE NAME SUMMARY OF CHANGE 16 33 05 61 CAST-IN-PLACE CONCRETE MANHOLES Page 1 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised July 2, 2024 Effective July 2, 2024 SECTION 33 05 61 1 CAST-IN-PLACE CONCRETE MANHOLES 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Sanitary Sewer, Water Appurtenance, or Reclaimed Water Appurtenance Cast-in-6 Place Concrete Manholes. 7 B. Deviations from this City of Denton Standard Specification: 8 1. None. 9 C. Related Specification Sections include but are not limited to: 10 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 11 Contract. 12 2. Division 1 - General Requirements. 13 3. Section 03 00 00 – Concrete and Concrete Reinforcing. 14 4. Section 03 30 00 – Cast-in-Place Concrete. 15 5. Section 03 34 13 – Controlled Low Strength Material (CLSM). 16 6. Section 03 80 00 – Modifications to Existing Concrete Structures. 17 7. Section 33 01 31 – Sewer and Manhole Testing. 18 8. Section 33 01 40 – Liners for Sanitary Sewer Structures. 19 9. Section 33 05 05 – Utility Trench Excavation, Embedment, and Backfill. 20 10. Section 33 05 81 – Frame, Cover, and Grade Rings. 21 11. Section 33 14 10 – Ductile Iron Pipe and Fittings. 22 12. Section 33 31 14 – Polyvinyl Chloride (PVC) Gravity Sanitary Sewer Pipe. 23 1.2 PRICE AND PAYMENT PROCEDURES 24 A. Measurement and Payment 25 1. Manhole 26 a. Measurement 27 1) Measured per each “Manhole” installed to a maximum depth of 6 feet. 28 b. Payment 29 1) The work performed and materials furnished in accordance with this item 30 and measured as provided under “Measurement” will be paid for at the unit 31 price bid per each “Manhole” installed for: 32 a) Various sizes. 33 b) Various types. 34 c. The price bid shall include: 35 1) Furnishing and installing manhole structure as specified by the Drawings 36 2) Excavation 37 3) Forms 38 4) Reinforcing steel, if required 39 33 05 61 CAST-IN-PLACE CONCRETE MANHOLES Page 2 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised July 2, 2024 Effective July 2, 2024 5) Concrete 1 6) Foundation 2 7) Drop pipe, if required 3 8) Vent piping, if required 4 9) Pipe stubs 5 10) Frame 6 11) Cover 7 12) Grade rings 8 13) Pipe connections 9 14) Pavement removal 10 15) Hauling 11 16) Disposal of excess material 12 17) Furnishing, placement, and compaction of backfill 13 18) Clean-up 14 2. Extra Depth Manhole 15 a. Measurement 16 1) Measured per each vertical foot of manhole depth beyond 6 feet from rim 17 to flow line, measured to the nearest foot. 18 b. Payment 19 1) The work performed and materials furnished in accordance with this item 20 and measured as provided under “Measurement” will be paid for at the unit 21 price bid per each “Extra Depth Manhole” installed for: 22 a) Various sizes. 23 c. The price bid shall include: 24 1) Furnishing and installing extra depth manhole structure as specified by the 25 Drawings 26 2) Excavation 27 3) Forms 28 4) Reinforcing steel (if required) 29 5) Concrete 30 6) Foundation 31 7) Drop pipe (if required) 32 8) Pipe stubs 33 9) Frame 34 10) Cover 35 11) Grade rings 36 12) Pipe connections 37 13) Pavement removal 38 14) Hauling 39 15) Disposal of excess material 40 16) Furnishing, placement, and compaction of backfill 41 17) Clean-up 42 3. Sanitary Sewer Junction Structure 43 a. Measurement 44 1) Measured per each Sewer Junction Structure installed. 45 b. Payment 46 33 05 61 CAST-IN-PLACE CONCRETE MANHOLES Page 3 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised July 2, 2024 Effective July 2, 2024 1) The work performed and materials furnished in accordance with this item 1 and measured as provided under “Measurement” will be paid for at the unit 2 price bid per each “Sewer Junction Structure” installed. 3 4 c. The price bid shall include: 5 1) Furnishing and installing junction structure as specified by the Drawings 6 2) Excavation 7 3) Forms 8 4) Reinforcing steel 9 5) Concrete 10 6) Foundation 11 7) Drop pipe, if required 12 8) Vent piping, if required 13 9) Pipe stubs 14 10) Frame 15 11) Cover 16 12) Grade rings 17 13) Pipe connections 18 14) Pavement removal 19 15) Hauling 20 16) Disposal of excess material 21 17) Furnishing, placement, and compaction of backfill 22 18) Clean-up 23 1.3 REFERENCES 24 A. Definitions 25 1. Manhole Type 26 a. Standard Manhole 27 1) Up to 6 feet deep (from rim to flowline). 28 b. Standard Drop Manhole 29 1) Standard Manhole with external drop connection(s). 30 c. Extra Depth Manhole 31 1) Additional manhole depth in excess of 6 feet (from rim to flowline). 32 B. Reference Standards 33 1. Reference standards cited in this Section refer to the current reference standard 34 published at the time of the latest revision date logged at the end of this Section 35 unless a date is specifically cited. 36 2. American Society for Testing and Measurement (ASTM): 37 a. C923 – Standard Specification for Resilient Connectors Between Reinforced 38 Concrete Manholes Structures, Pipes, and Laterals. 39 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 40 1.5 SUBMITTALS 41 A. Submittals shall be in accordance with Section 01 33 00. 42 B. All submittals shall be approved by the City prior to delivery. 43 33 05 61 CAST-IN-PLACE CONCRETE MANHOLES Page 4 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised July 2, 2024 Effective July 2, 2024 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 1 A. Product Data 2 1. Drop connection materials 3 2. Pipe connections at manhole walls 4 3. Stubs and stub plugs 5 4. Concrete mix design in accordance with Section 03 00 00. 6 1.7 CLOSEOUT SUBMITTALS [NOT USED] 7 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 8 1.9 QUALITY ASSURANCE [NOT USED] 9 1.10 DELIVERY, STORAGE, AND HANDLING 10 A. Storage and Handling Requirements 11 1. Secure and maintain a location to store the material in accordance with Section 01 12 66 00. 13 1.11 SITE CONDITIONS [NOT USED] 14 1.12 WARRANTY [NOT USED] 15 PART 2 - PRODUCTS 16 2.1 CITY-SUPPLIED PRODUCTS [NOT USED] 17 2.2 MATERIALS 18 A. Materials 19 1. Class ‘S’ Concrete in accordance with Section 03 00 00. 20 2. Reinforcing steel in accordance with Section 03 00 00. 21 3. Frame, cover, and grade rings in accordance with Section 33 05 81. 22 4. Pipe Connections 23 a. Utilize a rubber boot-type connector installed in a circular block out opening 24 conforming to ASTM C923. 25 5. Drop piping in accordance with Sections 33 14 10 or 33 31 14. 26 a. Use same material as sanitary sewer main. 27 6. Steps are not allowed. 28 B. Finishes 29 1. Interior lining in accordance with Section 33 01 40, if required. 30 2. Exterior coating not required for cast-in-place concrete manholes. 31 C. Manhole Sizing 32 1. 4-foot diameter 33 a. Used with pipe ranging from 8-inch to 12-inch for depths 12-feet or less. 34 2. 5-foot diameter 35 33 05 61 CAST-IN-PLACE CONCRETE MANHOLES Page 5 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised July 2, 2024 Effective July 2, 2024 a. Used with pipe ranging from 8-inch to 12-inch for depths greater than 12-feet. 1 b. Used with pipe ranging from 15-inch to 27-inch. 2 3. 6-foot diameter 3 a. Used with pipe ranging from 30-inch to 36-inch. 4 2.3 ACCESSORIES [NOT USED] 5 2.4 SOURCE QUALITY CONTROL [NOT USED] 6 PART 3 - EXECUTION 7 3.1 INSTALLERS [NOT USED] 8 3.2 EXAMINATION 9 A. Evaluation and Assessment 10 1. Verify lines and grades are in accordance with the Drawings. 11 3.3 PREPARATION 12 A. Foundation Preparation 13 1. Excavate 12-inches below proposed manhole foundation. 14 2. Replace excavated soil with 12-inches of crushed rock in accordance with Section 15 33 05 05. 16 a. If soil conditions or ground water prevent use of crushed rock base, a 4-inch 17 mud slab may be substituted if permitted by City. 18 1) Do not place forms on mud slab until concrete is demonstrated to have 19 cured to 2,000 psi compressive strength or 7-days have elapsed. 20 3.4 INSTALLATION 21 A. Manhole 22 1. Construct manhole to dimensions specified in the Drawings. 23 2. Cast manhole foundation and wall monolithically. 24 a. A cold joint with PVC water stop will only be allowed when the manhole depth 25 exceeds 12-feet. 26 b. No other joints are allowed unless specified in the Drawings. 27 3. Place, finish, and cure concrete in accordance with Section 03 30 00. 28 a. Allow concrete for manholes to cure a minimum of 3 days before backfilling 29 around structure. 30 B. Pipe connection at Manhole 31 1. Do not construct joints of sewer pipe within wall sections of manhole. 32 C. Invert 33 1. Construct invert channels to provide a smooth waterway with no disruption of flow 34 at pipe-manhole connections. 35 2. For direction changes of mains, construct channels tangent to mains with maximum 36 possible radius of curvature. 37 a. Provide curves for side inlets. 38 33 05 61 CAST-IN-PLACE CONCRETE MANHOLES Page 6 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised July 2, 2024 Effective July 2, 2024 3. Provide invert depth to spring line of pipe, and taper manhole bench to top of 1 largest pipe at manhole wall in accordance with the Drawings. 2 D. Drop Manhole Connection 3 1. Install drop connection when sewer lines enter manholes with 24-inches or more 4 above the manhole invert. 5 2. Embed drop piping with cement stabilized sand (CSS) or controlled low strength 6 material (CLSM) in accordance with Sections 33 05 05 or 03 34 13, respectively. 7 E. Final Rim Elevation 8 1. Grade Rings 9 a. New structures should be constructed so the total height of grade rings is as 10 close to 6-inches as practical to allow for future adjustments to no more than 11 12-inches of grade rings. 12 b. Install grade rings on a load bearing shoulder of manhole. 13 c. Install joint sealant for grade rings in accordance with Section 33 05 81. 14 1) Remove all debris, stones, and dirt between all grade rings to ensure a 15 watertight seal. 16 d. Install Infi-Shield External Gator Wrap on the exterior of all grade rings in 17 accordance with Section 33 05 81. 18 2. Frame and Cover 19 a. Install joint sealant between frame and manhole or grade rings in accordance 20 with Section 33 05 81. 21 1) Remove all debris, stones, and dirt between frame and manhole or grade 22 rings to ensure a watertight seal. 23 F. Internal Coating 24 1. Install manhole liner where specified in the Drawings in accordance with Section 25 33 01 40. 26 G. External Coating 27 1. No external coating is required for cast-in-place manholes. 28 H. Modifications and pipe penetrations in accordance with Section 03 80 00. 29 I. Junction Structures to be installed as specified in the Drawings. 30 3.5 REPAIR [NOT USED] 31 3.6 RE-INSTALLATION [NOT USED] 32 3.7 SITE QUALITY CONTROL 33 A. Site Tests and Inspections 34 1. Perform manhole vacuum testing in accordance with Section 33 01 31. 35 33 05 61 CAST-IN-PLACE CONCRETE MANHOLES Page 7 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised July 2, 2024 Effective July 2, 2024 3.8 SYSTEM STARTUP [NOT USED] 1 3.9 ADJUSTING [NOT USED] 2 3.10 CLEANING [NOT USED] 3 3.11 CLOSEOUT ACTIVITIES [NOT USED] 4 3.12 PROTECTION [NOT USED] 5 3.13 MAINTENANCE [NOT USED] 6 7 3.14 ATTACHMENTS [NOT USED] 8 END OF SECTION 9 10 Revision Log DATE NAME SUMMARY OF CHANGE 7/2/2024 Removed elastomeric PVC as an allowable material type in 2.2.A.4 11 33 05 62 PRECAST CONCRETE MANHOLES Page 1 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 SECTION 33 05 62 1 PRECAST CONCRETE MANHOLES 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Sanitary Sewer, Water Appurtenance, or Reclaimed Water Appurtenance Precast 6 Concrete Manholes. 7 B. Deviations from this City of Denton Standard Specification: 8 1. None. 9 C. Related Specification Sections include but are not limited to: 10 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 11 Contract. 12 2. Division 1 - General Requirements. 13 3. Section 03 34 13 – Controlled Low Strength Material (CLSM). 14 4. Section 03 80 00 – Modifications to Existing Concrete Structures. 15 5. Section 33 01 31 – Sewer and Manhole Testing. 16 6. Section 33 01 40 – Liners for Sanitary Sewer Structures. 17 7. Section 33 05 05 – Utility Trench Excavation, Embedment, and Backfill. 18 8. Section 33 05 81 – Frame, Cover, and Grade Rings. 19 9. Section 33 14 10 – Ductile Iron Pipe and Fittings. 20 10. Section 33 31 14 – Polyvinyl Chloride (PVC) Gravity Sanitary Sewer Pipe. 21 1.2 PRICE AND PAYMENT PROCEDURES 22 A. Measurement and Payment 23 1. Manhole 24 a. Measurement 25 1) Measured per each “Manhole” installed to a maximum depth of 6 feet. 26 b. Payment 27 1) The work performed and materials furnished in accordance with this item 28 and measured as provided under “Measurement” will be paid for at the unit 29 price bid per each “Manhole” installed for: 30 a) Various sizes. 31 b) Various types. 32 c. The price bid shall include: 33 1) Furnishing and installing manhole structure as specified by the Drawings 34 2) Excavation 35 3) Forms 36 4) Reinforcing steel, if required 37 5) Concrete 38 6) Foundation 39 33 05 62 PRECAST CONCRETE MANHOLES Page 2 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 7) Drop pipe, if required 1 8) Vent piping, if required 2 9) Pipe stubs 3 10) Interior lining 4 11) Frame 5 12) Cover 6 13) Grade rings 7 14) Pipe connections 8 15) Pavement removal 9 16) Hauling 10 17) Disposal of excess material 11 18) Furnishing, placement, and compaction of backfill 12 19) Clean-up 13 2. Extra Depth Manhole 14 a. Measurement 15 1) Measured per each vertical foot of manhole depth beyond 6 feet from rim 16 to flow line, measured to the nearest foot. 17 b. Payment 18 1) The work performed and materials furnished in accordance with this item 19 and measured as provided under “Measurement” will be paid for at the unit 20 price bid per each “Extra Depth Manhole” installed for: 21 a) Various sizes. 22 c. The price bid shall include: 23 1) Furnishing and installing extra depth manhole structure as specified by the 24 Drawings 25 2) Excavation 26 3) Forms 27 4) Reinforcing steel, if required 28 5) Concrete 29 6) Foundation 30 7) Drop pipe, if required 31 8) Pipe stubs 32 9) Interior lining 33 10) Frame 34 11) Cover 35 12) Grade rings 36 13) Pipe connections 37 14) Pavement removal 38 15) Hauling 39 16) Disposal of excess material 40 17) Furnishing, placement, and compaction of backfill 41 18) Clean-up 42 1.3 REFERENCES 43 A. Definitions 44 1. Manhole Type 45 a. Standard Manhole 46 1) Up to 6 feet deep (from rim to flowline). 47 33 05 62 PRECAST CONCRETE MANHOLES Page 3 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 b. Standard Drop Manhole 1 1) Same as Standard Manhole with external drop connection(s). 2 c. Extra Depth Manhole 3 1) Additional manhole depth in excess of 6 feet (from rim to flowline). 4 B. Reference Standards 5 1. Reference standards cited in this Section refer to the current reference standard 6 published at the time of the latest revision date logged at the end of this Section 7 unless a date is specifically cited. 8 2. American Society for Testing and Measurement (ASTM): 9 a. C443 – Standard Specification for Joint for Concrete Pipe and Manholes, Using 10 Rubber Gaskets. 11 b. C478 – Standard Specification for Precast Reinforced Concrete Manhole 12 Sections. 13 c. C923 – Standard Specification for Resilient Connectors Between Reinforced 14 Concrete Manholes Structures, Pipes, and Laterals. 15 d. D1187 – Standard Specification for Asphalt-Base Emulsion for Use as 16 Protective Coatings for Metal. 17 e. D1227 – Standard Specification for Emulsified Asphalt Used as a Protective 18 Coating for Roofing. 19 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 20 1.5 SUBMITTALS 21 A. Submittals shall be in accordance with Section 01 33 00. 22 B. All submittals shall be approved by the City prior to delivery. 23 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 24 A. Product Data 25 1. Precast Concrete Manhole 26 2. Drop connection materials 27 3. Pipe connections at manhole walls 28 4. Stubs and stub plugs 29 B. Shop Drawings 30 1. Pre-cast manhole drawings 31 1.7 CLOSEOUT SUBMITTALS [NOT USED] 32 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 33 1.9 QUALITY ASSURANCE [NOT USED] 34 1.10 DELIVERY, STORAGE, AND HANDLING 35 A. Storage and Handling Requirements 36 1. Secure and maintain a location to store the material in accordance with Section 01 37 66 00. 38 1.11 SITE CONDITIONS [NOT USED] 39 33 05 62 PRECAST CONCRETE MANHOLES Page 4 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 1.12 WARRANTY [NOT USED] 1 PART 2 - PRODUCTS 2 2.1 CITY-SUPPLIED PRODUCTS [NOT USED] 3 2.2 MATERIALS 4 A. Materials 5 1. Precast reinforced concrete sections shall be in accordance with ASTM C478. 6 2. Precast Joints 7 a. Provide gaskets in accordance with ASTM C443. 8 b. Provide external joint wrap – Infi-Shield Gator Wrap 9 c. Minimize number of joints. 10 d. Joint length to increase with manhole depth. 11 1) For example, use long joints at the bottom of manhole and shorter joints 12 toward the top. 13 e. Include manufacturer’s stamp on each section. 14 3. Lifting Devices 15 a. Manhole sections and cones may be furnished with lift lugs or lift holes. 16 1) If lift lugs are provided, place 180 degrees apart. 17 2) If lift holes are provided, place 180 degrees apart and grout during manhole 18 installation. 19 4. Frame, cover, and grade rings in accordance with Section 33 05 81. 20 5. Pipe Connections 21 a. Utilize an elastomeric PVC or rubber boot-type connector installed in a circular 22 block out opening conforming to ASTM C923. 23 6. Drop piping in accordance with Sections 33 14 10 or 33 31 14. 24 a. Use same material as sanitary sewer main. 25 7. Steps are not allowed. 26 B. Finishes 27 1. Interior lining is required for all pre-cast concrete manholes in accordance 28 with Section 33 01 40. 29 2. Exterior Coating 30 a. Coat with non-fibered asphaltic emulsion in accordance with ASTM D1187 31 Type I and ASTM D1227 Type III Class I. 32 C. Manhole Sizing 33 1. 4-foot diameter 34 a. Used with pipe ranging from 8-inch to 12-inch for depths 12-feet or less. 35 2. 5-foot diameter 36 a. Used with pipe ranging from 8-inch to 12-inch for depths greater than 12-feet. 37 b. Used with pipe ranging from 15-inch to 27-inch. 38 3. 6-foot diameter 39 a. Used with pipe ranging from 30-inch to 36-inch. 40 2.3 ACCESSORIES [NOT USED] 41 33 05 62 PRECAST CONCRETE MANHOLES Page 5 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 2.4 SOURCE QUALITY CONTROL [NOT USED] 1 PART 3 - EXECUTION 2 3.1 INSTALLERS [NOT USED] 3 3.2 EXAMINATION 4 A. Evaluation and Assessment 5 1. Verify lines and grades are in accordance with the Drawings. 6 3.3 PREPARATION 7 A. Foundation Preparation 8 1. Excavate 12-inches below proposed manhole foundation. 9 2. Replace excavated soil with 12-inches of crushed rock in accordance with Section 10 33 05 05. 11 a. If soil conditions or ground water prevent use of crushed rock base, a 4-inch 12 mud slab may be substituted if permitted by City. 13 1) Do not place forms on mud slab until concrete is demonstrated to have 14 cured to 2,000 psi compressive strength, or 7-days have elapsed. 15 3.4 INSTALLATION 16 A. Manhole 17 1. Construct manhole to dimensions specified in the Drawings. 18 2. Precast Sections 19 a. Provide bell-and-spigot design incorporating a premolded joint sealing 20 compound for wastewater use. 21 1) Install Infi-Shield External Gator Wrap on the exterior of all precast joints. 22 b. Clean bell spigot and gaskets, lubricate, and join. 23 c. Minimize number of segments. 24 d. Joint length to increase with manhole depth. 25 B. Invert 26 1. Construct invert channels to provide a smooth waterway with no disruption of flow 27 at pipe-manhole connections. 28 2. For direction changes of mains, construct channels tangent to mains with maximum 29 possible radius of curvature. 30 a. Provide curves for side inlets. 31 3. Provide invert depth to spring line of pipe, and taper manhole bench to top of 32 largest pipe at manhole wall in accordance with the Drawings. 33 C. Drop Manhole Connection 34 1. Install drop connection when sewer lines enter manholes with 24-inches or more 35 above the manhole invert. 36 2. Embed drop piping with cement stabilized sand (CSS) or controlled low strength 37 material (CLSM) in accordance with Sections 33 05 05 or 03 34 13, respectively. 38 39 33 05 62 PRECAST CONCRETE MANHOLES Page 6 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 D. Final Rim Elevation 1 1. Grade Rings 2 a. New structures should be constructed so the total height of grade rings is as 3 close to 6-inches as practical to allow for future adjustments to no more than 4 12-inches of grade rings. 5 b. Install grade rings on a load bearing shoulder of manhole. 6 c. Install joint sealant for grade rings in accordance with Section 33 05 81. 7 1) Remove all debris, stones, and dirt between all grade rings to ensure a 8 watertight seal. 9 d. Install Infi-Shield External Gator Wrap on the exterior of all grade rings in 10 accordance with Section 33 05 81. 11 2. Frame and Cover 12 a. Install joint sealant between frame and manhole or grade rings in accordance 13 with Section 33 05 81. 14 1) Remove all debris, stones, and dirt between frame and manhole or grade 15 rings to ensure a watertight seal. 16 E. Internal Coating 17 1. Install manhole liner for all precast concrete manholes in accordance with 18 Section 33 01 40. 19 F. External coating 20 1. Remove dirt, dust, oil, and other contaminants that could interfere with adhesion of 21 the coating. 22 2. Install coating in accordance with manufacturer’s recommendations. 23 G. Modifications and pipe penetrations in accordance with Section 03 80 00. 24 3.5 REPAIR [NOT USED] 25 3.6 RE-INSTALLATION [NOT USED] 26 3.7 SITE QUALITY CONTROL 27 A. Site Tests and Inspections 28 1. Perform manhole vacuum testing in accordance with Section 33 01 31. 29 3.8 SYSTEM STARTUP [NOT USED] 30 3.9 ADJUSTING [NOT USED] 31 3.10 CLEANING [NOT USED] 32 3.11 CLOSEOUT ACTIVITIES [NOT USED] 33 3.12 PROTECTION [NOT USED] 34 3.13 MAINTENANCE [NOT USED] 35 36 33 05 62 PRECAST CONCRETE MANHOLES Page 7 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 3.14 ATTACHMENTS [NOT USED] 1 END OF SECTION 2 3 Revision Log DATE NAME SUMMARY OF CHANGE 4 33 05 76 FIBERGLASS MANHOLES Page 1 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 SECTION 33 05 76 1 FIBERGLASS MANHOLES 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Glass-Fiber-Reinforced Polyester (Fiberglass) Sanitary Sewer Manholes. 6 B. Deviations from this City of Denton Standard Specification: 7 1. None. 8 C. Related Specification Sections include but are not limited to: 9 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 10 Contract. 11 2. Division 1 - General Requirements. 12 3. Section 03 00 00 – Concrete and Concrete Reinforcing. 13 4. Section 03 30 00 – Cast-in-Place Concrete. 14 5. Section 03 34 13 – Controlled Low Strength Material (CLSM). 15 6. Section 33 01 31 – Sewer and Manhole Testing. 16 7. Section 33 05 05 – Utility Trench Excavation, Embedment, and Backfill. 17 8. Section 33 05 81 – Frame, Cover, and Grade Rings. 18 9. Section 33 14 10 – Ductile Iron Pipe and Fittings. 19 10. Section 33 14 11 – Polyvinyl Chloride (PVC) Pressure Pipe. 20 11. Section 33 14 14 – High Density Polyethylene (HDPE) Pipe. 21 12. Section 33 31 10 – Fiberglass Reinforced Pipe for Gravity Sanitary Sewers. 