HomeMy WebLinkAbout1998-312ORDINANCE NO 7 (/ —21A
. N ORDINANCE AUTHORIZING THE EXECUTION OF CHANGE ORDERS #1, #2, AND #3
TO THE CONTRACT FOR RENOVATION OF DENTON CITY HALL AND MUNICIPAL
COMPLEX (CITY HALL EAST) — PROJECT II BETWEEN THE CITY OF DENTON AND DBR
CONSTRUCTION CO, PROVIDING FOR A CHANGE IN THE CONTRACT AMOUNT, AND
PROVIDING AN EFFECTIVE DATE (BID # 2184-GENERAL CONSTRUCTION AND
RENOVATION OF THE DENTON MUNICIPAL CENTER (CITY HALL EAST) AND CITY
HALL - PROJECT 11, PURCHASE ORDER # 85176 TO DBR. CONSTRUCTION COMPANY IN
THE NET AMOUNT OF $36,804 00 DEDUCT)
WHEREAS, on 4-21-98, the City awarded a contract for BID # 2184 — GENERAL
CONSTRUCTION AND RENOVATION OF THE DENTON MUNICIPAL CENTER (CITY
EAST) AND CITY HALL — PROJECT II in the amount of $1,065,587 00, and
WHEREAS, the City Manager having recommended to the Council that a change orders be
authorized to amend such contract agreement with respect to the scope and price and said change
orders being in compliance with the requirements of Chapter 252 of the Local Government Code,
NOW, THEREFORE,
THE COUNCIL OF THE CITY OF DENTON HEREBY ORDAINS
ACTION I. That the change order #1 decreasing, and change order # 2 increasing, and
change order # 3 increasing the amount of the contract agreement between the City and DBR
Construction Company copies of which are attached hereto, in a total deductive amount of THIRTY
SIX THOUSAND EIGHT HUNDRED FOUR and no/100 Dollars ($36,804 00), is hereby approved
and the expenditure of funds therefor is hereby authorized The contract amount is amended to read
$1,028,783 00 That this ordinance shall become effective immediately upon its passage and
approval
PASSED AND APPROVED this the � day of VeG oo j2f- , 1998
`t.V GL��tOr-
J { MILLER, MAYOR
ATTEST;
JEE �$R WAL/TERSjY ClSECRETARY
1/�f'8�fe
A1WROVED AS TO LEGAL FORM
HEBERRTLT LPPROUTY, CITY ATTORNEY
BY ///�/,ir
2184 CHANGE ORDERS #1, #2, #3 ORDINANCE
85176 TO DER CONSTRUCTION
Change Order OWNER IN
ARCHITECT (X 1
AIA Document G701 - CONTRACTOR I X1
Electronic Format FIELD ( )
OTHER 0
THIS DOCUMENT HAS IMPORTANT LEGAL CONSEQUENCES, CONSULTATION WITH AN ATTORNEY IS ENCOURAGED WITH RESPECT TO ITS
COMPLETION OR MODIFICATION AUTHENTICATION OF THIS ELECTRONICALLY DRAFTED AIA DOCUMENT MAY BE MADE BY USING AIA
DOCUMENT D401
PROJECT
(name address)
Denton City Hall & Municipal Co=Iaz
Renovations _•__,- Promct II
215 E. McK_Inney & b0I Ee_at_ Hickorv. Denton. Texas 76202
TO CONTRACTOR
(name address)
DBR Construction Cemnarry
P. O. Box 828
Denton, Texas 76202
The Contract is changed as follows
Ref Attachment "A".
