Loading...
HomeMy WebLinkAbout09-1966 I i fAt~ C~a f'y CITY OF DENTON, 'T'EXAS Specifications and Contract Documents For the Construction of HANGAR AND OFFICE BUILDINGS AT DENTON MUNICIPAL AIRPORT A. ` Prepared by c, `y DEPARTMENT OF COMMUNITY DEVELOPMENT c~ a• THE CITY OF DEN'PON r DENTON, TEXAS n SEPTEMBER, 1966 (SZ-Z~ 4t Addendum #3: This addendum shall be attached to are becoa;e a part of the Specifications and Contract Documents fo- the construction of Hangar and,Office Buildings at Denton Yu.ticipal Airport, City of Denton, Texas. 1. The note regarding tie beams listed on sheet 3 of the plans is ammended to read as follows: Tie beams shall havea maximum spacing of 20 feet on centers each way. 2. The 18" x 18" x 9" footing Indicated to be located beneath each column in the interior wall shall be omitted and replaced with the twelve (1211)' inch diameter piers and twenty (20") inch diameter bell required beneath all columns. 3. The five ton all. se electric heating and airconditioning unit indicated on sheet two of t'Ze plans shall be installed, complete, including exterior compressor, djetwork, wiring, thermostats,-and all other items of work required for a complete installation. 4: The contractor shall furnish nn9 install two water faucets in tte main hangar and office building, Both shall be located in the block wall, one adjacent to thq rest roots between bays B and F, and one in the same wall between bays B and C. I r Addendum 14: This addendum shall be attached to and become a part of the Specifications and Contract Documents for the construction of Hangar and Office Buildings at Denton Municipal Airport, City of Denton, Texas. 1. The first sentence of paragraph 100.5, Payment, is ammended to read as follows: Payment shall be based on a lump sum bid and shall be payable to the Contractor upon the completion of the project and acceptance by the City. 2. The exterior electrical service connection to the ma.ln hangar shall be made by the Contractor with no additional cost to the City. The underground connection shall extend from the transformer pad to the hangar, a distance of approximately 280 feet. The underground • electrical Installation shall conform to the requirements of tho City of Denton concerning such installations. Service drop shall consist of three wire 14/0 AWG (Cu) in r. 4 - inch conduit buried 42 - inches below finish grade. P. V. C. conduit Class 11 Direct But-lal may be used. All risers and 900 elbows :,hall be heavy wall galvanized. steel conduit. The ditch shall be made zvallable to General Telephone Company for telephone installation. 3. Asphalt the floor covering shall be Installed in the office, lobby, and rest rooms in the main hangar and office building. t The doors on the main hangar building shall open to provide an ning of a minimum of 108 feet in width and 19 feet in height, clear free of any obstructions. No part of any columns or beams shat. end Into the required opening. --Q LAI Iq ~ . i , %,mrm- TO -nn;;R; ' Sealed proposals ad,lresscd to tLe City of Denton, Denton County, Texas, will be received at the office of the City Secretary, City Hall, Denton, Texas, until 10:00 A.N., C.S.T., September 29, 1966, for constructing improvements at the City's Municipal Airport as follows: Contract A: For Constructing One (1) :•:atal Airplane Hangar with Office Space. Contract B: For Constructing Ten (10) Metal Airplane "T - Hangars". Contracts "A" and 143" will be awarded separately, but Bidders are invited to bid for either or both of said contracts. Bidders must submit with their bids a Cashiers or Certified Check payable to or endorsed, without recourse, to the City of Denton, Texas, in the, amount of $4,500 for Contract A and $1,750 for Contract B. or submit a Proposal Bond in the same amounts from a reliable Surety Company, as a guarantee that Bidder will enter into a contract and execute the required bond and guarantee within five (5) days after notice of award of contract to him. Bids without check or Proposal Bond will not be considered. In accordance with Article 5159(x) V.A.T.S. the successful Bidder will be required to furnish not only a Performance Bond in the amount of the contract, but also a Payment Bond in the amount of the contract, for ' the protection of all claimants supplying labor and materials as defined € in sr.id law. The bonds must be executed by an approved Surety Company holding a permit from the State of Texas to act as Surety, and acceptable according to the latest list of companies holding certificates of authority from the Secretary of the Treasury of the United States or• other Surety or Sureties acceptable to the City. a V . 1 f • i t i. All prices must be scatca i.„ :'igures The i ' City reserves the ri!;hz to ~c~; .:;,y o:- aids and to waive formalities. In case 017 cl-M)i;11:y OY lack of clearness in stat- ing the price in the bids, t;;c C:cy reserves vile right to con. sider the most advanta-cous co: s, :uctirn; z:,Icz•cof, or to reject the bid. Unreasonable or,u,:balanced prices will be con- sidorod sufficient cause ;Co;: rejection of any bid or bids. I Bidders are expected to •inspoct ha si.ee of the work and to in- form themselves regarding local conditions and conditions under .which the work is to be done. Not less than the prevailing rate of per diem wages for work of~ similar character in the City of Denton, and County of Denton, and not less than the general prevailing rate of per diem wages for legal holidays, Saturdays, Sundays, and overtime work shall be paid to all laborers, workmen and mechanics employed in connection with the foregoing Contracts. no City Council of the City of Denton has ascertained and here j specifies such general prev<.:.Iing rate, of per diem wages in said City and County to be as follows: Mechanic Workman or Prevailing (8 hour . i Type of Craft or Laborer Hourly Rate daX, ' Asphalt Heaterman $1.50 1 Asphalt Raker 1.75 ' Asphalt Shoveler 1.50 Batching PIz..t Scaleman 1.60 Carpenter 2.50 f Carpenter Helper 1.75 Concrete Finisher 2.25 f Concrete Finisher Helper 1.75 Form Builder (Structures) 2.25 Form Builder Helper (Structures)' 2.00 J Form Setter (Structures) 2.25 Form Setter Helper (Str'uctures' 2.00 Laborer, Comimon 1.45 Laborer, Utility Aian 1.50 Mechanic. 2.50 Mechanic Helper 1.75 OiI:.. 1.75 Paintb.' (Struc~ures) 2,25 Painter Helper (Structures) 1190 Pipe Layer (Concrete & C1.,-) 1195 Pipe La er Helper Concrete & Clay) 1.60 wo',:k .an Or .'rcvailing (8 hour I .0"na Ozl" Cr1:: Or Lnb.~~c :lour Rare daY~ ?Owar Equi O,)erzzo~:6: I sphalr istriou :or 2.00 As?halt Paving M..c:ginc 2.00 3u11dozer, Ovcr 30 2.50' Cranc, l/~4Vlina, SnoveA. `..1:5,7 C.1.) 2.50 ' Cane, Clamshell, Draaliaa, Shovol (I?! C..'. t.ua Oval) 2.75 ::iectricia.zs 3.75 Ce:•,,:nt Masons a.20 ~i:.ziers 2,00 lu,m'uers 2.75 Sheet Metal WorAerS 2.88' ~ . . ok:nccltion Grill Gpeator (Cr-wicr Mounted) 3.00 oundation Diiil Operator ('i'ruc:c Mounted) 3.00 oundation Drill.Operator Helper 2.00 Front End Loader (1 C.Y. and Less) 2.00 r ro•nt End Loader (Over 1. C .Y 2.25 Mixer (Over 16 C.F.) 2.40 Mixer (Concrete Paving) 2;50 ,rotor Grader Operator, Fine Grada 2.50 Concrete Paving Saw 1.75 :rotor Grader Operator' $2.35 ; Roller, Steel 'heel (Plant-;fix Pavement) 2,00 Roller, Steel Wheel (Other) 1.75 ' Roller, Pneumatic (Self -?ropeIled) ` 1150 Scrapers (Ovar 7 C.Y.) 2,50 Side Boon; 2.35 Tractor (Crawler Type) 80 H.P. and leas 1450 { Tractor (Crawler Type) Over 80 11.P. 2050 Tractor (Pneumatic) 80 H.P. lass 1.50 Tracror (P:.aumacic) Over 80 N.40. 1.75 , i Trenching Machine, light 2•.35 Trenching Machine, Heavy 3,50 Reinforcing Steel Setter; (Pav:.,:g) 1150 Strl~<.~u:3s ( ) .80 Reinforcing Steel Setter 1 Reinforcing Steel Sette-A: lit1r c:r 1150 : . Steel Worker (Structuroi) 2.60 ' Steel Worker Helper (Structural) 2.00 Spreader Box Man 1.75 True& Drivers: ' Single Axles Light 1.50 Single .'4 a, Heavy 1.50 f . Tar gem Axle or Sewltrai:er 1.50 Winch,- . 1•. 75' Vibrator, Man (Hand Type) 1.40 ' ; Welder 3.00 ~ . iU% J: iOrC0Oli10 1a; eS 0. Sundays, lc;;al 1•io'' idays, and OVeI ti~.;~ WorK. lnszruc::ions to Bii:ders, S;)ccifications, Plans and Can..rac,. Docua:. n-s b.L. JI .41 r.,, ;.:-,c offAce of the City , Se;:retary, City 'wril V A%o,;. r,nd c:, ►ic., C of said ins,.ru- ments may be obtainorl 40'evez,*A y" upon deposit o£ $25.00 as a guarantee o: ,c I-a ur:-a 02 the plans and specie r,ications. Said deposit will be vide(:; (1) The Bidder returns z ha plans and specifications ' within 72 hours a=ter the bid date; OR { (2) ine Non-Bidden returns the plans and specifications in good'. condition 72 hours prior to bid date; Otherwise the entire $25.00 deposit will be forfeited and no. refund made, Suppliers may obtain Specifications and plans at the address stated abova upon deposit Of Fifteen ($15,00) Dollars, which sum is non-refundable. It is the intention of the City Council of the City of Denton to issue tha time warrants ..)A the City of Denton for payment'of a past all oi~ the Contrac-cs to be made pursuant to this I { Notice, an8 to pay part. oi: all of the Engineer's fees in connaction therewith. 'i':Iu nip:::iraum a,a:ount of time warrant indebteaness to be incurred For said purposes shall be $125,000, the maximum rate of interest, such tine warrants are to bear is 4-12-% per annun, and the maturity date thereof shall be 19So, ino City has obtain((: carwmit,ae)ti:: from a ban's for the purchase of said time warr"n:.s ~ro;i tiie Contractor, so that said warrants shall be ::eliv:.::cd ; o the Contractor and the Contractor ; will immediately deliver said warrants to such bank and reeeiva in cash the par. value therefor. . =,y OF DzNiO:I, 'TEXAS BY:. BRCOXS HOLT,. r' ' CITY SECRETARY (J r. L , :SS UCTIGN 0 3:ODZM • oral wo:.c .:;c.u:ca t.i.S contract consists o: fur:.i5hind aA. i;c;Zci'i.Is, tu015, cc,uixrc,;t, etc. necessary for tl:c construCti-:~,l o. o:;,: ZCa L:,it Lc,! :;::abet and one hangar O.`.iCe bulldin60 CG+~;~)1C~.?, in aCCOrc1::.7C4p with the drawings znd as specified c.or. io, 2, teri, I.s ^ur^is:,.~d by : lac Ow„ar will furnish INTO materials. luC ('.O:,tractor shall t:. u.• L:a~CYlaIS, Cf~Uip7iCnt, etC. 3. Ti-•a of Cornletion: VGw,;,rr c:. sires L1-,C wor:c to he completed at tine earliest possible dcA cu. of cor.,pletion shall be as indicated in. tha Propo; al. - In the event, the Contrac or f~:;s to co:r.•):ete the project within t::e tine set fOVth in t:u: : copee.,l; Lha Gwr,er ehall withhold per uaneatly from th.: pay,.,. tc th,: Coatrlc for the sum of twenty- five ($25.00) dollars per :.::y zz, liruifIated damages, as set forth in Section 4.04 of the Conditions of the Agreement. 4. Bid Form: Bids shall be t..c.de c:. the blank form attached and the , complete documents and pl"r.s shzil be returned with the bids. Bids not so made will be considered out of form. 5. Perfo:.acnce Bond: With the execution and delivery of the contract, tae Contractor shall furnish performance bond for the full amount of the contract. Bond shall be executed by anki approved surety co,:.?any authorized to do business in the State of Texas, and acceptable accordin; to the latest list of coampanies holding Certi ' ficates o: Authority from the Secretary of the Treasury of the United States of A:narica. 6, Pav.ment Bond: In additioa to the Performance Pond the Contractor will furnish a P;.ymant Bond for the full amount of the contract, Pays-,ei.t Br.rd shall be executed by an• approved surety company au'tcorized to do busin.sss in:-the State of Texas, and acceptable according to the latest list of cospanies holding Certificates of Authority from the Secretary of the Treasury of the United States of America. 7. Bond: in additioa to t:.:: Performance Bond and Payment Bond, thc.`Joatractor will furnish a Maintenance Bond for ten (10%) perceat of the contract price. Maintenance Bond shall be executed by as approved r..:rety cor.pa:.y authorized to do business in the State of Texas, and acceptc;,le according to the latest list of companies holding Certificates of Authority from the Secretary of the Treasury of the United States of America. Maintenance Bond shall c rer:.ain in force f'or a-period of one ('1) year beyond the date of i. written acceptanco of the work by the Ow;er, to guarantee the repair and/or replacement of defective materials srd/or workmanship which may develop during this period. e 1 :.t his own expense :ooure all f:'a:.:: ;a, c~:.:.:c co; cult: os required o: aim a. by pay all patent u:..: 0 equipment 0: ..;:c coil; et:on o. phis project c::d s' all ~0:4A * z`c: G....