Exhibit 3 - Project ScheduleID Task NameDuration Start Finish1Hickory Creek Interceptor1561 daysFri 7/15/16Fri 7/8/222Completed Milestones983 daysFri 7/15/16Tue 4/21/203Engineering NTP0 daysFri 7/15/16Fri 7/15/164Project Kickoff Meeting0 daysWed 8/3/16Wed 8/3/165Survey93 daysFri 8/12/16Tue 12/20/166Level B SUE93 daysMon 9/12/16Wed 1/18/177Route Discussion/Selection Meeting0 daysWed 10/19/16Wed 10/19/16830% Design Submittal0 daysThu 1/12/17Thu 1/12/17930% Review Comments Received0 daysMon 3/6/17Mon 3/6/171060% Design Submittal0 daysTue 4/11/17Tue 4/11/171160% Review Meeting0 daysFri 6/2/17Fri 6/2/171290% Design Submittal0 daysWed 9/27/17Wed 9/27/171390% Review Comments Received0 daysWed 11/1/17Wed 11/1/1714Graveyard Siphon Analysis / Proposal Effort / Option Abandoned71 daysMon 11/20/17Mon 2/26/181590% Review Meeting0 daysFri 5/25/18Fri 5/25/1816100% Review Submittal0 daysFri 8/24/18Fri 8/24/1817100% Review Comments Received0 daysFri 9/7/18Fri 9/7/1818Plans Finalized (Sealed)0 daysWed 10/10/18Wed 10/10/1819Easement Acquisition743 daysFri 6/16/17Tue 4/21/2020Easement Documents Preparation 63 daysFri 6/16/17Tue 9/12/1721City Easement Acquisition680 daysWed 9/13/17Tue 4/21/2022Recent / Upcoming Milestones759 daysTue 8/13/19Fri 7/8/2223Recent Efforts294 daysTue 8/13/19Fri 9/25/20242019 Project Re-Kickoff Meeting0 daysTue 8/13/19Tue 8/13/19252019 Project Update Meeting0 daysThu 9/5/19Thu 9/5/1926City Provide Spec Standards / Desired Plan Updates10 daysThu 9/5/19Wed 9/18/1927FNI Prepare (Revised 100% )Draft Submittal20 daysThu 9/19/19Wed 10/16/1928Draft (Revised 100%) Submittal Internal QC7 daysThu 10/17/19Fri 10/25/1929Draft (Revised 100%) Submittal to City0 daysFri 10/25/19Fri 10/25/1930City Review Period / Funding Hold188 daysMon 10/28/19Wed 7/15/20312020 Project Re-Kickoff / ENV/ARCH Coordination32 daysThu 7/16/20Fri 8/28/207/158/310/191/123/64/116/29/2711/15/258/249/710/108/139/510/25JulOctJanAprJulOctJanAprJulOctJanAprJulOctJanAprJulOctJanAprJulOctJanAprJul201720182019202020212022City of DentonHickory Creek Interceptor3/4/2021Page 1 ID Task NameDuration Start Finish32Dry Fork Coordination & Mods / Archeology Commencement20 daysMon 8/31/20Fri 9/25/2033Phase I Archeology84 daysMon 9/28/20Thu 1/21/2134THC Permit Application Prep7 daysMon 9/28/20Tue 10/6/2035THC Permit Application Review / Approval5 daysWed 10/7/20Tue 10/13/2036Field Work Prep/Work15 daysWed 10/14/20Tue 11/3/2037Report Prep / Draft Submittal16 daysWed 11/4/20Wed 11/25/2038FNI Review3 daysThu 11/26/20Mon 11/30/2039City Review13 daysTue 12/1/20Thu 12/17/2040Submittal to THC / Review Period25 daysFri 12/18/20Thu 1/21/2141Phase II Archeology218 daysFri 2/26/21Tue 12/28/2142Contract Amendment to City4 daysFri 2/26/21Wed 3/3/2143PUB / City Council Approval Window / NTP14 daysThu 3/4/21Tue 3/23/2144Pre-Field Coordination4 wksWed 3/24/21Tue 4/20/2145Field Work4 wksWed 4/21/21Tue 5/18/2146Analysis / Interim Report4 wksWed 5/19/21Tue 6/15/2147THC Response Window4 wksWed 6/16/21Tue 7/13/2148Anticipated Construction Clearing Date0 daysTue 7/13/21Tue 7/13/2149Curation / Final Reporting Period24 wksWed 7/14/21Tue 12/28/2150Design Aspects60 daysMon 1/18/21Fri 4/9/2151Finalize Remaining Plans / Specs Items5 daysMon 1/18/21Fri 1/22/2152Internal QC5 daysMon 1/25/21Fri 1/29/2153Seal Plans / Specs10 daysMon 2/1/21Fri 2/12/2154Submit TCEQ Letter / Submit RR Permit40 daysMon 2/15/21Fri 4/9/2155Option A - Advertise Now350 daysSun 3/7/21Thu 7/7/2256Option A - Bid Phase60 daysMon 3/8/21Fri 5/28/2157Advertisement20 daysMon 3/8/21Fri 4/2/2158Award20 daysMon 4/5/21Fri 4/30/2159Execution20 daysMon 5/3/21Fri 5/28/2160Option A - Construction Phase290 daysMon 5/31/21Fri 7/8/2261Construction NTP10 daysMon 5/31/21Fri 6/11/2162Construction 260 daysMon 6/14/21Fri 6/10/2263Record Phase20 daysMon 6/13/22Fri 7/8/227/13JulOctJanAprJulOctJanAprJulOctJanAprJulOctJanAprJulOctJanAprJulOctJanAprJul201720182019202020212022City of DentonHickory Creek Interceptor3/4/2021Page 2