Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
8209PSA
Christina Dormady
Airport Engineering Services Amendment 3
Not Applicable
N/A
JULY 14, 2026
26-1026
8209 Amendment #3 Page 1 of 2
THIRD AMENDMENT TO CONTRACT
BY AND BETWEEN THE CITY OF DENTON, TEXAS
AND GARVER, LLC
PSA 8209
THE STATE OF TEXAS §
COUNTY OF DENTON §
THIS THIRD AMENDMENT TO CONTRACT 8209 (“Amendment”) by and
between the City of Denton, Texas (“City”) and Garver, LLC (“Engineer”); to that certain
contract executed on August 28, 2023, in the original not-to-exceed amount of $15,000
(the “Original Agreement”); amended on February 19, 2025 in the additional amount of
$70,000 aggregating a not-to-exceed amount of $85,000 (the “First Amendment”);
amended on May 7, 2025 in the additional amount of $53,200 aggregating a not-to-exceed
amount of $138,200 (the “Second Amendment”); (collectively, the Original Agreement,
the First Amendment, the Second Amendment, are the “Agreement”) for services related
to the design of the Airport Engineering Services.
WHEREAS, the City deems it necessary to further expand the services provided by
Engineer to the City pursuant to the terms of the Agreement, and to provide an additional
not-to-exceed amount $888,000 with this Amendment for an aggregate not-to-exceed
amount of $1,026,200; and
FURTHERMORE, the City deems it necessary to further expand the goods/services
provided by Engineer to the City;
NOW THEREFORE, the City and Engineer (hereafter collectively referred to as the
“Parties”), in consideration of their mutual promises and covenants, as well as for other
good and valuable considerations, do hereby AGREE to the following Amendment, which
amends the following terms and conditions of the said Agreement, to wit:
1. The additional services described in Attachment “A” of this Amendment, attached
hereto and incorporated herein for all purposes, for professional services related to
the Preliminary Engineering Report (PER) for Taxiway A Reconstruction project,
are hereby authorized to be performed by Engineer. For and in consideration of the
additional services to be performed by Engineer, the City agrees to pay, based on
the cost estimate detail attached as Attachment “A” to this Amendment, a total fee,
including reimbursement for non-labor expenses, an amount not to exceed
$408,000.
2. The additional services described in Attachment “B” of this Amendment, attached
hereto and incorporated herein for all purposes, for professional services related to
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
8209 Amendment #3 Page 2 of 2
the design of Taxiways H, J, and M Reconstruction project, are hereby authorized
to be performed by Engineer. For and in consideration of the additional services to
be performed by Engineer, the City agrees to pay, based on the cost estimate detail
attached as Attachment “B” to this Amendment, a total fee, including
reimbursement for non-labor expenses, an amount not to exceed $480,000.
3. This Amendment modifies the Agreement amount to provide an additional
$888,000 for the additional services, with a revised aggregate not to exceed total of
$1,026,200.
The Parties hereto agree that, except as specifically provided for by this Amendment, that
all of the terms, covenants, conditions, agreements, rights, responsibilities, and obligations
of the Parties, set forth in the Agreement, remain in full force and effect.
IN WITNESS WHEREOF, the City and the Engineer, have each executed this
Amendment electronically, by and through their respective duly authorized representatives
and officers on this date _________________________.
“Engineer”
GARVER, LLC
By: ______________________________
AUTHORIZED SIGNATURE, TITLE
APPROVED AS TO LEGAL FORM:
MACK REINWAND, CITY ATTORNEY
By:
_________________________________
“CITY”
CITY OF DENTON, TEXAS
A Texas Municipal Corporation
By: _______________________________
ATTEST:
By:
_________________________________
THIS AGREEMENT HAS BEEN
BOTH REVIEWED AND APPROVED
as to financial and operational
obligations and business terms.
_______________ ________________
SIGNATURE PRINTED NAME
__________________________________
TITLE
__________________________________
DEPARTMENT
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
Vice President
Ryan Adams
Airport
Director of Airport
KRISTI FOGLE, INTERIM CITY SECRETARY
07/14/2026
1508 Industrial Blvd
Suite 204
McKinney, TX 75069
TEL 972.377.7480
FAX 972.377.8380
www.GarverUSA.com
May 4, 2026
Ryan Adams, CM
Denton Enterprise Airport (DTO)
5000 Airport Rd.
Denton, TX 76207
Re: Denton Enterprise Airport (DTO)
Taxiway A Reconstruction Preliminary Engineering Report (PER)
Professional Services Proposal
Dear Mr. Adams,
Garver is pleased to submit this proposal to provide professional services relating to the improvements listed in
“Exhibit A - Scope of Services” for the referenced project.
COMPENSATION
For the Preliminary Engineering Report (PER) for Taxiway A Reconstruction project, the not-to-exceed fee of
$408,000.00 is based upon the scope of services provided in Exhibit A. A detailed breakdown of the proposed
fee for the engineering services is included in Exhibit B. The Garver Hourly Rate schedule can be found within
Exhibit C.
Garver is pleased to have this opportunity to submit this proposal, and we look forward to working with you on
this project. If you have any questions or would like any additional information, please feel free to call me at 214-
619-9048.
Sincerely,
GARVER
Sara Andrews, PE
Senior Project Manager
Attachments: Exhibit A – Scope of Services
Exhibit B – Garver Fee Spreadsheet
Exhibit C – Garver Hourly Rate Schedule
Exhibit D – Lamb Star Engineering Proposal (Survey)
Exhibit E – ECS Proposal (Geotech)
Attachment A
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
Exhibit A – Scope of Services
Taxiway A Reconstruction PER Garver Project No. 2502991
EXHIBIT A
(SCOPE OF SERVICES)
Generally, the Scope of Services includes professional services for a Preliminary Engineering Report
(PER) for the improvements to Taxiway A at Denton Enterprise Airport (DTO). Improvements will
consist primarily of the reconstruction of
Taxiway A shown in Exhibit C. The following professional services are included in this agreement.
• Surveying Services
• Geotechnical Services
• Design Services
o Preliminary Engineering Report
1. SURVEYING SERVICES
1.1. Design Surveys. Lamb Star Engineering, as a subconsultant to Garver, will provide field
survey data from field work for designing the project, and this survey will be tied to the Owner’s
control network. Lamb Star Engineering has provided a lump-sum cost within their proposal
found in Exhibit D.
1.2. Team members will be escorted by Garver staff currently badged at the Airport or Survey team
members will complete badge training at the Airport prior to conducting survey
1.3. Lamb Star Engineering will conduct field surveys, utilizing radial topography methods, at
intervals and for distances at and/or along the project site as appropriate for modeling the
existing ground, including locations of pertinent features or improvements. Buildings and other
structures, airfield pavements, streets, drainage features, airfield lights and signs, fences,
trees over eight inches in diameter, visible utilities as well as those underground utilities
marked by their owners and/or representatives, and any other pertinent topographic features
that may be present at and/or along the project site, will be located. Control points will be
established for use during construction. All surveys shall be conducted during normal working
hours.
1.4. Lamb Star Engineering will assemble data obtained during the performance of the field
surveys in an AutoCAD Civil3D base map drawing to be utilized for design of the project.
2. GEOTECHNICAL SERVICES
2.1. ECS, as a subconsultant to Garver, will be responsible for obtaining, interpreting, and
evaluating geotechnical data necessary for the design of this project. The summary of the
geotechnical services provided under this Scope of Services is noted in Exhibit E.
3. DESIGN SERVICES
3.1. General: Garver will prepare detailed construction drawings, specifications, instructions to
bidders, and general provisions and special provisions, all based on guides furnished to
Garver by the Owner and FAA, or internally developed by Garver. Contract Documents (Plans,
Specifications, and Estimates) will be prepared for award of one (1) construction contract.
These designs shall conform to the standards of practice ordinarily used by members of
Garver’s profession practicing under similar conditions and shall be submitted to TxDOT
Aviation from which approval must be obtained.
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
Exhibit A – Scope of Services
Taxiway A Reconstruction PER Garver Project No. 2502991
3.2. Project Administration
3.2.1. Garver will serve as the Owner’s representative for the project and furnish consultation
and advice to the Owner during the performance of this service. Garver will attend
conferences alone or with Owner’s representatives, local officials, state and federal
agencies, and others regarding the scope of the proposed project, its general design,
functions, and impacts.
3.2.2. Garver will assist in the development of grant reimbursement packets for review,
execution, and submittal to TxDOT Aviation by the Owner.
3.3. Owner / Agency Coordination: Garver’s project manager and/or design team will coordinate
with the Owner as necessary to coordinate design decisions, site visits, document
procurement, or other design needs.
3.4. Project Management Plan / Quality Control Procedures
5.3.1 Garver will develop a project specific project management plan. The project
management plan will include the project background, scope of work, stakeholder
contact information, project team organization and roles, design criteria, project
schedule, deliverables, and quality control procedures.
5.3.2 Garver will complete quality control reviews for each deliverable prior to any design
submission to Owner and/or FAA. Quality control reviews will be completed by qualified
project managers and project engineers who are experienced in the relevant discipline
and design elements under review. Weekly internal progress meetings will be held
during all design phases to ensure adequate quality control throughout the design
phases.
3.5. Environmental Coordination
3.5.1. Garver will develop a Stormwater Pollution Prevention Plan (SWPPP), including erosion
control plans and details. Upon Owner review, the SWPPP shall be submitted to TxDOT
Aviation for review. Garver will incorporate comments from the review agency.
3.5.2. Garver will coordinate and complete documentation for submission to FAA to receive
environmental clearance for the project. Documentation will include that required by the
documented Section 163 and CATEX questionnaire of FAA SOP 5.0. No environmental
agency coordination is expected for this project area
3.6. Airspace Analysis: Garver will prepare and submit the project to the FAA for permanent
airspace clearance on the Obstruction Evaluation and Airport Airspace Analysis (OE/AAA)
website and coordinate with FAA representatives.
3.7. Existing Conditions Review
3.7.1. Record Document Review: Garver will review record document data from the vicinity of
the construction site to evaluate existing conditions. Record document data may include
record drawings, record surveys, utility maps, GIS data, and previous design reports.
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
Exhibit A – Scope of Services
Taxiway A Reconstruction PER Garver Project No. 2502991
3.7.2. Site Visits: Garver’s civil and electrical engineers will perform up to two (2) site visits to
the project site to review existing conditions and evaluate survey and record document
data.
3.8. Pavement Design: Garver will develop a fleet mix for the proposed project based on aircraft
fleet data from the Airport Operator / Airport Master Plan / Traffic Flow Management System
Counts (TFMSC). Upon completion of the aircraft fleet mix, Garver will submit the fleet to the
Owner for review. Upon approval by the Owner, Garver will use FAARFIELD and life cycle
cost analysis methods to develop a recommendation for the most economical pavement
design. Based on this analysis and discussions with the Owner, a pavement design for the
project will be chosen. For concrete pavement design, Garver will design joint patterns and
jointing details.
