�soLUT1oN No. �011-047
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF DENTON, TEXAS,
APPOINTING A REPRESENTATIVE TO THE IH35E PROJECT STAKEHOLDER
COMMITTEE (SB 1420); AFFIRMATION OF COMMITMENT OF THE CITY OF DENTON,
TEXAS TO THE IH35E PROJECT 1N THE AMOUNT OF $250,000; AND PROVIDING AN
EFFECTIVE DATE.
WHEREAS, Texas Department of Transportation ("TxDOT") is engaged in project
development activities associated with the planned redevelopment of a 28-mile section of IH-
35E from I-635 to US 380 in Dallas and Denton Counties (the "IH35E Project"); and
WHEREAS, in Minute Order 112840, dated September 29, 2011, the Texas
Transportation Commission authorized TxDOT to issue a request for qualifications to develop,
design, construct, finance, maintain, and operate all or any portion of the IH35E Managed
LanesProj ect; and
WHEREAS, Section 228.013 of the Texas Transportation Code and TxDOT's rules
implementing that Section provide that a committee comprised of representatives from TxDOT,
the North Central Texas Council of Governments ("NCTCOG"), the North Texas Tollway
Authority ("NTTA"), and each city or county that provides local funding or right-of-way for a
toll project that will be developed to provide oversight for the project; and
WHEREAS, TxDOT and local stalceholders have determined those entities that may be
eligible to appoint members of the committee under Section 228.013 and TxDOT's rules; and
WHEREAS, the City of Denton, Texas has been requested by TxDOT to appoint one
member to represent the City on the committee, and to provide a copy of the resolution or other
action making or authorizing the appointment; and
WHEREAS, the City of Denton affirms funding of $250,000 of the IH35E Project within
the City of Denton, NOW, THEREFORE,
THE COUNCIL OF THE CITY OF DENTON HEREBY RESOLVES:
SECTION 1. The City Council of the City of Denton hereby appoints Pete Kamp as the
City of Denton representative to the Committee.
SECTION 2. The City Council of the City of Denton hereby affirms its commitment to
the IH35E Project in the amount of $250,000 within the City of Denton.
SECTION 3. This Resolution shall become effective immediately upon its passage and
approval.
PASSED AND APPROVED this the � day of ' i�%l2i�'�C� , 2011.
ATTEST:
JENNIFER WALTERS, CITY SECRETARY
� ,//� � � � �, ,
/
APPROVED AS TO LEGAL FORM:
ANITA BURGESS, CITY ATTORNEY
� �
BY:
Page 2 of 2
CSJ #: 0195-03-050
District #: 18-Dallas
Code Chart 64 #:11400
Project: IH 35E
Limits: From US 77 south of Denton to IH 35W
STATE OF TEXAS §
COUNTY OF TRAVIS §
LOCAL PROJECT ADVANCE FUNDING AGREEMENT FOR
VOLUNTARY LOCAL GOVERNMENT CONTRIBUTIONS
TO TRANSPORTATION IMPROVEMENT
PROJECTS WITH NO REQUIRED MATCH
ON-SYSTEM
THIS AGREEMENT is made by and between the State of Texas, acting through the Texas
Department of Transportation, called the "State", and the Citv of Denton, acting by and through its
duly authorized officials, called the "Local Government."
WITNESSETH
WHEREAS, Texas Transportation Code, Chapter 201 and 222 authorizes the State to lay out,
construct, maintain, and operate a system of streets, roads, and highways that comprise the State
Highway System; and,
WHEREAS, Texas Government Code Chapter 791 and Texas Transportation Code §201.209 and
Chapter 221, authorizes the State to contract with municipalities and political subdivisions; and,
WHEREAS, Texas Transportation Commission Minute Order Numbers 112844 and 113074
authorizes the State to undertake and complete a highway improvement generally described as to
reconstruct IH 35E from 4 lanes to 6-8 Mainlanes, construct 2 concurrent Managed/High Occupancy
Vehicle lanes and 2-3 frontage roads on IH 35E from US 77 south of Denton to IH 35W; and,
WHEREAS, the Local Government has requested that the State allow the Local Government to
participate in said improvement by providing a fixed contribution towards the construction cost to
reconstruct IH 35E from 4 lanes to 6-8 Mainlanes, construct 2 concurrent Managed/High Occupancy
Vehicle lanes and 2-3 frontage roads on IH 35E from US 77 south of Denton to IH 35W, called the
"Project"; and,
WHEREAS, the State has determined that such participation is in the best interest of the citizens of
the State;
NOW, THEREFORE, in consideration of the premises and of the mutual covenants and agreements
of the parties hereto, to be by them respectively kept and perFormed as hereinafter set forth, the
State and the Local Government do agree as follows:
AFA—LPAFA_VolProj Page 1 of 4 Revised 04/01/11
CSJ #: 0195-03-050
District #: 18-Dallas
Code Chart 64 #:11400
Project: IH 35E
Limits: From US 77 south of Denton to IH 35W
AGREEMENT
1. Time Period Covered
The period of this Local Project Advance Funding Agreement (LPAFA) is as stated in the Master
Agreement Governing Local Transportation Project Advance Funding Agreements (MAFA), without
exception.