CHANGE ORDER NUMBER One 1
DATE 3 Tune 1998
ARCHITECTS PROJECT NO 97174 00 D-5
CONTRACT DATE 21 April 1998
CONTRACT FOR Renovation
Not valid until signed by the Owner, Architect and Contractor
The original (Contract Sum)(GuaFaintsed Maximum Pne) was $ 1,065,587 00
Net change by previously authorized Change Orders $ 0.00
The (Contract Sum)( ) prior to this Change Order was $ 1,065,587 00
The (Contract Sum)(rdeamised Maximum Pne ) will be (-inersased)(decreased)
(unchanged) by this Change Order in the amount of $ 42,517.00
The new (Contract Sum)( ) including this Change Order will be $ 1,023,070.00
The Contract Tune will be (moreased)(deliFeass )(unchanged) by ( ) days
The date of Substantial Completion as of the date of this Change Order therefore is 5 March 1999
NOTE This summary does not reflect changes in the Contract Sum, Contract Time or Guaranteed Maximum Price which have been
authorized by Construction Change Directive
Corgan Associates Inc. CONTRACTOR
Address 501 Elm Street S, 500Addre::
BY �`�Dal�la�s, Texas 75202 R9S Construction. EQ gOg 828.
AlA
DATE June S , 1998v
BY
D TE Jun 1998
OWNER
Address
BY
AIA DOCUMENT G701 - CHANGE ORDER - 1987 EDITION - AIA - COPYRIGHT 1987 - THE AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW
YORK AVENUE, N W , WASHINGTON, D C , 20006-5292 WARNING, Unlicensed photocopying violates US copyright laws and is subject to legal
prosecution This document was electronically produced with permission of the AIA and can be reproduced without violation until the date of expiration as noted
below
Electronic Format G701-I987
User Document G701 DOC — 6/3/1998 AIA License Number 101193, which expires on 9/7/1998 — Page #1
ATTACHMENT"A"
June 1, 1998
RE Denton City Hall and Municipal Complex
Project 11
Corgan Associates Inc
97174 00 D-5
Value Engineering List,
11 Reduce construction contingency from $40,000 to $25,000 ($15,000 credit)
12 Eliminate the glass block mfill at Fire Sprinkler Riser Room adjacent to Corridor 101 Provide EIFS
mfill wall on Southwest corner of room to match existing plaster walls Existing wing walls are not to
be demoed ($3,000 credit)
13 Provide bored locksets as in lieu of specified mortise locks at DMC ($500 Credit)
15 Reduce wall tile in DMC restrooms 125 and 126 to Y-0" height on plumbing walls and eliminate wall
tale on nonplumbing walls as indicated on Supplementary Drawings SD-30 Wall finish to be paint at
locations tale has been eliminated ($1,000 Credit)
17 Provide Celotex ceiling tile pattern NPS-197 or equivalent ceiling tile in lieu of specified Armstrong
"Georgian" ($800 Credit)
18 Provide vinyl wall covering in lieu of fabric wallcovering in Room 105 and 107 along the
north and east walls Vinyl wallcovering to be equal to specified vmyl referenced in
Addendum item MI 21 ($2,000 Credit)
19 In lieu of the specified polymer resin type toilet partition, provide baked enamel metal todet partitions
with acceptable manufacturers Ampco Products, Inc, Global Steel Products Corporation, Sanymetal
Products Company, Inc or General Partition Manufacturing Corporation Acceptable Products are as
follows ($1,800 Credit)
(1) Floor Mounted Overhead Braced Toilet Partitions Academy by Sanymetal Product Cc
(2) Overhead Supported Toilet Partitions Century by Sanymetal Product Cc
(3) Wall Hung Urinal Screens Type F by Sanymetal Product Co
1 11 Replace hydronic coils in power mixing boxes with the electrical reheat coils as originally designed
(modified by Addendum Item Nl 28) on Sheet Mlat DMC ($7,380 Credit)
113 Rezone HVAC to eliminate up to (12) power mixing boxes and streamlme ductwork Reference