~. _:xa a:.y liability, for the u80 of patents in t:: is wor:c 9. C:an^' Of ? c O . tl.~ alio.:,acnCB i6 COltCmplated. ::otaave:, should a -icc~ssary clue to obstructions or other masons the Ow.-Le.`., a~rJab the rib ;c to r,iCke such change, no extra coape:.,,ation L:i.. Je allowed t::e Co:tractor. 10. °.ohe:t`', Protection: ~~nCds, sibns, poles, guy wires and all ocher property s'r.ccl'. be protected unless their removal is authorized and any pra;:Crty damage shall be satisfactorily restored by the Contractor. 11. Tnvas.:i~,ation of 7.oca1 C;,::c,icior.s 2rior to submission of a proposal, the'Contractor s'rall have made a careful examination of the site of the work acd of the contract documents including the plans and speci:icatioas and shall become informed as to the location and nature u: L~,e proposcd construction, the kind of facilities requiled bc:"ore rnd during the construction , period;'labor conditions, and all other matters chat may affect • the costs sad time of com.2let:on of the work. 12. Internratation of O::oted ?rices; Tn crsa of a difference between the writte:. words and the :inures ins L'ne -Proposal, the amount stated in written words will be con$idered as the bid. 13. Int,~rn.atr,tion or Seocir_c tio:a: Any question as to the meaning of any spocifica ions will be answered by Addendum which will be sent to all wan h:.va been zurnished with the plans and spec i:ications. P '.)SAL Denton, Texas nrtnher 13. 1966 PRO?OSAL OF s Inc. a corporation organised under 610 10W4 Of 00 SLt6tc Of ' a partnership consisting of anti individual trading as , a^o the City of Denton, Texas: ' Pursuant to Invitation to ;ii~ucrs, as publislied, the under- signed proroses to furnish all tabor, materials, and equipment, and perform all work for the complcee co..struction of oac ten uni; tee hangar and/or one hangar and ofice building, in the strict accordance with the attached S,•ci:r:tion::'and accompanying Plans for the following : ITEM ESTIMATED :DZS::.i: i'ION UNIT PRICE TOTAL SID \0. OUAtiTIT`! ('r:c0• ')e a,,itten in words (Figures) (Figures) 1 Lump Sum Construction of one ten ulit tee hangar, complete, the sum of dollars and nts lump sum. 2. Lump Sum Construction of one hangar and .%o(~i nol ,~aS1~f;~a9 fit hundred seventy-six - m o. dollars and cents lump sum. Sim, $ 89.876.00 3. Lump Sum construction o: both Iten No. 1 ' and Item, No. 2, com2lete, the sum o:' dollars and cents lump sum. $ $ within ten (10) ,ays aster she dite o writ;, t., ork and to sub. ' stantially comr-lete the wor., ~:,I.nin eighty (80) working day, as defined in (a Agreement. Enclosed with this or Certified CL-eck for Four Thousand- Five Hundred ~L-4-o-gOQ.00 :,;,recd shall be collected a:td rQtQinek; by cl,. r, a8 iitiui6aLL dtimagel in the event this Proposal is ncc~i>t. , , ti--e Owner within thirt3 (30) days after the date aciv,.rti,. ~;ie reception of Bids and the undersigned fails to ^x _u; ,,.tnict and the required bonds with the Owner, under tta o1, within tcn (10) days bfPer tine date said Proposal c. Otherwise, said check or bond shall he returned to the upon demand. The undersigned hereby U'.clore that he has visited the site and has carefully examined tl•.c Contract Documents relative to the work covered by the above bid. Respectfully submitted, • A-& S Steel Buildings. Inc. ' -P. 0. Box 40099 Houston .-Texas _ Add so B Title (Seal if Bidder is a corporation) n GENERAL CONDITIONS OF AGREEMENT 1. DEFINITIONS OF TERMS 1.01 OWNER, CONTRACTOR AND ENGINEER: The Owner and the Con- tractor are those mentioned as such in the Agreement. They are treated throughout the Contract Documents as if each were of the singular number and masculine gender. The Engineer shall be understood to be the Engineer of the Owner or his duly authorized representative. 1.02 CONTRACT DOCUMENTS: The Contract Documents shall consist of the Notice to Contractors (Advertisement) Special Conditions (Instructions to Bidders), Proposal, signed Agreement, Performance and Payment "onds (when required), Special Bonds (when required), General Conditions of the Agreement, Technical Specifications, Plans, and all moditipatione thereof incorporated in any of the documents before the execution of the agreement. r The Contract Documents are complementary, and what is called for by anyone shall be as binding as if called for by all. 1.03 SUB-CONTRACTOR: The term Sub-Contractor, as employed herein, includes only those having a direct contract with the Contractor and it includedd one who furnishes material worked to a special design accordirig to the plans or specifications of'-this work,"but does not include one who merely furnishes material not so worked. 1.04 WRITTEN NOTICE: Written notice shall be deemed to have been duly served if delivered in person to the individual or to a member of the firm or to an officer of the corporation for whom it is intended, or if delivered at or sent by registered mail to the last business address known to him who gives the notice. 1.05 WORK: Unless otherwise stipulated, the Contractor: shall provide and pay for all materials, supplies, machinery, equipment, tools, superintendence, labor, insurance, and all water, light, .power, fuel, transportation, and other facilities necessary for the execution and completion of the work covered by the contract documents. "mess otherwise specified, all materials shall be new and bot1; workmanship and materials shall be of a good 'quality. The Contractor shall, if required, furnish satisfactory evidence as to the kind and quality of materials. Materials or work described in words,which so applied have a well known technical or trade meaning,shall be held to refer to such recognized standards. 'I 1.06 EXTRA WORKi The term "Extra Work" as used in this contract shall be understood to mean and include all work that may be required by the Engineer or owner to be done by the Contractor 1 to accomplish any change, alteration or addition to the work shown upon the plans, or reasonably implied by the specifications, and not covered by the Contractor's Proposal, except as provided under "Changes and Alterations", herein. 1.07 WORKING DAY: A "Working Day" is defined as any day not including Saturdays, Sundays or any legal holidays, in which weather or other conditions, not under the control of than Contractor, will permit construction of the principal units of the work for continuous period of not lessthan seven (7) hours between 7:00 a.m. and 6:00 p.m. 1.08 CALENDAR DAY: A "Calendar Day" is any day of the week or month, no days being excepted. 1.09 SUBSTANTIALLY COMPLETED: By the term "Substantially Completed" is meant that the structure has been made suitable for use or occupancy or the facility is in condition to serve its intended purpose, but still may require minor miscellaneous work and adjustment. 2. CONTROL OF WORK 2.01 LINES AND GRADES: Unless otherwise specified, all lines and grades shall be furnished by the owner or his representative. Whenever necessary, construction work shall be suspended to permit performance of this work, but such suspension will be as brief as practicable and the Contractor shall be allowed no extra compen- sation therefor. The Contractor shall give the owner or the Engineer ample notice of the time and place where lines and grades i will be needed. All stakes, marks, etc., shall be carefully preserved by the Contractor, anu in case of careless destruction or removal by him or his employees, such stakes, marks, etc., shall be replaced at the Contractor's expense. 2.02 ENGINEER'S AUTHORITY AND DUTY: Unless otherwise specified, it is mutually agreed between the parties to this Agreement that the Engineer shall supervise all work included herein. He has the authority to stop the work whenever such stoppage may be necessary to insure the proper execution of the contract. In oraer to prevent delays and disputes and to discourage litigation, it is further agreed that the Engineer shall in all cases deter- mine the amounts and quantities of the veyeral kinds of work which are to be paid for under this contract. He shall determine all questions in relation to said work and the construction thereof, and shall in all cases decide every question which may arise relative to the execution of this contract on the part of said Contractor. The Engineer's estimates and findings shall be the conditions precedent to the right of the parties.hejeto to arb1tration or to any action on the contract, and to any rights of the Contractor to or to any action on the contract, t..d to I 2 s: any right- of the Contractor to receive any money under this contract, provided, however, that should the Engineer render any decision or give any direction which in the opinion of either party hereto, is not in accordance with the meaning and intent of this contract, either party may file with said Engineer within thirty (30) days his written objection to the decision or direction so rendered, and by such action may reseLve the right to submit the question so raised to arbitration as herein provided. It is the intent of this agreement that there shall be no delay in the execution of the work; therefore, the written decision or directions of the Engineer as rendered shall be.promptly carried out, and any claim arising therefrom shall be thereafter adjusted by arbitration as hereinafter provided. The Engineer shall, within a reasonable time, render and deliver to both t-pie Owner and the 1ontractor a written decision on all ;laims of the parties hereto and on all questions which may arise relative to the execution of the work or.the interpretation of the contra.-t, specifications and plans. should the Engineer fail to make such decision within a reasonable time, an appeal to arbitration may betaken as if his decision had been rendered against the party appe-Aing. • Whenever the words "directed", "required", "permitted" "des ignat:ed "considered necessary" "prescribed", or words of like import at used, it shall be understood that the direction, requirement, per- mission, order, designation or prescription, of the Engineer is intended; and similarly, the words "approval", "acceptable", "satisfactory", or words of like import shall mean approved by or acceptable or satisfactory to the Engineer. 2.03 SUPERINTENDENCE AND INSPECTION: It is agreed by the Con- tractor that the Engineer shall be and is hereby author4zed to appoint from time to time such subordinate engineers, supervisors or inspectors as the said Engineer may deem proper to inspect the material furnished and the work done under this agreement, and to see that the said material is furnished, and said work is done in accordance with the specifications therefor. The Contractor shall furnish all reasonable aid and assistance required by the subordinate engineers, supervisors or inspectors for the proper inspection and examination of the work. The Contractor shall regard and obey the directions and instruction of any subordinate engineers, supervisors or inspectors so appointed, when such directions and instructions are consistent with the obligations of this Agreement and the accompanying plans and specifications; provided, however, should the Contractor object to any order by any subordinate engineer, supervisor or inspector, the Contractor may within six (6) days make written appeal to the Engineer for his decision. 2.04 CONTRAMOR's D'OTY AND SUPERINTENDENCEs The Contractor shall give personal attention to the faithful prosecution and completion of this contract and shall keep on the work, during its progress, 3 a competent superintendent and any necessary assistants, all satisfactory to the Engineer. The superintendent shall represent the Contractor in his eLeence and all directions given to him shall be as binding as if given to the Contractor. Important directions shall be confirmed in writing to the Contractor. Other directions shall be so confirmed on written request in each case. 2.05 CONTRACTOR'S UNDERSTANDING: It is understood and agreed that the Contractor has, by careful examination, satisfied himself as to the nature and location of the work, the conformation of the ground, the character, quality and quantity of the materials to be encountered, the character of equipment and facilities needed preliminary to and during the prosecution of the work, the general and local conditions, and all other matters which can in any way affect the work under this contract. No verbal agreement or conversation with any officer, agent or employee of the Owner, either before or after the execution of this contract, shall affect or modify any of the terms or obligations herein contained. 