HomeMy WebLinkAbout1997-290ORDINANCE NO 97-a?9,0
AN ORDINANCE AUTHORIZING THE EXECUTION OF A CHANGE ORDER TO A
PURCHASE ORDER BETWEEN THE CITY OF DENTON AND, Fi 1RSTENBERc.
CONSTRUCTION CO. PROVIDING FOR A INCREASE IN THE PURCHASE ORDER PRICE,
AND PROVIDING AN EFFECTIVE DATE
WHEREAS, on 02.1.8-97, the City awarded a purchase order for PO# 73330 -
RFNOVATION OF DENTON CITY HALL in the amount of 51.283,600 00, and
WHEREAS, the City Manager having recommended to the Council that a change order be
authorized to amend such purchase order with respect to the scope and price and said change order
being in compliance with the requirements of Chapter 252 of the Local Government Code, NOW,
THEREFORE,
THE COUNCIL OF THE CITY OF DENTON HEREBY ORDAINS
SECTION I. That the change order increasing the amount of the purchase order between
the City and FURSTENBERG CONSTRUCTION CO copy of which is attached hereto, in the
amount of FORTY FIVE THOUSAND_EIGHT Hi INDRED EIGHTY THREE and no/100 Dollars
( 45,883 00), is hereby approved and the expenditure of funds therefor is hereby authorized The
purchase order amount is amended to read $1,329,483 00
SECTION 11. That this ordinance shall become effective immediately upon its passage and
approval
PASSED AND APPROVED this the6@'day of 1997
FIFILLER, MAYOR
ATTEST
JENNIFER WALTERS, CITY SECRETARY
BY
APPIWVED AS TO LEGAL FORM
HEBERT L PROUTY, CITY ATTO EY
BY Gc
DATE SEPTEMBER 23, 1997
TO Mayor and Members of the City Council
FROM Kathy DuBose, Assistant City Manager of Finance
SUBJECT PURCHASE ORDER # 73330 TO FURSTENBURG CONSTRUCTION CO.
CHANGE ORDER # 1, 4 AND 5
RECOMMENDATION: We recommend change order # 1 in the amount of $927 00, change order # 4 in
the amount of $24,999 00, and change order # 5 in the amount of $19,957 00 be approved Total change order
amount $45,883 00
SS MMMMA,RY: The change orders are for construction changes to the contract for renovation of City Hall,
215E McKinney, Denton, Texas Change Order # 1 is for the relocation of an office wall, change orders
# 4 and # 5 are detailed in change order synopsis attached as Exhibit A and B Note that change orders 2 and
3 were time related only and had no financial impact on the contract
Each item listed as portions of change order # 1, # 4 and # 5 have been reviewed by Corgan Associates
Architects and they concur with the cost figures presented
Most of the first change order items totaling less than $25,000 00 have been completed to avoid delay in
construction Council approval is required for all change orders over the $25,000 00 amount
PROGRAMS, DEPARTMENTS OR GROUPS AFFECTED. City Employees located at City Hall,
Facilities Management Division, Furstenburg Construction Inc, and Citizens of Denton
FISCAL IMPACT: Funds for these charge orders are available in the budget set aside for the City Hall
Renovation Account # 454-032-CHAL-9646-9101
Attachments Change Order # 4
Exhibit A - Change Order # 4 Synopsis
Change Order # 5
Exhibit B - Change Order # 5 Synopsis
Respectfully submitted
0
at u se
Assistant ity Manager of Finance
Approved
Name Tom D SFa—w—,C'PM
Title Purchasing Agent
938 AGENDA
Change Order
OWNER IXI
ARCHITECT I X )
AIA Document G701 -
CONTRACTOR I Xl
Electronic Format
FIELD I I
OTHER Q
THIS DOCUMENT HAS rMPORTANT LEGAL CONSEQUENCES CONSULTATION WITH AN ATTORNEY IS ENCOURAGED WITH RESPECT TO ITS
COMPLETION OR MODIFICATION AUTHENTICATION OF THIS ELECTRONICALLY DRAFTED AIA DOCUMENT MAY BE MADE BY USING AIA
DOCUMENT D401
PROJECT
(home add--)
General Construction and Renovation of the Deruot C40 Holt
Facilely
215 East McKamey
Demon, Texas 76201
TO CONTRACTOR
(roam, addma)
Furstenberg CoroMRcil"Comparry
2621 W Moektdgbud Latta
Dallas, Texas 75735
The Contract is chaWd as follows
As Indicated on Attachment "A" dated 9 September 1997
CHANGE ORDER NUMBER Four (4)
DATE 11 September 1997
ARCHITECTS PROJECT NO 95222 00 D-4
CONTRACT DATE January22,1997
CONTRACT FOR Renovation
Not valid until signed by the Owner, Architect and Contractor.