22 13. Section 33 31 14 – Polyvinyl Chloride (PVC) Gravity Sanitary Sewer Pipe. 23 1.2 PRICE AND PAYMENT PROCEDURES 24 A. Measurement and Payment 25 1. Manhole 26 a. Measurement 27 1) Measured per each “Manhole” installed to a maximum depth of 6 feet. 28 b. Payment 29 1) The work performed and materials furnished in accordance with this item 30 and measured as provided under “Measurement” will be paid for at the unit 31 price bid per each “Manhole” installed for: 32 a) Various sizes. 33 b) Various types. 34 c. The price bid shall include: 35 1) Furnishing and installing manhole structure as specified by the Drawings 36 2) Excavation 37 3) Forms 38 33 05 76 FIBERGLASS MANHOLES Page 2 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 4) Concrete foundation 1 5) Drop pipe, if required 2 6) Vent piping, if required 3 7) Pipe stubs 4 8) Frame 5 9) Cover 6 10) Grade rings 7 11) Pipe connections 8 12) Pavement removal 9 13) Hauling 10 14) Disposal of excess material 11 15) Furnishing, placement, and compaction of backfill 12 16) Clean-up 13 2. Extra Depth Manhole 14 a. Measurement 15 1) Measured per each vertical foot of manhole depth beyond 6 feet from rim 16 to flow line, measured to the nearest foot. 17 b. Payment 18 1) The work performed and materials furnished in accordance with this item 19 and measured as provided under “Measurement” will be paid for at the unit 20 price bid per each “Extra Depth Manhole” installed for: 21 a) Various sizes. 22 c. The price bid shall include: 23 1) Furnishing and installing extra depth manhole structure as specified by the 24 Drawings 25 2) Excavation 26 3) Forms 27 4) Concrete foundation 28 5) Drop pipe, if required 29 6) Pipe stubs 30 7) Frame 31 8) Cover 32 9) Grade rings 33 10) Pipe connections 34 11) Pavement removal 35 12) Hauling 36 13) Disposal of excess material 37 14) Furnishing, placement, and compaction of backfill 38 15) Clean-up 39 1.3 REFERENCES 40 A. Definitions 41 1. Manhole Type 42 a. Standard Manhole 43 1) Up to 6 feet deep (from rim to flowline). 44 b. Standard Drop Manhole 45 1) Standard Manhole with external drop connection(s). 46 c. Extra Depth Manhole 47 33 05 76 FIBERGLASS MANHOLES Page 3 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 1) Additional manhole depth in excess of 6 feet (from rim to flowline). 1 2 B. Reference Standards 3 1. Reference standards cited in this Section refer to the current reference standard 4 published at the time of the latest revision date logged at the end of this Section 5 unless a date is specifically cited. 6 2. American Society for Testing and Measurement (ASTM): 7 a. C76, Standard Specification for Reinforced Concrete Culvert, Storm Drain 8 and Sewer Pipe. 9 b. D3753, Standard Specification for Glass-Fiber-Reinforced Polyester 10 Manholes and Wetwells. 11 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 12 1.5 SUBMITTALS 13 A. Submittals shall be in accordance with Section 01 33 00. 14 B. All submittals shall be approved by the City prior to delivery. 15 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 16 A. Product Data 17 1. Fiberglass material data 18 2. Installation instructions for Fiberglass Manholes 19 3. Drop connection materials 20 4. Pipe connections at manhole walls 21 5. Materials for stubs and stub plugs, if applicable 22 6. Grade ring materials 23 7. External coating materials 24 8. Plugs for hydrostatic testing 25 B. Shop Drawings 26 1. Design and fabrication details of Fiberglass Manholes 27 C. Certifications 28 1. Manufacturer’s certification verifying fiberglass manholes meet or exceed the 29 requirements of ASTM D3753. 30 1.7 CLOSEOUT SUBMITTALS [NOT USED] 31 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 32 1.9 QUALITY ASSURANCE 33 A. Certifications 34 1. Upon completion of fabrication provide independent certification consisting of the 35 manufacturer’s testing report including test results verifying the manhole has been 36 sampled, tested, and inspected in accordance with and meets all the requirements of 37 ASTM D3753. 38 33 05 76 FIBERGLASS MANHOLES Page 4 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 1 1.10 DELIVERY, STORAGE, AND HANDLING 2 A. Storage and Handling Requirements 3 1. Secure and maintain a location to store the material in accordance with Section 01 4 66 00. 5 1.11 SITE CONDITIONS [NOT USED] 6 1.12 WARRANTY [NOT USED] 7 PART 2 - PRODUCTS 8 2.1 CITY-SUPPLIED PRODUCTS [NOT USED] 9 2.2 MATERIALS 10 A. Manufacturers 11 1. Manufacturer List 12 a. L.F. Manufacturing, Inc. 13 b. Containment Solutions, Inc. 14 2. Substitution requests for manufacturers or models not indicated above shall be 15 processed in accordance with Section 01 25 00. 16 B. Materials 17 1. Resin 18 a. Commercial grade unsaturated polyester resin or other suitable vinyl ester resin. 19 2. Reinforcing Materials 20 a. Commercial grade “E” type glass in the form of mat, continuous roving, chop 21 roving, roving fabric, or a combination of the above, with a coupling agent that 22 will provide a suitable bond between the glass reinforcement and the resin. 23 3. Interior Surfacing Material 24 a. Resin-rich layer of 0.010 to 0.020 inch thick. 25 4. Exterior Surface 26 a. Provide a UV inhibitor in the resin to a minimum of 0.125 inches. 27 1) Gel coat, paint, or other coatings are not permitted. 28 5. Fillers and Additives 29 a. Inert to the environment and manhole construction. 30 b. Thixotropic agents, catalysts, promoters, etc. may be added as required by the 31 specific manufacturing process to be used to meet the requirements of this 32 Section. The resulting reinforced-plastic material be in accordance with the 33 requirements of this Section. 34 1) Sand is not permitted as a filler. 35 6. Stub Outs 36 a. Factory install and glass in pipe stubs for all connections. 37 1) Field cuts of fiberglass manhole are not permitted. 38 2) Boot type connectors are not permitted. 39 33 05 76 FIBERGLASS MANHOLES Page 5 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 b. Pipe stubs to be installed shall be in accordance with Sections 33 14 11, 33 31 1 10, or 33 31 14. 2 1) Use same material as sanitary sewer main. 3 2) Upstream stub outs shall have belled ends for pipe types conforming to 4 Sections 33 14 11 and 33 31 10. 5 3) Downstream stub out shall be plain end or spigot end pipe. 6 7. Invert and manhole bench should be factory installed. 7 a. Provide invert depth to spring line of pipe, and taper manhole bench to top of 8 largest pipe at manhole wall. 9 C. Performance / Design Criteria 10 1. Provide Prefabricated Fiberglass Manholes in accordance with the shape, size, 11 dimensions, and details specified in the Drawings. 12 2. Unless modified in the Drawings, use manhole sections in accordance with ASTM 13 D3753. 14 3. Provide the following markings in 1-inch minimum tall stenciled letters on the 15 inside and outside of the barrel: 16 a. Manufacturer’s name or trademark 17 b. Manufacturer’s factory location 18 c. Manufacturer’s serial number 19 d. Total height and nominal diameter 20 e. Complies with ASTM D3753 21 4. Provide wall section thickness for depth of manhole according to ASTM D3753, 22 but not less than 0.48 inches in thickness. 23 5. Provide fabricated reducer bonded at factory to form a continuous unit at top of 24 manhole barrel to accept grade rings, frame, and cover. 25 6. Provide factory installed fiberglass bottom with 3-inch minimum anti-flotation 26 flange. 27 7. Load Rating 28 a. Complete manhole shall be designed to meet the following requirements: 29 1) HS-20 load rated, allowing a minimum dynamic load rating of 16,000 30 pounds when tested in accordance with ASTM D3753. 31 a) To establish this rating, the manhole may not leak, crack, or suffer 32 other damage when load tested to 40,000 pounds and shall not deflect 33 vertically downward more than 0.25-inches at the point of load 34 application when loaded to 24,000 pounds. 35 8. Stiffness 36 a. The manhole cylinder shall have the minimum pipe stiffness value as indicated 37 below when tested in accordance with ASTM D3753: 38 39 Height (feet) F/AY (psi) 0 to 10 1.26 10 to 20 2.01 21 to 25 3.02 26 to 30 5.24 40 D. Manhole Sizing 41 33 05 76 FIBERGLASS MANHOLES Page 6 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 1. 4-foot diameter 1 a. Used with pipe ranging from 8-inch to 12-inch for depths 12-feet or less. 2 2. 5-foot diameter 3 a. Used with pipe ranging from 8-inch to 12-inch for depths greater than 12-feet. 4 b. Used with pipe ranging from 15-inch to 27-inch. 5 6 3. 6-foot diameter 7 a. Used with pipe ranging from 30-inch to 36-inch. 8 E. Fiberglass Manhole Locations 9 1. Only permitted in non-paved areas which will not be paved in the future, unless 10 approved by City. 11 F. Drop Piping 12 1. Drop piping in accordance with Sections 33 14 10, 33 14 11, or 33 31 14. 13 a. Use same material as sanitary sewer main. 14 G. Concrete Manhole Base 15 1. Class ‘S’ concrete in accordance with Section 03 00 00. 16 H. Reinforcing Steel 17 1. In accordance with Section 03 00 00 18 I. Frame, Cover, and Grade Rings 19 1. In accordance with Section 33 05 81 20 2.3 ACCESSORIES [NOT USED] 21 2.4 SOURCE QUALITY CONTROL [NOT USED] 22 PART 3 - EXECUTION 23 3.1 INSTALLERS [NOT USED] 24 3.2 EXAMINATION 25 A. Evaluation and Assessment 26 1. Verify lines and grades are in accordance with the Drawings. 27 3.3 PREPARATION 28 A. Foundation Preparation 29 1. Excavate 20-inches below proposed manhole foundation. 30 2. Replace bottom 12-inches of excavated soil with crushed rock in accordance with 31 Section 33 05 05. 32 a. If soil conditions or ground water prevent use of crushed rock base, a 4-inch 33 mud slab may be substituted if permitted by City. 34 1) Do not place forms on mud slab until concrete is demonstrated to have 35 cured to 2,000 psi compressive strength, or 7-days have elapsed. 36 33 05 76 FIBERGLASS MANHOLES Page 7 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 3. Replace top 8-inches of excavated soil with Class ‘A’ concrete a minimum of 12-1 inches outside proposed manhole barrel, and install in accordance with Section 03 2 30 00. 3 4. Embed No. 4 steel reinforcement hooks at 12-inch centers in concrete foundation 4 circumferentially to prevent manhole flotation. 5 5. Do not place fiberglass manhole on foundation until concrete is demonstrated to 6 have cured to 3,000 psi compressive strength, or 14-days have elapsed. 7 8 3.4 INSTALLATION 9 A. Manhole 10 1. Construct manhole to dimensions specified in the Drawings. 11 2. Lower manhole barrel onto base section. 12 3. Ensure circumferential hooks are oriented to anchor flanges. 13 4. Pour additional 4-inches of Class ‘A’ concrete on hooks in accordance with the 14 Drawings and Section 03 30 00. 15 5. Backfill entire excavation to 12-inches below final grade with cement stabilized 16 sand (CSS) or controlled low strength material (CLSM) in accordance with Section 17 33 05 05 or 03 34 13. 18 a. Native backfill or select backfill will not be permitted. 19 B. Drop Manhole Connection 20 1. Install drop connection when sewer lines enter manholes with 24-inches or more 21 above the manhole invert. 22 2. Embed drop piping with cement stabilized sand (CSS) or controlled low strength 23 material (CLSM) in accordance with Sections 33 05 05 or 03 34 13. 24 C. Final Rim Elevation 25 1. Grade Rings 26 a. New structures should be constructed so the total height of grade rings is no 27 more than 6-inches. 28 b. Install grade rings on a load bearing shoulder of manhole. 29 c. Install joint sealant for grade rings in accordance with Section 33 05 81. 30 1) Remove all debris, stones, and dirt between all grade rings to ensure a 31 watertight seal. 32 d. Install Infi-Shield External Gator Wrap on the exterior of all grade rings in 33 accordance with Section 33 05 81. 34 2. Frame and Cover 35 a. Install joint sealant between frame and manhole or grade rings in accordance 36 with Section 33 05 81. 37 1) Remove all debris, stones, and dirt between frame and manhole or grade 38 rings to ensure a watertight seal. 39 3.5 REPAIR [NOT USED] 40 3.6 RE-INSTALLATION [NOT USED] 41 3.7 SITE QUALITY CONTROL 42 33 05 76 FIBERGLASS MANHOLES Page 8 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 A. Site Tests and Inspections 1 1. Perform manhole vacuum testing in accordance with Section 33 01 31. 2 3.8 SYSTEM STARTUP [NOT USED] 3 3.9 ADJUSTING [NOT USED] 4 3.10 CLEANING [NOT USED] 5 3.11 CLOSEOUT ACTIVITIES [NOT USED] 6 3.12 PROTECTION [NOT USED] 7 3.13 MAINTENANCE [NOT USED] 8 3.14 ATTACHMENTS [NOT USED] 9 END OF SECTION 10 11 Revision Log DATE NAME SUMMARY OF CHANGE 12 33 05 81 FRAME, COVER, AND GRADE RINGS Page 1 of 6 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised July 1, 2024 Effective July 1, 2024 SECTION 33 05 81 1 FRAME, COVER, AND GRADE RINGS 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Cast iron and compression molded composite frame and cover used as access port 6 into water, sanitary sewer, and storm drain structures such as manholes or vaults. 7 2. Concrete and HDPE grade rings for adjusting frame and cover grades. 8 3. Concrete collars for manholes in unimproved areas and asphalt pavement. 9 B. Deviations from this City of Denton Standard Specification: 10 1. None. 11 C. Related Specification Sections include but are not limited to: 12 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 13 Contract. 14 2. Division 1 - General Requirements. 15 3. Section 03 00 00 – Concrete and Concrete Reinforcing. 16 4. Section 03 30 00 – Cast-In-Place Concrete. 17 5. Section 33 01 35 – Adjusting Manholes, Inlets, Valve Boxes, and Other Structures 18 to Grade. 19 1.2 PRICE AND PAYMENT PROCEDURES 20 A. Measurement and Payment 21 1. Cast-Iron Frame Cover and Grade Rings 22 a. Measurement 23 1) This item is considered subsidiary to the structure containing the frame, 24 cover, and grade rings. 25 b. Payment 26 1) The work performed and materials furnished in accordance with this item 27 are subsidiary to the unit price bid per each structure complete in place and 28 no other compensation will be allowed. 29 2. Concrete Collars 30 a. Measurement 31 1) Measured per each concrete collar installed on an existing manhole. 32 b. Payment 33 1) The work performed and materials furnished in accordance with this item 34 and measured as provided under “Measurement” will be paid for at the unit 35 price bid per each “Concrete Collar” installed on an existing manhole. 36 c. The price bid shall include: 37 1) Concrete Collar 38 2) Excavation 39 3) Forms 40 33 05 81 FRAME, COVER, AND GRADE RINGS Page 2 of 6 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised July 1, 2024 Effective July 1, 2024 4) Reinforcing Steel 1 5) Concrete 2 6) Backfill 3 7) Pavement Removal 4 8) Hauling 5 9) Disposal of excess material 6 10) Furnishing, placement, and compaction of backfill 7 11) Clean-up 8 12) Additional pavement around perimeter of concrete collar as required for 9 rim adjustment on existing manhole 10 1.3 REFERENCES 11 A. Reference Standards 12 1. Reference standards cited in this Section refer to the current reference standard 13 published at the time of the latest revision date logged at the end of this Section 14 unless a date is specifically cited. 15 2. ASTM International (ASTM) 16 a. A48, Standard Specification for Gray Iron Castings. 17 b. A536, Standard Specification for Ductile Iron Castings. 18 3. American Association of State Highways and Transportation Officials (AASHTO) 19 a. AASHTO M306 – Standard Specification for Drainage, Sewer, Utility and 20 Related Castings 21 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 22 1.5 SUBMITTALS 23 A. Submittals shall be in accordance with Section 01 33 00. 24 B. All submittals shall be approved by the City prior to delivery. 25 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 26 A. Product Data 27 1. All castings shall be cast with: 28 a. Approved foundry’s name 29 b. Part number 30 c. Country of origin 31 2. Manufacturers: 32 a. Specifications 33 b. Load tables 34 c. Dimension diagrams 35 d. Anchor details 36 e. Installation instructions 37 B. Certificates 38 1. Manufacturer shall certify castings are manufactured in accordance with applicable 39 ASTM and AASHTO designations, including but not limited to, ASTM A48, A536, 40 and AASHTO M306. 41 1.7 CLOSEOUT SUBMITTALS [NOT USED] 42 33 05 81 FRAME, COVER, AND GRADE RINGS Page 3 of 6 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised July 1, 2024 Effective July 1, 2024 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1 1.9 QUALITY ASSURANCE [NOT USED] 2 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 3 1.11 FIELD CONDITIONS [NOT USED] 4 1.12 WARRANTY [NOT USED] 5 PART 2 - PRODUCTS 6 2.1 CITY-SUPPLIED PRODUCTS [NOT USED] 7 2.2 MATERIALS 8 A. Manufacturers 9 1. Water and Sanitary Sewer 10 a. Standard Cast Iron Frame and Cover 11 1) EJ – V1420 4-1/2” Frame with 6 Flange Holes 12 2) EJ – V1480A 32” Solid Cover Sanitary Sewer Min. 200 Lbs. 13 b. Water-Tight Cast Iron Frame and Ductile Iron Cover 14 1) EJ – V1420 4-1/2” Frame with 6 Flange Holes 15 2) EJ – V1480 CAM LOCK Cover 16 c. Composite Molded Frame and Cover 17 1) Composite Access Products – CAP ONE-30 18 2. Meter Manhole or Vault 19 a. Composite Molded Frame and Cover 20 1) Composite Access Products – CAP ONE-30 21 2) For locations where access can be restricted to authorized personnel only. 22 3. Storm Drain 23 a. Manholes and Junction Structures 24 1) Bass & Hays – VRM-30 BASS Cover 25 2) Bass & Hays – VRM-30 Ring 26 b. Inlets 27 1) Bass & Hays – VRM-30 BASS Cover 28 2) Bass & Hays – VRM-30 Ring 29 4. Substitution requests for manufacturers or models not indicated above shall be 30 processed in accordance with Section 01 25 00. 31 B. Castings – Allowed in all Areas 32 1. Cast iron castings in accordance with ASTM A48, Class 35B or better. 33 2. Ductile iron castings in accordance with ASTM A536, Grade 70-50-05 or better. 34 a. Ductile iron will only be allowed for water-tight manhole covers, all other 35 castings shall be cast-iron. 36 3. Capable of withstanding application of AASHTO HS-20 vehicle loading with 37 permanent deformation 38 4. Covers 39 33 05 81 FRAME, COVER, AND GRADE RINGS Page 4 of 6 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised July 1, 2024 Effective July 1, 2024 a. Size to set flush with frame with no larger than a 1/8-inch gap between frame 1 and cover 2 b. Provide 2-inch wide pick slots in lieu of pick holes 3 c. Provide gasket in frame and cover 4 5 C. Moldings – Allowed in Non-Traffic Areas Only 6 1. Consist of thermosetting resin matrix blended and/or combined with reinforcing 7 fiber rovings, short fiber filaments, or equivalent nonmetallic reinforcing 8 structure(s) 9 2. Thermosetting resin matrix shall be polymer, vinylester or a blend of both. 10 3. Thoroughly deflash and clean all moldings at parting lines, holes, notches, and 11 exposed edges before removing from molding operation. 12 4. Capable of withstanding application of AASHTO HS-25 vehicle loading with 13 permanent deformation. 14 5. Frame wall thickness shall be a minimum of 0.75 inches. 15 6. Add UV stabilizers with concentrations between 0.05% and 5% prior to shaping by 16 injection molding. 17 D. Standard Dimensions 18 1. Sanitary Sewer, Water, and Storm Drain 19 a. Provide a clear opening of 30 inches for all frames and cover assemblies unless 20 otherwise specified in the Contract Documents. 21 E. Standard Labels 22 1. Water 23 a. Cast lid with the word “WATER” in 1-inch minimum letters across the lid and 24 in accordance with the Drawings. 25 2. Sanitary Sewer 26 a. Cast lid with the words “SANITARY SEWER” in 1-inch minimum letters 27 across the lid and in accordance with the Drawings. 28 3. Storm Drain 29 a. Cast lid with the phrases “DUMP NO WASTE DRAINS TO RIVER”, 30 “STORM SEWER”, and bass picture, in accordance with the Drawings. 31 F. Hinged Covers are not permitted 32 G. Grade Rings 33 1. Provide grade rings in sizes from 2 inch up to 6 inch. 34 2. New structures should be constructed such that the total height of grade rings is no 35 more than 6 inches. 36 3. Total grade ring height on existing structures as result of an adjustment shall be 37 limited to the height specified in Section 33 01 35. 38 4. Materials 39 a. Concrete in traffic loading areas 40 b. Concrete or HDPE in non-traffic areas 41 1) HDPE shall have a minimum allowable traffic loading meeting AASHTO 42 HS-25. 43 33 05 81 FRAME, COVER, AND GRADE RINGS Page 5 of 6 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised July 1, 2024 Effective July 1, 2024 1 H. Joint Sealant 2 1. Provide a pre-formed or trowelable bitumastic sealant in an extrudable flat tape 3 form. 4 2. Provide a sealant that is not dependent on a chemical action for its adhesive 5 properties or cohesive strength. 6 3. Install Infi-Shield External Gator Wrap on the exterior of all grade rings in 7 accordance with the Drawings. 8 I. Concrete Collar 9 1. Concrete and reinforcing steel in accordance with Section 03 00 00. 10 2. Cast concrete collar in accordance with Section 03 30 00. 11 2.3 ACCESSORIES [NOT USED] 12 2.4 SOURCE QUALITY CONTROL [NOT USED] 13 PART 3 - EXECUTION 14 3.1 INSTALLERS [NOT USED] 15 3.2 EXAMINATION [NOT USED] 16 3.3 PREPARATION [NOT USED] 17 3.4 INSTALLATION 18 A. Grade Rings 19 1. Place as indicated in the Drawings. 20 2. Do not use steel shims, wood, stones, or other unspecified material to obtain final 21 surface elevation of the manhole frame. 22 3. Clean surfaces of dirt, sand, mud, or other foreign matter before placing sealant. 23 4. Seal each grade ring with sealant specified in this Section and as indicated in the 24 Drawings. 25 B. Frame and Cover 26 1. Water 27 a. For water structures install frame, cover, and grade rings in accordance with the 28 Drawings. 29 2. Sanitary Sewer 30 a. For sanitary sewer structures outside the 100-yr flood plain, install standard 31 frame, cover, and grade rings in accordance with the Drawings. 32 b. For sanitary sewer structures within the 100-yr flood plain, install water-tight 33 frame, cover, and grade rings in accordance with the Drawings. 34 3. Storm Drain 35 a. For storm drain structures install frame, cover, and grade rings in accordance 36 with the Drawings. 37 C. Joint Sealing 38 33 05 81 FRAME, COVER, AND GRADE RINGS Page 6 of 6 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised July 1, 2024 Effective July 1, 2024 1. Seal frame, grade rings, and structure with specified sealant. 1 2. Install Infi-Shield External Gator Wrap on the exterior of all grade rings in 2 accordance with manufacturer’s recommendations 3 D. Concrete Collar 4 1. Install concrete collar in accordance with the Drawings in unimproved and asphalt 5 areas. 6 3.5 REPAIR [NOT USED] 7 3.6 RE-INSTALLATION [NOT USED] 8 3.7 FIELD QUALITY CONTROL [NOT USED] 9 3.8 SYSTEM STARTUP [NOT USED] 10 3.9 ADJUSTING [NOT USED] 11 3.10 CLEANING [NOT USED] 12 3.11 CLOSEOUT ACTIVITIES [NOT USED] 13 3.12 PROTECTION [NOT USED] 14 3.13 MAINTENANCE [NOT USED] 15 3.14 ATTACHMENTS [NOT USED] 16 END OF SECTION 17 18 Revision Log DATE NAME SUMMARY OF CHANGE 7/1/2024 Specified that a composite manhole lid is to be used for a metering vault or manhole if the vault or manhole is enclosed; 2.2.A.2 19 33 05 97 UTILITY MARKERS/LOCATORS Page 1 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 17, 2024 Effective July 1, 2024 SECTION 33 05 97 1 UTILITY MARKERS/LOCATORS 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Buried and surface utility markers for utility construction 6 2. Surface utility markers for water and sewer mains as indicated in the Drawings 7 3. Curb Markings for water, fire or sewer service lines 8 B. Deviations from this City of Denton Standard Specification: 9 1. None. 10 C. Related Specification Sections include but are not limited to: 11 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 12 Contract. 