Supplementary Drawings SD 27,28 & 29 (Eliminate 7 - $5,817 Credit)
1 15 Provide PVC plumbing piping underground vs cast iron currently specified at DMC ($720 Credit)
117 Provide MC cable where allowed by NEC in lieu of specified EMT conduit ($3,000 Credit)
119 Eliminate aluminum window between Customer Service 105 and Workstation
Cluster 119 and provide framed gyp board opening in wall ($500 Credit)
120 Eliminate all thread duct support and provide strap hangers at ductwork ($1,000 Credit)
Total Credit - $42,517
Change Order
OWNER 1X]
ARCHITECT [ X ]
AIA Document G701 -
CONTRACTOR ( X]
Electronic Format
FIELD [ ]
OTHER 0
THIS DOCUMENT HAS IMPORTANT LEGAL CONSEQUENCES, CONSULTATION WITH AN ATTORNEY IS ENCOURAGED WITH RESPECT TO ITS
COMPLETION OR MODIFICATION AUTHENTICATION OF THIS ELECTRONICALLY DRAFTED ALA DOCUMENT MAY BE MADE BY USING AIA
DOCUMENT D401
PROJECT
(name address)
Denton City Hall & Municipal Complex Renovation - Project 11
215 E McKinney & 601 E Hickory
Denton, Texas 76202
TO CONTRACTOR
(name address)
DBR Construction Company
Post Office Box 828
Denton, Texas 76202
CHANGE ORDER NUMBER Two(2)
DATE 16 August 1998
ARCHITECTS PROJECT NO 97174 00
CONTRACT DATE 21 April 1998
CONTRACT FOR Renovation
The Contract is changed as follows
Revise entrance door and storefront to the Legal Department in the Denton City Hall as indicated on Supplementary Dmwmg SD-31
and per PCR #2 1, dated June 23, 1998
Not valid until signed by the Owner, Architect and Contractor
The ongmal (Contract Sum)(rduamllesil Mwuinuni Pnes) was $ 1,065,587 00
Net change by previously authorized Change Orders $ (42,517 00)
The (Contract Sum)(QuiliPaintsed li4ownum Pnea) prior to this Change Order was $ 1,023,070 00
The (Contract Sum)( ) will be (mcreased)(deoreased)
(uaskaiiged by this Change Order in the amount of $ 4,53500
The new (Contract Sum)(rdHaF811190d MaXIMPIRM PFIAA) including this Change Order will be $ 1,027,605 00
The Contract Time will be ()(unchanged) by zero ( 0) days
The date of Substantial Completion as of the date of this Change Order therefore is March 5, 1999
NOTE This summary does not reflect changes in the Contract Sum, Contract Tune or Guaranteed Maximum Price which have been
authorized by Construction Change Directive
CONTRACTOR OWNER
Address
Corgan Associates, Inc, 501 Elm Street, Suite
500 Dallas, Texas 75202
BY
DATE
Address
DBR Construction Company P O Box 828
Denton, Tex 76202 /
D/(TE
Address
City of Denton 215 E McKinney Denton
Texas 79202 /11--)
BY
AIA DOCUMENT G701 CHANGE ORDER 1987 EDITION - AIA - COPYRIGHT 1987 THE AMERICAN INSTITUTE OF ARCHITECTS 1735 NEW
YORK AVENUE N W WASHINGTON D C 20006 5292 WARNING Unlicensed photocopying violates U S copyright laws and is subject to legal
prosecution This document was electronically produced with permission of the AIA and can be reproduced without violation until the date of expiration as noted
below
Electronic Format G701-1981
User Document G701#2 DOC — 8/17/1998 AIA License Number 101193 which expires on 12/7/1999 -- Page #1
CORGAN ASSOCIATES, INC
30l ELM STREET
DALLAS TEXAS 7!-'023354
TEL 214 743 =0
PAX _ 4633 teal
EMAIL COROAN®CORGA-1 cool
To Mr Don Richards
DBR Construction Company
P O Box 828,
Denton, TX 76202
From Lotus Wolf
Proposed Change Request
23 June 1998
Project Denton City Hall Renovation
Project 11, Phase I and II
PCR 2
Please submit a wnteea proposal for modifications to the Work as identified here and on referenced attachments
Submit proposal within 7 days, or notify the Architect in writing of the date on which you anticipate subnuttmg
your proposal