3.9. Geometric Design: Garver will provide geometric design in accordance with FAA AC
150/5300-13 (latest edition) or other local standards. The following design criteria will be used
for airfield design:
• Airplane Design Group (ADG) – II
• Aircraft Approach Category (AAC) – D
• Taxiway Design Group (TDG) – 2B
3.10. Airfield Electrical
3.10.1. Airfield Lighting and Signage: Garver will provide electrical engineering services to
design the new lighting improvements on the project including but not limited to the
following: taxiway edge lighting and guidance signage.
3.11. Design Services Submission and Meeting Summary: The following design submittal phases
shall be included in the fee summary. A summary of each design phase and the associated
review meetings is included below.
3.11.1. Preliminary Engineering Report
3.11.1.1. Garver will develop a Preliminary Engineering Report and submit to the
Owner for review. Garver will develop up to two (2) reconstruction options
for Taxiway Alpha and cost estimates to execute the reconstruction of
Taxiway Alpha. It is anticipated that the Owner will review the design
submission within two weeks.
3.11.1.2. At the completion of the Owner review period, Garver will meet with the
Owner to review the Preliminary Engineering Report and to receive Owner
comments and direction.
4. PROJECT DELIVERABLES
4.1. The following deliverables will be submitted to the parties identified below. Unless otherwise
noted below, all deliverables shall be electronic.
• Preliminary Engineering Report to the Owner
o One hard copy to the Owner and TxDOT Aviation
• Other electronic files as requested
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
Exhibit A – Scope of Services
Taxiway A Reconstruction PER Garver Project No. 2502991
5. ADDITIONAL SERVICES
5.1. The following items are not included under this agreement but will be considered as additional
services to be added under Amendment if requested by the Owner.
• Redesign for the Owner’s convenience or due to changed conditions after previous
alternate direction. Changes conditions may include, but are not limited to major changes
to pavement, building, or utility alignments.
• Deliverables beyond those listed herein.
• Design of any utility relocation
• Subsurface Utility Exploration (SUE).
• Underdrain Design.
• DBE Program Goal Setting or Reporting.
• Final Engineering Report
• Pavement Design beyond that furnished in the Geotechnical Report.
• Runway Safety Area Inventory
• Engineering, architectural, or other professional services beyond those listed herein.
• Retaining walls or other significant structural design.
• Construction Administration Services, On-Site Construction Observation, and/or
Construction Materials Testing.
• Environmental Handling and Documentation, including wetlands identification or mitigation
plans or other work related to environmentally or historically (culturally) significant items.
• Permitting for environmentally sensitive areas.
• Coordination with FEMA and preparation/submittal of a CLOMR and/or LOMR.
• Services after construction, such as warranty follow-up, operations support, and Part 139
inspection support.
• The construction contract documents will require the Contractor to prepare, maintain, and
submit a SWPPP to DEQ
6. SCHEDULE
6.1. Garver shall begin work under this Agreement within a mutually agreeable schedule with the
Owner and execution of this Agreement. All design phases will start with a Notice to Proceed
(NTP) and stakeholder review comments from the subsequent phase.
Design Phase Calendar Days
Preliminary Engineering
Report
10 Weeks from Agreement Execution, NTP, and Design Kickoff
Meeting
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
EXHIBIT B
Denton Enterprise Airport (DTO)
Taxiway A Reconstruction PER
FEE SUMMARY
Title I Service Estimated Fees
Surveys (Lamb Star Engineering) $ 57,500.00
Geotechnical (ECS) $ 87,100.00
Preliminary Engineering Report $ 263,400.00
Subtotal for Title I Service 408,000.00$
L:\2025\A11-2500971 - DTO- Taxiway A Reconstruction PER\Contracts\Client\Draft\DTO - Taxiway A PER - Exhibit B -
Manhour Tables - 2026-05-04
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
EXHIBIT B
Denton Enterprise Airport (DTO)
Taxiway A Reconstruction PER
Preliminary Engineering Report
WORK TASK DESCRIPTION E-5 E-4 E-3 E-2 E-1 D-2 AM-2
hr hr hr hr hr hr hr
1. Civil Engineering
Coordination with FAA 2 2
Coordination with TxDOT 2
Coordination with Airport (DTO)8
Surveyor Field Work Coordination 4 8
Geotechnical Field Work Coordination 4 8
Prepare for Project Pre-Design Meeting (External)2 2
Attend Project Pre-Design Meeting (External)2 2
Analyze Survey Data 4 8
Analyze Geotechnical Bores 2 6 6
Analyze Geotechnical Draft Report 2 6 6
Records research and review 6 6
Site Visit (3 people, 2 trips)2 6 6
Setup Base Maps 6 12
Setup Report Template 6
Develop Project Management Plan 2 4
Develop Quality Control Plan 2 4
Conduct internal design kickoff meeting 2 2 2 2 2 2
Internal Weekly Meetings 12 12 12 12 12 12
Establish Design Criteria 2 2
Develop Fleet Mix using available data (TFMSC, 5010, etc.)2 8
Develop Pavement Design 2 12
Perform Program Civil 3D Modeling 6 24 30
Develop Taxiway A Program Profiles 6 16 24
Develop Program Markings 6 18
Prepare Preliminary Engineering Report
Develop Report Outline 2 8 4
Develop Executive Summary 2 8 4
Project Background Narrative 8
Design Standards Narrative 2 8
Program Layout Geometry Narrative 2 10
Program Layout Connector Location Narrative 2 8
Program Layout Naming Convention Narrative 8
Existing Utility Infrastructure Narrative 2 10
Proposed Utility Infrastructure Narrative 2 10
Program Marking Layout Narrative 2 8
Pavement Design Narrative 4 8
Construction Safety & Phasing Plans (CSPP) Narrative 4 8
Project Schedule Narrative 2 8
Engineer's Estimate Narrative 2 8
Prepare Preliminary Engineering Report Exhibits
Develop Program Layout Plan Exhibit 4 6 8 10 12
Develop Project Layout Plan Exhibit (Phase I)4 6 8 10 12
Develop Existing Drainage Area Map (Phase I Only)6 8 10 12
Develop Proposed Drainage Area Map (Phase I Only)6 8 10 12
Develop Construction Safety & Phasing Plans (Phase I Only)4 6 8 10 12
Develop Utility Map Exhibit 6 8 10 12
Quantities (Phase I)8 10 12
Quantities (Phase II)8 10 12
Quantities (Phase III)8 10 12
Develop opinion of probable cost (Phase I)8
Develop opinion of probable cost (Phase II)8
Develop opinion of probable cost (Phase III)8
Review Construction Emissions Inventory from Subconsultant 2 4
Develop Emissions Report Narative 2 6
Internal Draft Report QC 20 30
Revisions to Draft Report based on QC Review 12 12 12 12
Prepare for Report Review Meeting 2 4 2
Attend Report Review Meeting (3 People, on-site)4 4 4
Prepare and Distribute Report Review Meeting Minutes and Tasks 2 6
Subtotal - Civil Engineering 26 136 282 216 200 142 24
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
2.Electrical Engineering
Coordination with FAA 2
Coordination with Airport (TKI)4
Records research and review 4 4
Locate Existing Circuits 4 4
Lighting and Signage Assessment 4 4
Prepare Preliminary Engineering Report
Develop Report Outline 8 8
Existing Electrical Narrative 6 6
Existing Navigational Aids Narrative 2 2
Proposed Lighting and Signage Narrative 4 4
Visual Aids Narrative 2 2
Construction Safety & Phasing Plans (CSPP) Temporary Electrical Phasing Narrative 4 8
Existing Dry Utility Narrative 4 8
Proposed Dry Utility Narrative 4 8
Prepare Preliminary Engineering Report Exhibits
Develop CSPP Temporary Electrical Exhibit (Phase I Only)8 16
Develop Utility Map Exhibit 8 16
Perform Electrical Load Calculations 6 12
Internal Draft Report QC 16 16
Revisions to Draft Report based on QC Review 16 16
Subtotal - Electrical Engineering 16 106 0 118 0 0 0
Hours 42 242 282 334 200 142 24
SUBTOTAL - SALARIES: $262,022.00
DIRECT NON-LABOR EXPENSES
Document Printing/Reproduction/Assembly $408.00
Postage/Freight/Courier $200.00
Office Supplies/Equipment $200.00
Computer Modeling/Software Use $300.00
Travel Costs $270.00
SUBTOTAL - DIRECT NON-LABOR EXPENSES: $1,378.00
SUBTOTAL: $263,400.00
SUBCONSULTANTS FEE: $0.00
TOTAL FEE: $263,400.00
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
Rates Rates
Engineers / Architects Resource Specialists
E-1 161.00$ RS-1 104.00$
E-2 189.00$ RS-2 137.00$
E-3 225.00$ RS-3 194.00$
E-4 265.00$ RS-4 268.00$
E-5 322.00$ RS-5 335.00$
E-6 397.00$ RS-6 411.00$
E-7 444.00$ RS-7 460.00$
Planners Environmental Specialists
P-1 194.00$ ES-1 104.00$
P-2 230.00$ ES-2 131.00$
P-3 261.00$ ES-3 168.00$
P-4 320.00$ ES-4 198.00$
P-5 380.00$ ES-5 248.00$
ES-6 318.00$
Designers ES-7 398.00$
D-1 145.00$ ES-8 450.00$
D-2 164.00$
D-3 194.00$ Project Controls
D-4 227.00$ PC-1 106.00$
PC-2 140.00$
Technicians PC-3 178.00$
T-1 126.00$ PC-4 229.00$
T-2 170.00$ PC-5 280.00$
T-3 184.00$ PC-6 361.00$
T-4 218.00$ PC-7 454.00$
Surveyors Administration / Management
S-1 78.00$ AM-1 75.00$
S-2 93.00$ AM-2 96.00$
S-3 128.00$ AM-3 134.00$
S-4 175.00$ AM-4 171.00$
S-5 230.00$ AM-5 209.00$
S-6 268.00$ AM-6 272.00$
2-Man Crew (Survey) 344.00$ AM-7 320.00$
3-Man Crew (Survey) 403.00$ M-1 510.00$
2-Man Crew (GPS Survey) 344.00$
3-Man Crew (GPS Survey) 403.00$
Construction Observation
C-1 112.00$
C-2 140.00$
C-3 171.00$
C-4 221.00$
C-5 259.00$
Agreement for Professional Services
Taxiway A Reconstruction Per Garver Project No. 2500971
Garver Hourly Rate Schedule: July 2023 - June 2024
Classification Classification
Exhibit C
Denton Enterprise Airport (DTO)
Taxiway A Reconstruction PER
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
Exhibit DDocusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
ECS Southwest, LLP
Scope and Fee for Subsurface Exploration and Geotechnical
Engineering Services
DTO Taxiway A Reconstruction
5000 Airport Road
Denton, Denton County, Texas
ECS ID No. 63:4596-GP
March 19, 2026
Exhibit EDocusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
ECS Southwest, LLP March 19, 2026
ECS ID No: 63:4596-GP
Page | 2
March 19, 2026
Mr. Austin Hayes
Garver
3000 Internet Blvd
Suite 400
Frisco, Texas 75034
ECS ID No. 63:4596-GP
Reference: Scope and Fee for Subsurface Exploration and Geotechnical Engineering Services
DTO Taxiway A Reconstruction
5000 Airport Road
Denton, Denton County, Texas
Dear Mr. Hayes:
As requested, ECS Southwest, LLP (ECS), is pleased to be selected for this project and providing the
following lump sum scope and fee for subsurface exploration and geotechnical engineering services for
the above-mentioned project. Our understanding of the project is based on our review of the available
geological and geotechnical information in our files in vicinity of the site and Request for Geotechnical
Proposal (prepared by Garver, LLC., dated March 2, 2026) and geotechnical exhibit – Taxiway A (prepared
by Garver, LLC., dated September 2025) in the email dated March 16, 2026. This scope and fee outlines
our understanding of the project, the proposed scope of services, activity schedule, fees, and
authorization requirements.