13 2. Division 1 - General Requirements. 14 1.2 PRICE AND PAYMENT PROCEDURES 15 A. Measurement and Payment 16 1. Measurement 17 a. This item is considered subsidiary to pipeline and pipeline appurtenance 18 installation. 19 2. Payment 20 a. The work performed and materials furnished in accordance with this item are 21 subsidiary to the various pipeline and pipeline appurtenance bid items will be 22 installed. 23 3. The following items will be considered part of Utility Markers, and subsidiary to 24 the bid items indicated above: 25 a. Furnishing and installing surface markers as specified in the Drawings 26 b. Furnishing and installing tracer wire for all PVC and HDPE water lines and 27 HDPE force mains 28 c. Furnishing and installing detectable warning tape for all buried pipelines 29 d. Continuity testing of tracer wire 30 e. Replacement of non-continuous tracer wire 31 f. Mobilization 32 g. Pavement removal 33 h. Excavation 34 i. Hauling 35 j. Disposal of excess material 36 k. Furnishing, placement, and compaction of backfill 37 l. Clean-up 38 33 05 97 UTILITY MARKERS/LOCATORS Page 2 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 17, 2024 Effective July 1, 2024 1.3 REFERENCES 1 A. Reference Standards 2 1. Reference standards cited in this Section refer to the current reference standard 3 published at the time of the latest revision date logged at the end of this Section 4 unless a date is specifically cited. 5 2. American Public Works Association (APWA): 6 a. Uniform Color Code. 7 3. ASTM International (ASTM): 8 a. B170, Standard Specification for Oxygen-Free Electrolytic Copper – Refinery 9 Shapes. 10 b. B227, Standard Specification for Hard-Drawn Copper-Clad Steel Wire. 11 c. B910/B910M, Standard Specification for Annealed Copper-Clad Steel Wire. 12 d. B1010/B1010M, Standard Specification for Copper-Clad Steel Electrical 13 Conductor for Tracer Wire Applications. 14 e. D1248, Standard Specification for Polyethylene Plastics Extrusion Materials 15 for Wire and Cable. 16 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 17 1.5 SUBMITTALS 18 A. Submittals shall be in accordance with Section 01 33 00. 19 B. All submittals shall be approved by the City prior to delivery. 20 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 21 A. Product Data 22 1. Buried Markers 23 2. Surface Markers 24 1.7 CLOSEOUT SUBMITTALS [NOT USED] 25 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 26 1.9 QUALITY ASSURANCE [NOT USED] 27 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 28 1.11 FIELD CONDITIONS [NOT USED] 29 1.12 WARRANTY [NOT USED] 30 PART 2 - PRODUCTS 31 2.1 CITY-FURNISHED PRODUCTS [NOT USED] 32 2.2 MATERIALS 33 A. Manufacturers 34 33 05 97 UTILITY MARKERS/LOCATORS Page 3 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 17, 2024 Effective July 1, 2024 1. Provide new Utility Markers/Locators from a manufacturer regularly engaged in the 1 manufacturing of Utility Markers/Locators. 2 B. Materials 3 1. Buried Markers 4 a. Detectable Warning Tape 5 1) 5.0 mil overall thickness 6 2) Width – 3 inch minimum 7 3) Weight – 27.5 pounds per inch per 1,000 square feet 8 4) Triple Layer with: 9 a) Minimum thickness 0.35 mils solid aluminum foil encased in a 10 protective inert plastic jacket 11 (1) 100 percent virgin low density polyethylene 12 (2) Impervious to all known alkalis, acids, chemical reagents, and 13 solvents within soil 14 (3) Aluminum foil visible to both sides 15 5) Locatable by conductive and inductive methods 16 6) Printing encased to avoid ink rub-off 17 7) Color and Legends 18 a) Potable water lines 19 (1) Color – Blue (in accordance with APWA Uniform Color Code) 20 (2) Legend – Caution Potable Water Line Below (repeated every 24 21 inches) 22 b) Reclaimed water lines 23 (1) Color – Purple (in accordance with APWA Uniform Color Code) 24 (2) Legend – Caution Reclaimed Water Line Below (repeated every 24 25 inches) 26 c) Sewer Line 27 (1) Color – Green (in accordance with APWA Uniform Color Code) 28 (2) Legend – Caution Sewer Line Below (repeated every 24 inches) 29 b. Tracer Wire and Appurtenances 30 1) Tracer Wire 31 a) Color 32 (1) Blue for domestic water (potable) lines. 33 (2) Green for sanitary sewer gravity lines and force mains. 34 (3) Purple for raw and recycled water (non-potable) lines. 35 b) Open Cut Installation 36 (1) Copper-clad steel 12-AWG high strength, high carbon tracer wire 37 in accordance with ASTM B170, B227, B910/910M, and 38 B1010/1010M. 39 (2) Minimum 450 lb tensile break load 40 (3) Minimum 30 mils minimum high molecular-high density 41 polyethylene jacket in accordance with ASTM D1248. 42 c) Directional Bore or Carrier Pipe Installation 43 (1) Two (2) Copper-clad steel 12-AWG high strength, high carbon 44 tracer wires in accordance with ASTM B170, B227, B910/910M, 45 and B1010/1010M. 46 (2) Minimum 1,150 lb tensile break load 47 33 05 97 UTILITY MARKERS/LOCATORS Page 4 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 17, 2024 Effective July 1, 2024 (3) Minimum 45 mils high molecular-high density polyethylene jacket 1 in accordance with ASTM D1248. 2 d) Pipe Bursting Installation 3 (1) 7 x 7 stranded copper-clad steel 12-AWG high strength, high 4 carbon tracer wire in accordance with ASTM B170, B227, 5 B910/910M, and B1010/1010M. 6 (2) Minimum 4,700 lb tensile break load 7 (3) Minimum 50 mils high molecular-high density polyethylene jacket 8 in accordance with ASTM D1248. 9 2) Connectors 10 a) Splice along continuous runs of tracer wire for repair of a wire break, 11 or replacement of a failed segment of wire with 3M Brand DBR Direct 12 Bury Splice Kit or approved equal. 13 (1) Provide secure connection for two or more wires. 14 (2) Provide moisture sealing by means of a dielectric non-hardening 15 silicone sealant. 16 (3) Splice Kit shall be intended for use in direct bury applications. 17 (4) Rated for a minimum of 50V. 18 b) Branch connections for laterals, turnouts, services, and appurtenances 19 shall utilize DryConn Direct Bury Lug Aqua, or approved equal. 20 (1) Provide secure connection one or two wires to the main tracer wire 21 without cutting the main tracer wire. 22 (2) Provide moisture sealing by means of a dielectric non-hardening 23 silicone sealant. 24 (3) Branch connector shall be intended for use in direct bury 25 applications. 26 (4) Rated for a minimum of 50V. 27 3) Grounding / Termination 28 a) Grounding shall only be applied where indicated on the Drawings 29 b) Drive-in magnesium grounding anode rod with a minimum of 20-feet 30 of 12-AWG red HDPE insulated copper-clad steel wire connected to 31 the rod and specifically manufactured for this purpose. 32 c) Dead ends and stub-outs shall be terminated with a 3M Brand DBR 33 Direct Bury Splice Kit or approved equal. 34 2. Surface Markers 35 a. Provide as follows: 36 1) 4-inch wide, 6-feet minimum length, fiberglass composite, double-sided 37 marker, or approved equal 38 2) Posts with colored, ultraviolet resistant decals as follows: 39 a) Water Lines 40 (1) Color – Blue (in accordance with APWA Uniform Color Code) 41 (2) Legend – Caution Potable Water Line Below 42 b) Reclaimed water lines 43 (1) Color – Purple (in accordance with APWA Uniform Color Code) 44 (2) Legend – Caution Reclaimed Water Line Below 45 c) Sewer lines 46 (1) Color – Green (in accordance with APWA Uniform Color Code) 47 (2) Legend – Caution Sewer Line Below 48 33 05 97 UTILITY MARKERS/LOCATORS Page 5 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 17, 2024 Effective July 1, 2024 2.3 ACCESSORIES [NOT USED] 1 2.4 SOURCE QUALITY CONTROL [NOT USED] 2 PART 3 - EXECUTION 3 3.1 INSTALLERS [NOT USED] 4 3.2 EXAMINATION [NOT USED] 5 3.3 PREPARATION [NOT USED] 6 3.4 INSTALLATION 7 A. Buried Markers 8 1. Detectable Warning Tape – For all underground water and sanitary sewer lines 9 a. Install in accordance with manufacturer’s recommendations below natural 10 ground surface and directly above the utility for which it is marking. 11 1) Allow 18 inches minimum between utility and marker. 12 2) Bury to a depth of 3 feet or as close to the grade as is practical for optimum 13 protection and detectability. 14 2. Tracer Wire and Appurtenances 15 a. Install tracer wire such that it can be easily accessed for connection of line 16 tracing equipment, wire can be located without loss or deterioration of low 17 frequency signal, and without distortion of signal caused by more than one wire 18 being installed in close proximity to another. 19 b. Install tracer wire in the same trench or inside casing with pipe during pipe 20 installation. 21 1) Secure wire to the pipe at a maximum of 5-foot intervals and in accordance 22 with manufacturer recommendations, and the City Standard Details. 23 a) Do not place the tracer wire between service saddles and the main. 24 2) Securely bond all wire joints with an approved watertight connector to 25 provide electrical continuity. 26 3) Install wire at all tracer wire access points in accordance with City Standard 27 Details, providing no less than 24-inches of coiled wire. 28 c. Provide continuous tracer wire without splices from each tracer wire access 29 point, except where approved by City for spliced-in repair or replacement 30 connections. 31 d. Install tracer wire as a continuous single wire. No looping or coiling of wire is 32 permitted. 33 e. Protect wire insulation from damage during installation of embedment and 34 backfill. 35 f. Replace all wire that has broken, cut, or damaged insulation 36 g. Treat all connections between existing metallic pipe and plastic pipe as a 37 mainline dead-end, and ground using an approved waterproof connection to a 38 grounding anode, buried at the same depth as the tracer wire. 39 h. Connect new tracer wire to an existing utility that is being extended or tied into, 40 using approved splice connectors. 41 33 05 97 UTILITY MARKERS/LOCATORS Page 6 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 17, 2024 Effective July 1, 2024 i. At all main end caps, extend a minimum of 6 feet of tracer wire beyond the end 1 of the pipe, coil, and secured to the pipe for future connections. Splice the end 2 of the tracer wire to a grounding rod in accordance with manufacturer’s 3 recommendations and City Standard Details and bury grounding rod at the 4 same elevation as the main. 5 j. Place tracer wire access valve boxes spaced in accordance with City Standard 6 Details. 7 k. Maximum spacing between tracer wire access points shall be 500 feet. If meter 8 or hydrant spacing is greater than 500 feet then utilize Copperhead Mamba 9 Round Locate post marker or approved equivalent. 10 B. Surface Markers 11 1. Bury a minimum of 2 feet deep, with a minimum of 4 feet above ground 12 2. The warning sign for all surface markers shall be 21 inches (not including decaled 13 portion). 14 3. Place surface markers near fixed objects, if possible 15 4. Place Surface Markers at the following locations: 16 a. Unimproved areas only 17 b. Buried Features 18 1) Place directly above a buried feature. 19 c. Above-Ground Features 20 1) Place a maximum of 2 feet away from an above-ground feature. 21 d. Water lines 12-inches and larger: 22 1) Each right-of-way line (or end of casing pipe) for: 23 a) Highway crossings 24 b) Railroad crossings 25 2) Utility crossings such as: 26 a) High pressure or large diameter gas lines 27 b) Fiber optic lines 28 c) Underground electric transmission lines 29 d) Or other locations specified in the Drawings or directed by the City 30 e. For sanitary sewer lines: 31 1) In undeveloped areas, place marker maximum of 2 feet away from an 32 above-ground feature such as a manhole or combination air valve vault. 33 f. Place at 500-foot intervals along the pipeline. 34 g. As specified in Drawings. 35 C. Curb Markers 36 1. Curb Markers shall be lettered etchings in the existing or new concrete curb 37 2. Place Curb Markers at the following locations: 38 a. An etched “W” painted blue wherever a water service line crosses the curb 39 b. An etched “S” painted green wherever a sanitary sewer service line crosses the 40 curb 41 c. An etched “F” painted blue wherever a fire line crosses the curb 42 33 05 97 UTILITY MARKERS/LOCATORS Page 7 of 7 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised June 17, 2024 Effective July 1, 2024 3.5 REPAIR [NOT USED] 1 3.6 RE-INSTALLATION [NOT USED] 2 3.7 FIELD QUALITY CONTROL 3 A. Testing 4 1. After all trench backfill is completed and prior to final surface repair, perform 5 continuity and trace tests on all tracer wire in the presence of the City. 6 2. If the tracer wire is found to be non-continuous after testing, repair or replace the 7 failed segment of wire. 8 3.8 SYSTEM STARTUP [NOT USED] 9 3.9 ADJUSTING [NOT USED] 10 3.10 CLEANING [NOT USED] 11 3.11 CLOSEOUT ACTIVITIES [NOT USED] 12 3.12 PROTECTION [NOT USED] 13 3.13 MAINTENANCE [NOT USED] 14 3.14 ATTACHMENTS [NOT USED] 15 END OF SECTION 16 17 Revision Log DATE NAME SUMMARY OF CHANGE 6/17/24 Added requirements for curb markings of water, fire and sewer service line crossings; 1.1.A 6/17/24 Modified grounding and termination requirements for tracer wire; 2.2.B.1.b.3) 6/17/24 Added maximum spacing requirement for tracer wire access points; 3.4.A.2.k 18 33 05 98 LOCATION OF EXISTING UTILITIES Page 1 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 33 05 98 1 LOCATION OF EXISTING UTILITIES 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Locating and verifying the location and elevation of existing underground utilities 6 at proposed connection points or that may conflict with proposed facilities, by use 7 of: 8 a. Exploratory Excavation 9 b. Vacuum Excavation 10 B. Deviations from this City of Denton Standard Specification: 11 1. None. 12 C. Related Specification Sections include but are not limited to: 13 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 14 Contract. 15 2. Division 1 - General Requirements. 16 3. Section 33 05 05 – Utility Trench Excavation, Embedment, and Backfill. 17 1.2 PRICE AND PAYMENT PROCEDURES 18 A. Measurement and Payment 19 1. Location of Existing Utilities 20 a. Measurement 21 1) Measurement for this item shall be by lump sum. 22 b. Payment 23 1) The work performed and materials furnished in accordance with this item 24 shall be paid for at the lump sum price bid for “Location of Existing 25 Utilities” at proposed connection points and all proposed crossings. 26 c. The price bid shall include: 27 1) Coordination with utility owners 28 2) Grade survey 29 3) Pavement removal 30 4) Excavation 31 5) Vacuum excavation 32 6) Utility location 33 7) Hauling 34 8) Disposal of excess material 35 9) Furnishing, placement, and compaction of embedment 36 10) Furnishing, placement, and compaction of backfill 37 11) Clean-up 38 12) Surface restoration 39 1.3 REFERENCES 40 41 33 05 98 LOCATION OF EXISTING UTILITIES Page 2 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 A. Definitions 1 1. Exploratory Excavation: Commonly referred to as “potholing”, a method used to 2 locate existing 10” and smaller underground utilities through the use of standard 3 excavation equipment. 4 2. Vacuum Excavation: Method used to locate existing underground utilities of all 5 sizes, but which must be used for utilities 12 inches and larger, through the use of 6 geophysical prospecting equipment such as vacuum excavation. 7 B. Reference Standards 8 1. Reference standards cited in this Section refer to the current reference standard 9 published at the time of the latest revision date logged at the end of this Section 10 unless a date is specifically cited. 11 2. American Society of Civil Engineers (ASCE) 12 a. ASCE Publication CI/ASCE 38 (Standard Guideline for the Collection and 13 Depiction of Existing Subsurface Utility Data) 14 1.4 ADMINISTRATIVE REQUIREMENTS 15 A. Coordination 16 1. Stake areas for location at least 1 week prior to commencement of location. 17 2. Coordinate location of all utilities within vicinity of excavation prior to 18 commencing location. 19 3. Coordinate with City at least 48 hours prior to commencing on site for location of 20 utilities. 21 B. Sequencing 22 1. Location of utilities shall be performed prior to construction of the entire Work. 23 C. Scheduling 24 1. For critical utility locations, City may choose to be present during excavation. 25 2. Alter schedule for location of existing utilities to accommodate City personnel. 26 1.5 SUBMITTALS [NOT USED] 27 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 28 1.7 CLOSEOUT SUBMITTALS 29 A. Report of Utility Location 30 1. Horizontal location of utility as surveyed 31 2. Vertical elevation of utility as surveyed 32 a. Top of utility 33 b. Spring line of utility 34 c. Existing ground 35 3. Material type, diameter, and description of the condition of existing utility 36 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 37 1.9 QUALITY ASSURANCE [NOT USED] 38 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 39 33 05 98 LOCATION OF EXISTING UTILITIES Page 3 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1.11 FIELD CONDITIONS [NOT USED] 1 1.12 WARRANTY [NOT USED] 2 PART 2 - PRODUCTS [NOT USED] 3 2.1 CITY-FURNISHED PRODUCTS [NOT USED] 4 2.2 MATERIALS [NOT USED] 5 2.3 ACCESSORIES [NOT USED] 6 2.4 SOURCE QUALITY CONTROL [NOT USED] 7 PART 3 - EXECUTION 8 3.1 INSTALLERS [NOT USED] 9 3.2 EXAMINATION 10 A. Verification of Conditions 11 1. Verify location of existing utilities in accordance with Division 1 and the Drawings. 12 3.3 PREPARATION [NOT USED] 13 3.4 INSTALLATION 14 A. Exploratory Excavation 15 1. Do not perform Exploratory Excavation on 12 inch and larger utilities. 16 2. Verify location of all existing 10 inch and smaller utilities which cross or connect 17 to proposed facilities for construction. 18 a. Acquire record documentation from and coordinate with utility companies as 19 necessary to locate utility. 20 b. Expose to utility spring line. 21 c. Excavate and backfill trench for the Exploratory Excavation in accordance with 22 Section 33 05 05. 23 B. Vacuum Excavation 24 1. Verify location of all existing 12 inch and larger utilities which cross or connect to 25 proposed facilities for construction. 26 a. Designate the horizontal position of the existing underground utilities using 27 geophysical prospecting equipment. 28 b. Acquire record documentation from and coordinate with utility companies as 29 necessary to locate utility. 30 c. Perform excavation in general accordance with the recommended practices and 31 procedures described in ASCE Publication CI/ASCE 38. 32 C. Submit a report of the findings upon completion of location of existing utilities. 33 D. Notify City for appropriate design modifications if location of utility is in conflict with 34 the proposed facilities indicated in the Drawings. 35 33 05 98 LOCATION OF EXISTING UTILITIES Page 4 of 4 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 E. Place embedment and backfill in accordance with Section 33 05 05. 1 F. Once necessary data is obtained, immediately restore surface to existing conditions to: 2 1. Obtain a safe driving surface, if applicable 3 2. Ensure the safety of the general public 4 3. The satisfaction of the City 5 3.5 REPAIR [NOT USED] 6 3.6 RE-INSTALLATION [NOT USED] 7 3.7 FIELD QUALITY CONTROL [NOT USED] 8 3.8 SYSTEM STARTUP [NOT USED] 9 3.9 ADJUSTING [NOT USED] 10 3.10 CLEANING [NOT USED] 11 3.11 CLOSEOUT ACTIVITIES [NOT USED] 12 3.12 PROTECTION [NOT USED] 13 3.13 MAINTENANCE [NOT USED] 14 3.14 ATTACHMENTS [NOT USED] 15 END OF SECTION 16 17 Revision Log DATE NAME SUMMARY OF CHANGE 18 33 14 11 POLYVINYL CHLORIDE (PVC) PRESSURE PIPE Page 1 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 SECTION 33 14 11 1 POLYVINYL CHLORIDE (PVC) PRESSURE PIPE 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 Section Includes: 5 1. Polyvinyl Chloride (PVC) Pressure Pipe 4-inch through 12-inch for potable water 6 and reuse applications 7 2. Polyvinyl Chloride (PVC) Pressure Pipe 6-inch through 24-inch for pressure rated 8 gravity sanitary sewer applications. 9 Deviations from this City of Denton Standard Specification: 10 1. None. 11 Related Specification Sections include but are not limited to: 12 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the Contract 13 2. Division 1 - General Requirements 14 3. Section 33 01 10 – Cleaning and Acceptance Testing of Water and Sewer Force 15 Mains 16 4. Section 33 01 30 – Closed Circuit Television (CCTV) Inspection 17 5. Section 33 01 31 – Sewer and Manhole Testing 18 6. Section 33 01 32 – Cleaning of Sewer Mains 19 7. Section 33 05 05 – Utility Trench Excavation, Embedment, and Backfill 20 8. Section 33 05 97 – Utility Markers/Locators 21 9. Section 33 14 10 – Ductile Iron Pipe and Fittings 22 1.2 PRICE AND PAYMENT PROCEDURES 23 Measurement and Payment 24 1. PVC Water Pipe 25 a. Measurement 26 1) Measured horizontally along the ground surface from center line to center 27 line of fitting, manhole, or appurtenance of PVC Pressure Pipe installed. 28 b. Payment 29 1) The work performed and materials furnished in accordance with this item 30 and measured as provided under “Measurement” will be paid for at the unit 31 price bid per linear foot for “PVC Water Pipe” installed for: 32 a) Various sizes. 33 b) Various types of backfill. 34 c. The price bid shall include: 35 1) Furnishing and installing PVC Pressure Pipe as specified by the Drawings 36 2) Furnishing and installing Ductile Iron Fittings in accordance with Section 37 33 14 10 38 3) Pavement removal 39 33 14 11 POLYVINYL CHLORIDE (PVC) PRESSURE PIPE Page 2 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 4) Excavation 1 5) Hauling 2 6) Disposal of excess material 3 7) Furnishing, placement and compaction of embedment 4 8) Furnishing, placement and compaction of backfill 5 9) Trench Dams 6 10) Thrust restraint 7 11) Gaskets 8 12) Clean-up 9 13) Cleaning 10 14) Disinfection 11 15) Testing 12 2. PVC Gravity Sewer Pressure Pipe 13 a. Measurement 14 1) Measured horizontally along the ground surface from center line to center 15 line of fitting, manhole, or appurtenance of PVC Pressure Pipe installed. 16 b. The work performed and materials furnished in accordance with this item and 17 measured as provided under “Measurement” will be paid for at the unit price bid 18 per linear foot for “PVC Gravity Sewer Pressure Pipe” installed for: 19 1) Various sizes. 20 2) Various types of backfill. 21 c. The price bid shall include: 22 1) Furnishing and installing PVC Pressure Pipe as specified by the Drawings 23 2) Furnishing and installing couplings 24 3) Utility Markers/Locators 25 4) Pavement removal 26 5) Excavation 27 6) Hauling 28 7) Disposal of excess material 29 8) Furnishing, placement and compaction of embedment 30 9) Furnishing, placement and compaction of backfill 31 10) Trench Dams 32 11) Gaskets 33 12) Clean-up 34 13) Cleaning 35 14) Testing 36 1.3 REFERENCES 37 Abbreviations and Acronyms 38 1. PVC – Polyvinyl Chloride 39 Reference Standards 40 1. Reference standards cited in this Section refer to the current reference standard 41 published at the time of the latest revision date logged at the end of this Section 42 unless a date is specifically cited. 43 2. American Association of State Highway and Transportation Officials (AASHTO). 