Loading...
HomeMy WebLinkAbout02-1985 5 Cl fY OF DENTON, TEXAS SPECIFICATIONS AND CONTRACT DOCUMENTS FOR 2 MO GROUND STORAGE TANK BID NO. 9435 FEBRUARY 1985 UTILITY BOARD MAYOR ROLAND LANEY, CHAIRMAN RICHARD O. STEWART EDWARD COOMES LEONARD HERRING, JR. CITY COUNCIL NANC`! BOYD LINNIE Mc ADAMS JOHN THOMPSON MARK CHEW JIM RIDDLESPERGER CHARLES HOPKINS RAY STEPHENS JOE ALFORD CITY MANAGER CHRIS HARTUNG r DIRECTOR OF UTILITIES R.E. NELSON, P.E. ASSISTANT DIRECTOR OF UTILITIES C. DAVID HAM, P.E. FREESE AND NICHOLS, INC. CONSULTING} ENGINEERS FORT WORTH, TEXAS C3 t+ 1 TABLE OF CONTENTS BIDDING REQUIREMENTS PAGE INVITATION FOR BIDS 00010-1 INSTRUCTIONS TO BIDDERS 00100-1 LOCATION MAP L-1 PROPOSAL 00300-1 ~ DATA SHEET (Not Used) D-1 MINIMUM WAGE SCALE - SCHEDULE "B" MWS-1 CONTRACTOR FORMS AND AGREEMENT CONTRACT AGREEMENT 1 + PERFORMANCE BOND "11 3 PAYMENT BOND 5 INSURANCE CERTIFICATE GENERAL CONDITIONS GC-1 It SUPPLEMENTARY CONDITIONS ! 00800-1 DIVISION CONSTRUCTION REQUIREMENTS 01001 General Construction Requirements 01002 MEasurement and Payment 01001-1 01002-1 DIVISION 11--j- SITE WORK 02100 Clearing and Grubbing 02201 Earthwork 02100-1 I 02272 Grassing for Erosion Control 02201-1 02272-1 { 02614 Pretensioned Concrete Cylinder Pipe ~ 02614-1 DIVISION I CONCRETE 03100 Concrete Formwork 03100-1 03200 Concrete Reinforcement 03300 Cast-In-Place Concrete 0320-1 033055-1 DIVISION V~ ME_ TALS 05710 Miscellaneous Metals 05710-1 TABLE OF CONTENTS - Continued PAGE DIVISION 1X - FINISHES 09872 Tank Painting 09872-1 09905 Plant Painting 09905-1 J OIVISION XI - EQUIPMENT 11000 General Equipment Stipulations 11000-1 11426 Submersible Sump Pump 11426-1 11435 Cathodic Protection 11435-1 OIVISION XII1 - SPECIAL CONSTRUCTION 13401 Welded Ground Storage Tank 13401-1 1- OIVISION XV - MECHANICAL 15061 Steel Pipe & Fittings 15061-1 1 15062 Cast Iron Pipe & Fittings 15062-1 15078 Miscellaneous Piping & Fittings 15078-1 15101 Gate Valves 15101-1 i 15103 Butterfly Valves 15103-1 ' 15136 Miscellaneous Valves 15136-1 I DIVISION XVI - ELECTRICAL 16000 General Electrical Requirements 16000-1 r 16100 Wire and Conduit System 16100-1 I a Y CITY OF DENTON, TEXAS 2.0 MG GROUND STORAGE TANK BID DATE: 2:00 P.M., April 2, 1985 , i i ADDENDUM NO. 1 SPECIFICATIONS 13401 WELDED STEEL GROUND STORAGE TANK r 1. 1.01 SCOPE - To paragraph two, second sentence, after access ladders, insert the following: "target water level indicator" 2. 2.03 Appurtenances - After H. CLEAN OUT MANHOLES, add the following: "I. TARGET WATER LEVEL INDICATOR A suitable water level indicator with a target shall be installed. The indicator shall be located by the exterior access ladder and shall be visible from the plant i Administration Building. The cable and cable fasteners shall be 316 stainless steel. The level indicator shall be a Varec Series 6700 or approved equal." i r Bidders shall acknowledge rec,ipt of Addendum No. 1 in the space provided in the Proposal. i s s i i FREESE AND NICHOLS, INC. Consulting Engineers March 20, 1985 ADDENDUM NO, 1 - Page-1 • 1 f J CITY OF DENTON, TEXAS 2.0 MG GROUND STORAGE TANK Bid Date: 2:00 P.M., April 2 1985 i ADDENDUM NO. 2 Specifications i I . 13401 WELDED STEEL GROUND STORAGE TANK 1111 1. 1.01 SCOPE - To paragraph two, first sentence Change ",.an inside diameter of 150 feet..." v to: "...an inside diameter of 150'-6"... 2. 1.02 GOVERNING STANDARDS - To paragraph one, after sentence one, add the following: "The Contractor may elect to use the criteria set forth in Appendix "C" of the AWWA Standards for welded steel tanks. A one-day mean temperature of 1° shall be used." Particular attention should be shown to the additional requirements for weld x-rays and testing in Appendix "C". PLANS Sheet 1 of 3: Change proposed 2 MG tank diameter from "1501-0" to ,1150'-6". t Bidders shall acknowledge receipt of Addendum No. 2 in the space provided in the Proposal. END OF ADDENDUM NO, 2 a FREESE AND NICHOLS, INC. CONSULTING ENGINEERS March 260 1985 f Addendum No. 2 - Page-1 l INVITATION FOR BIDS Sealed proposals addressed to Mr. John J. Marshall, Purchasing Agent of the City of Denton, Texas will be received at the office of the Purchasing Agent at the City of Denton Service Center/Warehouse at 901-8 Texas Street, until 2;00 P.M., April 2, 1985 for the construction of 2.0 MG GROUND STORAGE TANK BID NUMBER 9435 At this time and place the proposals will be publicly opened and read aloud. Any bid received after closing time will be returned unopened, Copies of Plans, Specifications, and Contract Documents are on file and may be examined without charge in the office of the Purchasing Agent, 901-B Texas Street, and Director of Utilities, Municipal Building, Denton, Texas. Copies of Plans, Specifications and Contract Documents may be procured from Freese and Nichols, Inc., Consulting Engineers, 811 Lamar Street, Fort Worth, Texas, upon a nonrefundable deposit of $15.00. A cashier's check, certified check or acceptable bidder's bond, payable to the City of Denton, Texas in an amount not less than five (5%) percent of the bid submitted, must accompany each bid as a guarantee that, if awarded the contract, the Bidder will, within ten (10) days of award of contract, enter into a contract and execute bonds on the forms provided in the Contract Documents. Attention is called to the fact that not less than the prevailing wage rates, as established by the City of Denton, Texas, and as hereinafter set , forth in the Contract Documents hereinbefore described and which are made a part hereof, must be paid on this project. r Performance and Payment Bonds shall be furnished as set forth in the Instructions to Bidders. In case of ambiguity or lack of clearness in stating proposal prices, the City of Denton, Texas reserves the right to adopt the most advantageous construction thereof, or to reject any or all bids, and waive formalities. No bid may be withdrawn within sixty (60) days after date on which bids are opened. CITY OF DENTON, TEXAS John J. Marshall, C.P.M. Purchasing Agent r a 00010-1 a ti i INSTRUCTIONS TO BIDDERS 1. Defined Terms. Terms used in these Instructions to Bidders which are define n the eneral Conditions of the Agreement have the meanings assigned to them in the General Conditions. f 2. qualification of Bidders. To demonstrate his qualifications for the n Project, each Bidder must be prepared to submit within five (5) days of Owner's request written data as to the Bidder's Qualifications such as financial data, previous experience, list of available equipment, and evidence of authority to conduct business in the jurisdiction where the project is located, 3. Examination of Contract Documents and Site. 3.1 Before submitting his Bid, each Bidder must (a) examine the Contract Documents thoroughly, (b) visit the site to familiarize himself with local conditions that may in any manner affect performance of the work, (c) familiarize himself with federal, state and local laws, ordinances, rules and regulations affecting performance of the work, and (d) carefully correlate his # observations with the requirements of the Contract Documents. i 3.2 Reference is made to the Supplementary Conditions for the identification of those surveys and investigation reports of subsurface or latent physical conditions at the site or otherwise affecting performance of the work which have been relied upon by Engineer in preparing the Drawings and Specifications. The data is furnished for information only and neither the Owier nor Engineer guarantees the accuracy of the data. Before submitting his Bid each Bidder will, at his own expense, make such additional surveya and investigations as he may deem necessary to determine his bid price for performance of the work within the k terms of the Contract Documents. 3.3 The submission of a Bid will constitute an incontrovertible r representation by the Bidder that he has complied with every requirement of this Article 3. 4, Interpretations. All questions about the meaning or intent of the ,I Contract ocuments shall be submitted to Engineer in writing. Replies will i be issued by Addenda mailed or delivered to all parties recorded by I Engineer as having received the bidding documents, questions r 1 eceived less than two days prior to the date for opening of Bids may not be answered. } Only questions answered by formal written Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect. 5. Bid Security, Each bid must be accompanied by a certified or cashier s c eck or an approved Bidder's Bond underwritten by a surety named in the current list of "Surety Companies Acceptable on Federal Bonds" as 001001 r . published in the Federal Register by the Audit Staff Bureau of Accounts, U.S. Treasury Department, for the sum of five (5%) percent of the amount of the maximum total bid as a guarantee that, if awarded the contract, the Bidder will promptly enter into a Contract and execute a Performance and Payment Bond on the forms included in the Contract Documents, Certified or cashier's check shall brn made payable to the Owner, 6, Contract Time, The number of days for the completion of work (the I Contrac me sh-aall be inserted by the Bidder in the space provided in the Bid (Proposal) and will be included in the executed Agreement. Provisions for liquidated damages are set forth in the Supplementary Conditions. The Owner desires that the project be completed by July 15, 1985. Considera- tion may be given in awarding the Contract to the bidder's proposed I completion time. 7, Bid Form Proposal). f 7.1 Bidders shall use the Bid (Proposal) forms included in the documents for each contract Bid. Bid (Proposal) forms are to be left attached to documents in same manner as received by Bidders, i Supplemental data to be furnished shall be included in same sealed envelope with Proposal. 7.2 Bid (Proposal) Forms must be completed in ink. The Bid price of each item on the form must be stated in words, if specifically requested, and/or numerals, in case of a conflict, words will take precedence, 7.3 Bids by corporations must be executed in the corporate name by the president or a vice-president (or other corporate officer ' accompanied by evidence of authority to sign) and the corporate seal shall be affixed and attested by the secretary or an assistant secretary, The corporate address and state of incorporation shall be shown below the signature. 7.4 Bids by partne-ships must be executed in the partnership name and signed by a p..-tner, his title must appear under his signature and the official address of the partnership must be shown below the signature. 7.5 All names must be printed below the signature, 7.6 The Bid shall contain an acknowledgment of receipt of all Addenda (the numbers of which shall be filled in on the Bid form), i 8. Submission of Bids, Bids shall be submitted at the time and place indicated In the nv ation for Bids and shall be included in an opaque sealed envelope, marked with the Project title and name and address of the 1 Bidder and accompanied by the Bid Security and other required documents, , 9, Modification and Withdrawal of Bids. Bids may be modified or withdrawn by an appropriate ocu me-n7y executed (in the manner that a ( }3 00100-2 . 1 Y Bid must be executed) and delivered to the place where Bids are to be ti submitted at any time prior to the opening of Bids. Bids may not be withdrawn after opening of Bids for the period set forth in the Invitation for Bids. 10. Opening of Bids. Bids will be opened as indicated in the Invitation 1 for 3iids received after such time will not be considered, and will be returned unopened. 11, Bids to Remain Open. All Bids shall remain open for the period of time setset fin the Invitation for Bids, but Owner may, in his sole discretion, release any Bid and return the Bid Security prior to that date, r 12. Award of Contract, 12.1 Owner reserves the right to reject any and all Bids and waive any and all formalities, and the right to disregard all nonconforming or conditional Bids or counter proposals. 12.2 In evaluating Bids, Owner will consider the qualifications of the Bidders, whether or not the Bids comply with the prescribed requirements, and alternates and unit prices if requested in the F Bid forms. He may consider the qualifications and experience of Subcontractors and other persons and organizations (including those who are to furnish the principal items of material or equipment) proposed for those portions of the work as to which the identity of Subcontractors and other persons and organiza- tions must be submitted as specified in the Supplementary 1 Conditions or Specifications. He may conduct such investigations as he deems necessary to establish the responsibility, qualifi- cations and financial ability of the Bidders, proposed Subcon- tractors and other persons and organizations to do the work in accordance with the Contract Documents to Owner's satisfaction within the prescribed time. Owner reserves the right to reject the Bid of any Bidder who does not meet any such evaluation to Owner's satisfaction. 12.3 If a contract is to be awarded, it will be awarded to the lowest responsible Bidder whose evaluation by Owner indicates to the Owner that the award will be in the best interests of the Project. 12.4 It is expected that the Owner's evaluation of bids and award of contract will be made as set forth in the Invitation for Bids. The successful bidder will be notified by a Notice of Award which may be a letter or telegram. Time of completion is very important and failure to meet completion schedule will subject 1 the Contractor to liquidated damages as provided in the Supplementary Conditions section of the Contract, t 1 A) 00100-3 tl 1 13. Execution of Contract. formal notice 13.1 eaccepted , shall Bidder, execute within the formal fifteen Contract days after i Agreement and of award required Bonds on the forms prepared and submitted by the Owner. 13.2 The Owner will issue a Notice to Proceed authorizing the Contractor to commence work. 14, Wage Rates. There shall be paid on the project not less than the ' genera preva-iTing rates of wages in the locality of the project, which prevailing wage rates have been determined by the Owner in accordance with statutory requirements. There is included immediately following these Instructions to Bidders a schedule giving for various classifications the minimum rates as have been established by the Owner. 15. Sales Taxes. The Owner qualifies as an exempt agency pursuant to the , provis ons o rticle 20.04 (F) of the Texas Limited Sales, Excise and Use Tax Act, and is not subject to any State or City sales taxes. I The Contractor performing this contract may purchase, rent or lease all materials, supplies, equipment used or consumed in the performance of this contract by issuing to his supplier an exemption certificate in lieu of the tax, said exemption certificate complying with the State Comptroller's ruling N95-0.01, Any such exemption certificate issued by the Contractor in lieu of the tax shall be subject to the provisions of the State Comptroller's ruling 095-0.09 as amended to be effective October 2, 1960. 16. Performance and Payment Bonds. Performance and Payment Bonds are require or S project an s a l be provided in accordance with Article 5 of the General Conditions. i END OF INSTRUCTIONS TO BIDDERS ~i 1 I i 00100-4 s ' l i f Afs• 10 • /otr p 31 1 • t sr ~.n frWra t~ tHt r fr fl Y ~7Mf MSrrR [attu Me^'•"t r«a rrYwt tlG ' f n fr Q u,... uh Olri ceYOY M Y • ~ t caau v G ` y u 1 CM !ei sr j j!'I•M ° i ,1rr r t tt ~ r DENTON ■x p " uR011r U p 3 ,w y ~StYwrt tr" ~j~ MMlrt a _ r riY 1 °4I 1 N MM[R H ~ Wi ~ .l rMUlr sr r t q t C if if rrw.nr a y s " p yR ■ep R c ql... r.e "°O° i. t' i ? 1r ` j 'Ury y YIIMY ' t 1 M 1 M 15 S77 Q fl 1, as ` _ tl ^p MCY JRr I ws MRr f r r ~ r - o r r' I r " M a M ~ S I ,10010. 1 fl ~ 1( X 1 I M t I~ a N $ : s x f 1 tWo pp ~ K1f( SI f y • V11fe• , J" IM it Y <a w, Y ° 1APPROX, SCALE 2u= 4 MILE 3 kY _ i y y' ~ i~ ~ 'scare c tt .f ~ a At \-c0 ~ ~ I r••, QQ \ ' _ - - WATER PLANT t w Il uOIH•rr 1 % sw~r yG ~ - _ L r t ► it = p 3 r4 e...0 ,Oat twl Vt•[go I • Os r J It 3m "Ak, 0 4*0 ',J t el 0 OMLM* jjj~ i _jfmr r PROJECT, - L"ATiO N 11'I r',U,V / MM •r l [it (Ito r C { ss i , IF 1 I f 0~ 1[•1• I - All T I i BID (PROPOSAL) Denton Texas 1 _ April _2 1985 PROPOSAL OF _ Advance Tank-Texas, Inc. + 4800 Walden Rd,, Beaumont, Texas 77707 + A Corporation organized and existing under the laws of the State of Texas , a partnership consisting of the business name of an individual. TO: John J, Marshall., C.P.M. t Purchasing Agent PROPOSAL FOR: 2 MG GROUND STORAGE TANK, BID NO, 9435 The undersigned Bidder, pursuant to the foregoing Invitation for Bids, has carefully examined the Instructlons to Bidders, this Proposal, the { Supplemental Conditions, the form of Contract Agreement and Bonds, the General Conditions of the Agreement, the Specifications, the Plans, and + also the site of the work, and will provide all necessary labor, superintendence, machinery, equipment, tools, materials, services and other facilities to complete fully all the work as provided in the Contract Documents; and binds himself upon formal acceptance of his Proposals to execute a contract and bonds, according to the prescribed forms, for the following prices to-wit: Item Description No. Price to he Written in Words) Amount For the fabrication, erection and construction of one (1) 2.0 million gallon welded steel ground storage tank, complete with foundation, valves, piping connections, concrete retaining wall, grading, and site work, for the lump sum amount of Four Hundred, Thirty-Three Thousand and No/100 Dollars 5433,000,00 00300-1 9 3 Within fifteen (.l5) days after formal acceptance of this Proposal by a Notice of Award of contract, the undersigned will execute the Contract Agreement and will furnish approved surety bonds and such other bonds as , required by the Contract Documents for the faithful performance of the Contract. In the event the Contract Agreement and bonds are not executed within the came above set forth, the attached bid security in the amount of 5% of Total Amount of This Bid Is to become the property of the Owner as liquidated damages for the delay and additional work caused thereby. The undersigned agrees to substantially complete all work covered by these Contract Documents within 180 consecutive calendar days from the day established for the start -the work as set forth in a written Notice to Proceed to be issued by the Owner or by the Engineer for the Owner. Except by mutual agreement of the Owner and the Contractor the date established for the start of work will be not less than ten (10j days or not more than thrity (30) days after the date of the Contract Agreement. Receipt is acknowledged of the following addenda: ?i Addendum No. 1 March 20, 1985 { Addendum No. 2 March 26, 1985 ii Addendum No. 3 Addendum No, 4 Addendum No, 5 Re Zctfully submit d ISK i By +m s Attested By; Dennis L. Lagrimini, Vice-Pres. (Print Name and Title) P. 0. Box 7273 Secretary Beaumont, Texas 77706 ress # (SEAL) If Bidder Is a Corporation NOTE; Do not detach bid forms from other papers. Fill in with ink and submit complete with attached papers, ! 00300-2 I i 5 i r l i 1 . J , j DATA SHEET AND SUBMITTAL INFORMATION CONTRACTORS CO'TRACTOR'S NAME: r ADDRESS: PHONE NO.: CONTRACTOR'S RELATED WORK EXPERIENCE (LIST THREE REFERENCES) CLIENT: ADDRESS: PHONE NO. DESCRIPTION: CLIENT: ADDRESS: PHONE Nu.: DESCRIPTION: CLIENT: ADDRESS: PHONE NO.: DESCRIPTION: , TYPE OF SUB CONTRACTOR NAME ADDRESS PHONE NO. 1 TYPE OF SUB CONTRACTOR NAME s ADDRESS PHONE NO. 4 Submit additional data sheets if necessary, D-I s i f SCHEDULE "9" / CITY OF DENTON MINIMUM WAGE RATES FOR PUBLIC ENGINEERING (HIGHWAY/HEAVY) CONSTRUCTION AND UNOERGROOND UTILITY CONTRACTS k The rates below have been determined by the City of Denton, Texas in accordance with the statutory requirements and prevailing Local wages. Overtime shall be paid for at the race of one and one-half (1-1/2) times the regular rates for eveky hour worked in excess of forty (40) hours per week. c Trade-Craft Classification Rate Per Hour Air Tool Man i Asphalt Heatermin ; Asphalt Raker 6.55 Asphalt Shoveler 5.00 Batching Plant Scaleman 6.50 Batterboard Setter Carpenter 6.65 Carpenter Helper 5.45 Concrete Finisher (Paving) 7.05 Concrete Finisher Helper (Paving) 5.50 { Concrete Finisher (Structures) 6.80 Concrete Finisher Helper (Struct) 5.55 Concrete Ruboer Elect:ician 9.50 Electr.lclan Helper 5.50 i Form Builder (St:uctu:es) 6.70 Form Builaer Helper (Struct) 5.00 Form Liner (Paving a Curb) 7.25 Form Setter (Paving 6 Curb) 6.10 i Form Setter Helper (Paving I Curb) 4.50 Form Setter (Structures) 7.00 Form Setter Helper (Structures) 5.65 Laborer, Common 4.00 Laborer, Utility Men 4.90 Manhole Builder, Brick g Mechanic 6.70 Mechanic Helper 5.00 Oiler 6.05 Serviceman 5.75 Painter 1Structures) Painter Helper (Structures) Piledriveeman Pipelayer 5.75 Pipelayer Holpei 4.75 Powderman 7.00 Reinioreing Steel Setter (Paving) 5.00 Reinforcing Steel Setter (Struct) 6.60 Reinforcing Steel Setter Helper 4.30 Steel Worker (Structural) 5.25 Steel worker Helper'(Structural) Sign rrrector Sign erector Helper Spreader Sox man e.00 Swamper 4.95 power tqui2ment Ccerators, , Asphalt Distributor 6.00 Aspnalt Paving Machine 6.95 Broom or sweeper operator 5.20 Bulldozer 150 HP s Lesa 6.25 + Bulldozer 150 HP 6.7$ Concrete Paving Curing Macnine 6.50- Concrete Paving Finisnimg Macn 4.60 1 1 ""1Q Trade-Craft Classification Rate Per Hour Concrete Paving Form Grader Concrete Paving Joint Machine ¢ Concrete Paving Longitudinal Float 6.35 i. Concrete Paving Mixer 7.75 Concrete Paving Saw 6.05 Concrete Paving Spreader Paving Sub Grader - Crane, Clamshell, Backhoe, Derrick, Dt4gline, Shovel (less than 1 1/2 CY) 7.00 r Crane, Clamshell, Backhoe, Derrick, Dragline, Shovel (1 1/2 CY a Over) 7,35 i Crusher or Screening Plant Operator F Elevating Grader , f Form Loader. Foundation Drill Operator (Crawler 4ounted) ` 7 Foundation Drill Op. (Truck Mounted) 8.25 Foundation Drill Operator Helper 5.45 Front End Loader (2 1/2 CY a Leas) 6.15 Front End Loader (Over 2 1/2 CY) 1.25 Hoist (Over 2 drums) 6.09 Mixer (Over 16 CFI Mixer (16CF 6 Less) Motor Grader Operator, Fine Grade 7.55 Motor Grader Operator 7.25 ' Roller, Steel Wheel (Plant-Mix Pavements) 6.35 ' Roller, Steel Wheel (Other-Flat Wheel or Tamping) 6,45 Roller, Pneumatic (Sell-Propelled) 5.L5 Scrapers 117 CY a Less) 6,25 Scraper.; (Over 17 CY) 6.90 Side Boom Tractor (Crawler Tyre) 150 HP a Less Tractor (Crawler Type) over 130 HP 6.90 Tractor (Pneumatic) 80 RP S Less 9.60 ' Tractor (Pneumatic) over 80 HP 6.75 Traveling 4ixer Trenching Machine, Light Trenching Macnine, Heavy Wagon Drill, Boring Macnine or Post dole Driller operator 5.25 Truck Drivers, Single Axle, Light 5.33 Single Axle, Heavy Tandom Axle or Semitrailer Lowooy-Float Transit-Mix 5.70 Wincn ;i Weider 7,15 Welder Helper The CGWTRArTOR sna1L -omp:y witn all State and Federal :.a•as apnllcaole to sucn worx, The above acs .minimumAr3t4$, 3ldders an,~ll oasa tnei: oi,:s on rates that' expect t0 pay, i. In excesa :nose listed. The ` OWNER will cot consider c1Aixis for extra payment to =NTRACTOR Oft account of payment of wages signer than tnose speci!ied, G - 11.5 t i 41 CONTRACT AGREEMENT STATE OF TEXAS COUNTY OF Denton ¢ THIS AGREEMENT, made and entered into this 16 day of April f A.D., 19 85 , by and between the City of Denton of the County of Denton and state of 'texas, acting through its City Manager thereunto duly authorized so to do, Party of the First Part, hereinafter termed the OWNER, and Advance Tank-Texas, Inc, of the City of Beaumont , County of Jefferson • and State of Texas Party of the Second Part, hereinafter i termed CONTRACTOR. WITNESSETH, That for and in consideration of the payments and agreements hereinafter mentioned, to be made and performed by the Party of E the First Part (OWNER), and under the conditions expressed in the bonds bearing even date herewith, the said Party of the Second Part (CONTRACTOR) hereby agrees with the said Party of the First Part (OWNER) to commence and complete the construction of certain improvements described as follows, t 2.0 MG Ground Storage Tank - Bid No. 9935 ,i and all extra work in connection therewith, under the terms as stated in the General Conditions of the Agreement; and at his (or their) own proper cost and expense to furnish all the materials, supplies, machinery, equip- ment, tools, superintendence, labor, insurance, and other accessories and services necessary to complete the said construction, in accordance with the conditions and'prices stated in the Proposal attached hereto, and in accordance with all the General Conditions of the Agreement, the Special Conditions, the Notice to Bidders (Advertisement for Bids), Instructions r 10-15•-71 .178 1 I to Bidders, and the Performance and Payment Bonds, all attached hereto, and in accordance with the plans, which includes all maps, plats, blue- prints, and other drawings and printed or written explanatory matter thereof, and the Specifications therefor, as prepared by FREESE AND NICHOLS, INC., herein entitled the ENGINEER, each of which has been identi- fied by the CONTRACTOR and the ENGINEER, all of which are made a part hereof and collectively evidence and constitute the entire contract. The CONTRACTOR hereby agrees to commence work on or after the date established for the start of work as set forth in a written notice ' to commence work and to substantially complete all work within the time stated in the Proposal, subject to such extensions of time as are pro- vided by the General and Special Conditions, The OWNER agrees to pay the CONTRACTOR in current funds the C price or prices shown in the Proposal, which forms a part of this Con- tract, such payments to be subject to the General and Special Conditions of the Contract, IN WITNESS WHEREOF, the parties to these presents have executed this Agreement in the year and day first above written. i ATTEST; ~ f Cit of Denton 1 Part =rIsar rt 0 N R - 1 By g i t City Manager (SEAL) . y ATTEST; Q Advance Tank-Texas, Inc. Pa• y-~of the Secon rt C NTRACTOR yc~ ai✓ /1 By c~C ` T i t e VI C, ,E'Es 11-A61vtr- 1 (SEAL) 2 10/22/73 ' 178 i I ~ '"alb PERFORMANCE BOND STATE OF TEXAS COUNTY OF Denton Q 1 KNOW ALL MEN BY THESE PRESEN'CS; That Advance Tank-Texas, Inc. of the City of yak -Wtyh- , County of and State of Texas as PRINCIPAL, andri n5!cQ ~~~v Q, ,uct. I m k 1 c~nu t v i V n_~ c~ tJY Q ~N•GLfti ~"^~~s UR TY authorized under the laws of the State of Texas to act as surety on bonds for principals, are held and firmly bound unto the _ City of Denton , as OWNER, in the penal sum of Four Hundred, Thirty-Three Tounsand and No[100 Dollars 433,000.00 for the payment whereof, the said Principal and Surety bind themselves and J their heirs, administrators, executors, successors and assigns, jointly 1 and severally, by these presents. + WHEREAS, the Principal has entered into a certain written contract r J with the OWNER, dated the 16 day of aril 19 85 for the con- struction of 2.0 MG Ground Storage lank - Bid No. 9435 whirh contract is hereby referred to and made a part hereof as fully and to ` the same extent as if copied at length herein. NOW, THEREFORE, the condition of this obligation is such, that if the said Principal shall faithfully perform said Contract and shall in all respects duly and faithfully observe and perform all and singular the cove- nants, conditions and agreements in and by said contract agreed and cove- nanted by the Principal to be observed and performed, and according to the true intent and meaning of said Contract and the Plans and Specifications hereto annexed, then this obligation shall be void, otherwise to remain in full force and effect; PROVIDED, HOWEVER, that this bond is executed pursuant to the provisions of Article 5160 of the Revised Civil Statutes of Texas as amended f, 3 ~ 10-15-71 • 'r8 ..ANA. 1 ' I ! I by acts of the 56th Legislature, Regular Session, 1959, and all liabilities on this bond shall be determined in accordance with the provisions of said Article to the same extent as if it were copied at length herein, " PROVIDED FURTHER, that if any legal action be filed upon this bond, venue shall lie in Denton County, State of Texas. Surety, for value received, stipulates and agrees that no change, extension of time, alteration or addition to the terms of the contract, or to the work performed thereunder, or the plans, specifications, or drawings accompanying the same, shall in anywise affect its obligation on this bond, and it does hereby waive notice of any such change, extension of time, alter- ation or addition to the terms of the contract, or to the work to be per- I , formed thereunder. ' IN WITNESS WHEREOF, t e said Principal and Surety have signed and sealed this instrument this 4) day of 19 85 ~ ,ipCa<~,tic.~, k1.L~fti1 anGC~.G-tMc~ncGif . +y~?t.nu~_` Advance Tank-Texas, Inc, .J - ctCL~~itc ad"r~~~an~. r nc pa ure y , i Ti tleV16 J916'5i ENi TItle~~rcl_,T c., Address PO (2'0 X Address ?Ll.5477 &4(A rho Ajl T.4'. -77706 d 1A4Zv),t., X 7 7 0. I !a_ . i (SEAL) (SEAL) The name and address of the Resident Agent of Surety Is: L/ NOTE; Date of Bond must not be prior to date of Contract. IV ~i. lZlfr~- d 4 10-15-71 x'78 707 I I r r CERTIFIED COPY GENERAL POWER OF ATTORNEY r NO. FG 36 KNOW ALL MEN BY TIIESE PRESENTS, ` That FIDELITY AND GUARANTY INSURANCE UNDERWRITERS, INC„ a corporation organized and existing under the laws of the State of Ohio, and having Its principal office at 100 Light Slivel, Baltimore, Maryland 21203, does hereby constitute and appoint E. L. Purcell, Jr. , Alfreda Mills and Edward Arena of the City of Houston State of Texas , Its true and lavlful AttomeySiin-Fact, with power and authority to sign its name as surety to, and to execute, seal, acknowledge and deliver any and alt bonds, undertakings, recognizances or other written obligations in the nature thereof; and the said I FIDELITY AND GUARANTY INSURANCE UNDERWRITERS, INC. hereby ratifies and confirms all of the acts of said Attorney-in-fact, pursuant to these premises. This appointment is made under and by authority of a by-law of the said FIDELITY AND GUARANTY INSURANCE UNDERWRITERS, INC., a certified copy of which is hereto annexed and made a part of this Power of Attorney. IN WITNESS WHEREOF, the said FIDELITY AND GUARANTY INSURANCE UNDERWRITERS, INC. Ws caused this Instrument to be sealed with its corporate seal, duly attested by the signatures of its Vice•President and Assistatt Secretary, this 29th day of January 19 85 , E FIDELITY AND GUARANTY INSURANCE i UNDERWRITERS, INC. i , f (Signed) a,,• i ..V/re.PiuiJri r. r (SEAL) (Signed) Jr..J.t. Caz3noilY Anamnl Secretary. , i STATE OF MARYLAND ) , BALTIMORE CITY ) ss, On this 29th day of January 19 85 , befom: me personally came J. M. Raley, Jr. Vice President of FIDELITY AND GUARANTY INSURANCE UNDERWRITERS, INC. and J. J. Casserly Secrete of said Corporation, Secretary with both of whom I um personally acquainted, who tieing by me severally sworn, said that they, the said J, NI. Raley, Jr, and J. J. Casaerly were respectively the Vice President and Assistant Secretary of the said FIDELITY AND GUARANTY INSURANCE UNDERWRITERS, INC., the corporation described in and which executed the foregoing Power of Attorney; that they each knew the seal of said corporation; that the seal affixed to said Power of Ailorney was such corporate sent, that it was so affixed by authority of the by-laws of said corporation; and that they signed their names hereto by like authority as Vice President and Assistant Secretary, respectively, of the Corporation. r My Commission expires the first day of July, 19 86, (SEAL) (Signed) Margaret D1, Hurst NOTARY PUBLIC Fs 8 I t9-air Copy of flyLaw "Article VI, Section 7 - Execution of Instruments, The Chairman of the Ifoard, the President, any Executive Vice President, any Vice Presidenl, including the Financial Vice President, or any Assistant Vice President, in conjunction with the Secretary or an Assistant Secretary, shall have power on behulf of the Company: (a) to execute, acknowledge, verify and deliver all contracts, obligations, in- struments and documents whatsoever in connection with its business, including, without limiting the foregoing, any and all bonds, guarantees, undertakings, recognizances, stipulations, policies oC insurance, deeds, leases, mortgages, re- leases, satisfactions and agency agreements; (b) to appoint one or more persons for any or all of the purposes mentioned In I the preceding paragraph (a), including affixing the seal of the Company," I, Michael P. lienunond an Assistant Secretary of FIDELITY AND GUARANTY INSURANCE UNDERWRITERS, INC,, do hereby certify that the foregoing is a full, true and correoi Oopy,oflhe original power of attorney given by said Company to F. L. Purcell, Jr. , Alf reds, Mills and Edward Arens of Houston, Texas authorizing and empowering them to sign bonds as therein set forth, which power of attorney has never been revoked and is still in full force and effect. And I do further certify that said Power of Attorney was given in pursuance of a by-law of said Company, and that the ` foregoing Is t, true amyl convct copy of sold by-law, In Testimony Whereof, I have hereunto set my hand and the seal of FIDELITY AND GUARANTY INSURANCE UN- DERWRITERS, INC. this 16 day of April 19 85 I i { Asslsrrmt Secretary, i j { t i f f i i CERTIF1rD COPY GENERAL POWER OF ATTORNEY No......,,,75048 / Nnow all Men by these Presentst That UNITED STATES FIDELITY AND GUARANTY COMPANY, a corporation organized and existing under the laws of the .hate of Maryland, and having its principal office at the City of Bsllimorc, In the Slate of Maryland, does hereby constitute and appoint s Alfroda Mills s of the City of Houston State of Texas , its true and lawful attorney )oNo tsftAltpyl}kloyexxbcx for the;-Vowing purposes, to will To sign Its name as surety to, and to execute, seal and acknowledge any and all bonds, and to respectively do and perform any and all sets and things let forth In the resoludoo of the Board of Directors of the said UNITED STATES FIDELITY AND GUARANTY COMPANY, it certified copy of which is hereto annexed and made a part of this Power of Allorney; and the said UNITED STATES FIDELITY AND GUARANTY COMPANY, through us, Its Hoard of Directors, batch), ratifies and confirms all and whatsoever the said ( Alfreda Mills I may lawfully do In the premises by virtue of these presents, In Wltrtasa Whereo/, the maid UNITED STATES FIDELITY AND GUARANTY COMPANY has caused this instrument to be traded with its corporate seal, duly attested by the signatures of its Viee•Presldent and Assistant Secretary, ibis 2" day of October A, D. 1962 UNITED STATES FIDELITY AND GUARANTY COMPANY. (Signed) By...... A1-.,Cr„Ho,lmee........... Vka•Prrtfdent. (SEAL) (Signed) E.,.$Y..'311f.fingt.on..... Assistant Secretary. STATE OF MARYLAND, BALTINIORE CITY, eel On this 23J day of October A. D. 1962, before we personally came A. C. Holmes Vice-President of the UNITED STATES FIDELITY AND GUARANTY COMPANY and E, '.it. Buffington Assistant Secretary of maid Company, with both of whom I am personally acquainted, who being by me severally duly sworn, said that they resided In the City of Baltimore, Marylandl that they, the laid A. C. Holmes and E. 4Y. Buffington were respectively the Vice-President and the Assistant Secretary of the said UNITED STATES FIDELITY AND GUARANTY COMPANY, the car. po"lio" described in and which executed the foregoing Power of Attorney; that they each knew the seal of said corporation; that the seal el nFAxed to said Power of Attorney was such corporate seal, that It was so fixed by order of the Board of Directors of said corpora. Lion, and that they signed their names thereto by like order as Vlce•Prrddent and Assistant Secretary, respectively, of the Company, My commission expires the first lb7dR3vlxylurlZdRxwxxye Monday in Mays A. D. 1963 (SEAL) (Signed} bnne,.K.