PROJECT BACKGROUND INFORMATION
Existing Site Conditions
The project site is located at 5000 Airport Road in Denton, Denton County, Texas (GPS: 33.1986 N, 97.1967
W). ECS did not visit the site prior to preparing this scope and fee. Based on Google Earth aerial maps, the
site is developed with structures and pavements. The existing Taxiway A pavement are constructed from
asphalt. Based on the information provided by the client, distresses including fatigue cracking, longitudinal
and transverse cracks and block cracking were observed on the site.
Project Description
Based on the information and plan provided, we understand the proposed project will include the
reconstruction of Taxiway A. The taxiway and apron will be used by aircraft having gross weights of 60,000
lbs or more. Based on the information provided in Request for Geotechnical Proposal, final grade of new
pavement will roughly match existing pavement grades to promote surface drainage from the taxiways to
the turfed areas adjacent to the taxiways.
ECS SOUTHWEST, LLP TX Registered Engineering No. F-8461
Geotechnical Construction Materials Environmental Facilities
2621 WESTSIDE DRIVE, FORT WORTH, TX 76107 T: (682) 350-2250 F: (817) 847-8616
ECS Florida, LLC ECS Mid-Atlantic, LLC ECS Midwest, LLC ECS Pacific, Inc. ECS Southeast, LLC ECS Southwest, LLP
ECS New York Engineering, PLLC – An Associate of ECS Group of Companies www.ecslimited.com
“ONE FIRM. ONE MISSION.”
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
ECS Southwest, LLP March 19, 2026
ECS ID No: 63:4596-GP
Page | 3
Please note that a topographic drawing and grading plan were not available at the time of this scope and
fee. ECS should be provided with topographic drawings and a grading plan prior to initiating our services
to review our proposed depth of borings regarding actual cut/fill depths and make changes to our
proposed scope and fee as necessary.
SCOPE OF SERVICES
Our integrated services will include drilling borings by drilling crews based on instructions provided by
ECS. Our services will also include laboratory testing of representative soil samples, and engineering
analyses presented in a site-specific engineering report.
Utility Clearance
Per state law, we will contact Texas 811 the public utility to locate underground utilities at the site.
Typically, Texas 811 will not locate utilities beyond the point of distribution (meters or gauge points) on
private property. The risk of hitting utilities that Texas 811 did not mark can be reduced by engaging a
private utility locating service. The risks include hitting gas lines, electrical lines, fiber optic lines, and many
other utility service lines. This can result in electrocution, gas leaks or explosions, loss of services to
businesses as well as tremendous costs for lost business, interruption of service, and repair along with
potential legal liability.
We have included the cost of a private utility line locator in our “Base Services”. Private utility locator
services can aid in identifying utilities that incorporate significant iron content in the conduit materials.
However, utilities without significant ferrous (iron) content are more difficult to detect. These include
most sanitary sewer alignments, copper or PVC water lines, fiber optic lines without tracer ribbons, copper
electric lines with no surface exposure, drainage tiles/pipes, irrigation lines, etc.
Using a private utility locator does not guarantee that all utilities will be identified. However, this service
lowers the risk and potential liability of the client while also protecting the safety of our field exploration
crews.
We will coordinate our exploration locations around marked utilities and utilities pointed out to us by the
owner/client. However, we will not be responsible for any utilities not marked or not pointed out to us by
the landowner or client.
Site Access
Based on our review of available aerial photographs, the site appears to be accessible to a truck-mounted
drilling rig.
Regarding site access, we have made the following assumptions:
• This scope and fee assume that no special permits will be required. The pavement coring and
drilling will take place during nighttime (10 pm to 6 am).
• Landowner notification will be provided by the client. ECS will work with the project team in
providing site access diagrams for the drill rig as needed, but actual coordination with
landowners to obtain access permission will be provided by the client.
• Taxing within the work areas will be blocked off prior to our arrival. ECS cannot be held
responsible for damage to, nor the cleanliness of, vehicles not moved from the work area.
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
ECS Southwest, LLP March 19, 2026
ECS ID No: 63:4596-GP
Page | 4
Field Exploration
ECS proposes to perform the following in general accordance with the local standards and practices listed:
a. Field locate the test locations by handheld GPS unit / taping and pacing from existing site features /
available plans. Elevations will be interpolated from the plans provided/or referenced from published
topographical maps.
b. Obtain a public utility locate ticket for location of underground lines. See further information in the
Utility Clearance section above.
c. Private utility locate service to clear the boring locations.
d. Mobilize a pavement coring crew and core the pavement in twenty-nine (29) locations as requested.
e. Mobilize a truck mounted drilling rig to the site.
f. As requested, twenty-nine (29) borings will be drilled on the project site. These boring locations will
be cored and drilled within the taxiway areas to a depth of 10 feet below the existing grades. The
approximate locations are shown in the figure below.
g. Perform testing and sampling in general accordance with ASTM standards and local practices.
h. Measure the depth of groundwater within each exploration location at the time of drilling and prior
to backfilling.
i. Obtain bulk samples of auger cuttings from select borings for laboratory testing.
The explorations will be extended to the depths listed above or to mechanical refusal (shallow rock or
other impenetrable obstructions), whichever occurs first.
Site Departure Conditions
Upon completion of subsurface exploration, we will backfill each of the locations with the soil removed
and mound the excess spoils back up over the test location. In pavement areas, we will patch the asphalt
or concrete surface with cold mix asphalt patch or quick setting concrete of an equivalent or greater
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
ECS Southwest, LLP March 19, 2026
ECS ID No: 63:4596-GP
Page | 5
thickness. Some post drilling settlement of the boreholes should be expected and may require future
maintenance to repair any settlement and prevent a tripping hazard. This maintenance is not included in
our scope of services or fees. No other restoration will be provided. ECS will not be responsible for
restoration of, but not limited to the following: grass, shrubs, trees, flower beds, or ruts caused by drilling
operations. The client must communicate areas that must not be disturbed in advance of field operations.
Typically, we will not provide site repairs beyond what is outlined above unless specifically contracted.
Alternatively, we will remove excess spoils from job sites and dispose of them in an approved manner for
a negotiated fee.
Please note that some disturbance to off-pavement, gravel-covered, grass-covered areas, including the
possible cutting of trees, or running over of brush and understory in wooded areas might occur. We will
attempt to limit such disturbance; however, we have not budgeted for site repairs including filling of tire
ruts, seeding of lawn areas, replacement of bushes or the planting of trees, etc. If necessary, additional
site repairs can be provided at an additional cost.
Laboratory Testing
Upon completion of field exploration operations, the samples will be returned to our laboratory for
further identification, visual classification, and testing. Laboratory testing may include the following:
LABORATORY TEST
Natural Moisture Content
Gradation Analysis
Atterberg Limits
Standard/Modified Proctor
California Bearing Ration (CBR)
Swell Test
Unconfined Compressive Strength of Soil
Sulfate Content, pH, Organic content
Lime pH Series
Engineering Report
Upon completion of the field exploration, laboratory testing, and engineering analyses, we will prepare a
written engineering report that will include:
a. A review of published soils mapping and/or geologic information.
b. Observations from our site reconnaissance and personnel on the drill rig, including current site
conditions, surface drainage features, and surface topographic conditions, and/or available satellite
imagery.
c. A description of the field exploration and laboratory tests performed.
d. A site location diagram and a field exploration diagram.
e. Final logs of the soil borings in accordance with industry standard practices for geotechnical
engineering. Elevations will be interpolated from civil drawings or referenced from topographic
information that you supply.
f. Photographs with a visual scale indicating pavement thickness for all pavement cores.
g. The results of the laboratory tests will be plotted on the final exploration logs and/or included on
separate test report pages.
h. Discussion of the subsurface materials encountered along with groundwater conditions observed.
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
ECS Southwest, LLP March 19, 2026
ECS ID No: 63:4596-GP
Page | 6
i. Subsurface cross sections/profiles may be included that graphically represent the subsurface
conditions.
j. Recommendations for preparation of subgrade for the reconstructed taxiway pavement (lime treated
subgrade, cement treated subgrade, cement treated base, etc.).
k. Recommendations regarding preparation of existing soils (native or otherwise) including
recommendations regarding undercut and backfill.
l. Pavement design value recommendations – ECS to provide k-value, CBR, resilient modulus, etc
recommended for pavement design. Garver will perform the pavement design based on the subgrade
recommendations. All paving materials will follow the FAA specification requirements for
construction.
m. Testing and recommendations for pavement design related to sulfates.
n. Recommendations regarding surface and subsurface drainage, during and after construction.
o. Recommendations for embankment design and construction, if required.
p. Recommendations for suitable configuration(s) of cut slopes, fill slopes, temporary excavations, if
required.
FEE
ECS will provide the services outlined in this scope and fee for a lump sum fee of $75,800.00.
Our fee assumes that the site is accessible based upon our assumptions detailed in this document. If
additional services are requested or required based on differing site conditions, we will contact you for
verbal and written authorization to proceed with the additional services.
SCHEDULE
Our ability to access the site and perform the field exploration may be impacted by precipitation, excessive
temperatures, or other atmospheric conditions. Field exploration will be performed during nighttime (10
pm to 6 am) Monday through Friday.
We have assumed that the client will assist in accessing the site (with the current site owners/occupants).
We anticipate being able to mobilize to the site within approximately 2 to 3 weeks after receiving
authorization to proceed, notification that on-site personnel if any has been made, and upon clearing
utilities.
We anticipate that the drilling operations will require about 3 to 4 nights, and that the laboratory testing,
will require about 7 to 14 days, followed by our engineering analyses. For time budget purposes, the entire
scope should take about 6 to 8 weeks from initial authorization through final report submission. If there
is a specific due date for the report, please let us know. Verbal comments on findings can be provided
within 7 days of completion of the borings, if requested.
CLOSING
If other services are required because of unexpected field conditions, or because of a request for
additional services, they will be invoiced in accordance with a negotiated fee. Before modifying or
expanding the extent of our exploration program, we will contact you for your review and authorization.
Our insurance carrier requires that we receive written authorization prior to initiation of work, and a
signed contract prior to the release of any work product. This letter is the agreement for our services.