44 3. ASTM International (ASTM): 45 33 14 11 POLYVINYL CHLORIDE (PVC) PRESSURE PIPE Page 3 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 a. D1784, Standard Specification for Rigid Poly(Vinyl-Chloride) (PVC) 1 Compounds and Chlorinated Poly(Vinyl Chloride) (CPVC) Compounds. 2 b. D3139, Standard Specification for Joints for Plastic Pressure Pipes Using 3 Flexible Elastomeric Seals. 4 4. American Water Works Association (AWWA): 5 a. M23, PVC Pipe – Design and Installation. 6 5. American Water Works Association/American National Standards Institute 7 (AWWA/ANSI): 8 a. C600, Installation of Ductile-Iron Water Mains and their Appurtenances. 9 b. C605, Underground Installation of Polyvinyl Chloride (PVC) Pressure Pipes and 10 Fittings for Water. 11 c. C900, Polyvinyl Chloride (PVC) Pressure Pipe, and Fabricated Fittings, 4 IN 12 through 60 IN, for Water Transmission and Distribution. 13 6. NSF International (NSF): 14 a. 61, Drinking Water System Components – Health Effects. 15 b. 372, Drinking Water System Components – Lead Content. 16 7. Underwriters Laboratories, Inc. (UL). 17 a. 1285, Standard for Pipe and Couplings, Polyvinyl Chloride (PVC), and Oriented 18 Polyvinyl Chloride (PVCO) for Underground Fire Service 19 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 20 1.5 SUBMITTALS 21 Submittals shall be in accordance with Section 01 33 00. 22 All submittals shall be approved by the City prior to delivery. 23 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 24 Product Data 25 1. For PVC Pressure Pipe that is used for water distribution or wastewater gravity 26 mains, including: 27 a. PVC Pressure Pipe 28 b. Manufacturer 29 c. Dimension Ratio 30 d. Joint Types 31 2. Restraint 32 a. Retainer glands 33 b. Thrust harnesses 34 c. Any other means of restraint 35 3. Gaskets 36 4. Couplings for gravity sewer applications only 37 Certificates 38 1. Furnish an affidavit certifying the PVC Pressure Pipe meets the provisions of this 39 Section, all inspections have been made, and all tests have been performed in 40 accordance with AWWA C900. 41 1.7 CLOSEOUT SUBMITTALS [NOT USED] 42 33 14 11 POLYVINYL CHLORIDE (PVC) PRESSURE PIPE Page 4 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1 2 1.9 QUALITY ASSURANCE 3 Qualifications 4 1. Manufacturers 5 a. Finished pipe shall be the product of 1 manufacturer for each size, unless 6 otherwise approved by the City. 7 1) Change orders, specials, and field changes may be provided by a different 8 manufacturer upon City approval. 9 b. Pipe manufacturing operations shall be performed under the control of the 10 manufacturer. 11 c. Furnish all pipe in accordance with AWWA C900. 12 1.10 DELIVERY, STORAGE, AND HANDLING 13 Delivery and Acceptance Requirements 14 1. Pipe manufactured more than 2 years prior to installation date will not be accepted 15 by the City. 16 Storage and Handling Requirements 17 1. Secure and maintain a location to store the material in accordance with Section 01 18 66 00. 19 2. Store and handle in accordance with the guidelines as stated in AWWA M23. 20 a. When long-term storage (more than 2-months) with exposure to direct sunlight 21 is unavoidable, cover PVC pipe with an opaque material and provide adequate 22 air circulation above and around the pipe as required to prevent excessive heat 23 accumulation. 24 1.11 FIELD CONDITIONS [NOT USED] 25 1.12 WARRANTY [NOT USED] 26 PART 2 - PRODUCTS 27 2.1 CITY-FURNISHED PRODUCTS [NOT USED] 28 2.2 MATERIALS 29 Manufacturers 30 1. Manufacturer List (Potable Water Pipe) 31 a. Diamond Plastics 32 b. JM Eagle 33 c. Northern Pipe Products 34 d. Westlake Pipe & Fittings 35 e. Certa-Lok by CertainTeed 36 f. Vinyltech 37 2. Manufacturer List (Gravity Sewer Pipe) 38 a. Diamond Plastics 39 33 14 11 POLYVINYL CHLORIDE (PVC) PRESSURE PIPE Page 5 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 b. JM Eagle 1 c. Westlake Pipe and Fittings 2 d. Vinyltech 3 3. Manufacturer List (Couplings) 4 a. Multifittings Sewer Brute repair coupling 5 b. HARCO C900 repair coupling 6 c. Smith-Blair 226 or 228 repair clamp 7 4. Substitution requests for manufacturers not indicated above shall be processed in 8 accordance with Section 01 25 00. 9 Pipe 10 1. Manufactured in accordance with AWWA C900. 11 2. Pipe for potable water shall be in accordance with NSF 61 and 372. 12 3. Pipe shall be approved by the Underwriter’s Laboratories, in accordance with UL 13 1285. 14 4. Pipe shall have a lay length of 20 feet except for special fittings or closure pieces 15 necessary to comply with the Drawings. 16 5. The pipe material shall be PVC, meeting the requirements of ASTM D1784, with a 17 cell classification of 12454. 18 6. Pipe shall be colored blue for potable water applications. Pipe shall be colored 19 green for sanitary sewer applications. Pipe shall be colored purple for reuse water 20 applications. 21 7. Outside diameters must be equal to those of cast iron and ductile iron pipes. 22 8. The following minimum Dimension Ratio’s apply: 23 24 Application Diameter (inch) Min Pressure Class (psi) Potable Water 4 through 12 DR 14 Pressure Rated Gravity Sewer Main 6 through 24 DR 25 9. Pipe Markings 25 a. Meet the minimum requirements of AWWA C900. Minimum pipe markings 26 shall be as follows and shall be applied at intervals of not more than 5 feet: 27 1) Manufacturer’s name or trademark and production run record or lot code 28 2) Nominal pipe size in inches and outer diameter base 29 3) Dimension Ratio 30 4) Pressure class 31 5) Hydrostatic integrity test pressure on all standard length hydrostatic-tested 32 pipe 33 6) AWWA C900 34 7) Mark of certifying agency for pipe intended for potable-water service or if 35 not intended for potable water “NOT FOR POTABLE USE” 36 8) For deflectable joints, the maximum allowable axial joint deflection in 37 degrees 38 Pressure and Deflection Design 39 33 14 11 POLYVINYL CHLORIDE (PVC) PRESSURE PIPE Page 6 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 1. Base pipe design on trench conditions and design pressure class specified in the 1 Drawings. Pipe shall be designed in accordance with the methods indicated in 2 AWWA M23 for trench construction, using the following parameters: 3 a. Unit Weight of Fill (w) = 130 pcf 4 b. Live Load = AASHTO HS 20 5 c. Trench Depth = 12 feet minimum or as indicated in Drawings 6 d. Maximum E’ = 1,000 max 7 e. Deflection Lag Factor = 1.0 8 f. Working Pressure (Pw) = 150 psi 9 g. Surge Allowance (Ps) = 100 psi minimum 10 h. Test Pressure = 11 1) No less than 1.25 times the stated working pressure (187 psi minimum) of 12 the pipeline measured at the highest elevation along the test section. 13 2) No less than 1.5 times the stated working pressure (225 psi minimum) at 14 the lowest elevation of the test section. 15 i. Maximum Calculated Deflection = 3 percent 16 j. Restrained Joint Safety Factor (SF) = 1.5 17 k. Maximum Joint Deflection = 100 percent of the manufacturer’s 18 recommendations. 19 2. Verify trench depths after existing utilities are located. 20 a. Accommodate vertical alignment changes required because of existing utility or 21 other conflicts by an appropriate change in pipe design depth. 22 b. In no case shall pipe be installed deeper than its design allows. 23 3. Provisions for Thrust 24 a. Mechanically restrain all bends, tees, plugs, or other fittings with retainer glands 25 in accordance with Section 33 14 10. 26 b. Restrained joints, where required, shall be used for a sufficient distance from 27 each side of the bend, tee, plug, valve, or other fitting to resist thrust which will 28 be developed at the design pressure of the pipe. For the purpose of thrust the 29 following shall apply: 30 1) Calculate valves as dead ends. 31 2) Design pressure shall be greater than both the pressure class of the pipe and 32 the internal pressure (Pi). 33 3) Restrain joints with the following: 34 a) External mechanical joint restraint system in accordance with Section 35 33 14 10; or 36 b) Certa-Lok by CertainTeed restrained joint system. 37 c. The Pipe Manufacturer shall verify the length of pipe with restrained joints to 38 resist thrust in accordance with the Drawings and the following: 39 1) Calculate the weight of the earth (We) as the weight of the projected soil 40 prism above the pipe, for unsaturated soil conditions. 41 2) Soil density = 110 pcf (maximum value to be used), for unsaturated soil 42 conditions 43 3) In locations where ground water is encountered, reduce the soil density to 44 its buoyant weight for the backfill below the water table. 45 a) Reduce the coefficient of friction to 0.25. 46 4. Joints 47 33 14 11 POLYVINYL CHLORIDE (PVC) PRESSURE PIPE Page 7 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 a. Joints shall be gasket, bell and spigot, and push-on type in accordance with 1 ASTM D3139. 2 b. Since each pipe manufacturer has a different design for push-on joints, gaskets 3 shall be part of a complete pipe section and purchased as such. 4 c. Lubricant must be non-toxic and NSF approved for potable water applications. 5 5. Couplings 6 a. Approved couplings are only allowed for gravity sewer applications. Potable 7 water couplings are addressed under Section 33 14 10. 8 6. Detectable Markers 9 a. Provide detectable markers in accordance with Section 33 05 97. 10 2.3 ACCESSORIES [NOT USED] 11 2.4 SOURCE QUALITY CONTROL [NOT USED] 12 PART 3 - EXECUTION 13 3.1 INSTALLERS [NOT USED] 14 3.2 EXAMINATION [NOT USED] 15 3.3 PREPARATION [NOT USED] 16 3.4 INSTALLATION 17 General 18 1. Install pipe, fittings, specials, and appurtenances in accordance with this Section, 19 AWWA C600, AWWA C605, AWWA M23, and the pipe manufacturer’s 20 recommendations. 21 2. Lay pipe to the lines and grades indicated in the Drawings. 22 3. Excavate and backfill trenches in accordance with Section 33 05 05. 23 4. At the close of each operating day: 24 a. Keep the pipe clean and free of debris, dirt, animals, and trash – during and after 25 the laying operation. 26 b. Effectively seal the open end of the pipe using a gasketed night cap. 27 5. Embed pipe in accordance with Section 33 05 05. 28 6. Installation of PVC pipe within casing is only permitted with restrained joints. 29 Pipe Handling 30 1. Haul and distribute pipe at the project site. 31 2. Handle piping with care to avoid damage. 32 a. Inspect each joint of pipe and reject or repair any damaged pipe prior to 33 lowering into the trench. 34 b. Use only nylon ropes, slings, or other lifting devices that will not damage the 35 surface of the pipe for handling the pipe. 36 Pipe Jointing 37 1. Mechanical Joints 38 a. Install mechanical joints in accordance with Section 33 14 10. 39 33 14 11 POLYVINYL CHLORIDE (PVC) PRESSURE PIPE Page 8 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 2. Push-on Joints 1 a. Install push-on joints as defined in AWWA C900. 2 b. Wipe gasket seat inside the bell clean of all extraneous matter. 3 c. Place the gasket in the bell in the position specified by the manufacturer. 4 d. Apply a thin film of non-toxic vegetable soap lubricant to the inside of the 5 gasket and the outside of the spigot prior to entering the spigot into the bell. 6 e. Assemble the pipe joint by sliding the lubricated spigot end into the gasketed 7 bell end to the reference mark on the spigot. 8 f. When using a field cut plain end piece of pipe, refinish the field cut to conform 9 to AWWA C605. 10 g. For gravity sewer applications only, an approved manufacturer’s coupling shall 11 be utilized to join two plain-end pipes per the guidelines provided by the 12 coupling manufacturer. 13 3. Joint Deflection 14 a. Deflect the pipe only when necessary to avoid obstructions or to meet the lines 15 and grades shown in the Drawings. 16 b. Joint deflection shall not exceed 100 percent of the manufacturer’s 17 recommendation. 18 Detectable Metallic Tape Installation 19 1. See Section 33 05 97. 20 3.5 REPAIR [NOT USED] 21 3.6 RE-INSTALLATION [NOT USED] 22 3.7 FIELD QUALITY CONTROL 23 Potable Water Mains 24 1. Hydrostatic testing of water mains: 25 a. Hydrostatically test the mains in accordance with Section 33 01 10. 26 Gravity Sewer Mains 27 1. Closed Circuit Television (CCTV) Inspection 28 a. Provide a Post-CCTV Inspection in accordance with Section 33 01 30. 29 2. Sewer Pipe Testing 30 a. Test pipe in accordance with Section 33 01 31. 31 3.8 SYSTEM STARTUP [NOT USED] 32 3.9 ADJUSTING [NOT USED] 33 3.10 CLEANING 34 Potable Water Mains 35 1. Cleaning, disinfection, and bacteriological testing of water mains: 36 a. Clean, flush, pig, disinfect, and bacteriological test the mains in accordance with 37 Section 33 01 10. 38 Gravity Sewer Mains 39 1. Cleaning of Sewer Mains 40 a. Clean the mains in accordance with Section 33 01 32. 41 33 14 11 POLYVINYL CHLORIDE (PVC) PRESSURE PIPE Page 9 of 9 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 3.11 CLOSEOUT ACTIVITIES [NOT USED] 1 3.12 PROTECTION [NOT USED] 2 3.13 MAINTENANCE [NOT USED] 3 3.14 ATTACHMENTS [NOT USED] 4 END OF SECTION 5 Revision Log DATE NAME SUMMARY OF CHANGE 6 33 14 13 BURIED STEEL PIPE Page 1 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 33 14 13 1 BURIED STEEL PIPE 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Buried Steel Pipe 36-inches and larger for potable water applications in 6 conformance with AWWA C200. 7 B. Deviations from this City of Denton Standard Specification: 8 1. None. 9 C. Related Specification Sections include but are not limited to: 10 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 11 Contract. 12 2. Division 1 - General Requirements. 13 3. Section 33 01 10 – Cleaning and Acceptance Testing of Water Mains. 14 4. Section 33 01 12 – Joint Bonding and Electrical Isolation. 15 5. Section 33 05 05 – Utility Trench Excavation, Embedment, and Backfill. 16 6. Section 33 05 97 – Utility Markers/Locators. 17 7. Section 33 14 05 – Nuts, Bolts, and Gaskets. 18 8. Section 03 34 13 – Controlled Low Strength Material (CLSM). 19 1.2 PRICE AND PAYMENT PROCEDURES 20 A. Measurement and Payment 21 1. Buried Steel Pipe 22 a. Measurement 23 1) Measured horizontally along the surface from center line to center line of 24 the fitting or appurtenance of Buried Steel Pipe installed. 25 b. Payment 26 1) The work performed and materials furnished in accordance with this item 27 and measured as provided under “Measurement” will be paid for at the unit 28 price bid per linear foot for “AWWA C200 Steel Pipe” installed for: 29 a) Various sizes. 30 b) Various types of backfill. 31 c. The price bid shall include: 32 1) Furnishing and installing Buried Steel Pipe as specified by the Drawings 33 2) Mobilization 34 3) Coating 35 4) Lining 36 5) Utility Markers/Locators 37 6) Pavement removal 38 7) Excavation 39 8) Hauling 40 33 14 13 BURIED STEEL PIPE Page 2 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 9) Disposal of excess material 1 10) Furnishing, placement, and compaction of embedment 2 11) Clay Dams 3 12) Joint restraint 4 13) Buried Steel Pipe Fittings 5 14) Bolts and nuts 6 15) Welding 7 16) Gaskets, if allowed 8 17) Furnishing, placement, and compaction of backfill 9 18) Clean-up 10 19) Cleaning 11 20) Disinfection 12 21) Testing 13 22) Test Bulkheads 14 2. Buried Steel Pipe Fittings 15 a. Measurement 16 1) This item is considered subsidiary to Buried Steel Pipe installed. 17 b. Payment 18 1) The work performed and materials furnished in accordance with this item 19 are subsidiary to the unit price bid per linear foot of Buried Steel Pipe 20 installed. 21 1.3 REFERENCES 22 A. Abbreviations 23 1. DFT – Dry Film Thickness 24 2. Mil – Thousandth of an Inch 25 3. PDV – Pressure-diameter value 26 B. Reference Standards 27 1. Reference standards cited in this Section refer to the current reference standard 28 published at the time of the latest revision date logged at the end of this Section 29 unless a date is specifically cited. 30 2. American Architectural Manufacturers Association (AASHTO). 31 3. American Society of Mechanical Engineers (ASME): 32 a. B16.1, Gray Iron Pipe Flanges and Flanged Fittings Classes 25, 125 and 250). 33 b. Boiler and Pressure Vessel Code (BPVC). 34 4. American Society of Testing and Materials (ASTM): 35 a. C33, Standard Specifications for Concrete Aggregates. 36 b. C144, Standard Specification for Aggregate for Masonry Mortar. 37 c. C150, Standard Specification for Portland Cement. 38 d. C216, Standard Specification for Facing Brick (Solid Masonry Units Made 39 from Clay or Shale). 40 e. D16, Standard Terminology for Paint, Related Coatings, Materials, and 41 Applications. 42 f. DD522, Standard Test Methods for Mandrel Bend Test of Attached Organic 43 Coatings. 44 g. D2240, Standard Test Method for Rubber Property-Durometer Hardness. 45 33 14 13 BURIED STEEL PIPE Page 3 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 h. D4541, Standard Test Method for Pull-Off Strength of Coatings Using Portable 1 Adhesion Testers. 2 i. E165, Standard Practice for Liquid Penetrant Examination for General Industry. 3 5. American Welding Society (AWS): 4 a. A2.4, Standard Symbols for Welding, Brazing and Nondestructive 5 Examination. 6 b. A3.0, Standard Welding Terms and Definitions. 7 c. D1.1, Structure Welding Code - Steel. 8 6. American Water Works Association (AWWA): 9 a. C200, Steel Water Pipe - 6 Inches and Larger. 10 b. C205, Cement Mortar Protective Lining and Coating for Steel Water Pipe 4 Ins 11 and Larger Shop-Applied. 12 c. C206, Field Welding of Steel Water Pipe. 13 d. C207, Steel Pipe Flanges for Waterworks Service - Sizes 4 IN through 144 IN. 14 e. C208, Dimensions for Fabricated Steel Water Pipe Fittings. 15 f. C210, Liquid-Epoxy Coating Systems for the Interior and Exterior of Steel 16 Water Pipelines. 17 g. C216, Heat Shrinkable Cross-Linked Polyolefin Coatings for the Exterior of 18 Special Sections, Connections, and Fittings for Steel Water Pipelines. 19 h. C222, Polyurethane Coatings for the Interior and Exterior of Steel Water Pipe 20 and Fittings. 21 i. M11, Steel Pipe - A Guide for Design and Installation. 22 7. American Water Works Association/American National Standards Institute 23 (AWWA/ANSI). 24 8. International Organization for Standardization (ISO). 25 9. NACE International (NACE): 26 a. SP0188, Discontinuity (Holiday) Testing of New Protective Coatings on 27 Conductive Substrates. 28 10. NSF International (NSF): 29 a. 61, Drinking Water System Components - Health Effects. 30 b. 372, Drinking Water System Components – Lead Content. 31 11. Spray Polyurethane Foam Alliance (SPFA). 32 12. Society for Protective Coatings (SSPC)/National Association of Corrosion 33 Engineers (NACE): 34 a. PA 2, Measurement of Dry Coating Thickness with Magnetic Gages. 35 b. SP 1, Solvent Cleaning. 36 c. SP 2, Hand Tool Cleaning. 37 d. SP 3, Power Tool Cleaning. 38 e. SP 10/NACE No. 2, Near-White Blast Cleaning. 39 f. SP 0188, Discontinuity (Holiday) Testing of New Protective Coatings on 40 Conductive Substrates. 41 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 42 1.5 SUBMITTALS 43 A. Submittals shall be in accordance with Section 01 33 00. 44 B. All submittals shall be approved by the City prior to fabrication and delivery. 45 33 14 13 BURIED STEEL PIPE Page 4 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 1 A. Qualifications 2 1. Submit manufacturer and welder qualifications in accordance with Article 1.9. 3 B. Product Data 4 1. Exterior Coating 5 a. Material data 6 b. Application recommendations 7 c. Field touch-up procedures 8 2. Heat Shrink Sleeves, if applicable 9 a. Material data 10 b. Installation recommendations 11 3. Joint Wrappers, if applicable 12 a. Material data 13 b. Installation recommendations 14 4. Mixes 15 a. Mortar for interior joints and patches 16 b. Bonding agents for patches 17 5. Gaskets 18 C. Shop Drawings 19 1. Wall thickness design calculations sealed by a Professional Engineer Licensed in 20 Texas, including: 21 a. Internal pressure 22 1) Working Pressure 23 2) Test Pressure 24 3) Surge pressure 25 b. External pressure 26 1) Deflection 27 2) Buckling 28 3) Extreme loading conditions 29 c. Special physical loading such as supports or joint design 30 d. Thermal expansion and/or contraction 31 2. Thrust restraint calculations for all fittings, valves, and deflections, including the 32 restraint length, sealed by a Professional Engineer Licensed in Texas. 33 3. Fabrication and lay drawings showing a schematic location with profile and a 34 tabulated layout schedule that is sealed by a Professional Engineer Licensed in 35 Texas, including: 36 a. Pipe class 37 b. Joint types 38 c. Fittings 39 d. Outlets 40 e. Thrust Restraint 41 f. Stationing (in accordance with the Drawings) 42 g. Transitions 43 h. Joint deflection 44 i. Interior lining 45 33 14 13 BURIED STEEL PIPE Page 5 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 j. Outlet locations for welding, ventilation, and access 1 k. Welding requirements and provisions for thermal stress control 2 4. Pipe within Casing 3 a. Provide drawings detailing how pipe is restrained to prevent floating within 4 casing. 5 5. Shop and field welding data: 6 a. Provide a weld map indicating the location, type, size, and extent of proposed 7 welds in accordance with AWS A2.4. 8 1) Submit welding terms in accordance with AWS A3.0. 9 2) Indicated by welding symbols or sketches, details of welded joints, and 10 preparation of base metal. 11 3) Distinguish between shop and field welds. 12 D. Certificates and Test Reports 13 1. Prior to shipment of the pipe, the pipe manufacturer shall submit the following: 14 a. A Certificate of Adequacy of Design stating that the pipe to be furnished 15 complies with AWWA C200, AWWA C205, AWWA C210, AWWA C222, 16 and this Section. 17 b. Copies of results of factory hydrostatic tests shall be provided to the City. 18 c. Mill certificates, including chemical and physical test results for each heat of 19 steel. 20 d. A Certified Test Report from the polyurethane coating manufacturer indicating 21 that the coatings were applied in accordance with manufacturer's requirements 22 and in accordance with this Section. 23 e. Certified test reports for welder certification for factory and field welds in 24 accordance with AWWA C200, Section 4.11. 25 f. Certified test reports for cement mortar tests. 26 g. Certified test reports for steel cylinder tests. 27 E. Daily Records 28 1. Submit daily welding records in accordance with Article 3.7 – Field Quality 29 Control. 30 1.7 CLOSEOUT SUBMITTALS 31 A. Test and Evaluation Reports 32 1. All test reports generated during testing. 33 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 34 1.9 QUALITY ASSURANCE 35 A. Qualifications 36 1. Manufacturer Requirements: 37 a. Certified under S.P.F.A. or I.S.O. quality certification program for steel pipe 38 and accessory manufacturing. 39 b. Finished pipe shall be the product of 1 manufacturer. 40 c. Pipe manufacturing operations (pipe, lining, and coatings) shall be performed 41 under the control of the manufacturer. 42 33 14 13 BURIED STEEL PIPE Page 6 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 d. The pipe manufacturer shall not have less than 5 years successful experience 1 manufacturing pipe of the particular type and size indicated and be able to 2 demonstrate an experience record that is satisfactory to the City. 3 1) Pipe manufacturing operations (pipe, fittings, lining, and coating) shall be 4 performed at 1 location, unless otherwise approved by the City. 5 e. Manufacture pipe and fittings in accordance with the latest revisions of AWWA 6 C200, AWWA C205, AWWA C208, AWWA C210, and AWWA C222. 