„Q!Ar,t0'V.......... Notary Public, STATE OF MARYLAND Set, BALTIMORE CITY, 3amea F. Carney Clerk of the Superior Court of Baltimore City, which Court U a Court of Record, and has a seal, do hereby certify that Anne H. OtBrien t Esquire, before whom the annexed affidavits were made, and who has thereto subscribed his name, was at the (]me of to doing a Notat Public of the State of Maryland, in and for the City of Baltimore, duly commlesioned and sworn and outltorited by law to admlmdtter oaths and take acknowledgments, or proof of deeds to he recorded therein. I further certify that I am acquainted with the handwriting of the said Noury, and verily believe the signature to be his genuine signature. In Testimony Whereof, I hereto set my hand and affix the seal of the Superior Court of Baltimore City, the same being s Court of Record, this 25111 day of October , A. D. 1962 { (S9AL) (Signed) 4A(gQA Xr,.,Gf1?',t 9Z Clerk, of the Superior Court of llaldmore City, ye 3 costf 1 COPY OF RESOLUTION II That Whereat' It is necessary for the effectual transaction of business that this Company appoint agents and attorneys with power and authority to act for it and in Its name in States other than Maryland, and in the Territories of the United Slales and In the Provinces of the Dominion of Canada and In the Colony of Newfoundland. There/ore, be It Resolred, that this Company do, and it hcrehy does, authorize and empower its President or either of its Vice. Presidents In conjunction with its Secretary or one of Ili A-'.etant Secretaries, under Its corporate seal, to appoint any person or persons as atlorney or atiorueysdndact, or agent or agents of said Company, in Its name and s Its act, to execute and deliver any and all con• tracts guaranteeing the fidelity of persons holding positions of public or private trust, guaranteeing the performances of contracts other than Insurance policin and executing or guaranteeing honds and undertakings, required or permitted in all actions or proceedinge, or by law allowed, and , Also, In Its name and as Its attorney or attorneys-in•fact, or agent or agents to execute and guarantee the conditions of any and all bonds, recognizanets, obligations, stipulations, undertakings or anything In the nature of either of the some, which are or may by low, municipal or olherwlce, or by any Statute of the United States or of any State or Temilory of the United Slates or of the Provinces of the Dominion of Canada or of the Colony of Newfoundland, or by the rules, regulations, orders, customs, practice or discretion of any board, body, organization, office or officer, toes], municipal or otherwise, be allowed, required or permlttnd to be executed, made, taken, plven, tendered, accepted, filed or recorded for like security or protection of, by or for any person or persons, corporation, body, office, interest, municipality or other association or organization whatsoever, In any and all capacities whatsover, conditioned for the doing or not doing of anything or any conditions which may be provided for in any such bond, recognizance, obligation, stipulation, or undertaking, or anything In the nature of either of the same, It Miohael P, Hammond ■n Assistant Secretary of the UNITED STATES FIDELITY AND GUARANTY COMPANY, do hereby certify that the foregoing is a full, true and correct copy of the original power of attorney given by said Company to Alfredo Mills of, Houston, Texas aulhorixing and empowering her to sign bonds as therein set forth. Which power of attorney has never been revoked and Is still In full force and effect. And 1 do fnsther Certify that said Power of Attorney was given in pursuance of a resolution adopted at a regular meeting of the Board of Directors of said Company, duly called and held at the office of the Company In the City of Baltimore, nn the 11th day of i July, 1910, at which meeting a quorum of the Board of Directors was present, and that the foregoing Is a true and correct copy of said I}` reaoiullon, and the whole thereof as recorded In the minutes of said meeting, In Testimony Wheeeo/, I have hereunto set my hand and the seal of the UNITED STATES FIDELITY AND GUARANTY , COMPANY on April l6a 1985 1 1 (Data) C ~r Assfstanf S^rrelary, a , t, , r i I 7 i 1 1 I *Vsc - COMPLAINT NOTICE f f i I - 't I, COMPLAINT NOTICEt Should any dispute arise about your E premium or about a claim that you have filed, contact the ager}t or write to the company that issued the policy, bond, ann 1ty contract or certificate. If the problem is not resolved, you may also write the State Department C, 1110 San Jacinto, Austin,BTexas ~78786.~raThis notice of ~ complaint procedure is for information only and does not become a part or condition of this policy, bond, annuity contract or certificate. If you decide to write the comPan answered most rapidly if r your inquiry can be you will write one of these branch } offices: Manager F Fidelity and Guaranty Insurance Underwriters, Inc. P. O. Box 809019 Dallas, TX 75380 i Manager Fidelity and Guaranty Insurance Underwriters, Inc. P. 0. Box 4477 Houston, TX 77210 Manager Fidelity and Guaranty Insurance Underwritera, Inc, 300 Tower Life Building 310 South Saint Mary's Street San Antonio, TX 78205 c. 4 i E. The USF&G Companies• Fidelity and Guaranty Life Insurance Company Fidelity and Guaranty Insurance Underwriters, Inc, j .4 1 } 1 USKU INSURANCE COMPLAINT NOTICE C COMPLAINT NOTICE; Should any dispute arise about your premium or about a claim that you have filed, contact J the agent or write to the company that Issued the policy, bond, annuity contract or certificate. If the problem is not 1 resolved, you may also write the State Board of Insuranco, Department C, 1110 San Jacinto, Austin, Texas 76786. t; This notice of complaint procedure is for Information only and does not become a part or condition of this policy, bond, annuity contract or certificate, If you decide to write to the company, your inquiry can be answered most rapidly if you will write one of these branch offices; r` Manager United States Fidelity and Guaranty Companies P. O. Box 809018 Dallas, TX 75380 „ Manager United Stales Fidelity and Guaranty Companies P. O. Box 4477 Houston. TX 77210 + t '1[ f Manager 1 United States Fidelity and Guaranty Companies 300 Tower Life Building J f 310 South Saint Mary's Slreot } San Antonio, TX 78205 i 1 The USF&G Companies Fidelity and Guaranty Life Insurance Company L Taxm 40 (8 84) 1 5 1 PAYMENT BOND STATE OF TEXAS , COUNTY OF Denton KNOW ALL MEN BY THESE PRESENTS; That Advance Tank-Texas, Inc. of the City of Beaumont County of JeffersonaLnd State of Texas ' ' ' P,r~/ • FAK-LVL C"' EJ ~~IVZGYIY ~C•N t1.tY as PRINCIPAL, and :Y..ta 7~n~~ti Z,,,, Zhr~, as SURETY, authorized under the laws of the State of Texas to act as surety on bonds for principals, arr,, held and firmly bound unto the City of Denton as OWNER, in the penal sum of Four Hundred, Thrity-Three Thousand 1 and No/100 Dollars 433,000.00 ) for the payment whereof, I the sa r nc pa an Surety bind themselves and their heirs, administrators, executors, successors and assigns, jointly and severally, by these presents. WHEREAS, the Principal has entered into a certain written contract with the Owner, dated the 16 day of April 19 85 for the construction of 2.0 MG Ground Storage Tank - Bid No. 9435 which contract is hereby referred to and made a part hereof as fully and to 3 the same extent as if copied at length herein. NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the said Principal shall pay all claimants supplying labor and material him subcontractor then this obligation prosecution shall i be void; otherwise provided said contracts in I to e remain i full force and effect; I PROVIDED, HOWEVER, that this bond is executed pursuant to the provisions of Article 5160 of the Revised Civil Statutes of Texas as amended by acts of the 56th Legislature, Regular Session, 1959, and all liabilities on this bond shall be determined in accordance with 'the provisions of said Article to the same extent as if it were copied at length herein. PROVIDED FURTHER, that if any legal action be filed upon this I: bond, venue shall lie in Denton County, State of Texas. 5 10-15-71 .'78 f 1i Surety, for value received, stipulates and agrees that no change, extension of time, alteration or addition to the terms of the contract, or / to the work performed thereunder, or the plans, specifications or drawings accompanying the same, shall in anywise affect its obligation on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the contract, or to the work to be ti performed thereunder. IN WITNESS WHEREOF, the said Principa) and Surety have signed and sealed this instrument this 1~_ day of t1Qi 19 85 Y Advance Tank-Texas, Inc. t ck Cl/nl r nc pa _11 e, ty By By Title cE ~Pf5/ Title_ ZTo%'Nt1~ /N-f4e-7- Address P Gx 7a 7 Addressr 13e) 7 J 4 Au ~~ron>T 7'X. 777~w~,~i~~ 'T>( 7 7 J /h 3 (SEAL) (SEAL) _ k The name and address of the Resident Agent of Surety is; i ` Note; Date of Bond roust not be prior to date of Contract, V f _ eel r 10-15-71 .1 178 CERTIFIED COPY GENERAL POWER OF ATTORNEY NO. FG 36 KNOW ALL MEN BY THESE PRESENTS: That FIDELITY AND GUARANTY INSURANCE UNDERWRITERS, under the laws of the State of Ohio, and having Its principal office at 100 Light Streert, Baltimlorc, Maryland 21203,1(foes s 1 hereby constitute and appoint E. L. Purcell, Jr., Alfreda Mills and Edward Arens of the City of Houston State of Texts x Its true and lawful Attomeyain-Fact, with power and authority to sign its name as surety to, and to execute se.l o and deliver any and all bonds, undertakings, recognlzances or other wrirren obligations In the nature flicm-of; and ilia l said FIDELITY AND GUARANTY INSURANCE UNDERWRITERS, INC. hereby ratifies and confirms all of file acts of snid Allorney-in•fact, pursuant to these premises. This appointment Is made under and by authority of a by-law of the said FIDELITY AND GIJARANI'Y INSURANCE UNDERWRITERS, INC., a certified copy of which is hereto annexed and made a part of this Power of A tutncy• IN WITNESS WHEREOF, the said FIDELITY AND GUARANTY INSURANCE UNDPRWR1117,16, INC. has z caused this instrument to be scaled with its corporate seal, duly arrested by the signatures of its Vice-President and Assistant t Secretary, this 29th day of January 19 85 . I FIDELITY AND GUARAN'T'Y INSURANCE UNDERWRITERS, INC. ` r (Signed) BY Vlrnf'rrs/dtuL ' f 11 Y (SEAL) (Signed) J, J, Caoser7. ~JJIfrYnl SIIYNnrv( STATE OF MARYLAND ) ss' BALTIMORE CITY ) { On this 29th day of January 19 85, before me personally came Raley, Jr. , INSURANCE UNDERWRITERS, INC. and J. J. Casserly Vice President of PIDLiLITY AND GUARANTY Secretary of Bald Corporation, with both of whom I am personally acquainted, who being by Inc severally sworn, soldsthat they, the sald J. % Raley, Jr, and J. J. Casserl.y t were respectively the Vice President and Assistant Secretary of the said FIDELITY AND GUARANTY INSURANCE UNDERWRITERS, INC., the corporation described In and which executed the foregoing Power of Attorney; That they each f ! knew the seal of said eorporntion; that the seal affixed to said power of Attorney was such corporate seal; Ihal it was so affixed by authority of the by-laws of said corporation; and that they signed their names hereto by like authority as Vice President and Assistant Secretary, respectively, of ilia Corporation. My Commission expires the first clay of July, i9 86, (SEAL) (Signed)Margaret bf. Htzrrtt NOTARY PUBLIC FS 8119.0 Copy of By-Law "Article VI, Section 7 • Execution of Instruments. The Chairman of the Board, the. Presidenl, any Executive Vice President, any Vice President, including the financial Vice President, or any Assistant Vice President, in conjunction with (lie Secretary or an Assistant Secretary, shall have / power on behalf of the Company: (a) to execute, acknowledge, verify and deliver all contracts, obligation, in- stntmenls and documents whatsoever in connection with its business, including, without limiting the foregoing, any and all bonds, guarantees, undertakings, recognizanees, stipulations, policies of insurance, deeds, mortgages, re. leases, satisfactions and agency agreements; i (b) to appoint one or more persons for any or all of the , u mes mentioned in file preceding paragraph (a), Including affixing the seal of Compgriv," h f, Michael P. Harnniond an Assistant Secretary of FIDELITY AND GUARANTY INSURANCE UNDERWRITERS, INC., do hereby certify that the foregoing is a full, true and co rcel copy of the original power of attorney given by sold Company to E. L. Purcell, Jr. , Alfreda Mills j and Edward Arens of Hottaton, Texas authorizing and empowering them to sign bonds as therein set forth, which power of attorney has never been revoked and is still in full force and effect, And I do furlhcr certify that said Power of Attorney was given in pursuance of a by-law of said Company, and that the foregoing is a'true and correct copy of said by-law. i In Testimony Whereof, I have hereunto set my hand and the seal of FIDELITY AND GUARANTY INSURANCE UN- DtiRWitITL'RS, ENC. this lb day of April '19 45 Xf ..1..a'1,••••J11, 11111'1` A.ssisYanl Secretary. r , i I f j CERTIFIED COPY I) GENERAL POWER OF ATTORNEY No........ 75048 Know all Neat by there Preaentet That UNITED STATES FIDELITY AND GUARANTY COMPANY, a curporatiou organized and e.xiettng under the lade of the State of Maryland, and having fie principal office at the City of Baltimore, in the State of Maryland, Boca hereby constitute and appoint Alfroda Mills k of the City of Houston State of Texas Its true and lawful attorney X~tW J9t*X7S1F1pXXAX for the following purposes, to Witt To sign its name as surety to, and to execute, seal and acknowledge any and all bonds, and to respectively do and perform any and all acts and things set forth In the resolution of the Board of Directors of the sold UNITED STATES FIDELITY AND GUARANTY COMPANY, a certified copy of which is hereto annexed and made a part of this Power of Attorney; and the said UNITED STATES FIDELITY AND GUARANTY COMPANY, through us, Its Board of Directors, hereby ratifies and confirms aril and whatsoever the sold ' Alfreda Mills q may lawfully do in the premises by virtue of them -ro"ats. In Witness Wyereol, the said UNITEI STATES FIDELITY AND GUARANTY COMPANY has caused this instrument to be sealed with Its corporate acted, duly attested by .,+e signatures of Its Vice-Yreoldent and Assistant Secretary, this 25111, day of October A. D. 1982 UNITED STATES FIDELITY AND GUARANTY COMPANY. (Signed) By,,,...Nolrnes (S~+) Yke.Yraaldent. (Signed) E ,lY .puffin t STATE OF MARYLAND, ) Rttutont Sauetary, BALTIMORE CITY, 1} got t on this 2511111 day of October A. D, 1982, before me personally come + I A. C. Holmes Vice-President of the UNITED STATES FIDELITY AND GUARANTY COMPANY and E. W. Buffington whom I am personally acquainted, who being by we severaby duly sworn, told that they resided In the City of Baltimor,vMasylandl that they, the said A. C. Holmes and M. 4V. Buffin ton ills Vice-President and the Assistant Secretary of the said UNITED STATES FIDELITY AlD GUARANTY COMPANY, ~cor. poration deictibed In sod which executed the foregoing Power of Attorney; that they each knew the seal of said corporalionl that the seal affixed to said Power of Attorney was such corporate seal, that It was so fixed by order of the Board of Directors of sold corpora, flan, and that they olgeted their names thereto by 11ke order as Vice-president and Assistant Secretary, respectively, of the Company. My commiulon expires the Ent tbmcW*9xAxf2ibS xx.xxx Monday in Mayt A . D , 1983, ~ (SEAT,) (Signed} ~ At1ne.Xo.,Q;#rtoto...... r STATE OF MARYLAND 1 Notary Pubrk, BALTIMORE CITY, I' James F. Carney Clerk of the Superior Court of Baltimore City, whleh Court is a Court of Record, and has a seal, do hereby certify that whom the sauteed a~tdavits were made, end who has thereto subscribed his name, wue of rho time onto doing a Notary Public ofEthe State of Maryland, in sad for the City of Baltimore, duly commissioned and sworn and authorized by law to administer oaths and take acknowledgments, or proof of deeds to be recorded therein, I further certify that f am acquainted with the handwriting of the ssld Notary, and verily believe the signature to be his genuine signature, Ls Testimony Whereof, I hereto get my hand and affix the seal of the Superior Court of Baltimore City, the goats being a Court of Record, this 881y day of October , A. D, 19 82 (SEAL) (Signed) dRmi. F',•,,.Ci#?rnPy Fg 9 to.srt Clerk of the Superior Court of Baltimore City, 'ate' COPY OF RESOLUTION Thar Whereas, it is neceteary for the effectual transaction of business that this Company appoint agents and attorneys with power and authority to act for it and In Its name In $talc$ other than Marytand, and In the Territories of the United Slates and In the Provinces of the Dominion of Canada and in the Colony of Newfoundland. Therefore, be iz Resolved, that this Company do, and It hereby does, authorize and empower its President or either of Its Vice Presidents In conjunction with Its Secretary or one of its Assistant Secretaries, under Its corporate seal, to ap or any as attorney or attorneys-In-fact, or o ent o t, person 6 r agents of said Company, in its name and as its act, to execute and deliver any y and all con, Iracls guaranteeing the fidelity of persons holding poaftions of public or private trust, guaranteeing the performances of contracts other than insurance pollcles and executing or guaranteeing bonds and undertakings, required or permitted in all actions or proceedings, or by law allowed, and Alm, In Its memo and as its attorney or attorneys-ln•fact, or agent or agents to execute and guarantee the conditions of any and all bonds, recognirances, obligations, stipulations, undertakings or anything In the nature of either of the same, which are or may by law, municipal or otherwise, or by any Statute of the United Slates or of any Stale or Territory of the United States or of the Provinces of the Dominion of Canada or of the Colony of Newfoundland, or by the rules, regulations, orders, customs, practice or discretion of any board, body, organization, office or officer, local, municipal or otherwise, be allowed, required or permitted to be executed, made, taken, glven, tendered, accepted, filed or recorded for he security or protection of, by or for any person or persons, corporation, body, office, interest, municipality or other associadon or organization what"e er, in any and ell capacities whatsover, conditioned for the doing or not doing of anytMng or any conditions which may be provided for In any such bond, recogntzance, obligation, stipulation, or undertaking, or anything In the nature of either of the same, 4 Michael P, Hammond 1 GUARANTY COMPANY, do hereby certify that the foregoing is it full, true and correct copy of helori8 power d power FIbEWTY AND by said Company to Al freda Mills of attorney given °f Houston s Texas autheriring and empowering j forth, which power of attorney has never been revoked and Is still In full force and effect. her o sign bonds as therein set 1 Power torn 1 Board ofnDisco orsnofosaldrtCompany, duly called and held at the office ofutheaCompany resolution ohe i City adopted tBaltimore, regular g day the lull, 1410, At which meeting a quoutn of he Board of Dlrectors was present, and that the foregoing is a true and correct vpy of said t teeolotion, and the whole thereof as recorded In the minutes of sold meeting, In Teallntonr Whereo/, I have hereunto set my hand and the seal of the UNITED STATES FIDELITY AND GUARANTY COMPANY or, April 16, 1985 (Date) 1 f t 'I T!/r i1C•~w~+'~11 `faatstant Secretary. f t ,If i { 1 1 COMPLAINT NOTICE COMPLAINT NOTICE& Should any dispute arise about your premium or about a claim that you have filed, contact the agent or write to the company that issued the policy, bond, annuity contract or certificate. If the problem is not " resolved, you may also write the State Board of Insurance, - Department C, 1110 San Jacinto, Austin, Texas 78786. This notice of complaint procedure is for information only and does not become a part or condition of this policy, bond, annuity contract or certificate. if you decide to write the company, your inquiry can be answered most rapidly if you will write one of these branch officest Manager Fidelity and Guaranty Insurance Underwriters, Inc. P. 0. Box 809019 y Dallas, TX 75380 { Manager Fidelity and Guaranty Insurance Underwriters, Inc. P. 0. Box 4477 Houston, TX 77210 Manager Fidelity and Guaranty Insurance Underwriters, Inc. 300 Tower Life Building 310 South Saint Mary's Street San Antonio, TX 78205 k • 1 C The USF&G Companies Fidelity and Guaranty Life Insurance Company Fidelity and Guaranty Insurance Underwriters, Inc. Tom 40 i t r r r U Min SMU INSURANCE COMPLAINT NOTICE l COMPLAINT NOTICE: Should any dispute arise about your premium or about a claim that you have filed, contact the agent or write to the company that issued the policy, bond, annuity conlract or certificate. II the problem is not J resolved, you may also write the State Board of Insurance, Department C, 1110 San Jacinto, Austin, Texas 78788. I This notice of complaint procedure Is for information only and does not become a part or condition of this policy, t ; bond, annuity contract or certificate. ' If you decide to write to the company, your inquiry can be answered most rapidly if you will writo one of these branch offices: Manager I f United States Fidelity and Guaranty Companies P. 0. Box 809019 Dallas, TX 75380 Manager United States Fidelity and Guaranty Companies P. 0. Box 4477 Houston, TX 77210 Manager United States Fidelity and Guaranty Companies 300 Tower Life Building 310 South Saint Mary's Street San Antonio, TX 78205 r i i t The USF&G Companies Fidelity and Guaranty Life Insurance Company Tin es 40 (9.94) y` CITY OF DENTON INSURANCE MINIMUM REQUIREMENTS J Without limiting any of the other obligations or liabilities of the I Contractor, the Contractor shall provide and maintain until the work is completed and accepted by the City of Denton, owner, ' minimum insurance coverage as follows; l 1 1 TYPE OF COVERAGE LIMITS OF LIABILITY I. WORKMEN'S COMPENSATION STATUTORY 11. COMPREHENSIVE GENERAL LIABILITY i Bodily Injury $300,000 $1,000,000 Each occurance Aggregate Property Damage $100,000 Each accident III. COMPREHENSIVE AUTOMOBILE LIABILITY Bodily Injury $300,000 $1,000,000 Each person Each accident Property Damage $100,000 Each accident A. In addition to the insurance described above, the Contractor shall obtain at his expense an OWNER'S PROTECTIVE LIABILITY INSURANCE POLICY with the r following limits, BODILY INJURY PROPERTY DAMAGE $300,000 each person $100,000 each accident $300,000 each accident $1,0UU,000 aggregate Covering the work to be performed by the Contractor for the City of Denton. B, The contractor will furnish the Owner's Protective Policy described above and execute the Certificate described on the following page to the City of Denton for its approval. Insurance must be accepted before commencing any work under the contract to which this insurance applies. The City of Denton will be listed on all policies as an additional named insured. #0399c T T -~e CERTIFICATE OF INSURANCE THIS IS TO CERTIFY that the following policies, subject to their terms, conditions and exclusions, have / the company or companies shown below: been issued by THIS CERTIFICATE OF INSURANCE neither affirmatively or negatively amends, extends or alters the coverage afforded by the policy or policies shown below, ,or is it an endorsement making the person, firm or corporation at whose request it is issued an additional insured on the policy or policies referred to herein, In the event of any material change in or cancellation of the policy or policies, the company or companies will mail ten (f0) days' written notice to the party to whom this certificate is addressed, r , NAME AND ADDRESS OF PARTY TO WHOM CERTIFICATE IS ISSUED FDA Cfty of Denton Bid 901-B Texas St, Denton, TX 7b201 ..aCr-r~x,rz,r<,-..~rf ~7~{ r / Attn: John J. Marshall C. P. M. L , Purchasing Agent J i' NAME AND AODREaS OF INSURED; _ r 41 tq~ L.:- ~c r Jl / ~ ! 'J 7 711 4j Imunnce Company Folic Expiration Typo of Ineurancs Policy EffeeNve Number 4 Oslo Data Whit rS OF LIABILITY' Workmands Comoensatfon ~ 08.2.3.2 /T 3 $ 7 I'/_tpe~ starutory Employers Liablbty S Comprehensive - BEmployers Liabllity Limits-$100,000 General l.iabi odily Injury - r VIP doa/S t1 ,_/°kt 8 " 00, 60 0 each Occurrence $ A regale Products D 0 & Coln feted Operations Property Damage $ d 04 Each Occurrence 0 Aggregate Operations S d D O Aggregate Protective S DD Aggregate Cannac tual y $ /DD d0 Nggngete rraucrs Comprehensive /J / & Completed Operations Automotilte Uabftlty" C~r QI l Injury 00 0 6. Each Person 41/ $ $ &)U0QEach Occurrence r Property Damage 1~Mf3REL~ 1~ - $ 1001 do 6 cacti Occwrence M s C} M rc~ 1 _ q, ovd~ and vCCua~c-ti+?. 1(!/~rxov~.- 8.Y_c,s~'~/ 0138 /~'7 7-/ 8~ '7-/-d'S' 1, vtl~; noD AEG'-2~r~Ar~ r:Ab#nce of any appropriate entry meahf no such insurann Ir In force. Covers all owned, non-owned or tetrad vehlcles, NAME AND ADDRESS OF AGENCY ~t,t.FCa-- ~~.r ac.ve-r•.r..4. '""f~•t--~y-4 ~K"~t Ve 2 VG1 i FttoNe wvtsaaa, of Acarrr,T t>~ ~ ~ s Authorized RepreseAl`a,*(ViMstR I)~;1a~Yranc 0 virjbilerred to above, 131-2 1 f - s GENERAL CONDITIONS 7 ARTICLE 1 - DEFINITIONS Wherever used in these General Conditions or in the other Contract I~ Documents, the following terms have the meanings indicated which are Nk% applicable to both the singular and plural thereof; Addendum (Addenda) - A supplement to the Contract Documents issued in writing prior to the receipt of bids, Agreement - The written Agreement between OWNER and CONTRACTOR covering the Work to be performed, Application for Payment -The form furnished by ENGINEER which is to be used by CONTRACTOR in requesting progress payments and which is to 1 include the schedule of values required by paragraph 14.1 and an af- fidavit of CONTRACTOR that progress payments theretofore received on account of the Work have been applied by CONTRACTOR to discharge in full all of CONTRACTOR's obligations reflected in prior Applications for Payment and that all materials and work included in the application for payment conform to the requirements of the Contract Documents, Bid - The offer or proposal of the Bidder submitted on the prescribed form setting forth the prices for the Work to be performed, I Bidder - Any person, firm or corporation submitting a Bid for the Work. Bonds - Bid, performance, pay,nent, maintenance bonds and other instru- ments of security, furnished by CONTRACTOR and his surety in accordance with the Contract Documents. Calendar Day - A calendar day of twenty-four hours measured from mid- night to the next midnight and is any day of the week, no days being . excepted. Contract Amendment - A written agreement signed by both parties altering the terms of the General Conditions and/or the Supplementary Conditions. Change Order - A written order to CONTRACTOR signed by OWNER authorizing an addition, deletion or revision in the Work, or an adjustment in the A Contract Price or the Contract Time, issued after execution of the Agreement, Contract Documents - The Agreement, Addenda, Invitation for Bids, In- structions to Bidders, CONTRACTOR's Bid, the Bonds, the Notice of Award, these General Conditions, the Supplementary Conditions, the Specifi- cations, Drawings and Modifications, F&N-78 GC-l i Contract Price - The total moneys payable to CONTRACTOR under the Contract Documents, Contract Time - The number of days stated in the Agreement for the com- pletion of the Work, computed as provided lo paragraph 17,2 CONTRACTOR - The person, firm or corporation with whom OWNER has executed the Agreement. Drawings - The drawings which show the character and scope of the Work to be performed and which have been prepared or approved by ENGINEER E.' and accepted by Owner and are referred to in the Contract Documents except shop drawings as required by the Contract Documents. ENGINEER - The person, firm or corporation named as such in the Agreement. 2` r Field Order - A written order issued by ENGINEER which clarifies or interprets the Contract Documents in accordance with paragraph 9.3 or " orders minor changes in the Work in accordance with paragraph 10.2. Modification - (a) Contract Amendment; (b) Change Order; (c) Field Order, Notice of Award - A written notice by OWNER to the apparent successful Bidder stating that upon compliance with the conditions precedent to be fulfilled by him within the time specified, OWNER will execute and deliver the Agreement to him. Notice to Proceed - A written notice given by OWNER to CONTRACTOR. (with a copy to ENGINEER) fixing the date on which the Contract Time will commence to run and on which CONTRACTOR shall start i:o perform his obli- gations under the Contract Documents. OWNER - A public body or authority, corporation, association, partner- ship, or individual for whom the Work is to be performed. Project - The entire construction to be performed as provided in the ( r Contract Documents. i Resident Project Representative - The authorized representative of ENGI- NEER who is assigned to the Project site or any part thereof. Shop Drawings - All drawings, diagrams, illustrations, brochures, schedules and other data which are prepared by CONTRACTOR, a Subcontractor, manu- facturer, supplier or distributor and which illustrate the equipment, II~ material or some portion of the Work. I f j F&N-78 GC_2 Specifications - Those portions of the Contract Documents consisting of written technical descriptions of materials, equipment, construction systems, standards, procedures and workmanship as applied to the Work, Subcontractor - An individual, firm or corporation having a direct con- tract with CONTRACTOR or with any other Subcontractor for the performance of a part of the Work at the site. Substantial Completion - Certification by ENGINEER that the construction of the Project or a specified part thereof is sufficiently completed, in accordance with the Contract Documents, so that the Project or specified part can be utilized for the purposes for which it was in- tended pursuant to the provisions of Paragraph 14.7, 14.9; or if there be no such certification, the date when final payment is due in ac- cordance with Paragraph 14.12. 1 Supplementary Conditions - A portion of the Contract Documents which 1 modifies the General Conditions by making additions, clarifications and/or deletions. In cases of conflict between the Supplementary Conditions and the General Conditions, the Supplementary Conditions shall have precedence over the General Conditions. Work - Any and all obligations, duties and responsibilities necessary to the successful completion of the Project assigned to or undertaken by CONTRACTOR under the Contract Documents, including all labor, materials, equipment and other incidentals, and the furnishing thereof. Working Day - A day not including Saturdays, Sundays or any of the following holidays: New Year, Washington's Birthday, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day and Christmas Day, in which weather or other conditions, not under ~ the control of the CONTRACTOR, will permit construction of the principal units of the work for a period of not less than seven (7) hours between 7;00 A.M. and 6:00 P.M. i ARTICLE 2 - PRELIMINARY MATTERS Execution of Agreement: I 2.1 The Agreement, Conds and such other portions of the Contract Documents as may be required will be executed and delivered by CON- . TRACTOR to OWNER within fifteen (15) days after receipt of the Notice I F of Award. The Owner shall detvnrilne the number of counterparts required. 1 ? The OWNER will execute the counterparts. OWNER, CONTRACTOR and ENGINEER s r a i i' 4• r F&N-7B GC-3 y 1 i shall each receive an executed counterpart of the Contract Documents and additional conformed copies as required, Delivery of Bonds; I , 2,2. When he delivers the executed Agreement to OWNER, CONTRACTOR shall also deliver to OWNER such Bonds as he may be required to furnish In accordance with paragraph 5.1 and 5.4. Copies of Documents. 2.3, OWNER shall furnish to CONTRACTOR up to ten (10) copies (unless otherwise provided in the Supplementary Conditions) of the Contract Documents as are reasonably necessary for the execution of the Work. Additional copies will be furnished, upon request, at the cost of re- production. ! Contractor's Pre-Start Representations; I 2.4. CONTRACTOR represents that he has familiarized himself with, and assumes full responsibility for having familiarized himself with, the nature and extent of the Contract Documents, Work, locality, and with all local conditions and federal, state and local laws, ordinances, i rules and regulations that may in any manner affect performance of the Work, and represents that he has correlated his study and observations with the requirements of the Contract Documents, CONTRACTOR also represents that he has studied all surveys and investigation reports of subsurface and latent physical conditions referred to in the Contract Documents and will make such additional surveys and Investigations as he deems necessary for the performance of the Work at the Contract Price in accordance i with the requirements of the Contract Documents and that he has correlated the results of all such data with the requirements of the Contract Documents, Commencement of Contract Time, Notice to Proceed; R, 2.5. The Contract Time will commence on, and include, the day following the date established in the Notice to Proceed issued by Owner to Contractor. Starting the Project; 2,6. CONTRACTOR sh&11 start to perform his obligations under the Contract Documents on the date when the Contract Time commences to run, No Work shall be done at the site prior to the date on which the Contract f Time commences to run. I M-78 GC-4 m I! i Before Starting Construction: 2.7. Before undertaking the Work, CONTRACTOR shall carefully study and compare the Contract Documents and check and verify pertinent figures shown thereon and all applicable field measurements. He shall at once report in writing to ENGINEER any conflict, error or discrepancy which he may discover. 2,8. Within ten (10) days after delivery of the executed Agree- 2 ment by OWNER to CONTRACTOR, CONTRACTOR shall submit to ENGINEER for f approval, an estimated progress schedule indicating the starting and completion dates of the various stages of the Work, and a preliminary schedule of Shop Drawing submissions. 2.4, When CONTRACTOR delivers the executed Agreements the CONTRACTOR ` shall furnish OWNER and ENGINEER certificates of insurance as required r by Article 5, After delivery of the executed Agreement by OWNER to CONTRACTOR, but before starting the Work at the site, a conference r will be held to review the above schedules, to establish procedures for handling Shop Drawings and other submissions and for processing 1 Applications for Payment, and to establish a working understanding i between the parties as to the Project, Present at the conference will be OWNER or his representative, ENGINEER, Resident Project Representatives, CONTRACTOR and his Superintendent. I ARTICLE 3 - CORRELATION, INTERPRETATION AND INTENT OF CONTRACT DOCUMENTS 3.1. It is the iri~ent of the Specifications and Drawings to de- scribe a complete Project to be constructed in accordance with the Contract Documents. The Contract Documents comprise the entire Aree- ment between OWNER and CONTRACTOR. They may be altered only by a' Mudification. } 3.2, The Contract Documents are complementary; what is called for by one is as binding as if called for by all. If CONTRACTOR finds a conflict, error or discrepancy in the Contract Documents, he shall call it to ENGINEER's attention in writing at once and before pro- ceeding with the Work affected thereby. Any Work that may reasonably be inferred from the Specifications or Drawings as being required to 4 produce the intended result shall be supplied whether or not it is specifically called for. Work, materials or equipment described in words which so applied have a well-known technical or trade meaning shall be deemed to refer to such recognized standards. t ±1 3q)))) 3 ' F&N-78 GC-5 1 r . ARTICLE 4 - AVAILABILITY OF LANDS; PHYSICAL CONDITIONS; REFERENCE POINTS Availability of Lands: 4.1. OWNER shall furnish, as indicated in the Contract documents I and not later than the date when needed by CONTRACTOR, or such later date as set forth in the Contract Documents, the lands upon which the Work is to be done, rights-of-way for access thereto, and such other lands which are designated for the use of CONTRACTOR, Easements for permanent structures or permanent changes in existing facilities will be obtained and paid for by OWNER, unless otherwise specified in the Contract Documents, If CONTRACTOR believes that any delay in OWNER's furnishing these lands or easements entitles him to an extension of the Contract Time, he may make a claim therefor as provided in Article ! 