HomeMy WebLinkAbout1996-223ORDINANCE NO 9(v _01a3
AN ORDINANCE AUTHORIZING THE EXECUTION OF A CHANGE ORDER TO A
CONTRACT BETWEEN THE CITY OF DENTON AND, DICKERSON CONSTRUCTION
PROVIDING FOR AN INCREASE IN THE CONTRACT PRICE, AND PROVIDING AN
EFFECTIVE DATE
WHEREAS, on 3-5-96, the City awarded a contract forAID#A A9---- SC'RIPTi1RF
STREET 20" AND R" WATERLIN in the amount of $l QM,$97.54, and
WHEREAS, the City Manager having recommended to the Council that a change order
be authorized to amend such contract with respect to the scope and price and said change order
being in compliance with the requirements of Chapter 252 of the Local Government Code,
NOW, THEREFORE,
THE COUNCIL OF THE CITY OF DENTON HEREBY ORDAINS
SECTION I. That the change order increasing the amount of the contract between the
City and DI KE.RSON CONSTRI iC TION copy of which is attached hereto, in the amount of
SEVENTEEN THOUSANDSEVENTY THREE and 751100--- Dollars ($17,073_75), is hereby
approved and the expenditure of funds therefor is hereby authorized The contract amount is
amended to read $1,092,936 25
SECTION That this ordinance shall become effective immediately upon its passage
and approval
PASSED AND APPROVED this the Lit day of 1996
5044-A•f(i4..•f.C�... a
JACIk MILLER, MAYOR
ATTEST
JENNIFER WALTERS, ITY SECRETARY
BY
A ROVED AS TO LEGAL FORM
HEBERT L PROUTY, CITY ATTORNEY
G
BY
DATE OCTOBER 1, 1996
1 ► 1g';I Y
TO Mayor and Members of the City Council
FROM Ted Benavides, City Manager
SUBJECT PURCHASE ORDER #64553 - SCRIPTURE STREET 20" AND 8"
WATERLINE - CHANGE ORDER #2
RECOMMENDATION: We recommend that change order 42 in the amount of $17,073 75 be
approved and that the contractor, Dickerson Construction, be authorized to proceed
SUMMARY: This change order increases the contract by a total of $36,038 75 (change order #1
$18,965 00 approved by Council July 2, 1996, change order #2 $17,073 75 proposed) The new total
will be $1,092,936 25
This change order will allow for the replacement of an existing 4" waterline on Ponder Street with a
6" waterline consisting of approximately 442' of 6" line with appurtenances
During the construction of the 20" waterline it was determined that the existing 4" line on Ponder
Street was in very poor condition Replacement of this line will leave the Panhandle/Egan and
Scripture area with all new lines
Public Utility Board recommends approval
BACKGROUND: Purchase Order #64553 for Dickerson Construction, location map, Minutes from
Public Utility Board
PROGRAMS, DEPARTMENTS OR GROUPS AFFECTED. City of Denton Utility Department,
Dickerson Construction Company
FISCAL IMPACT: Funds for this change order are available from Water and Sewer Bond Account
#662-08 1 -RB89-R205-9138 and brings the project 3 1% over estimated budget
Respectfully submitted
ed Benavides
City Manager
Approved By
Name Tom D Shaw, C P M
Title Purchasing Agent
774 AGENDA
CITY OF DENTON CHANGE ORDER
Engineering 8 Transportation 64553
4 Name of Project 5 Project Acet No 6 Date Prepared
Scripture -Fulton Upgrade 662-081-RB89-R205.9138 July 31, 1996
Name and Address of Contractor
Dickerson Construction - P 0 Box 181 - Celina, TX 75009
8 Description of Work Included in Contract
Install new and upgrade waterline
9 Changes ordered and reason ordered (List individual changes as A, B, C, D, etc
Install new six inch waterline and replace old four inch waterline
Contract Item Estimated Unit
Changes No Quantity Price
C 0 Unit Estimated Estimated
Price Cost Cost
B 2 16-A
�61
EA
$500
00
63
EA
$500
00
$30,500 00
$31,500
00
C 2 13 1-C
12
EA
$450
00
14
EA
$450
00
S 5,400 00
$ 6,300
00
D SP-43
27
EA
$100
00
28
EA
$100
00
S 2,700 00
$ 2,800
00
SP-42
8
EA
$500
00
9
EA
$500
00
$ 4,000 00
$ 4,500
00
$73,548 75
$90,622
50
Total
Total
As of Change order #1
11 Original Contract Price
81.075.862
50
Increase in
Contract Price $
17,073 75
New Contract Price $1,092,936 25 Decrease in Contract Price N/A
12 Contract time increased/decreased by 5 days New contract time 105 days
THE AFOREMENTIONED CHANGE, AND WORK AFFECTED THEREBY, IS SUBJECT TO ALL CONTRACT STIPULATIONS AND COVENANTS
13 ISSUED FOR REASONS INDICATED ABOVE
14 ACCEPTED BY CITY ENGINEER l �
7-31-9�
Date
15 ACCEPTED BY CONTRACTOR �"--��'i' 1— J / / f y
c 4.r re Title Date
16 ASSISTANT CITY MANAGER
DIRECTOR OF UTILITIES
CONDITIONS OF APPROVAL
17 PURCHASING/FINANCE
COUNCIL APPROVAL (If needed)
AEE00399
Signature
Signature
Title
Title
Date
Date
Signature Title Date
901-B TEXAS STREET
P NU BE
64553
VENDOR
DICKERSON CONSTRUCTION INC
P 0 BOX 181
CITY OF DENTON, TEXAS
PURCHASE ORDER
DATE/VENDOR NO DO
04-10-96 C25
DIC52500
DENTON, TX 76201
CUMENT
SHIP TO
CONFIRMATION ONLY C25
ENGINEERING
221 N ELM
DENTON, TX 76201
TYPE
S
CELINA TX 75009
*** NOTE THIS ORDER WAS MODIFIED ***
ITEM ACCOUNT NUMBER UNITS NUMBER DESCRIPTION BID NO LINE AMOUNT
01 662 081 R889 R205 9138 0 00 SCRIPTURE - FULTON UPGRADE 1,056,897 50
WATERLINE CONSTRUCTION
02 662 081 RB89 R205 9138
03 662 081 RB89 R205 9138
0,00 CHANGE ORDER #1
0 00 CHANGE ORDER #2
TOTAL FOR P 0
18,965 00
17,073 75
1,092,936 25
The City of Denton, Texas is tax exempt -House BIII No 20 —
Reference PO Number on all B/L, Shipments and Invoices
Shipments are F 0 B City of Denton, or as indicated BY
Purchasing Division
FItems Received Date Voucher Number Amount
PURCHASING
I
3
,CRi PrvR E
SHEET 12
g" �/RTERun�L
}
cr
LL
cr
W
a
Z
O
a
SHEET II
6" WATERLINE
C44RNGE ORbE?
tJ 0 7.
WATERLINE
E kTE N) S10N
PUBLIC UTILITIES BOARD
MINUTES EXCERPT
10 CONSIDER APPROVAL OF CHANGE ORDER NO 2 FOR THE 20 INCH
WATER LINE PROJECT ON SCRIPTURE IN THE AMOUNT OF $17,000
Mr Coplen made a motion to approve the item Mr Norton seconded the
motion, all ayes, no nays, motion passed unanimously