7 2. Welders 8 a. Use only competent, skilled, and qualified workmen. 9 b. Welder Qualifications Records (WQR) in accordance with AWWA C206, 10 ASME BPVC Section IX, or AWS D1.1 as required for both factory and field 11 welders. 12 1.10 DELIVERY, STORAGE, AND HANDLING 13 A. Packing 14 1. Prepare pipe for shipment to: 15 a. Afford maximum protection from normal hazard of transportation. 16 b. Allow pipe to reach project site in an undamaged condition. 17 2. Do not deliver pipe damaged in shipment to the project site unless such damaged 18 pipe is properly repaired. 19 3. After the completed pipe and fittings have been removed from the final cure at the 20 manufacturing plant: 21 a. Protect pipe lining from drying by means of plastic end covers banded to the 22 pipe ends. 23 b. Maintain covers over the pipe ends at all times until ready to be installed. 24 c. Maintain moisture inside the pipe by periodic addition of water as necessary. 25 4. Carefully support pipes during shipment and storage. 26 a. Separate pipe, fittings, and specials so they do not bear against each other and 27 securely fasten the whole load to prevent movement in transit. 28 b. Ship pipe on padded bunks with tie-down straps approximately over stulling (in 29 accordance with AWWA M11). 30 c. Store pipe on padded skids, sand or dirt berms, tires, or other suitable means to 31 protect the pipe from damage. 32 d. Internally support and brace pipe, fittings, and specials in accordance with 33 AWWA M11. 34 1) Do not remove stulls until backfill operations are complete (excluding final 35 clean up), unless it can be demonstrated to the City’s satisfaction that 36 removal of stulls will not adversely affect pipe installation. 37 B. Delivery, Handling, and Storage 38 1. Inspection of pipe’s interior coating for excessive cracking by both the City and the 39 Contractor to occur once the 1st shipment of pipe is delivered to the Site. 40 a. If excessive cracking is found, modify shipping procedures to reduce or 41 eliminate cracking. 42 2. Deliver, handle, and store pipe in accordance with the manufacturer's 43 recommendations to protect coating systems. 44 33 14 13 BURIED STEEL PIPE Page 7 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3. Secure and maintain a location to store the material in accordance with Section 01 1 66 00. 2 4. Haul pipe directly from the plant to the Site and string along pipeline alignment to 3 minimize rehandling of the pipe. Pipe damaged as a result of handling shall be 4 removed from the Site and replaced at no additional cost to the City. 5 1.11 FIELD CONDITIONS [NOT USED] 6 1.12 WARRANTY [NOT USED] 7 PART 2 - PRODUCTS 8 2.1 CITY-SUPPLIED PRODUCTS [NOT USED] 9 2.2 MATERIALS 10 A. Manufacturers 11 1. Allowed Manufacturers: 12 a. Thompson Pipe Group 13 b. Northwest Pipe 14 c. American Spiralweld 15 2. Submit Substitution requests for manufacturers not indicated above in accordance 16 with Section 01 25 00. 17 B. Materials 18 1. General 19 a. Manufacture pipe and fittings in accordance with AWWA C200, AWWA 20 C205, AWWA C208, AWWA C210, and AWWA C222. 21 b. All pipe lining material in contact with potable water shall be in accordance 22 with NSF 61 and 372. 23 2. Steel Requirements: 24 a. In accordance with the requirements of AWWA C200 25 b. Continuous casting 26 c. Homogeneous 27 d. Suitable for field welding 28 e. Fully killed 29 f. Fine austenitic grain size 30 g. Minimum yield strength of 42,000 psi 31 3. Fittings 32 a. Fabricate all fittings from hydrostatically tested pipe. 33 b. Design fittings and specials in accordance with AWWA C208 and AWWA 34 M11, except for the following: 35 1) Utilize crotch plates for outlet reinforcement for all PDVs greater than 36 6,000 unless indicated otherwise in the Drawings. 37 2) Where indicated on the Drawings, utilize collars or wrapper in lieu of 38 crotch plates to allow for working space and supports. 39 c. All bend fittings shall be long radius (minimum 2.5 times the pipe inner 40 diameter) to permit easy passage of pipeline pigs. 41 4. Exterior Polyurethane Coating 42 33 14 13 BURIED STEEL PIPE Page 8 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 a. Pipe: 1 1) Polyurethane Coating shall be factory applied and meet the requirements of 2 AWWA C222. Use a Coating Standard ASTM D16, Type V system which 3 is a 100-percent solids, 2-component polyurethane (or 2-package 4 polyisocyanate, polyol-cured urethane) coating. 5 a) Components shall have balanced viscosities in their liquid state and 6 shall not require agitation during use. 7 b) Conversion to Solids by Volume: 97 percent ± 3 percent 8 c) Temperature Resistance: Minus 40 degrees F and plus 150 degrees F 9 d) Minimum Adhesion: 1500 psi, when applied to steel pipe which has 10 been blasted to comply with SSPC SP 10/NACE No. 2 11 (1) Cure Time: For handling in 2-3 minutes at 120 degrees F and full 12 cure within 7 days at 70 degrees F 13 e) Maximum Specific Gravities 14 (1) Polyisocyanate resin, 1.20 15 (2) Polyol resin, 1.15 16 f) Minimum Impact Resistance: 80 inch-pounds using 1-inch diameter 17 steel ball 18 g) Minimum Tensile Strength: 2000 psi 19 h) Hardness: Minimum Durometer hardness of 65 on the Shore D scale in 20 accordance with ASTM D2240 21 i) Flexibility Resistance 22 (1) ASTM D522 using 1-inch mandrel 23 (2) Allow coating to cure for 7 days. 24 (3) Perform testing on test coupons held for 15 minutes at temperature 25 extremes specified above. 26 j) Dry Film Thickness: 35 mils 27 k) Coating shall be a self-priming, plural component, 100 percent solids, 28 non-extended polyurethane, suitable for burial or immersion and shall 29 be: 30 (1) Durashield 110, Durashield 210, or Durashield 310 as 31 manufactured by LifeLast, Inc., 32 (2) Protec II as manufactured by Futura Coatings, or 33 (3) City approved equal. 34 2) The coating manufacturer shall have a minimum of 5 years’ experience in 35 the production of this type coating. 36 b. Specials, Fittings, Repair, and Connections 37 1) Provide shop-applied and field-applied coating as follows: 38 a) Durashield 210, Durashield 310, or Durashield 310 JARS as 39 manufactured by LifeLast, Inc., or 40 b) Protec II as manufactured by Futura Coatings. 41 c) Mix and apply polyurethane coatings in accordance with the coating 42 manufacturer's recommendations. 43 5. Special Coatings in Tunnels and Casings 44 a. Pipe to be placed in tunnel or casing shall have a full, continuous mortar 45 coating over the polyurethane coating. 46 33 14 13 BURIED STEEL PIPE Page 9 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 b. Mortar coating shall have at least 2 raised mortar rings, each approximately 2 1 feet long and sufficiently higher than the outside diameter of the pipe bell, 2 including heat shrink sleeve, and to allow for band mortar ring loss as pipe is 3 pushed into casing. 4 6. Cement Mortar Linings 5 a. Shop apply cement mortar linings. 6 b. Shop-apply cement mortar linings in accordance with the requirements of 7 AWWA C205 with the following modifications: 8 1) Sand shall be silica sand in accordance with ASTM C33. 9 2) Curing of the linings shall be in accordance with the requirements of 10 AWWA C205. 11 7. Gaskets 12 a. Flange in accordance with AWWA C207. 13 b. Provide Gaskets in accordance with Section 33 14 05. 14 8. Bolts and Nuts 15 a. Flanged Ends 16 1) Flange in accordance with AWWA C207. 17 2) Provide bolts and nuts in accordance with Section 33 14 05. 18 9. Isolation Flanges 19 a. In accordance with Section 33 01 12. 20 10. Flange Coatings 21 a. Petrolatum Tape System in accordance with Section 33 14 05. 22 11. Threaded Outlets and Taps 23 a. Provide CC Threads and furnish and install brass bushings for the outlet size 24 indicated. 25 12. Weld Lead Outlets 26 a. Additional outlet configurations are required to be approved by the City prior to 27 fabrication. 28 b. Outlets shall be flanged, not threaded. 29 c. Spacing of outlets shall be no closer than 500 feet. 30 d. Weld a plate onto the outlet for closure and encase in cement mortar. 31 e. Record northing, easting, and top of flange elevation on job set of Record 32 Drawings in accordance with Section 01 78 39. 33 13. Mixes 34 a. Mortar for Joints 35 1) 1 part Portland Cement to 2 parts sand. 36 2) Cement – ASTM C150, Type I or II. 37 3) Sand 38 a) Sharp silica base 39 b) ASTM C144 40 4) Interior joint mortar shall be mixed with as little water as possible so that 41 the mortar is very stiff, but workable. 42 5) Water for cement mortar shall be from a potable water source. 43 b. Mortar for Patching 44 1) Same as for interior joints 45 c. Bonding Agent 46 1) Cement Mortar Lining 47 33 14 13 BURIED STEEL PIPE Page 10 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 a) In accordance with NSF 61 and NSF 372 if cement lining is in contact 1 with potable water. 2 2) Cement Mortar Lining Patching 3 a) Probond Epoxy Bonding Agent ET-150, parts A and B 4 b) Sikadur 32 Hi-Mod, or 5 c) Approved equal. 6 14. Heat Shrink Sleeves for Polyurethane Coated Steel Pipe 7 a. Primer 8 1) Provide as recommended by the sleeve manufacturer. 9 b. Filler Mastic 10 1) Provide mastic filler as recommended by the heat shrink sleeve 11 manufacturer. 12 2) Size and type shall be as recommended by the sleeve manufacturer for type 13 of pipe and joint. 14 c. Joint Coating 15 1) Cross-linked polyolefin wrap or sleeve with a mastic sealant, 85 mils total 16 thickness, suitable for pipeline operating temperature, sleeve material 17 recovery as recommended by the manufacturer. 18 a) High recovery sleeves shall be provided for bell and spigot and 19 coupling style joints with a minimum of 50 percent recovery. 20 b) Sleeve length shall provide a minimum of 3 inches overlap onto intact 21 pipe coating on each side of the joint. 22 c) Width to take into consideration shrinkage of the sleeve due to 23 installation and joint profile 24 d. Heat shrink sleeves in accordance with AWWA C216, as manufactured by: 25 1) Canusa, 26 2) Raychem, or 27 3) Approved equal. 28 e. Provide heat shrink sleeve suitable to interior joint welding without damage to 29 heat shrink sleeve. 30 C. Performance / Design Criteria 31 1. Pipe Design 32 a. Design, manufacture, and test steel pipe in accordance with AWWA C200, 33 AWWA M11, and the special requirements of this Section. 34 b. Sizes and pressure classes (working pressure) shall be as shown below. 35 c. For the purposes of pipe design, working pressure plus transient pressure shall 36 be as indicated below. 37 d. Fittings, specials, and connections shall be designed for the same pressures as 38 the adjacent pipe. 39 e. Base pipe design on trench conditions and the design pressure in accordance 40 with AWWA M11 using the following parameters: 41 1) Unit Weight of Fill (W) = 130 pounds per cubic foot 42 2) Live Load 43 a) Cooper E-80 for railroad crossings 44 b) AASHTO HS-20 for all other installations 45 3) Trench Depth = As indicated on the Drawings 46 4) Deflection Lag Factor (Dl) = 1.0 47 5) Coefficient (K) = 0.10 48 33 14 13 BURIED STEEL PIPE Page 11 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 6) Maximum Calculated Deflection (Dx): 1 a) Dx = 3 percent (for polyurethane coated and cement mortar lined pipe) 2 b) Dx = 2 percent (for cement mortar coated and lined pipe) 3 7) Soil Reaction Modulus (E'): < (less than or equal) to 1,000 psi 4 8) Working Pressure = 200 psi 5 a) Test Pressure 6 (1) No less than 1.25 minimum times the stated working pressure (250 7 psi minimum) of the pipeline measured at the highest elevation 8 along the test section. 9 (2) No less than 1.5 times the stated working pressure (300 psi 10 minimum) at the lowest elevation of the test section. 11 9) Surge Allowance = 100 psi, minimum 12 a) Where Total Pressure (including surge) = 200 psi + 100 psi = 300 psi 13 f. Where the pipe requires additional external support to achieve the specified 14 maximum deflection, the Contractor and pipe supplier will be required to 15 furnish alternate methods for pipe embedment. 16 1) No additional compensation will be made to the Contractor by the Owner 17 where this method is required. 18 g. Trench depths indicated shall be verified after existing utilities are located. 19 1) Vertical alignment changes required because of existing utility or other 20 conflicts shall be accommodated by an appropriate change in pipe design 21 depth. 22 2) In no case shall pipe be installed deeper than its design allows. 23 h. Field fabrication or cutting is not allowed, unless otherwise approved by the 24 City. 25 i. Design pipe for full vacuum conditions without buckling or damage to lining, 26 coating, or pipe joints. 27 2. Provisions for Thrust 28 a. Restrained joints shall consist of welded joints. Resist thrust at bends, tees, or 29 other fittings by welding joints. 30 1) Thrust at bends adjacent to casing shall be restrained by welding joints 31 through the casing and a sufficient distance each side of the casing. 32 2) The distance for thrust restraint shown on the Drawings is the minimum 33 restraint and does not relieve the manufacturer from calculating the restraint 34 needs as specified herein. 35 a) In no case shall the restrained distance be less than indicated on the 36 Drawings. 37 b. Provide joint restraint for sufficient distance from each side of the bend, tee, 38 plug, or other fitting to resist thrust which develops at the design pressure of the 39 pipe. 40 c. The length of pipe designed with restrained joints to resist thrust shall be the 41 complete responsibility of the pipe manufacturer in accordance with AWWA 42 M11 and the following: 43 1) Calculate the weight of the earth (We) as the weight of the projected soil 44 prism above the pipe, for unsaturated soil conditions: 45 a) Soil Density 46 (1) Unsaturated soil conditions = 110 pounds per cubic foot (maximum 47 value to be used) 48 33 14 13 BURIED STEEL PIPE Page 12 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 (2) Locations with groundwater = buoyant weight for the backfill 1 below the water table 2 2) Coefficient of friction = 0.25 (maximum value to be used for polyurethane 3 coated steel pipe) 4 3) Use the minimum soil cover indicated in the Drawings over the entire 5 restrained area. 6 4) Design pressure shall be 300 psi (working pressure + surge allowance). 7 3. Inside Diameter 8 a. The inside diameter, including the cement mortar lining, shall be a minimum of 9 the nominal diameter of the pipe specified unless otherwise indicated on the 10 Drawings. 11 12 4. Wall Thickness 13 a. The minimum pipe wall steel thickness shall be as designed, but not less than 14 0.1875 inches or pipe D/230, whichever is greater for pipe and fittings, with no 15 minus tolerance, where D is the nominal inside pipe diameter. 16 b. Where indicated on the Drawings, pipe and fittings shall have thicker steel pipe 17 wall. 18 c. The minimum steel wall thickness shall also be such that the fiber stress shall 19 not exceed: 20 1) 50 percent of the minimum yield strength of the steel for working pressure, 21 or 18,000 psi (whichever is less), and 22 2) 75 percent of the minimum yield strength of the steel at the maximum 23 pressure (including transient pressure), or 27,000 psi (whichever is less), 24 nor the following, at the specified working pressure: 25 Pipe Type Maximum Stress at Working Pressure Polyurethane Coated Steel 23,000 psi Mortar Coated Steel (for Casing Only) 18,000 psi 26 d. Pipe which is placed in casing or tunnel shall have a minimum pipe wall steel 27 thickness of 0.25 inches or pipe D/144, whichever is greater, where D is the 28 nominal pipe diameter. 29 e. Pipe and fittings that are above grade or exposed (not in a trench, casing, or 30 tunnel) shall have a minimum pipe wall steel thickness of 0.375 inches or pipe 31 D/144, whichever is greater. 32 f. Pipe, fittings, and specials shall be designed such that the maximum stresses in 33 the pipe due to thrust loading will not exceed 18,000 psi. 34 5. Seams 35 a. Except for mill-type pipe, the piping shall be made from steel plates rolled into 36 cylinders or sections thereof with the longitudinal and girth seams butt welded 37 or shall be spirally formed and butt welded. 38 1) There shall be not more than 2 longitudinal seams. 39 2) Girth seams shall be butt welded and shall not be spaced closer than 6 feet 40 except in specials and fittings. 41 6. Joint Length 42 a. Maximum joint length shall not exceed 50 feet. 43 33 14 13 BURIED STEEL PIPE Page 13 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 b. Maximum joint length of steel pipe installed in casing shall meet the project 1 requirements. 2 c. Manufactured random segments of pipe will not be permitted for straight runs 3 of pipe. 4 1) Closing piece segments, however, shall be acceptable. 5 7. Joint Bonds, Insulated Connections, and Flange Gaskets 6 a. In accordance with Section 33 01 12. 7 8. Pipe Ends 8 a. Allowable pipe ends include: 9 1) Lap welded slip joints 10 2) Butt strap joint 11 3) Flanged joint 12 4) Flexible coupled joint 13 5) Roll groove gasket joint 14 b. Weld or harness pipe ends where indicated and as necessary to resist thrust 15 forces. 16 1) Thrust at bends adjacent to casing shall be restrained by welding joints 17 through the casing and a sufficient distance each side of the casing. 18 c. Rubber Gasket Joint (O-ring or Carnegie Joints) 19 1) Allowed for pipe sizes 54-inch diameter and smaller. 20 2) In accordance with AWWA C200. 21 3) Joint Configuration: 22 a) Bell 23 (1) Flared bell end formed and sized by forcing the pipe or a plug die 24 or by expanding on segmental dies. 25 b) Spigot 26 (1) Rolled spigot or carnegie-shaped steel joint ring in accordance with 27 AWWA C200 and as shown as Item F or H in Figure 8-1 of the 28 AWWA M11. 29 4) Check the welded area of bell and spigot pipe ends after forming by the dye 30 penetrant or magnetic particle method. 31 5) The difference in diameter between the interior diameter (I.D.) of the bell 32 and the outer diameter (O.D.) of the spigot shoulder at point of full 33 engagement with an allowable deflection shall be no more than 0.04 inches 34 as measured on the circumference with a diameter tape. 35 6) The gasket shall have sufficient volume to approximately fill the area of the 36 groove and shall conform to AWWA C200. 37 7) The joint shall be suitable for the specified test and/or surge pressure and 38 deflection. 39 8) Joints shall be of clearances such that water tightness shall be provided 40 under all operating and test conditions with a pipe diameter deflection 41 based upon the supplied pipe coating. 42 9) Joints shall be electrically continuous. 43 d. Lap Welded Slip Joint 44 1) Provided in all locations for pipe where joints are welded for thrust 45 restraint. 46 2) Inside/Outside Weld Requirements: 47 33 14 13 BURIED STEEL PIPE Page 14 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 a) Weld from the inside or outside for pipe diameters 42-inches and 1 larger. 2 b) Weld from the outside for 36-inch pipe diameters. 3 3) Ends of pipe, fittings, and specials for field welded joints shall be prepared 4 with 1 end expanded in order to receive a plain end making a bell and plain 5 end type of joint. 6 a) Clearance between the surfaces of lap joints shall not exceed 1/8 inch at 7 any point around the periphery. 8 4) In addition to the provisions for a minimum lap of 1-1/2 inches as specified 9 in AWWA C200, the depth of bell shall be such as to provide for a 10 minimum distance of 1 inch between the weld and the nearest tangent of 11 the bell radius when welds are to be located on the inside of the pipe. 12 5) Precisely paint a circumferential 3/4-inch insertion band on pipe spigots. 13 a) Leading edge of band to indicate minimum insertion. 14 b) Trailing edge of band indicating maximum insertion. 15 c) Pulled joints to occur within the band around the entire circumference. 16 e. Flanges 17 1) Provide flanged joints at connections to valves and where indicated on the 18 Drawings. 19 2) Ends to be fitted with slip-on flanges shall have the longitudinal or spiral 20 welds ground flush to accommodate the type of flanges provided. 21 3) Provide pipe flanges and welding of flanges to steel pipe in accordance 22 with AWWA C207 and AWWA C206. 23 4) Pipe flanges shall be of rated pressure equal to or greater than the adjacent 24 pipe class. 25 5) Match flanges, including bolt pattern, to the fittings or appurtenances which 26 are to be attached. 27 6) Provide Class E flanges in accordance with AWWA C207 and drilled in 28 accordance with ASME B16.1 Class 125. 29 7) When Isolation Flanges are required by the Drawings, accommodate the 30 require spacing for drillings for mylar sleeves in accordance with Section 31 33 01 12. 32 f. Flexible Couplings 33 1) Provide flexible couplings where specified on the Drawings. 34 2) Ends to be joined by flexible couplings shall be: 35 a) Plain end type, prepared in accordance with AWWA C200. 36 b) Grind welds flush to permit slipping of the coupling in at least 1 37 direction to clear the pipe joint. 38 c) Harness bolts and lugs in accordance with AWWA M11. 39 g. Butt Strap Closure Joints 40 1) Install where necessary to make closure to pipe previously installed. 41 2) Provide in accordance with AWWA C206 and applicable provisions of this 42 Section. 43 9. Polyurethane Coating 44 a. Applicator Qualifications 45 1) Equipment shall be certified by the coating manufacturer to meet the 46 requirements for: 47 a) Material mixing 48 b) Temperature control 49 33 14 13 BURIED STEEL PIPE Page 15 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 c) Application rate 1 d) Ratio control for multi-part coatings 2 2) Equipment not meeting the written requirements of the coating 3 manufacturer shall be rejected for coating application until repairs or 4 replacement of the equipment is made to the satisfaction of the City. 5 3) Personnel responsible for the application of the coating system shall: 6 a) Provide certification of attendance at the coating manufacturer’s 7 training class within the last 3 years. 8 b) Be present during all coating application work and be responsible for 9 controlling all aspects of the coating application. 10 b. Surface Preparation 11 1) Remove visible oil, grease, dirt, and contamination in accordance with 12 SSPC SP 1. 13 2) Remove surface imperfections such as metal slivers, burrs, weld splatter, 14 gouges, or delamination in the metal by filing or grinding prior to abrasive 15 surface preparation. 16 3) In cold weather or when moisture collects on the pipe and the temperature 17 of the pipe is less than 45 degrees F, preheat pipe to a temperature between 18 45 and 90 degrees F but no lower than 5 degrees F above dew point. 19 4) Clean pipe by abrasive blasting with a mixture of steel grit and shot to 20 produce the surface preparation cleanliness as required by coating 21 manufacturer and in accordance with this Section. 22 a) Recycled abrasive shall be cleaned of debris and spent abrasive in an 23 air wash separator. 24 5) Blast media mixture and gradation shall be adequate to achieve a sharp 25 angular surface profile as required by coating manufacturer and to the 26 minimum depth specified. 27 6) Protect prepared pipe from humidity, moisture, and rain. 28 7) Keep pipe clean, dry, and free of flash rust. 29 a) Remove all flash rust, imperfections, or contamination on cleaned pipe 30 surface by re-blasting prior to primer application. 31 8) Complete priming and coating of pipe in a continuous operation the same 32 day as surface preparation. 