2. Project Funding and Work Responsibilities
The State will authorize the performance of only those Project items of work which the Local
Government has requested and has agreed to pay for as described in Attachment A, Payment
Provision and Work Responsibilities which is attached to and made a part of this contract. In addition
to identifying those items of work paid for by payments to the State, Attachment A, Payment
Provision and Work Responsibilities, also specifies those Project items of work that are the
responsibility of the Local Government and will be carried out and completed by the Local
Government, at no cost to the State.
3. Payment of Funds
Whenever funds are paid by the Local Government to the State under this agreement, the Local
Government shall remit a check or warrant made payable to the "Texas Department of
Transportation Trust Fund." The check or warrant shall be deposited by the State in an escrow
account to be managed by the State. Funds in the escrow account may only be applied by the State
to the Project. If, after final Project accounting, excess funds remain in the escrow account, those
funds may be applied by the State to the Local Government's contractual obligations to the State
under another advance funding agreement with approval by appropriate personnel of the Local
Government.
4. Right of Access
If the Local Government is the owner of any part of the Project site, the Local Government shall
permit the State or its authorized representative access to the site to perform any activities required
to execute the work.
5. Adjustments Outside the Project Site
The Local Government will provide for all necessary right of way and utility adjustments needed for
performance of the work on sites not owned or to be acquired by the State.
6. Responsibilities of the Parties
Responsibilities of the Parties will be under the conditions as provided for in the MAFA, without
exception.
7. Document and Information Exchange
The Local Government agrees to electronically deliver to the State all general notes, specifications,
contract provision requirements and related documentation in a Microsoft� Word or similar
document. If requested by the State, the Local Government will use the State's document template.
The Local Government shall also provide a detailed construction time estimate including types of
activities and month in the format required by the State. This requirement applies whether the local
entity creates the documents with its own forces or by hiring a consultant or professional provider. At
AFA—LPAFA_VolProj Page 2 of 4 Revised 04/01/11
CSJ #: 0195-03-050
District #: 18-Dallas
Code Chart 64 #:11400
Project: IH 35E
Limits: From US 77 south of Denton to IH 35W
the request of the State, the Local Government shall submit any information required by the State in
the format directed by the State.
8. Inspection and Conduct of Work
Unless otherwise specifically stated in Attachment A, Payment Provision and Work Responsibilities,
to this contract, the State will supervise and inspect all work performed hereunder and provide such
engineering inspection and testing services as may be required to ensure that the Project is
accomplished in accordance with the approved plans and specifications. All correspondence and
instructions to the contractor performing the work will be the sole responsibility of the State. Unless
otherwise specifically stated in Attachment A to this contract, all work will be perFormed in accordance
with the Standard Specifications for Construction and Maintenance of Highways, Streets, and
Bridges adopted by the State and incorporated in this agreement by reference, or special
specifications approved by the State. .
9. Increased Cost
Increased cost will be under the conditions as provided for in the MAFA, without exception.
10. Maintenance
Project maintenance will be under the conditions as provided for in the MAFA, without exception,
11. Termination
Termination of this LPAFA shall be under the conditions as stated in the MAFA, without exception.
12. Notices
Notices of this LPAFA shall be under the conditions as stated in the MAFA, without exception.
Local Government:
City Engineer
City of Denton
901-A Texas Street
Denton, Texas 76209
State:
Director of Contract Services
Texas De�artment of Transportation
125 E. 11 " Street
Austin, Texas 78701
13. Successors and Assigns
The State and the Local Government each binds itself, its successors, executors, assigns, and
administrators to the other party to this agreement and to the successors, executors, assigns, and
administrators of such other party in respect to all covenants of this agreement.