2.06 CHARACTER OF WORKMEN: The Contractor agrees to employ only orderly and competent men, skillful in the performance of the type of work required under this contract, to do the work; and agrees that whenever the Engineer shall inform him in writing that any man or men on the work are, in his opinion, Incompetent, unfaith- ful or disorderly, such man or men shall be discharged from the work and shall not again be employed on the work without the Engineer's written consent. 2.07 CONTRACTOR'S BUILDING: The building of structures for housing men, or the erection of tents or other forms of protection, will be permitted only at such places as the Engineer shall direct, and the sanitary conditions of the grounds in or about such struc- tures shall at all times be.maintained in a:mantier satisfactory to the Engineer, 2.08 SANITATION: Necessary sanitary conveniences for the use of laborers on the work, properly secluded from public observation, shall be constructed and maintained by the Contractor in such manner and at such points as shall be approved by the Engineer, and their use shall be strictly enforced. 2.09 SHOP DRAWINGS: The Contractor shall submit to the'Etigineer, with such promptness as to cause no delay in his own work or in that of any other Contractor, four copies, unless otherwise speci- fied, of all shop and/or setting drawings and schedules required for the work of the various trades, and the Engineer shall pass upon them with reasonable prcmptness, making desired corrections, The Contractor shall make any correction required by the Engineer, file with him two corrected copies and furnish such other copies as may be needed. The Engineer's approval of such drawings or 4 schedules shall not relieve the Contractor from responsibility for deviations from drawings or specifications, unless he has in writing called the Engineer's attention to such deviations at the time of submission, nor shall it relieve him from responsibility for deviations for errors of any sort in shop drawings or schedules. .10 PRELIMINARY APPROVAL: The Engineer shall not have the power Lo waive the obligations of this contract for the furnishing by the Contractor of good material, and of his performing good work as herein described, all in full accordance with the plans and specifications. No failure or omission of the Engineer to condemn any defective work or materiai. shall release the Contractor from the obligations ;:o at once tear out, remove and properly replace the same at any time prior to final acceptance upon the discovery of said defective work or material; providea, however, t}at the engineer shall, upon request of the Contractor, inspect and accept or reject any material furnished, and in evenb the material has been once accepted by tha Engineer, such acceptance shall be binding on the Owner, unless it can be cleaily shown that such material furnished does not meet the specifications for this work. Any questioned work may be ordered taken up or removed for re- examination, by the Engineer, prior to final acceptance, and if found not is accordance with the specifications for said work, all expense of removing, re-examination and replacement shall be borne by the Contractor, othctwise the expense thus incurred shall be allowed as Extra Work, and shall be paid for by the owner; prov:.ded that, where inspection or approval is specifically re- quired by the specifications prior to performance of certain work, should the Contractor proceed with such work regaceting prior inspection or approval he shall bear all expense of taking up, removing, and replacing this work, if so directed by the Engineer. 2.11 DEFECTS AND THEIR REMEDIES: It is further agreed that if the work or any part thereof, or any material brought on the site of the work for use in the work or selected for the same, shall be deemed by the Engineer as unsuitable or not in conformity with the specifications, the Contractor shall, after receipt of written notice thereof from the Engineer, forthwith remove such material and rebuild or otherwise remedy, such work so that it shall be in full accordance with this contract. 2.12 CHANGES AND ALTERATIONS: The Contractor further agrees that the owner may make such changes and alterations as the Owner may see fit, in th4 line, grade, form, dimensions, plans, or materials for the work herein contemplated, or any part thereof, either before or after the beginning of the constructbn, without affect- ing the validity of this contract and the accompanying performance and payment bonds. 5 If such changes or alterations diminish the quantity of the work to be done, they shall not constitute the basis for a claim for damages, or anticipated profits on the work that may be dispensed with, except as provided for unit price items under Section 5 "Measurement and Payment". If the amount of work is increased, and the work can fairly be classified under the specifications, such incoase shall be paid for according to the quantity actually done and at the unit price, if any, established for such work under this contract, except as provided for unit price items under Section 5 "Measurement and Payment"; otherwise, such additional work shall be paid for as provided under Extra Work. In case the Owner shall make such changes or alterations as make useless any work already done, of material already furnished or used in said work, then the Owner shall recompense the Contractor for any matc~:-ial or labor so used, and for any loss occasioned by such change, due to actual expenses incurred in preparation for the work as originally'planned. 2.13 RIGHT OF ENGINEER To MQDIFY METHODS AND EQUIPMENT: If at any time the methods or equipment used by the Contractor are for,nd to be inadequate to secure the quality of work or the rate of progress required under this contract, the Engineer may order the Contractor in writing to increase their safety or imporve their character and efficiency, and the Contractor shall comply with such order. If at any time the working force of the Contractor is inadequate for securing the progress herein specified, the Contractor shall, if so ordered'in writing, increase his force or equipment, or both, to such an extent as to five reasonable assurance of compliance with the schedule of progress. 3. GENERAL OBLIGAi'IONS AND RESPONSIBILITIES 3.01 KEEPING OF PLANS AND SPECIFICATIONS ACCESSIBLE: The Eng+neer shall furnish the Contractor with an adequate and reasonable number of copies of all plans and specifications without expense to him, and the Contractor shall keep one copy of the same constantly accessible on the work, with the latest revisions noted thereon. 3.02 OWNERSHIP OF DRAWINGSs All drawings, specifications and copies thereof furnished by the Engineer shall not be reused on other work, and, with the exception of the signed contract sets, are to be returned to him on request, at the completion of the workA Alf models are the property of the Owner. 3.03 ADEQUACY OF DESIGN: it !a understood that the owner believes he has employed competent engineers and designers. It is, there- fore, agreed that the owner shall be responsible for the adequacy of the design, sufficiency of the Contract Documents, the safety of the structure and the practicability of the operations of the 6 completed project; provided, the Contractor has complied with the requirements of the said Contract Documents, all approved modifi- cations thereof, and additions and alterations thereto approved in writing by the Owner. The burden of proof of such compliance shall be upon the Contractor to show that he has complied with the said requirements of the Contract Documents, approved modifi- cations thereof and all approved additions and alterations thereto. 3.04 RIGHT OF ENTRY: The owner reserves the right to enter the property or location on which the works herein contracted for are to be constructed or installed, by such agent or agents as he may elect, for the purpose of supervising and inspecting the work, or for the purpose of constructing or installing such collateral work as said owner may desire. 3.05 COLLATERAL CONTRACTS: The Owner agre!, to provide,by separate contract or otherwise, all labor and material essential to the completion of the work specifically excluded from this contract, in such manner as not to delay the progress on the work, or damage said Contraqtor, except where such delays are specifically sgentioned elbe,Aere in the Contract Documents. 3.06 DISCREPANCIES AND OMISSIONS: It is further agreed that it is the intent of this contract that all work must be done and all material must be furnished in accordance with the generally accepted practice, a,d in the event of any discrepalcies between the separate + contract documents, specifications,or drawings, the Engineer shall define which is intended to apply to the work. 3.07 EQUIPMENT, MATERIALS AND CONSTRUCTION PLANT: The Contractor shall provide all tools, equipment, machinery, materials, and construction plant and facilities necessary in the prosecution and completion of the contract, except as otherwise specifically set forth to be provided by the owner. The Contractor shall be respon- sibie for the care, preservation, conservation, and protection of all tools, apparatus, accessories, facilities, all means of construc- tion, and any and all parts of the work whether the Contractor has been paid, partially paid, or not paid for such work, until the entire work is completed and accepted. 3.08 DAMAGESs In the event, the Contractor is damaged in the course of the completion of the work by the act, neglect, omission, mistake, or default of the Owner, or of the Engineer, or of any' other Contractor employed by the owner upon the work, therby causing loss to the Contractor, the Owner agrees that he will reim- burse the Contractor for such loss. In the event, the Owner is damaged in the course of the work by the act, negligence , omission, mistake, or default of the Contractor, or should the Contractor unreasonably delay the progress of the work being done by others on the job so as to cause loss for which the Wner becomes liable, then the Contractor shall reimburse the owner for.such loss. 7 3.09 PROTECTION AGAINST ACCIDENT TO EMPLOYEES AND THE PUBLIC: The Contractor shall take out and procure a policy or policies of work- men's compensation insurance with an insurance t:ompany licensed to transact business in the State of Texas, which policy shall comply with the Workmen's Compensation Law of the State of Texas. The Contractor shall at all times exercise reasonable precautions for the safety of employees and others on or near the work and shall comply with all applicable provisions of Federal, State and Municipal safety laws and building and construction codes. All machinery and equipment and other physical hazards shall be guarded in accordance with the "Manual of Accident Prevention in Construction" of the Associated General Contractors of America, except where incompatible with Federal, State, or Municipal laws or regulations. The Contractor shall provide such machinery guards, safe walk-ways, ladders, bridges, gangplanks, and other safety devices as may be required by the Engineer as requisite to the prevention of accidents. The Contractor and his Sureties shall indemnify and save harmless the Owner and all his officers, agents, and employees from all suits, actions, or claims of any character, name and description brought for or on account of any injuries or damages received or sustained by any person or persons or property, on account of any negligent act or fault of Contractor, his agents or employees, in the execution of said contract; or on account of the failure of the Contractor to provide necessary barricades, warning lights or signs; and will be required to pay any judgment, with costs, which may be obtained against the Owner growing out of such injury or damage. 3.10 PERFORMANCE AND PAYMENT BONDS: Unless otherwise specified, it is further agreed by the parties to this Contract that the Contractor will execute separate performance and payment bongs, each in the sum of one hundred (100) per cent of the total con- tract price, on standard forms for this purpose, guaranteeing faithful performance of the work and the fulfillment of any guarantee+s required, and further guaranteeing payment to all persons supplying labor and materic-as or furnishing him any equip- ment in the execution of the Contract, and it is agreed that thib Contract shall not be in effect until such performance and payment bonds are furnished and approved by the Owner. Unless otherwise approved in writing bythe owner, the surety cf)mpany underwriting the bonds shall be acceptable according to the latest list of companies holding certificates of authority from the Secretary of the Treasury of the United States. i Unless otherwise specified, the cost of the premium for the performance and payment bonds shall be included in the Contractor's, proposal. 