33 9) Abrasive blast exterior surfaces to a near-white blast cleaning with a 34 minimum 3.0 mil angular profile in bare steel in accordance with SSPC SP 35 10/NACE No. 2. 36 c. Equipment 37 1) 2-component, heated airless spray unit in accordance with coating 38 manufacturer’s recommendation 39 d. Temperature 40 1) Minimum 5 degrees F above dew point temperature. 41 2) Surface temperature not less than 60 degrees F during application. 42 e. Humidity 43 1) Heating of pipe surfaces may be required to meet requirements of this 44 Section if relative humidity exceeds 80 percent. 45 f. Resin 46 1) Do not thin or mix resins; use as received. 47 2) Store resins at a temperature recommended by the coating manufacturer. 48 g. Application 49 33 14 13 BURIED STEEL PIPE Page 16 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1) Applicator shall be certified by the coating manufacturer and conform to 1 coating manufacturer's recommendations. 2 a) Thinning is not permitted. 3 2) Apply directly to pipe to achieve a total dry film thickness (DFT) in 4 accordance with Article 2.2.B.2. 5 3) Multiple-pass, 1 coat application process is permitted provided maximum 6 allowable recoat time specified by coating manufacturer is not exceeded. 7 4) Provide cutbacks in accordance with coating manufacturer’s 8 recommendations as appropriate for the type of joint and heat shrink sleeve 9 to be used. 10 h. Recoating 11 1) Recoat only when coating has cured less than maximum time specified by 12 coating manufacturer. 13 2) When coating has cured for more than recoat time, brush-blast, or 14 thoroughly sand the surface. 15 3) Blow-off cleaning using clean, dry, high pressure compressed air. 16 17 i. Curing 18 1) Do not handle pipe until coating has been allowed to cure, per 19 manufacturer's recommendations. 20 D. Utility Markers/Locators 21 1. Provide utility markers and locators in accordance with Section 33 05 97. 22 2.3 ACCESSORIES [NOT USED] 23 2.4 SOURCE QUALITY CONTROL 24 A. Marking for Identification 25 1. For each joint of pipe and each fitting, plainly mark on 1 end: 26 a. Class for which it is designated 27 b. Date of manufacturer 28 c. Identification number 29 d. Top centerlines on all specials 30 B. Hydrostatic Pressure Testing 31 1. Perform hydrostatic pressure testing in accordance with AWWA C200. 32 2. Hydrostatically test each joint of pipe prior to application of lining or coating. 33 a. The internal test pressure shall be that which results in a fiber stress equal to 75 34 percent of the minimum yield strength of the steel used. 35 b. Each joint of pipe tested shall be completely watertight under maximum test 36 pressure. 37 c. Test pressure shall be held for sufficient time to observe the weld seams. 38 d. Maintain a recording pressure gauge, reference number of pipe tested, etc. 39 1) The pipe shall be numbered in order that this information can be recorded. 40 C. Test fittings by: 41 1. Hydrostatic test 42 2. Magnetic particle test 43 3. Ultrasonic 44 33 14 13 BURIED STEEL PIPE Page 17 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 4. Radiography 1 5. Dye penetrant test 2 D. Factory Testing 3 1. Cement Mortar Lining 4 a. Test shop-applied cement mortar lining in accordance with AWWA C205. 5 2. Polyurethane Coating 6 a. Test in accordance with AWWA C222. 7 b. Thickness: Test thickness of coating in accordance with SSPC PA 2. 8 1) Test coating system applied to the pipe for holidays in accordance with the 9 procedures outlined in NACE SP0188 using a high voltage spark tester 10 (operating at 100 volts per mil), for the dry film thickness (DFT) as 11 indicated in this Section. 12 c. Adhesion Testing 13 1) Polyurethane coatings or linings shall have an adhesion to steel of 1,500 14 pounds per square inch, minimum. 15 2) Test polyurethane coating adhesion to steel substrates using pneumatic pull 16 off equipment, such as HATE Model 108 or Delfesko Positest, in 17 accordance with ASTM D4541 and AWWA C222, except as modified in 18 this Section. 19 3) Adhesion testing records shall include: 20 a) Pipe identification 21 b) Surface tested (interior or exterior) 22 c) Surface temperature 23 d) Coating thickness 24 e) Tensile force applied 25 f) Mode of failure 26 g) Percentage of substrate failure relative of dolly surface 27 4) Glue dollies for adhesion testing to the coating surface and allowed to cure 28 for a minimum of 12 hours. 29 a) Score polyurethane coatings around the dolly prior to conducting the 30 adhesion test. 31 5) Failure shall be by adhesive and cohesive failure only. 32 a) Adhesive failure is defined as separation of the coating from the steel 33 substrate. 34 b) Cohesive failure is defined as failure within the coating, resulting in 35 coating remaining both on the steel substrate and dolly. 36 6) Retest partial adhesion and glue failure if the substrate failure is less than 37 50 percent relative of the dolly surface area and the applied tension was less 38 than the specified adhesion. 39 7) Glue failures in excess of the minimum required tensile adhesion are 40 accepted as meeting the specified adhesion requirements. 41 8) Conduct, accept, and reject adhesion tests on polyurethane pipe coating and 42 lining independently (where applicable). 43 9) Frequency of adhesion testing in accordance with AWWA C222. 44 10) Randomly select repair patches on the polyurethane coating for adhesion 45 testing in a manner as described herein and at the discretion of the coating 46 inspector conducting the adhesion tests. 47 33 14 13 BURIED STEEL PIPE Page 18 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 a) Adhesion of repairs shall be as specified by the coating manufacturer 1 for the type of repair. 2 E. City Testing and Inspection 3 1. The City reserves the option to have an independent testing laboratory inspect pipe 4 and fittings at the pipe manufacturer's plant, at the City's expense. 5 a. The City and their testing laboratory shall have free access to the 6 manufacturer's plant. 7 b. The pipe manufacturer shall provide the City a proposed fabrication schedule at 8 least 2 weeks prior to start of fabrication. The City will then advise the 9 manufacturer whether the tests will be required to be performed by an 10 independent testing laboratory. 11 c. In the event the City elects to retain an independent testing laboratory to make 12 material tests and weld tests, it is the intent that the tests be limited to 1 spot 13 testing of each category unless the tests fail to meet the standard. 14 1) In the event of failed tests, the City reserves the right to have the laboratory 15 make additional tests and observations. 16 2. The inspection and testing by the independent testing laboratory anticipates that 17 production of pipe shall be completed over a normal period of time and without 18 "slow- downs" or other abnormal delays. 19 a. In the event that an abnormal production time is required and the City is 20 required to pay excessive costs for inspection, the Contractor is required to 21 reimburse the City for such costs over and above those which would have been 22 incurred under a normal schedule of production as determined by the City. 23 PART 3 - EXECUTION 24 3.1 INSTALLERS [NOT USED] 25 3.2 EXAMINATION [NOT USED] 26 3.3 PREPARATION [NOT USED] 27 3.4 INSTALLATION 28 A. General 29 1. Install steel pipe, fittings, specials, and appurtenances in accordance with AWWA 30 M11, the pipe manufacturer’s recommendations, this Section, and as required for 31 the proper functioning of the completed pipe line. 32 2. Lay pipe to the lines and grades as indicated in the Drawings. 33 3. Excavate, embed, and backfill trenches in accordance with Section 33 05 05. 34 4. At the close of each operating day: 35 a. Keep the pipe clean and free of debris, dirt, animals, and trash – during and 36 after the laying operation. 37 b. Effectively seal the open end of the pipe using a gasketed night cap. 38 5. Install in accordance with Section 33 05 15. 39 6. Inspect and test each joint for holidays immediately prior to pipe being lowered into 40 the ditch. 41 33 14 13 BURIED STEEL PIPE Page 19 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 a. All damaged areas and holidays are to be repaired before the pipe is lowered 1 into the trench. 2 7. Place and consolidate embedment and backfill prior to removing pipe stulls (where 3 stulls are required per AWWA M11). 4 8. Maximum allowable pipe deflection is limited to: 5 a. 2 percent for mortar coated and lined steel pipe. 6 b. 3 percent for polyurethane coated and mortar lined steel pipe. 7 9. Bond all pipe joints, excluding welded joints and insulated joints, in accordance 8 with Section 33 01 12. 9 B. Pipe Handling 10 1. Haul and distribute pipe and fittings at the project site. 11 2. Handle pipe with care to avoid damage. 12 a. Pipe shall be handled at all times with sufficient non-abrasive slings, belts, or 13 other equipment designed to prevent damage to the coating or lining. 14 b. The spacing of pipe supports required to handle the pipe shall be adequate to 15 prevent cracking or damage to the lining or coating. 16 c. Inspect each joint of pipe and reject or repair any damaged pipe prior to 17 lowering into the trench. 18 d. The equipment shall be kept in such repair that its continued use is not injurious 19 to the coating. 20 e. Do not lay pipe in wet conditions. 21 C. Line Up at Bends 22 1. Line up pipe for joining to prevent damage to pipe joints. 23 a. Thoroughly clean the bell and spigot ends of each joint of pipe of foreign 24 matter, rust, and scale before placing spigot into bell. 25 2. Where abrupt changes in grade and direction occur, employ special shop fabricated 26 fittings for the purpose. 27 a. Field cutting the ends of the steel pipe to accomplish angular changes in grade 28 or direction of the line shall not be permitted. 29 D. Pipe Jointing 30 1. Rubber Gasket Joints 31 a. Join rubber gasket joints in accordance with the manufacturer’s 32 recommendations. 33 b. Clean bell and spigot of foreign material. 34 c. Lubricate gaskets and bell, and relieve gasket tension around the perimeter of 35 the pipe. 36 d. Engage spigot as far as possible in bell, allowing for a minimum gap of 0.5 inch 37 for inside joint grouting after any joint deflection. 38 e. Joint deflection or pull shall not exceed 80 percent of the manufacturer’s 39 recommendation. 40 f. Check gasket with feeler gauge all around the pipe. 41 g. In areas of petroleum hydrocarbon soil contamination, install hydrocarbon 42 resistant gaskets in accordance with Section 33 14 05. 43 2. Welded Joints 44 a. Weld joints in accordance with AWWA C206. 45 33 14 13 BURIED STEEL PIPE Page 20 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1) Contractor shall provide adequate ventilation for welders and for City's 1 representative to observe welds. 2 2) Welds shall be full circle fillet welds, unless otherwise specified. 3 3) Welding shall be completed after application of field applied joint coating. 4 b. Adequate provisions for reducing temperature stresses shall be the 5 responsibility of the Contractor. 6 c. After the pipe has been joined and properly aligned and prior to the start of the 7 welding procedure: 8 1) The spigot and bell shall be made essentially concentric by shimming or 9 tacking to obtain clearance tolerance around the periphery of the joint. 10 2) In no case shall the clearance tolerance be permitted to accumulate. 11 d. Before welding: 12 1) Thoroughly clean pipe ends. 13 2) Weld pipe by machine or by the manual shielded electric arc process. 14 3) Welding shall be performed so as not to damage lining or coating. 15 4) Cover polyurethane coating as necessary to protect from weld splatter. 16 e. Furnish labor, equipment, tools, and supplies including shielded type welding 17 rod. 18 1) Protect welding rod from any deterioration prior to its use. 19 2) If any portion of a box or carton is damaged, reject the entire box or carton. 20 f. Hand Welding 21 1) The metal shall be deposited in successive layers. 22 2) Not more than 1/8 inch of metal shall be deposited in each pass. 23 3) Each pass except the final, whether in butt or fillet welds, shall be 24 thoroughly bobbed or peened to relieve shrinkage stresses and to remove 25 dirt, slag, or flux before the succeeding bead is applied. 26 4) Each pass shall be thoroughly fused into the plates at each side of the 27 welding groove or fillet and shall not be permitted to pile up in the center of 28 the weld. 29 5) Undercutting along the side shall not be permitted. 30 g. Welds shall be free from pin holes, non-metallic inclusions, air pockets, 31 undercutting, and/or any other defects. 32 h. If the ends of the pipe are laminated, split, or damaged to the extent that 33 satisfactory welding contact cannot be obtained, remove the pipe from the line. 34 i. Furnish each welder employed with a steel stencil for marking the welds to 35 easily identify work of individual welders. 36 1) Have each welder stencil the pipe adjacent to the weld with the stencil 37 assigned to him. 38 a) In the event any welder leaves the job, his stencil shall be voided and 39 not duplicated if another welder is employed. 40 j. Welders 41 1) Field welding shall be performed by one of the following firms: 42 a) Thompson Pipe Group, Nels Thomsen, (972) 262-3600 43 b) Fuller’s Service Company, Barry Fuller, (817) 477-3841 44 c) Scott’s Welding, Scott Fowler, (972) 978-7865 45 d) Fletcher’s Welding, Darrell Fletcher 46 e) Eddie’s Welding Service, Eddie Pierce, (817) 909-6089 47 f) National Welding Corporation, Nash Williams, (801) 255-5959 48 g) The Rangeline Group, (800) 346-5971 49 33 14 13 BURIED STEEL PIPE Page 21 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 2) After each welder has qualified in the preliminary tests referred to in 1 Article 1.9, inspections shall be made of joints in the line. 2 a) Inspection to be performed by a Certified Welding Inspector retained 3 by the City. 4 3) Any welder making defective welds shall not be allowed to continue. 5 3. Exterior Joint Protection 6 a. Heat Shrink Sleeves 7 1) General 8 a) Field coat buried pipe joints after pipe assembly in accordance with 9 AWWA C216, using Heat Shrink Sleeves. 10 b) Width of heat shrink sleeve shall be sufficient to overlap the 11 polyurethane coating by a minimum of 3 inches. 12 c) Overlapping of 2 or more heat shrink sleeves to achieve the necessary 13 width will not be permitted. 14 2) Installation 15 a) Clean pipe surface and adjacent coating of all mud, oil, grease, rust, 16 and other foreign contaminates with a wire brush in accordance with 17 SSPC SP 2 or SSPC SP 3. Remove oil or grease contamination by 18 solvent wiping the pipe and adjacent coating in accordance with SSPC 19 SP 1. 20 (1) Clean the full circumference of the pipe and a minimum of 6 inches 21 onto the existing coating. 22 b) Remove all loose or damaged pipe coating at joint and either repair the 23 coating as specified herein or increase the length of the joint coating, 24 where reasonable and practical. 25 c) Complete joint bonding of non-welded pipe joints before application of 26 joint coating. 27 d) Joint bonds shall be low profile bonds and all gaps and crevices around 28 the bonds shall be filled with mastic sealant. 29 e) Store sleeves in shipping box until use is required. 30 (1) Keep dry and sheltered from exposure to direct sunlight. 31 (2) Store off the ground or concrete floors and maintain at a 32 temperature between 60 degrees F and 100 degrees F as 33 recommended by the sleeve manufacturer. 34 f) Metal surface shall be free of all dirt, dust, and flash rusting prior to 35 sleeve application. 36 g) Preheat pipe uniformly to between 140 degrees F and 160 degrees F or 37 as recommended by the sleeve manufacturer. 38 (1) Monitor pipe temperature using a surface temperature gauge, 39 infrared thermometer, or color changing crayons. 40 (2) Protect preheated pipe from rain, snow, frost, or moisture with 41 tenting or shields and do not permit the joint to cool. 42 h) Prime joint with specified primer and fill all cracks, crevices, and gaps 43 with mastic filler in accordance with the manufacturer’s 44 recommendations for the full circumference of the pipe. 45 i) Apply heat shrink sleeve when it is at a minimum temperature or 60 46 degrees F and while maintaining the pipe temperature above the 47 preheat temperature specified. 48 33 14 13 BURIED STEEL PIPE Page 22 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 j) Apply sleeve in accordance with the manufacturer’s instructions and 1 center the sleeve over the joint to provide a minimum of 3-inch overlay 2 onto the existing pipe coating. 3 k) Apply heat to the sleeve using either propane fire infrared heaters or 4 wrap around heaters. 5 (1) Hold flame a minimum of 6 inches from the sleeve surface. 6 (2) Periodically roll the coating on the pipe surface. 7 (3) Heat from the center of the sleeve to the outer edge until properly 8 seated, then begin in the opposite direction. 9 (4) Monitor sleeve for color change, where appropriate, or with 10 appropriate temperature gauges. 11 (5) Take care not to excessively heat the parent coating. 12 l) Completed joint sleeve shall be fully bonded to the pipe and existing 13 coating surface, without voids, mastic beading shall be visible along the 14 full circumference of the sleeve, and there shall be no wrinkling or 15 excessive burns on the sleeves. 16 (1) Sleeves which do not meet these requirements shall be removed 17 and the joint recoated as directed by the City. 18 (2) Minor repairs may be repaired using heat shrink sleeve repair kits. 19 m) Allow the sleeve to cool before moving, handling, or backfilling. In 20 hot climates, provide shading from direct sunlight. 21 (1) Water quenching will be allowed only when permitted by the 22 sleeve manufacturer. 23 4. Interior Joint Grouting 24 a. Upon completion of backfilling of the pipe trench, clean out dirt or trash which 25 has collected in the joint and moisten the concrete surfaces of the joint space by 26 spraying or brushing with a wet brush. 27 b. Fill the inside of the joint recess with a stiff cement mortar. 28 c. Where the mortar joint opening is 1 inch or wider, such as where trimmed 29 spigots are required, apply a bonding agent to mortar and steel surface prior to 30 placing joint mortar. 31 d. Ram or pack the stiff mortar into the joint space and take extreme care to ensure 32 that no voids remain. 33 e. After the joint has been filled, level the surfaces of the joint mortar with the 34 interior surfaces of the pipe with a steel trowel so that the surface is smooth. 35 5. Protective Welded Joints Coating System – Weld After Backfill 36 a. General 37 1) Apply protective coating at the pipe joints as follows: 38 a) Apply a 3-layer joint coating system consisting of a factory applied 39 polyurethane coating with a DFT in accordance with this Section. 40 b) A field applied 60-mil by 6 inch wide strip of CANUSA HCO Wrapid 41 Tape heat resistant tape at the location of the welding 42 c) A field applied 110-mil (full recovered thickness) by 18 inch wide 43 CANUSA AquaWrap high shrink heat shrinkable joint sleeve 44 d) After the heat shrinkable joint sleeve is installed, backfill the trench and 45 weld the joint. 46 2) The Contractor is responsible for his operations so they do not damage the 47 factory applied coating system. 48 33 14 13 BURIED STEEL PIPE Page 23 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3) When applying the 3-layer joint coating system for post welding the joints, 1 the Contractor must show that his operation will not damage the joint 2 coating system to the City’s satisfaction. 3 4) The Contractor will be required to fully uncover a maximum of 10 joints, 4 selected at random by the City to visually inspect and test the joint after 5 welding. Any damage must be repaired. 6 a) If the Contractor’s welding procedure damages the 3-layer joint coating 7 system, the Contractor, at the direction of the City, will be required to 8 modify his welding procedure. 9 b. Joint Coating (3 Layer) 10 1) Apply 3-Layer Joint Coating System before welding the joint 11 2) Pipe Manufacturing and Heat Tape 12 a) Polyurethane coating shall be applied over entire length of pipe with 13 thickness in accordance with Article this Section. 14 b) The Contractor shall field apply 60-mil thick by 6 inch wide strip of 15 CANUSA HCO Wrapid Tape heat resistant tape to the exterior bell end 16 of the pipe, centered on the location of the welding, over factory 17 applied polyurethane coating. 18 3) Surface Preparation and Installation for Heat Shrinkable Joint Sleeve 19 a) Clean pipe surface and adjacent coating of all mud, oil, grease, rust, 20 and other foreign contaminates with a wire brush in accordance with 21 SSPC SP 2 or SSPC SP 3. Remove oil or grease contamination by 22 solvent wiping the pipe and adjacent coating in accordance with SSPC 23 SP 1. 24 (1) Clean the full circumference of the pipe and a minimum of 6 inches 25 onto the existing coating. 26 b) Remove all loose or damaged pipe coating at joint and either repair the 27 coating in accordance with this Section or increase the length of the 28 joint coating, where reasonable and practical. 29 c) Complete joint bonding of pipe joints before application of joint 30 coating. 31 (1) Joint bonds shall be low profile bonds and all gaps and crevices 32 around the bonds shall be filled with mastic sealant. 33 d) Store sleeves in shipping box until use is required. 34 (1) Keep dry and sheltered from exposure to direct sunlight. 35 (2) Store off ground or concrete floors and maintain at a temperature 36 between 60 degrees F and 100 degrees F as recommended by the 37 sleeve manufacturer. 38 e) Metal surface shall be free of all dirt, dust, and flash rusting prior to 39 sleeve application. 40 f) Preheat pipe uniformly to between 140 degrees F and 160 degrees F or 41 as recommended by the sleeve manufacturer. 42 (1) Monitor pipe temperature using a surface temperature gauge, 43 infrared thermometer or color changing crayons. 44 (2) Protect preheated pipe from rain, snow, frost, or moisture with 45 tenting or shields and do not permit the joint to cool. 46 g) Prime joint with specified primer and fill all cracks, crevices, and gaps 47 with mastic filler in accordance with the manufacturer’s 48 recommendations for the full circumference of the pipe. 49 33 14 13 BURIED STEEL PIPE Page 24 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 h) Apply heat shrink sleeve when it is at a minimum temperature or 60 1 degrees F and while maintaining the pipe temperature above the 2 preheat temperature specified. 3 (1) Apply sleeve in accordance with manufacturer’s instructions and 4 center the sleeve over the joint to provide a minimum of 3-inch 5 overlay onto the existing pipe coating. 6 i) Apply heat to the sleeve using either propane fire infrared heaters or 7 wrap around heaters. 8 (1) Hold flame a minimum of 6 inches from the sleeve surface. 9 (2) Periodically roll the coating on the pipe surface. 10 (3) Heat from the center of the sleeve to the outer edge until properly 11 seated, then begin in the opposite direction. 12 (4) Take care not to excessively heat the parent coating. 13 (5) Monitor sleeve for color change, where appropriate, or with 14 appropriate temperature gauges. 