12, CONTRACTOR shall provide for all additional lands and access thereto that may be required for temporary construction facilities or storage of materials and equipment. E Physical Conditions - Surveys and Reports: i, 4,2. Reference is made to the Supplementary Conditions for identi- fication of those surveys and investigation reports of subsurface and latent physical conditions at the Project site or otherwise affecting I performance of the Work which have been relied upon by ENGINEER in preparation of the Drawings and Specifications. The data is for general information and the OWNER and ENGINEER do not guarantee the accuracy. j Unforseen Physical Conditions; E i 4.3. CONTRACTOR shall, within three {3} days after discovery, notify OWNER and ENGINEER in writing of any subsurface or latent physical conditions at the site differing materially from those indicated in the Contract Documents. ENGINEER will investigate those conditions and advise OWNER s t in writing if further surveys or subsurface tests are necessary, Thereafter, Owner shall obtain the necessary additional surveys and tests and furnish j copies to ENGINEER and CONTRACTOR. If ENGINEER finds that the results j, f of such surveys or tests indicate that there are subsurface or latent physical conditions which differ materially from those intended in the Contract Documents, and which could not reasonably have been anticipated ! or discovered by CONTRACTOR through his efforts as represented pursuant to Article 2.4 of these General Conditions, a Change Order may be issued I Incorporating the necessary revisions. Reference Points: J 4.4, OWNER shall provide engineering surveys for construction to 1 establish reference points which in his judgment are necessary to enable f ~j j F&N-78 GC-6 { i i . tJ CONTRACTOR to proceed with the Work. CONTRACTOR shall he respons'lble for surveying and laying out the Work (unless otherwise provided in the Supplementary Conditions), and shall protect and preserve the established reference points and shall make no changes or relocations s without the prior written approval of OWNER, lie shall report to ENGINEER whenever any reference point is lost or destroyed or requires relocation because of necessary changes in grades or locations, CONTRACTOR shall replace and accurately relocate all reference points so lost, destroyed r or moved. ARTICLE 5 - BONDS AND INSURANCE Performance, Payment and Other Bonds: 5.1. CONTRACTOR shall furnish performance and payment Bonds as , security for the faithful performance and payment of all his obligations j under the Contract Documents, These Bonds shall be in amounts at least equal to the Contract Price, and (except as otherwise provided in the ' Supplementary Conditions) in such form as set forth in the Contract Documents and with such corporate sureties as are licensed to conduct business in the state where the Project is located and are named in the current list of "Surety Companies Acceptable on Federal Bonds" as published in the Federal Register by the Audit Staff Bureau of Accounts, U. S, Treasury Department. The performance bond and payment bond shall be extended to include the Correction Period set forth in Article 13.10. 5,2, If the surety on any Bond furnished by CONTRACTOR is declared a bankrupt or becomes insolvent or its right to do business is terminated in any state where any part of the Project is located is revoked CONTRACTOR shall within five (5) days thereafter substitute another Bond and surety, both of which shall be acceptable to OWNER. Contractor's Insurance Requirements: 5.3, CONTRACTOR shall purchase and maintain such insurance as will protect him from claims under workmen's compensation laws, disability benefit laws or other similar employee benefit laws; from claims for damages because of bodily injury, occupational sickness or disease, or death of his employees, and claims insured by usual personal injury liability coverage; from claims for damages because of bodily injury, sickness or disease, or death of any person other than his employees including claims insured by usual personal injury liability coverage; ' and from claims for injury to or destruction of tangible property, in- cluding loss of use resulting therefrom - any or all of which may arise out of or result from CONTRACTOR's operations under the Contract Documents, whether such operations be by himself or by any Subcontractor or anyone `fff! s F&N-78 GC-7 "T, 4 1 J i i directly or indirectly employed by any of them or for whose acts any of them may be legally liable, This insurance shall include the specific coverage and be written for not less than any limits of liability and maximum deductibles specified in the Supplementary Conditions or required by law, whichever is greater, shall include contractual liability insurance and shall include OWNER and ENGINEER as additional insured parties, 4 The Contractor shall maintain such additional insurance as he may deem appropriate. With the execution of the Agreement, CONTRACTOR shall file with OWNER and ENGINEER certificates of such insurance, acceptable to OWNER; these certificates shall contain a provision that the cover- ] < age afforded under the policies will not be cancelled or materially 1 changed until at least fifteen (15) days' prior written notice has been given to OWNER and ENGINEER. i u! Additional Bonds and Insurance; 5.4, Prior to delivery of the executed Agreement by OWNER to CON- TRACTOR, OWNER may require CONTRACTOR to furnish such other Bonds and i such additional insurance, in such form and with such sureties or insurers as OWNER may require. if such other Bonds or such other insurance are specified by written instructions given prior to opening of Bids, the premiums shall be paid by CONTRACTOR; if subsequent thereto, they shall be paid by OWNER (except as otherwise provided in paragraph 6.7), ARTICLE 6 - CONTRACTOR'S RESPONSIBILITIES Supervision and Superintendence; t 6.1. CONTRACTOR shall supervise and direct the Work efficiently with his best skill and attention, He shall be sol-ly responsible for the means, methods, techniques, sequences and proce, res of construction and safety at the site. CONTRACTOR shall be solely responsible to see that the finished Work complies accurately with the Contract Documents. ' CONTRACTOR, ENGINEER and OWNER intend that CONTRACTOR shall be an independent contractor and not the agent or employee of either OWNER or ENGINEER, s 6.2. CONTRACTOR shall keep at the project site at all times during its progress of the work a competent resident superintendent, who shall not pe replaced without written notice to OWNER and ENGINEER except under extraordinary circumstances. The superintendent will be CONTRACTOR's representative at the site and shall have authority to act on behalf of CONTRACTOR. All communications given to the superintendent shall J be as binding as if given to CONTRACTOR. f F&N-18 GC'8 I - r j Labor, Materials and Equipment; 6.3, CONTRACTOR shall provide competent, suitably qualified person- nel to survey and lay out the Work and perform construction as required r by the Contract Documents. de shall at all times maintain good disci- pline and order at the site. 6.4. CONTRACTOR shall furnish all materials, equipment, labor, transportation, construction equipment and machinery, tools, ap- pliances fuel, power, light, heat, telephone, water and sanitary facilities and all other facilities and incidentals necessary for the ' execution, testing, initial operation and completion of the Work. 6.5. All materials and equipment which is to be incorporated into the Project shall be new, except as otherwise provided in the Contract Documents. If required by ENGINEER, CONTRACTOR shall furnish satisfactory evidence as to the kind and quality of materials and equip- ment. 6.6. All materials and equipment shall be applied, installed, connected, erected, used, cleaned and conditioned in accordance with I the instructions of the applicable manufacturer, fabricator or pro- cessors, except as otherwise provided in the Contract Documents. The CONTRACTOR shall furnish the OWNER with four (4) sets of all operating instructions, maintenance manuals and parts list for all mechanical ` and electrical equipment furnished for the project. Substitute Materials or Equipment, 6.7. If the Specifications, law, ordinance or applicable rules or regulations permit CONTRACTOR to furnish or use a substitute that is equal to any material or equipment specified, and if CONTRACTOR wishes to furnish or use a proposed substitute, he shall, prior to the conference called for by paragraph 2.9, make written application to ENGINEER for approval of such a substitute certifying in writing that the proposed substitute will perform adequately the functions called for by the general design, be similar and of equal substance to that specified and be suited to the same use and capable of per- forming the same function as that specified; and identifying all vari- ations of the proposed substiute from that specified and indicating r available maintenance service. No substitute shall be ordered or in- stalled without the written approval of ENGINEER who will be the judge of equality and many require CONTRACTOR to furnish such other data about the proposed substitute as he considers pertinent. No substitute shall be ordered or installed without such performance guarantee and ` bonds as OWNER may require which shall be furnished at CONTRACTOR's expense. F&N-7B GC-9 r 1 5 r` I 1 ' 1 1 M I Concerning Subcontractors; 6.8, CONTRACTOR shall not employ any Subcontractor or other person or organization (including those who are to furnish the principal items of materials or equipment), whether initially or as a substitute, against whom OWNER may have reasonable objection. Acceptance of any Subcontractor, other person or organization by OWNER shall not constitute a waiver of any right of OWNER to reject defective Work or Work not in conformance with the Contract Documents. If OWNER after due investigation has reasonable objection to any Subcontractor, other person or organization proposed by CONTRACTOR, CONTRACTOR shall submit an acceptable substitute. CONTRACTOR shall not be required to employ any Subcontractor, other parson or organization against whom he has reasonable objection, CONTRACTOR shall not without the consent of OWNER make any substitution for any Subcontractor, other person or organization who has been accepted by OWNER, 6.9. CONTRACTOR shall be fully responsible for all acts and omis- sions of his Subcontractors and of persons and organizations directly or indirectly employed by them and of persons and organizations for whose acts any of them may be liable to the same extent that he is responsible for the acts and omissions of persons directly employed by him. Nothing in the Contract Documents shall create any contractual relationship be- tween OWNER or ENGINEER and any Subcontractor or other person or organization having a direct contract with CONTRACTOR, nor shall it create any obligation on the part of OWNER or ENGINEER to pay or to see to th^ payment of any i moneys due any Subcontractor or other person or organization, except as may otherwis3 be required by law. OWNER or ENGINEER may furnish to any Subcontractor or other person or organization, to the extent practicable, evidence of amounts paid to CONTRACTOR on account of specific Work done i in accordance with the schedule of values, 6.10. The divisions and sections of the Specifications and the identifications of any Drawings shall not control CONTRACTOR in dividing the Work among Subcontractors or delineating the Work to be performed by any specific trade. 6.11. CONTRACTOR agrees to bind specifically every Subcontractor ~ to the applicable terms and conditions of the Contract Documents for the benefit of OWNER. Patent Fees and Royalties; 1 6.12. CONTRACTOR shall pay all license fees and royalties and assume all costs incident to the use in the performance of the Work and the completed Project of any invention, design, process, product or device which is the subject of patent rights or copyrights held by others, i F&N-78 GC-10 1 1 I 1 T ~Y9 CONTRACTOR shall indemnify and hold harmless OWNER and ENGINEER and anyone directly or indirectly employed by either of them from and against all claims, damages, losses and expenses (including attorneys fees) arising out of any infringement of patent rights or copyrights incident to the 1 use in the performance of the Work or resulting from the incorporation _S in the Work of any invention, design, process, product or device and shall defend all such claims in connection with any alleged infringement of such rights. 6.13. CONTRACTOR shall obtain and pay for all construction permits and licenses and shall pay all governmental charges and inspection fees necessary for the prosecution of the Work, which are applicable at the time of his Bid. OWNER shall assist CONTRACTOR, when necessary, in obtaining ! a such permits and licenses. CONTRACTOR shall pay all public utility charges. Laws and Regulations: 6.14. CONTRACTOR shall give all notices and comply with all laws, ordinc,ices, rules and regulations applicable to the Work. If CONTRACTOR observes that the Specifications or, Drawings are at variance therewith, he shall give ENGINEER prompt written notice thereof, and any necessary i changes shall be adjusted by an appropriate Modification. If CONTRACTOR 1 performs any Work contrary to such laws, ordinances, rules and regulations, and without such notice to ENGINEER, he shall bear all costs arising therefrom, Taxes: 6.15. CONTRACTOR shall pay all sales, consumer, use and other similar taxes required to be paid by him in accordance with the law of the place where the Work is to be performed. M Use of Premises: 6,16. CONTRACTOR shall confine his equipment, the storage of materials and equipment and the operations of his workmen to areas permitted by law, ordinances, permits, or the requirements of the Contract Documents, and shall not unreasonably encumber the premises with materials or equipment. s' 6.17. CONTRACTOR shall not load nor permit any part of any structure to be loaded with weights that will endanger the structure, nor shall he subject any part of the Work to stresses or pressures that will endanger j it. s Record Drawings: , 6,18, CONTRACTOR shall keep one record copy of all Specifications, Drawings, Addenda, Modifications, and Shop Drawings at the site in good ery ~i tl .H F&N-78 GC-11 s, 1 . r S , 1 order and annotated to show all changes made during the construction process, These shall be available to ENGINEER and shall be delivered to him for OWNER upon completion of the Project, Safety and Protection: 6.19. CONTRACTOR shall be responsible for initiating, maintaining , and supervising all safety precautions and programs in connection with the Work. He shall take all necessary precautions for the safety of, and shall provide the necessar or loss to: Y protection to prevent damage, injury 6.19.1. all employees on the Project site and other persons who may be affected thereby, i 6,19.2. all the Work and all materials or equipment to be incorporated therein, whether in storage on or off the site, and 619,3. other property at the site or adjacent thereto, including, but not limited to, trees, shrubs, lawns, walks, pave- ;j meats, roadways, structures and utilities not designated for removal, relocation or replacement in the course of construction. CONTRACTOR shall comply with all applicable laws, ordinances, rules, I regulations and orders of any public body having jurisdiction for the safety of persons or property or to protect them from damage, injury or loss, He shall erect and maintain, as required by the conditions and progress of the Work, all necessary safeguards for its safety and { protection. He shall notify owners of adjacent utilities when prosecution of the Work may affect them. All damage, injury or loss to any property referred to in paragraph 6,19,2 or 6,19,3 caused, directly or indirectly, in whole or in hart, by CONTRACTOR, any Subcontractor or anyone directly rw or indirectly employed by any of them or anyone for whose acts any ' of them may be liable, shall be remedied by CONTRACTOR, CONTRACTOR's duties and responsibilities for the safety and protection of the Work shall continue until such time as all the Work is completed and ENGINEER has issued a notice to OWNER and CONTRACTOR in accordance with paragraph 14.12 that Work is acceptable. Emergencies: 6,20, In any emergency affecting the safety of persons or property, the CONTRACTOR shall act, at his discretion, to prevent threatened damage, injury or loss, Any additional compensation or extension of time claimed b.y the Contractor on account of emergency work shall be determined as provided in Article 11 and 12 for Changes in the Work. F&N-78 GC-12 j' I M 1 i 3 1 ' Shop Drawings and Samples; 6.21. After checking and verifying all field measurements, CONTRACTOR shall submit to ENGINEER for approval, in accordance with the accepted schedule of Shop Drawing submissions (see paragraph 2.8) five copies (or at ENGINEER's option, one reproducible copy) of all Shop Drawings, which shall have been checked by and stamped with the approval of CONTRACTOR and identified as ENGINEER may rEquire. The data shown on the Shop Drawings III will be complete with respect to dimensions, design criteria, materials of construction and the like to enable ENGINEER to review the information as required. 1 6.22. CONTRACTOR shall also submit to ENGINEER for approval with such promptness as to cause no delay in Work, all samples required by F the Contract Documents. All samples will have been checked by and stamped with the approval of CONTRACTOR, identified clearly as to material, manu- facturer, any pertinent, catalog numbers and the use for which intended, J 6.23. At the time of each submission, CONTRACTOR shall in writing j call ENGINEER's attention to any deviations that the Shop Drawings or ] sample may have from the requirements of the Contract Documents. 6.24. ENGINEER will review and approve with reasonable promptness Shop Drawings and samples, but his review and approval shall be only for conformance with the design concept of the Project and for compliance with the information given in the Contract Documents, The approval of a separate item as such will rcot indicate approval of the assembly in which the item functions. CONTRACTOR shall make any corrections required I by ENGINEER and shall return the required number of corrected copies of Shop Drawings and resubmit new samples until approved, CONTRACTOR shall direct specific attention in writing to revisions other than the corrections called for by ENGINEER on previous submissions. CONTRACTOR's stamp of approval on any Shop Drawing or sample shall constitute a repre- I, sentation to OWNER and ENGINEER that CONTRACTOR has either determined I, and verified all quantities, dimensions, field construction criteria, materials, catalog numbers, and similar data or he assumes full responsibility for doing so, and that he has reviewed or coordinated each Shop Drawing or sample with the requirements of the Work and the Contract Documents. 6,25. Where a Shop Drawing or sample submission is required by + the Specifications, no related Work shall be commenced until the submission 1 has been approved by ENGINEER. A copy of each approved Shop Drawing i r and each approved sample shall he kept in good order by CONTRACTOR at 1 ` 0e site and shall be available to ENGINEER. { a F&N-7b GC-13 a tl t; I I I i 6.23, ENGINEER's approval of Shop Drawings or samples shall not relieve CONTRACTOR from his responsibility for any deviations from the requirements of the Contract Documents unless CONTRACTOR has in writing called ENGINEM 's attention to such deviation at the time of submission and ENGINEER has given written approval to the specific deviation, nor shall any approval by ENGINEER relieve CONTRACTOR from responsibility for errors or ommissions in the Shop Drawings, Cleaning: t~ 6,27, CONTRACTOR shall keep the premises free from accumulations of waste materials, rubbish and other debris resulting from the Work, J and at the completion of the Work he shall remove all waste materials, rubbish and debris from and about the premises as well as all tools, construction equipment and machinery, and surplus materials, and shall leave the site clean and ready for occupancy by OWNER. CONTRACTOR shall restore to their original condition those portions of the site not designated for alteration by the Contract Documents. Indemnification: 6.28. CONTRACTOR shall indemnify and hold harmless OWNER and ENGINEER and their agents and employees from and against all claims, damages, losses and expenses including, but not limited to, attorneys' fees arising out of or resulting from any act, omission or defect connected with the performance of the Work, provided that such claim, damage, loss or expense (a) is attributable to bodily injury, sickness, disease or death, or to iniury to or destruction of tangible property (other than the Work itself) ,to the loss of use resulting therefrom and (b) is caused in whole or in part or materials, act or omission of CONTRACTOR/ any Subcontractor, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable, regardless of wheth,.r or not is caused I in part negligently or otherwise, by a party indemnified hereunder. 6.29. In any and all claims against OWNER or ENGINEER or any of their agents or employees by any employee of CONTRACTOR, any Sub- contractor, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable, the indemnification obligation under paragraph 6.28 shall not be limited in any way by any limitation on the amount or type of damages, compensation or benefits payable by or for CONTRACTOR or any Subcontractor under workmen's cum- i pensation acts, disability benefit acts or other employee benefit acts. j I F&N - 78 GC-14 i a o r.. 1 4 y ARTICLE 7 - WORK BY OTHERS 7.1. OWNER may perform additional work related to the Project fff by himself, or he may let other direct contracts. CONTRACTOR shall afford the other contractors who are parties to such direct contracts (or OWNER, if he is performing the additional work himself), reasonable opportunity for the introduction and storage of materials and equip- ment and the execution of work, and shall properly connect and co- ordinate his Work with theirs. 7.2. If any part of CONTRACTOR's Work depends for proper execution or result upon the work of any such other contractor (or OWNER), CONTRACTOR shall inspect and promptly report to ENGINEER in writing any defects or deficiencies in such work that render it un- suitable for such proper execution and result. His failure so to report [ shall constitute an acceptance of the other work as fit and proper for the relationship of his Work except as to defects and deficiencies which may appear in the other work after the execution of his Work. 7.3. CONTRACTOR shall do all cutting, fitting and patching of his Work that may be required to make its several parts come together properly and fit it to receive or be received by such other work. CONTRACTOR shall not endanger an work of others exca- vating or otherwise altering their work and will only ucutnor alter their work with the written consent of ENGINEER and of the other con- tractors whose work will be affected. 7.4. If the performance of additional work by other contractors or OWNER is not noted in the Contract Documents prior to the execution of the Agreement, notice thereof shall be given to CONTRACTOR prior to starting any such additional work. ? i ARTICLE 8 - OWNER'S RESPONSIBILITIES 8.1. OWNER shall issue all communications to CONTRACTOR through ENGINEER. 8.2. In case of termination of the employment of ENGINEER, OWNER shall appoint an engineer against whom CONTRACTOR makes no unreason- able objection, whose status under the Contract Documents shall be that of the former ENGINEER. Any dispute in connection with such ap- pointment shall be subject to arbitration. 8.3. OWNER shall furnish the data required of him under the Contract Documents promptly and shall make payments to CONTRACTOR promptly after they are due as provided in paragraphs 14,4 and 14.12. e' s E8N-78 GC-15 'i i . 'SSA. . i i 8.4. OWNER's duties in respect of providing lands and easements and providing engineering surveys to establish reference points are set forth in paragraphs 4.1 and 4.4. Paragraph 4.2 refers to OWNER's identifying i and making available to CONTRACTOR copies of surveys and investigation reports of subsurface and latent physical conditions at the site or other- wise affecting performance of the Work which have been relied upon by ENGINEER in preparing the Drawings and Specifications. 8.5. OWNER's responsibility in respect of certain inspections, tests and approvals is set forth in paragraph 13.2. `i 8.6. In connection with OWNER's right to stop Work or suspend Work, see paragraphs 13.8 and 15.1. Paragraph 15.2 deals with OWNER's right E to terminate services of CONTRACTOR under certain circumstances. i ARTICLE 9 - ENGINEER'S STATUS DURING CONSTRUCTION I Owner's Representative: 9.1. ENGINEER will be OWNER's representative during the construction period unless the OWNER advises the CONTRACTOR of other arrangements. The duties and responsibilities and the limitations of authority of ENGINEER I as OWNER's representative during construction are set forth in Articles 1 through 17 of these General Conditions and shall not be extended without written consent of OWNER and ENGINEER. j e Visits to Site; j 9.3. The ENGINEER will make visits to the site to familiarize himself generally with the progress and quality of the Work and to determine in general if the Work is proceeding in accordance with the Contract Documents. On the basis of his on-site observations as an ENGINEER, j he will keep the OWNER informed of the progress of the Work, and will endeavor to guard the OWNER against defects and deficiencies in the Work of the CONTRACTOR. The ENGINEER will not be required to make exhaustive or continuous on-site inspections to check the quality or quantity of M the Work. Clarifications and Interpretations; 9.3. ENGINEER will issue with reasonable promptness such written clarifications or interpretations of the Contract Documents (in the form of Drawings or otherwise as he may determine necessary, which shall ~ be consistent with or reasonably inferable from the overall intent of ? the Contract Documents. If CONTRACTOR believes that a written clarification j F&N-78 GC-16 1 • j 1 , r 1 •i i i and interpretation entitles him to an increase in the Contract Price, he may make a claim therefor as provided in Article 11. Rejecting Defective Work: I 9.4. ENGINEER will have authority to disapprove or reject Work which is "defective" (which term is hereinafter used to describe Work y that is unsatisfactory, faulty or defective, or does not conform to the requirements of the Contract Documents or does not meet the requirements of the Contract Documents or does not meet the requirements of any in spection, test or approval referred to in paragraph 13.2 or has been 1 ` damaged prior to approval of final payment). He will also have authority to require special inspection or testing of the Work as provided in para- graph 13.7, whether or not the Work is fabricated, installed or completed. Shop Drawings, Change Orders and Payments: ' 9.5. In connection with ENGINEER 's responsibility for Shop Drawings ! and samples, see paragraphs 6.21 through 6.26 inclusive. t 9.6. In connection with ENGINEER's responsibility for Change Orders, see Articles 10, 11 and 12. 9.7. In connection with ENGINEER's responsibilities in respect of Applications for Payment, etc., see Article 14. Resident Project Representatives: 9.8. If OWNER and ENGINEER agree, ENGINEER will furnish a Resident Project Representative and assistants to assist ENGINEER in carrying out his responsibilites at the site. The duties, responsibilities and limitations of authority of any such Resident Project Pepresentative and assistants shall be as set forth in the Supplemental Conditions. Decisions on Disagreements: 9.9. ENGINEER will be the interpreter of the requirements of the Contract Documents and the judge of the performance thereunder. In his capacity as interpreter and judge ENGINEER will exercise his best efforts to insure faithful performance by both OWNER and CONTRACTOR. ENGINEER will not show partiality to either and will not be liable for the result of any interpretation or decision renderer in good faith. Claims, disputes and other matters relating to the execution and progress of the Work or the interpretation of or performance under the Contract Documents . FAN-78 GC-17 1 1 i shall be referred to ENGINEER for decision; which he will render in wr,l.,ing within a reasonable time. ' 9.10. Either OWNER or CONTRACTOR may demand arbitration with ' respect to any such claim, dispute or other matter that has been re- ferred to ENGINEER, except any which have been waived by the making or acceptance of final payment as provided in paragraph 14,15, such arbitration to be in accordance with Article 16, However, no demand for arbitration of any such claim, dispute or other matter shall be made until the earlier of (a) the date on which ENGINEER has rendered his decision or (b) the tenth (10th) day after the parties have presented their evidence to ENGINEER if he has not rendered his written decision before that date. No demand for arbitration shall be made later than s thirty (30) days after the date on which ENGINEER rendered his written decision in respect of the claim, dispute or other matter as to which arbitration is sought; and the failure to demand arbitration within ' said thirty (30) days' period shall result in ENGINEER's decision being final and binding upon OWNER and CONTRACTOR, If ENGINEER renders a decision after arbitration proceedings have been initiated, such decision may be entered as evidence but shall not supersede the arbitration proceedings, except where the decision is acceptable to the parties concerned, Limitations on ENGINEER'S Responsibilities; 9,11. Neither ENGINEER's authority to act under this Artir,le 9 t' or elsewhere in the Contract Documents nor any decision made by him in good faith either to exercise or not exercise such authority shall f give rise to any duty or responsibility of ENGINEER to CONTRACTOR, any Subcontractor, any materialman, fabricator, supplier or any of their agents or employees or any other person performing any of the Work. 9,12. ENGINEER will not be responsible for CONTRACTOR's means, methods, techniques, sequences or procedures of construction, or the safety precautions and programs incident thereto, and he will not he i responsible for CONTRACTOR's failure to perform the work in accordance with Vie Contract Documents, The ENGINEER shall have no responsibility with respect to safety and has no obligation to see that the CONTRACTOR's safety obligations are fulfilled. 9.13. ENGINEER will not be responsible for the acts or omissions of CONTRACTOR, or any Subcontractor, or any of his or their agents or employees, or any other persons at the site or otherwise performing any of the Work, s F&N-78 GC-18 1 i ARTICLE 10 - CHANGES IN THE WORK 10.1. Without invalidating the Agreement, OWNER may, at any time or from time to time, order additions, deletions or revisions in the Work; these will be authorized by Change Orders. Upon receipt of a t Change Order, CONTRACTOR shall proceed with the Work Involved, All such Work shall be executed under the applicable conditions of the Contract Documents, If any Change Order causes an increase or de- crease in the Contract Price or an extension or shortening of the Contract Time, an equitable adjustment will be made as provided in Article 11 or Article 12 on the basis of a claim made by either party. 10.2. ENGINEER may authorize minor changes or alterations in the Work not involving extra cost or contract time and not incon- sistent with the overall intent of the Contract Documents. These may be accomplished by a Field Order. If CONTRACTOR believes that any minor change or alteration authorized by ENGINEER entitles him to an increase in the Contract Price or Contract Time, he shall not proceed with the work and shall in writing advise the ENGINEER and request a Change Order. 10.3. Additional Work performed by CONTRACTOR without author- ization of a Change Order will not entitle him to claim an increase in the Contract Price or an extension of the Contract Time, except in the case of an emergency as provided in paragraph 6.20 and except as provided in paragraph 13.7. + 10.4. OWNER, after consideration and approval, may execute ap- propriate C;tange Orders prepared by ENGINEER covering changes in the Work to be performed as provided in paragraph 4.3, and Work performed in an emergency as provided in paragraph 6.20 and any other claim of CONTRACTOR for a change in the Contract Time or the Contract Price which is approved by ENGINEER, ARTICLE 11 - CHANGE OF CONTRACT PRICE 11.1. The Contract Price constitutes the total compensation pay- able to CONTRACTOR for performing the Work. All duties, responsi- bilities and obligations assigned to or undertaken by CONTRACTOR shall be at his expense without change in the Contract Price. 1 11.2. The Contract Price may only be changed by a Change Order. Any claim for an increase in the Contract Price shall be based on written 1 notice delivered to OWNER and ENGINEER within ten (10) days of the I occurrence of the event giving rise to the claim. Notice of the amount of the claim with supporting data shall be delivered within thirty (30) days of such occurrence unless ENGINEER allows an additional F&N-78 GC-19 2 1 1 r C ~ period of time to ascertain accurate cost data. All claims for ad- Justments in the Contract Price shall be determined by ENGINEER if OWNER and CONTRACTOR cannot otherwise agree on the amount involved, , 11.3. The value of any Work covered by a Change Order or of any claim for an increase or decrease in the Contract Price shall be de- termined in one of the following ways, 11.3.1, Where the Work involved is covered by unit prices contained in the Contract Documents, by application of unit prices r, to the quantities of the items involved, unless actual quantities " differ from bid quantities by twenty (20%) percent. Revised con- sideration will be given to that portion in excess of the twenty (20%) percent difference subject to mutual acceptance of a revised unit price. I 11.3.2 By mutual acceptance of a lump sum. L 11.3,3 On the basis of the actual cost directly related to the Work plus a Contractor's Fee for overhead and profit in the amount of fifteen (15%) percent. The actual cost shall be limited to; la;,ur, including foremen; materials entering perma- nently into the work; the ownership or rental cost of construction k plant and equipment during the time of use on the extra work; power and consumable supplies for the operation of power equip- ment; insurance; and social security and old age and unemploy- ment contributions, 11.4. The amount of credit to be allowed by CONTRACTOR to OWNER for any such change which results in a net decrease in cost, will be + the amount of the actual net decrease which decrease shall include a CONTRACTOR's Fee for overhead and profit in the amount of fifteen (154 percent. When both additions and credits are involved in any ' I one change, the CONTRACTOR's fee of fifteen (15%) percent shall be figured on the basis of the net increase, if any. i 11.5. Whenever the cost of any Work is to be determined pursuant to paragraph 11.3, CONTRACTOR will submit in form prescribed by ENGINEER an itemized cost breakdown together with supporting data. ARTICLE 12 - CHANGE OF THE CONTRACT TIME 12.1. The Contract Time may only be changed by a Change Order, f Any claim for an extension in the Contract Time shall be based on written notice delivered to OWNER and ENGINEER within ten (10) days of the occurrence of the event giving rise to the claim. Notice of the extent F&N-78 GC-2G i i k of the claim with supporting data shall be delivered within thirty (30) days of such occurrence unless ENGINEER allows an additional period of time to ascertain more accurate data. All claims for adjustment I in the Contract Time shall be determined by ENGINEER if OWNER and CON- TRACTOR cannot otherwise agree. Any change in the Contract Time re- sulting from any such claim shall be incorporated in a Change Order. i' 12.2. The Contract Time will be extended in an amount equal to time lost due to delays beyond the control of CONTRACTOR if he makes ` a claim therefor as provided in paragraph 12.1. Such delays shall include, but not be restricted to, acts or neglect by any separate contractor employed by OWNER, fires, floods, labor disputes, epidemics, or acts of God other than weather conditions, No time extensions will be allowed for weather conditions for Project using calendar days for 1 the Contract Time. 12.3 The CONTRACTOR agrees that time is of the essence of this contract, and that for each day of delay beyond the number of days herein agreed upon for the completion of the work herein specified and contracted for (after due allowance of such extension of time as Is provided for in Article 12) the OWNER may withhold permanently from the CONTRACTOR's total compensation, the amount per day set forth in Supplementary Conditions, not as a penalty, but as liquidated damages ' and for added expense for engineering services, etc. ARTICLE 13 - WARRANTY AND GUARANTEE, TESTS AND INSPECTIONS, CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK Warranty and Guarantee; i 13.1. CONTRACTOR warrants and guarantees to OWNER and ENGINEER that all materials and equipment will be new unless otherwise specified and that all Work will be of good quality and free from faults or defects ; and in accordance with the requirements of the Contract Documents and of any inspections, tests or approvals referred to in paragraph 13.2. All unsatisfactory Work, all faulty or defective Work, and all Work not conforming to the requirements of the Contract Documents at the time of acceptance thereof or of such inspections, tests or approvals, i shall be considered defective. Prompt notice of all defects shall be given to CONTRACTOR. All defective Work, whether or not in place, may be rejected, corrected or accepted as provided in this Article 13. Tests and Inspections; 13.2. If the Contract Documents, laws, ordinances, rules, regu- lations or orders of any public authority having ,jurisdiction require a l F&N-78 GC-21 I j, y 1 •r I any Work to specifically be inspected, tested, or approved by some public, body, CONTRACTOR shall assume full responsibility therefor, pay all costs in connection therewith and furnish ENGINEER the required certificates of inspection, testing or approval. All other inspections, tests and approvals required by the Contract Documents shall be per- formed by organizations selected by OWNER and the costs thereof shall be borne by OWNER unless otherwise specified, 13.3. CONTRACTOR shall give ENGINEER timely notice of readiness o'• of the Work for all inspections, tests or approvals. If any such Work required so to be inspected, tested or approved is covered without written approval of ENGINEER, it must, if requested by ENGINEER, be uncovered for observation, and such uncovering shall be at CONTRACTOR's expense unless CONTRACTOR has given ENGINEER timely notice of his intention to cover such Work and ENGINEER has not acted with reasonable promptness in response to such notice. 