3.11 LOSSES FROM NATURAL'CAUSES: Unless o'..herwise specified, all loss or damage to the Contractor arising out of the nature of the work to be done, or from the action of the elements, or from any unforseen circumstances in the prosecution of the same, or from unusual obstructions or difficulties which may be encountered in the prosecution of the work, shall be sustained and borne by the Contractor at his own cost and expense. 3.12 PROTECTION OF ADJOINING PROPERTY: The said Contractor shall take proper means to protect the adjacent or adjoining property or properties in any way ergcountered, which might be injured or seriously affected by any process of construction to be under- taken under this agreement, from any d::,nage or injury by reason of said process of construction; ar:] he shall be litble for any and all claims for such damage on account of his failure to fully protect all adjoining property. The Contractor agrees to indemnify, save and hold harmless the owner against any claims for damages due to any injury to any adjacent or adjoining property, arising or growing out of the performance of the contract; but any such indemnity shall not a0ply to any-claim of any kind arising out of the existence or character of the work. 3.13 PROTECTION AGAINST CLAIMS OF SUB-CONTRACTORS, LABORERS MATERIALMEN AND FURNISHERS OF MACHINERY, EQUIPMENT AND SUPPLIES: The Contractor agrees that he will indemnify and save the owner harmless from all claims growing out of the lawful demands of sub-contractors, laborers, workmen, raechanics, materialmen, and furnishers of machinery and parts thereof, equipment, power tools, and all supplies, including commissary, incurred in the further- ance of the performance of this contract. When so desired by the Owner, the Contractor shall furnish satisfactory evidence that all obligations of the nature hereinabove designated have been paid, discharged or waived. If the Contractor fails so to do, then the owner may at the option of the Contractor either pay directly any unpaid bills, of which the Owner has written notice, or withhold from the Contractor's unpaid compensation a sum of money deemed reasonably sufficient to liquidate any and all such lawful claims until satisfactory evidence is furnished that all liabilities have been fully discharged; where upon payments to the Contractor shall be resumed in full, in accordance with the terms of this contract, but inno event shall the provisions of this sentence be construed to impose any obligation upon the Owner by either the Contractor or his Surety. 3.14 PROTECTION AGAINST ROYALT7ES OR PATENTED INVENTION: The Contractor shall pay all royalties and license fees, and shall provide for the use of any design, device, material or process covered by letters patent or copyright by suitable legal agree- ment with the patentee or Owner. The Contractor shall defend all suits or claims for infringement of any patent or copyright rights and shall indemnify and save the Owner harmless from any loss on account thereof, except that the owner shall defend all 9 such suits and claims and shall be responsible for all such loss when a particular design, device, material, or process, or the product of a particular manufacturer or manufacturers is specified or required by the Owner; provided, however, if choice of alternate design, device, material,.or process is allowed to the Contractor, then Contractor shall indemnify and save Owner harmless from any loss on account thereof. If the material or process specified required by the Owner is an in- fringement, the Contractor shall be responsible for such loss unless he promptly gives such information to the Owner. 3.15 LAWS AND ORDINANCES: The Contractor shall at all times observe and comply with all Federal, State and local laws, ordin- ances and regulations, which in any manner affect the Contract or the work, and shall indemnify and save harmless the owner against any claim arising from the violation of any such laws, ordinances, and regulation, whether by the Contractor or his employees, except where such violations are called for by the provisions of the Contracts Documents. If the Contractor observed that the plans and specifications are at variance there- with, he shall promptly notify the Engineer in writing, and any necessary changes shall be adjusted as provided in the contract for changes in the work. If the Contractor performs any work knowing it to be contrary to such laws, ordinances, rules and regulations, and without such notice to the Engineer, he shall bear all costs arising therefrom. In case the Owner is a body politic and corporate, the law from which it derives its powers, inoofar as the same regulates the objects for which, or the manner in which, or the conditions under which the Owner may enter into contract, shall be controlling, and shall be considered as part of this contract, to the same effect as though embodied herein. 3.16 ASSIGNMENT AND SUBLETTING: The Contractor further agrees that he will retain personal control and will give his personal attention to the fulfillment of this contract and that he will not cssign by Power of Attorney, or otherwise, or sublet said contract without the written consent of the Owner, and that no part or feature of the work will lie sublet to anyone objection- able to thF. Engineer or the Owner. The Contractor further agrees that the subletting of any portion or feature of the work, or materials required in the performance of this contract, shall not relieve the Contractor from his full obligations-to the Owner, as provided by this Agreement. 3.17 CONTRACTOR'S AND SUB-CONTRACTOR'S INSURANCE: The Contractor shall not commence work under this contract until he has obtained all the insurance required under the following sub-paragraphs and such insurance has been approved by the Owner, nor shall the Contractor allow any sub-conizactor to commence work on a sub- contract as required for the Contractor. 10 3.171 COMPENSATION INSURANCE: The Contractor shall procure and shall maintain during the life of this contract Workmen's Compen- sation Insurance for all of his mployees to be engaged in work on the project under this contract and, in case of any such work sublet, the Contractor shall require the sub-contractor similarly to provide Workmen's Compensation insurance for all of the latter's employees to be engaged in such work, unless such employees are covered by the protection afforded by the Contractor's Workmen's Compensation Insurance. In case any class of employees engaged in hazardous work on the project under this contract is not protected under the Workmen's Compensation Statue, the Contractor shall provide and shall cause each sub-contractor to provide adequate Employer's General Liability Insurance for the protection of such of his employees not otherwise protected. 3.172 CONTRACTOR'S PUBLIC LIABILITY AND PROPERTY DAMAGE INSURANCE: The Contractor shall procure and shall maintain during the life of this contract Contractor's Public Liability Insurance in an amount not less than $50,000 for injuries, including accidental death, to any one.-person, and subject to the same limit for each person, in ai`-amount not less than $100,000 on account of one accident, and Contractor's Property Damage Insurance in an amount of not less than $25,000 on account of one accident and $50,000 aggregate. 3.173 ADDITIONAL LIABILITY: The Contractor shall furnish insur- ance as separate policies or by additional endorsement to one of the above mentioned policies, and in the amount as set forth for public liability and property damage, the following insurence: a. Contingent Liability b. Blasting, prior to any blasting being done. c. Collapse of buildings or structures adjacent to excav- ation (if excavations are to be performed adjacent to same). d. Damage to underground utilities. e. Builders risk (where above-ground structures are involved). 3.174 AUTOMOBILE INSURANCE - BODILY INJURY AND PROPERTY DAMAGE.- The Contractor shall procure and maintain, during the life of this contract, Automobile Insurance in an amount not less than $25,000 for injuries, including accidental death, to any one person and subject to the same limit for each person, an amount not less than $50,000 on account of one accident, and automobile property damage insurance in an amount not less than $5,000. 3.175 SCOPE OF INSURANCE AND SPECIAL HhZARD: The Insurance required under the above paragraphs shall.provide adequate pro- tection fnr the Contractor and his sub-contractors, respectively, against damage claims which may arise from operations under this contract, whether such operations by the insured or by any one 11 directly or indirectly employed by him. Insuranco also shall be provided against special hazards, if any, as may be set forth in the Special Conditions or Special Provisions, ar elsewhere in these Contract Documents. 3.176 PROOF OF CARRIAGE OF INSURANCE: The Contractor shz:? 1 furnish the Owner with satisfactory proof of coverage by insur- ance required in these Contract Documents in amounts and by carriers satisfactory to the Owner. Proof of carriage of insur- ance by sub-contractors shall be furnishes 4. PROSECUTION AND PROGRESS 4.01 TIME AND ORDER OF COMPLETION: It is the meaning and intent of this contract, unless otherwise herein specifically provided, that the contractor shall be allowed to prosecute his work at such times and seasons, in such order of precedence, and in such manner as shall be most conductive to economy of construction; provided, however, that the order and the time of prosecution shall be such that the work shall be substantially completed as a whole and in part, in accordance with this contract, the plans and specifications, and within the time of completion designated in the Proposal; provided, also that when the Owner is having other work done, either by contract or by his own force, the Engineer may direct the time and manner of constructing the work done under this contract, so that conflict will be avoided and the construction of the various works being done for the owner shall be harmonized. The Contractor shall submit, at such times as may reasonably be requested by the Engineer, schedules which shall show the order in which the Contractor proposed to carry on the work, with dates in which the Contractor will start the several parts of the work, and estimated dates of completion of the several parts, 4.02 EXTENSION OF TIME: Should the Contractor be delayed in the completion of the work by any act or neglect of the Owne, or Engineer, or of any employees of either,or by other contractors employed by the Owner, or by changes ordered in the work, or by strikes, lockouts, fires, and unusual delays by common carriers, or unavoidable cause or causes beyond the Contractor's control, or by any cause which the Engineer shall decide justifies the delay, then an extension of time shall be allowed for completing the work, sufficient to compensate for the delay, the amount of the extension to be determined by the Engineer; provided, however, that the Contractor shall give the Engineer prompt notice in writing of the cause of such delay. 4.03 HINDRANCES AND DELAYS: No claims shall be made by the Contractor for damages resulting from hindrances or delays from any cause (except where the work is stopped by order of the owner) 12 during the 2rogress of any portion of the work embraced in this contract. In case said work shall be stopped by the act of the owner, then such expense as in the judgment of the Engineer is caused by such stoppage of said work shall be paid by the Owner to the Contractor. 4.04 LIQUIDATED DAMAGES: The Contractor agrees that time is of the essence of this contract, and that for each clay of delay beyond the number of days herein agreed upon for the completion of the work herein specified and contracted for (after due allowance for such extension of time as is provided for under Extension of Time hereinabove), the Owner may withhold permanently from the Contractor's total compensation, the sum set forth in the Special Conditions or Special Provisions (or as elsewhere set forth in these Contract. Documents), as stipulated liquidated damages for such delay. 