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
ECS Southwest, LLP March 19, 2026
ECS ID No: 63:4596-GP
Page | 7
Your acceptance of this scope and fee may be indicated by signing and returning a copy of this document
to us. We are pleased to have this opportunity to offer our services and look forward to working with you
on the project.
Respectfully submitted,
ECS SOUTHWEST, LLP
Ishtiaque Hossain, PhD, P.E. Michael Batuna, P.E.
Vice President, Office Manager Vice President, Asst. Office Manager
IHossain@ecslimited.com MBatuna@ecslimited.com
Enclosures: Scope and Fee Acceptance Sheet
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
ECS Southwest, LLP March 19, 2026
ECS ID No: 63:4596-GP
Page | 8
SCOPE AND FEE ACCEPTANCE
Scope and Fee No.: 63:4596-GP
Scope of Work: Subsurface Exploration and Geotechnical Engineering Services
Project: DTO Taxiway A Reconstruction
Location: 5000 Airport Road, Denton, Denton County, Texas
Base Services: $75,800.00
Client Signature: Date:
Printed Name: Title:
Please complete this page and return one copy to ECS to indicate acceptance of this scope and fee and to
initiate work on the above-referenced project.
BILLING INFORMATION
(please print or type)
Contact Person:
Telephone No. of Contact Person:
Email of Contact Person:
Party Responsible for Payment:
Company Name:
Billing Address:
Telephone Number:
Accounts Payable Email Address:
Client Project/Account Number:
Special Conditions for Invoices:
ECS offers a full array of services to assist you with all phases of your project, including but not limited to:
- Phase I, II and III Environmental
Site Assessments - Wetlands Delineations - Asbestos/Lead Paint Services
Indoor Air Quality/Mold Services - Natural Resources - Groundwater Remediation
- Third Party Mechanical,
Electrical, Plumbing Inspections
Services - Construction Materials Testing
and Special Inspections - LEED® Consulting Services - Geo-Structural Design
- Building Envelope, Roofing, and
Waterproofing Consultation - Specialty Materials and
Forensics Testing - Monitoring Services - Pre- and Post-Construction
Condition Assessments
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
1508 Industrial Blvd
Suite 204
McKinney, TX 75069
TEL 972.377.7480
FAX 972.377.8380
www.GarverUSA.com
May 4, 2026
Ryan Adams, CM
Denton Enterprise Airport (DTO)
5000 Airport Rd.
Denton, TX 76207
Re: Denton Enterprise Airport (DTO)
Taxiways H, J, M Reconstruction Design
Professional Services Proposal
Dear Mr. Adams,
Garver is pleased to submit this proposal to provide professional services relating to the improvements listed in
“Exhibit A - Scope of Services” for the referenced project.
COMPENSATION
For the design of Taxiways H, J, and M Reconstruction project, the not-to-exceed fee of $480,000.00 is based
upon the scope of services provided in Exhibit A. A detailed breakdown of the proposed fee for the engineering
services is included in Exhibit B. The Garver Hourly Rate schedule can be found within Exhibit C.
Garver is pleased to have this opportunity to submit this proposal, and we look forward to working with you on
this project. If you have any questions or would like any additional information, please feel free to call me at 214-
619-9048.
Sincerely,
GARVER
Sara Andrews, PE
Senior Project Manager
Attachments: Exhibit A – Scope of Services
Exhibit B – Garver Fee Spreadsheet
Exhibit C – Garver Hourly Rate Schedule
Exhibit D – Lamb Star Engineering Proposal (Survey)
Exhibit E – ECS Proposal (Geotech)
Attachment B
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
Exhibit A – Scope of Services
Taxiways H, J, and M Reconstruction Garver Project No. 2502991
EXHIBIT A
(SCOPE OF SERVICES)
Generally, the Scope of Services includes professional services for improvements to Taxiways H, J,
and M at Denton Enterprise Airport (DTO). Improvements will consist primarily of the reconstruction of
Taxiways H, J, and M shown in Exhibit C. The following professional services are included in this
agreement.
• Surveying Services
• Geotechnical Services
• Design Services
o 60% Preliminary Design
o 90% Final Design
o 100% Issued for Bid
• Bidding Services
1. SURVEYING SERVICES
1.1. Design Surveys. Lamb Star Engineering, as a subconsultant to Garver, will provide field
survey data from field work for designing the project, and this survey will be tied to the Owner’s
control network. Lamb Star Engineering has provided a lump-sum cost within their proposal
found in Exhibit D.
1.2. Team members will be escorted by Garver staff currently badged at the Airport or Survey team
members will complete badge training at the Airport prior to conducting survey
1.3. Lamb Star Engineering will conduct field surveys, utilizing radial topography methods, at
intervals and for distances at and/or along the project site as appropriate for modeling the
existing ground, including locations of pertinent features or improvements. Buildings and other
structures, airfield pavements, streets, drainage features, airfield lights and signs, fences,
trees over eight inches in diameter, visible utilities as well as those underground utilities
marked by their owners and/or representatives, and any other pertinent topographic features
that may be present at and/or along the project site, will be located. Control points will be
established for use during construction. All surveys shall be conducted during normal working
hours.
1.4. Lamb Star Engineering will assemble data obtained during the performance of the field
surveys in an AutoCAD Civil3D base map drawing to be utilized for design of the project.
2. GEOTECHNICAL SERVICES
2.1. ECS, as a subconsultant to Garver, will be responsible for obtaining, interpreting, and
evaluating geotechnical data necessary for the design of this project. The summary of the
geotechnical services provided under this Scope of Services is noted in Exhibit E.
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
Exhibit A – Scope of Services
Taxiways H, J, and M Reconstruction Garver Project No. 2502991
3. DESIGN SERVICES
3.1. General: Garver will prepare detailed construction drawings, specifications, instructions to
bidders, and general provisions and special provisions, all based on guides furnished to
Garver by the Owner and FAA, or internally developed by Garver. Contract Documents (Plans,
Specifications, and Estimates) will be prepared for award of one (1) construction contract.
These designs shall conform to the standards of practice ordinarily used by members of
Garver’s profession practicing under similar conditions and shall be submitted to TxDOT
Aviation from which approval must be obtained.
3.2. Project Administration
3.2.1. Garver will serve as the Owner’s representative for the project and furnish consultation
and advice to the Owner during the performance of this service. Garver will attend
conferences alone or with Owner’s representatives, local officials, state and federal
agencies, and others regarding the scope of the proposed project, its general design,
functions, and impacts.
3.2.2. Garver will assist in the development of grant reimbursement packets for review,
execution, and submittal to TxDOT Aviation by the Owner.
3.3. Owner / Agency Coordination: Garver’s project manager and/or design team will coordinate
with the Owner as necessary to coordinate design decisions, site visits, document
procurement, or other design needs.
3.4. Project Management Plan / Quality Control Procedures
5.3.1 Garver will develop a project specific project management plan. The project
management plan will include the project background, scope of work, stakeholder
contact information, project team organization and roles, design criteria, project
schedule, deliverables, and quality control procedures.
5.3.2 Garver will complete quality control reviews for each deliverable prior to any design
submission to Owner and/or FAA. Quality control reviews will be completed by qualified
project managers and project engineers who are experienced in the relevant discipline
and design elements under review. Weekly internal progress meetings will be held
during all design phases to ensure adequate quality control throughout the design
phases.
3.5. Environmental Coordination
3.5.1. Garver will develop a Stormwater Pollution Prevention Plan (SWPPP), including erosion
control plans and details. Upon Owner review, the SWPPP shall be submitted to TxDOT
Aviation for review. Garver will incorporate comments from the review agency.
3.5.2. Garver will coordinate and complete documentation for submission to FAA to receive
environmental clearance for the project. Documentation will include that required by the
documented Section 163 and CATEX questionnaire of FAA SOP 5.0. No environmental
agency coordination is expected for this project area
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
Exhibit A – Scope of Services
Taxiways H, J, and M Reconstruction Garver Project No. 2502991
3.6. Airspace Analysis: Garver will prepare and submit the project to the FAA for permanent
airspace clearance on the Obstruction Evaluation and Airport Airspace Analysis (OE/AAA)
website and coordinate with FAA representatives.
3.7. Construction Safety and Phasing Plan
3.7.1. Garver will develop a construction safety and phasing plan (CSPP) for the project. During
development of the CSPP, Garver will hold a meeting with Airport staff and other
stakeholders at the Airport’s request to obtain feedback regarding operations during each
proposed phase of construction.
3.7.2. After receiving comments from the meeting, Garver will develop a preliminary CSPP for
the Owner’s review prior to submission to the FAA. After incorporating Owner comments,
the CSPP will be submitted to FAA for review through the OE/AAA website.
3.8. Existing Conditions Review
3.8.1. Record Document Review: Garver will review record document data from the vicinity of
the construction site to evaluate existing conditions. Record document data may include
record drawings, record surveys, utility maps, GIS data, and previous design reports.
3.8.2. Site Visits: Garver’s civil and electrical engineers will perform up to two (2) site visits to
the project site to review existing conditions and evaluate survey and record document
data.
3.9. Pavement Design: Garver will develop a fleet mix for the proposed project based on aircraft
fleet data from the Airport Operator / Airport Master Plan / Traffic Flow Management System
Counts (TFMSC). Upon completion of the aircraft fleet mix, Garver will submit the fleet to the
Owner for review. Upon approval by the Owner, Garver will use FAARFIELD and life cycle
cost analysis methods to develop a recommendation for the most economical pavement
design. Based on this analysis and discussions with the Owner, a pavement design for the
project will be chosen. For concrete pavement design, Garver will design joint patterns and
jointing details.
3.10. Geometric Design: Garver will provide geometric design in accordance with FAA AC
150/5300-13 (latest edition) or other local standards. The following design criteria will be used
for airfield design:
• Airplane Design Group (ADG) – II
• Aircraft Approach Category (AAC) – D
• Taxiway Design Group (TDG) – 2B
3.11. Modeling: Garver will develop preliminary vertical alignments based on the requirements of
FAA AC 150/5300-13 (latest edition). Upon the completion of vertical alignments, assemblies
will be developed based on the pavement design and corridors will be modeled for each
taxiway alignment. Modeling will include all surface changes from centerline of corridor to tie
into existing grade for the project site. At the completion of individual corridor developments,
all corridors will be combined into a final grading surface. Modeling will be an iterative process
to determine the most efficient design solution.
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
Exhibit A – Scope of Services
Taxiways H, J, and M Reconstruction Garver Project No. 2502991
3.12. Grading and Drainage: Grading and drainage design shall be completed in accordance with
FAA AC 150/5300-13 (Airport Design), FAA AC 150-5320-5 (Airport Drainage Design), and
applicable local drainage codes.
3.13. Airfield Electrical
3.13.1. Airfield Lighting and Signage: Garver will provide no electrical engineering services to
design the new lighting improvements on the project.