13.4. Neither observations by ENGINEER nor inspections, tests or approvals by persons other than CONTRACTOR shall relieve CONTRACTOR from his obligation to perform the Work in accordance with the requirements of the Contract Documents. Access to Work. i 13.5. ENGINEER and his representatives and other representatives 4 of OWNER will at reasonable times have access to the Work. CONTRACTOR shall provide proper and safe facilities for such access and observation of the Work and also for any inspection or testing thereof by others, Uncovering Work: , 13.6. If any Work is covered contrary to the written request of ENGINEER, it must, if requested by ENGINEER, be uncovered for ENGINEER's observation and replaced at CONTRACTOR's expense. 13.7. If any Work has been covered which ENGINEER has not speci- fically requested to observe prior to its being covered, or it ENGINEER considers it necessary or advisable that covered Work be inspected I or tested, CONTRACTOR, at ENGINEER's request, shall uncover, expose or otherwise make available for observation, inspection or testing as ENGINEER may require, that portion of the Work in question, furnishing all necessary labor, material and equipment. If it is found that such Work is defective, CONTRACTOR shall bear all the expenses of such un- covering, exposure, observation, inspection and testing and of satis- factory reconstruction, including compensation for additional professional ` services, and an appropriate deductive Change Order shall be issued, `I If, however, such Work is not found to be defe.:tive, CONTRACTOR shall f F:&N-78 GC-22 II a, 1 l , f be allowed an increase in the Contract Price or an extension of the Contract Time, or both, directly attributable to such uncovering, exposure, observation, inspection, testing and reconstruction if he makes a claim therefor as provided in Articles 11 and 12. Owner May Stop the Work; 1 13.8. If the Work is defective, or CONTRACTOR fails to supply 1 sufficient skilled workmen or suitable materiels or equipment, or fails to conform to the progress schedule require' oy Paragraph 14.1, or if CONTRACTOR fails to make prompt payi,;~.I1: to Subcontractors or for labor, materials or equipment, OWNER may order CONTRACTOR to stop the Work or any portion thereof, until the cause for such order has been , eliminated; however, this right of OWNER to stop the Work shall not give rise to any duty on the part of OWNER to exercise this right for the benefit of CONTRACTOR or any other party, Correction or Removal of Defective Work: 13.9, If required by ENGINEER prior to approval of final payment, + CONTRACTOR shall promptly, withoift cost to OWNER and as specified by ENGINEER, either correct any defective Work, whether or not fabricated, j installed or completed, or, if the Work has been rejected by ENGINEER, remove it from the site and replace it with nonjefective Work. If CONTRACTOR does not correct such defective Work or remove and replace such rejected Work within a reasonable time, all as specified in a written notice from ENGINEER, OWNER may have the deficiency corrected or the rejected Work removed and replaced. All direct or indirect costs of such correction or removal and replacement, including compen- sation for additional professional services, shall be paid by CONTRACTOR, , and an appropriate deductive Change Order shall be issued. CONTRACTOR shall also bear the expenses of making good all Work of others destroyed or damaged by his correction, removal or replacement of his defective Work. One Year Correction Period: 13.10. If , after the approval of final payment and prior to the expiration of one year thereafter or such longer period of time as may be prescribed by law or by the terms of any applicable special guarantee required by the Contract Documents, any Work is found to be defective, CONTRACTOR shall promptly, without cost to OWNER and in accordance with OWNER's written instructions, either correct such defective Work, or, if it has been rejected by OWNER, remove it from i the site and replace it with nondefective Work. If CONTRACTOR does not promptly comply with the terms of such instructions, OWNER may have the defective Work corrected or the rejected Work removed and 1 i s F'&N-78 GC-23 i , 1 1 ' n replaced, and all direct and indirect r.-sts of such removal and re- placement, including compensation for additional professional services, j shall be paid by CONTRACTOR. Acceptance of Defective Work; 13,111 If, instead of requiring correction or removal and replace- ment of defective Work, OWNER prefers to accept it, he may do so, In such case, if acceptance occurs prior to approval of final payment, a Change Order shall be issued incorporating the necessary revisions in the Contract Documents, including appropriate reduction in the Con- pay- tract appropriate t amount acceptance be occurs paid by after CONTRACTOR approval to of OWfinal NER. an Price; ment, Neglected Work by Contractor: 13.12. If CONTRACTOR should fail to prosecute the Wc~* in accordance ( with the Contract Documents, including any requirements of the progress schedule, OWNER, after seven (7) days' written notice to CONTRACTOR may, without prejudice to any other remedy he may have, make good such deficiencies and the cost thereof (including compensation for additional professional services) shall be charged against CONTRACTOR in which a. case a Change Order shall be issued incorporating the necessary revisions in the Contract Documents including an appropriate reduction in the Contract Price. If the payments then or thereafter due CONTRACTOR are not sufficient to cover such amount, CONTRACTOR shall pay the dif- ference to OWNER. ARTICLE 14 - PAYMENTS AND COMPLETION i Schedules: 14.1. At least ten (10) days prior to submitting the first Appli- p cation for a progress payment, CONTRACTOR shall submit a progress schedule, a final schedule of Shop Drawing submission and a schedule of values of the Work. These schedules shall be satisfactory in form and sub- stance to ENGINEER, The schedule of values shall include quantities and unit prices aggregating the Contract Price, and shall subdivide the Work into parts duringsufficient construction, Uponserve approvaltof basis for progress payments It values bNEER It shall be ication fforEPayment,furnished by ENGINEERated into the formdofeAppl Application for Progress Payment: 4i I 14.21 At least ten (10) days before each progress payment falls 3 i due (but not more often than once a month), CONTRACTOR shall submit to i i ; F&N-78 GC-24 11i I 1 41 ENGINEER for review an Application for Payment on a form supplied by the OWNER filled out and certified by CONTRACTOR covering the Work completed If payment is requested on the basis / as of the date of the Application. of materials and equipment not incorporated in the Work but delivered t and suitably stored at the site, the Application for Payment shall also q be accompanied by such data as required by OWNER. Each subsequent Appli- cation for Payment shall also include an affidavit of CONTRACTOR stating a that all previous progress payments received on account of the Work have been applied to discharge in full all of CONTRACTOR's obligations reflected in prior Applications for Payment. The CONTRACTOR shall certify on each Application for Payment that the Work performed to date complies with the Contract Documents. Contractor's Warranty of Title; 14.3. CONTRACTOR warrants and guarantees that title to tl,lwhrk, materials and equipment covered by any Application ether incorporated in the Project or not, will pass to OWNER at the time of ~ ttoeass"Liens claims security rances hereina at free an fter clear in these all Geliens neral Conditions referred"). Approval of Payments; after receipt of each a da s aft 10 9 14.0.. ENGINEER will, within ten Y Application for Payment, either indicate in writing his approval of payment and present the Application to OWNER, or return the Application to CONTRACTOR indicating in writing his reasons for refusing to approve payment. In the latter case, CONTRACTOR may make the necessary corrections and resubmit the Application. OWNER shall, within ten (10) days of presentation to him of the approved Application for Payment, pay CONTRACTOR the amount approved by ENGINEER less ten (10%) percent of the amount thereof which Contract other Documents~~~t may shall tnuFaafomrth in and the less all be retained by the OWNER as set ENGINEER's approval of any payment requested in an Application 14.5. for Payment will constitute a representation by him to OWNER, based on ENGINEER's on-site observations of the Work ii, progress as an experienced and qualified design professional and on his review of the Application for Payment and the accompanying data and schedules that the Work has progressed to the point indicated; that, to the best of his knowledge, information and belief, the quality of the Work is In accordance with the Contract Documents (subject to an evaluation of the Work as a functioning Project upon Substantial Completion, to the results of any subsequent tests called for in the Contract Documents and any qualifications stated the amou in his approval); and that roCONTRACTOR suchepayment ENGiINCERnwill not thereby d approved, However, by approving F&N-78 GC-25 S l l I i be deemed to have represented that he made exhaustive or continuous on- site inspections to check the quality or the quantity of the Work, or that he has reviewed the means, methods, techniques, sequences, and pro- cedures of construction, or that he has made any examination to ascertain how or for what purpose CONTRACTOR has used the moneys paid or to be paid to him on account of the Cortract Price, or that title to any Work, materials or equipment has paLsed to OWNER free and clear of any Liens. 14 6, ENGINEER may refuse to approve the whole or any part of any payment if, in his opinion, it would be incorrect to make such representations to OWNER. He may also refuse to approve any such payment, or because of subsequently discovered evidence or the results of subsequent inspections or tests, nullify any such payment previously approved, to such extent as may be necessary in his opinion to protect OWNER from loss because; 14,6.1. the Work is defective, or completed Work has been damaged requiring correction or replacement, 14.6.2. claims or Liens have been filed or there is reason- able cause to believe such may be filed, 14.6.3. the Contract Price has been reduced because of Modifications, 14,6.4. OWNER has been required to correct defective Work ' or complete the Work in accordance with paragraph 13,11, or 14.6.5. of unsatisfactory prosecution of the Work, including failure to furnish acceptable submittals or to clean up. 14.6.6, reasonable indication that the Work will not be completed within the Contract Time, 14,6,7, reasonable doubt that the Work can be completed for the unpaid balance of the Contract Price, r Substantiai Completion; 14.7. Prior to fimAl payment, CONTRACTOR may, in writing to OWNER and ENGINEER, certify teat the entire Project is substantially complete and request that ENGINEI'k issue a certificate of Substantial Completion, Within a reasonable time thereafter, OWNER, CONTRACTOR and ENGINEER shall make an inspection of th(, Project to determine the status of completion. If ENGINEER does not consider the Project substantially complete, he will notify CONTRACTOR in writing giving his reasons therefor, If ENGINEER considers the Project substantially complete, he will prepare and deliver is&N-78 GC-26 I i to OWNER a tentative certificate of Substantial Completion which shall fix the date of Substantial Completion and the responsibilities between OWNER and CONTRACTOR for maintenance, heat and utilities, There shall be attached to the certificate a tentative list of items to be completed or corrected before final payment, and the certificate slall fix the h time within which such items shall be completed or corrected, said time to be within the Contract Time. OWNER shall have seven (7) days after receipt of the tentative certificate during which he may make written objection to ENGINEER as to any provisions of the certificate or attached list. If, after considering such objections, ENGINEER concludes that the Project is not substantially complete, he will within fourteen (14) days after submission of the tentative certificate to OWNER notify CONTRACTOR In writing, stating his reasons therefor, If, after consideration of v OWNER's objections, ENGINEER considers the PROJECT substantially complete, he will within said fourteen (14) days execute and deliver to OW;iER and CONTRACTOR a definitive certificate of Substantial Completion (with a revised tentative list of items to be completed or corrected) reflecting such changes from the tentative certificate as he believes justified after consideration of any objections from OWNER, The failure of the ENGINEER to include any items on such tentative list of items to be completed does not alter the responsibility of the CONTRACTOR to complete all Work in accordance with the Contract Documents, 14.8. OWNER shall have the right to exclude CONTRACTOR from the Project after the date of Substantial Completion, but OWNER shall allow CONTRACTOR reasonable access to complete or correct items on the tentative list. Partial Utilization, 14.9. Prior to final payment, OWNER may request CONTRACTOR in writing r to permit him to use a specified part of the Project which he believes he may use without significant interference with construction of the other parts of the Project, If CONTRACTOR agrees, he will certify to OWNER and ENGINEER that said part of the Project is substantially com- I plete and request ENGINEER to issue a certificate of Substantial Completion for that part of the Project, Within a reasonable time thereafter OWNER, a CONTRACTOR and ENGINEER shall make an inspection of that part of the Project to determine its status of completion. If ENGINEER does not consider that it is substantially complete, he will notify OWNER and CONTRACTOR in writing giving his reasons therefor, If ENGINEER considers that part of the Project to be substantially complete, he will execute and deliver to OWNER and CONTRACTOR a certificate to that effect, fixing the date of Substantial Completion as to that part of the Project, at- taching thereto a tentative list of items to be completed or corrected ' before final payment and fixing the responsibility between OWNER and 1 h&N-78 GC-27 1 G CONTRACTOR for maintenance, heat and utilities as to that part of the Project, OWNER shall have the right to exclude CONTRACTOR from any part ~ of the Project which ENGINEER has so certified to be substantially com- plete, but OWNER shall allow CONTRACTOR reasonable access to complete or correct items on the tentative list. Final Inspection; 14,10. Upon written notice from CONTRACTOR that the Project is complete, ENGINEER will make a final inspection with OWNER and CONTRACTOR and will notify CONTRACTOR in writing of all particulars in which this inspection reveals that the Work is incomplete or defective. CONTRACTOR shall immediately take such measures as are necessary to remedy such deficiencies. Final Application for Payment; 1 14,11, After CONTRACTOR has completed all such corrections to the i satisfaction of ENGINEER and delivered all maintenance and operating instructions, schedules, guarantees, Bonds, certificates of inspection and other documents - all as required by the Contract Documents, he may mako application for final payment following the procedure for progress payments. The final Application for Payment shall be accompanied by such data and schedules as 014NFR may reasonably require, together with complete and legally effective releases or waivers (satisfactory to OWNER) of all Liens arising out of the Contract Documents and the labor and services performed and the material and equipment furnished thereunder. In lieu thereof and as approved by OWNER, CONTRACTOR may furnish receipts or releases in full-, an affidavit of CONTRACTOR that the release , s and ~ receipts include all labor, services, material and equipment for which a Lien could be filed, and that all payrolls, material and equipment bills, and other indebtedness connected with the Work for which OWNER or his property might in any way be responsible, have been paid or otherwise f satisfied; and consent of the Surety, if any, to final payment, If any Subcontractor, materia.Iman, fabricator or supplier fails to furnish a release or receipt in full, CONTRACTOR may furnish a Bond or other collateral satisfactory to OWNER to indemnify him against any lien. Approval of Final Payment. 14.12. ff, on the basis of his observation and review of the Work during construction, his final inspection and his review of the final inspection and his review of the final Application for Payment - all as required by the Contract Documents, ENGINEER is satisfied that the r Work has been completed and CONTRACTOR has fulfilled all of his obligations F&N-78 GC-2R ~yy under the Contract Documents, he will, within ten (10) days after receipt of the final Application for Payment, indicate in writing his approval of payment and present the Application to OWNER for payment. There- upon ENGINEER will give written notice to OWNER and CONTRACTOR that the Work is acceptable subject to the provisions of paragraph 14,15, Otherwise, he will return the Application to CONTRACTOR, indicating in writing his reasons for refusing to approve final payment, in which case CONTRACTOR shall make the necessary corrections and resubmit the Application. OWNER shall, within ten (10) days of presentation to him of an approved final Application for Payment, pay CONTRACTOR the amount approved by ENGINEER. 14,13, If after Substantial Completion of the Work final com- pletion thereof is materially delayed through no fault of CONTRACTOR, and ENGINEER so confirms, OWNER, upon certification cv ENGINEER, and S without terminating the Agreement, may make payment of the balance due for that portion of the Work fully completed and accepted, If the remaining balance for Work not fully completed or corrE^ted is a less than the retainage stipulated in the Agreement, and if bonds have been furnished as required in paragraph 5,1, the written consent of the Surety to the payment of the balance due for that portion of the Work fully completed and accepted shall be submitted by the CONTRACTOR to the ENGINEER prior to certification of such paymer'.. Such payment shall be made under the terms and conditions governing final payment, except that it shall not constitute a waiver of claims, Contractor's Continuing Obligation; l 14,14, CONTRACTOR's obligation to perform the Work and complete the Project in accordance with the Contract Documents shall be absolute, Neither approval of any progress or final payment by ENGINEER, nor the issuance of a certificate of Substantial Completion, nor any pay- ment by OWNER to CONTRACTOR under the Contract Documents, nor any use or occupancy of the Project or any part thereof by OWNER, nor any act of acceptance by OWNER nor any failure to do so, nor any correction of defective work by OWNER shall constitute an acceptance of Work not in accordance with the Contract Documents, Waiver of Claims, 14,15. The making and acceptance of final payment shall consti- tute a waiver of all claims by CONTRACTOR against OWNER other than those previously made in writing and still unsettled. FRN-78 GC-29 1 ARTICLE 15 - SUSPENSION Or WORK AND TERMINATION e Owner May Suspend Work; 15.1. OWNER may, at any time and without cause, suspend the Work or any portion thereof for a period of not more than ninety (90) days by notice in writing to CONTRACTOR and ENGINEER which shall `ix the ` date on which Work shall be resumed, CONTRACTOR shall resume the Work ` on the date so fixed, CONTRACTOR may be allowed an increase in the Contract Price or an extension of the Contract Time, or both, directly ` attributable to any suspension if he makes a claim therefor as provided I in Articles 11 and 12, Owner May Terminate; 15.2. If CONTRACTOR is adjudged as bankrupt or insolvent, or if he makes a general assignment for the benefit of his creditors, or if a trustee or receiver is appointed for CONTRACTOR or for any of his property, or if he files a petition to take advantage of any debtor's act, or to reorganize under the bankruptcy or similar laws, or if he repeatedly fails to supply sufficient skilled workmen or suit- i able materials or equipment, or if he repeatedly fails to make prompt p&yments to Subcontractors or for labor, materials or equipment or if he disregards laws, ordinances, rules, regulations or orders of any public body having Jurisdiction, or if he disregards the authority of ENGINEER, or if he otherwise violates any provision of the Contract # Documents, then OWNER may, without prejudice to any other right or 1 remedy and after giving CONTRACTOR and his Surety seven (7) days' written i notice, terminate the services of CONTRACTOR and take possession of j the Project and of all materials, equipment, tools, construction equipment i and machinery thereon owned by CONTRACTOR, and finish the Work by whatever method he may deem expedient. In such case CONTRACTOR shall not be entitled to receive any further payment until the Work is finished. If the unpaid balance of the Contract Price exceeds the direct and indirect costs of completing the Project, including compensation for additional professional services, such excess shall be paid to CONTRACTOR. If such costs exceed such unpaid balance, CONTRACTOR shall pay the I difference to OWNER, Such costs incurred by 014NER shall be deter,aned by ENGINEER and Incorporated in a Change Order, 15,3, Where CONTRACTOR's services have been so terminated by OWNER, said terminations shall not affect any rights of OWNER against CONTRACTOR then existing or which may thereafter accrue, Any retention or payment of moneys by OWNER due CONTRACTOR will not release CONTRACTOR from liability, i FAN-78 GC-30 1 15.4. Upon seven (7) days' written notice to CONTRACTOR and ENGI- NEER, OWNER may, without cause and without prejudice to any other right 1 or remedy, elect to abandon the Project and terminate the Agreement. r In such case, CONTRACTOR shall be paid for all 11ork executed and any expense sustained plus a reasonable profit, Contractor May Stop Work or Terminate: 15.5. If, through no act or fault of CONTRACTOR, the Work is suspended for a period of more than ninety (90) days by OWNER or under an order of court or other public authority, or ENGINEER fails to act on any Application for Payment within thirty (30) days after it is submitted, or OWNER fails to pay CONTRACTOR any sum approved by ENGINEER v or awarded by arbitrators within thirty (30) days of its approval and presentation, then CONTRACTOR may, upon seven (7) days' written notice to OWNER and ENGINEER, terminate the Agreement and recover from OWNER payment for all Work executed and any expense sustained plus a reason- able profit. In addition and in lieu of terminating the Agreement, If ENGINEER has failed to act on an Application for Payment or OWNER has failed to make any payment as aforesaid, CONTRACTOR may upon seven (7) days' notice to OWNER and ENGINEER stop the Work until he has been paid all amounts then due. ARTICLE 16 - ARBITRATION 16.1. All claims, disputes and other matters in question arising 111 out of, or relating to, this Agreement or the breach thereof except for claims which have been waived by the making or acceptance of final payment as provided by paragraph 14,15, shall be submitted to arbitra- tion at the request of either party to the dispute. The parties may 1 agree upon one arbiter, otherwise, there shall be three, one named in writing by each party, and the third chosen by the two arbiters so selected; or if the arbiters fail to select a third within ton (10) days, he shall be chosen by a District Judge serving the County in which the major portion of the Project is located, unless otherwise specified. Should the party demanding arbitration fail to name an arbiter within ten (10) days of the demand, his right to arbitrate shall lapse, and the decision of the ENGINEER shall be final and binding on him. Should the other party fail to choose an arbiter within ten arbiter, (arrt days, to asu appoint with anhouaderstorr in- formation demanded In writing, the a the rbiters are empowered by both parties to take ex parte proceedings, The arbiters shall act with promptness, The decision of any two shall be binding on both parties to the contract, The decision of the arbiters upon any question sub- matted to arbitration under this contract shall be a condition 1! 1F&N-78 GC-31 precedent to any right of legal action, The decision of the arbiter or arbiters may be filed in court to carry it into effect, The arbiters, if they deem the case demands it, are authorized to award the party whose contention is sustained, such sums as they deem proper for the time, expense and trouble incident to the appeal, and if the appeal was taken without reasonable cause, they may award damages for any delay occasioned thereby, The arbiters shall fix their own compensation, unless otherwise provided by agreement, and shall assess the cost and charges of the arbitration upon either or both parties, The award ` of the arbiters must be made in writing. I 16.2. CONTRACTOR will carry on the Work and maintain the progress schedule during any arbitration proceedings, unless otherwise agreed by him and OWNER in writing, ARTICLE 17 - MISCELLANEOUS Giving Notice: 17,1. Whenever any provision of the Contract Documents requires the giving of written notice it shall be deemed to have been validly given if delivered In person to the individual or to a member of the firm or to an officer of the corporation for whom it is intended, or if delivered at or sent by registered or certified mail, pr.tage pre- paid, to the last business address known to him who gives the notice, Computation of Time, j r 1 17,2. When a period of time is referred to in the Contract Docu- ments by days, it shall be computed to exclude th< first and include the last day of such period, If the last day of any such period falls on a Saturday or Sunday or on a day made a legal holiday by the law G of the applicable jurisdiction, such day shall be omitted from the computation. General: 17.3. All Specifications, Drawings and copies thereof furnished by ENGINEER shall remain his property, They shall not be used on another Project, and, with the exception of those sets which have been signed in connection with the execution of the agreement, shall be returned to him on request upon completion of the Project. 17,4, The duties and obligations imposed by these General Con- ditions and the rights and remedies available hereunder, and, in particular F&N-78 GC-32 a but without limitation, the warranties, guarantees and obligations imposed upon CONTRACTOR by paragraphs 6.28, 13.11 13,10 and 14,3 and the rights and remedies available to OWNER and ENGINEER thereunder, shall be in addition to, and shall not be construed in any way as a limitation of, any rights and remedies available to them which are t otherwise imposed or available by law, by special guarantee or by other provisions of the Contract Documents. :F 17.5. The Contract Documents shall be governed by the law of the place of the Project. ' i M l F . I l l 1 E&N-78 GC-33 i i SUPPLEMENTARY CONDITIONS 1, REFERENCE POINTS: The Engineer will provide at the site of the work horizonta ControT-in the form of a base line or grid reference points and vertical control in the form of a base line or grid reference points and vertical control in the form he bench shall From be h responsible for the established by the Engineer, complete layout of the work and for establishing lines and elevations as needed during construction, The Contractor shall furnish and elevations as needed during construction. The Contractor shall furnish at his own I 3 expense labor, including the services of competent personnel, equipment, including accurate surveying instruments, stakes, templates, platforms, tools, and materials as may be required for laying out any and all parts of the work. The Engineer will be available for assistance in an advisory capacity. 'i 2. INSURANCE: The Contractor shall comply with the requirements of Paragrapfi-ii 3 of the General Conditions and shall, at his own expense, purchase, maintain and keep in force such insurance as will protect him from claims set forth below which may arise out of or result from his operations under this Contract, whether such operations are by himself or i by any Subcontractor or by anyone directly or indirectly employed by any of them or by anyone for whose acts any of them may be liable. Minimum insurance requirements are to be as outlined in the Table of "Insurance Minimum Requirements" immediately following the Payment Bond. Such insurance as is required in the "Insurance Minimum Reqnuitremheeventnts" be written so that the Owner will be notified in writing, cancellation, restrictive amendment or non-renewal at least thirty days prior to such action. The Certificate of Insurance, immediately following E the insurance requirements, shall be filled out with the Owner prior to the commencement of the work. All insurance required in the "Insurance Minimum Requirements" shall be policy co-insured requiredthe City shall receive a written with h`every of InDenton surance as duplicate copy of The stated limits of insurance required byy the "Insurance Minimum Requirements" arc.? MINIMUM ONLY and it sha11 be the Contractorminimum limits s responsibility to Tee ine what limits are adequate, may be basic policy limits or any combination of basic limits and umbrella limits. 1n any event, the Contractor is fully responsible for all losses arising out of, resulting from or connected with operations under this contact whether or not said losses are covered by insurance. The Owner°s acct,,tance of Certificates of Insurance that in any respect do not comply with the Contract requirements does not release the Contractor from compliance herewith. The Owner and Contractor waive all rights against each other for damages such extent rights their as interests they e may have ctoethe by caused insurance ufire nder o this other Section, perils except the i 00800-I proceeds of such insurance when held by the Owner as trustee. The Con- tractor shall require similar waivers by Subcontractors and Sub-subcon- 41 tractors. 3. INSPECTION: The Owner will inspect or cause inspection to be per forme on a ^'items of work for this project, The use of the term "ENGINEER", "OWNER'S AGENT", OR "OWNER'S DES[GP :D REPRESENTATIVE" regarding inspection in the Contract Documents mall be understood to mean the Owner will perform inspection duties with his own forces. 4. LIQUIDATED DAMAGES: In the event the Contractor fails to attain subs an a completion of the entire project (all bid items) within the time set forth In the Proposal, the Owner may withhold money permanently from the Contractor's total compensation the amount set forth in the table below as liquidated damages and for added expenses for engineering services, etc., in accordance with Article 12 of the General Conditions. Amount of Contract Amount of Liquidated Damages Less than s 50000.00 3 60.00 Per Day $ 5,000.00 to 14,999.99 80.00 Per Day 15,000.00 to 24,999.99 100.00 Per Day 250000.00 to 491999.99 120.00 Per Day 60,000.00 to 99,999.99 160.00 Per Day :t 1000000.00 to 11000,000.00 240,00 Per Day More than 100000000.00 500.00 Per Day i The Owner will be the sole judge as to whether the work has been completed within the allotted time. {i 4. MINIMUM WAGE SCAM The rates shown in "Schedule D" (following the Data_'S"Het have been determined by the City of Denton, Texas, in A accordance with the statutory requirements and prevailing local wages, j lY END OF SUPPLEMENTARY CONDITIONS r } f1 { r 00800•.2 'I qW i f 01001 GENERAL CONSTRUCTION REIC) IREENTS 1.01 SCOPE OF WORK transportation~fsethe rvicesfurnishing allf The work involv~polsdeequthis ipment,contract all materials, 4 labor and superintendence necessary for the construction and completion of the 2 MG Ground Storage Tank shown in the Plans and specified herein, Work includes necessary excavation, pipings valves, concrote valve vaults and retaining walls, tank foundation, and site grading for a complete turn-key Job. 1.02 EXCESS EARTH Excess earth from the various excavations (earth tnot he requiredo~or ' backfill or embankment) disposed hall be off the site, at no additional expense to the Owner. 1,03 UNCLASSIFIED EXCAVATION Excavation will be unclassified, it shall be the responsibility of the bidder to make such subsurface investigations as he deems necessary to determine the nature of material to be excavated. 1.04 CORRECTION PERIOD r, Nothing in the General Conditions Article 13 concerning the cor- 1 on period shall establish a period of limitation with respect secti t to any other obligation which Contractor has under the Contract Documents. The establishment of time periods relatea only to the specific obligations of Contractor to correct the work, and has no relatios~ocumentsemaymbewsoiughtwtocbehenforced, norstontile time Contract t, within which proceedings may be commenced to establish his lia- bility with respect to his obligations other than to specifically correct the work Performance correction period shall be covered by the extension 1.05 CONN.'CTIONS TO EXISTING FACILITIES It will be necessary, during the course of construction, to make one or involved in makingtconnections which iwill arequiretamshutAll downoof the r existing system shall be carefully planned and coordinated with £ both the Engineer and the Owner so that "down" time of the existing water system may be held to a minimum, On occasions when the existing water system is down for purpose of making a connection, f work shall proceed on a 24-hour schedule until the system is back f{ In operation. a 01001-1 a 1 , , 1.06 WORKMANSHIP 1 These specifications contain detail instructions and descriptions covering the major items of construction and wurkmanship necessary for buildiny and completing the various units or elements of the project, The specifications are intended to be so written that only first class workmanship and finish of the best grade and quality will result, The fact that these specifications may fail to be so complete as to cover all details will not relieve the Contractor of full responsibility for providing a completed project of high quality, first class finish and appearance and satisfactory for operation, all within the apparent intent of the plans and specifications, f 1.07 SANITATION FACILITIES y, The Contractor shall provide portable toilet facilities, (Chem-cans) or equal in sufficient number for the Contractor's use throughout the course of the project and in accordance with OSHA requirements. Con- tractor's personnel will not be permitted to use toilet facilities in the existing plant buildings. 