5. MEASUREMENT AND PAYMENT 5.01 QUANTITIES AND MEASUREMENTS: No extra or customary measure- ments of any kind will be allowed, but the actual measured and/or computed length, area, solid contents, number, and weight only shall be considered, unless otherwise specifically provided. 5.02 ESTIMATED QUANTITIES: This Agreement, including the specifications, plans and estimate, is intended to show clearly all work to be done and material to be furnished hereunder. Where the estimated quantities are shown for the various classes of work to be done and material to be furnis:ed under this Contract, they are approximate and are to be used only as a basis for estimating the probable cost of the work and,for comparing the proposals offered for the work. Itis understood and agreed that the actual amount of work to be done and material to be furnished under this contract may differ somewhat from these estimates, and that where the basis for payment under this contract is the unit price method, payment shall be for the actual amount of such work done and the material furnished. Where payment is based on the unit price method, the Contractor agrees that he will make no claim for damages, anticipated profits or otherwise on account of any differences which may be found between the quantities of work actually done, the material actually furnished under this contract and the estimated quantities contem- plated and contained in the propor.A; provided, however, that in case the actual quantity of any item should become as much as i5% more than, or 25% less than the estimated cr contemplated quantity for sucli items, then either party to this Agreement, upon demand, shall be entitled to a revised consideration upon the portion of the work above or below 25% of the estimated quantity. 13 Any revised consideration in to be determined by agreement between the parties, otherwise by the terms if this Agreement, as provided under "Extra Work". 5.Q3 PRICE OF WORK: In consideration of the furnishing of all the necessary labor, equipment and material, and the completion of all work by the Contractor, and on the completion of all work and of the delivery of a'..1 material embraced in this contract in full conformity with the specifications and stipulations herein con- tained, the owner agrees to pay the Contractor the prices set forth in the Proposal hereto attached, which has been made a part of this contract. The Contractor hereby agrees to receive such prices in full for furnishing all material and all labor required for the aforesaid work, also for all expense incurred by him, and for well and truly performing the same and the whole thereof in the manner artd according to this Agreement, the attached specifi- cations and requirements of the Engineer, 5.04 PARTIAL PAYMENTS: On or before the 10th day of each month the Engineer shall prepare a statement showing as completely as practicable the total value of the work done by the Contractor up to and including the last day of the preceding month; said state- ment shall also include the value of all sound materials delivered on the site of the work that are to be fabricated into the work. The Owner shall then pay the Contractor on or before the 15th day of the current month the total amount of the Engineer's statement, less 10 per cent of the amount thereof, which 10 per cent shall be retained until final payment, and further less all previous payments and all further sums ig understood, however, that in case the whole work be near to completion and some unexpect- ed and unusual delay occurs due to no fault or neglect on the part of the Contractor, the Owner may upon written recommendation of the Engineer ;gay a reasonable and equitable portion of the retained percentage to the Contractor; or the Contractor, at the Owneu's option, may be relieved of the obligation to fully complete the-work and, thereupon, the Contractor shall receive payment of the balance due him under the contract subject only to the condi- tions stated under "Final Payment". 5.05 USE OF COMPLETED PORTIONS: The Owner shall have the night to take possession of and use any completed or partially completed portions of the work, notwithstanding the time for completing the entire work or such portions may not have expired, but such taking possession and use shall not be deemed an acceptance of any work not completed in accordance with the Contract Documents. If such prior use increases the cost of or delays the work, the Contractor shall be entitled to such extra compensation, or extension of timb, or both, as the Engineer may determine. I 14 I 5.06 FINAL COMPLETION AND ACCEPTANCE: Within ten (10) days after the Contractor has given the Engineer written notice that the work has been completed, or substantially completed, the Engineer and the Owner shall inspect the work and within said time, if the • work be found to be completed or substantially completed in accord- ance with the Contract Documents, the Engineer shall issue to the Owner and the Contractor his Certificate of Completion, and there- upon it shall be the duty of the Owner withinlthe (10) days to issue a certificate of Acceptance of the work to the Contractor. 5.07 FINAL PAYMENT: Upon the issuance of the Certificate of Completion, the Engineer shall proceed to make final measure- ments and prepare final statement of the value of 311 work per- formed and materials furnished under the terms of the Agreement and shall certify same to the Owner, who shall pay to the Contractor on or after the 30th day, and before the 35th dap, after the date of the Certificate of Completion, the balance due the Contractor under the terms of this Agreement, provided he has fully performed his contractual obligations under the terms of this contract; and said payment shall become due in any event upon ebid performance by the Contractor. Neither the Certificate of Acceptance nor the final payment, norany provision in the Contract Documents, shall relieve the Contractor of the obligation for fulfillment of any warranty which may be required in the Special Conditions of the Specifications. 5.08 PAYMENTS WITHHELD: The Owner may, on account of subse- quently discovered evidence, %Athho'ld or nullify the whole or part of any certificate to such extent as may be necessary to protect himself from loss on account of: a. Defective work not remedied. b. Claims filed or reasonable evidence indicating probable filing or claims. C. Failure of the Contractor to make payments properly to sub-contr9ctors or for material or labor. d. Damage to another contractor. When the above grounds are removed, or the Contractor provided a Surety Bond satisfactory to the Owner, which will protect the Owner in the amount withheld, payment shall be made for amounts withheld because of them. 5.09 DELAYED PAYMENTS: Should the Owner fail to make rayment to the Contractor of the sum named in any partial or final statement, when payment is due, or should the Engineer fail to issue any statement on or*before the date above provided, then the owner shall pay to the Contractor, in addition to the eum shown as due by such statement, interest thereon at the rate of six (6) per cent per annum, unless otherwise specified, from date due as 15 provided under "Partial Payments" and Final Payments", until fully paid, which shall fully liquidate any injury to the Con- tractor growing out of such delay in payment, but the ri-'At is expressly reserved to the Contractor in the event payments be not promptly made, as provided tinder "Partial Payments", at any time thereafter to treat the contract as aLandoned by the owner and recover compensation, as provided under "Abandonment of Contract". unless such payments are withheld in accordance with the provisions of "Payments Withheld'. 6. EXTRA WORK AND CLAIMS 6.01 EXTRA WORK: It is agreed that the Contractor shall perform all Extra Work under the direction of the Engineer when presented with a Written Work Order signed by the Engineer, subject however, to the right of the Contractor to require a written confirmation of ssch Extra Work Order by the Owner. It is also agreed that the compensation to be paid the Contractor for performing said ` Extra Work shall be determined by one or more of the following methods: Method A - By agreed unit prices; or Method B - By agreed lump sum; or Method C - If neither Method A nor Method B be agreed upon before the Fxtra Work is commenced, then the Contractor shall be paid the "actual field cost" of the work, plus fifteen (15) per cent. In the event,said Extra Work be performed and paid for under Method C, then the provisions of this paragraph shall apply and the "actual field cost" is hereby defined to include the cost of all workmen, such as foremen, timekeepers, mechanics and laborers, and materials, supplies, teams, trucks, and rentals on machinery and equipment, for the time actually employed or used on such Extra Work, plus actual transportation charges necessarily incurred tdgether with all power, fuel, lubricants, water, and 0-filar operating expenses, also all necess2ry incidental expenses incurred directly on account of such Extra Work, including Social Security', Old Age Benefits and other payroll taxes, and a rateable proportion of premiums on Performance and Payment Bonds, and Maintenance Bonds, and on Public Liability and Property Damage, and workmen's Compen- sation, and all other insurance as may be required by any law or ordinance, or directed by the Engineer or owner, or by them agreed to. The Engineer may direct the form in which accounts of the "actual field cost" shall be kept and the records of these accounts shall be made available to the Engineer. The Engineer may also specify in writing, before the work commences, the method of doing the work and the type and kind of machinery and equipment to be used; otherwise these matters shall be determined by the Contractor. Unless otherwise agreed upon, the prices for the use of machinery lb i and equipment shall be determined by using 100 por cent, unless otherwise specified, of the latest schedule of Equipment Owner- ship Expense adopted by the Associated General Contractors of America. Where practicable the terms and prices for the use of • machenery and equipment shall be incorporated in the Written Extra Work Order. The fifteen (15%) per cent of the "actual field cost" to be paid the Contractor shall cover and compensate him for his profit, overhead, general superintendence and field office expense, and all other elements of cost and expense not embraced within the "actual field cost" as hereindefined, save that where the Contractor's Camp or Field Office must he main- tained primarily on account of such Extra Work; then the cost to maintain and operate the same shall be included in the "actual field cost". No claim for Extra Work of any kind will be allowed unless ordered in writing by the Engineer. In case any order: or instructions, either oral or written, appear to the Contractot in involve Extra Work for which he should receive compensation or an adjustment in the construction-time, he shall make written request to the Engineer for written order authorizing such Extra Work. Should a difference of opinion arias as to what does or does not constitute Extra Work, or as to the payment therefor, and the Engineer insists upon its performance, the Contractor shall proceed with the work after making written request for written order and shall keep an accurate account of the "actual field cost" thereof, as provided under Method C. The Contractor will thereby perserve the right to sub- mit the matter of payment to arbitration, as hereinbelow provided. ',►.02 TIME OF FILING CLAIMS: It is further agreed by both parties hereto that all questionscf dispute or adjustment presented by the Contractor shall be in writfng and filed with the Engineer within thirty (30) days after the Engineer has given any directions, order or instruction to which the Contractor desires to take excep- tion. The Engineer shall, within a reasonable time, reply to such written exceptions by the Contractor and render his final decision in writing. In case the Contractor should appeal from the Engineer's decision, and demand for arbitration shall be filed with the Engineer and the Owner in writing within ten (10) days after the date of delivery to Contractor of the Engineer's final decision. It is further agreed that final acceptance of the work by the Owner and the acceptance by the Contractor of the final payment shall be a bar to any claims by either party, except where noted otherwise in the Contract documents. 