The orlgimal (Contract Sum)( ) was
Net change by previously authorized Change Orden
The (Contract Sum)(G"Failialed Migumian44i") prior to this Change Order was
The (Contract Sum)( ) will be (mereased)(deereased)
(wishaxge9)-by this Change Order In the amount of
The new (Contract Sum)(Gesswead Maiamum Raise) including this Change Order will be
$ 1 283,600 00
$ 92700
$ 1,28462700
$ 24,072 00
$ 1,308,599 00
The Contract Time will be (mcreased)(deereased)(eaehaegedQ) by five ( 5) days y¢,
The date of Substmtttal Completion as of the date of is ge Order therefore is 8 a tit geptamber 15 1997 %F N
P cludlw�9 vm"l wetas tN Ctryescu to( aw;Z lai
NOTE This summary does not reflect changes in the Contract Sum, Contract Time or Guaranteed Maximum Price which have been
authorized by Consructton Change Directive
RA OWNER
Address
Address
Corgan Associates, Inc.
Purstenberg Construction, Inc
501 Elm Street, Suite 500
2621 W Mockingbird Lane
Dallas, Texas 75202
Deltas, Texas 75235
Address
City of Demon
215 East McKinney
Deacon. Texas 76201
SY
'/ - Q AI 7'i?it —
DATE A + a tact -r CZATIE 19// 41
AIA DOCUMENT G701 - CHANGE ORDER - 1987 EDITION - AIA COPYRIGHT 1987 THE AMERICAN INSTITUTE OF ARCHITECTS 1735 NEW
YORK AVENUE N W. WASHINGTON DC, 20006.5292 WARNING, Unlicensed phol000pying violates U S copynght laws and is subject to legal
prosecution This document was electsontoatly produced with perils xia of the AIA and cm be repreduad without violation will the date of expiration W noted
below
Electronic Format G701-1987
User Document G701#4#2 DOC — 9/11/1997 AIA License Number 101193, which expires on 9/7/1998 -- Page #1
EXHIBIT A
CITY HALL RENOVATION
CHANGE ORDER SYNOPSIS
September 9, 1997
CHANGE ORDER #1
add
$927
CHANGE ORDER #2
time revision/change due to signed contracts late
CHANGE ORDER #3
time revision/September 8, 1997
CHANGE ORDER #4/ACCOUNT # 454-032-CHAL-9646-9101
• Installing stainers at each fan coil
unit as indicated on supplementary drawings
SD-35 and 36 as requested by Owner
Cost to include labor only
add
300
0 Revise layout of sidewalk at east
parking lot as indicated
on supplementary drawing #37
add
750
e Provide two return air transfer
boots for room 127 as indicated
on supplementary drawing SD-38
Provide access panel from
room 127 to corridor 128 above
the ceiling to access FP-#15
control panel
add
548
• Provide fur downs at window
locations as indicated on
supplementary drawings 47 and 48
add
1,939
0 Provide carved sticks as
indicated in the contract documents
for the dias and lectern
add
1,000
s ADA platform/State of Texas
add
10,014
e Unforeseen brick work in the
CMO conference room
add
305
• Fill holes in lobby, floor the area
add
1,075
9 Fur out roof drain in CMO kitchen area
add
413
i Grinding unforeseen bolts in CC Chambers
add
570
® Install 2x2 light fixtures in A/V hall
add
280
3810 fm
September 9, 1997
4
•
Pier - adjustment
add
376
•
Screening modification
add
350
•
Furr-out of electrical panel
in women's basement R R
add
485
•
Vapor barrier
add
933
•
Ballast replacement
add
2100
•
Add switch for exhaust fan, room 163
add
262
•
