Exhibit 5 - PresentationHickory Creek Interceptor Phases 1&2 Construction Contract Award ID 21-953 PUB21-086 Public Utilities 5/24/21 City Council 5/25/21 Project Manager: Tracy L. Beck, P.E. PROJECT SCOPE & BENEFITS •Scope: Installation of approximately 13,000 linear feet (2.46 miles) of a variety sizes of sewer main from 30, 36, 42, 48 and 54-inch along Hickory Creek between Fort Worth Drive (US 377) and I-35W •Benefits Increase the carrying capacity. The existing interceptor was installed in the 1980s and needs expanded capacity to accommodate future growth projected to occur in the Hickory Creek Basin. PUB21-086 and File ID 21-953 205/24/21 and 5/25/21 BID RESPONSE SUMMARY IFB* Ranking Company City Response Total (Base Bid) 1 Mountain Cascade of Texas Alvarado $7,175,985.00 2 Blue Star Utilities Venus $7,392,908.00 3 Western Municipal Construction of Texas, LLC.Hickory Creek $7,912,030.00 4 Wilson Contractor Services, LLC Denton $7,774,467.00 5 Thalle Construction Company Alvarado $8,189,882.00 6 S.J. Louis Construction of Texas, Ltd.Mansfield $8,273,398.50 05/24/21 and 5/25/21 3 * IFB (Invitation for Bid) solicitation methodology was used to select lowest responsible bid (aka “Low Bid”). PUB21-086 and File ID 21-953 SCHEDULE (Subject to change pending Archeological Findings) ✓Advertise 03/14/21 ✓Design Amend#1 (PUB/Council) 03/22-23/21 ✓Pre-Bid Meeting 03/31/21 ✓Solicitation Closed, Bids Open 04/13/21 Target PUB (Construction)05/24/21 Target Council (Construction)05/25/21 Target Construction Completion June 2022 4 41DTN580 41DTN624 05/24/21 and 5/25/21 PUB21-086 and File ID 21-953 STAFF RECOMMENDATION •Adoption of an ordinance awarding the construction contract for the Hickory Creek Interceptor Phase I & II Project to Mountain Cascade Construction of Texas. 5 ✓Project funding is currently available ✓Project funding sources include: Wastewater Project CO Funds 05/24/21 and 5/25/21 Contract Amount $ 7,175,985.00 5% Contingency $ 358,799.25 Total Not-to-Exceed Amount $ 7,534,784.25 PUB21-086 and File ID 21-953 Questions? 605/24/21 and 5/25/21 PUB21-086 and File ID 21-953 Design: Freese and Nichols –File #6479, PO #177323 Construction: Mountain Cascade of Texas –File #7252, PO #Pending BUDGET –Contract Summary 7 Original Contract Amount $654,135.00 Amendment #1 $310,420.00 Total Not-to-Exceed Amount $964,555.00 Contract Amount $ 7,175,985.00 5% Contingency $ 358,799.25 Total Not-to-Exceed Amount $ 7,534,784.25 05/24/21 and 5/25/21 PUB21-086 and File ID 21-953 Following Slides are for reference 05/24/21 and 5/25/21 8PUB21-086 and File ID 21-953 CURRENT ACTIVITIES ▪Phase 1 Archeological Survey completed. Both sites exhibit burned sandstone rock concentrations and mussel shell debris requiring a Phase 2 Archeological Study ▪Construction project bidding initiated restricting work in historically-sensitive areas until cleared ▪Coordination with Dry Fork Interceptor Project and the Hickory Creek Interceptor Phase 3 Project 905/24/21 and 5/25/21 PUB21-086 and File ID 21-953 Southern Site near US 377 05/24/21 and 5/25/21 10PUB21-086 and File ID 21-953 05/24/21 and 5/25/21 11 Northern Site near Bonnie Brae PUB21-086 and File ID 21-953 PROJECT SCOPE: Hickory Creek Interceptor Phase III ▪Construct approximately 9,700 LF of 30” sewer line with an improved alignment to replace the existing 12”. Also include the rehabilitation of an existing 12” sewer line that crosses the creek. Drill Down Meeting 12DATEPUB21-086 and File ID 21-953 Project Scope: Dry Fork Interceptor This project consists of installation of a 24” Wastewater line between Bonnie Brae and the Hickory Creek Interceptor that will also provide sewer service to the corridor along I-35W. 13PUB21-086 and File ID 21-953 SCHEDULE COORDINATION (target dates) PHASE HCI 1 & 2 (PM Tracy L. Beck, P.E.) Dry Fork Interceptor (PM Robin Davis) HCI 3 * (PM Tracy L. Beck, P.E.) Design Complete Design Complete* Barring Necessary Changes for Archaeological Findings 12/24/21 Plans are at 90% Review Advertisement 03/07/21 02/17/22 02/17/22 Advertisement Closes 04/13/21 03/22/22 03/22/22 PUB 05/24/21 03/07/22 03/07/22 City Council 05/25/21 03/22/22 03/22/22 Construction Start 06/11/21 05/20/22 05/20/22 Construction End 06/10/22 04/07/23 04/07/23 05/24/21 and 5/25/21 14 •Project Manager to execute advertisement of HCI 3 based on progress of HCI 1 & 2 PUB21-086 and File ID 21-953