6.03 ARBITRATION: All questions of dispute under this Agreement shall be submitted to arbitration at the request of either party to the dispute. The parties may agree upon one arbiter; otherwise, there shall be three, one named in writing by each party, and the third chosen by the two arbiters so selected; or if the arbiters fail to select a thiA within ten (10) days, he shall be chosen 17 i by a District Judge serving the County in which the majorportion of the project is locdted, unless otherwise specified. Should the party demanding arbitration fail to name an arbiter within ten (10) days, the Engineer shall appoint such arbiter. Should either party Tefuse or neglect to supply the arbiters with any papers or iniormation demanded in writing, the arbiters are empowered by both parties to take ex parts proceedings. The arbiters shall act with promptness. The decision of any two shall be binding on both parties to the contract. The decision of the arbiters upon any question submitted to arbitration under this contract shall be a condition precedent to any right of legal action. The decision of the arbiter or arbiters may be filed in count to carry it into effect. The arbiters, if they deem the case demands it, are authorized to award the party whose contention is sustained, such sums as they deem proper for the time, expense and trouble incident to the appeal, and if the appeal was taken without reasonable cause, they may award damages for any delay occasioned thereby. The arbiters shall fix their own compensation, unless otherwise provided by agreement, and shall assess the cost and charges of the arbitration upon either or both parties. The award of the arbiters must be made in writing. 7. ABANDONMENT OF CONTRACT 7.01 ABANDONMENT BY CONTRACTOR: In Case the Contractor should abandon and fail or reftse to resume work within ten (10) days after written notifica;:ion from the Owner, or the Engineer, or if the Contractor fails to comply with the orders of the Engineer, when such orders are consistent with the Contract Documents, then, and in that case, where performance and payment bonds exist, the Surety on the bonds shall be notified in writing and directed to complete the work, and a copy of said notice shall be delivered to the Contractor, After receiving said notice of .abandonment, the Contractor shall not remove from the work any machinery, equipment, tools, materials, or supplies then on the job, but the same, together with any materials, and equipment under contract for the work, may be held for use on the work by the owner or the surety on the performance and payment bonds, or another contractor in completion of the work; and the Contractor shall not receive any rental or credit therefor (except when used in connection with Extra Work, where credit shall be allowed as provided for under Section 6, Extra Work and Claims), it being understood that the use of such equip- ment and materials will ultimately reduce the cost to complete the work and be reflected ih the final settlement. 18 s. Where there is no performance bond provided or in case the Surety should fail to commence compliance with the notice for completion hereinbefore provided for, within ten (10) days after service of such notice, then the owner may provide for completion of the work in either of the following elective manners: 7.011 The Owner may thereupon employ such force of men and use such machineery, equipment, tools, materials, and supplies as said owner may deem necessary to complete the work and charge the oxpense of such labor, machinery, equipment, tools, materials, and supplies to said Contractor, and expense so charged shall be de- ducted and paid by the owner out of such moneys as may be due, or that may thereafter at any time become due to the Contractor under and by virtue of this Agreement. In case such expense is less than the sum which would have been payable under this contract if the same had been completed by the Contractor, then said Con- tractor shall receive the difference. In case such expense is greater than the sum which would have been payable under this Contract if the same had been completed by said Contractor, then the contractor and/or his Surety shall pay the amount of such excess to the Owner; or 7.012 The Owner, under sealed bids, after five (5) days notice published one or more times in a newspaper having yeneral circulation in the county of the location of the work, may let the contract for the completion of the work under substantially the same terms ank' conditions which are provided in this contract. In case of any increase in cost to the Owner under the new contract as compared to what would have been the cost under this contract, such increase shall be charged to the Contractor and the Surety shall be and remain bound therefor. However, should the cost to complete any such.new contract prove to be less than what would have been the cost to complete under this contract, the Contractor and/or his Surety shall be credited with the difference. When the work shall have been substantially completed the Con- tractor his Surety shall be so notified and Certificates of Completion and Acceptance, as provided in Paragraph 5.06 herein- above, shall be issued. A complete itemized statement of the contract amounts, c,rtified to by the Engineer as being correct, shall then be prerared and delivered to the Contractor and his Surety, whereupon the Contractor and/or his Surety, by said statement, within fifteen (15) days after the date of such Certificate of Completion. In the event, the statement of accounts shows that the cost to complete the work is less than that which would have been the cost to the owner had the work been completed by the Contractor under the terms of this Contracts or when the Contractor and/or his Surety shall pay the balance shown to be due by thehk to the Owner, then all machinery, equipment, tools, materials, o- supplies left 19 on the site of work shall be turned over to the Contractor and/or his Surety. Should the, coat to complete the work exceed the contract pr;,-e, and the Contractor and/or his Surety fail to pay the amount . i the Owner within the time designated hereinabove, and there remains any machinery, equipment, tools, materials, or supplies on the site of work, notice thereof, together with an itemized list of such equipmentand maietials,,'shall be mailed to the Contractor and his Surety at the respective addresses designated in this contract; provided, however, that actual written notice given in any manner will satisfy this condition. After mail- ing, or other giving of such notice, such property shall be held at the risk of the Contractor and his Surety subject only to the duty of the Owner to exercise ordinary care to protect such pro- perty. After fifteen (15) days from the date of said notice the owner may sell such machinery, equipment, tools, materials or supplies and apply the net sum derived from such sale to the credit of the Contractor and his Surety. Such sale may be made at either public or private sales, with or without notice, as the Owner may elect. The owner shall release any machinery, equipment, tools, materials, or supplies, which remain on the work and belong to persons other than the Contractor or his Surety, to their proper owners. The books on all operations provided herein shall be open to the Contractor and his Surety. 7.02 ABANDONMENT BY OWNER: In case the Owner shall fail to comply with the terms of this Contract, and should fail or refuse to comply with said terms within ten (10) days after written notification by the Contractor, then the Contractor may suspend or wholly abandon the work, and may remove therefrom all machinery, tools and equipment, and all materials on the site of work that have not been included in payments to the Contractor and have not been wrought into the work. And thereupon, the Engineer shall make an estimate of the total amount earned by the Contractor, which estimate shall include the value of all work actually com- pleted by said Contractor (at the prices stated in th;; attached proposal where unit prices are used), the value of all partially completed work at a fair and equitable priog% and the amount of all Extra Work performed at the prices aviceed?-upon, or provided for by the terms of this contract, and reasonable sum to cover the cost of any provisions made by the Contractor to carry the whole work to completion and which cannot be utilized. The Engineer shall then make a final statement of the balance due the Contractor by deducting from the above estimate all previous payments by the Owner, and all other sums that may be retained by the Owner under the terms of this Agreement, and shall certify sar- to the Owner, who shall pay to the Contractor, on or before th (30) days after the date of the notification by the Contrac- to) the balance shown by said final statement as due the Contractor under the terms of this Agreement. 20 DETAIL SPECIFICATIONS PROPOSED OFFICE AND BANGER BUILDING FOR AEROSMITH DENTON CORPORATION CITY OF DENTON, TEXAS w OWNER SECTION - 100 GENERAL 100.1 MATERIALS: These specifications are intended to be so written that only materials of the beat quality and grade will be furnished. The fact that the specifications may fail to be sufficiently complete in some detail will not relieve the Contractor of full responsibility for providing materials of high quality and protecting them adequately until incorporation in the project. The specifications for materials set out the minimum standard of quality which the Owner believes necessary to procure a satisfactory project. No substitutions will be permitted until the Contractor has received written permission of the Engineer to maka a substitution for the materials which has been specified. 100.2 WORKMANSHIP: These specifications contain detail instructions and descriptions covering the major items of construction and workman- ship necessary for building and completing the various units or elements of the project. The specifications are intended to be ®o written. that only first class workmanship and finish of the best grade and quality will result. The fact that these specifications may fail to be so complete as to cover all details will not relieve the Contractor of full responsibility for providing a completed project of high quality, first claw finish and appearance and satisfactory for opera- tion, all within tht apparent intent of the plans and specifications. 100.3 HANDLING MATERIALS NOT APPROVED: The Contractor shall remove from the site any materials found to be damaged and any materials not meeting the specifications shall be taken off the site. These materials shall be removed promptly, unless the Engineer will accept the materials after repairing. Materials which are installed and found damaged or not acceptable, shall be removed and replaced. Inspection before inst6lla- tion shall not relieve the Contractor from responsibility to furnish good quality materials. 100-1 r s 100.4 STANDARD SPECIFICATIONS: All construction shall conform to the applicable standard specifications of the City of Denton, Texas. Bidders shall inspect the site of the proposed building and familiarize themselves with all building and other codes and regulations which will be imposed by the City of Denton for such projects. 100.5 PAYMENT: Payment shall be based on a lump sum bid and shall be payable to the contraction upon the completion of the project acceptance by the city. Payment shall be made by the issuance of time warrants as stated in the notice to Bidders of these specifications. 100.6 LOCATION: The building will be erectea on the airport property as shown on sheet #E3 of the attached plans s;hich are made a part of these specifications. 100.1 The hangar building as described in these specifications and drawings shall be erected to include the accessories as shown, including skylight panels, hangar doors, door tracks, roof extension over the hangar doors and sheeted door shrouds. Roof and wall sheeting as well as sheeting of shrouds and guttering and downspouts and other trim shall have a vinyl color coating as specified by the City of Denton. Hangar doors shall operate on tracks set in concrete base. 100.2 SECTION 101 - EXCAVATION 101.1 Building site The contractur shall fine grade the area to be covered by the building and level same ready to receive the three- inch thick layer of cushion sand. Sand fill shall be spread so top will be five inches below the level of the finished floor slay. 101.2 Foundations Piers shall be drilled of the size shown on the plans and located at the column centers. Excavate for the spread footings under the haydite block wall which separates the hangar from the lean-to. Excavate for the concrete grade beams along the exterior wall and under the haydite block wall, and for all tie beams. 