1,08 SALVAGED MATERIAL i During construction of the project any equipment or materials which has been the property of the Owner and which is salvaged by the Contractor shall remain the property of the Owner. Brick and concrete rubble shall be the property of the Contractor and shall be disposed of off the plant site, 1,09 MATERIALS These specifications are interded to be so written that only # materials of the best quality and grade will be furnished. The fact that the specifications may fail to be sufficiently complete in some detail will not relieve the Contractor of full respon- sibility for providing materials of high quality and protecting them adequately until incorporation in the structure. The specs- fications for materials set out the minimum standard of quality which the Owner believes necessary to procure a s atisfactory pro- ject. No substitutions will be permitted until the Contractor has received written permission of the Engineer to make a substitution for the material which has been specified, Where the term "or equal", or "or approved equal" is used, it is understood that if a material, product, or piece of equipment of the specified name and quality is furnished it will be approvable, ` as the particular nar;e was used for the purpose of establishing a standard of quality acceptable to the Owner, If a product of any other, name is proposed for use, the Engineer's approval thereof must to obtained before the proposed substitute is procured by the 1 ' 01001-2 ti: i Contractor, Wherever the term "or equal" is used, it is understood to mean "or approved equal". 1.10 COST BREAKDOWN i Within thirty (30) days after the execution of the Contract, and 3 not less than ten (10) days prior to the first monthly estimate, the Contractor shall submit to the Engineer a cost breakdown of the work under this Contract, This breakdown is for use by the Engi- neer in preparing the monthly estimates and for the Owner's use in cost accounting for the project, The breakdown shall be in detail, itemizing all items of equipment and construction and shall accurately reflect the cost of all work as included in the bid prices. Cost breakdown shall be such that an overall cost of the various elements of the project can be determined. 1.11 PROGRESS SCHEDULES E Within 10 days prior to submission of first monthly progress payment, the Contractor shall prepare and submit to the Engineer for approval six copies of the schedule in which the Contractor proposes to carry on the work, the date of which he will start the several major activities (including procurement of materials, ~ plants, and equipment) and the contemplated dates for completing the same. The schedule shall be in the form of a progress chart of suitable scale to indicate graphically the percentage of work scheduled for completion at any time. As the work progresses, the Contractor shall enter on the chart the actual progress at the end of each partial payment period or at such intervals as directed by the Engineer, The Contractor shall also revise the schedule to i reflect any adjustments in contract time approved by the Engineer. Three copies of the updated schedule shall be delivered at such i intervals as directed by the Engineer, ► If, in the opinion of the Engineer, work accomplished falls behind that scheduled, the Contractor shall take such action as necessary to improve his progress. In addition, the Engineer may require 1 the Contractor to submit a revised schedule demonstrating his grogram and proposed plan to make up lag in scheduled progress and ' to insure completion of the work within the contract time. If the Engineer finds the proposed plan not acceptable, he may require the Contractor to increase the work force, the construction plant and equipment, the number of work shifts or the overtime opera- tions without additional cost to the Owner, Failure of the Contractor to comply with these requirements shall 3 be considered grounds for determination by the Engineer that the Contractor is failin? to prosecute the work with such diligence as will insure its comr,~'Ion within the time specified. 01001-3 1 1 I } i 1.12 TESTS I In addition to the tests called for in the Specifications, the Owner may have tests made of pipe and materials for conformity with the Specifications by an independent testing laboratory. Such independent laboratory will be selected and paid by the Owner, The Owner may require the Contractor to furnish mill test certificates on reinforcing steel or wire, cast iron pipe and fittings, and cement, 1,13 POWER FOR CONSTRUCTION The Contractor shall provide at his own expense electrical power for project construction, 1,14 FINAL TESTING AND OPERATION Prior to presentation for final acceptance of the work under this contract, the Contractor shall have started and operated all units of the plant for a sufficient duration of time to permit the Engineer to observe overall performance of the respective units and equipment, Such operation shall be properly coordinated with the Owner's operating personnel. 1,15 SANITATION AND CLEANUP j 11 During construction, the Contractor shall maintain the premises in an orderly, neat, and presentable condition, Scraps and debris shall not be left scattered around but shall be assembled in one place. When construction under this Contract has been otherwise completed, the Contractor shall remove all left over construction materials, equipment, scraps, debris and rubbish, and leave the site in a neat, well kept appearance, At the completion of the work, all buildings and structures shall be 1 broom clean. Pipes shall be left free of any and all foreign material, The Con- tractor shall remove all marks, stains, dirt and soil from all finished surfaces and shall thoroughly clean all floors, clean and polish all finished hardware and other such devices, 1,16 DISINFECTION After completion of the work the Contractor shall disinfect the various piping and all appurtenances (disinfection procedures for th 210 MG Ground Storage Tank are discussed in Section 13401, WELDED e STEEL GROUND STORAGE TANK), prior to being placed in service, shall be thoroughly flushed with clean water and then filled with ping chlorinated water in which the residual shall be maintained at not less than 50 ppm for 24 hours, The Contractor shall furnish all materials, labor, etc,, for disinfecting, 01001-4 1 r 1. 17 SEQUENCE OF CONSTRUCTION The Contractor shall plan and perform his work, in cooperation with the Owner, so that shut-dawn times shall be short time intervals at { times and durations acceptable to the Owner, 1.18 PROTECTING EXISTING STRUCTURES AND UTILITIES Where excavation or demolition endangers adjacent structures and utilities, the Contractor shall at his own expense carefully support and protect all such structures and/or utilities so that there will be no failure or settlement. Where it is nece~bary to move services, poles, guy wires, pipelines or other obstructions, the Contractor shall notify and cooperate with the utility owner. In case damage to an existing structure or utility occurs, whether , failure or settlement, the Contractor shall restore the structure or utility to its original condition and position without compen- sation from the Owner, Contractor shall repair or replace all damaged street surfaces, driveways, sidewalks, curb and gutter, fences, drainage j structures, or other structures, to the satisfaction of the Engineer and the Owner, Structures shall be restored to a con- dition equal to or better than the original condition and of a similar material and design, The costs of such repair or replace- ment shall be borne by the Contractor and shall be included in the Proposal. f The Engineer has shown all existing piping, valves, electrical conduits, utility poles, etc, as best can be determined from available records. The Contractor shalt verify the type, size, and location of all existing piping and valves in the construction area, All piping, valves, electrical conduit, etc, in the construction area shall be removed and/or relocated as necessary in a manner acceptable to the Engineer, and no additional com- pensation will be considered for relocating any of these items whether shown on the plans or not, 1.19 REFERENCE STANDARDS Reference to the standards of any technical society, organization, or association, or to codes of local and state authorities, shall mean the latest standard, code, specification, or tentative specification adopted and published at the date of taking bids, unless specifically stated otherwise, 1,20 METHODS OF OPERATION The Contractor shall inform the Engineer in advance concerning his plans for carrying on each part of the work, but the Contractor alone shall be responsible for the safety, adequacy, and ef- ficiency of his plant, equipment, and methods, 01001-5 1. Any method of work suggested by the Owner or Engineer, but not i specified, shall be used at the risk and responsibility of the Contractor, and the Engineer and Owner will assume no responsibility l therefor. Review by the Owner or Engineer of any plan or method of work proposed by the Contractor shall not relieve the Contractor of any responsibility therefor and such review shall .ot be considered as an assumption of any risk or liability by the Owner or Engineer, or any officer, agent, or employee thereof, The Contractor shall have no claim on account of the fallure or inefficiency of any plan or method so reviewed, The Owner and the Engineer will not be responsible for any act or omission of the Contractor, or any subcontractor, or any of their agents or employees, or any other persons performing any of the work. The Owner and Engineer will not be responsible for any failure of the Contractor or his subcontractors or any other persons to perform the work in accordance with the requirements of the contract s documents. 1,21 UNFAVORABLE CONSTRUCTION CONDITIONS During unfavorable weather, wet ground, or other unsuitable construction conditions, the Contractor, shall confine his oper- ations to work which will not be affected adversely thereby, No portion of the work shall be constructed under conditions which would affect adversely the quality or efficiency thereof, unless special means or precautions are taken by the Contractor to perform the work in a proper and satisfactory manner. I 1,22 PUMPING AND 1111111111 OPERATIONS i. s The Contractor shall provide all necessary pumping, as required by the excavation work specification, to remove all surface water, ground water, leakage, and water from other sources, from excavations, 1.23 DEFINITIONS Whenever the words, forms or phrases defined herein, or pronouns used in their place occur in these specifications, or in any i. document or instrument herein contemplated, the intent and meaning shall be interpreted as follows; BHP - Brake Horsepower BIL - Basic Impulse Level BTU - British Thermal Unit R 01001-6 I I 1 EQUIPMENT MANUFACTURER OR VENDOR - A manufacturing company engaged in the production of equipment or materials purchased for use in this project. GPM or gpm - Gallons per Minute HP - Horsepower KVA - Kilovolt Amperes KW - Kilowatt MGD - Million Gallons per Day NPSH - Net Positive Suction Head i ' PIV - Peak Inverse Voltage j PF - Power Factor RPM - Revolutions per Minute TDWR - Texas Department of Water Resources j THD - Texas Department of Highways and Public Transportation 1,24 STANDARDS Reference to technical society, organization or body is made in i Specifications in accordance with the following abbreviations: AASHO American Association of State Highway CFficials AIA American Institute of Architects ACI American Concrete Institute AGA American Gas Association AGMA American Gear Manufacturer's Association r 1 AISI American Iron and Steel Institute AISC American Institute of Steel Construction I AMCA Air Moving and Conditioning Association ANSI American National Standard Institute t ASA American Standards Association ASHRAE American Society of Heating, Refrigeration and Air Conditioning Engineers ASME American Society of Mechanical Engineers € ASTM American Society for Testing Materials i AWSC American Welding' Society Code AWWA American Water Works Association CS1 Construction Specification Institute FIA Factory Insurance Association FM Factory Manual FS Federal Specification IEEE Institute of Electrical and Electronic Engineers NAAMM National Association of Architectural Metal Manufacturers f j 01001-7 1 NBFU National Board of Fire NEMA National Electrical Manufacturers Association NEPA National Fire Protection Association NBS National Bureau of Standards NEC National Electric Code OSHA Federal Occupational Safety & Health Act, 1970 J SMACNA Sheet Metal and Air Conditioning Contractors National 1 Association, Incorporated SPR Simplified Practice Recommendation UBC Uniform Building Code UL Underwriters Laboratories, Inc, 1,25 HANDLING MATERIALS NOT APPROVED The Contractor shall remove from the site any materials found to be damaged, and any materials not meeting the specifications. These materials shall be removed promptly, unless the Engineer will accept the materials after repairing. Materials found to be damaged, or not acceptable to the Engineer, shall be removed, Inspection before installation shall not relieve the Contractor from any responsibility to furnish good quality materials, 1.26 WATER FOR CONSTRUCTION The Contractor m: ,v purchase water as required for construction taps. charge then he shall install at his expense, a slow closing valve on the 1 , outlet and a suitable meter. When the Contractor is using water' from the taps, he shall open the tap valve in the morning and use the valve which he has installed for control at all other times. At night, upon cessation of construction operations, the tap valve shall be closed. At all other times when the Contractor's valve remains on the outlet, the Contractor shall keep necessary wrenches available at the tap so that the valve can be quickly 1 removed by the City if necessary. The Owner will not be required to furnish water unless the Contractor adheres to the City's requirements. 1.27 OTHER UTILITIES The Contractor shall make his own arrangements for any other utility requirements in connection with the project, 1,28 OPERATION AND MAINTENANCE MANUALS Prior to installation and operation of the equipment the Vendor shall furnish to the Engineer four (4) copies of Manuals giving Installation and Operation Instructions, Maintenance Procedures, Parts List and other pertinent information for all valves Installed on the project, O10U1-8 1 For each type of equipment to be furnished and installed under this contract, the Contractor shall prepare an uperation and maintenance I manual covering; a. Equipment function, normal operating characteristics, and limiting conditions. b. Assembly, installation, alignment, adjustment, and checking instructions, c. Operating instructions for startup, routine and normal operation, regulation and control, shutdown, and emergency conditions. d. Lubrication and maintenance instructions, e, Guide to "troubleshooting", f, Parts lists, and predicted life of parts subject to wear, Outline, cross-section, and assembly drawings; engineering data; and wiring diagrams, h, Test data and performance curves, where applicable, The operation and maintenance manuals shall be in addition to any instructions or, parts lists packed with or attached to the equipment } when de l l verp,. , Manualo shall be prepared by the Equipment Manufacturer and shall also incorporate appropriate final certified shop drawings, performance curves, and test data as required by the specifications. Manuals may be manufacturer's standard instructions, but shall be supplemented, if necessary, to covor any special feature not included in standard material. Manuals shall be bound in plastic ring or loose leaf binders, preferably limited to 8-1/2 by 11 inch page size, with large drawings folded to such dimension. END OF SECTION F i i 01001.9 T T i i 01002 MEASUREMENT AND PAYMENT 1,00 GENERAL 1,01 SCOPE The "Bid Price" as set forth in the proposal shall include the furnishing of all labor, tools, material, machinery, appliances, p and lant and equipment appurtenant to and necessary for the construction hereinmspecifinednin a first strictcaccordancawith workmanlike these manner specifications and ~ accompanying Plans, The "Bid Price" shall also include any and all kinds, amount, and class of excavation, backfilling, pumping or drainage, sheeting, M shoring and bracing, disposal of any and all surplus materials, permanent protection of all overhead, surface or underground structures; removal and replacement of any poles, conduits, pipe j lines, fences, appurtenances and connections, cloaning up, overhead expense, bond, public liability and compensation and property damage insurance, patent fees, and royalties, risk dine to the elements, and profits, unless otherwise specified. The bid price shall also include all other incidentals not speci- fically mentioned above that may be required to fully construct the tank, complete in place, in accordance with the true intent and meaning of the specifications and dk:uompanying Plans. 1,02 810 ITEM NO, 1 Item No, 1 shall cover the construction of the 2,0 million gallon ground storage tank, all as required by the Plans and Specifications, This bid item shall include the concrete retaining wall, storage tank foundation, inlet pipe, discharge outlet, overflow, overlow pad, inlet, outlet, and drain valves, the tank itself and all its appurtenances, and coating interior and exterior of tank, Grading around the tank, replacement of bermuda grass sod, and all other items shall be included in Bid Item No, 1, END OF SECTION I , 01002-1 s' 02100 SITE PREPARATION 1.00 GENERAL 2.00 DESCRIPTION This item will consist of preparing for construction operations by the removal and disposal of all obstructions from designated areas, where removal of such obstructions is not otherwise provided for in the Plans and Specifications, Such obstructions shall be considered to include remains of foun- cations, floor slabs, concrete, brick, lumber, plaster, abandoned utility pipes or conduits, shacks, and other debris, This item shall also include the removal of trees, stumps, bushes, shrubs, miscellaneous stone, brick, concrete sidewalks, drainage structures, manholes inlets, abandoned railroad tracks, scrap iron, all rubbish and debris, whether above or below ground, except live 4 utility facilities, J It is the intent of this specification to provide for the removal and J disposal of all obstructions and objectionable materials not specifically provided for elsewhere by the Plans and Specifications, 3.00 CONSTRUCTION METHODS + Designated areas of this project shall be cleared of all structures, obstructions and vegetation, as defined above, except trees or shrubs specifically designated by the Engineer for preservation. Trees and shrubs designated for preservation shall be carefully trimmed as ' directed and shall be protected from scarring, barking, or other injuries during construction operations. Exposed ends of pruned ' limbs shall be treated with an approved asphaltic material. h Unless otherwise indicated on Plans, all foundations, underground obstructions, Mumps, roots, etc, shall be removed to the following depths; A, In areas to receive embankment, two (2') feet below natural ground, B. In areas to be excavated, two (21) feet below the lower i elevation of the excavation. C, In all other areas, one (11) foot below natural ground. Holes remaining after removal of all obstructions shall be backfiiled and tamped as directed by the Engineer, The Contractor shall complete the operation of preparing the site by blading, bulldozing, 02100-1 1 1 / f V C ; or by other approved methods, so that the prepare of holes, ditches and other abrupt irregularities of contour changesinelevationssandl be free , The remaining ends of all abandoned storm drains, culverts s i sewers, conduits, and water or gas pipes over three (311) 11 hesinry diameter, shall be plugged with an adequate quantity of concrete to form a tight closure when backfilling is required, f~ All materials and debris removed shall become the property of the Contractor unless otherwise provided for on the Plans or in the Specifications, and shall be removed from the project site, beiusedsinnembankmentsn concrete, when permitted by the EngineerVeme y j ofttheagoverning specifications e Section shall 20conform to 29 EARTHWORK. requirem mts 4,00 PAYMENT Payment for Site Preparation shall be included in the lump sum bid ' for the pru,)ect, END OF SECTION ~II j 0 s f . f r I 1 02100-2 y l 02201 EARTHWORK I 1.00 GENERAL f 1.01 SCOPE The Contractor shall perform all excavation and embankment as may be necessary for the construction, to line and grade shown on the Plans, of all structures, roadways, utilities, and incidentals thereto. In making excavations, the Contractor shall do all necessary shoring, bracing, sheeting, pumping and bailing. Where necessary to determine the location of existing pipes, valves, or other underground structures, the Contractor, after a careful examination of available records, shall make all explorations and excavations for such purpose. Temporary support, adequate protection, and maintenance of all underground and surface pipes, structures and other obstructions encountered in the progress of the work shall be furnished by the Contractor at his own expense. 1,02 EXCAVATION t A. STORAGE All excavation shall be unclassified and shall include all materials encountered regardless of their nature or manner in r which they are removed. Excavated material to be used for backfill may be deposited by the Contractor in storage piles at points convenient for rehandling the material during the backfilling operations. The locatlon of storage piles shall be subject to the approval of the Engineer, t B. EXCESS EARTH Excess earth from the various excavations, which is not required 1 for buckf111 on the plant site, shall be disposed of by the Contractor at locations to be arranged for by the Contractor, 2,00 PRODUCTS 2,01 MATERIALS A. CONCRETE FOR BACKFILL, BLOCKING, CRADLING AND ENCASEMENT { All concrete used for these purposes shall be 1500 psi as specified in Section 03305, CAST IN PLACE CONCRETE. 02201-1 l' y: A t l B. SELECT MATERIAL with sufficient permeabi A non-expansive soil of seepage water characteristics to allow rapid elimination shall be used to backfill against the walls of lity the structures except as otherwise noted. f C. IMPERVIOUS CLAY a. •A. Impervious clay material shall have a liquid limit greater than 30% and plasticity index greater than 15. 0. TOPSOIL i Organic weathered topsoil shall be cleaned of major root ' systems, weeds, brush and debris. E. GRANULAR BACKFILL MATERIAL s Granular backfill as required for backfilling under and adjacent ei to structures and for pipe embedment shall be defined as free 1 flowing sandy material which contains no clay and is reasonably free of organic material, The material shall have a plasticity ,l index of 4.0 or less and shall meet the following requirements; 81 eve Si• 1 e Percent Passim , r ~ inch - 1 inch 100 f I No. 90 - 100 40 y No. 100 600 _ 10 Granular embedment shall not form mud or muck when wet. In addition to all other requirements, material furnished for use as embedment for water mains shall have a resistivity of not • lass than 5,000 ohms/cm3. Material embedment shall be subject to testing uforicomplianceewithithis requirement at the time of delivery to the project. Any material so tested and found to have a resistivity lessthan that required by this specification shall be removed from the Project and disposed of at the Contractor's expense, 3.00 EXECUTION i 3.01 EXCAVATIONS A. STRUCTURAL EXCAVATION i E Excavation shall extend a sufficient distance from walls and footings to allow for forms, installation of services and for 02201••2 i tai r 1 f inspection, except where concrete for walls and footings is authorized to be deposited directly against excavated surfaces, ` Where the dxcavation is made below the elevations indicated on the Plans or required herein through the fault of the Contractor, the excavation shall be restored to the proper elevation with lean (1500 psi) concrete at the expense of the Contractor, 1 In order that the Engineer may judge the adequacy of the proposed foundation, the Contractor, if required, shall make soundings to determine the character of the subgrade material. The maximum depth of such soundings will not be required to exceed five feet below the proposed footing grade, The final elevation to which a foundation is to be constructed i 1 shall be as shown on the Plans or as raised or lowered by written order from the Engineer when such alterations are judged proper to satisfactorily comply with the design requirements for the structure. Should it be found necessary to change the depth of footings from that shown on the Plans, the necessary a alteration in the details of the structure shall be accomplished in a manner as directed by the Engineer, who shall have the right to substitute revised details if required. When a structure is to rest on an excavated surface other than rock, special care shall be taken not to disturb the bottom of the excavation, and removal of the last material required to reach foundation final grade shall not be performed until just before the structure is to be placed, All rock or other hard foundation material shall be free from ) all loose material, cleaned, and rut to a firm surface whether level, stepped, or serrated, as required by the Plans, All seams shall be cleaned out and filled with concrete at the time the structure is placed, f ~ B. TRENCH EXCAVATION Trench excavation comprises excavation for all water lines, sludge lines, drain lines, sewer lines, miscellaneous lines, and appurtenances for the various types of lines. All excavations shall be made by open cut to a minimum depth of four, (411) inches below bottom of pipes, No blasting will be allowed. Sides of trenches shall be kept as nearly vertial as possible, and if required, shall be properly sheeted and braced. Trenches shall be not less than twelve (1211) inches nor more than twenty-four (24") inches wider than the outside diameter of the pipe to be laid therein and shall be excavated true to line so that a clear space on each side of the pipe is not less than six (611) inches for pipe fifteen (15") inches and smaller, nine (9") inches for pipe over fifteen 151 inches up to and including thirty (3011) inches and twelve ~12") inches for pipe over thirty (3011) inches ,l 3 ' 02201-3 E , f 1 In diameter. Bell holes shall be excavated to insure pipe resting for its entire length on the granular material at the bottom of the trench. Excavation for manholes and other accessories shall be sufficient to leave at least twelve (1211) Inches in the clear between the outer surfaces and the excavation. Except at locations where rock excavation forms the bottoms of the trenches, care shall be. taken not to excavate below the required depths. Where rock excavation is required, the rock shall be excavated a minimum clearance depth of four ' (411) inches, (six (6") inches for water lines) and backfilled to the required elevation with granular material thoroughly tamped ' to the satisfaction of the Engineer, If unstable foundation is encountered, it shall be removed and replaced with crushed rock to an elevation of four (411) Inches below bottom of pipe, to the satisfaction of the Engineer. 1 3.02 BACKFILL A. LEAN CONCRETE BACKFILL Lean concrete backfill is to be used at the locations shown on y the Plans. Lean concrete shall be 1500 psi concrete as specified in Section 03305, CAST IN PLACE CONCRETE, B. CONCRETE BLOCKING, CRADLE AND ENCASEMENT Concrete blocking, cradle and encasement shall be 1500 psi concrete as specified in Section 03305, CAST IN PLACE CONCRETE. Blocking shall be placed so as to rest against firm undisturbed trench walls, The supporting area for each block shall be at least as great as that indicated on the Plans and shall be F sufficient to withstand the thrust, including water hammer, which may develop. Each block shall rest on a firm undisturbed foundation of trench sides and bottom, Where pipes are placed below structures they shall be completely encased in 1500 psi :I. concrete, which shall extend up to bottom of structure as shown on the Plans, C. EMBEDMENT INSTALLATION All lines, except water lines, shall have a minimum of 4" granular embedment below the pipe. Water lines shall have a minimum of six (611) inches below the bottom of pipe. Granular embedment shall be as specified in paragraph 2.01E, GRANULAR BACKFILL MATERIAL, of this specification. The initial layer of , embedment placed to receive the pipe shall be brought up to a ; grade slightly higher than that required for the bottom of the pipe and the pipe shall be placed thereon and brought to grade by tamping, or by removal of the slight excess amount of embedment under the pipe, Adjustment to grade line shall be made by scraping away or filling with embedment material, 02201-4 l . t Sr Wedging or blocking up of pipe will not be permitted, Each pipe / section shall have a uniform bearing on the embedment for the length of the pipe, except Immediately at the ,joint, Granular embedment shall be used for backfill in the pipe zone and for a minimum depth of six (611) inches over the pipe. Embedment shall be jetted or tamped to 95% Standard Proctor Density, D. BACKFILLING TRENCHES 1. Under Pavement and within Right-of-Way; All lines located under paved surfaces or within dedicated street right-of-way, shall be backfilled completely with granular embedment material to the top of the trench and compacted to 95% Standard Proctor Density, 2. Outside Paved Areas or Street Right-of-Way; After j sufficient time has elapsed for the free moisture to be gone from the embedment material, the remaining backfill may be either tamped in layers not to exceed six (611) inches in depth, or if excavated trench material is suitable for jetting, shall be placed in layers not exceeding three (31) feet in depth and thoroughly settled by jetting with water in a manner approved by the Engineer, After the backfill has reasonably dried out and settled, it shall be brought to grade and jetted a second time, Compaction of the backfill shall be to 90% Standard Proctor Density, and density tests may be made as deemed necessary by the Engineer, If such tests determine that the backfill does not meet this required density, the Contractor will be r required to remove all the backfill to the point one (11) foot above the pipe or as required by the Engineer and rebackfilled with suitable material until the density required Is obtained, E. BACKFILL FOR STRUCTURES After completion of foundation footings and walls and other construction below the elevations of the final grades, all forms shall be removed and the excavation cleaned of any trash, debris or other objectionable matter prior to backfilling, Contractor shall secure the approval of the Engineer prior to placing back fill around any of the structures, Contractor shall be responsible for settlement, and shall restore surfaces should any settlement occur, Unless otherwise specified or shown on the plans, select m aterial mc.etinig the requirements of paragraph 2,016, SELECT MATE structures.~f specification bea be used backfill 9 placed in layers y 02201-5 s approximately nine (9") inches in depth, properly moistened to approximately optimum requirements, and each layer compacted by machine tampers or other suitable equipment to a density of 95% Standard Proctor Density. Where pipes, walks, or other ` construction is to be-placed on or in the backfilled material, f the backfilling shall be done in a thorough manner to preclude J after-settlement. The select material backfill shall be brought up to eighteen (1811) inches below finished grade. A 1.0-foot la er of impervious clay (from six (6") inches to eighteen (18"~ inches below finished grade) shal'I be compacted in place for the full width of the original excavation from the J r side of the structure. F. TOPSOIL All areas which have been excavated but do not receive paved surfaces shall receive six (6") inches of topsoil unless otherwise shown on the Plans. The six (61') inches of topsoil shall be dumped in separate piles and uniformly distributed by blade, grader or other suitable equipment. Topsoil shall not be pitced when the ground is frozen or excessively wet, Each layer or layers shall be compacted to a density approximately that of undisturbed topsoil adjacent to the site. A sample of the topsoil shall be submitted to the Owner for approval prior to hauling to the job site. 3.03 FINISHING AND CLEAN-UP t All areas which do not receive any type of paved surface, shall be graded as shown on the Plans and raked smooth and even so that they will drain generally away from the structures toward the roads and streets or the natural drainage course. All clods of earth shall be ! broken up and no rocks, trash or debris shall remain on or near the a surface of the finished grade, 4.00 PAYMENT i Payment for Ea+^thwork, Including Trench Excavation, Granular Material, Backfill, Clean-up and incidentals complete in place, shall be includeri in the lump sum bid for the complete Project, which shall include all materials, equipment, labor, construction, and clean-up s as shown on the Plans and covered in the Specifications. END OF SECTION k 02201-6 s ti i 1 i 1 02212 GRASSING FOR EROSION CONTROL 1.00 GENERAL 1.01 SCOPE - The work covered by this section of the specifications includes furnishing all plant, labor, equipment and materials and performing all work for providing Bermuda grass erosion control protection for 1 the slope behind the retainin as shown on the drawings, The work includes preparing the slopes land ground surfaces removing, hauling and placing the Bermuda grass at theflocationsng, shown on the drawings or as ordered by the Engineer, and maintenance ' of the grass erosion control, including waterin e mowing, until acceptance b g, fertilizing, and soon as practical, Y the Owner. All areas shall be grassed as 2.00 MATERIALS 2,01 SOURCE OF BERMUDA GRASS w l The source of the Bermuda grass is the responsibility ' Contractor, Failure b t good useable weed free condition, actor to obtain Bermuda gross in a shall result in the Contractor as determined by the Engineer, providing grass at his own expense. oan alternate source of 2.02 FERTILIZER Fertilizer will be 16-8_8 nutrients a u or the equivalent to I"Irnish ' 4 ent to 16-8-8 applied at the required rateortional Fertilizer shall be uniformly distributed by a common fertilizer distributor or other equipment approved b 3.00 EXECUTION Y the Engineer, 3.01 REMOVAL Bermuda grass for erosion control shall be living or growing Bermuda grass, When stripped and supplied to the surfaces to be protected, the grass and topsoil shall be in a moist condition, da Bermuda grass may be striped by scrapers or other means, Of grass Shall be allowedenly to yield sufficient material which be placed within two days. Stri Stripping , period not to exceed two days, Str pping to eight inches, sshallbbeStocapdepthfof sixy 02272-1 1 i ' 3.02 PREPARATION OF THE SLOPE c Surface of the areas to receive grass shall be smoothly and uniformly graded to the slopes and grades as shown on the drawings with a J tolerance of plus or minus two inches 2"} prior to grassing. The areas to be grassed shall be lightly scarified, wetted, and rolled prior to placement of the grass. 