14. Amendments
Amendments to this LPAFA shall be made as described in the MAFA, without exception.
15. Incorporation of Master Agreement Provisions
This LPAFA incorporates all relevant provisions of the MAFA in effect on the date of final execution
of this LPAFA, unless such MAFA provision is specifically excepted in this agreement. Any conflict
between the terms of the MAFA and this LPAFA shall be governed and controlled by this LPAFA.
16. State Auditor
AFA—LPAFA_VolProj Page 3 of 4 Revised 04/01/11
CSJ #: 0195-03-050
District #: 18-Dallas
Code Chart 64 #:11400
Project: IH 35E
Limits: From US 77 south of Denton to IH 35W
The state auditor may conduct an audit or investigation of any entity receiving funds from the State
directly under the contract or indirectly through a subcontract under the contract. Acceptance of
funds directly under the contract or indirectly through a subcontract under this contract acts as
acceptance of the authority of the state auditor, under the direction of the legislative audit committee,
to conduct an audit or investigation in connection with those funds. An entity that is the subject of an
audit or investigation must provide the state auditor with access to any information the state auditor
considers relevant to the investigation or audit.
17. Insurance
If this agreement authorizes the Local Government or its contractor to perform any work on State
right of way, before beginning work the entity performing the work shall provide the State with a fully
executed copy of the State's Form 1560 Certificate of Insurance verifying the existence of coverage
in the amounts and types specified on the Certificate of Insurance for all persons and entities working
on State right of way. This coverage shall be maintained until all work on the State right of way is
complete. If coverage is not maintained, all work on State right of way shall cease immediately, and
the State may recover damages and all costs of completing the work
18. Signatory Warranty
Each signatory warrants that the signatory has necessary authority to execute this agreement on
behalf of the entity represented.
THIS AGREEMENT IS EXECUTED by the State and the Local Government in duplicate.
THE LOCAL GOVER��'NENT — CITY OF DENTON
� , u �
�
B ;�� �" ,., � . m � _ m -
�� ���. ��� .��� .... -� � -� ����� ����
t� ��c�� C. Campbell
City Manager
Date: � ��..�':����_..���.�..���.
Approved as to Form:
Anita Bur ��
City Attor �+��'� �
�
� �
gy: � � � ,,,� qa.� �..� � a ....�
,..�������.��..
Anita Burgess
City Attorney
TH� ,�T�T� +I�� TEXAS
�
�����. � �� �
�� .�
B * �° � ��
y. � _ „ � �.
. .�� � �� ,
����.� �
� William L. Hale, P.E.
� Interim Dallas District Engineer
Texas Department of Transportation
Date: ��� �� �� �
AFA—LPAFA_VolProj
ATTEST:
Jennifer Walters
City ,� �r�tary
BY�� , �
_.�.�� "��.� � .�.. ��
� Jennif r ��lt�rs
City �� ����ry
Page 4 of 4
Revised 04/01/11
CSJ #: 0195-03-050
District #: 18-Dallas
Code Chart 64 #:11400
Project: IH 35E
Limits: From US 77 south of Denton to IH 35W
Attachment A
PAYMENT PROVISION AND WORK RESPONSIBILITIES
The Local Government will provide a fixed contribution of 250 000 towards the cost to reconstruct IH
35E from 4 lanes to 6-8 Mainlanes, construct 2 concurrent Managed/High Occupancy Vehicle lanes
and 2-3 frontage roads on IH 35E from US 77 south of Denton to IH 35W. The Local Government's
fixed contribution for this improvement includes construction items and direct state costs.
Total Federal State Local
Description Estimate Cost Participation Participation Participation
...% .. __�� �. r o_ ................� Cost ��._�...............o....�.....
(Fixed)
COSt /o /o COSt
Construction (by State) $228,959 0% $0 0% $0 100°/o $228,959
Direct State Cost @ 9.19°/o $21 041 0% $0 0% ° $21.04
_..� .�.N.. � .....� . � . ..... � . ........$0 100 /o .�..�..� .
direct State Cost @5.94% $13,600 0% $0 100% $13,600 0% $0
I n ���. � � . ...... _ .. .�.� � �.�.�.�.�..._.....
TOTAL� 0 $13,600 � (Flxed) $250,000
....._��..._ m..�263,600 __ ���. �_.... � ...... ....... ��.�_
Total Local Government Participation = $250,000 (fixed)
Total Payment by the Local Government to the State on full execution of this Agreement =$250,000 (fixed)