101.3 Back Fill After concrete grade beams and tie beams have set and forms have been removed, back-fill all trenches, using the excavated material. Back-fill shall be well puddled and rammed in place. 1Pi-l SECTION 102 - CONCRETE WORK 102.1 All concrete shall be 3,000 pound, five sack, transit mix, and shall be well puddled in piers, beams and footings. in placing concrete in forms and over sand cushion, care shallbs exercised so that reinforcing steel will not be disturbed. 102.2 Concrete floor slabs shall have a steel-trowelled finish and slab in hangars shall have treatment of hardener and shall have a slight pitch toward the floor drains. Hangar slab shall be saw-cut into rec- tangles approximately forty by thirty feet in size. 102.3 Reinforcing steel in piers, beams and slabs shall be of the sizes and spacing shown on the plans and in no case shall there be leas than one and one-half inches coverage of concrete over any reinforcing steel. 102.4 Forms for foundation beams shall be constructed of good lumber without cracks or knot-holes and shall be the size shown on the plans. They shall be well braced, straight and true and the tops of the beans shall be level. a 102-1 SECTION 103 - MASONRY 103.1 Partitions separating the hangar and lean-to and those enclosing the offices, toilet rooms,, radio room and shop shall be constructed of haydite blocks having the thickness shown on the plans. 103.2 Ladder type reinforcing shall be provided at every second course, and the courses shall be laid up with cement mortar. 103.3 The top course of the 8-inch wall will consist of lintel blocks filled with concrete and reinforced as shown on the plans. 103+1 SECTION 104 - STEEL BUILDING 104.1 Design: Structural steel sections and welded plate members shall be designed in accordance with the RISC "Specifications for the Design, Fabrication and Erection of Steel Buildings". All light gage cold formed structural members shall be designed in accordance with AISI "Specifica- tions for Design of light gage cold formed as-eel structural members". 104.2 Primary Structural Framing: 1. Steel used in fabrication of rigid frames, columns and tapered beams shall have a minimum yield of 42,000 psi and shall conform to minimum requirements of A 42, at manufacturers options. 2. All structural steel members shall be built-up welded shaped or hot rolled sections. 3. Flanges and webs of built-up welded members shall be joined by a continuous automatic submerged arc welding process. All shop welding shall be by operators qualified as prescribed in the "Standard Qualification Procedure of the American welding Society". 104.3 Secondary Structural Members: 1. Steel used in fabrication of light gage cold formed structural steel members shall have minimum yield of 50,000 psi. Purlins and girts shall be precision formed "Z" sections frcm high strength steel. 2. Lateral bracing to provide longitudinal rigidity against wind forces shall be furnished with adjusting nuts on each end. 104.4 Painting of Structural Members All members and parts shall be thoroughly cleaned to remove all diri, grease, oil and loose mill scale and shall be given one full shop coat of special high quality rust inhibiting zinc chromate primer. 104.5 Field connections: 1. All building parts shall be shop punched for bolted field assembly. 2. Rigid frame connection bolts shall be of high tensile steel conforming to ASTH A-325 requirements. 3. Bolts for connection of secondary members shall be minimum of ~ " Cadmium plated machine bolts. 104.6 Roof and Wall Covering: 1. Roof and wall panels shall be minimum 26 gauge galvanized deep rib sheets. Galvanized steel covering shall have minimum zinc coating of 1.25 oz. per square foot - in accordance with A.S.T.M. A-446 or A-932. Colored paneling shall consist of high tensile special alloy galvanized steel sheets, properly chemically cleaned and de-greased before application of baked on enamel painting to both sides of sheet. 104-1 104.7 General: 1. All materials furnished shall be within the standard industry tolerances for that material as specified for the building and the stated design conditions. 2. Foundation design shall be the responsibility of the buyer and all materials and labor required for the foundation design will be furnished by the buyer, unless otherwise specified. Anchor bolts shall be set in strict accordance with manufacturers anchor bolt setting plan. 3. Building manufacturer shall provide anchor bolt setting plans and errection drawings as required to complete the building. 104.8 The interior walls of the lobby and offices shall be covered with one-quarter inch thick pre-finished plywood, type as selected. The plywood shall be attached to the walls by i" x 2" continuous nailing strips attached to the girts and spaced not more than twenty-four inches on centers. 104•Z SECTION 105 - MISCELLANEOUS METAL 105.1 Furnish and install steel bar joists aver the area to be used for offices, radio room and shop. Size, apszing shall be as shown on the plans. After the insulation is place6 over the joists, install a metal deck, 24-gauge in thickness. 105.2 Furnish and install steel door frames where shown on the plans, same to be securely anchored to the haydite the walls and filled with the necessary reinforcing for hinges and locks. 105.3 All windows shown on the pales shall be 3-feet by 4-feet in size, double hung, aluminum, and shall be securely anchored to the walls with the heads set at the same height as that of the doors. 105.4 The front entrance door shall be 3-feet by seven-feet in size and shall have a borrowed light on each side 18 inches vide. Door and side-lights shall be glazed with crystal plate glass. (Pittsburg Graylite #51). Door, sidelights and frame shall be constructed of tubular aluminum. 105.5 Provide door closer and push bar for exterior door only. 105-1 SECTION 106 - INSULATION 106.1 Roof insulation shall be furnished and installed under the entire roof area with the exception of the canopies over the hangar doors. 106.2 Insulation shall be approved fiber glass, blanket-type, one and one-half inches thick and backed with white vinyl, 106.3 The insulation shall be supported above two-inch mesh. 20 Gauge galvanized wire netting. 106.4 Insulation over the steel joists in the lean-to and in the exterior wall of the offices, radio room and shop shall be approved fiber glass, blanket-type, one and one-half inches thick and backed with white vinyl. I 106-1 / SECTION 107 - PAINTING 107,1 Wooden doors shall receive a shop coat .,f spar varnish on the top and bottom edges, and one coat of primer paint before finish painting, 107.2 The hollow-core wood doors and metal frames in the haydite block partitions shall be given two coats of enameled paint in color selected. 107.3 The interior surface of the haydite block walls in the office, lobby and toilet areas shall be given two coats of water base paint. 107-11 SBCTION 108 - PLu RING 108.1 Plumbing work shall include furnishing and installing the plumbing fixture shown in the two toilet rooms; the flour drains and sand and grease trap in the hangar; and the septic tank and laterals to be located adjacent to the hangar building in compliance with Denton City Code. 108.2 The plumbing contractor shall dig the trenches necessary for the laying of underground piping and after inspection and approval of his work he shall back-fill the trenches, being careful to wet and tap all fill in place. 108.3 Basis for bid on septic tank Ahall assume location within 24 feet of nearest outside wall of rest room location. 108.4 Water lines shall be extended to all points required from an existing 1" water service pipe approximately 5 feet from the Building. 108-1 SECTION 109 - ELECTRICAL 109.1 This contract includes furnishing all labor and material required to install the electric system indicated on the plans. 109.2 All work shall be done in conformance with the City of Denton's specifications and with the provisions of the National Electrical Code, and none of the work shall be covered until it has been inspected and approved. 109.3 The contractor shall arrange with the public Service Company to bring service to the building and for setting the meter, cutout, etc. 109.4 All wiring shall be run in rigid conduit from the service panel , to the various outlets throughout the building. 109.5 Base and wall outlets shall be duplex. 109.6 Light fixtures in the lean-to area shall be 4-foot two tube flourescent. (Note that the shop area will not have ceiling fixtures.) 109.7 Light fixtures in the hangar shall be placed directly on the bottom of the steel trusses and shall be 18" diameter Benjamin-type. i • i 109-1' Y.e'?• ff SECTION 110 - ASPHALTIC PAVEMENT 110.1 The bid will include the installation of prime cost and 2 inches of Hot Mix Asphaltic Concrete on a base graded and laid by the Denton Public Works Department, who will thus establish drainage pattern for the master area. 110.2 Installation of prime coat and and asphalt surface course shall be in accordance with the City of Denton standard specifications. r, A R t 110-1 3 The above plans, specifications, bid, bid proposal, and/or drawings are hereby approved by the contracting parties, and are incorporated into and made a part of the general contract agreement by and between Contractor and the City of Denton, called owner. Dated and a orsed this I c r day of *-)(J y C H I!NE A.D., 19 A A S Steel Buildings. Inc. Contractor By.; f _ CITY OF DENTON, TEXAS, OWNER r, 10 ti • By: Robert L. Pearce Director of Community Development it FNOO VfIOA GV39 38Y37d x I z ea I 1 . LIMOS SDKV iHOAH3d ANOMPAtvr ONV-IAYVM1 AO 2o.4Ao ■wo.. . 9MO;) jjsodaa P"°44aPkJ Oe11 O1'fi~~~1A0■ - A4 Y~..O~ YDO,s Y f i ~z i i g1.'3 yro Ell ~u 6 i A "At Zr 1 Z RIO " y OD iY Q O.O u Q N Ci) 143 ® v < i U 1 W= '9 f u tA . g~ ~Ln a ;Q' i i O 4 C , i 'd i t b Q O 'i I w a F ~ 1 o O now "Ju Z 75 Z ~ ~ O ~ ~ ~'A ~1y ~ ~j i ~ 8 ~ M ~ V~W M~~ i i i i ~1 Iti ffY.. 7777 QQQ ~ O i x'17 ~ ~ ~'O O t N° ~ r pd < J 9 g a~ j t I CA IC I ~ d' z u ~t sy r:: o ~ j a . ~ ~ O ~ w i9 .9 ~ v ~ •v 'a 1 0 p two ~ I ~ ~ rl xC~ go ~ j z ' r. • W , o OG p w ~ j ~ i .ap I 9 a ~ ~ ~•a ' o 'E ~ ~ ` a ~ ~ ~ v S 44 o H w t'E c i A~ , ~4 U Uli.~ i~ 3 2@ t G i~ Q~ i 3 Q \ i ti aNOg maox av3H 38v37d x °z a~ WS1011 JMI%UVd r ■rOW.IAIWO GNVIA&dWW AO some ■wO« AguIoa Ilsoba PWAbIDP cool came"dwA{i-ANI.Ow00 v"At f~~ "1 TAM 00 06. H°a i.~ O f ..9r~ $ i vi t E €8'o ayE co f 'a'te i 49 o i '4 o all Q,";g o z L o d ~ 8~ r 08 41 po 4• O O Y i ark ~'ti ~ ~ WA Y • ~ ~j ~ ~ ~ V ~ '~'a a ~ ,a z ~ tko u lL h O a i;~ J r g~ u $ o „ iC3•C c < C ~ p'y ~ ref ~ ~ 'G ~ ' ~ ~ W ~ ~ e~a p~ >4 rd S i d a w o 4= 5 ~ 777YYYJJJ~~~ ~Si \ W• O~ M aB 3 4 € ~u t m:s E a8 NO QM=&j Ogre pit Rmwo;=iff~ n Z • ¢ ~ ~ $ $ ~ H ~ aW' C9 •.Qe ~ ~ 6 ~ ~ r7 ~L ~ ~ , ~ ~ iii ~ ~ .9 ,e v 4) w 1 , ''W' O,S` •4 p. a .S w' z, ~O 'fl $ ►Yi j.e 4 Cl O ~ 11 . % V a -O V " > , a. ° Q ~ +'$1 qJ ~ .a .Y y o C in 44 0 Il o j:.'j O e o o ro b G a E ui! ~ °se ati o.d H i A.1 E75 ~a U0 o a «b Y w v V l Y , S•I .s •I` 40 0 F7 b • • b U .E.0 40 Z 13•5 oca' 10 ab H ' ~ 'g I = ~ 'e9V p~ o , ! ~ $ vi a t 8 a e 4 i 9 0. My b p-• CL "ZO b, 4j n cwr -B r4 w ON ;a D $ 4; u 4j v'~1 E y t ci~ p~ 3w9~c~ OP4 .0 p'~~m ~ w~ S o a} CS u I, Y$ Y IQ CO m Y lux r O a to w `:.-1 V Oq to a V Cb: .5p A fs. g o s Y 1a+ r' 0 166 a. . O 1. 3`a.a H a fi '9 ~ uj .0 lag .1- ~ ~ ~ O ~ ~ ~ to ~ {O ~ Y (0~Qm W o ~ 't G ~ Yw ~+'C m ~ ~b~~6 syg ,~Y G~j`~Y ~ ~ ir'S8~`y~~~ YQ Z too o aZ tpl •r. M wi .^1 17 •0 yt •D ! '~i t/~. J36 .7 y ~S F4 A A ~ Si.9k~ Q ,~O ¢ C7 O a O 4S ~ ~ ~ O I ~ ~ w Q b 1. ~ ~ Y g .s Y Y g~ 0 44 Q m g a Y~~~ Sy ° o p 7w°, cn ~r o $ a'•r~ . .29 ' CpI uC ~~H 1.4 a r p ! Q o MQ 9 ~0$ ~Q{+ I ! • ,b Q b•~ C > Cl ° H OL• v . °n. a a T.~ Y$, F_~ ° e0 Y i y Y $ H W •u O tD ! t .2 c°OaNio61p o>;*+d~ ioGo~wI ~ a.~eE G 8 m 44 4 oG O v u Lp .0 N Y .5 O ~ G w a z cis ! yhj Z ! ~ t~j, F 9 ~ i~ t zi eqr t+ SY7 IA -V .o gg 8y~ ~ u b ~ ~ p c°Eon ~ `",u ( ~ tl ~G VS ~ ~ z ~•a~i'~.• ~ .owr!