3.14. Specifications and Contract Documents
3.14.1. Technical Specifications: Detailed specifications shall be developed using FAA
"Standards for Specifying Construction for Airports" AC 150/5370-10 (latest edition) or
other appropriate standards approved for use by the FAA. Additional supplementary
specifications will be developed for project requirements not covered by FAA
AC150/5370-10 or when state or local standards are approved by the FAA.
3.14.2. Construction Contract Documents: Garver will develop construction contract
documents based on TxDOT Aviation standards. TxDOT Aviation will complete all
front-end documents. A specimen copy of the General Provisions and applicable
prevailing wage rates will be obtained by Garver from the FAA and/or Department of
Labor as appropriate for incorporation into the specifications for the proposed project.
Final construction contract documents will be submitted to the Owner for final review
and approval.
3.15. Quantities and Engineer’s Opinion of Probable Cost: Garver will develop detailed quantities
in PDF format for use in construction cost estimating for each design phase. Quantities will
be completed by pay item. Upon the completion of quantity development, Garver will review
previous cost data and market conditions and complete an Engineer’s Opinion of Probable
Cost.
3.16. Design Services Submission and Meeting Summary: The following design submittal phases
shall be included in the fee summary. A summary of each design phase and the associated
review meetings is included below.
3.16.1. 60% Preliminary Design
3.16.1.1. Garver will develop 60% preliminary design plans, specifications, and
engineer’s report and submit these to the Owner and TxDOT for review. It is
anticipated that the Owner and TxDOT will review the design submission
within one week.
3.16.1.2. At the completion of the Owner review period, Garver will meet with the
Owner and TxDOT to review the 60% preliminary design plans,
specifications, and engineer’s report and to receive Owner and TxDOT
comments and direction.
3.16.2. 90% Final Design
3.16.2.1. Garver will develop 90% final design plans, specifications, and engineer’s
report and submit these to the Owner and TxDOT.
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
Exhibit A – Scope of Services
Taxiways H, J, and M Reconstruction Garver Project No. 2502991
3.16.2.2. At the completion of the Owner review period, Garver will meet with the
Owner and TxDOT to review the 90% Final design plans, specifications, and
engineer’s report and to receive Owner and TxDOT comments and direction.
3.16.3. 100% Issued for Bid (IFB)
3.16.3.1. Garver will develop 100% IFB plans and specifications and submit these to the
Owner for review. It is anticipated that the Owner will review the IFB submission
within two weeks.
4. BIDDING SERVICES
4.1. Bidding. Garver will assist City of Denton in advertising for and obtaining bids or negotiating
proposals for one prime contract for construction, materials, equipment and services; and,
where applicable, maintain a record of prospective bidders to whom Bidding Documents have
been issued, attend a pre-bid conference, and attend the Bid Opening. The Owner will pay
advertising costs outside of this contract.
4.2. Garver will issue addenda as appropriate to interpret, clarify or expand the Bidding
Documents. Garver will consult with and advise the Owner as to the acceptability of
subcontractors, suppliers and other persons and organizations proposed by the prime
contractor(s) (herein called "Contractor(s)") for those portions of the work as to which such
acceptability is required by the Bidding Documents. Garver will consult with the Owner
concerning the acceptability of substitute materials and equipment proposed by Contractor(s)
when substitution prior to the award of contracts is allowed by the Bidding Documents.
4.3. Garver will attend the bid opening, prepare a bid tabulation, and assist the Owner in evaluating
bids or proposals and in assembling and awarding contracts for construction, materials,
equipment, and services. Garver will assist the Owner in the execution of all contract
documents and furnish a sufficient number of executed documents for the Owner, Contractor
and TxDOT Aviation.
5. PROJECT DELIVERABLES
5.1. The following deliverables will be submitted to the parties identified below. Unless otherwise
noted below, all deliverables shall be electronic.
• 60% Preliminary Design Plans, Specifications, and Engineer’s Estimate of Probable Cost
to the Owner, and TxDOT Aviation.
• 90% Final Design Plans, Specifications, and Engineer’s Estimate of Probable Cost to the
Owner, and TxDOT Aviation. Other electronic files as requested.
• 100% Issued for Bid Plans, Specifications, and Engineer’s Estimate of Probable Cost to
the Owner and FAA.
• Other electronic files as requested
6. ADDITIONAL SERVICES
6.1. The following items are not included under this agreement but will be considered as additional
services to be added under Amendment if requested by the Owner.
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
Exhibit A – Scope of Services
Taxiways H, J, and M Reconstruction Garver Project No. 2502991
• Redesign for the Owner’s convenience or due to changed conditions after previous
alternate direction. Changes conditions may include, but are not limited to major changes
to pavement, building, or utility alignments.
• Deliverables beyond those listed herein.
• Design of any utility relocation
• Subsurface Utility Exploration (SUE).
• Underdrain Design.
• DBE Program Goal Setting or Reporting.
• Preliminary Engineering Report
• Final Engineering Report
• Pavement Design beyond that furnished in the Geotechnical Report.
• Runway Safety Area Inventory
• Engineering, architectural, or other professional services beyond those listed herein.
• Retaining walls or other significant structural design.
• Construction Administration Services, On-Site Construction Observation, and/or
Construction Materials Testing.
• Environmental Handling and Documentation, including wetlands identification or mitigation
plans or other work related to environmentally or historically (culturally) significant items.
• Permitting for environmentally sensitive areas.
• Coordination with FEMA and preparation/submittal of a CLOMR and/or LOMR.
• Services after construction, such as warranty follow-up, operations support, and Part 139
inspection support.
• The construction contract documents will require the Contractor to prepare, maintain, and
submit a SWPPP to DEQ
7. SCHEDULE
7.1. Garver shall begin work under this Agreement within a mutually agreeable schedule with the
Owner and execution of this Agreement. All design phases will start with a Notice to Proceed
(NTP) and stakeholder review comments from the subsequent phase.
Design Phase Calendar Days
60% Preliminary Design 6 Weeks from Agreement Execution, NTP, and Design Kickoff
Meeting
90% Final Design 5 Weeks from Receipt of 60% Preliminary Design Comments
100% Issued for Bid 2 Weeks from Receipt of 90% Final Design Comments
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
Exhibit B
Denton Enterprise Airport (DTO)
Taxiways H, J, and M Reconstruction
FEE SUMMARY
Title I Service Estimated Fees
Lump Sum Surveys (Lamb Star Engineering) $ 50,500.00
Lump Sum Geotechnical (ECS) $ 38,500.00
Lump Sum 60% Preliminary Design $ 200,000.00
Lump Sum 90% Final Design $ 161,000.00
Lump Sum Bidding Services $ 30,000.00
Subtotal for Title I Service 480,000.00$
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
Exhibit B
Denton Enterprise Airport (DTO)
Taxiways H, J, and M Reconstruction
60% Preliminary Design
WORK TASK DESCRIPTION E-5 E-4 E-3 E-2 E-1 D-2 AM-2
hr hr hr hr hr hr hr
1.Civil Engineering
Coordination with FAA 1 2
Coordination with Airport (DTO)2 2
Coordination with TxDOT 2
Internal Preliminary Design Kickoff Meeting 2 2 2 2 2 2
Internal Weekly Progress Meetings 2 4 4 4 4 4
Design Kickoff Meeting 2 2 2 2 2 2 2
Site Visit (3 people, 2 trip)12 12 12
Project Management Plan Development 4 6
Base Map Setup 2 4 8 16
Establish Design Criteria and Parameters 2 2 8
Review As-Built Drawings 2 4 8
Develop Preliminary Construction Safety and Phasing Plan 2 2 6 12
CSPP Submission to FAA Through OEAAA 2 4 8
CATEX Documentation 4 4 8 10 12
Develop Geometric Layout 2 4 12
Develop Horizontal Alignments 2 4 12
Develop Vertical Alignments 2 4 18
Develop Assemblies 1 2 6
Develop Corridor Model 2 8 30
Develop Fleet Mix 4 2 4
Develop Pavement Design 4 2 4
Pre-Development Flow Calculations 1 1 2 4
Post-Development Flow Calculations 1 1 2 4
Drainage Structural Design Calculations 2
Preliminary Plans
Cover Sheet 1 2 2
Sheet Index 1 2 2
General Notes 1 2 4
Project Layout Plan 1 4 8
Survey Control Plan 1 4 8
Construction Safety Plans 1 8 16
Construction Safety Details 1 4 8
Existing Conditions Plans 1 4 8
Erosion Control Plans 1 6 12
Erosion Control Details 1 4 8
Demolition Plans 4 8 16
Demolition Details 1 4 8
Drainage Plans 6 12 24
Drainage Details 2 2 4 8
Typical Sections 2 8 16
Paving Plans 2 8 16
Paving Details 1 4 8
Grading Plans 2 8 16
Grading Details 1 4 8
Joint Layout Plans 1 4 8
Joint Details 1 4 8
Pavement Marking Plans 2 8 16
Pavement Marking Details 1 4 8
Develop Preliminary Construction Contract Documents 4 4 4
Develop Preliminary Technical Specifications 4 4 4
Develop Preliminary Supplemental Specifications 4 4
Develop Preliminary Quantities 2 10 10
Develop Preliminary Opinions of Probable Construction Costs 4 6
Internal Quality Control (QC) Review 40 30 4 4 4 4 4
Incorporate QC Review Comments 2 4 8 24 24
Prepare for Preliminary Plan Review Meeting 2 2 6 2
Attend Preliminary Plan Review Meeting (3 People, on-site)6 6 6
Prepare and Distribute Preliminary Review Meeting Minutes and Tasks 1 2 4 2
Prepare and Submit Permanent Airspace Study 1 2 4
Subtotal - Civil Engineering 45 103 118 260 184 298 28
Hours 45 103 118 260 184 298 28
SUBTOTAL - SALARIES: $198,659.00
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
DIRECT NON-LABOR EXPENSES
Document Printing/Reproduction/Assembly $391.00
Postage/Freight/Courier $50.00
Office Supplies/Equipment $200.00
Computer Modeling/Software Use $500.00
Travel Costs $200.00
SUBTOTAL - DIRECT NON-LABOR EXPENSES: $1,341.00
SUBTOTAL: $200,000.00
SUBCONSULTANTS FEE: $0.00
TOTAL FEE: $200,000.00
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
Exhibit B
Denton Enterprise Airport (DTO)
Taxiways H, J, and M Reconstruction
90% Final Design
WORK TASK DESCRIPTION E-5 E-4 E-3 E-2 E-1 D-2 AM-2