THIS IS NOT A, CHI\GE ORDER, CONSTRUCTION CHANGE DIRECTIVE OR JL DIRECTION TO
PROCEED WITH THE WORK DESCRIBED IN THE PROPOSED MODIFICATIONS
2 1 Provide pricing for the modification of the entrance door and storefront to the Legal
Department in the City Hall as indicated on Supplementary Drawing SD-31 Relocate
door 137 to gypsum board wall kX111 door opening with storefront Provide electric
strike at door 137 with push button located adjacent to Legal Receptionist Install 18" e
24" wood framed window with 6" opening in glasss above V-0" wide a 24" long plastic
laminate countertop Wood frame to match detailing at storefront Relocate aluminum
vestibule to align w A storefront
22 Provide pricing for the modification of the storefront at Legal Department in City
Hall as indicated on Supplementary Drawing SD-31 and stated above In lieu of
relocating the aluminum vestibule wall, replace with wood storefront
End of PCR
Encl
cc Bruce Heningron/Denton
P \97 174�tp\D4� D L: PCR
COROAN ASSOCIATES INC
Sot ELM sTUEET
DALLAS TEXAS'S:o2 3334
TEL 2147482000
FAX 214 03 828t
Drawn by UW
Date 18 June 1998
Supplementary Drawing
No. 31
18 June 1998
Project Denton City Hall & DMC Renovation
No. 97174 00 File* D-10 Item: PCR #2
PAFrriA L fLoolk PLAN • 4ITY WALL
„ 1 it
1.0
a Order OWNER
Chan [�
9 ARCHITECT [ X [
AIA Document G701 - CONTRACTOR [ X]
FIELD [ �
Electronic Format OTHER p
I HIS DOCUMENT HAS IMPORTANT LEGAL CONSEQUENCES, CONSULTATION WITH AN ATTORNEY IS ENCOURAGED WITH RESPECT TO ITS
COMPLETION OR MODIFICATION AUTHENTICATION OF THIS ELECTRONICALLY DRAFTED AIA DOCUMENT MAY BE MADE BY USING AIA
DOCUMENT D401
PROJECT
(name address)
Denton Cav Hall & Municipal Complex Renovation -Protect lI
215 E McKinney & 601 E Hicko
Denton Texas 76202
TO CONTRACTOR
(name address)
DBR Construction Company
Post Office Box 828
Denton, Texas 76202
The Contract is changed as follows
CHANGE ORDER NUMBER Three(3)
DATE 14 September 1998
ARCHITECT'S PROJECT NO 97174 00
CONTRACT DATE 21 April 1998
CONTRACT FOR Renovation
changed out once the new KussWin Keyways are recerveu
Not valid until signed by the Owner, Architect and Contractor
The original (Contract Sum) was $ 1,065,587 00
Net change by previously authorized Change Orders $ (37,96200
The (Contract Sum) ) prior to this Change Order was $ 1,027,605 00
The (Contract Sum)( ) will be (increased)(deewasad)
by this Change Order in the amount of $ 1,17800
The new (Contract Sum) ) Including this Change Order will be $
1,o7�t'792ti oa
The Contract Time Will be(wA;easadX4si;raasad)(unchanged) by zero (, days
The date of Substantial Completion as of the date of this Change Order therefore is March 5, 1999
NOTE This summary does not reflect changes in the Contract Sum, Contract Time or Guaranteed Maximum Price which have been
authorized by Construction Change Directive
cuironsruction Co. C"i%" of Denton
Corgan Associates. Inc.
Address Address Address
501 Elm Street, Suite 500, Dalian Texas P 0 Box 828, Denton, Texas 76202 215E &*Kumey, DerOOILTexas 76202
75202 By
BY
BY —
_ A 9i 9�
DATETE V 1/ V1
)s soot 96
AIA DOCUMENT G701 CHANGE ORDER 1987 EDITION AIA COPYRIGHT 1987 THE AMERICAN INSTITUTE OF ARCHITECTS 1735 NEW YORK
AVENUE N W WASHINGTON, D C , 20006 5292 WARNING, Unlicensed photocopying violates it S copyright laws and is subject to legal prosecution This
document was electronically produced with permission of the AIA and can be reproduced without violation until the date of expiration as noted below
Electronic Format G701-1987
User Document G701#3 DOC -- 9/1411998 AIA License Number 101193, which expires on 12/7/1999 -- Page #1