°i .ono ¢~E~.o I ~ f~~~ ~.9~30 'v~tnM .9r•~ ~~s•~~ [OYDLt 501+''ii~t'-[OIIO ZOOLZ SY\31, -NOLsl',IH SulplcnH JUVH leu4 11RK tit, j+tn,4 I001 tv~tcautd-~~ ~ :~~:ud •g z H~11i'f'',dS NO.I,Sf I~./H 9"931 .suj puv Hull".-.;g a6r, r►.inrts aNVIAHVW 30 A?iVdXOrl jpoda," puv Strrap Td L Table of Contents Sample Contract agreement Notice to Bidders a-d Information 6 Instruction to Bidders a-f i Proposal, g-h General Conditions of Agreement 1-20 Detail Specifications: O:neral 100 &xcavation 101 Concrete Work 102 Masonry 103 Steel Building 104 Miscellaneous Metal 105 Insulation 106 ' Painting 107 ' Plumhing i08 Electrical 109 A:;haltic Pavement 110 o;,,, TEXAS COUNTY OF DENTON X THIS AGREEMENT, made and onto -ed into this I_ day of N6ver►ber , A.D. 1966 , by a id betw?en n A S steel 8u1ldinas. Ihc. of the County of - arms Sta :c of Texas, Party of the First Part, hereinafter called CONTRACT-0i, and the City of Denton, Texas, a municipal corporation, of the County of Denton, State of Texas, Party of the Second Part, hereinafter called OWNER, WITNESSETHr i . That for and in consideration of the payments and agreements hereinafter mentioned to be made and performed by owner, and under the conditions expressed in the bond bearing even date herewith, the Contractor hereby agrees with owner to commence and complete the construction of certain improvements described as follows: One hangar andooffice building, including 15,000 square yards of asphalt paving, and all extra work in connection therewith, under the terms as stated in the Invitation for Bids, Pro.)osal, and Information and Special Instructions to Bidders, and General Conditions of Agree- -gent attached hereto and hereh--~ r a part of this contract by reference the same as if set forth at length hereinr and at Con- tractor's own proper cost and expense to furnish all materials, :supplies, machinery, equipment, tools, supervision, labor, insur- .rice :'ad other accessories and services necessary to complete the ;aid construction in accordance with the conditions and prices stated in the proposal atta(7h_-1 hereto, and in accordance with the conditions and prices staLc,i i, the proposal, and in accordance with all the General Condition:: o!: ",greement, and in accordance wit'Ai the plans, which include 1,11 -.ps, plats, blueprints and other drawings and printed or written ex.)lanatory matter thereof, and specifications therefor, as prepar,id by the City Engineer of the 4 City of Denton, Texas, each of which has been identified by the endorsement of the Contractor and -;he said City Engineer therein. ' Contractor hereby agrees to commence work within ten (10) days after the date written notice shall have been given to com- :fence, and to substantially complete said work within 80 working days after the date established in the written notice to cornence work. Owner agrees to pay the Contractor in current funds for the performance of the construction of the work in accordance with the proposal submitted therefor, subject to additions and deductions, as provided in the General Conditions of Agreement, and to make payments on account thereof as provided therein. IN WI.NESS WHEREOF, chc ~-'krti.es have executed this Agreement . in duplicate in the year and o:+ the date first above written. A & S Steel Buildings. inc. Contractor TEST: C- .y OF DENTON, TE3WS, Owner Warren Whitson, Jr., Mayor City of Denton, Texas ATT ~ 111t4 0o Bolt, City Se retary City of Denton, Texas APPROVED AS TO LEGAL FORM,: 11, xv J 0. Barton, City Attorney .-j z y of Denton, Texas Addendum #1: This addendum shall be attached to and become a part of the Specifications and Contract Documents for the construction of Hangar and Office Buildings at Denton Municipal Airport, City of :Denton, Texas. 1, The first paragraph of sheet a, Notice to Bidders, is ammended to read as follows: Sealed proposals addressed to the City of Denton, Denton County, Texas, will be received at the office of the City Secretary, City Hall, ' Denton, Texas, until 10:00 A.M., C.S.T., October 13, 1966, for constructing improvements 2. The second paragraph of sheet d, Notice to Bidders is ammended to read as i follows : + Instructions to Bildars, Proposal Forms, Specifications, Plans and Contract Documents may be examined at the office of the City Secretary, City Hall, Denton, Texas, and copies of said instruments may be obtained from said City Secretary, upon deposit of $5.00 as a guarantee of the safe retwrn of the plans and specifications, Said deposit will be returned provided: (1) The Bidder returns the plans and specifications within 72 hours after the bid date; OR (2) The Non-Bidder returns the plans and specifications in good condition,72 hours prior to bid :ate; Otherwise the entire $5.00 deposit will be forfeited and no refund made. Suppliers may obtain Specifications and Plans at the address stated above upon deposit of Five ($5,00) Dollars, which sum is non-refundable. . I Addendum #2: This addendum shall be attached to and become a part of the , Specifications and Contract Documents for the construction of Hangar and Office Buildings at Denton Municipal Airport, City of Denton, Texas. • 1. Paragraph 108,3 of Section 108 - Plumbing shall be amended to , read as follows: Basis for bid on septic tanks shall assume location 25 feet from building. A prefabricated septic tank may be substituted for the septic tank in the plans, when specifically approved by the engineer in writing.. 2. Paragraph 110.1 of Section 110 - Asphaltic Pavement shall have the following addition: ' I Total area to receive prime coat and asphaltic concrete shall be 15,000 square yards. R , 1 Power of Attorney FIDELITY AND DEPOSIT COMPANY OF MARYLAND HOME OFFiCb EAITIMOKE, MD. KNOW ALL MEN BY THESE PRESENTS: That the FIDELITY AND DEPOSIT COMPANY OF MARYLAND, a corpora. tion of the State of Maryland, by I,M.H.C. GRIFFITH ,Vice. President, and M. A. XELLY , Assistant Secretary, in pursuance of authority granted by Article V1, Section 2, of the By-Laws of said Com- pany, which reads as follows: "The President, or any one of the Executive Vice-Presidents, or any one of the additional Vice-Presidents specially authorised w to do by the Board of Directors or by the Executive Committee, shall have power, by and with the concurrence of the Sec- retary or any one of the Assistant Secretaries, to appoint Resident Vice-Presidents, Resident Assistant Secretaries and Attorneys- in-Fad as the business of the Company may require, or to authorise any person or persons to execute on behalf of the Company any bonds, undertakings, recognizances, stipulations, policies, contracts, agreements, deeds, and releases and assignments o( judgments at decrees, mortgages and instruments in the nature of mortgages, and also all other instruments and documtvts which the business the Company may require, and to affix the seal of the Company thereto," does hereby nominate, constitute and appoint William S. Price, John H. Trueheart, Roland F. Bonewitz, V.A. Browning, Max D. Scott, Douglas L. Stockman and Marvin M. Durrenberger, all of Houston, Texas, EACH its true and lawful agent and Attorney-in-Fact, to make, execute, seal and deliver, for, and on its behalf as surety, and as its act and deed: any and all bonds and undertakings... , ..EXCEPT bonds on behalf of independent Executors, Community Survivors and Community Guardians.. And the execution of such bonds or undertakings in pursuance of these presents, shall be as bindingg upon said Company, as fully and amply, to all intents and purposes, as if they had been duly executed and acJcnowl- edged by the regularly elected officers of the Company %t its office in Baltimore, Maryland, in their own proper persons. This power of attorney revokes that issued on behalf of William S. Price, etal, dated April 6, 1965, and Marvin M. Durrenberger, dated July 13, 1966. The said Assistant Secretary does hereby certify that the aforegoint is it true copy of Article Vf, Section 2, of the By-Laws of said Company, and is now in fora. IN WITNESS WHEREOF, the said Vice-President and Assistant Secretary have hereunto subscribed their names and affixed the Corporate Seal of the said FIDELITY AND DEPOSIT COMPANY OF MARYLAND, this ....................dtbh........................day of................. ..SeDtgzbe.L........... A. D. 19....66. ATTEST: FIDELITY AND DEPOSIT C031PANY OF 31ARYLAND (SIGNED) ................M...A,...K7r1 LX....................... By..........................S:d~i._ ll. (SEAL) Assistant Secretary Vice-Presidens STATE OF MARYLAND 33: CITY OF BALTIMORE On this 8th day of September A.D. 19 66 before the subscriber, a Notary P-iblic of the State of Maryland, in and for the City of Baltimore, duly commissioned and qualitsied, came the above-named Via-President and Assistant Secretary of the FtmeLtrY AND Damn CoitrANY of MAxyLAND, to me personally known to be the individuals and officers described in and who executed the preceding instrument, and they each acknowledged the execution of the same, and being by me duty sworn severally and each for himself deposeth and saith, that they are the said officers of the Company aforesaid, and that the seat affiQ to the preceding instrument is the Corporate Seal of said Cr.mpany and that the said Corporate Seal and their signatures as such officers were duly affixed and subscribed to the said instrument by the authority and direction of the said Corporation. IN TasTIMONY Weattor, I have hereunto set my hand and affixed my Official Seal, at the City of Baltimore, the day and year first above written. (SIGNED) .F.n XTL..D....1~liFS......................... (SEAL) Notary Public Commission Expires.-.LulY...1.~..1957 R. D. GILLISS CERTIFICATE I,--»»..»..»._.»........_......»...... » Assistant Secretary of the FIDELITY AND Dlrost COMPANY or MAxYLAND, do hereby certify that the attached Power of Attorney dated...... Sep tgmbe r..8th.»_ ....................19 in behalf of _ _..»....._».~ii1.1.1,P! ;i._..P.rLCe.,I-v~ Al......... s_. , is a true and correct copy and that same has been in full force and effect since the date thereof and is in full force and effect on the date of this certificate. and I do further certify that the said ,...lm.._aufa who executed the attached Power of Attorney as Vice President and Amistant Secretary respectively, were on the date of the execution of the attached Power of Attorney the dully elected Vice-President and Assistant See. rotary Of the FIDELITY AND DSrosur COMrANT or MAaYLAND, and that the said ..............Yft3..13.5~.._.~x$ $.I was one of the additional Vice-Presidents specially authorized by the Board of Directors to appoint any Attorney-in-Fact or to authorize any person or persons to execute on behalf of the Company any bonds, reeognitances, stipulations, undertakings, deeds, releases of mortgages, contracts, ag~rieements and policies, and to affix the seat of the Company thereto as provided In said Article VI, Section 2 Of the By-Laws of the FIDaLiTy AND DarastT CourAn or MAaTLAxD, IM TaTtMT as or, I have hereunto subscribed my name asid affixed a corporate se" the said Company, this L1419--Cd. A iris fant Seadary agoR ufiox avau nvaw x t QAiOH a3MVNI OAU3d i fYOw l3,VIP GWr1AHYY4 A0 221440 2n0.. . Uto,) ~rsoda - paeeltjap~► ooo. on..u,wau -A NVA.03 W. OLG r rod $ 00 -5 t; 94 C) !-r Ie~~ ofl i ,,.c a+ o Ua o ON ZT-0 40 r bn w i I I ~ Q z wu ~ w 8 u ~ O O 3 .,~ti g v r..o$ a O3o III<,,,, 1Q I , } 1_ryy ~ i ~s i ,S i•~a x~ .'~O w w c a pp ~ W ~ .age ' ~ ~d•~0 ~ ~ ~ Fro W~ o W to E~ 0 H W 1 i ~y i f(;w o ~ V~ {ate j of ~VCd G i~Fo 0. a ~ju~ a .9~ z f, zz ~ ~ ~ ~ 1.. 6! i .C Q •4 ~ •V S' (y 1 X ~ u t 8 3d ae cc$v i 3 ¢ f Mmoo; 0-1111111 F ~oa unox av3u 3sv3'ra x 0 V w~ b 6 O i QISIOU .LNHIl1Avd arowu~~~ ONV1AlIVW !O sol.~o awoa .u[pdu[o p«oda(j na~.i cool OxHolle01'1 - AN~~aOD 00019 - - - - , W n " •v ~ poar c rw -cc m1~ W C o A h :,c z 0 ~ - ar a, ew E cv rs u e CIO qq :7 u u, m ~ bC i s l3 E ~ i ar ~3 c ~ ~ h I p eOa 0.1 0 J (n r. V) f: C3 l~•o w V) w w i .a E= o~ v Ci A Oa Q Q w _ o 04 L O g IL Fm~ p C y~ z~~ ^ O± A F. c a C4 i I Y LL Vi G} W b y 9 t3 D I c v ;v 3 Ell u O ! °o a v .00 .0 v r, rJ ! i t' 04 ° C4COO q b " W np~j~~ • Q WpLe '1 ^~o I q O w I ai w M.- ® u F O v y O pc a > u',-08 >oc~~+ ax i] .66 L vii z 3 rl 04 >.b L' g~ E kl W i E vq~ E y_ W~ cr3 3 i ~E I~ 5, 0x4 ~ O ~ U f9 ' ~p 3 ;ado a8i ~.0. a? `aJI l E h 3 rq d a E Ub A4 o g4.8 i Fidelity and Deposit COMPANY OF MARYLAND Rlis jWcx 41 B miing a" lower .1twe 14 HUUS WN. BRANCH !V. & Pr<ccs, Y1oe-P'radert: 1001 Wit" Ctq Natia w BU& Ham r , $avrra a Tax As WON f 0~1►1-~ls1i. tam tl'I~! , , t r x