AN ORDINANCE AUTHORIZING THE EXECUTION OF A CHANGE ORDER TO A
CONTRACT BETWEEN THE CITY OF DENTON AND TONTO CONSTRUCTION, INC ,
AND PROVIDING AN EFFECTIVE DATE
WHEREAS, on February 17, 1987, the City awarded a contract
for the construction of certain improvements to the Water
Treatment Plant Upgrade Phase II, Bid No 9657, and
WHEREAS, the City Manager having recommended to the Council
that a change order be authorized to amend such contract and said
change order being in compliance with the requirements of art
2368a, V A C S , NOW, THEREFORE,
BE IT ORDAINED BY THE COUNCIL OF THE CITY OF DENTON
SECTION I That the change order to the contract between the
City and Tonto Construction, Inc in the amount of Twenty-nine
Thousand Eight Hundred and Two Dollars and Fourteen Cents
($29,802 14) is hereby approved and the expenditure of funds
therefor is hereby authorized
SECTION II That this ordinance shall become effective
immediately upon its passage and approval
PASSED AND APPROVED this the 1st day of December, 1987
ATTEST
IN W ^
APPROVED AS TO LEGAL FORM
DEBRA ADAMI DRAYOVITCH, CITY ATTORNEY
�l�1111 �Z ,, 1 i /L_!
DATE December 1, 1987
CITY COUNCIL REPORT
TO. Mayor and Members of the City Council
ROM Lloyd V Harrell, City Manager
SUBJECT CHANGE ORDER #6
TONTO CONSTRUCTION, INC
RECOMIENDATION We recommend this Change Order #6 in the amount of
$29,802 14 to Tonto Construction, Inc be approved
SUiSI RT This change order involves the replacement of a caustic soda
tank in conjunction with the Denton Water Treatment Plant upgrade
order The Public Utility Advisory Board has approved this change
BACKGROUND Memo of December 1, 1987
Proposal from Tonto Construction
PROGRAMS, DEf�ARTMENTS OR GROUPS AFFECTED
FISCAL 111PACT
Water Treatment Plant Upgrade Phase II
1987/88 Water Utility Bond Funds
Account # 623-008-0460-9101
Res/pect�l/l l�y�//s�ubmi tted
Lloyd V Harrell
City Manager
Prepared by
N Tom D Shaw, C P M
Title Assistant Purchasing Agent
Approved
41on
Marshall, C P M
;m'eX
1tle. Purchasing Agent
Dec( 5er 1, 1987
CITY COUNCIL AGENDA ITEM
TO CHAIRMAN AND MEMBERS OF THE PUBLIC UTILITIES BOARD
FROM R E Nelson, Executive Director of Utilities
SUBJECT CHANGE ORDER #6- (Caustic Tank-TONTO CONSTRUCTION
INC) WATER TREATMENT PLANT
RECOMMENDATION
The Public Utilities Board, at their meeting of November 18, 1987,
recommended to the City Council approval of the attached change order
#6 concerning replacement of a caustic tank in conjunction with Phase II
Upgrade of the Denton Water Treatment Plant Project in the amount of
$29,802 14
SUMMARY:
The existing fiberglass sodium hydroxide tank has been seriously leaking
after several attempts at repairs by the tank manufacturer The existing
tank needs to be replaced by a polyethylene tank of the same size and
capacity as soon as possible
BACKGROUND
In 1981, a fiberglass tank was installed at the Water Treatment Plant for
the purpose of changing over to liquid sodium hydroxide (caustic) for
adjusting the Ph of water in the treatment process Since that time, the
fiberglass tank has been subjected to this highly corrosive chemical and
has not withstood the deterioration even after several repairs were made
by the tank manufacturer Since that time, the water treatment industry
has developed a more chemically inert tank using polyethylene
Polyethylene does not react with sodium hydroxide and has been found to
be highly suitable for containing this highly corrosive chemical
The Utilities Staff needs to get this unsatisfactory tank replaced at this
time by Tonto Construction Company as a part of the Water Treatment
Plant Phase II upgrade contract This tank is in danger of rupture which
could result in a possible shutdown of the Water Treatment Plant
5168U 9
Page 2
A second tank of polyethylene material has recently been installed by
Tonto Construction Company as part of this project However, the