hr hr hr hr hr hr hr
1.Civil Engineering
Coordination with FAA 2 2
Coordination with Airport (DTO)2 2
Coordination with TxDOT 2 2
Internal Weekly Progress Meetings 4 4 4 4 4 4
Site Visit (2 people, 2 trips)12 12
Prepare for Final Plan Review Meeting 2 2
Attend Final Plan Review Meeting (3 People, on-site)4 4 4 2
Prepare and Distribute Final Review Meeting Minutes and Tasks 2 2
Incorporate (Owner/FAA/State) CSPP Comments 2 4 4 4
Prepare Final Construction Safety and Phasing Plan 2 4 4
CSPP Submission to FAA Through OEAAA 2 4
Update Construction Safety and Phasing Plan 1 2
Update Geometric Layout 1 2
Update Horizontal Alignments 1 2
Update Vertical Alignments 1 2
Update Assemblies 1 2
Update Corridor Model 2 4
Update Fleet Mix using available data (TFMSC, 5010, etc.)2
Update Pavement Design 2
Update Drainage Basin Development 2 4
FAA Design Checklist 2 4
Final Plans
Cover Sheet 1 2
Sheet Index 1 2
General Notes 1 2 2
Project Layout Plan 1 1 4 4
Survey Control Plan 1 1 2 4
Construction Safety Plans 4 2 6 6
Construction Safety Details 1 6 6
Existing Conditions Plans 3 6 6
Erosion Control Plans 4 8 8
Erosion Control Details 1 4 8
Demolition Plans 1 2 6
Demolition Details 1 4
Drainage Plans 1 4 8
Drainage Details 1 4 8
Underdrain Plans 2 6 6
Underdrain Details 2 6 8
Utility Plans 1 6
Utility Details 1 6 8
Typical Sections 6 8
Paving Plans 1 4 8
Paving Details 2 8 16
Grading Plans 1 4 8 10
Grading Details 2 8 10
Joint Layout Plans 2 8 8
Joint Details 8 8
Elevation Plans 1 6 8 8
Elevation Details 1 8 8
Pavement Marking Plans 1 6 12
Pavement Marking Details 1 6 12
Cross Sections 6 12
Develop Final Technical Specifications 4 10
Develop Final Supplemental Specifications 4 10
Develop Final Quantities 5 10 10 10
Develop Final Opinions of Probable Construction Costs 4 8
Final Engineer's Report 2 12 5
Final Engineer's Report 2 12 5
Internal Quality Control (QC) Review 40 30
Incorporate QC Review Comments 3 6 12 12 12
Incorporate Final (Owner/FAA/State) Review Comments 6 6 6 6 4
Develop and Submission of CATEX 4
Subtotal - Civil Engineering 40 69 141 113 192 258 22
Hours 40 69 141 113 192 258 22
SUBTOTAL - SALARIES: $159,583.00
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
DIRECT NON-LABOR EXPENSES
Document Printing/Reproduction/Assembly $492.00
Postage/Freight/Courier $50.00
Office Supplies/Equipment $200.00
Computer Modeling/Software Use $500.00
Travel Costs $175.00
SUBTOTAL - DIRECT NON-LABOR EXPENSES: $1,417.00
SUBTOTAL: $161,000.00
SUBCONSULTANTS FEE: $0.00
TOTAL FEE: $161,000.00
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
Exhibit B
Denton Enterprise Airport (DTO)
Taxiways H, J, and M Reconstruction
Bidding Services
WORK TASK DESCRIPTION E-5 E-4 E-3 E-2 E-1 D-2 AM-2
hr hr hr hr hr hr hr
1.Civil Engineering
Coordination with TxDOT and DTO 4
Dispense Plans and Specs to Prospective Bidders 2 2
Review and Respond to Bidder Questions 8 12 12
Draft and Distribute Addendums 6 12
Prepare for Pre-Bid Meeting 6 6
Attend Pre-Bid Meeting (2 people, on-site)6 6
Bid Opening (2 people, on-site)3 3
Prepare Bid Tabulation 4
Evaluate Bids and Prepare Recommendation of Award 1 4 2
Prepare Contract Documents 4 6
Prepare Issued for Construction Plans and Specifications 4 12 12
Subtotal - Civil Engineering 1 45 16 61 2 12 0
Hours 1 45 16 61 2 12 0
SUBTOTAL - SALARIES: $29,666.00
DIRECT NON-LABOR EXPENSES
Document Printing/Reproduction/Assembly $179.00
Postage/Freight/Courier $75.00
Office Supplies/Equipment $0.00
Travel Costs $80.00
SUBTOTAL - DIRECT NON-LABOR EXPENSES: $334.00
SUBTOTAL: $30,000.00
SUBCONSULTANTS FEE: $0.00
TOTAL FEE: $30,000.00
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
Rates Rates
Engineers / Architects Resource Specialists
E-1 161.00$ RS-1 104.00$
E-2 189.00$ RS-2 137.00$
E-3 225.00$ RS-3 194.00$
E-4 265.00$ RS-4 268.00$
E-5 322.00$ RS-5 335.00$
E-6 397.00$ RS-6 411.00$
E-7 444.00$ RS-7 460.00$
Planners Environmental Specialists
P-1 194.00$ ES-1 104.00$
P-2 230.00$ ES-2 131.00$
P-3 261.00$ ES-3 168.00$
P-4 320.00$ ES-4 198.00$
P-5 380.00$ ES-5 248.00$
ES-6 318.00$
Designers ES-7 398.00$
D-1 145.00$ ES-8 450.00$
D-2 164.00$
D-3 194.00$ Project Controls
D-4 227.00$ PC-1 106.00$
D-5 274.00$ PC-2 140.00$
PC-3 178.00$
Technicians PC-4 229.00$
T-1 126.00$ PC-5 280.00$
T-2 170.00$ PC-6 361.00$
T-3 184.00$ PC-7 454.00$
T-4 218.00$
Management / Administration
Surveyors AM-1 75.00$
S-1 78.00$ AM-2 96.00$
S-2 93.00$ AM-3 134.00$
S-3 128.00$ AM-4 171.00$
S-4 175.00$ AM-5 209.00$
S-5 230.00$ AM-6 272.00$
S-6 268.00$ AM-7 320.00$
S-7 291.00$ M-1 510.00$
S-8 351.00$
2-Man Crew (Survey) 344.00$
3-Man Crew (Survey) 403.00$
2-Man Crew (GPS Survey) 344.00$
3-Man Crew (GPS Survey) 403.00$
Construction Observation
C-1 112.00$
C-2 140.00$
C-3 171.00$
C-4 221.00$
C-5 259.00$
Agreement for Professional Services
Taxiways H, J, and M Reconstruction Garver Project No. 2502991
Garver Hourly Rate Schedule: July 2023 - June 2024
Classification Classification
Exhibit C
Denton Enterprise Airport (DTO)
Taxiways H, J, and M Reconstruction
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
Exhibit DDocusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
ECS Southwest, LLP
Scope and Fee for Subsurface Exploration and Geotechnical
Engineering Services
DTO Taxiways H, J and M Reconstruction
5000 Airport Road
Denton, Denton County, Texas
ECS ID No. 63:4557-GP (Rev.1)
March 19, 2026
Exhibit EDocusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
ECS Southwest, LLP March 19, 2026
ECS ID No: 63:4557-GP (Rev.1)
Page | 2
March 19, 2026
Mr. Austin Hayes
Garver
3000 Internet Blvd
Suite 400
Frisco, Texas 75034
ECS ID No. 63:4557-GP (Rev.1)
Reference: Scope and Fee for Subsurface Exploration and Geotechnical Engineering Services
DTO Taxiways H, J and M Reconstruction
5000 Airport Road
Denton, Denton County, Texas
Dear Mr. Hayes:
As requested, ECS Southwest, LLP (ECS), is pleased to be selected for this project and providing the
following lump sum scope and fee for subsurface exploration and geotechnical engineering services for
the above-mentioned project. Our understanding of the project is based on our review of the available
geological and geotechnical information in our files in vicinity of the site and Request for Geotechnical
Proposal (prepared by Garver, LLC., dated March 2, 2026) and geotechnical exhibit – Taxiways H, J and M
(prepared by Garver, LLC., dated September 2025) in the email dated March 2, 2026. This scope and fee
outlines our understanding of the project, the proposed scope of services, activity schedule, fees, and
authorization requirements.
PROJECT BACKGROUND INFORMATION
Existing Site Conditions
The project site is located at 5000 Airport Road in Denton, Denton County, Texas (GPS: 33.2000 N, 97.1938
W). ECS did not visit the site prior to preparing this scope and fee. Based on Google Earth aerial maps, the
site is developed with structures and pavements. The existing Taxiways H, J, and M pavement are
constructed from asphalt. Based on the information provided by the client, distresses including fatigue
cracking, longitudinal and transverse cracks, and PCC shoving down the entire length of the taxiway were
observed on the site.
Project Description
Based on the information and plan provided, we understand the proposed project will include the
reconstruction of Taxiways H, J and M. The taxiway and apron will be used by aircraft having gross weights
of 60,000 lbs or more. Based on the information provided in Request for Geotechnical Proposal, final
ECS SOUTHWEST, LLP TX Registered Engineering No. F-8461
Geotechnical Construction Materials Environmental Facilities
2621 WESTSIDE DRIVE, FORT WORTH, TX 76107 T: (682) 350-2250 F: (817) 847-8616
ECS Florida, LLC ECS Mid-Atlantic, LLC ECS Midwest, LLC ECS Pacific, Inc. ECS Southeast, LLC ECS Southwest, LLP
ECS New York Engineering, PLLC – An Associate of ECS Group of Companies www.ecslimited.com
“ONE FIRM. ONE MISSION.”
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
ECS Southwest, LLP March 19, 2026
ECS ID No: 63:4557-GP (Rev.1)
Page | 3
grade of new pavement will roughly match existing pavement grades to promote surface drainage from
the taxiways to the turfed areas adjacent to the taxiways.
Please note that a topographic drawing and grading plan were not available at the time of this scope and
fee. ECS should be provided with topographic drawings and a grading plan prior to initiating our services
to review our proposed depth of borings regarding actual cut/fill depths and make changes to our
proposed scope and fee as necessary.
SCOPE OF SERVICES
Our integrated services will include drilling borings by drilling crews based on instructions provided by
ECS. Our services will also include laboratory testing of representative soil samples, and engineering
analyses presented in a site-specific engineering report.
Utility Clearance
Per state law, we will contact Texas 811 the public utility to locate underground utilities at the site.
Typically, Texas 811 will not locate utilities beyond the point of distribution (meters or gauge points) on
private property. The risk of hitting utilities that Texas 811 did not mark can be reduced by engaging a
private utility locating service. The risks include hitting gas lines, electrical lines, fiber optic lines, and many
other utility service lines. This can result in electrocution, gas leaks or explosions, loss of services to
businesses as well as tremendous costs for lost business, interruption of service, and repair along with
potential legal liability.
We have included the cost of a private utility line locator in our “Base Services”. Private utility locator
services can aid in identifying utilities that incorporate significant iron content in the conduit materials.
However, utilities without significant ferrous (iron) content are more difficult to detect. These include
most sanitary sewer alignments, copper or PVC water lines, fiber optic lines without tracer ribbons, copper
electric lines with no surface exposure, drainage tiles/pipes, irrigation lines, etc.
Using a private utility locator does not guarantee that all utilities will be identified. However, this service
lowers the risk and potential liability of the client while also protecting the safety of our field exploration
crews.
We will coordinate our exploration locations around marked utilities and utilities pointed out to us by the
owner/client. However, we will not be responsible for any utilities not marked or not pointed out to us by
the landowner or client.
