HomeMy WebLinkAbout1990-1192651L-9/3689 ORDINANCE NO. �7 AN ORDINANCE AUTHORIZING THE EXECUTION OF A CHANGE ORDER TO A CONTRACT BETWEEN THE CITY OF DENTON AND JAGOE-PUBLIC COMPANY; PROVIDING FOR AN INCREASE IN THE CONTRACT PRICE; AND PROVIDING AN EFFECTIVE DATE. WHEREAS, on March 12, 1990, the City awarded a contract for the construction of certain improvements to Jagoe-Public Company in the amount of $1,173,266.50; and WHEREAS, the City Manager having recommended to the Council that a change order be authorized to amend such contract with respect to the scope and price and said change order being in compliance with the requirements of Chapter 252 of the Local Government Code; NOW, THEREFORE, BE IT ORDAINED BY THE COUNCIL OF THE CITY OF DENTON: SECTION I. That the change order to the contract between the City and Jagoe-Public Company, a copy of which is attached hereto, in the amount of Twenty Thousand One Hundred Eleven and 98/100 ($20,111.98) Dollars, is hereby approved and the expenditure of funds therefor is hereby authorized. SECTION II. That this ordinance shall become effective immediately upon it passage and approval. PASSED AND APPROVED this p1/15lday of , 1990. BOB CASTLEBERRY, MAY R ATTEST: JE IFER WALTERSr Cl/T^Y SECRETARY BY: �IX�LXitA APPROVED AS TO LEGAL FORM: DEBRA A. DRAYOVITCH, CITY `ATTORNEY BY: DATE: August 21,1990 CITY COUNCIL REPORT TO: Mayor and Members of the City Council FROM: Lloyd V. Harrell, City Manager SUBJECT: BID #1069 - OAK HICKORY & FRY PAVING AND DRAINAGE (CHANGE ORDER #3) P.ECOMMENDATION: We recommend Change Order #3, to Bid #1069, in the amount of $20,111.98 be approved. SUylMARY: This Change Order is for additional curb/gutter and sidewalk required along Fry Street due to additional work required for water and sewer services. A portion of this expense is for the addition of handicap ramp along Fry Street. The original contract price was $1,173,266.50. Change Order 1 and 2 previously approved by Council, increased the project to $1,209,379.92. Change Order #3 increases the total to $1,229,249.90. BACKGROUND: City of Denton, Change Order dated August 9, 1990, and Memorandum dated August 8, 1990 from David Salom, Civic Engineering. PROGRAMS, DEPARTMENT OR GROUPS AFFECTED: Engineering Department, Jagoe Public Construction and citizens utilizing the Fry Street area. FISCAL IMPACT: Funds for this Change Order will come from Street Improvement Bond Funds. Account #434-002-0010-8503-9105. Respectfully submitted: L1 d V. Harrell City Manager Prepared by: Name: Tom D. Shaw, C.P.M. Title: Purchasing Agent TS/jh 044.DOC CITY OF DENTON CHANGE ORDER 1. Division(Department) Purchase Order No. 3. Change Order No. Engineering 96854 3 4. Name of Project 5. Project Acct No. 6. Date Prepared Oak,Hickory & Fry Paving /Drainage 434-UO2-0010-8503-9105 August 9, 1990 Name and Address of rac LUV Jagoe-Public Co P.U. Box 25U - Denton, Tx. 762U1 8. escription of Worknc u e in Contract See Memo Attached 9. C anges ordered and reason or ere ist individual changes as: A, B, C, D. etc. See Memo Attached U. bid --T-r1ginal Contract Revised Negotiatedrigina evise Contract Item Estimated Unit Estimated C.O. Unit Estimated Estimated Changes No. Quantity Price Quantity Price Cost Cost B. C. D. otal Total 11. Original Contractrice U Increase in Conlract Price , New Contract Price *$112999 Decrease in Contract Price *with Change Order 12. Contract ime increased/decrease y ays. New contract ime ays THE AFOREMENTIONED CHANGE, AND WORK AFFECTED THEREBY, IS SUBJECT TO ALL CONTRACT STIPULATIONS AND COVENANTS. 