Utilities Staff thought that the existing fiberglass tank could be salvaged
by further repairs which has proven not to be the case
PROGRAMS, DEPARTMENTS OR GROUPS AFFECTED
City of Denton, Denton Municipal Utilities, Engineers and Contractors,
and the citizens
F15CAL IMPACT:
Previous Contract Amount $30618,309 27
Net increase in contract amt 1
for tank $29,802 l4
Revised Contract Amount $3,648,11 1 41
Net change in contract time of completion- no change
ec/tf/idly submitted,
v
loyd Harrell
City Manager
Prepared & Approved by:
X21-9 �ol--
E Nelson, Executive Director
Department of Utilities
Exhibit I Change Order #6
Minutes PUB Meeting of 11/18/87
5168U:9.10
Con r...o consCrucCion Inc
GENERAL AND HEAVY CONSTRUCTION
TC 114-042
October 14, 1987
Mr C David Ham, P E
Director of Water h
Wastewater Utilities
Service Center/Warehouse
901-A Texas Street
Denton, Texas 76201
RE Denton Water Treatment Plant
Upgrade - Phase II
SUBJECT Change Order No 6 (Caustic Tank)
Dear Mr Ham
Please find attached five (5) copies of Change Order No 6
regarding the new caustic tank additions for your execution
Please return a fully executed copy to us upon your approval
Sincerely,
TONTO CONSTRUCTION, INC
Alov
Glenn A Landry
Vice President
GA/rmo
Enclosure
2417 WEST PARK ROW 0 SUITE 200 0 ARLINGTON TEXAS 76013 0 PHONE (817) 480 0666 0 METRO 461 6633
CHANGE OR EXTRA WORK ORDER
PROJECT Denton Water Treatment Plant Upgrade - Phase 2
CONTRACT No 9657
OWNER City of Denton, Texas
CONTRACTOR: Tonto Construction Co
CHANGE ORDER NO Six (6) DATE October 6, 1987
CHANGE OR EXTRA WORK TO BE PERFORMED
Contractor to replace the existing fiberglass sodium hydroxide tank
with a polyethylene tank of the same size and capacity as specified in
Section 11234 of the Contract Specifications The tank is to be
insulated, heat traced and is to meet all other provisions of the
contract drawings The tank is to be provided with appurtenances of
the same size and location as the tank which is to be replaced The
contractor is to ensure that the heat tracing on the new tank is
compatible with existing circuit breakers and wiring which was provided
for energizing the heat tracing on the existing tank or will make
revisions as necessary to accommodate the new tank
The existing tank is to be relocated to the City of Denton Wastewater
Treatment Plant and be set in the storage yard located near the pole
barn
Amount to be Added $ 29,802 14
The compensation agreed upon in this Change or sxtre Work Order is a
full, complete and final payment for all costs the contractor may incur
as a result of or relating to this change whether said costs are known,
unknown, foreseen or unforseen at this time, including without
limitation, any cyst for delay, extended overhead, ripple or impact
cost, or any other effect on changed or unchanged work as a result of
this Change or Extra Work Order
Previous Contract Amount $ 3,618,309 27
Net Increase in Contract Amount $ 29,802 14
Revised Contract Amount 8 3,648,111 41
Net Change in Contract Time of Completion No Change
Revised contract time of completion June 29. 1988
Recommended by
FREESE AND NICHOLS, INC
By _C :?'
Approved by OWNER
By
Approved by
Mwil . t
EXCERPT FROM MINUTES
PUBLIC UTILITIES BOARD
November 18, 1987
TREATMENT_ PLANT i
Ham introduced this item stating that the existing fiberglass
sodium hydroxide tank has been seriously leaking after several
attempts at repairs by the tank manufacturer The existing tank
needs to be replaced by a polyethylene tank of the same size and
capacity as soon as possible
Previous Contract Amount 03,618,309 27
Net increase in contract amt 1
for tank t29.,802 14
Revised Contract Amount 03,648,111 41
Net change in contract time of completion- no change
LaForte made a motion that the Board recommend approval to the
City Council for change order #6 in the amount of �29,802 14
Second by Thompson All ayes, no nays, motion carried