Site Access
Based on our review of available aerial photographs, the site appears to be accessible to a truck-mounted
drilling rig.
Regarding site access, we have made the following assumptions:
• This scope and fee assume that no special permits will be required. The pavement coring and
drilling will take place during nighttime (10 pm to 6 am).
• Landowner notification will be provided by the client. ECS will work with the project team in
providing site access diagrams for the drill rig as needed, but actual coordination with
landowners to obtain access permission will be provided by the client.
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
ECS Southwest, LLP March 19, 2026
ECS ID No: 63:4557-GP (Rev.1)
Page | 4
• Taxing within the work areas will be blocked off prior to our arrival. ECS cannot be held
responsible for damage to, nor the cleanliness of, vehicles not moved from the work area.
Field Exploration
ECS proposes to perform the following in general accordance with the local standards and practices listed:
a. Field locate the test locations by handheld GPS unit / taping and pacing from existing site features /
available plans. Elevations will be interpolated from the plans provided/or referenced from published
topographical maps.
b. Obtain a public utility locate ticket for location of underground lines. See further information in the
Utility Clearance section above.
c. Private utility locate service to clear the boring locations.
d. Mobilize a pavement coring crew and core the pavement in ten (10) locations as requested.
e. Mobilize a truck mounted drilling rig to the site.
f. As requested, ten (10) borings will be drilled on the project site. These boring locations will be cored
and drilled within the taxiway areas to a depth of 10 feet below the existing grades. The approximate
locations are shown in the figure below.
g. Perform testing and sampling in general accordance with ASTM standards and local practices.
h. Measure the depth of groundwater within each exploration location at the time of drilling and prior
to backfilling.
i. Obtain bulk samples of auger cuttings from select borings for laboratory testing.
The explorations will be extended to the depths listed above or to mechanical refusal (shallow rock or
other impenetrable obstructions), whichever occurs first.
Site Departure Conditions
Upon completion of subsurface exploration, we will backfill each of the locations with the soil removed
and mound the excess spoils back up over the test location. In pavement areas, we will patch the asphalt
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
ECS Southwest, LLP March 19, 2026
ECS ID No: 63:4557-GP (Rev.1)
Page | 5
or concrete surface with cold mix asphalt patch or quick setting concrete of an equivalent or greater
thickness. Some post drilling settlement of the boreholes should be expected and may require future
maintenance to repair any settlement and prevent a tripping hazard. This maintenance is not included in
our scope of services or fees. No other restoration will be provided. ECS will not be responsible for
restoration of, but not limited to the following: grass, shrubs, trees, flower beds, or ruts caused by drilling
operations. The client must communicate areas that must not be disturbed in advance of field operations.
Typically, we will not provide site repairs beyond what is outlined above unless specifically contracted.
Alternatively, we will remove excess spoils from job sites and dispose of them in an approved manner for
a negotiated fee.
Please note that some disturbance to off-pavement, gravel-covered, grass-covered areas, including the
possible cutting of trees, or running over of brush and understory in wooded areas might occur. We will
attempt to limit such disturbance; however, we have not budgeted for site repairs including filling of tire
ruts, seeding of lawn areas, replacement of bushes or the planting of trees, etc. If necessary, additional
site repairs can be provided at an additional cost.
Laboratory Testing
Upon completion of field exploration operations, the samples will be returned to our laboratory for
further identification, visual classification, and testing. Laboratory testing may include the following:
LABORATORY TEST
Natural Moisture Content
Gradation Analysis
Atterberg Limits
Standard/Modified Proctor
California Bearing Ration (CBR)
Swell Test
Unconfined Compressive Strength of Soil
Sulfate Content, pH, Organic content
Lime pH Series
Engineering Report
Upon completion of the field exploration, laboratory testing, and engineering analyses, we will prepare a
written engineering report that will include:
a. A review of published soils mapping and/or geologic information.
b. Observations from our site reconnaissance and personnel on the drill rig, including current site
conditions, surface drainage features, and surface topographic conditions, and/or available satellite
imagery.
c. A description of the field exploration and laboratory tests performed.
d. A site location diagram and a field exploration diagram.
e. Final logs of the soil borings in accordance with industry standard practices for geotechnical
engineering. Elevations will be interpolated from civil drawings or referenced from topographic
information that you supply.
f. Photographs with a visual scale indicating pavement thickness for all pavement cores.
g. The results of the laboratory tests will be plotted on the final exploration logs and/or included on
separate test report pages.
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
ECS Southwest, LLP March 19, 2026
ECS ID No: 63:4557-GP (Rev.1)
Page | 6
h. Discussion of the subsurface materials encountered along with groundwater conditions observed.
i. Subsurface cross sections/profiles may be included that graphically represent the subsurface
conditions.
j. Recommendations for preparation of subgrade for the reconstructed taxiway pavement (lime treated
subgrade, cement treated subgrade, cement treated base, etc.).
k. Recommendations regarding preparation of existing soils (native or otherwise) including
recommendations regarding undercut and backfill.
l. Pavement design value recommendations – ECS to provide k-value, CBR, resilient modulus, etc
recommended for pavement design. Garver will perform the pavement design based on the subgrade
recommendations. All paving materials will follow the FAA specification requirements for
construction.
m. Testing and recommendations for pavement design related to sulfates.
n. Recommendations regarding surface and subsurface drainage, during and after construction.
o. Recommendations for embankment design and construction, if required.
p. Recommendations for suitable configuration(s) of cut slopes, fill slopes, temporary excavations, if
required.
FEE
ECS will provide the services outlined in this scope and fee for a lump sum fee of $33,400.00.
Our fee assumes that the site is accessible based upon our assumptions detailed in this document. If
additional services are requested or required based on differing site conditions, we will contact you for
verbal and written authorization to proceed with the additional services.
SCHEDULE
Our ability to access the site and perform the field exploration may be impacted by precipitation, excessive
temperatures, or other atmospheric conditions. Field exploration will be performed during nighttime (10
pm to 6 am) Monday through Friday.
We have assumed that the client will assist in accessing the site (with the current site owners/occupants).
We anticipate being able to mobilize to the site within approximately 2 to 3 weeks after receiving
authorization to proceed, notification that on-site personnel if any has been made, and upon clearing
utilities.
We anticipate that the drilling operations will require about 1 to 2 nights, and that the laboratory testing,
will require about 7 to 14 days, followed by our engineering analyses. For time budget purposes, the entire
scope should take about 5 to 7 weeks from initial authorization through final report submission. If there
is a specific due date for the report, please let us know. Verbal comments on findings can be provided
within 7 days of completion of the borings, if requested.
CLOSING
If other services are required because of unexpected field conditions, or because of a request for
additional services, they will be invoiced in accordance with a negotiated fee. Before modifying or expanding the extent of our exploration program, we will contact you for your review and authorization.
Our insurance carrier requires that we receive written authorization prior to initiation of work, and a
signed contract prior to the release of any work product. This letter is the agreement for our services.
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
ECS Southwest, LLP March 19, 2026
ECS ID No: 63:4557-GP (Rev.1)
Page | 7
Your acceptance of this scope and fee may be indicated by signing and returning a copy of this document
to us. We are pleased to have this opportunity to offer our services and look forward to working with you
on the project.
Respectfully submitted,
ECS SOUTHWEST, LLP
Ishtiaque Hossain, PhD, P.E. Michael Batuna, P.E.
Vice President, Office Manager Vice President, Asst. Office Manager
IHossain@ecslimited.com MBatuna@ecslimited.com
Enclosures: Scope and Fee Acceptance Sheet
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
ECS Southwest, LLP March 19, 2026
ECS ID No: 63:4557-GP (Rev.1)
Page | 8
SCOPE AND FEE ACCEPTANCE
Scope and Fee No.: 63:4557-GP (Rev.1)
Scope of Work: Subsurface Exploration and Geotechnical Engineering Services
Project: DTO Taxiways H, J and M Reconstruction
Location: 5000 Airport Road, Denton, Denton County, Texas
Base Services: $33,400.00
Client Signature: Date:
Printed Name: Title:
Please complete this page and return one copy to ECS to indicate acceptance of this scope and fee and to
initiate work on the above-referenced project.