15 j) Completed joint sleeve shall be fully bonded to the pipe and existing 16 coating surface, without voids, mastic beading shall be visible along the 17 full circumference of the sleeve, and there shall be no wrinkling or 18 excessive burns on the sleeves. 19 (1) Sleeves which do not meet these requirements shall be removed 20 and the joint recoated as directed by the City. 21 (2) Minor repairs may be repaired using heat shrink sleeve repair kits. 22 k) Allow the sleeve to cool before moving, handling, or backfilling. 23 (1) In hot climates, provide shading from direct sunlight. 24 (2) Water quenching will be allowed only when permitted by the 25 sleeve manufacturer. 26 l) Perform holiday testing using a high voltage holiday tester (operating at 27 100 volts per mil) at each joint after field application of heat shrinkable 28 joint sleeve in accordance with NACE SP0188. 29 (1) If any holidays or cuts are detected, the sleeve shall be repaired 30 using the heat shrink sleeve manufacturer’s recommendation. 31 (2) The damaged area shall be covered with a minimum of 50-mm 32 overlap around the damaged area. 33 E. Protection of Buried Metal 34 1. Coat buried ferrous metal such as bolts and flanges, which cannot be protected with 35 factory or field-applied polyurethane coatings or heat shrink sleeves, with 36 petrolatum tape in accordance with Section 33 14 05 and encase in Controlled Low 37 Strength Material in accordance with Section 03 34 13. 38 3.5 REPAIR 39 A. Repair and Field Touchup of Polyurethane Coating 40 1. For repair and field touch-up of polyurethane coating, apply: 41 a. Lifelast Durashield 210, 310, or 310 JARS, or 42 b. Protec II as manufactured by Futura Coatings. 43 c. Coating manufacturer’s recommendation. 44 2. Holidays 45 a. Remove all traces of oil, grease, dust, dirt, and other debris. 46 b. Roughen area to be patched by sanding with rough grade sandpaper (40 grit). 47 33 14 13 BURIED STEEL PIPE Page 25 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 c. Apply a coat of repair material described above with the same thickness as the 1 factory applied polyurethane in accordance with this Section. 2 d. Work repair material into scratched surface by brushing or rolling in 3 accordance with manufacturer's recommendations. 4 e. Retest for Holiday. 5 3. Field Cuts or Large Damage 6 a. If in the opinion of the City the polyurethane coating is excessively damaged, 7 the pipe segment will be rejected until the coating system is removed and 8 replaced so that the system is in a like-new condition. 9 b. Remove burrs from field cut ends or handling damage and smooth out edge of 10 polyurethane coating. 11 c. Remove all traces of oil, grease, dust, dirt, and other debris. 12 d. Roughen area to be patched with rough grade sandpaper (40 grit). 13 e. Feather edges and include overlap of 2 inches of roughened polyurethane in 14 area to be patched. 15 f. Apply a coat of repair material described above with the same thickness as the 16 factory applied polyurethane as indicated in this Section, in accordance with 17 manufacturer's recommendations. 18 g. Work repair material into scratched surface by brushing. 19 h. Feather edges of repair material into prepared surface. 20 i. Cover at least 1 inch of roughed area surrounding damage or adjacent to field 21 cut. 22 j. Test repairs for holidays. 23 B. Patch of Cement Mortar Lining 24 1. Repair cracks larger than 1/16 inch. 25 2. Pipes with dis-bonded linings will be rejected. 26 3. Excessive patching of lining shall not be permitted. 27 4. Repair in accordance with AWWA C205 and as follows: 28 a. Apply bonding agent to patch area. 29 b. Patching of lining shall be allowed where area to be repaired does not exceed 30 100 square inches and has no dimension greater than 12 inches. 31 c. In general, there shall be not more than 1 patch in the lining of any joint of 32 pipe. 33 5. Wherever necessary to patch the pipe, make the patch with the mortar indicated. 34 6. Do not install patched pipe until the patch has been properly and adequately cured, 35 unless approved by the City. 36 3.6 RE-INSTALLATION [NOT USED] 37 3.7 FIELD QUALITY CONTROL 38 A. Daily Records 39 1. Submit daily welding reports for field welding showing welder and joint welded 40 monthly. Include the following at a minimum: 41 a. Welder’s name 42 b. Joint welded 43 1) Joint identification number assigned to match lay drawings 44 2) Pipe Station 45 33 14 13 BURIED STEEL PIPE Page 26 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 3) Observations made 1 B. Field Tests and Inspections 2 1. Quality Control of Field Applied Polyurethane Coating 3 a. Surface Preparation 4 1) Visually inspect surface preparation to ensure cleanliness and dryness 5 requirements have been met. 6 2) Use Testex tape on at least 1 joint per day to ensure that adequate profile is 7 being achieved. 8 b. Visual 9 1) Visually inspect cured coating to ensure that the coating is completely 10 cured with no blisters, cracks, pinholes, missed areas, excessive roughness, 11 "sticky", or "gooey" areas. 12 2) Check to ensure that the coating completely covers the steel and existing 13 coating. 14 c. Thickness 15 1) Use a magnetic dry film thickness (DFT) gauge on cured coating to ensure 16 adequate thickness has been achieved according to SSPC PA 2. 17 a) If the thickness of the coating is below the minimum specified millage 18 anywhere along the length of the pipe, adjustments must be made to the 19 spray system to correct the problem. 20 2) At a minimum, the thickness shall be measured for every 50 square feet of 21 sprayed area. 22 d. Adhesion 23 1) Perform the following procedure on a minimum of 1 joint per day: 24 a) Select area to test that has cured for at least 1 hour for fast setting 25 coatings. 26 b) Test and repair in accordance with AWWA C222 Dolly Pull-off Test. 27 e. Holiday Testing 28 1) Perform in accordance with NACE SP0188. 29 2) Holiday test using a high voltage holiday tester at each joint no sooner than 30 1 hour after field application of polyurethane coating. 31 f. Inspection at Welding Joints 32 1) When applying the 3-layer joint coating system for post welding the joints, 33 the Contractor must show that his operation will not damage the joint 34 coating system to the City's satisfaction. 35 2) The Contractor will be required to fully uncover a maximum of 10 joints, 36 selected at random by the City or City to visually inspect and test the joint 37 after welding. 38 3) Any damage must be repaired. 39 4) If the Contractor's welding procedure damages the 3-layer joint coating 40 system, the Contractor, at the direction of the City, will be required to 41 modify his welding procedure. 42 2. Weld Testing 43 a. Dye penetrant tests in accordance with ASTM E165 or magnetic particle test in 44 accordance with AWWA C206 and set forth in AWS D.1.1. shall be performed 45 by the Contractor under the supervision and inspection of the City’s 46 Representative or an independent testing laboratory on all full welded joints. 47 33 14 13 BURIED STEEL PIPE Page 27 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1) Welds that are defective will be replaced or repaired, whichever is deemed 1 necessary by the City, at the Contractor's expense. 2 2) If the Contractor disagrees with the City's interpretation of welding tests, 3 test sections may be cut from the joint for physical testing. The Contractor 4 shall bear the expense of repairing the joint, regardless of the results of 5 physical testing. 6 3) The procedure for repairing the joint shall be approved by the City before 7 proceeding. 8 b. City may reject any areas not meeting the deflection requirements of this 9 Specification. 10 3. Hydrostatic testing of water mains: 11 a. Hydrostatically test the mains in accordance with Section 33 01 10. 12 C. Manufacturer’s Technician for Pipe Installation 13 1. Pipe Manufacturer’s Representative 14 a. If required by the City or requested by the Contractor during construction, the 15 pipe manufacturer shall furnish the services of a factory trained, qualified, job 16 experienced technician to advise and instruct as necessary in pipe laying and 17 pipe jointing. 18 1) The technician shall assist and advise the Contractor in his pipe laying 19 operations and shall instruct construction personnel in proper joint 20 assembly and joint inspection procedures. 21 2) The technician is not required to be on-site full time. 22 3) The technician shall be regularly on-site during the first 2 weeks of pipe 23 laying and thereafter as requested by the City or Contractor. 24 2. Polyurethane Coating Manufacturer’s Representative 25 a. The pipe manufacturer shall provide services of polyurethane coating 26 manufacturer's representative and a representative from the heat shrink joint 27 manufacturer for a period of not less than 3 days at beginning of actual pipe 28 laying operations to advise Contractor and City regarding installation, including 29 but not limited to: 30 1) Handling and storage 31 2) Cleaning and inspecting 32 3) Coating repairs 33 4) Field applied coating 34 5) Heat shrink installation procedures 35 6) General construction methods and how they may affect pipe coating 36 b. Representative shall be required to return if, in the opinion of the City, the 37 polyurethane coating or the Contractor's construction methods do not comply 38 with Contract Specifications. 39 1) Cost for the manufacturer’s representatives to return to the site shall be at 40 no additional cost to the City. 41 3.8 SYSTEM STARTUP [NOT USED] 42 3.9 ADJUSTING [NOT USED] 43 3.10 CLEANING 44 A. Cleaning, disinfection, and bacteriological testing of water mains: 45 33 14 13 BURIED STEEL PIPE Page 28 of 28 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1. Clean, flush, pig, disinfect, and bacteriological test the mains in accordance with 1 Section 33 01 10. 2 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3 3.12 PROTECTION [NOT USED] 4 3.13 MAINTENANCE [NOT USED] 5 3.14 ATTACHMENTS [NOT USED] 6 END OF SECTION 7 8 Revision Log DATE NAME SUMMARY OF CHANGE 9 33 31 10 FIBERGLASS REINFORCED PIPE FOR GRAVITY SANITARY SEWERS Page 1 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 SECTION 33 31 10 1 FIBERGLASS REINFORCED PIPE FOR GRAVITY SANITARY SEWERS 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Fiberglass Reinforced Pipe 18-inch and larger for gravity sanitary sewer 6 applications. 7 B. Deviations from this City of Denton Standard Specification: 8 1. None. 9 C. Related Specification Sections include but are not limited to: 10 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 11 Contract. 12 2. Division 1 - General Requirements. 13 3. Section 33 01 30 – Closed Circuit Television (CCTV) Inspection. 14 4. Section 33 01 31 – Sewer and Manhole Testing. 15 5. Section 33 01 32 – Cleaning of Sewer Mains. 16 6. Section 33 05 05 – Utility Trench Excavation, Embedment, and Backfill. 17 7. Section 33 05 15 – Installation of Carrier Pipe in Casing or Tunnel Liner Plate. 18 8. Section 33 05 97 – Utility Markers/Locators. 19 9. Section 33 31 16 – Sanitary Sewer Service Connections and Service Line. 20 1.2 PRICE AND PAYMENT PROCEDURES 21 A. Measurement and Payment 22 1. Fiberglass Reinforced Pipe 23 a. Measurement 24 1) Measured horizontally along the surface from center line to center line of 25 the manhole or appurtenance. 26 b. Payment 27 1) The work performed and materials furnished in accordance with this item 28 and measured as provided under “Measurement” will be paid for at the unit 29 price bid per linear foot for “Fiberglass Reinforced Pipe” installed for: 30 a) Various sizes. 31 b) Various types of backfill. 32 c. The price bid shall include: 33 1) Furnishing and installing Fiberglass Sewer Pipe as specified by the 34 Drawings 35 2) Utility Markers/Locators 36 3) Pavement Removal 37 4) Excavation 38 5) Hauling 39 33 31 10 FIBERGLASS REINFORCED PIPE FOR GRAVITY SANITARY SEWERS Page 2 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 6) Disposal of excess material 1 7) Furnishing, placement, and compaction of embedment 2 8) Furnishing, placement, and compaction of backfill 3 9) Trench Dams 4 10) Fittings 5 11) Gaskets 6 12) Clean-up 7 13) Cleaning 8 14) Testing 9 1.3 REFERENCES 10 A. Abbreviations and Acronyms 11 1. FRP – Fiberglass Reinforced Pipe 12 B. Reference Standards 13 1. Reference standards cited in this Section refer to the current reference standard 14 published at the time of the latest revision date logged at the end of this Section 15 unless a date is specifically cited. 16 2. ASTM International (ASTM): 17 a. D3236, Standard Test Method for Apparent Viscosity of Hot Melt Adhesives 18 and Coating Materials. 19 b. D3262, Standard Specification for “Fiberglass” (Glass-Fiber-Reinforced 20 Thermosetting-Resin) Sewer Pipe. 21 c. D3681, Standard Test Method for Chemical Resistance of "Fiberglass" (Glass-22 Fiber-Reinforced Thermosetting-Resin) Pipe in a Deflected Condition. 23 d. D3839, Standard Guide for Underground Installation of “Fiberglass” (Glass-24 Fiber-Reinforced Thermosetting-Resin) Pipe and Fittings. 25 e. D4161, Standard Specification for “Fiberglass” (Glass-Fiber-Reinforced 26 Thermosetting-Resin) Pipe Joints Using Flexible Elastomeric Seals. 27 f. F477, Standard Specification for Elastomeric Seals (Gaskets) for Joining Plastic 28 Pipe. 29 3. American Water Works Association (AWWA): 30 a. M45, Fiberglass Pipe Design. 31 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 32 1.5 SUBMITTALS 33 A. Submittals shall be in accordance with Section 01 33 00. 34 B. All submittals shall be approved by the City prior to delivery. 35 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 36 A. Product Data 37 1. Manufacturer 38 2. Manufacturer Number (identifies factory, location, and date manufactured.) 39 3. Nominal Diameter 40 4. Beam load 41 5. Laying lengths 42 33 31 10 FIBERGLASS REINFORCED PIPE FOR GRAVITY SANITARY SEWERS Page 3 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 6. ASTM designation 1 B. Shop Drawings 2 1. For Fiberglass Reinforced Pipe 24-inch diameter and larger: 3 a. Pipe details 4 b. Joint details 5 c. Miscellaneous items to be furnished and fabricated for the pipe 6 d. Dimensions 7 e. Tolerances 8 f. Wall thickness 9 g. Properties and strengths 10 h. Pipe calculations 11 1) Calculations confirming the pipe will handle anticipated loading signed and 12 sealed by a Professional Engineer Licensed in Texas. 13 C. Certificates 14 1. Furnish an affidavit certifying Fiberglass Reinforced Pipe has been tested and is in 15 accordance with this Section and ASTM D3262. 16 1.7 CLOSEOUT SUBMITTALS [NOT USED] 17 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 18 1.9 QUALITY ASSURANCE 19 A. Qualifications 20 1. Manufacturers 21 a. Finished pipe shall be the product of 1 manufacturer for each size per project. 22 b. Pipe manufacturing operations shall be performed under the control of the 23 manufacturer. 24 c. All pipe furnished shall be in accordance with this Section and ASTM D3262. 25 1.10 DELIVERY, STORAGE, AND HANDLING 26 A. Delivery 27 1. Provide adequate strutting during transport to prevent damage to the pipe, fittings, 28 and appurtenances. 29 B. Storage and Handling Requirements 30 1. Gravity pipe shall be stored and handled in accordance with the manufacturer’s 31 guidelines. 32 2. Secure and maintain a location to store the material in accordance with 33 Section 01 66 00. 34 33 31 10 FIBERGLASS REINFORCED PIPE FOR GRAVITY SANITARY SEWERS Page 4 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 1.11 FIELD CONDITIONS [NOT USED] 1 1.12 WARRANTY [NOT USED] 2 PART 2 - PRODUCTS 3 2.1 CITY-FURNISHED PRODUCTS [NOT USED] 4 5 2.2 MATERIALS 6 A. Manufacturers 7 1. Manufacturer List 8 a. HOBAS Pipe 9 b. Flowtite 10 2. Substitution requests for manufacturers or models not indicated above shall be 11 processed in accordance with Section 01 25 00. 12 B. Performance / Design Criteria 13 1. Pipe 14 a. Fiberglass pipe shall be designed, manufactured, and tested in accordance with 15 ASTM D3262 and AWWA M45. 16 b. Design pipe for service loads that include: 17 1) External groundwater and earth loads 18 2) Jacking/pushing loads 19 a) The allowable jacking/pushing capacity shall not exceed 40 percent of 20 the ultimate compressive strength or the maximum allowable 21 compressive strength recommended by the manufacturer, whichever is 22 less. 23 3) Traffic loads 24 4) Practical considerations for handling, shipping, and other construction 25 operations 26 c. Pipe design shall be based on trench conditions in accordance with AWWA 27 M45 using the following parameters: 28 1) Unit Weight of Fill (W) = 130 pounds per cubic foot 29 2) Live Load: 30 a) Cooper E-80 for railroad crossings 31 b) AASHTO HS-20 for all other installations 32 3) Trench Depth = As indicated on the Drawings 33 4) Deflection Lag Factor (Dl) = 1.0 34 5) Bedding Coefficient (Kx) = 0.10 35 6) Maximum Calculated Deflection: 36 a) Delta x = 3 Percent 37 7) Soil Reaction Modulus (E'): less than or equal to 1,000 psi 38 d. Where the pipe requires additional external support to achieve the specified 39 maximum deflection, the Contractor and pipe supplier will be required to 40 furnish alternate methods for pipe embedment. 41 1) No additional compensation will be made to the Contractor by the Owner 42 where this method is required. 43 33 31 10 FIBERGLASS REINFORCED PIPE FOR GRAVITY SANITARY SEWERS Page 5 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 e. Designed under the supervision of a Professional Engineer licensed in the State 1 of Texas, who shall seal and sign the design. 2 f. Standard lay length of 20 feet, except for special fittings or closure pieces 3 necessary to comply with the Drawings. 4 g. Drawings or deflection design may require a higher pipe stiffness, but in no 5 case should the pipe stiffness be less than 46 psi. 6 h. Accommodate vertical alignment changes required because of existing utility or 7 other conflicts by an appropriate change in pipe design depth. 8 i. In no case shall pipe be installed deeper than its design allows. 9 10 2. Dimensional Tolerances 11 a. Inside diameter 12 1) Maximum 1/8 inch variance from the nominal inside diameter allowed. 13 b. Roundness 14 1) Difference between major and minor outside diameters not to exceed 0.1 15 percent of the nominal outside or ¼ inch, whichever is less. 16 c. Wall thickness 17 1) Provide minimum single point thickness no less than 98 percent of stated 18 design thickness. 19 d. End Squareness 20 1) Provide pipe ends square to pipe axis with maximum tolerance of 1/8 inch. 21 e. Fittings 22 1) Provide tolerance of angle of elbow and angle between main and leg of wye 23 or tee to ±2 degrees. 24 2) Provide tolerance of laying length of fitting to ±2 inches. 25 C. Materials 26 1. Resin Systems 27 a. Only use polyester resin system with proven history of performance in this 28 particular application. 29 2. Glass Reinforcements 30 a. Use reinforcing glass fibers of highest quality commercial grade E-glass 31 filaments with binder and sizing compatible with impregnated resins to 32 manufacture components. 33 3. Fillers 34 a. Silica sand or other suitable materials may be used. 35 b. Use 98 percent silica with maximum moisture content of 0.2 percent. 36 4. Resin Additives 37 a. Not to detrimentally affect the performance of the product. 38 5. Internal liner resin 39 a. Suitable for service as sewer pipe. 40 b. Highly resistant to exposure to sulfuric acid produced by biological activity 41 from hydrogen sulfide gases. 42 c. In accordance with ASTM D3681. 43 6. Gaskets 44 a. Supply from approved gasket manufacturer in accordance with ASTM F477 45 and suitable for service intended. 46 33 31 10 FIBERGLASS REINFORCED PIPE FOR GRAVITY SANITARY SEWERS Page 6 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 b. Affix to pipe by means of suitable adhesive or install in a manner to prevent 1 from rolling out of pre-cut groove in pipe or sleeve coupling. 2 c. Provide the following gaskets in potentially contaminated areas. 3 1) Petroleum (diesel, gasoline) – Viton 4 2) Other contaminants – Manufacturer recommendation 5 7. Couplings 6 a. Field connect pipe with fiberglass sleeve couplings manufactured by the pipe 7 manufacturer that utilize elastomeric sealing gaskets as sole means to maintain 8 joint water tightness. 9 b. For connection to non-FRP gravity sewer pipe, utilize Straub Flex Coupling or 10 Smith-Blair Repair Clamp 228. 11 12 8. Joints 13 a. In accordance with ASTM D4161 14 9. Pipe markings in accordance with ASTM D3236. Minimum pipe markings shall 15 be as follows: 16 a. Manufacturer 17 b. Manufacturer Number (identifies factory, location, date manufactured, shift, 18 and sequence) 19 c. Nominal diameter 20 d. Beam load 21 e. Laying length 22 f. ASTM designation 23 10. Connections 24 11. Use only manufactured fittings in accordance with Section 33 31 16 25 12. Detectable Metallic Tape in accordance with Section 33 05 97. 26 2.3 ACCESSORIES [NOT USED] 27 2.4 SOURCE QUALITY CONTROL [NOT USED] 28 PART 3 - EXECUTION 29 3.1 INSTALLERS [NOT USED] 30 3.2 EXAMINATION [NOT USED] 31 3.3 PREPARATION [NOT USED] 32 3.4 INSTALLATION 33 A. General 34 1. Install pipe, fittings, specials, and appurtenances in accordance with this Section, 35 AWWA M45, ASTM D3839, and with the pipe manufacturer’s recommendations. 36 2. Lay pipe to the lines and grades as indicated in the Drawings. 37 3. Excavate and backfill trenches in accordance with Section 33 05 05. 38 4. Embed pipe in accordance with Section 33 05 05. 39 5. Installation of carrier pipe within casing in accordance with Section 33 05 15. 40 33 31 10 FIBERGLASS REINFORCED PIPE FOR GRAVITY SANITARY SEWERS Page 7 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 B. Pipe Handling 1 1. Haul and distribute pipe and fittings at the project site. 2 2. Handle pipe with care to avoid damage. 3 a. Inspect each joint of pipe and reject or repair any damaged pipe prior to 4 lowering into the trench. 5 b. Use only nylon ropes, slings, or other lifting devices that will not damage the 6 surface of the pipe for handling pipe. 7 3. At the close of each operating day: 8 a. Keep the pipe clean and free of debris, dirt, animals, and trash – during and 9 after the laying operation. 10 b. Effectively seal the open end of the pipe using a gasketed night cap. 11 12 C. Pipe Jointing 13 a. Clean dirt and foreign material from the gasketed socket and the spigot end. 14 b. Assemble pipe joint by sliding the lubricated spigot end into the gasketed bell 15 end to the reference mark. 16 c. Install such that identification marking on each joint are oriented upward toward 17 the trench opening. 18 d. When making connection to manhole, use an elastomeric seal or flexible boot to 19 facilitate a seal. 20 D. Connection Installation in accordance with Section 33 31 16. 21 E. Detectable Metallic Tape Installation in accordance with Section 33 05 97. 22 3.5 REPAIR 23 A. Repair in accordance with manufacturer’s recommendations. 24 3.6 RE-INSTALLATION [NOT USED] 25 3.7 FIELD QUALITY CONTROL 26 A. Gravity Sewer Mains 27 1. Closed Circuit Television (CCTV) Inspection 28 a. Provide a Post-CCTV Inspection in accordance with Section 33 01 30. 29 2. Sewer Pipe Testing 30 a. Test pipe in accordance with Section 33 01 31. 31 3.8 SYSTEM STARTUP [NOT USED] 32 3.9 ADJUSTING [NOT USED] 33 3.10 CLEANING 34 A. Gravity Sewer Mains 35 1. Cleaning of sewer mains 36 a. Clean the mains in accordance with Section 33 01 32. 