13. ISSUED FOR REASONS INDICAIED ABOVE: 14. ACCEPTED BY CITY ENGINEER: 15. ACCEPTED BY CONTRACTOR: N 16. ASSISTANT CITY MANAGER 'Jii I u) �— _c:J. 01 DIRECTOR OF UTILITIES: LJ ' CONDITIONS OF APPROVAL: roll Coll 17. PURCHASING/FINANCE on Supervisor n4ture —Titre gnature 0-9-5?o aIe V-ir,.-F.'-..... y-9-9p lit`lle Date Signature �e ---ffa-fe igna ure --TTETe— )—fate Signature ---Tl-FFe-- —6afe-- COUNCIL APPROVAL (If needed) 0637E Date Fry Street Overlaq • - _- - Cy c 1 *.w i 3:.4 5P"" CITY Of DENTON y SiD SHEET 317• SA6-3200, D/FM ?4M434-2S20 _Ni:neenrq ?ivision 817/566-8358 .,ecartment V?.:S6c-?-151 ,'4ntr3ctor: ;roJect: ;q 3t "Ner!iq 31d 40.: ?ti9 Ito. r. a ntrsct ng Days: 5 ?eriod 7 - / -g To 7 - ?a address: P.O. Sox 250, Benton, Texas Estimated Contract goat: P 0. No.: 96854-Acct.*4340002 5885 8508 9105 Days Used 1A04 Unit Quantity Quantity :,E%RIPT1ON OF WORK Of Original Completed ;'em • Measure Estimate to Deb SP-51 Mtll .A 2" N11AC �veriay SY 1,378 . 1378 SP-15.A �tj'at ialve EA 1 1 P- ".? :4I rt Manhole EA 1 C flange Orders: 3-8 Remove Cone. C & G 3-C Remove Conc. Drives �idititiiteel 3.2-A Cant. 5.3-4-1 6" Coat - 8.3-A 4- Cone. S1W 8.3-8 6"Corte. D/W SP-2 Concrete Saw Lf SY SY SY Lf valet ,r- •.- Unit of Compteteot,. - _- Price Work f8.35 tl L,306 $150.00 $150.00 $250.00 $0.00 TOTAL $11,656.30 530 $1.80 $954.00 10.67 $4.00 $42.68 54.04 $35.00 $1,891.40 568 $6.00 $3,408.00 23 $23.50 $540.50 S59.17 $20.00 $11,183.40 50 $23.50 $1,363.00 424 $1.00 $42400 Pagt 1 Fry Street Overlay .y ;tem t;c:ra Quantity Quantity yaiue 6DESCRIPT Of Original Completed Unit of Completed rudWre Estimate to Date Price Work tinge Orders Cow 3rmk„ q Out C,rw. LF 305 'tl .00 M5.00 Change Order %tal ;20, i 1 1.98 Partial Estimate Total $31,768.23 Less Previous Estimate Amount Due This Estimate • � rF pop 2 rb � The undersigned Contractor certifies that all work on hand , including materials and equipment , covered by this Periodical Payment has been completed or delivered in accorder" ante the Contract Documents, that all amounts have been paid by him for work, materials, and equipment for which Previous Payments were issued and r ived from the Owner, aW that current payment shovn herein is due. CONTRACTOR JAGOE—PUBLIC CO. By Date �O alefXW for Payment by: Total Value of Original Contract Performed 14 s-6.30 Extra Work Pgrformed - Shown Above or Zo tlnspccl Dole --=-- Attached Statement Materials on Hand - Shown Above or _ ion Dept. Date Attached Statement Approved for Payment By: Utility Dept. or City Engr. Date Total Val ue of Work to Date less: Amt. Retained -./_% Net Amount Earned on Contract less Amount of Previous Payments BALANCE DUE THIS ESTIMATE 3/.� ZS