BILLING INFORMATION
(please print or type)
Contact Person:
Telephone No. of Contact Person:
Email of Contact Person:
Party Responsible for Payment:
Company Name:
Billing Address:
Telephone Number:
Accounts Payable Email Address:
Client Project/Account Number:
Special Conditions for Invoices:
ECS offers a full array of services to assist you with all phases of your project, including but not limited to:
- Phase I, II and III Environmental
Site Assessments - Wetlands Delineations - Asbestos/Lead Paint Services
Indoor Air Quality/Mold Services - Natural Resources - Groundwater Remediation
- Third Party Mechanical,
Electrical, Plumbing Inspections
Services - Construction Materials Testing
and Special Inspections - LEED® Consulting Services - Geo-Structural Design
- Building Envelope, Roofing, and
Waterproofing Consultation - Specialty Materials and
Forensics Testing - Monitoring Services - Pre- and Post-Construction
Condition Assessments
Docusign Envelope ID: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04
Certificate Of Completion
Envelope Id: F6B8289A-8A1F-4254-BEB5-F3C8B0386F04 Status: Completed
Subject: Please DocuSign: City Council Contract 8209 Airport Engineering Services - Amendment 3
Source Envelope:
Document Pages: 50 Signatures: 5 Envelope Originator:
Certificate Pages: 6 Initials: 1 Christina Dormady
AutoNav: Enabled
EnvelopeId Stamping: Enabled
Time Zone: (UTC-06:00) Central Time (US & Canada)
901B Texas Street
Denton, TX 76209
christina.dormady@cityofdenton.com
IP Address: 198.49.140.10
Record Tracking
Status: Original
5/8/2026 11:37:49 AM
Holder: Christina Dormady
christina.dormady@cityofdenton.com
Location: DocuSign
Signer Events Signature Timestamp
Christina Dormady
christina.dormady@cityofdenton.com
Buyer
City of Denton
Security Level: Email, Account Authentication
(None)
Completed
Using IP Address: 198.49.140.10
Sent: 5/8/2026 11:43:15 AM
Viewed: 5/8/2026 11:43:34 AM
Signed: 5/8/2026 11:44:33 AM
Electronic Record and Signature Disclosure:
Not Offered via Docusign
Lori Hewell
lori.hewell@cityofdenton.com
Purchasing Manager
City of Denton
Security Level: Email, Account Authentication
(None)
Signature Adoption: Pre-selected Style
Using IP Address: 198.49.140.104
Sent: 5/8/2026 11:44:36 AM
Viewed: 5/11/2026 7:17:44 AM
Signed: 5/11/2026 7:18:45 AM
Electronic Record and Signature Disclosure:
Not Offered via Docusign
Leah Bush
leah.bush@cityofdenton.com
Assistant City Attorney
Security Level: Email, Account Authentication
(None)Signature Adoption: Pre-selected Style
Using IP Address: 198.49.140.10
Sent: 5/11/2026 7:18:47 AM
Viewed: 5/11/2026 9:09:52 AM
Signed: 5/11/2026 9:40:10 AM
Electronic Record and Signature Disclosure:
Not Offered via Docusign
Mitchell McAnally
MRMcAnally@GarverUSA.com
Vice President
Security Level: Email, Account Authentication
(None)Signature Adoption: Pre-selected Style
Using IP Address: 97.77.16.177
Sent: 5/11/2026 9:40:14 AM
Resent: 5/26/2026 9:07:41 AM
Resent: 6/2/2026 8:43:17 AM
Resent: 6/22/2026 8:29:44 AM
Viewed: 6/22/2026 8:42:18 AM
Signed: 6/22/2026 8:45:23 AM
Electronic Record and Signature Disclosure:
Accepted: 5/11/2026 9:42:05 AM
ID: e44bd37f-43f7-4f71-80cc-2664e8d5d0a5
Signer Events Signature Timestamp
Ryan Adams
Ryan.adams@cityofdenton.com
Director of Airport
Security Level: Email, Account Authentication
(None)Signature Adoption: Drawn on Device
Using IP Address: 2a09:bac2:bab6:2e46::49c:11
Signed using mobile
Sent: 6/22/2026 8:45:25 AM
Viewed: 6/22/2026 8:51:28 AM
Signed: 6/22/2026 8:52:28 AM
Electronic Record and Signature Disclosure:
Accepted: 6/22/2026 8:51:28 AM
ID: 868f9f4b-799f-491b-812a-924538d65b03
Cheyenne Defee
cheyenne.defee@cityofdenton.com
Procurement Administration Supervisor
City of Denton
Security Level: Email, Account Authentication
(None)
Completed
Using IP Address: 198.49.140.10
Sent: 6/22/2026 8:52:32 AM
Viewed: 7/15/2026 10:38:43 AM
Signed: 7/15/2026 10:39:09 AM
Electronic Record and Signature Disclosure:
Not Offered via Docusign
Cassey Ogden
Cassey.Ogden@cityofdenton.com
Interim City Manager
City of Denton
Security Level: Email, Account Authentication
(None)
Signature Adoption: Pre-selected Style
Using IP Address: 198.49.140.10
Sent: 7/15/2026 10:39:12 AM
Viewed: 7/15/2026 11:46:47 AM
Signed: 7/15/2026 11:46:52 AM
Electronic Record and Signature Disclosure:
Not Offered via Docusign
Kristi Fogle
Kristi.Fogle@cityofdenton.com
Chief of Staff
Security Level: Email, Account Authentication
(None)Signature Adoption: Pre-selected Style
Using IP Address: 198.49.140.10
Sent: 7/15/2026 11:46:55 AM
Viewed: 7/15/2026 2:23:54 PM
Signed: 7/15/2026 2:29:04 PM
Electronic Record and Signature Disclosure:
Accepted: 7/15/2026 2:23:54 PM
ID: d1b5e934-6be3-4a41-ad22-0dade3f58bab
In Person Signer Events Signature Timestamp
Editor Delivery Events Status Timestamp
Agent Delivery Events Status Timestamp
Intermediary Delivery Events Status Timestamp
Certified Delivery Events Status Timestamp
Carbon Copy Events Status Timestamp
Cheyenne Defee
cheyenne.defee@cityofdenton.com
Procurement Administration Supervisor
City of Denton
Security Level: Email, Account Authentication
(None)
Sent: 5/8/2026 11:44:36 AM
Electronic Record and Signature Disclosure:
Not Offered via Docusign
Carbon Copy Events Status Timestamp
Gretna Jones
gretna.jones@cityofdenton.com
Legal Secretary
City of Denton
Security Level: Email, Account Authentication
(None)
Sent: 6/22/2026 8:52:31 AM
Viewed: 6/23/2026 1:00:17 PM
Electronic Record and Signature Disclosure:
Not Offered via Docusign
City Secretary Office
citysecretary@cityofdenton.com
Security Level: Email, Account Authentication
(None)
Sent: 7/15/2026 2:29:07 PM
Electronic Record and Signature Disclosure:
Not Offered via Docusign
Chase Patterson
chase.patterson@cityofdenton.com
Security Level: Email, Account Authentication
(None)
Sent: 7/15/2026 2:29:08 PM
Electronic Record and Signature Disclosure:
Accepted: 1/16/2026 8:54:46 AM
ID: 128aeebf-f582-4d7d-8915-282ecdfa3749
Witness Events Signature Timestamp
Notary Events Signature Timestamp
Envelope Summary Events Status Timestamps
Envelope Sent Hashed/Encrypted 5/8/2026 11:43:15 AM
Envelope Updated Security Checked 6/4/2026 2:01:41 PM
Envelope Updated Security Checked 6/4/2026 2:01:42 PM
Certified Delivered Security Checked 7/15/2026 2:23:54 PM
Signing Complete Security Checked 7/15/2026 2:29:04 PM
Completed Security Checked 7/15/2026 2:29:08 PM
Payment Events Status Timestamps
Electronic Record and Signature Disclosure
ELECTRONIC RECORD AND SIGNATURE DISCLOSURE
From time to time, City of Denton (we, us or Company) may be required by law to provide to
you certain written notices or disclosures. Described below are the terms and conditions for
providing to you such notices and disclosures electronically through your DocuSign, Inc.
(DocuSign) Express user account. Please read the information below carefully and thoroughly,
and if you can access this information electronically to your satisfaction and agree to these terms
and conditions, please confirm your agreement by clicking the 'I agree' button at the bottom of
this document.
Getting paper copies
At any time, you may request from us a paper copy of any record provided or made available
electronically to you by us. For such copies, as long as you are an authorized user of the
DocuSign system you will have the ability to download and print any documents we send to you
through your DocuSign user account for a limited period of time (usually 30 days) after such
documents are first sent to you. After such time, if you wish for us to send you paper copies of
any such documents from our office to you, you will be charged a $0.00 per-page fee. You may
request delivery of such paper copies from us by following the procedure described below.
Withdrawing your consent
If you decide to receive notices and disclosures from us electronically, you may at any time
change your mind and tell us that thereafter you want to receive required notices and disclosures
only in paper format. How you must inform us of your decision to receive future notices and
disclosure in paper format and withdraw your consent to receive notices and disclosures
electronically is described below.
Consequences of changing your mind
If you elect to receive required notices and disclosures only in paper format, it will slow the
speed at which we can complete certain steps in transactions with you and delivering services to
you because we will need first to send the required notices or disclosures to you in paper format,
and then wait until we receive back from you your acknowledgment of your receipt of such
paper notices or disclosures. To indicate to us that you are changing your mind, you must
withdraw your consent using the DocuSign 'Withdraw Consent' form on the signing page of your
DocuSign account. This will indicate to us that you have withdrawn your consent to receive
required notices and disclosures electronically from us and you will no longer be able to use your
DocuSign Express user account to receive required notices and consents electronically from us
or to sign electronically documents from us.
All notices and disclosures will be sent to you electronically
Unless you tell us otherwise in accordance with the procedures described herein, we will provide
electronically to you through your DocuSign user account all required notices, disclosures,
authorizations, acknowledgements, and other documents that are required to be provided or
made available to you during the course of our relationship with you. To reduce the chance of
you inadvertently not receiving any notice or disclosure, we prefer to provide all of the required
notices and disclosures to you by the same method and to the same address that you have given
us. Thus, you can receive all the disclosures and notices electronically or in paper format through
the paper mail delivery system. If you do not agree with this process, please let us know as
described below. Please also see the paragraph immediately above that describes the
consequences of your electing not to receive delivery of the notices and disclosures
electronically from us.
Electronic Record and Signature Disclosure created on: 7/21/2017 3:59:03 PM
Parties agreed to: Mitchell McAnally, Ryan Adams, Kristi Fogle, Chase Patterson
How to contact City of Denton:
You may contact us to let us know of your changes as to how we may contact you electronically,
to request paper copies of certain information from us, and to withdraw your prior consent to
receive notices and disclosures electronically as follows:
To contact us by email send messages to: purchasing@cityofdenton.com
To advise City of Denton of your new e-mail address
To let us know of a change in your e-mail address where we should send notices and disclosures
electronically to you, you must send an email message to us at melissa.kraft@cityofdenton.com
and in the body of such request you must state: your previous e-mail address, your new e-mail
address. We do not require any other information from you to change your email address..
In addition, you must notify DocuSign, Inc to arrange for your new email address to be reflected
in your DocuSign account by following the process for changing e-mail in DocuSign.
To request paper copies from City of Denton
To request delivery from us of paper copies of the notices and disclosures previously provided
by us to you electronically, you must send us an e-mail to purchasing@cityofdenton.com and in
the body of such request you must state your e-mail address, full name, US Postal address, and
telephone number. We will bill you for any fees at that time, if any.
To withdraw your consent with City of Denton
To inform us that you no longer want to receive future notices and disclosures in electronic
format you may:
i. decline to sign a document from within your DocuSign account, and on the subsequent
page, select the check-box indicating you wish to withdraw your consent, or you may;
ii. send us an e-mail to purchasing@cityofdenton.com and in the body of such request you
must state your e-mail, full name, IS Postal Address, telephone number, and account
number. We do not need any other information from you to withdraw consent.. The
consequences of your withdrawing consent for online documents will be that transactions
may take a longer time to process..
Required hardware and software
Operating Systems: Windows2000? or WindowsXP?
Browsers (for SENDERS): Internet Explorer 6.0? or above
Browsers (for SIGNERS): Internet Explorer 6.0?, Mozilla FireFox 1.0,
NetScape 7.2 (or above)
Email: Access to a valid email account
Screen Resolution: 800 x 600 minimum
Enabled Security Settings:
•Allow per session cookies
•Users accessing the internet behind a Proxy
Server must enable HTTP 1.1 settings via
proxy connection
** These minimum requirements are subject to change. If these requirements change, we will
provide you with an email message at the email address we have on file for you at that time
providing you with the revised hardware and software requirements, at which time you will
have the right to withdraw your consent.
Acknowledging your access and consent to receive materials electronically
To confirm to us that you can access this information electronically, which will be similar to
other electronic notices and disclosures that we will provide to you, please verify that you
were able to read this electronic disclosure and that you also were able to print on paper or
electronically save this page for your future reference and access or that you were able to
e-mail this disclosure and consent to an address where you will be able to print on paper or
save it for your future reference and access. Further, if you consent to receiving notices and
disclosures exclusively in electronic format on the terms and conditions described above,
please let us know by clicking the 'I agree' button below.
By checking the 'I Agree' box, I confirm that:
• I can access and read this Electronic CONSENT TO ELECTRONIC RECEIPT OF
ELECTRONIC RECORD AND SIGNATURE DISCLOSURES document; and
• I can print on paper the disclosure or save or send the disclosure to a place where I can
print it, for future reference and access; and
• Until or unless I notify City of Denton as described above, I consent to receive from
exclusively through electronic means all notices, disclosures, authorizations,
acknowledgements, and other documents that are required to be provided or made