37 33 31 10 FIBERGLASS REINFORCED PIPE FOR GRAVITY SANITARY SEWERS Page 8 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised December 27, 2022 Effective July 1, 2024 3.11 CLOSEOUT ACTIVITIES [NOT USED] 1 3.12 PROTECTION [NOT USED] 2 3.13 MAINTENANCE [NOT USED] 3 3.14 ATTACHMENTS [NOT USED] 4 5 END OF SECTION 6 7 Revision Log DATE NAME SUMMARY OF CHANGE 8 33 31 14 POLYVINYL CHLORIDE (PVC) GRAVITY SANITARY SEWER PIPE Page 1 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised July 1, 2024 Effective July 1, 2024 SECTION 33 31 14 1 POLYVINYL CHLORIDE (PVC) GRAVITY SANITARY SEWER PIPE 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Polyvinyl Chloride (PVC) pipe 4-inch through 6-inch for gravity sanitary sewer 6 services. 7 2. Polyvinyl Chloride (PVC) pipe 8-inch through 24-inch for gravity sanitary sewer 8 main applications. 9 B. Deviations from this City of Denton Standard Specification: 10 1. None. 11 C. Related Specification Sections include but are not limited to: 12 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 13 Contract. 14 2. Division 1 - General Requirements. 15 3. Section 33 01 30 – Closed Circuit Television (CCTV) Inspection. 16 4. Section 33 01 31 – Sewer and Manhole Testing. 17 5. Section 33 01 32 – Cleaning of Sewer Mains. 18 6. Section 33 05 05 – Utility Trench Excavation, Embedment, and Backfill. 19 7. Section 33 05 97 – Utility Markers/Locators. 20 8. Section 33 31 16 – Sanitary Sewer Service Connections and Service Line. 21 1.2 PRICE AND PAYMENT PROCEDURES 22 A. Measurement and Payment 23 1. PVC Gravity Sewer Pipe 24 a. Measurement 25 1) Measured horizontally along the surface from center line to center line of 26 the manhole, or appurtenance. 27 b. Payment 28 1) The work performed and materials furnished in accordance with this item 29 and measured as provided under “Measurement” will be paid for at the unit 30 price bid per linear foot for “PVC Gravity Sewer Pipe” installed for: 31 a) Various sizes. 32 b) Various backfills. 33 c. The price bid shall include: 34 1) Furnishing and installing PVC Gravity Sewer Pipe with joints as specified 35 by the Drawings 36 2) Furnishing and installing couplings 37 3) Utility Markers/Locators 38 4) Pavement removal 39 33 31 14 POLYVINYL CHLORIDE (PVC) GRAVITY SANITARY SEWER PIPE Page 2 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised July 1, 2024 Effective July 1, 2024 5) Excavation 1 6) Hauling 2 7) Disposal of excess material 3 8) Furnishing, placement, and compaction of embedment 4 9) Furnishing, placement, and compaction of backfill 5 10) Trench Dams 6 11) Gaskets 7 12) Clean-up 8 13) Cleaning 9 14) Testing 10 1.3 REFERENCES 11 A. Abbreviations and Acronyms 12 1. PVC – Polyvinyl Chloride 13 B. Reference Standards 14 1. Reference standards cited in this Section refer to the current reference standard 15 published at the time of the latest revision date logged at the end of this Section, 16 unless a date is specifically cited. 17 2. American Association of State Highway and Transportation (AASHTO). 18 3. ASTM International (ASTM): 19 a. D1784, Standard Specification for Rigid Poly(Vinyl Chloride) (PVC) 20 Compounds and Chlorinated Poly(Vinyl Chloride) (CPVC) Compounds. 21 b. D2412, Standard Test Method for Determination of External Loading 22 Characteristics of Plastic Pipe by Parallel-Plate Loading. 23 c. D3034, Standard Specification for Type PSM Poly(Vinyl Chloride) (PVC) 24 Sewer Pipe and Fittings. 25 d. D3212, Standard Specification for Joints for Drain and Sewer Plastic Pipes 26 Using Flexible Elastomeric Seals. 27 e. F679, Standard Specification for Poly (Vinyl Chloride) (PVC) Large-Diameter 28 Plastic Gravity Sewer Pipe and Fittings. 29 4. Texas Administration Code: 30 a. Chapter 217, (30 TAC §217), Design Criteria for Sewerage System. 31 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 32 1.5 SUBMITTALS 33 A. Submittals shall be in accordance with Section 01 33 00. 34 B. All submittals shall be approved by the City prior to delivery. 35 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 36 A. Product Data 37 1. Product data sheet 38 2. Manufacturer 39 3. Nominal pipe diameter 40 4. Standard dimension ratio (SDR) 41 33 31 14 POLYVINYL CHLORIDE (PVC) GRAVITY SANITARY SEWER PIPE Page 3 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised July 1, 2024 Effective July 1, 2024 5. Cell classification 1 6. Laying lengths 2 B. Certificates 3 1. Furnish an affidavit certifying the PVC Gravity and Pressure Rated Gravity Sewer 4 Pipe has been air and deflection tested and is in accordance with this Section and 5 ASTM D3034, ASTM F679. 6 1.7 CLOSEOUT SUBMITTALS [NOT USED] 7 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 8 1.9 QUALITY ASSURANCE 9 A. Qualifications 10 1. Manufacturers 11 a. Finished pipe shall be the product of 1 manufacturer for each size per project, 12 unless otherwise approved by the City. 13 1) Change orders, specials, and field changes may be provided by a different 14 manufacturer upon City approval. 15 b. Pipe manufacturing operations shall be performed under the control of the 16 manufacturer. 17 c. Furnish Gravity Sewer Pipe in accordance with ASTM D3034 (4-inch through 18 15-inch) and ASTM F679 (18-inch through 27-inch). 19 1.10 DELIVERY, STORAGE, AND HANDLING 20 A. Delivery and Acceptance Requirements 21 1. Pipe manufactured more than 2 years prior to installation date will not be accepted 22 by the City. 23 B. Storage and Handling Requirements 24 1. Gravity pipe shall be stored and handled in accordance with the manufacturer’s 25 guidelines. 26 2. Protect pipe from UV exposure. 27 a. When long-term storage (more than 2-months) with exposure to direct sunlight 28 is unavoidable, cover PVC pipe with an opaque material and provide adequate 29 air circulation above and around the pipe as required to prevent excessive heat 30 accumulation. 31 3. Secure and maintain a location to store the material in accordance with Section 01 32 66 00. 33 33 31 14 POLYVINYL CHLORIDE (PVC) GRAVITY SANITARY SEWER PIPE Page 4 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised July 1, 2024 Effective July 1, 2024 1.11 FIELD CONDITIONS [NOT USED] 1 1.12 WARRANTY [NOT USED] 2 PART 2 - PRODUCTS 3 2.1 CITY-FURNISHED PRODUCTS [NOT USED] 4 2.2 MATERIALS 5 A. Manufacturers 6 1. Manufacturer List (Pipe) 7 a. 4-inch through 15-inch (ASTM D3034) 8 1) Diamond Plastics 9 2) JM Eagle/Ring-Tite 10 3) Northern Pipe Products 11 4) Westlake Pipe & Fittings 12 5) Vinyltech 13 b. 18-inch through 24-inch (ASTM F679) 14 1) Diamond Plastics 15 2) JM Eagle 16 3) Westlake Pipe & Fittings 17 2. Manufacturer List (Couplings) 18 a. 4-inch through 12-inch 19 1) GPK 20 2) HARCO 21 3) Multi Fittings 22 4) Westlake Pipe & Fittings 23 5) Indiana Seal Shearguard™ Coupling Kit 24 b. 15-inch through 24-inch 25 1) GPK 26 2) HARCO 27 3) Multi Fittings 28 4) Westlake Pipe & Fittings 29 5) Smith-Blair 228 30 6) Straub Flex Coupling 31 3. Substitution requests for manufacturers or models not indicated above shall be 32 processed in accordance with Section 01 25 00. 33 34 B. Performance / Design Criteria 35 1. Pipe 36 a. Designed in accordance with 30 TAC §217. 37 b. Design in accordance with ASTM D3034 for 4-inch through 15-inch gravity 38 pipe, ASTM F679 for 18-inch through 24-inch gravity pipe. 39 c. PVC Gravity Sanitary Sewer Pipe shall be approved by the Underwriters 40 Laboratories, Inc. 41 d. Assume a standard lay length of 14 feet and 20 feet except for special fittings or 42 closure pieces necessary to comply with the Drawings. 43 33 31 14 POLYVINYL CHLORIDE (PVC) GRAVITY SANITARY SEWER PIPE Page 5 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised July 1, 2024 Effective July 1, 2024 e. PVC in accordance with ASTM D1784, with a cell classification of 12454 or 1 12364. 2 f. The following Standard Dimension Ratio’s apply: 3 4 Application Diameter (inch) Min Performance Designation Sewer Service 4 through 6 SDR 26/PS115 Gravity Sewer Main 8 through 24 SDR 26/PS115 5 g. Deflection Design 6 1) Base pipe design on pipe stiffness, soil stiffness, and load on the pipe. 7 2) Design pipe according to the Modified Iowa Formula as detailed by the 8 Uni-Bell PVC Pipe Association in the Handbook of PVC Pipe, using the 9 following parameters: 10 a) Unit Weight of Fill (w) = 130 pounds per cubic foot 11 b) Live Load = AASHTO HS 20 12 c) Trench Depth = 12 feet minimum, or as indicated in Drawings 13 d) Maximum (E’) = 1,000 max 14 e) Deflection Lag Factor (DL) = 1.0 15 f) Bedding Factor constant (K) = 0.1 16 g) Mean radius of the pipe (r), inches, as indicated in Drawings 17 h) Marston’s load per unit length (W), pounds per inch, calculate per 18 Drawings 19 i) PVC modulus of elasticity (E) = 400,000 psi 20 j) Moment of inertia of pipe wall per unit length, (I) = t3/12, (in4/in), per 21 pipe type and size 22 (1) Where (t) = pipe thickness, inches 23 k) Maximum Calculated Deflection = 5 percent 24 25 h. Pipe Flotation: If the pipe is buried in common saturated soil (about 120 pounds 26 per cubic foot) with at least 1½ pipe diameters of cover, pipe is generally not 27 subject to flotation. If shallower, check groundwater flotation potential. 28 Flotation will occur if: 29 30 Fb > Wp + Wf + Wd 31 32 Where: Fb = buoyant force, pound per foot 33 Wp = empty pipe weight, pound per foot 34 Wf = weight of flooded soil, pound per foot 35 Wd = weight of dry soil, pound per foot 36 37 Values and formulas for the above variables can be obtained from the pipe 38 manufacturer and site-specific soil conditions. 39 i. Verify trench depths after existing utilities are located. 40 j. If vertical alignment changes due to an existing utility or other conflict, verify 41 whether change in required pipe design stiffness is required. 42 k. In no case shall pipe be installed deeper than its design allows. 43 2. Pipe markings 44 33 31 14 POLYVINYL CHLORIDE (PVC) GRAVITY SANITARY SEWER PIPE Page 6 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised July 1, 2024 Effective July 1, 2024 a. In accordance with ASTM D3034 and ASTM F679. 1 b. Minimum pipe markings shall be as follows: 2 1) Manufacturer’s Name or Trademark and production record 3 2) Nominal pipe size 4 3) PVC cell classification 5 4) ASTM or Standard Dimension Ratio (SDR) designation or pipe stiffness 6 5) Seal of testing agency that verified the suitability of the pipe 7 3. Color 8 a. Pipe shall be green in color. 9 1) Any discoloration in the pipe shall be sufficient cause for rejection. 10 b. Fittings shall be green or white in color. 11 4. Joints 12 a. Joints shall be gasket, bell and spigot, push-on type in accordance with 13 ASTM D3212. 14 b. Since each pipe manufacturer has a different design for push-on joints; gaskets 15 shall be part of a complete pipe section and purchased as such. 16 5. Couplings 17 a. Only couplings with a rigid housing shall be allowed. Flexible pipe couplings 18 are not allowed to join pipe. 19 6. Connections 20 a. Only use manufactured fittings. 21 b. In accordance with Section 33 31 16 22 7. Detectable Metallic Tape 23 a. In accordance with Section 33 05 97 24 2.3 ACCESSORIES [NOT USED] 25 2.4 SOURCE QUALITY CONTROL 26 A. Test pipe in accordance with ASTM D2412 assuming minimum pipe stiffness of 46 psi 27 at 5 percent deflection. 28 PART 3 - EXECUTION 29 3.1 INSTALLERS [NOT USED] 30 3.2 EXAMINATION [NOT USED] 31 3.3 PREPARATION [NOT USED] 32 3.4 INSTALLATION 33 A. General 34 1. Install pipe, specials, and appurtenances in accordance with this Section, Section 33 35 05 05, and the pipe manufacturer’s recommendations. 36 2. Lay pipe to the lines and grades as indicated in the Drawings. 37 3. Excavate and backfill trenches in accordance with Section 33 05 05. 38 4. Embed PVC pipe in accordance with Section 33 05 05. 39 33 31 14 POLYVINYL CHLORIDE (PVC) GRAVITY SANITARY SEWER PIPE Page 7 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised July 1, 2024 Effective July 1, 2024 B. Pipe Handling 1 1. Haul and distribute pipe and fittings at the project site. 2 2. Handle piping with care to avoid damage. 3 a. Inspect each joint of pipe and reject or repair any damaged pipe prior to 4 lowering into the trench. 5 b. Use only nylon ropes, slings, or other lifting devices that will not damage the 6 surface of the pipe for handling the pipe. 7 3. At the close of each operating day: 8 a. Keep the pipe clean and free of debris, dirt, animals, and trash – during and after 9 the laying operation. 10 b. Effectively seal the open end of the pipe using a gasketed night cap. 11 C. Pipe Joint Installation 12 a. Clean dirt and foreign material from the gasketed socket and the spigot end. 13 b. Assemble pipe joint by sliding the lubricated spigot end into the gasketed bell 14 end to the reference mark. 15 c. Install such that identification marking on each joint are oriented upward toward 16 the trench opening. 17 d. When making plain end to plain end connections install the approved 18 manufactured coupling in accordance with the manufacturer’s guidelines . 19 D. Connection Installation 20 1. In accordance with Section 33 31 16. 21 E. Detectable Metallic Tape Installation 22 1. In accordance with Section 33 05 97. 23 3.5 REPAIR [NOT USED] 24 3.6 RE-INSTALLATION [NOT USED] 25 26 3.7 FIELD QUALITY CONTROL 27 A. Gravity Sewer Mains 28 1. Closed Circuit Television (CCTV) Inspection 29 a. Provide a Post-CCTV Inspection in accordance with Section 33 01 30. 30 2. Sewer Pipe Testing 31 a. Test pipe in accordance with Section 33 01 31. 32 3.8 SYSTEM STARTUP [NOT USED] 33 3.9 ADJUSTING [NOT USED] 34 3.10 CLEANING 35 A. Gravity Sewer Mains 36 1. Cleaning of sewer mains 37 a. Clean the mains in accordance with Section 33 01 32. 38 33 31 14 POLYVINYL CHLORIDE (PVC) GRAVITY SANITARY SEWER PIPE Page 8 of 8 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised July 1, 2024 Effective July 1, 2024 3.11 CLOSEOUT ACTIVITIES [NOT USED] 1 3.12 PROTECTION [NOT USED] 2 3.13 MAINTENANCE [NOT USED] 3 3.14 ATTACHMENTS [NOT USED] 4 END OF SECTION 5 6 Revision Log DATE NAME SUMMARY OF CHANGE 7/1/2024 Changed allowable SDR to be only SDR-26; 2.2.B.1.f 7 33 32 11 BYPASS PUMPING OF EXISTING SEWER SYSTEMS Page 1 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 SECTION 33 32 11 1 BYPASS PUMPING OF EXISTING SEWER SYSTEMS 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Bypass pumping of the existing sewer system for 15-inch and larger sewer mains, 6 unless otherwise specified in the Contract Documents. 7 B. Deviations from this City of Denton Standard Specification: 8 1. None. 9 C. Related Specification Sections include but are not limited to: 10 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the 11 Contract. 12 2. Division 1 - General Requirements. 13 1.2 PRICE AND PAYMENT PROCEDURES 14 A. Measurement and Payment 15 1. Measurement 16 a. Measurement for this item will be by lump sum. 17 2. Payment 18 a. The work performed and materials furnished in accordance with this item will 19 be paid for at the lump sum price bid for “Bypass Pumping”. 20 3. The price bid shall include: 21 a. Mobilization 22 b. Development of bypass plans 23 c. Transportation and storage 24 d. Setup 25 e. Confined space entry 26 f. Plugging 27 g. Pumping 28 h. Clean up 29 i. Manhole restoration 30 j. Surface restoration 31 1.3 REFERENCES 32 A. Reference Standards 33 1. Reference standards cited in this Section refer to the current reference standard 34 published at the time of the latest revision date logged at the end of this Section 35 unless a date is specifically cited. 36 2. Occupational Safety and Health Organization (OSHA). 37 38 33 32 11 BYPASS PUMPING OF EXISTING SEWER SYSTEMS Page 2 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1.4 ADMINISTRATIVE REQUIREMENTS 1 A. Coordination 2 1. Schedule meeting with City to review sewer shutdown prior to replacing or 3 rehabilitating any facilities. 4 2. City reserves the right to delay schedule due to weather conditions or other 5 unexpected emergency within the sewer system. 6 3. Review bypass pumping arrangement or layout in the field with City prior to 7 beginning operations. Facilitate preliminary bypass pumping run with City staff 8 present to affirm the operation is satisfactory to the City. 9 4. After replacement or rehabilitation of facilities, coordinate the reestablishment of 10 sewer flow with City. 11 5. Provide onsite continuous monitoring during all bypass pumping operations using 12 one of the following methods: 13 a. Personnel on site, or 14 b. Portable SCADA equipment. 15 1.5 SUBMITTALS 16 A. Submittals shall be in accordance with Section 01 33 00. 17 B. All submittals shall be approved by the City prior to delivery. 18 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 19 A. For 15-inch and larger sewer mains, submit a detailed plan and description outlining all 20 provisions and precautions taken with regard to the handling of sewer flows. 21 1. Submit the plan to the City for approval a minimum of 14 days prior to 22 commencing work. Include the following details: 23 a. Schedule for installation and maintenance of the bypass pumping system 24 b. Staging areas for pumps 25 c. Pump sizes, capacity, number of each size, and power requirements 26 d. Calculations for static lift, friction losses, and velocity 27 e. Pump curves showing operating range and system head curves 28 f. Sewer plugging methods 29 g. Size, length, material, joint type, and method for installation of suction and 30 discharge piping 31 h. Method of noise control for each pump and/or generator, if required 32 i. Standby power generator size and location 33 j. Suction and discharge piping plan 34 k. Emergency action plan identifying the measures taken in the event of a pump 35 failure or sewer spill 36 l. Staffing plan for responding to alarm conditions identifying multiple contacts 37 by name and phone numbers (office, mobile) 38 m. A contingency plan to implement in the event the replacement or rehabilitation 39 has unexpected delays or problems 40 1.7 CLOSEOUT SUBMITTALS [NOT USED] 41 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 42 33 32 11 BYPASS PUMPING OF EXISTING SEWER SYSTEMS Page 3 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 1.9 QUALITY ASSURANCE [NOT USED] 1 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 2 1.11 FIELD CONDITIONS [NOT USED] 3 1.12 WARRANTY [NOT USED] 4 PART 2 - PRODUCTS 5 2.1 CITY-FURNISHED PRODUCTS [NOT USED] 6 2.2 EQUIPMENT 7 A. Pumping 8 1. Provide equipment that will convey the following: 9 a. City-provided flow data. 10 1) Full flow capacity of the sewer main, if data is not available 11 a) Calculate using Manning’s equation assuming the following: 12 (1) Roughness coefficient, n = 0.013 13 2. Provide fully automatic self-priming pumps. 14 a. Foot-valves or vacuum pumps are not permitted for priming the system. 15 3. Pumps must be constructed to allow dry running for periods of time to account for 16 the cyclical nature of sewer flow. 17 4. Provide 1 stand-by pump for each size to be maintained on site. Place backup 18 pumps on line, isolated from the primary system by valve. 19 5. If multiple pumps are required to meet the flow requirements, provide the necessary 20 fittings and connections to incorporate multiple discharges. 21 6. Noise levels of the pumping system must follow the more stringent of the 22 requirements below: 23 a. City noise ordinance 24 b. No more the 65dB when measured at a distance of 300-ft from the source. 25 1) The noise level will be the average of sound level meter readings taken 26 consecutively at any given time from 4 or more diametrically opposite 27 positions measured at a distance of 300-ft from the source. 28 c. May be subject to special noise mitigation as required by the City. 29 B. Piping 30 1. Install pipes with joints which prevent the incident of flow spillage. 31 C. Plugs or Stop Logs 32 1. Plugs 33 a. Select a plug made for the size and potential pressure head that will be 34 experienced. 35 b. Provide an additional anchor, support, or bracing to secure plug when back 36 pressure is present. 37 c. Use accurately calibrated air pressure gauges for monitoring the inflation 38 pressure. 39 33 32 11 BYPASS PUMPING OF EXISTING SEWER SYSTEMS Page 4 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 d. Place inflation gauge at location outside of confined space area. Keep the 1 inflation gauge and valve a safe distance from the plugs. 2 e. Never over inflate the plug beyond pressure rating. 3 2.3 ACCESSORIES [NOT USED] 4 2.4 SOURCE QUALITY CONTROL [NOT USED] 5 PART 3 - EXECUTION 6 3.1 INSTALLERS [NOT USED] 7 3.2 EXAMINATION [NOT USED] 8 3.3 PREPARATION 9 A. Locate the bypass pipelines in the area to minimize disturbance to existing utilities. 10 Obtain approval from the City for use of locations. 11 B. Make preparations to comply with OSHA requirements when working in the presence 12 of sewer gases, oxygen-deficient atmospheres, and confined spaces. 13 C. Do not begin bypass preparation and operation until City approval of the submittals 14 requested in accordance with the requirements of this Section. 15 3.4 INSTALLATION 16 A. Install and operate pumping and piping equipment in accordance to the submittals 17 provided in accordance with the requirements of this Section. 18 B. Sewer flow stoppage 19 1. Plugging 20 a. Use confined space procedures and equipment during installation when 21 necessary. 22 b. Thoroughly clean the pipe before insertion of the plug. 23 c. Insert the plug seal surface completely so it is fully supported by the pipe. 24 d. Position the plug where there are not sharp edges or protrusions that may 25 damage the plug. 26 e. Use pressure gauges for measuring inflation pressures. 27 f. Minimize upstream pressure head before deflating and removing. 28 C. Sewer flow control and monitoring 29 1. Take precautions to ensure sewer flow operations do not cause flooding or damage 30 to public or private property. 31 a. The Contractor is responsible for any damage resulting from bypass pumping 32 operations. 33 2. Begin continual monitoring of the sewer system as soon as the sewer is plugged or 34 blocked. Be prepared to immediately start bypass pumping if needed due to 35 surcharge conditions. 36 3. Sewer discharge may be into another sewer manhole, appropriate vehicle, or 37 container only. Do not discharge sewer into an open environment such as an open 38 channel or earthen holding facility. 39 33 32 11 BYPASS PUMPING OF EXISTING SEWER SYSTEMS Page 5 of 5 CITY OF DENTON IFB 8833 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Baker Offsite Sewer Revised October 22, 2020 Effective July 1, 2024 4. Do not construct bypass facilities where vehicular traffic may travel over the 1 piping. 2 a. Provide details in the suction and discharge piping plan that accommodate both 3 the bypass facilities and traffic without disrupting either service. 4 3.5 REPAIR [NOT USED] 5 3.6 RE-INSTALLATION [NOT USED] 6 3.7 FIELD QUALITY CONTROL 7 A. Field Tests and Inspections 8 1. Perform leakage and pressure tests of the bypass pumping pipe and equipment 9 before actual operation begins. Have City on Site during tests. 10 3.8 SYSTEM STARTUP [NOT USED] 11 3.9 ADJUSTING [NOT USED] 12 3.10 CLEANING [NOT USED] 13 3.11 CLOSEOUT ACTIVITIES 14 A. Once plugging or blocking is no longer necessary, remove in such a way that permits 15 the sewer flow to slowly return to normal – preventing surge, surcharging, and major 16 downstream disturbance. 17 3.12 PROTECTION [NOT USED] 18 3.13 MAINTENANCE [NOT USED] 19 3.14 ATTACHMENTS [NOT USED] 20 END OF SECTION 21 22 Revision Log DATE NAME SUMMARY OF CHANGE 23 24