3.03 PLACEMENT Bermuda grass shall be uniformly distributed over the surfaces to receive grass erosion protection to a depth of not less than six inches. After uniformly distributing the grass and dressing the site to true and uniform grade, the surface shall be lightly compacted by rolling with a flat roller weighing from 20 to 40 pounds per linear inch. After placing the Bermuda grass on the slopes and surfaces, the areas shall be fertilized at a rate of 300 pounds per acre. Immediately after application of fertilizer to an area, the area shall be thoroughly watered. n After the initial watering, the areas shall be watered as soon as drying of the surface is evident. Watering shall be repeated at such intervals as necessary to maintain a moist condition of the soil until eighty percent (80%) of the area grassed has taken root and is growing in a good healthy condition. The watering shall be done in a manner which will prevent excessive erosion of the soil, j 3.04 MAINTENANCE The maintenance of all grassed areas shall be the responsibility of the Contractor until final acceptance of the project or for 90 days after grass is planted, whichever is longer. Maintenance shall ~I include but not be limited to fertilizer, weed control, watering and mowing. Watering and mowing shall be performed when necessary or when ordered by the Engineer, 3.05 ACCEPTANCE Y Final acceptance of the grassing will be made only during the growing season after all work is completed. The grass growth on acceptance must not be over 6-inches high and have a minimum coverage of 80% healthy, green, relatively weed-free grass. The grass shall have been maintained as required in Paragraph 3,04 during the entire time since sprigging, Upon final acceptance of the completed structure, or 90 days after the grass is planted, whichever is later, the Owner will assume responsibility for watering and maintenance of thn slopes. t 02272-2 a R 1 4.00 PAYMENT i k. Payment for grassing for erosion control will be included in the lump sum price bid for the complete project, which shall include E compensation for providing all labor, equipment, materials, water, fertilizer and weed control, hauling, preparing the slopes and areas to receive grassing, placing, watering, fertilizing, mowing if regwired, and maintaining the areas until final acceptance has been ra made and all other work necessary and incidental to this phase of the work, END Of SECTION t R i E l 1 e i . I. J , 1 5 , 02212-3 1 1 a 02614 PRESTRESSED CONCRETE CYLINDER PIPE_ 1.00 GENERAL 1,01 SCOPE Furnish and install all concrete cylinder pipe and fittings, and specials, including connections and appurtenances completely as shown on the Plans and specified herein and make hydrostatic test. 1.02 SUBMITTALS i Submit the required shop drawings to the Engineer for approval before fabrication or shipment to the job site. All of the drawings and data shall be complete and shall include a , complete description of the pipe offered, including cuts, tabulated H layout and all pertinent engineering data required for a complete evaluation of the submittal, Prior to delivery of the pipe to the project site, the manufacturer shall furnish an affidavit certifying that all pipe, fittings, and specials, and other- products and materials furnished, comply with the applicable provisions of this Specification. 2.00 PIPE 2.01 GENERAL i Prestressed concrete cylinder pipe, fittings and specials shall be designed, fabricated and tested in accordance with the latest requirements of AWWA C-301, "Reinforced Concrete Pressure Pipe - Steel Cylinder Type, Prestressed, for Water and Other Liquids" with additional requirements or modifications as described herein. I 2,02 PIPE DESIGN CLASSES Sizes and design pressure classes shall be 3611, 50 psi, Fittings, specials and connections shall be same class as the associated pipe c unless otherwise indicated, All pipe and fittings shall be clearly marked with the pressure class and piece number to permit easy identification in the field. Pipe design shall be based on trench conditions shown on the Drawings, The select backfill in the pipe zone will be selected or processed material from trench eRcavation which is loose workable material free of lumps or rocks larger than 2 Inches in their greatest dimension. Material will be consolidated or compacted to a' least eighty five percent (85%) of max' um density, Standard Proctor, as determined by ASTM D698, "dst for Moisture-Density Relations for Soils." ' 02614-1 i 1 i I . Pipe shall be designed for the trench depths indicated using a Soil Rgaction Modulus F.' of 700, and a maximum pipe deflection of D /4,000. 2.03 SPECIAL REQUIREMENTS FOR CONCRETE CYLINDER PIPE , A. CEMENT , Cement for use on inside and outside mortar coating shall be Type [I Portland Cement, with not more than five (5%) percent tricalcium aluminate (CM). 8. FLANGES Flanges shall have ANSI Drilling of class equal to or greater than the pipe class, unless otherwise specified, and shall match f class of valves or appi:rtenances which are attached. 2.04 INSPECTION AND TESTING d A. GENERAL The Owner reserves the option to have an independent testing laboratory, at the Owner's expense, inspect pipe and fittings at the pipe manufacturer's plant to ensure compliance with the applicable specifications. The Owner's testing laboratory and Engineer shall have free access to those parts of the manufacturer's plant that are necessary to ensure compliance with the governing standard. The pipe manufacturer shall notify the Owner, in writing, at least two weeks ahead of pipe fabrication as to start of fabrication and fabricating schedule so that the Owner can advise the manufacturer as to Owner's decision regarding tests to be performed by an independent testing laboratory. In event the Owner elects to retain an independent testing laboratory to make material tests and weld I tests, it is the intent that the tests be limited to one spot testing of each category unless tests do show compliance, theCe s with the Standard. Owner r right to have the ensure compliancetofythekfinishedonal and tests product with the Standard, In any event, the manufacturer shall perform the tests described in AWWA C301, and furnish the Owner with a copy of the test reports, if requested, at the expense of the pipe manufacturer. r The pipe manufacturer shall furnish the owner with affidavit of compliance as outlined in the Standard. 8. SPECIAL FITTINGS All welds for water tightness in special pipe and fittings that have not been hydrostatically tested may be examined by use of 02614-2 i . visible dye penetrant system meeting requirements of ASTM E165; however, collar reinforcement and all other lapwelds shall be tested by introducing air under 10 psi pressure between the I collar and cylinder and checking for leaks around and through the welds with soap solution. The area to receive the dye penetrant shall be cleaned flee from , contaminants that might interfere with with the penetrant process. The temperature of the steel in the weld area shall be between 60 and 125 degrees F. when the penetrant is applied, x Dwell time of six hours shall be allowed after application of the penetrant and developer before interpreting the results, Defects that are found shall be repaired and the test repeated until all defects are eliminated. Colored penetrant shall be f removed before fittings are lined. 1 3.00 EXECUTION 3.01 INSTALLATION A. PIPE HANDLING Pipe, fittings, valves and other accessories shall be hauled to and distributed at the site of the project by the Contractor, they shall at all times be handled with care to avoid damage. Before lowering into the trench, each joint of pipe shall be i inspected, and any damaged pipe shall be rejected. The pipe shall be kept clean during the laying operation and i free of all sticks, dirt, and trash, and at the close of each I operating day, the open end of the pipe shall be effectively sealed against the entrance of all objects and especially water. No pipe shall be laid in water. B. PIPE JOINTING , 1. spigot General: rings Before shall laying be thoroughly cleanedeb the bell and p 9 g thoroughly Y brushing and s wiping. If any damage to the protective coating on the metal has occurred, it wiII be required of the Contractor to repair such damage before the pipe is laid. Sections of pipe shall be tightly fitted together and care shall be exercised to secure true alignment and grade, When a joint of pipe is being laid, the casket shall be placed on the spigot ring and the spigot end of the pipe shall then be entered into the bell of the adjoining pipe and forced into position, The gasket and the inside surface of the bell shall be lubricated with an approved lubricant (flax soap) which will facilitate the telescoping of the ,joint, The inside joint recess between ends of the pipe sections shall have a maximum opening of seven eights 02614-3 1 i { r i (7/811) inch and minimum of one quarter i1/411) inch, No l "blocking up" of pipe or joints will be permitted, and if the pipe is not uniformly supported or the Joint not made up properly, the joint shall be removed and the trench , shall be properly prepared. For interior welded joints backfilling shall be completed before welding. For exterior field welded Joints, adequate working room shall be provided under and beside the pipe. Exterior 6oint; The exterior joint shall be made by placing a joint wrapper around the pipe which will be held in place by means of two metal straps. The wrapper shall be nine (911) inches wide for pipe 36" and larger, and seven (711) Inches wide for smaller pipe, and hemmed on each side. The wrapper shall be fiberglass reinforced or burlap cloth, of such length that it will encircle the pipe, leaving enough opening between ends to allow the mortar to be poured inside the wrapper to the joint, The wrappers shall be similar and equal to those manufactured by Mar-Mac Manufacturing Company, The grout used for pouring the joint shall consist of one part portland cement to two parts clean, fine, sharp sand, as specified for interior joints, and mixed to the consistency of thick cream, The joint shall be filled with this grout from one side in one continuous operation until the grout has flowed entirely around the pipe. During the filling of the Joint, the sides of the wrapper shall be patted or manipulated as required to settle the mortar and expel any entrapped air, 3. Interior Joints: Upon completion of backfilling of the pipe i trench, the inside joint recess shall be filled with a stiff cement mortar consisting of one part of cement to two parts of sand by a qualified workman working inside the pipe. Cement shall be ASTM C150, Type II or Type III with the modification that the cement shall contain not more than five (5%) percent tricalcium aluminate (OA). Sand shall conform to ASTM Specification C144 (plaster sand), Prior to placing of mortar, any dirt, or trash which has collected in the joint shall be cleaned out and the concrete surfaces of the Joint space shall be moistened by spraying or brushing with a wet brush. The stiff mortar shall be rammed or packed into the joint space and extreme care shall be taken to insure that no voids remain in the joint space, After the joint has been filled, the surfaces of the joint fi shall be leveled with the interior surfaces of the pipe with a steel trowel so that the surface is smooth. F 02614-4 Interior joints of pipe smaller than 71 inches shall have the bottom of the bell buttered with mortar, prior to inserting the spigot, such that vihen the spigot is pushed into position it will extrude surplus mortar from the joint. The surplus mortar shall be struck off flush with the inside of the pipe by pulling a filled burlap bag or an inflated ball through the pipe with a rope, 4, Welded Joints: Joints to be welded shall be telescoped together with rubber gasket as specified above and aligned perfectly with the adjacent section of pipe, Welding shall be accomplished by laying a filler rod ^ between the steel bell of one section and the steel spigot of the other, and welding the bell to the outside of the spigot. No less than three (3) complete passes shall be used to make the weld which shall be watertight, i When the joint weld is completed the exterior joint shall be poured with mortar as specified above. Sufficient time shall elapse to allow the mortar to set-up before skidding y assembled sections into the casing. High early strength cement may be used for this purpose if desired, After all sections are in final position, the interior joint shall be filled as specified above. i C. PROTECTION OF EXPOSED METAL All exposed ferroup metal shall be protected by a minimum of one (111) inch coating of Portland Cement mortar consisting of one part cement, as specified for inside joints, and two parts sand. , Exposed Iiurfaces such as, but not limited to, flanges, bolts, j caulked joints, threaded outlets, closures, etc,, shall have coating reinforced with galvanized wire mesh, i The surface receiving a cement mortar coating shall be thoroughly cleaned and wetted with water just prior to placing the cement mortar coating. After placing, care shall be taken to prevent cement mortar from drying out too rapidly by covering i with damp earth or burlap, Cement mortar coating shall not be applied during freezing weather. D. PATCHING Excessive patching of lining or coating will not be permitted. Patching of lining or coating will be allowed where area to be repaired does not exceed 100 square inches and has no dimensions greater than 12 inches. In general, there shall not be more than one patch on either the lining or the coating of any one joint of pipe, 02614-5 ~rrr>r r . f - i Wherever necessary to patch the pipe, patch shall be made with a mortar of one part Portland Cement and two parts clean sharp sand; all measurements to be by weight. Pipe thus patched shall i not be installed until the patch has been properly and adequately cured and approved for laying by the Engineer. E. PIPE BEDDING Trench bottom shall be excavated below the pipe for installing pipe bedding as specified under EARTHWORK. Pipe shall be laid on the bedding such that it is supported uniformly from end to end. u. F. BACKFILLING As soon as the pipe joint has been complete, the joint mortar 1 has set-up and all concrete blocking completed, the backfilling in the "pipe zone" to a point at least 12 inches above the pipe shall be done as specified under EARTHWORK. 3.02 HYDROSTATIC TEST r A. GENERAL After the pipe has been laid and backfilled, each valved section j of newly 1,-,Id pipe shall be subjected to a hydrostastic pressure test. For any section being tested, the pressure applied shall be such that at the lowest point in the section, the test pressure shall be equal to the pipe design class. Test pressure shall be as indicated on the hydraulic gradient sheet of the plans. I r Each valved section of pipe shall be slowly filled with water r and the specified test pressure shall be supplied by means of a pump connected to the pipe in a satisfactory manner, The pump, pipe connection, and all necessary apparatus including gauges and meters shall be furnished by the Contractor. Water for filling line may be obtained from the existing system to which the pipeline connects, i B, PROCEDURE C Care shall be used to see that all air vents are open during the filling. After the line, or section thereof, has been completely filled, it shall be allowed to stand under a slight pressure at least 24 hours to allow the pipe to absorb what water it will and to allow the escape of air from any air pockets, During this period, the plugs, valves, manholes and connections shall be examined for leaks, If any are found, these shall be stopped, or in the case of valves in the main 02614-6 i' 1 1 f 1 line or plugs, provision shall be made for measuring the leakage during the test. The water necessary to maintain the test pressure shall be measured through a meter or by other means satisfactory to the Owner, Contractor shall furnish all necessary equipment and make tests at his expense. Before applying the specified test pressure, all air shall be j expelled from the pipe. In the event it is necessary to expel 9 'I1 air from high points other than where taps are provided, the Contractor may tap the line for this purpose and afterward tightly plug the tap with a brass plug. No extra compensation will be made for these taps. Duration of test shall be four (4) j hours. C. EXAMINATION UNDER PRESSURE N During the last two hours of the test, the entire route of the 1 pipeline under test shall be inspected to locate any leaks or breaks, Any defective ,joints, cracked or defective pipe, fittings, or valves discovered in consequence of this pressure j =•1 test shall be removed and replaced with sound material in the ! manner provided and the test shall be repeated until satisfactory results are obtained. 0. PERMISSIBLE LEAKAGE s ~ No pipe installation will be accepted until the leakage is less j than 25 gallons per mile, per 24 hours, per inch of nominal j diameter of pipe, based on 32' joint lengths and 100 psi test { pressure, E. LEAKAGE DEFINED Leakage is defined as the net quantity of water to be supplied into the newly laid pipe, or any valved section of it, necessary 1 3 to maintain the specified leakage test pressure after the pipe has been filled with water and the air expelled. F. VARIATION FROM PERMISSIBLE LEAKAGE Should any test of pipe laid disclose leakage greater than that specified, the Contractor shall at his own expense, locate and repair, the defective ,joints, until the leakage is within the specified allowance, 1 ! END OF SECTION l 02614-7 i f l f 03100 CONCRETE FORMWORK 1.00 GENERAL 1.01 SCOPE The work covered by this item consists of furnishing all material and labor required for forming, tieing, bracing and supporting the wet concrete, the reinforcing steel and all embedded items until the ` concrete has developed sufficient strength to permit form removal. I , 1.02 GOVERNING STANDARDS All forming materials, accessories and their use shall conform to the requirements of: ACi-347 Concrete Formwork American Concrete Institute, P. 0. Box 19150, Redford Station Detroit, Michigan 48219 AISC Manual of Steel Construction j ! American Institute of Steel Construction 400 North Michigan Avenue Chicago, Illinois 60611 AISI Cold-Formed Steel Design Manual American Iron and Steel Institute New York, New York 2.00 PRODUCTS 2.01 MATERIALS s A. LUMBER All lumber for forms and falsework shall be properly seasoned a and of good quality. It shall be free from loose or unsound y knots, knot holes, twists, shakes, decay, splits, and other imperfections which would affects its strength or impair the finished surface of the concrete. The lumber used for facing or s sheathing shall be surfaced on at least one side and two edges, and shalt be sized to uniform thickness. Lumber of nominal one-inch thickness or plywood of 3/4-inch thickness will be permitted for general use on structure if backed by a sufficient number of studs and. wales. ,J 03100-1 i i . i 8. FORM LINING j Timber forms for exposed concrete surfaces which are to be given a rubbed finish, shall be facelined with an approved type of form lining material. If plywood is used for form lining, it shall be made with tinter-proof adhesive, shall have a minimum thickness of one-fourth inch, and preferably shall be oiled at the mill and then re-oiled or lacquered on the job before using. ` If fiber board is used it shall be tempered Masonite Concrete R Form Presdwood, having a minimum thickness of three-sixteenths -y inch and shall be thoroughly wet with water at least 12 hours before using. The water shall be applied to the screen side of the board and the boards shall be stacked screen ssde to screen I side. The smooth hard face shall be used as the contact surface of the form. If desired by the Contractor, such surfaces may be formed with three-fourths inch thick plywood made with water-proof adhesive backed with adequate studs and wales, keeping in mind that the greatest strength of the outer plies should be at right angles to the studding, and in this case, form lining will not be required. Edges and faces of adjacent panels shall be carefully aligned and the joints between panels shall be filled with patching plaster or cold water putty to prevent leakage, and sanded lightly with No. 0 sandpaper to make the joints smooth. Forms which are being reused shall have all unused form tie holes I filled and smoothed as described above so as to be perfectly { smooth. C. SPECIAL FORM LUMBER 1. Molding specified for chamfer strips or other uses shall be made of redwood, cypress, or pine materials of such grade that will not split when nailed and which can be maintained to a true line without warping. The molding shall be mill cut and dressed on all faces. Where shown on the plans, forms shall be filleted at sharp corners, both inside and outside, and at edges, with triangular chamfer strips. The strips shall be of sizes indicated. All chamfer strips shall be thoroughly oiled before installation on forms. 2. Forms for railings and ornamental work shall be constructed to standards equivalent to first class mill work. All moldings, panel work, and bevel strips shall be straight and true with neatly mitered joints and of such design that the finished work shall be true, sharp, and clean-cut. _i i 03100-2 D, CARTON FORMS i fireboar Carton forms drilledapiersaforbbuildingsrwhere and grade on the plans. be corrugated fibreboard void forms msas 4al Carton forms shall las, fabricated and distriboed by Savway Carton Forms, hwater Texas, and shall beuat withspathan " in ratfin delpmith.nFoatedrmswishall be impregnated througho ors all e desi to resistant adhesive. aF nommalhconstructionnload support the 5 concrete plus i to oid forms are to be installed accor Fibreboard v conditiongwhentconcrete manufacturers recommendations and in dry is poured. s E. METAL. FARMS ` ifications for "Forms" as regards design, + The foregoing spec beveled projections, mortar-tightness, filleted corners, and wetting shall bracing, alignment, removal, re-use, oiling, remaindtrue torShapshall e- Abp apply equally to meta ThW1e metal use for f of such thickness that bolt and rivet heads on the facing sides shall be countersunk. { or other connecting devices shall be designed to Clamps, pins, together and to allow removal without hold the forms rigidly injury to the concretel Metal hich notobeoused sent line u smooth surface or p pro metal free from rust, grease, or care shall be exercised to keep other foreign material such as will tend to discolor the concrete. F, PAN/SLIP FORMS Pan/Slip Forms, when required, shall meet all of the applicable portions of this specification) G, FORM TIES i the Engineer shall be used Metal form ties of a type approved by provision to to hold forms in place. Such ties shall have p f permit ease r o~m a ties wilimnot}bes ehere~ rmittedtexceptcbyied. used inside of The use of wire meta app ances to of the Eng~naer. A sha r 11 approva inch from nthet surfacebofrtheved oneihalfcorrect the forms of t at hold least them i i a dep d concrete and shall be so constructed that metal maor be rspaelmove I without undue injury to the surface from chipping Such devices, when removed, shall leave a smooth opening in the concrete surface not larger than seven-eighths inch in diameter. I % 03100-3 + Burning off of rods, bolts, or ties will not be permitted, Metal ties shall be held in place by devices attached to wales. Each device shall be capable of developing the strength of the tie, Metal and wooden spreaders which are separate from the C forms shall be wired to top of form and shall be entirely 1 f1 removed as the concrete is being placed. Where wire ties are permitted, all wires shall be ct.it back at least one-half inch N from the face of the concrete with a sharp chisel or nippers. The use of metal form ties of a type that are encased in paper or other material to allow the removal of complete tie, leaving a hole through the concrete structure, will not be permitted in ' the construction of basement or water bearing walls. ti ~1 sf H. FORM OIL i The oil used for this purpose shall be a light clear oil which will nut discolor or otherwise injuriously affect the concrete r surface or delay or impair curing operations. i 2.02 STRENGTH REQUIREMENTS A. DESIGN LOADS r Forms shall be designed for the pressure exerted by a liquid weighing 150 pounds per cubic foot. The rate of placing the concrete, temperature of the concrete, and whethe the concrete is vibrated or not, shall be taken into consideration in determining the depth of the equivalent liquid. An additional live load of 50 pounds per square foot shall be allowed on horizontal surfaces, The maximum unit stresses shall not exceed 125 percent of the allowable stresses used for the design of structures, s B, ALIGNMENT CONTROL I True alignment of walls and other vertical surfaces having straight lines or rectangular shapes shall be controlled by the a following procedure: Forming shall be arranged with p 9 rovisions for adjusting the horizontal alignment of a form after the form 1 has been filled with concrete to grade, using wedges, turnbuckles, or other approved adjustment methods, The general procedure will be to establish a transit line or other approved reference such that adjustments can be made to an established line while the concrete in the top of the form is still plastic, Adjusting facilities shall be at intervals which will permit ! adjustments to a straight line, The Contractor shall be 1 responsible for this alignment check, and shall furnish his own 1 personnel for such checking and adjustment. Tolerance for the adjustment shall be subject to the Engineer's approval, No forms will be approved for pouring until adequate adjusting facilities are in place, 03100-4 i 1 C. FALSEWORK All falsework shall be designed and constructed so that no ` excessive settlement or deformation will occur, and so that the necessary rigidity will be provided. All timber used in falsework centering shall be sound, in good condition, and free from defects which will impair its strength, Steel members shall be of adequate strength and of such shape as to be suitable for the purpose intended. Timber piling may be of any species of wood which will withstand driving satisfactorily and which will adequately support the superimposed load. r Where sills or timber grillages are used to support falsework columns, such sills and grillages, unless founded on solid rock, shale or other hard materials shall be placed in excavated pits and backfilled to prevent the softening of the supporting material by drip from the forms or by rains that may occur during the construction process. Sills or grillages shall be of i ample size to support the superimposed load without settlement. Falsework which cannot be founded on a satisfactory spread footing sha'1 be supported on piling which shall be driven to a bearing capacity sufficient to support the superimposed load without settlement. 3.00 EXECUTION 3,01 GENERAL REQUIREMENTS i A. FORM WORK Forms shall be built mortar-tight and of material sufficient in strength to prevent bulging between supports. They shall be set and maintained to the lines designated until the concrete is sufficiently hardened to permit form removal, During the elapsed time between the building of the forms and the placing of the concrete, the forms shall be maintained in a manner to eliminate warping and shrinking. If, at any stage of the work, the forms show signs of bulging or sagging, that portion of the concrete causing such condition shall be immediately removed, if 1 necessary, and the forms shall he reset and securely braced against further movement, Forms or form lumber to be reused shall be maintained clean and in good condition as to accuracy, shape, strength, rigidity, tightness, and smoothness of surface. All forms shall be so constructed as to permit removal without damage to the concrete, Particular and special care must be exercised in framing forms for copings, offsets, railing, and i all ornamental work, so that there will be no damage to, or marring of, the concrete when the forms are removed, Whenever practicable, forms shall be erected complete before the reinforcement is placed, For narrow walls and other locations I 1 03100-5 1 I where access to the bottom of the forms is not otherwise readily attainable, adequate cleanout openings shall be provided. B. EMBEDDED ITEMS Before placing concrete, care shall be taken to determine that all embedded items are firmly and securely fastened in place as indicated in the drawings or required by the Engineer. All t„ embedded items shall be thoroughly clean and free of oil and i, other foreign material. Anchor bolts shall be set to exact locations by the use of suitable anchor bolt templates, or as otherwise shown on the plans. C. PLACING REINFORCEMENT Reinforcement in concrete structures shall be carefully and accurately placed and rigidly supported as provided in the Item "Concrete Reinforcement", D. WETTING AND OILING FORMS The facing of all forms shall be treated with a suitable form - M oil before concrete is placed. In hot weather, both sides of i the face forms may be required to be treated with oil to prevent J warping and to secure tight ,points. The oil shall be applied before the reinforcement is placed. In general, all surfaces of forms which will come in contact with the concrete shall be wetted immediately before the concrete is placed. E. CLEANING FORMS 1 At the time of placing concrete, the forms shall be clean and entirely free from all chips, dirt, sawdust, and other extraneous matter. Forms for slab, beam and girder construction shall not have tie wire cuttings, nails, matches or any other matter whatsoever which would mar the appearance of the finished 'i construction, All forms shall be cleaned to the satisfaction of the Engineer, and kept free of foreign matter of all kinds during concrete placing, F. ENGINEERS APPROVAL 3 The Contractor shall notify the Engineer upon completion of various portions of the work required for placing concrete so that inspection may be made as earl,, as is practicable, When all items have been found to be in order, the Engineer will authorize the contractor to proceed with the placement. 3.02 REMOVAL OF FORMS . i Forms shall be removed in such a manner that the underlying concrete surface is not marred or dama,,,~ in any way. Forms may be removed in 03100-6 • 1 1 'I 1 1 not less than the number of curing days set forttl in the following table; E' Forms and falsework under slabs, beams and girders where deflections due to dead load moment may ; exist 7 days Forms for walls, columns, sides of piers, massive structural components and other members not resisting a bending moment during curing 1 day 1 ~F4J Forms for concrete of minor structural load 3 j carrying importance 1 day END OF SECTION i 1 i j E t a s S \t 03100-7 F:1 r 1 03200 CONCRETE REJNFORCEMENT 1.00 GENERAL 1.01 SCOPE The work covered by this item consists of furnishing all the reinforcing materials and labor required for cutting, bending, tieing, splicing, placing and supporting the reinforcement in the material grades, sizes, quantities and locations as shown on the plans. 1.02 GOVERNING STANDARDS I All reinforcing materials and the cutting, bending, tieing, splicing, placing and supporting of same shall be in compliance with the following listed standards unless otherwise noted in the Contract Documents. The publications listed below are from: ASTM - American Society for Testing and Materials, 1916 Race St,, Philadelphia, Pa. 19103. 4 ACI - American Concrete Institute, P.O. Box 19150, Redford Station, Detroit, Michigan 48219, CRSI - Concrete Reinforcing Steel Institute, 180 N. LaSalle St., Chicago, Ill. 60601. AWS - American Welding Society, Inc., 550 N.W. LeJeune, P, 0. Box 3510400 Miami, Fla. 33135, i other specifications and proprietary items are as noted, j The Contractor shall maintain one (1) copy of each of the applicable ; standards at the construction field office or job site. ASTM-A82 Standard Specification for Cold-Drawn Steel Wire for Concrete Reinforcement ASTM-A185 Standard Specification for Welded Steel Wire Fabric Concrete Reinforcement ASTM-A615 Standard Specification for Deformed and Plain Billet- Steel Bars for Concrete Reinforcement i ACI-315 Manual of Standard Practice for Detailing Reinforced Concrete Structures ACI-318 Building Code Requirements for Reinforced Concrete AWS-D1.4 Structural Welding Code-Reinforcing Steel CRSI Manual of Standard Practice r 3 1 03200-1 1.03 DELIVERY, STORAGE AND HANDLING I` r A. STORAGE Steel reinforcement shall be stored above the surface of the ground upon platform skids, or other supports and shall be protected as far as practicable from mechanical injury and Y surface deterioration caused by exposure to conditions producing rust, When placed in the work, it shall be free from dirt, her forei e reinforcementpshall beltaggedtand storednforteaselof correlation with shop drawings. 2.00 PRODUCTS 2.01 MATERIALS i A. BARS All bar reinforcement shall conform to Deformed Billet-Steel Bars for Concrete Reinforcement, ASTM Designation A-615. Unless 1 otherwise specified, bars shall be Grade 60 with a minimum yield strength of 60,000 psi, B. WIRE FABRIC Wire for fabric reinforcement shall be Cold-)raven steel wire conforming to the requirements for Cold-Drawn Steel Wire for Concrete Reinforcemment, ASTM Designation A-82, and Fabricated in accordance with ASTM Designation A-18G. i a C. SUPPORTS Bar supports or chairs shall be furnished in accordance with the Concrete Reinforcing Steel Institute Manlal of Standard j Practice. Bar supports which will be used in slabs or beams which will have a rubbed finish on the bottom side shall have uniform nigh density polyethylene tips on the legs. The tips shall be approximately 1/4-inch thick between the ends of the chair legs and the form, and shall be as manufactured by Plastichair or equal. + 2.02 FABRICATION A. BENDING The reinforcement shall be bent cold by machine to shapes indicated on the Plans. Bends shall be true to shapes indicated, and irregularities in bending shall be cause for refection. Unless otherwise shown on the Plans, all Hook and Bend Details and Tolerances shall conform to the requirements of ACI-315 and ACI-318. a 03200-2 1 ,a 1 I . B. SHOP DRAWINGS The Contractor or the Supplier shall prepare and submit detailed shop drawings for each detail of the general plans requiring the JJ use of reinforcing steel. Each sheet shall have a title. The 1 shup drawings shall be submitted in duplicate for the review of i the Engineer, After review and making any necessary corrections, six (6) copies of the shop drawings shall be submitted for final approval, The approved shop drawings will be distributed as follows: 2 - Engineer I - Supplier 2 - Contractor 1 - Owner 1 The Shop Drawings shall conform to the recommendations of ACI-315. ,1 J 3.00 EXECUTION ' 1 j 3.01 GENERAL CONSTRUCTION REQUI,EMENTS A. APPROVAL BY THE ENGINEER No concrete shall be deposited until the Engineer has inspected and approved the placing of the reinforcing steel and given permission to place concrete. Exposed reinforcing steel intended for bonding with future extensions shall be effectively protected from corrosion, B. SPLICES 1• Lap Splices: No splicing of bars, except when shown on tisa Plans, will be permitted without the written approval the Engineer. Approval of bar bending schedules or ofof placing drawings will constitute written approval. Lap splices which are permitted shall have a lap in accordance with the table of Tension Bar-Laps and Embedment lengths shown on the Plans e as s . The bar s shall be ri wired at all splices in a manner approvedgbylthelEnginoer, Sheets of wire fabric shall overlap each other sufficiently I1 to maiitain a uniform strength and shall be securely i fastened, 2, Welded Splices: WeldInC of reinforcing str,el is not iii permitted without tho written approval of the Engineer, When permitted, the welding must br, done in coripliance with the requirements of AWS-012.1, 3. Mechanical Splices: Mechanical splices where shown on the plans or permitted by the Engineer shall be made using "Cadweld" (or equal) reinforcing bar connectors, installed 03200-3 i 1 r Y in strict accordance with the manufacturer's instructions and recommendations. The mechanical device shall develop the full tensile strength of the bar, C. TOLERANCES All reinforcement shall be placed as shown on the Plans with the following maximum tolerances: Cover + 1/8" Specings + 3/16" in 12" D. PLACING 1, General: Steel reinforcement shall be placed in the exact position as shown on the Plans and held securely in place during the placing of the concrete. The minimum clear distance between bars shall be two times the bar diameter, € Vertical stirrups shall always pass around the main tension F members and be securely attached thereto. All reinforcing ~ shall be wired together at a sufficient number of intersections to produce a sound or sturdy . ~ mat or ca reinforcement that will maintain the reinforcement ine the intended positions when the concrete is poured. Every 4th intersection is considered maximum unless otherwise authorized by the Engineer, 2, Approval: No concrete shall be deposited until the Engineer has inspected and approved the placing of the reinforcing i steel and given permission to place concrete. Exposed reinforcing steel intended for bonding with future i« extensions shall be effectively protected from corrosion. 3. Tieing and Supporting: The reinforcing steel in all concrete slabs shall be held firmly in place, as shown on the drawings, by wire supports or "cha4~,s". Wire sizing and spacing of the chairs shall be sufficient to properly support the steel, and shall be in accordance with CRSI Manual, "Recommended Practice for Placing Bars," 4, Spacers: The reinforcing steel in all concrete wails shall % be spaced its proper distance from the face of the forms, f as shown on the drawings, by means of approved galvanized metal spacers or approved precast mortar or concrete blocks. Before any concrete is placed, all mortar blocks to be used for holding steel in position adjacent to formed surfaces shall be cast in individual molds, at which time the blocks shall be immersed in water for the remainder of at least a four-day curing period, The blocks shall preferably be cast with the sides beveled and in such manner that the size of the block increases away from the surface to be placed against the forms. Blocks in the form ' 03200-4 r C . 