HomeMy WebLinkAbout1994-081ORDINANCE NO. / -/ r0efl AN ORDINANCE AUTHORIZING THE EXECUTION OF A CHANGE ORDER TO A CON- TRACT BETWEEN THE CITY OF DENTON AND OSCAR RENDA CONTRACTING ; PROVIDING FOR AN INCREASE IN THE CONTRACT PRICE; AND PROVIDING AN EFFECTIVE DATE. WHEREAS, on OCTOBER 5, 1993 , the City awarded a contract for UNIVERSITY DRIVE SANITARY SEWER in the amount of $ 577,145.00 ; and WHEREAS, the City Manager having recommended to the Council that a change order be authorized to amend such contract with respect to the scope and price and said change order being in compliance with the requirements of Chapter 252 of the Local Government Code; NOW, THEREFORE, THE COUNCIL OF THE CITY OF DENTON HEREBY ORDAINS: SECTION I. That the change order increasing the amount of the contract between the City and OSCAR RENDA CONTRACTING , a copy of which is attached hereto, in the amount of TWENTY SIX THOUSAND THREE HUNDRED NINTY SEVEN and 29/100--- Dollars is 79_7o7_An %_ 9a harahv annroved and the expenditure of funds therefor authorized. SECTION II. That this ordinance immediately upon its passage and approval, PASSED AND APPROVED this the 1994. APPROVED AS TO LEGAL FORM: DEBRA A. DRAYOVITCH, CITY ATTORNEY shall become effective day of , DATE: MAY 3, 1994 CITY COUNCIL REPORT TO: Mayor and Members of the City Council FROM: Lloyd V. Harrell, City Manager SUBJECT: CHANGE ORDER #2 - OSCAR RENDA CONTRACTING UNIVERSITY DRIVE SANITARY SEWER RECOMMENDATION: We recommend change order number two to Oscar Renda Contracting be approved in the amount of $26,397.29. SUMMARY: The contract for University Drive Sanitary Sewer was awarded to Oscar Ronda Contracting on October 5, 1993 in the amount of $577,145.00. The project is substantially complete and on time. This change order is to allow payment to be made for actual work done at the unit price of the contract. The change order consist of five items. 1. Air and Mandrel Testing $ 5,152.50 2. Concrete Saw Cutting $ 880.00 3. 6" Concrete Pavement $13,380.00 4. Removing Installed Sewer $ 7,313.00 5. Casing Spacers $ (328.00) $26,397.00 Other decreases in contract estimated quantities have reduced the contract price by $17,005. This along with reductions in change order number one have resulted in a total contract price of $576,537.00, a, reduction of $607.70. BACKGROUND: Letter from Oscar Renda, Minutes from PUB meeting of April 18, 1994. GROUPS AFFECTED: Water/Waste Water Utility, FISCAL IMPACT: Funds for this change order are available in the original contract funds due to overall reduction in contract price. t.� alpectfully u mitted: 46 loyd V. Harrell City Manager Approved: Name: Tom D. Shaw,C.P.M. Title: Purchasing Agent 4B8.AGENDA APR-25-'94 MON 14:07 ID: ITY OF DENTON UR TEL NO:817-566-8120 4883 P01 14 'S1 -94 OSCAR REND Contracting, Inc.- +7 BENSON LANE • ACANOKE, TEXAS 76262 . (817)401-2702 Hr. Glenn Gary, moq. associate Denton municipal utilities 901 Texas ctroat, municipal Building Denton, Tx 76201 Ref university Drive sanitary cower Dear Hr. nary, In receipt of your letter dated April o6, 1994, O.R.C. will agree to the price calculated by the city pursuant to aid Item 8P-42, Remove sanitary sewer. This should finalize any itemsordleft to be algrandgupon with regards to change for this change Thereforeoreed to items changeOrder, whichas6 uld &IDof Please Hots that pallow 1thapcloaeoutyofgthis contract. ries listed below repregont only the "extra work- for each bid item as the original contract am08nts have been requested on the final pay estimate. ITEM AMOUNT EXTRA 1. Air p mandrel Test of pipeline To CONTRACT from 45+01 - 1+01 - 4480 LF x 1.15 9 5,152.50 2- SID item 6P-2 880.00 3. 8ID Item 5-e 13,360,00 4. 210 Itom BP-42 7,313.59 S. BID Item 6.4 Credit to City _ 1328,901 Total 'Total Extra credit 26. 709 26, 09 26.801 Grand Total $ 26 3�I If you have any queetiona, please notify me. sincerely, 014l^ G401E � Project manager RPR-25-194 MON 14:09 ID: ITY OF DENTON UA TEL NO:817-566-8120 9833 PO4 EXCERPT FROM PUBLIC UTILITIES BOARD MINUTES April 18, 1994 The following item was considered: 11. CONSIDER APPROVAL OF UNIVERSITY DRIVE SANITARY SEWER CHANGE ORDER #2 Allison presented this item. After eItem extensive discussion, Coplen made a motion to approve Seconded by Thompson. All ayes, no nays, motion carried.