Add duplex's for exhaust 137 and 132
add
228
•
Relocate fire panel circuit and power
add
1153
•
Furr-out for light switch room #116
add
128
•
Paint around legal window
add
520
•
Ad controls to AHU-NI & N2 and
circuit for hot water heater
add
343
TOTAL
$24,999
3810 fm
September 9, 1997
5
Change Order
AIA Document 0701
Electronic Format
OWNER
I X]
ARCHITECT
lX]
CONTRACTOR
[X]
FIELD
[]
OTHER []
THIS DOCUMENT HAS IMPORTANT LEGAL CONSEQUENCES, CONSULTATION wIT11 AN ATTORNEY IS ENCOURAGED WITH RESPECT TO ITS
COMPLFnON OR MODIFICATION AUTHENTICATION OF THIS ELECTRONICALLY DRAFTED AIA DOCUMENT MAY BE MADE BY USING AIA
DOCUMENT D401
PROJECT
(name address)
General Construction and Renovation of the Denton Cry Hall
CHANGE ORDER NUMBER Five (5)
Facility
215 East MclGaney
DATE 11 September 1997
Demon Texas 76201
TO CONTRACTOR
ARCHITECTS PROJECT NO 95222 00 D-4
(mane addm=)
Farstcnberg Construction Company
CONTRACT DATE January22, 1997
2621 W Mocicmgbird Lane
CONTRACT FOR Renovation
Dallas, Texas 75235
The Contract is changed as follows
As indicated on Attachment "A" dated 9 September 1997
Not valid until signed by the Owner, Architect and Contractor
The ongtnal (Contract Som)( ) was
S
1,283,600 00
Net change by previously authorized Change Orders
$
24,999 00
The (Contract Sum ) Prior to this Change Order was
$
1,308,599 00
The (Contract Sum)( ) will be (mcneased)(daereasedy
("oloaeged)-by this Change Order in the amount of
$
19,957 00
The new (Contract Sum)(49varallead Afiffiaunam Pineal mcludirg this Change Order will be
$
1,328,556 00
The Contract Tune will be by fourteen ( 14) days
The date of Substantial Completion as of the date of this Change Order therefore is 5 p m
October 3 1997
NOTE This summary does not reflect changes in the Contract Sum Contract Tune or Guaranteed Maximum Price which have been
authorized by Construenpn Change Directive
O
OWNER
Address Address
Corgan Associates. Inc
Address
Furstenberg Construction, Inc
501 Elm Street, $iute 500
City of Denton
2621 W Mockingbird Lane
Dallas, Taxes 75202
215 Eau McKinney
Dallas, Texas 75233
Denton, Texas 76201
BY
DATE Sint t_ Iq1 tre�1r1-//-�J
AIA DOCUMENT G701 - CHANGE ORDER 1987 EDITION - AIA - COFYRIGtn' 1997 THE AMERICAN INSTITUTE OF ARCHITECTS 1735 NEW
YORK AVENUE, N W WASHINGTON, DC, 20006-5292 WARNING Unlioawed photocopying violates US copyright laws and n subject to legal
prosecution Ilia document was electronically produced with pennittton of the AIA and can be mproduad without violation until the dote of eapuwon a noted
below
Electronic Format G701-1987
User Document, 9701#5 DOC -- 9/11/1997 AIA License Number 101193 which expires on 9MI998 -- Page #1
EXHIBIT B
CHANGE ORDER #5
ITEMS NOT COMPLETED
Dais modification in order to accommodate technical support systems, for
example speakers, voting option buttons and monitors This will lower
top portion of the dais to allow a better relationship with citizens
It will lower technical support systems down into leg space area, per
model constructed by Corgan & Associates
$18,457
o Clean CMO hall wall
3810 fm
September 10, 1997
1,500
TOTAL $19,957
7