1 ~i i of a frustum of a cone or pyramid are preferred. Suitable ? tie wires shall be provided in each block for anchoring the block to the steel, and to avoid displacement when placing ' the concrete. Unless specifically authorized by the Engineer, the size of the surface to be placed adjacent to the forms shall not exceed two and one-half (2-1/2") inches square or the equivalent thereof when circular or rectangular areas are provided. Blocks shall be accurately cast to the thickness required, and the surface to be i placed adjacent to the forms shall be a true plane free of surface imperfections. ENO OF SECTION i 1 k . f i l 2 +f l I l t y s 03200-5 t 03305 CAST-IN-PLACE CONCRETE i 1.00 GENERAL 1 Concrete shall be composed of portland cement, fine aggregate, coarse aggregate, and water, properly proportioned and mixed as hereinafter specified, All structural concrete shall be 3000 psi; concrete for blocking, cradle, or encasement shall be 1500 psi. I; 2,00 PRODUCTS 2,01 MATERIALS Portland Cement shall conform to the Specifications and tests for Type I Portland Cement of the American Society for Testing Materials, ; 11 Designation C-150. y Fine aggregate shall consist of natural, washed and screened sand having clean, hard, strong, durable, uncoated grains complying with the requirements for ASTM C33, The sand shall generally be of such size that all will pass a 3/8 inch sieve, at least 95% pass a 1/4 Inch screen and at least 15% be retained on a No. 8 sieve, Aggregate shall not contain strong alkali, or organic material which gives a color darker than the standard color when tested in accordance with i ASTM Specification Designation C4, Coarse aggregate shall be evenly graded and shall consist of sound, washed and screened gravel, free of clA,,, balls, or clean, crushed ,,tone, having clean, hard, strong, durable, uncoated particles free from dust, clay balls, injurious amounts of soft, friable, thin, elongated, or laminated pieces, alkali, organic, or other deleterious : matter, Coarse aggregates shall comply with ASTM C33 and shall not have more than 5% passing a No, 4 sieve and the maximum size shall not exceed that hereinafter specified; maximum size is defined as being the next larger screen than the one on which 15% is retained. Water for concrete shall be clean and free from oil, acid, alkali, organic matter or other harmful impurities. Water which is suitable for drinking or for ordinary household use will be acceptable for concrete. Where available, wager shall be obtained from mains of a waterworks system. Where aluminum anchors, aluminum shapes, or aluminum electrical conduits are embedded in concrete, all contact surfaces shall be painted with zinc chromate primer in accordance with United States Joint Army-Navy Specification JAN-P-735, The paint shall be allr4ed to thoroughly dry before the aluminum is placed in contact with she concrete, r ' 03305-1 Aluminum surfaces to be placed in contact with concrete, wood, or E masonry construction, except where the alumianlum is to be embedded in concrete, shall be given a heavy coat of an resistant bituminous paint before installation, kali- Shall meet the requirements of United The bituminous paint used States Military Specification MIL-P-6883. The paint shall be applied as it is received from the F manufacturer without the addition of any thinner. All steel or other ferrous metal to be mounted on or placed in contact with dry/cured concrete such as valve operator floor stands, ienleaccordancectrical eon tc. 0903all be pal. paintteed on the mounting surface 3,00 EXECUTION 4 3.01 CONCRETE PROPORTIONS AND CONSISTENCY f , Concrete shall be proportioned to give the necessary workability and strength and shall conform to the following governing requirements: Min. 28 Da 1 y Min, Cement Max. Size Max, Water 3I Compressive Sags Per of Coarse Gals, Per Strength -psi Cu. Yd. Aggregrate 8d Slump I 9 Inches Use I 41000 6.5 1" ~ 1 3,000 5.5 1 5,40 ^ 3-4 General 11 8.25 4-6 general j 11500 4.0 11-1121, 6 25 0 4 Grout 810 None 8.00 - Lean Con- The proportions of fine and coarse aggregate shall be such that the requirements of the following table are complied with: Maximum Size of Coarse Aggregate Ratio of Coarse Aggregate to Fine i Aggregate on Basis of Dry and Rodded Volumes Minimum 3/4° a-x m-um 4 In and Over 0.6 1.0 ?.,5 2.0 In no case shall the amount of coarse material be such as to pro duce harshness in placing and honeycombing in the structure when forms are removed. In the determination of the amount of water required for mix, consideration shall be given to the moisture content of the aggregate. The net amount of water in the mix will be the amount added at the mixer; plus the free water in the ag regate; and minus the absorption of `he aggregate, based on thirty ?30) minutes 03305-2 I` I absorption period, No water allowance will be made for evaporation after batching. The methods of measurement of materials shall be such that the proportions of water to cement can be closely controlled during the progress of the work and easily checked at any time by the Engineer or his representative. To avoid unnecessary or haphazard changes in " consistency, the aggregate shall he obtained from sources which will insure a uniform quality and grading during any single day's operation and they shall be delivered to the work and handled in such manner that the variation in moisture content will not interfere with the steady production of concrete of reasonable degree of uniformity. All sources of supply shall be approved by the Engineer. All material shall be separately and accurately measured. Measurement, may be made by weight or by volume, as may be elected by the Contractor; however, all equipment for measurement of materials shall be subject to approval by the Engineer, The proportions of the mix shall be such as to produce concrete that can be puddled readily into the corners and angles of the forms and around the reinforcing without excessive spading or vibrating, and without segregation or undue accumulation of water or laitance on the surface, 1 3,02 PLACING CONCRETE The Contractor shall give the Engineer sufficient advance notice before starting to place concrete in any unit of the structure to permit inspection of the forms, the reinforcing steel placement, and preparation for pouring. Unless authorized by the Engineer, no concrete shall be placed in any unit prior to the completion of all form work and the placement of all reinforcement for that unit, The sequence of placing concrete shall be as provided on the Plans or ! i in the Specifications, The operation of depositing and compacting the concrete shall be conducted so as to form a compact, dense, ! Impervious mass of uniform texture, which will show smooth faces on all surfaces. The placing shall be so regulated that the pressures caused by the plastic concrete shall not exceed the loads used in the design of forms. i Careful attention shall be given by the Contractor to the proper j curing of all concrete. The curing methods shall use sheet materials 1 conforming to ASTM C171 or membrane curing compound conforming to ASTM C309, Membrane curing is not permitted on surfaces to be rubbed or on surfaces on which additional concrete, mortar or terrazzo is to be applied. Unless the curing method is otherwise noted or specified, the curing method shall be selected by the c,mtractor and submitted to the Engineer for approval, • 03305-3 ! All concrete shall be cured for a period of seven consecutive days. 3,03 BLOCKING OF PIPE FITTINGS Concrete bloc.~ing shall be placed at bends, tees, wyes, crosses, plugs, etc. she concrete blocking shall be placed so as to rest against firm urrjisturbed trench walls. The supporting area for each block shall be sufficient to withstand the thrust, including water hammer. Each block, except those for upward thrusts, shall rest on a firm, undisturbed foundation of trench bottom. Blocking at bends shall be computed based upon pipe thrust at bends, or tees, with internal pressure of 50 psi. Where upward thrusts are to be blocked, the concrete blocking shall be of sufficient weight to resist the thrust and the concrete shall be reinforced as directed by the Engineer. Blocking size shall be computed based upon a maximum safe allowable soil bearing pressure of 1500 pounds per square foot of undisturbed earth. The concrete blocking shall be placed against undisturbed trench walls, with a minimum of 18 inches between trench wall and pipe, Blocking shall extend a minimum of 0,75 x pipe diameter below and above the centerline of pipe and shall not extend beyond any ,joints. If requested by the Engineer, the ends of the thrust blocks shall be contained in wood or metal forms, Where upward thrusts are to be blocked, the concrete shall be formed from the centerline of pipe upward. 3.04 RUBBED FINISH All exposed vertical concrete surfaces shall receive a two (2) coat application of THOROSEAL PLASTER MIX, 1/8" to 1/4" in thickness, in j r accordance with the manufacturer's recommendations. Form treatments or curing compounds shall not contain any ingredients which might stain or otherwi3e prevent a good bond to the concrete, Do not app1 when temperature is 40°F or expected to drop below 40°F within 24 y i hours after application. Prepare surface according to manufacturer's recommendations, Apply a key coat of THOROSEAI. at a rate of 2 lbs, per sq. yard by brush using 1 part ACRYL 60 to 3 parts of clean water. Allow this coat to dry 5 days. Next apply a trowel coat of THOROSEAL PLASTER 1 MIX using a solution of 1 part of ACRYL 60 and 3 parts clean water. ; f Apply at the rate of 4 to 6 lbs. of mix per sq. yard. Apply and cure 1 according to manufacturer's recommendations. END OF SECTION k f 03305-4 a 05710 MISCELLANEOUS METALS 1,00 GENERAL 1.01 SCOPE Furnish and install all miscellaneous and ornamental specialty metal work shown on the drawings or specified herein. Provide anchors, hangers, rods, bars, brackets or fasteners required to complete this work and to connect to work by others. Provide inserts for :oncrete where necessary. Submit six (6) copses of shop drawings for all miscellaneous metals SHOP DRAWINGS, accordance approval General neer's with toobeginning any work. for Engi l 1.02 FABRICATION When a specific manuf?.rturer's article or apparatus is specified, it ' shall be applied, assembled, or otherwise installed in accordance with the manufacturer's specifications, Insofar as possible, all items shall be shop fabricated and assembled ready for erection. Fabricate articles to proper shape with sharp lines and smooth surfaces. Connections shall be securely welded, .r 14 E bolted or riveted and welds shall be dressed smooth on exposed surfaces. Thickness of metal and component parts shall be of size adequate to withstand strains reasonably anticipated for its usage, Provide lugs, rabbets or brackets to allow for proper assembly and Exposed edges and ends of metal shall be dressed smooth fit. close where exposed. Castings shall be of proper design, sound and exposed parts shall have no blemishes, Remove fins, casting lugs, or other unnecessary parts, grind rough edges and shape for fit with other component parts. I ~ 2.00 MATERIALS A. STEEL ROLLED SHAPES ASTM A36, having a minimum yield strength not less than 36,000 psi. B, MISCELLANEOUS STEEL ASTM A-36, Plates and bars shall conform to ASTM A-284, 05710-1 a x C. CAST STEEL, GENERAL PURPOSE ASTM A-27, Grade 65-35 D. CAST STEEL, STRUCTURAL t ASTM A148, Grade 80-50, i r• E. STEEL FORGINGS ASTM A668, Class C or F. F. CAST IRON 1 Soft, gray iron, ASTM A-48, Class 30, 30,000 psi tensile strength. Accessories and connections shall be steel unless noted otherwise, i G. GALVANIZING i Galvanized metals shall conform to ASTM A-123 and ASTM A-386. E H. WELDING ELECTRODES Electrodes shall be of the type- required for the purpose f intended. Use E70 series for manual arc welding, . I. ALUMINUM i i Aluminum shall be of an alloy suitable for the function intended. Finish shall be as noted on the drawings, otherwise shall be of recognized industry standard for the type of component, J. FASTENERS ' Fasteners shall be of the type required for the purpose intended and particular application and shall be of a recognized industry f standard for the type of components. Fasteners shall include; I Masonry Sleeve Anchors - Molly "Parasleeve", Ramset "Dyna Bolt", or approved equal, Concrete Expansion Bolts - Hilti "Kwik Bolt" or approved equal Hollow Wall Fasteners - Hilti "Kwik Tog" or approved equal Plaster and Drywall Fasteners - Plastic insert wedges Adhesive anchors - Hilti "HVA Adhesive Anchor" or approved equal K. SHOP PAINT All ferrous metals shall receive one coat of rust-inhibitive primer as specified in Section 09905, PLANT PAINTING. • 05710-2 r : I_ L. WELD WV HERS { Furnish welding washers of a design to conform to deck configuration for all welds. 3.00 EXECUTION 3.01 MISCELLANEOUS STRUCTURAL FABRICATION Steel components shall be shop fabricated of standard structural shapes, or bent plates to the designs shown on the drawings. Frames shall be shop assembled by v„ilding or bolting. Set frames in place plumb, level and square in all directions and securely brace to prevent displacement until built into construction, < 3.02 MISCELLANEOUS FABRICATION Fabricate ali miscellaneous steel components, rack, stands, supports, or other ite;is to the design noted on the drawings and utilizing `I structural shapes, bent plates, sheet steel or other material as required to construct the item. Generally, assembly shall be by welding with all joints ground smooth, Provide brackets, fillets, plates and anchor bolts as required and finish with one coat of shop paint. 3.03 MISCELLANEOUS FRAMES Fabricate frames as detailed by welding, bolting or fasteners using best modern practice. Frames shall be true to dimension and shall be set plumb and securely braced to prevent displacement until built into construction. Provide welding frames it each roof penetration for mechanical equipment, including exhaust fans, flues and ventilators. Frames shall be field welded across top chords of steel joist and shall be of sizes required by equipment. Provide holes in outstanding angle legs for boltirnr a)od curbs. 3.04 WELDED FIELD CONNECTION Welds shall be made only by operators who have previously qualified by tests, as prescribed by the "Standard Qualifications Procedure" in the "Structural Welding Code - Steel" by the American Welding Society ' to perform the type of work required. The Contractor shall provide the certification that welders have passed qualification test within six months gust prior to performance of work. All field welds shall be of the type indicated on the drawings or specified herein, All welding must be approved. END OF SECTION 05710-3 1 V ' I 1 1 M 09872 TANK PAINTING 1.00 GENERAL 1.01 SCOPE the con of The work oa d is thesection includes • surfaces, a 1.02 RELATED 'ARK SPECIFIED ELSEWHERE Coating and painting of all other surfaces is specified in Section 09905. 1.03 REFERENCE SPECIFICATIONS AND STANDARDS general aspects of other requirements of A. Without limiting the g re aration, coating and these specifications, all surface p p form to the painting Of ior nulrementsdofxtheiSteelrStructureslPainting Council re applicable q ' printed instructions. and the manufacturers g, The Er decision anylofbtheireference specif1ications and and/or con standards contained herein. 1.04 CONTRACTOR ractical Lxperience and The Contractor shall have three years of specified products to successful history In the application surfaces irement water tanks. aUloistrofureferencesaandsJobtantiate this requ ti s completions. 1.05 QUALITY ASSURANCE A. GENERAL Quality assurance procedures and practices shall be utilized to monitor all phases of surface preparation, application Procedures inspection throughout the duratio, of the project, be utilized or practices nmeetprecognized adef ndiacceptediprofessional provided they standards and are approved by the Engineer. ` B, SURFACE PREPARATION Surface preparation will be based upon comparison with, "Pictorial Surface Preparation Standard; for Painting steel 09872-1 i Surfaces", SSPC-Vis i ASTM Designation D220; "Standards Methods of Evaluation Degree of Rusting on Painted Steel Surfaces", SSPC-Vis-2 ASTM Designation D610; Visual Standard for surfaces of New Steel Airblast Cleaned with Sand Abrasive". C. APPLICATION No coating or paint shall be applied; when the surrounding air temperature or the temperature of the surface to be coated or ' painted is below 40 degrees F.; to wet or damp surfaces or in rain, snow, fog or mist; when the temperature is less than 5 s degrees F. above the dewpoint; when it is expected the air temperature will drop below 40 degrees F. six hours after application of coating and paint. Dewpoint shall be measured by use of an instrument such as a Sling Psychrometer in conjunction with U.S. Department of Commerce Weather Bureau Psychrometric Tables. 1 If above conditions are prevalent, coating or painting shall be delayed or postponed until conditions are favorable, The day's f coating or painting shall be completed in time to permit the film sufficient drying time prior to damage by atmospheric conditions. D. THICKNESS AND HOLIDAY CHECKING Thickness of coatings and paint shall be checked with a ( non-destructive, magnetic type thickness gauge. Use an instrument such as a Tooke Gauge if a destructive tester is deemed necessary, Coating integrity of interior coated surfaces shall be tested with an approved inspection device, Holiday detection shall be performed prior to application of aluminum or metallic finish coats, Non-destructive holiday detectors shall not exceed 67-1/2 volts nor shall destructive holiday detectors exceed the voltage recommended by the manufacturer of the coating system. For thicknesses between 10 and 20 miles (250 1 microns and 500 microns) a non-sudsing type wetting agent, such 1 as Kodak Photo-Flo, shall be added to the water prior to wetting I the detector sponge. All pinholes shall be marked, repaired in accordance with the manufacturer's printed recommendations and retested. No pinholes or other irregularities will be permitted in the final coating, E. INSPECTION DEVICES i I The Contractor shall furnish, until final acceptance of coating ` and painting, inspection devices in good working condition for detention of holidays and measurement of dry-film thickness of r coating and paint, The Contractor shall also furnish U.S, Department of Commerce, National Bureau of Standards certified J thickness calibration plates to test accuracy of dry-film 1 thickness gauge and certified instrumentatioi to test accuracy y 09872-2 1 4 7 of holiday detectors. The Engineer may elect to use his own iii elcometer paint thickness guage and his own Tinker and Rasor a holiday detector, at his option. Dry-film thickness gauges and holiday detectors shall be made p available for the Engineer's use at all times until final # acceptance of application. Holiday detection devices shall be operated in the presence of the Engineer. s. F. WARRANTY INSPECTION Warranty inspection shall be conducted during the eleventh month following completion of all coating and painting work. All defective work shall be repaired in accordance with this specification and to the satisfaction of the Engineer/Owner. ,l 1,06 SAFETY AND HEALTH REQUIREMENTS i A. GENERAL In accordance with requirements set forth by regulatory agencies 4 applicable to the construction industry and manufacturer's printed instructions and appropriate technical bulletins and manuals, the Contractor shall provide and require use of personnel protective lifesaving equipment for persons working in or about the project site, B. HEAD AND FACE PROTECTION AND RESPIRATORY DEVICES Equipment shall include protective helmets which shall be worn by all persons while in the vicinity of the work. In addition, workers engaged in or near the work during sandblasting shall 1 wear eye and face protection devices and air purifying, halfmask or mouthpiece respirator with appropriate filter. Barrier creams shall be used on any exposed areas of skin. 1 C. VENTILATION J Where ventilation is used to control hazardous exposure, all !9 equipment shall be explosion proof. Ventilation shall reduce the concentration of air contaminant to the degree a hazard does not exist, Air circulation and exhausting of solvent vapors shall be continued until coatings have fully cured. 1 D, SOUNDS LEVELS c Whenever the occupational noise exposure exceeds maximum allowable sound levels, the Contractor shall provide and require the use of approved ear protective devices. i 4 ~ . 09672.3 1 Y 1 I E. ILLUMINATION Adequate illumination shall be provided while work is in progress, including explosion-proof lights and electrical equipment. Whenever required by the Engineer, the Contractor ` shall provide additional illumination and necessary supports to cover all areas to be inspected. The level of illumination for h inspection purposes shall be determined by the Engineer. i F. TEMPORARY LADDERS AND SCAFFOLDING D All temporary ladders and scaffolding shall conform to r applicable safety requirements. They shall be erected where requested by the Engineer to facilitate inspection and be moved by the Contractor to locations requested by the Engineer. 2.00 PRODUCTS 2.01 GENERAL i' A. Materials specified are those that have been evaluated for the specific service. Products of the Tnernec Co, are listed to establish a standard of quality. Equivalent materials of other manufacturers may be substituted on written approval of the Engineer. Requests for substitution shall include manufacturer's literature for each product giving the name, product number, generic type, descriptive information, solids by volume, recommended dry film thickness and certified test reports showing results to equal the performance criteria of the products specified herein. In addition, a list of five projects shall be submitted in which each product has been used and rendered satisfactory service. i r Any material savings shall be passed to the Owner in the form of r a contract dollar reduction. i Manufacturer's color charts shall be submitted to the Engineer at least 30 days prior to paint application. General Contractor and painting Contractor shall coordinate work so as to allow sufficient time (normally seven to ten days) for paint to be delivered to the job site. B. All materials shall be brought to job site in original sealed containers. They shall not be used until the Engineer has inspected .ontents and obtained data from information on containers or label, Materials exceeding storage life recommended by the manufacturer shall be rejected. a 09872-4 9 1 } z C. All coatings and paints shall be stored in enclosed structures to protect them from weather and excessive heat or cold. Flammable coatings or paint must 'oe stored to conform with City, County, State and Federal safety codes for flammable coating or paint materials. At all times coatings and paints shall be protected from freezing. 0. INTERIOR TANK COATING SYSTEM: POLYAMIDE EPOXY Surface Preparation: SSPC-SP10 After surface preparation and prior to painting, all weld seams must brushed Allow with a of primer 20-1255. ; coat. 1st Coat: Tnemec Series 20-1255 Beige Pota-Pox at 4.0.-6.0 dry mils. ' 2nd Coat: Tnemec Series 20-2000 White Pota-Pox at 4.0-6.0 dry mils. Total dry film thickness shall be 10.0 mils minimum. EXTERIOR TANK COATING SYSTEM: MEDIUM PERFORMANCE GLOSS ALKYD Surface Preparation: SSPC-SP6 - I~ 1st Coat; Tnemec Series 37-77 Chem-Prime at 2.5.-3.5 dry mils. 2nd Coat: Tnemec Series 82 Silicone Alkyd at 1,5-2.0 dry mils. M 3rd Coat; Tnemec Series 82 Silicone Alkyd at 1.5-2.0 dry mils. Total System 6.0 mils minimum. 2,02 DISINFECTION MATERIALS oAWWAtStandardsaandcregulatoryaagenciesequirements of applicable 3.00 EXECUTION ` 3.01 GENERAL All surface preparation, coating and painting shall conform to applicable standards of the Steel Structures Painting Council, and the manufacturer's printed instructions, Material applied prior to approval of the surface by the Engineer shall be removed and reapplied to the satisfaction of the Engineer at the expense of the Contractor. 09872-5 1 1 i i ~ All work shall be performed by skilled craftsmen qualified to perform } the required work in a manner comparable with the best standards of practice. Continuity of personnel shall be maintained and transfers of key personnel shall be coordinated with the Engineer. The Contractor shall provide a supervisor at the work site during cleaning and application operations. The supervisor shall have the authority to coordinate work and make decisions pertaining to the fulfillment of the contract. Dust, dirt, oil, grease or any foreign matter that will affect the adhesion or durability of the finish must be removed by washing with clean rags dipped in an approved cleaning solvent and wiped dry with clean rags. Coating and painting systems include surface preparation, prime coating and finish coatings. Unless otherwise specified, prime 1 coating shall be field applied, Where prime coatings are shop i applied, the Contractor shall instruct suppliers to provide the prime coat compatible with the finish coat specified. Any off-site work which does not conform to this specification is subject to rejection by the Engineers. All interior tank surfaces, to be coated with + epoxy, shall be field cleaned and primed. Shop applied prime coatings which are damaged during transportation, J construction or installation, shall be thoroughly cleaned and touched up in the field as directed by the Engineer. The Contractor shall use repair procedures which insure the complete protection of all adjacent primed. The specified repair method and equipment may include wire brushing, hand or power tool cleaning or dry air blast cleaning. In order to prevent injury to surrounding painted areas blast cleaning may require use of lower air pressure, small nozzle and abrasive particle sizes, short blast nozr'; distance from surface shielding and masking. If damage is too extensive or uneconomical to touch-up, then the item shall be recleaned and coated or painted as directed by she Engineer. s c The Contractor's coating and painting equipment shall be designed for application of materials specified and shall be maintained in first class working condition. Compressors shall have suitable traps and filters to remove water and oils from the air. Contractor's equip- ment shall be subject to approval of the Engineer. Application of the first coat shall follow immediately after surface + preparation and cleaning and before rust bloom occurs. Any cleamld areas not receiving first coat within this period shall be recleaned prior to application of the first coat, Prior to assembly, all surfaces made inaccessible after assembly shall be prepared as specified herein and shall receive the coating or paint system specified, , 0.)872-6 i r 1 3.02 SURFACE PREPARATION The latest revision of the following surface preparation specifica- tions of the Steel Structures Painting Council shall form a part of this specification; 1. Solvent Cleaning (SSPC-SP1): Removal of oil, grease, soil and other contaminants by use of solvents, emulsions, cleaning compounds, steam cleaning of similar materials and methods which involve a solvent of cleaning action. 2. Hand Tool Cleaning (SSPC-SP2)_; Removal of loose rust, loose ro TTscale an other er mental foreign matter to degree specified by hand chipping, scraping, sanding and wirebrushing. 3, power Tool Cleaning_(SSPC-SP3)t Removal of loose rust, loose 1 FM sca e an other detrimental foreign matter to degree specified by power wirebrushing, power impact tools or power sanders. f 4. White Metal Blast Cleaning SSPC-SP5 Blast cleaning to a gray-white uniform metallic color until each element of surface area is free of all visible residues. 5. Commercial Blast Cleaning (SSPC-SP6); Blast cleaning until at least two-th rds of each element of surface area is free of all visible residues. i 6. Brush-off Blast Cleaning (SSPC-SP7); Blast cleaning to remove loose rust, loose moose rust, oose m scale other detrimental foreign matter to degree specified. ' 7. Near White Blast Cleanin (SSPC-SP10 ; Blast cleaning to near yT wh tie metaess, until at least 95 percent of each element of surface area is free of all visible residues. Slag and weld metal accumulation and spatters not removed by the i Fabricator, Erector or Installer shall be removed by chipping and grinding. All sharp edges shall be peened, ground or otherwise blunted as required by the Engineer. j { Field blast cleaning for all surfaces shall be by dry method unless i otherwise directed. s a Particle size of abrasives used in blast cleaning shall be that which will produce a 1-1/2 - 2 mil (37.5 micros - 50.0 microns) surface profile or in accordance with recommendations of the manufacturer of the specified coating or paint system to be applied. Abrasive used in blast cleaning operations shall be new, washed graded and free of contaminants that would interfere with adhesion of j 09872-7 Qk I r I I , i coating or paint and shall not be reused unless specifically approved by the Enginer, During blast cleaning operations, caution shall be exercised to i insure that existing coatings or paint are not exposed to abrasion from blast cleaning. The Contractor shall keep the area of his work in a clean condition q and shall not permit blasting materials to accumulate as to consti- tute a nuisance or hazard to the prosecution of the ;,irk or the operation of the existing facilities. Blast cleaned surfaces shall be cleaned prior to application of specified coatings or paint. No coatings or paint shall he applied over damp or moist surfaces. All welds shall be neutralized with a suitable chemical compatible with the specified coating materials, Surface preparation for the specific system shall be as noted in Section 2.01 Paragraph D. 3.03 APPLICATION, GENERAL a~ Coating and paint application shall conform to the requirements of the Steel Structures Painting Council Paint Application Specification SSPC-PA1, latest revision, for "Shop, Field and Maintenance Painting", the American Water Works Association and the manufacturer of the coating and paint materials, Thinning shall be permitted only as recommended by the manufacturer { and approved by the Engineer, t Each application of coating or paint shall be applied evenly, free of brush marks, sags, runs, with no evidence of poor workmanship, Care shall be exercised to avoid lapping on glass or hardware, Coatings and paints shall be sharply cut to lines. Finished surfaces shall be free from defects or blemishes, Protective coverings or drop cloths shall be used to protect floors, fixtures, and equipment, Care shall be exercised to prevent coatings or paints from being spattered onto surfaces which are not to be coated or painted. Surfaces from which materials cannot be removed satisfactorily shall be recoated or repainted as required to produce a finish satisfactory to the Engineer, When two coats of coating or paint are specified, where possible, the first coat shall contain sufficient approved color additive to act as an indicator of coverage or the two coats must be of contrasting color, T 09872-8 z I 1 Film thicknesses per coat specified in Section 2.01 Par, 0s are i ILI minimum required. Contractor shall apply additional necessary to achieve the specified thickness, All materials shall he applied as specified, All welds and irregular surfaces shall receive a brush coat of the a specified product prior to application of the first complete coat, # 3.04 COATING SYSTEMS APPLICATION After completion of surface preparation as specified for the specific system, materials shall be applied as noted in Section 2.01 Par. D. 3,05 COLOR SCHEME The Owner w111 select colors for the project, The Contractor shall g chart manufacturer's coating and paintingo the Engineer operations. 3.06 SOLVENT VAPOR REMOVAL All solvent vapors shall be completely removed by suction type exhaust fans and blowers before placing in operating service. i 3.07 CLEAN UP Upon completion of the work, all staging, scaffolding and containers i shall be removed from the site or destroyed in a manner appontai by the Engineer. Coating or paint spots and oil or stains upon adjacent surfaces shall be removed and the job site cleaned. All damage to surfaces resulting from the work of this section shall be cleaned, repaired, or refinished to the satisfaction of the Engineer at no cost to the Owner. END OF SECTION j 09872-9 R I j ` 09905 PLANT PAINTING 1.00 GENERAL 1.01 SCOPE The work covered by this item of the Specifications includes furnishing all paint, labor, and materials and performing a operations in accordance with this section of the Specifications and the applicable portion of the Plans. The contractor shall furnish all labor, material, equipment and services for cleaning and painting of surfaces as follows; A. All metal work, equipment and machinery (except stainless steel, aluminum, and architectural work), f B• All exposed piping and valves, except PVC piping (including pipe and valves in vaults), C. All structural steel. Finish field painting shall not be applied to machinery, equipment or other piping until operational tests are completed. 1.02 STORAGE AND CLEAN-UP 1 The Contractor shall use one convenient location at each site for keeping all materials and doing all mixing, etc, shall be properly protected with drop cloths, Oilylragsoandhwasteace ► shall be frequently removed and under no circumstances shall they be allowed to accumulate, At the completion of the work, the Contractor shall leave ctorytcondiain surfaces and 1,03 SUBMITTALS The Contractor shall submit six (6) sets of full and complete shop drawings on the paint in accordance with the General Conditions, Article 6, SHOP DRAWINGS, All of the data shall be complete and shall include a complete description of the paint system offered, including color codes and all pertinent engineering data required for a complete evaluation of the submittal. Submittal data shall be in such form and so presented that the Engineer may readily review the i data, i f 09905-1 i 2.00 PRODUCTS i 2.01 MATERIALS A. GENERAL Coatings shall be delivered to the job in original containers marked with the name of the manufacturer and the specification number. The coating shall not show excessive settling in a freshly opened full can and shall be easily redispursed with a paddle to a smooth, homogenous state. It shall show no curdling, livering, caking, or color separation and shall be free from lumps and skins. Only the highest grade paint of each manufacturer and that which ' is suitable for the use intended will be approved. Only those thinners and solvents specified in the paint formulas shall be used, More than the prescribed amount of thinner may be added only to the extent of maintaining the minimum spreading rate designated in each individual formulation. 'M The Contractor shall provide the Engineer with a color chart which will show the various colors available, and the Owner will select colors to be used, B. RUST PENETRATING PRIMER This primer shall be the best grade primer recommended by the , finish coating manufacturer for use under the metal protective paint. Primer and finish coats must be the product of one manufacturer, i C. ENAMEL PAINT Paint for exterior surfaces shall be Tnemec Enduratone, DuPont OULUX, Metal Protective, Koppers Rustarmor, Mobil (equal), or approved equal. The color shall be factory mixed and all paint for this project shall be from the same mixed batch. Chips shall be submitted to the Owner for final color selection. 2,02 PREPARATION OF METAL SURFACES A. GENERAL 1 All Surfaces shall be suitable cleaned before applying coatings. All mill scale, rust, and other foreign matter shall be removed by sandblasting or pickling as specified below, B, FIELD PREPARATION OF SURFACES All metal surfaces exposed only to the elements and direct sunlight shall be thoroughly cleaned of all mill scale, rust, F 09905-2 f ' f 1 and other foreign matter by sandblasting to a gray metal in accordance with SSPC-SP6, "Commercial Blast Cleaning". All sandblasting shall be done after erection unless otherwise approved by the Engineer, Any surface that is sandblasted shall be thoroughly cleaned of sand and dust and the surface coated the same day it is sandblasted, All sand used in sandblasting operations, sediment in the clarification basin, rust, paint and scale accumulating from cleaning operations, and all other material in the basin, shall be removed by the Contractor. All sandblasted surfaces shall be swept clean again after all blasting is c.,npleted. In the event that sandblasted surfaces are not coated immediately after cleaning and rust reforms on sandblasted surfaces, such rusty surface shall be re-cleaned by sandblasting again y immediately before coating. R C. SHOP PREPARATION OF SURFACES I All exterior metal surfaces may be shop cleaned by either pickling or blasting as described below. Heavy deposits of oil, grease, etc., shall be removed as required before pickling or blasting. Prime and finish coats shall be as specified and are the same for either cleaning method, 1, Pickling: All steel shall be pickled in a suitable solution of hot sulphuric, hydrochloric, or phosphoric acid for the time required to remove all mill scale, rust, and scale, ; The solution shall contain an inhibitor to prevent base 1 metal attack, After draining momentarily, all steel shall be thoroughly rinsed with water. Following water rinsing, the steel shall be immersed in hot dilute phosphoric acid to further neutralize the surface and to provide a rust inhibitive iron phosphate paint base, The primer shall be applied while the steel is still warm except for the case of large assemblies where the separate parts must be ' pickled before assembling, 2, Blasting: All exterior steel surfaces shall be grit blasted to remove all mill scale, rust and scale, To insure proper i cleaning, the metal surfaces shall be blasted to a gray metal finish and the maximum particle size shall bra no larger than that passing a 16 inch screen, The blotted surface shall be primed immediately after cleaning and free of dust, oil or moisture at the time of painting. 0. WORKMANSHIP All paint and finishing materials shall be applied by skilled workmen and shall be brushed or sprayed in even, thorough coats, without runs, crazing, sags or other blemishes, All coats, regardless of the material, shall be thoroughly dry before 09905-3 r s } i• 1 4 i . applying succeeding coats. Full drying time as recommended by i the manufacturer of the particular paint involved shall be allowed between coats. Enamel, paint, or shellac shall be properly sanded between coats. All products shall be applied in accordance with the manufacturer's recommendations. 3,00 EXECUTION 3.01 SURFACES TO BE PAINTED t All exposed unpainted structural steel, Piping (except PVC), valves machinery, pumps, motors and equipment shall be given one coat of rust-inhibitive primer and two coats of machinery enamel as specified in Paragraphs 2.018 and 2,01C. Items of metal that have received f shop coats shall have such shop coats touched up and be given two field coats of machinery enamel as specified above. w END OF SECTION • 1 M r 09905-4 i i V I r'1 11000 GENERAL EQUIPMENT STIPULATIONS i 1,01 SCOPE These General Equipment Stipulations apply, in general, to all equip- ment, They supplement the detailed equipment specifications but in case of conflict the detailed equipment specifications shall govern. 1.02 COORDINATION The Contractor shall assume full responsibility for coordination of the entire project, including verification that all structures, 1 piping, and equipment components to be furnished and installed by him arG compatible. For equipment to be furnished by Owner and installed under this contract, the Contractor shall be responsible for proper installation, startup and all necessary adjustments so that the equipment is placed in proper operation condition. The Contractor shall also be responsible for coordinating with other separate contractors as required for complete installation and operation of equipment, r 1.03 ADAPTATION OF EQUIPMENT Equipment to be furnished and installed under this contract shall be readily adaptable for installation and operation in the structures shown on the drawings. No responsibility for alteration of a planned structure to accommodate other types of equipment will be assumed by the Owner. Equipment which requires alteration of the structures will be considered only if the Contractor assumes all responsibility for making and coordinating all necessary alterations. All such alterations shall be made at the Contractor's expense, 5 1,04 PATENT ROYALTIES All royalties and fees for patents covering materials, articles, apparatus, devices, or equipment (as distinguished from rocesses) shall be included in prices quoted by equipment suppliers. 1,05 EQUIPMENT GUARANTEE 1 The Contractor shall guarantee all equipment furnished and installed by him under this contract against (a) faulty or inadequate design, (b) improper assembly or erection, (c) defective workmanship or materials, and (d) leakage, 9reakage, or other failure. For equipment furnished by Owner and installed under this contract, the Contractor shall guarantee against leakage, breakage o4^ other failure 3 due to improper assembly or erection and against improper installation of the equipment, The guarantee period shall be as defined in the General Requirements, ;i 11000-1 i y. I 1,06 WORKMANSHIP AND MATERIALS All equipment shall be designed, fabricated, and assembled in accordance with the best modern engineering and shop practice. Individual parts shall be manufactured to standard sizes and gages so that repair parts, furnished at any time, can be installed in the % field, Like parts of duplicate units shall he interchangeable. , .r Equipment shall not have been in service at any time prior to delivery, except as required by tests. Materials shall be suitable for service conditions. Iron castings shall be tough, close-grained gray iron free from blowholes, flaws, or excessive shrinkage and shall conform to ASTM A48. Except where otherwise specified, structural and miscellaneous ~ fabricated steel used in items of equipment shall conform to the Standards of the American Institute of Steel Construction. All structural members shall be considered as subject to shock or vibratory loads, Unless otherwise specified, all steel which will be submerged, all or in part, during normal operation of the equipment shall be at least 1/4 inch th`ck, t 1.06 LUBRICATION Equipment shall be adequately lubricated by systems which require attention no more frequently than weekly during continuous operation. Lubrication systems shall not require attention during startup or shutdown and shall not waste lubricants. Lubricants of the type recommended by the equipment manufacturer, cross referenced with major oil company lubricants, shall be provided I in sufficient quantity to fill all lubricant reservoirs and to replace all consumption during testing, startup, and operation prior to acceptance of equipment by the Owner. ` 1.08 ELECTRIC MOTORS { Unless otherwise required by the detailed equipment specifications, motors furnished with equipment shall comply with the following; A. Motors shall be designed and applied in compliance with NEMA, ANSI, IEEE, and AFBMA standards and the NEC for the specific duty imposed by the driven equipment, J B. Where frequent starting occurs, motors shall be designed for frequent starting duty equivalent to the duty service required by the driven equipment. i C. Unless recognized and defined by the standards and codes for intermittent duty as a standard industry practice, all motors l shall be rated for continuous duty at 40°C. ambient. Motor, temperature rise above 40°C, ambient on continuous operation at. { nameplate horsepower shall not exceed the NEMA limit, I 11000-2 I D. Motors shall be designed for full voltage starting. E. Motor bearing life shall be based upon the actual operating load conditions imposed by the driven equipment, F. Motors shall be sized for the altitude at the location where the equipment is to be installed, , G. Motors shall be sized so that, under maximum continuous load imposed by the driven equiprent, the motor nameplate horsepower for continuous operation in 40°C. ambient is at least 15 percent I more than the driven load. H. Where the detailed specifications call for encapsulated motor windings, the motor shall have a sealed insulation system I designed for a more severe environment than usual varnish I treatments can withstand, The insulation system shall be General Electric "Polyseal", Allis-Chalmers "Poxeal", or U.S. Motors "Everseal". Motors in this case may be single voltage rated. { 1. Motors shall have a clamp-type grounding terminal Inside the motor conduit box, J. Motors with external conduit boxes shall have oversized conduit boxes, It is the intent of this general specification to allow the ' manufacturer's standard motor on integrally constructed motor driven equipment such as appliances, hand tools, etc., that is i specified by model number in which a redesign of the complete jp unit would he required for a motor with other features as may be specified herein, r Unless otherwise required by the detailed equipment 1 specifications, motors within the horsepower ranges indicated below shall be rated and constructed as follows: r (1) Below 1/2 HP, F A. 115 volt, 60 hz„ single phase, B. Dripproof or totally enclosed, supplier's option, i C. Permanently lubricated sealed bearings, 0. BuilC-in manual-reset thermal protector; or furnished with integrally mounted stainless steel enclosed manual motor-overload switch, ,I 11000-3 1 i ) (2) 1/2 to 1 HP, A. 230/460 volt, 60 hz., 3 phase. B. Dripproof or totally enclosed, supplier's option, C. Specially insulated for use in damp locations below 20 C. D. Permanently lubricated sealed bearings. (3) 1-112 HP and Above; I A. 230/460 volt, 60 hz., 3 phase. B. Dripproof or totally enclosed, supplier's option, C. Specially insulated for use in damp locations below 20 C. D, Oil or grease lubricated antifriction or oil lubricated sleeve bearings. E. Vertical motors shall have 15 year average-life thrust bearings, 1 1.09 SAFETY GUARDS All belt or chain drives, fan blades, couplings, and other moving or t rotating parts shall be covered on all sides by a safety guard, Safety guards shall be fabricated from 16 USS gage or heavier galvanized or aluminum-clad sheet steel or 1/2 inch mesh galvanized expanded metal, Each guard shall be designed for easy installation and removal, All necessary supports and accessories shall be provided for each guard, Supports and accessories, including bolts, shall be galvanized. All safety guards in outdoor locations shall be designed to prevent the entrance of rain and dripping water. 1.10 ANCHOR BOLTS Equipment suppliers shall furnish suitable anchor bolts for each item of equipment. Anchor bolts, together with templates or setting drawings, shall be delivered sufficiently early to permit setting the anchor bolts when the structural concrete is placed, Two nuts shall be furnished for each bolt. Unless otherwise shown or specified, anchor bolts for items of equipment mounted on baseplates shall be long enough to permit 1-112 inches of grout beneath the baseplate and to provide adequate anchorage into structural cnncrete, 11000-4 ti . i Unless otherwise shown, anchor bolts, nuts, and washers shall be hot-dip galvanized in conformity with ASTM A153 and A385, or zinc plated in conformity with ASTM A165, Type GS, 1,11 SPECIAL TOOLS AND ACCESSORIES Equipment requiring periodic repair and adjustment shall be furnished complete with all special tools, instruments, and accessories required for proper maintenance. Equipment requiring special devices for lifting or handling shall be furnished complete with those devices, 1.12 PROTECTION All equipment shall be boxed, crated, or otherwise completely enclosed and protected during shipment, handling, and storage. All equipment shall be protected from exposure to the elements and shall be kept thoroughly dry at all times. Pumps, motors, electrical equipment, and other equipment having antifriction or sleeve bearings shall be stored in weathertight warehouses which are maintained at a temperature at least 60° F. 1 Painted surfaces shall be protected against impact, abrasion, 1 discoloration, and other damage. All painted surfaces which are damaged prior to acceptance of equipment shall be repainted to the satisfaction of the Engineer. Electrical equipment, controls, and insulation shall be protected against moisture or water damage. All space heaters provided in the equipment shall be kept connected and operating at all times until equipment is placed in service, I 1.13 INSTALLATION CHECK An experienced, competent, and authorized representative of the manufacturer or supplier of each item of equipment to be furnished and installed under this contract shall visit the site of the work and inspect, check, adjust if necessary, and approve the equipment installation, In each case, the equipment supplier's representative shall be present when the equipment is placed in operation. The equipment supplier's representative shall revisit the job site as often as necessary until all trouble is corrected and the equipment - Installation and operation are satisfactory in the opinion of the Engineer, Each equipment supplier's representative shall furnish to the Owner, i through the Engineer, a written report certifying that the equipment (1) has been properly installed and lubricated, (2) is in accurate alignment, (3) is free from any undue stress imposed by connecting piping or anchor bolts, and (4) ) has been operated under full load conditions and that it operated satisfactorily. !a ` 11000-5 h 1 j . i All costs for this work shall be included in the prices quoted by equipment suppliers. Manufacturer's representative requirements for equipment furnished by Owner are outlined in Appendix I for each item of equipment. The Contractor shall be responsible for coordinating with each manufacturer concerning dates and times for installation of equipment to insure proper scheduling of representatives visits. 1.14 OPERATIONS AND MAINTENANCE MANUALS For each type of equipment to be furnished and installed under this contract, the Contractor shall prepare an operation and maintenance manual covering: A. Equipment function, normal operating characteristics, and limiting conditions. 8. Assembly, installation, alignment, adjustment, and checking instructions. C. Operating instructions for startup, routine and normal operation, regulation and control, shutdown, and emergency conditions. 0. Lubrication and maintenance instructions, E. Guide to "troubleshooting". , F. Parts lists, and predicted life of parts subject to wear. G. Outline, cross-section, and assembly drawings; engineering data; and wiring diagrams. I H. Test data and performance curves, where applicable. The above information, as applicable, shall be provided for the i following equipment; , (LIST ALL ITEMS REQUIRING 0&M MANUALS HEREIN) The operation and maintenance manuals shall be in addition to any instructions or parts lists packed with or attached to the equipment r when delivered. 1 Manuals shall be printed on heavy, first quality paper, 8-1/2 x 11 inch size with standard 3-hole punching. Drawings and diagrams shall be reduced to 8-1/2 x 11 inches or 11 x 11 inches. Where reduction is not practicable, larger drawings shall be folded separately, and placed in envelopes which are bound into the manuals. Each envelope shall bear suitable identification on the outside. n T, I' 11000-6 c I ~ . Two preliminary copies of each manual, temporarily bound in heavy paper covers bearing suitable identification, shall be submitted to the Engineer at the time of submittal of the shop drawings, After ` review by the Engineer, four final copies of each operation and maintenance manual shall be prepared and delivered to the Engineer ` not later than 90 days prior to placing the equipment into operation, ; f^ The final manuals shall be bound in stiff artificial black leather, metal hinged binders, equivalent to Pilgram Self-Expanding Fastlock ,ilk 3 Binders, 3-post style, Operations and maintenance manuals for equipment furnished by the Owner will be provided by the equipment j supplier and will not be part of this contract. i , END OF SECTION i i , i i i r 1 s 1 I 1 11000-7 Y.. ti l , 11426 SUBMERSIBLE SUMP PUMP 1.00 GENERAL The Contractor shall furnish and install a submersible sump pump as specified at the location shown in the Plans. The pump and motor shall have a standard manufacturer's nameplate securely affixed in a conspicuous place showing the serial number, model number, manufacturer, ratings, and other pertinent nameplate data. The Contractor shall submit six (6) sets of full and complete shop drawings including wiring diagrams in accordance with General Conditions, Article 6, SHOP DRAWINGS. Shop Drawings shall include a complete description of all equipment offered, including catalogs, cuts, and all pertinent engineering data required to fully evaluate the equipment. The Equipment Manufacturer shall submit with the shop drawings a list of ten (10) similar installations which have been in satis- factory operation for at least one year. Four (4) sets of Operation and Maintenance Manuals shall be ,l submitted to the Owner prior to final acceptance of the equipment, 2.00 PRODUCTS The sump pump shall have cast iron motor housing and volute, bronze impellers, and stainless steel shaft. The pump shall be j equipped with a heavy-duty internal mercury float switch. The I r pump shall have a capacity of not less than 40 gpm at a total dynamic head of 20 feet. ? The motor shall be totally-encased, sealed, and non-ventilating ' I] and shall have automatic thermal overload protection, The motor shall be 112 HP, 115 Volt, 1150 RPM and shall be suitable for continuous duty, The sump pump shall be Aurora Model NSS 20 or approved equal. 3.00 EXECUTION I Upon completion of installation of equipment, an acceptance test to verify the satisfactory operation of the unit shall be conducted, The test shall be conducted in a manner approved by and in the presence of the Engineer, The unit shall be checked for excessive noise, vibration, general operation, etc. The unit 41 must perform in a manner acceptable to the Engineer before final acceptance will be made by the Owner, ° END Of SECTION (j 1142.6-1 "i a t 11435 CATHODIC PROTECTION 1.00 GENERAL 1.01 SCOPE Furnish and install all equipment, materials, and all other work and items required for a complete and functioning cathodic protection l tank system at f the l Denton internal, Water Treatment Plant. of the ground storage t The complete Cathodic Protection System shall be a Wallace and Tiernan POLATROL Cathodic Protection System, The average water quality in the tank is as follows: a. Total hardness 140 mg/1 r.. b, pH 8.2 c. Sulfates 52 mg/l d. Chlorides 32.5 mg/1 e. Total dissolved solids 234 mg/l > 1.02 CERTIFICATION A The following certifications of experience and qualifications to perform the work shall be submitted- a. A list of five (5) or more similar installations at least two (2) years old, b. Accreditation of the Supervision as a MACE, Corrosion Specialist. s 2,00 PRODUCTS 2.01 MATERIALS be of the highest Materials furnished under this section shall t quality, regularly used in commercial practice and shall conform to i the following; a. Rectifier Unit - A conventional rectifier unit shall be housed in a weatherproof cabinet with provisions for locking and shall be equipped with a transformer and silicon rectifier, a unit , voltmeter, a separate ammeter for each output circuit, and shall have provisions for manually adjusting the voltage output in 20 or more equal steps from 0-100% of rated capacity, The i A.C,an and rectifier unit shall b15manufactured single y phWallace ase, 60 a Hz,Tier 115 shall be designed for power. 11435-1 n s b. Automatic Controller - The controller shall be housed inte- grally within the rectifier unit, line automatic controller shall be capable of regulating its direct current output as follows; 1. Manual operation shall permit uniform adjustment over the full rectifier capacity from 0 to 100%, without trans- former taps. 2. Automatic operation, using a potentiostat control wherein the current output is automatically adjusted to maintain the structure at a pre-selected potential (in accordance with NACE Standard RP-01-69) with reference to a standard reference electrode positioned contiguous to the structure. 3. Automatic operation, using potentiostat control wherein the current output is automatically adjusted to maintain the structure polarized potential, free of IR drop, at a preselected value utilizing standard reference electrodes { positioned at a considerable distance from the structure. The polarized potential is continuously monitored with no interruption of the applied current (in accordance with NACE Standard RP-01-69). , The controller shall have no moving parts, and shall be capable of autolilatically maintaining the structure-to-electrolyte I potential at 900 millivolts with respect to a single copper/copper sulfate reference electrode within an accuracy of 25 millivolts. The system shall be controlled through the use of reference half-cells. The controller shall have an automatic current limiter to prevent over protection. c. Structure-to-Electrolyte Potential Meter - The controller shall be cnuipped with a calibrated voltmeter which shall be so connected to read, from the system reference cells, the structure-to-electrolyte potential being maintained by the cathodic protection system. d. Referr,nce Electrodes - The system shall be equipped with copper/copper sulfate reference electrodes designed for a minimum five year life. The electrodes shall have appropriate ion a<change end caps, electrolyte ion contaminant barriers, and air entrapment relief ports. The reference electrode shall be mrdel 11IRP-801, or equal. The electrodes shall remain N stable for a minimum period of two (2) years. e. The anodes shall be Piatinex (platinum-niobium). The anodes 1 shalt be designed for vertical installation within the tank and spaced at proper current for vertical installation within the tank and spaced at proper current distribution to all interior ii water' contact surfaces. 114,5-2 z \ r \1 I f. The system shall be designed and manufactured by Wallace and Tiernan, and six (6) sets of shop drawings detailing the complete installation shall be submitted for review. 3.00 EXECUTION 3.01 INSTALLATION The system shall be installed by personnel who are specifically full cathodic are engaged trained the this work b servicing e of and who installatiion t and manufacturer protecton time i equipment. The tank shall be provided with appropriate anode material, , suspended below the water line from steel eye rings welded to the ti structure. Anode material shall be spiralled around 5/16" braided polyester rope attached to the steel eye ring supports. All eye rings and angle iron supports shall be welded in place prior to sandblasting and painting. Electrical contact between the anode ; material and the supports or structure shall be prohibited. A. ENERGIZING Following installation, the system shall be energized and adjusted for optimum operation by a trained employee of the manufacturer. After the unit is adjusted, measurements of structure-to-water potential shall be taken using a copper/ copper sulfate half-cell as a reference electrode. A report shall be bwhich level5t results obtained as well as recommended M' R. CRITERIA FOR PROTECTION The structure-to water potentials at which the cathodic pro- I, ) tection system is set to operate shall be in accordance with the the eprotection of t Corrosion Engineers established In the NACE National Association Standard RP-01-69. E, INSTRUCTIONS Prior to final acceptance, a minimum eight (B) hour verbal instruction period on the operation and maintenance of the installed system shall be provided to the Owner. In addition, detailed operating and maintenance manuals shall be furnished in accordance with Section 11000, GENERAL EQUIPMENT STIPULATIONS, ENO OF SECTION 'i. - 11435-3 Y i l A F J r 1 V 1 t 41 i • 13401 WELDED STEEL GROUND STORAGE TANK 1,00 GENERAL I 1.01 SCOPE The work to be done comprises the furnishing of all materials, labor, ti tools, appliances, equipment and appurtenances necessary to the design, fabrication, and erection of a welded steel treated water storage tank with roof, on a foundation, complete with all appurtenances and painting, as shown on the Plans. The tank shall have an inside diameter of 150 feet, a water depth at the wall of 15.0 feet to the overflow, a total height of 15.5 feet, and a capacity of approximately two (2) million gallons. Appur- tenances include inlet and outlet connections, vent, roof hatch, drain, shell manhole, overflow, and access ladders, in accordance , with orientation shown on the Plans. 1.02 GOVERNING STANDARDS i All work in both shop and field shall be in accordance with all , applicable requirements of the "Standard Specifications for Elevated Steel Water Tanks, Standpipes, and Reservoirs," in its latest amended form, as jointly adopted by the American Water Works Association MOD) and the American Welding Society (05.2) except as noted herein. I 1.03 SUBMITTALS , The Contractor shall submit six (6) sets of full and complete shop drawings on the storage tank in accordance with General Conditions, Article 6, SHOP DRAWINGS. All of the drawings shall be complete and include a complete description of the tank being offered including all pertinent engineering data required to fully evaluate the tank. The information shall include: 1 1. Critical Dimensions and Tank Construction Drawings 2• Piping and Appurtenances Descriptions 3. Construction Materials Submittal data shall be in such form and so presented that the Engineer may readily review the data. The tank erection contractor shall submit with the shop drawings a list of ten (10) similar installations which have been in sans- factory operation for at least five (5) years. 13401-1 1 41 2.00 PRODUCTS / 2,01 DESIGN The reservoir shall be designed and erected in strict accordance with the latest AWWA Specification D100, "Standard Specifications for Elevated Steel Water Tanks, Standpipes, and Reservoirs," and American Welding Society, except as noted herein. Joints shall be welded; except bolts may be used for minor attach- ments, Threads shall be burred outside the nuts to prevent easy removal of the nuts. The reservoir shall be constructed with lap welded bottom (top ~ side only) coned up to center with a slope of one inch per ten i feet; shell plates shall be butt welded; and roof is to be lap , welded and conical with a slope of three fourths (3/411) inch per foot. Conical roof shall be supported by a suitable framework of structural steel, The minimum thickness of the plates shall be 1/4 inch for those in contact with water and the minimum thickness of plates not in contact with water shall be 3/16 inch, The following loads shall be used in the design of the reservoirs. a, Dead Load shall be the estimated weight of all permanent construction and fittings. i b. Live Load shall be the weight of all the liquid when the tank is filled to overflowing, plus snow load on roof. - ~II C, Wind Load or pressure shall be assumed to be 30 lb, on ? 1 vertical or plane surfaces, 18 lb,, on projected areas of }1 conical and curved plate surfaces. d. Snow Load shall be 25 lb. per square feet of the horizontal j projection of the tank surfaces having a slope of less than 30 degrees with the horizontal. For surfaces with greater I slope, the snow loads shall be neglected, Adequacy of Design: As tanks are of manufacturers own design, the Tank Contractor shall be responsible for the adequacy of design in " accordance with the above referenced specifications. Ir 2.02 MATERIALS f All materials used in the fabrication and erection of the tanks shall conform in all respects to AWWA Specifications 0100 unless otherwise specified herein, Materials shall be of high grade and quality throughout. Materials shall be mill inspected at the t' 13401-2 t I1 1 r , Contractor's expense and two copies of the mill test reports shall be furnished to the Owner upon request. 2.03 APPURTENANCES A. GENERAL The tank shall be complete with the accessories as shown on thA Plans and/or described below. Moderate variations to allow `oc use of the Contractor's standard provided that the features are similar n and will be is f equal or superior to that shown or specified. All piping shall have a minimum wall thickness of 1/4 inch and all flanges shall p be ASA #125 Standard, # t 8. LADDERS i The tank shall be provided with suitable inside and outside ladders. Ladders shall conform with Paragraph 6.4 of the AWWA M Specifications, except that the ladder shall extend above the tank roof and shall make u 180° bend and connect to the roof, A safety cage shall be provided for outside ladder. A Safety- Climb rail with one set of harness shall be furnished with the 1 inside ladder. { t C. INLET AND OUTLET PIPE The inlet and outlet pipe shall be as shown on the Plans. D. OVERFLOW s The overflow shall be 12 inches in diameter, as detailed on the Plans. 1. E. TANK VENT i A vent with a minimum diameter of 4'-0" shall be provided. Vent shall be complete with bronze insect screen. F. DRAIN The drain shall be as detailed on the Plans. ' G. ROOF MANHOLES 1 The contractor shall furnish a roof door or hatch which shall be placed at the outside and inside tank ladders. The Hatch ~ shall have a minimum opening dimension or diameter of 30 inches. The hatch shall comply with all the AWWA require- ments and shall have a hasp for locking, hinges to permit ' laying hatch all way back, and a handle for raising. a 13401-3 A . 1 ' C\ I 1 i E H. CLEAN OUT MANHOLES Two-30 inch clean out manholes with blind flanges, near the flour of the tank, shall be located as shown on the Plans. The covers shall be bolted to the tank and sealed with a gasket. 3.00 EXECUTION a7 3.01 FABRICATION AND ERECTION The concrete ring foundation shall conform to the requirements specified in Section 03305, CAST IN PLACE CONCRETE and as shown on 't the Plans, The foundation material shall be thoroughly compacted as required in Section 02201, EARTHWORK for compacted embankment and backfill, and as shown on the Plans. i The tank floor plates shall be placed on a 2-inch sand cushion which has been thoroughly saturated with low viscosity asphalt primer or road oil. The sand shall be free flowing material with r 100% passing the 3/811 screen. Welding, riveting, shop fabrication, and erection shall conform to the applicable paragraphs of AWWA Specification 0100, except where modified by these Specifications. All welding shall conform strictly to Section 8 of the AWWA Specification D100 (American Welding Society Spec, D5.2). Certification of the welders will be required prior to the start of erection of the tank. Shop fabrication shall conform with Section 10 of AWWA Spec. 0100. In addition to laboratory testing required by Contractor in AWWA Spec. 0100, the Owner may require shop and/or field inspection of the material and/or fabrication by an independent Testing Laboratory, the cost of which will be paid by the Owner. ! Painting of the tank and accessories shall be in accordance with Section 09872, TANK PAINTING. 3.02 DISINFECTION After the specified drying time has passed for the paint, the tank shall be swept clean and washed down with water. The Owner will furnish the water, Chlorine shall then be injected as the tank is being filled. Sufficient chlorine shall be applied so that when the tank is completely full, the water will contain chlorine in the amount of 50 ppm or more. Spray disinfection, as specified in Bulletin 22 of the New York Stace Department of Health, may be used 11 as an alternate to the above method. After disinfection by either method, the Owner will fill the tank with potable water and test samples for bacteria presence. If not properly disinfected, the IP 13401-4 0 4 i f r i ks cess shall be repeated at the Contractor's expense. Any lea / pro ll be repaired in accordance with AWWA found in the tank sha Specification 4100. END OF SECTION I" i t i ( i t I ~ y f z Y 1 i t 13401-5 .A 11 f 4 { i 1 I 15051 STEEL PIPE AND FITTINGS 1,00 GENERAL The Contractor shall furnish and install all steel pipe and fittings, including taps, connections, and appurtenances, com- pletely as shown on the Plans and specified herein. 1 The Contractor shall submit six (6) sets of full and complete shop drawings on the steel pipe in accordance with General Conditions, Article 6, SHOP DRAWINGS. All of the drawings and data shall be complete and shall include a complete description of the pipe j offered, including paint schedule and all pertinent engineering data required for a complete evaluation of the submittal, ` i Submittal data shall be in such form and so presented that the Engineer may readily review the data, I 2,00 PRODUCTS Steel pipe shall be in accordance with the following specifiea- t1ons of the American Water Works Association: f f Tentative Standard Specifications for Fabricated Electrically F 1 Welded Steel Water Pipe, Designation C201, _ Tentative Standard Specifications for Mill-Type Steel Water Pipe, Designation C202. Standard Specifications for Coal-Tar Enamel Protective Coatings for Steel Water Pipe, Designation C203. Standard Specifications for Cement-Mortar Protective Lining and Coating for Steel Water Pipe, Designation C205, Standard Specifications for Field Welding of Steel Water Pipe Joints, Designation C206. Lap welded pipe will not be acceptable. Steel pipe shall be designed for a working pressure of 50 psi with a minimum wall thickness of 1/4". Steel pipe for chemicals shall be black Schedule BO seamless steel ' pipe, Grade B, in accordance with ASTM Specifications A 106, Fittings shall be forged steel fittings and use white lead thread compound on all threaded joints. Unions shall be forged steel tongue and groove flanged with lead gaskets. + ,I ` 15061-1 iS i Y S i I 41 f , I 3.01 INSTALLATION Steel pipe shall be installed with flanged ends, victaulic ends, ; inndicated,onethedPlanseandoprovidedin screw these nspecificatall as ions. All h piping shall be thoroughly cleaned to remove dirt, dust, rust, grease, and other foreign matter prior to laying. Pipe in trenches or otherwise shall be brought to the required line and grade and held securely in position while all connections are being made. No displacement of the pipe which would cause undue strain on the joint will be permitted. Flanged connections shall be made by means of erection bolts and drift pins, without undue "forcing", and with no restraint on the ends of the pipe or fitting which would prevent pressure from be- ing evenly and uniformly applied on the gasket. The pipe or fitt- i shall ng must be free to move in any direction while bolting. Bolts r aroundbtherentireyfltiened, ange. Flange hbolts turn, shall tbe a uniform installed rate with bolt heads in one direction. All field welds the AWWA Specification f steel pipe shall be done in accordance with Designation C206, "Field Welding of Steel Water Pipe Joints." All steel pipe connected by screwed fittings shall have all burrs removed by reaming prior to threading. Screw joints shall be made with graphite and oil or an approved graphite compound, applied to male thread only, Threads shall be full cut, and not more than three threads on the pipe shall remain exposed. Caulking of threaded joints to prevent leaks will not be permitted. Unions shall be provided where required for disconnection. Changes in pipe sizes shall be made with reducing fittings; the use of long fromscrewconcs and on piping plans shall or b as suorted for proper installation. 3.02 SEAMS Girth seams, except in fabricated bends, shall be a minimum dis- tance of 20 feet apart. The angular change at miter welds in elbows shall not exceed 15 degrees, The maximum number of longitudinal seams shall be as follows; one seam f 11 d 2010; two seams for 22" through 48", or 6 through i Pipe shall be connected by butt welding, screwed flanges, Dresser or Uictaulic Style Couplings, as indicated on the plans. Ends shall be prepared for the particular type of connection to be used, j i# s 15061-2 a i LL- Flanges for pipe shall be in accordance with ANSI Standard for Steel Pipe Flanges, drilled to ANSI Class 125, unless otherwise shown. i Victaulic and Dresser Style Couplings shall be as specified ir, Section 15078, MISCELLANEOUS PIPE AND FITTINGS. 3,04 PIPE COATING The interior surfaces of all steel pipe and fittings shall be cleaned in the shop by sandblasting to a gray metal in accordance with AWWA C203, After cleaning, the interior surfaces shall be primed and painted in accordance with AWWA C203. Mortar lining conforming to AWWA C205 may be used in lieu of coal tar enamel to coat the interior of the pipe. i Field or shop welds in pipe or fittings shall be located so that the interor surface at the connection is accessible for hand patching of the coating, c The exterior of ail steel pipe and fittings shall be cleaned and { shop primed with one coat of rust inhibitive primer as specified 1 t in Section 09905, PLANT PAINTING. 3,05 HYDROSTATIC TESTS All tests shall be made as directed and in the presence of, and to the satisfaction of the Engineer. All steel pipe shall be tested at 100 psi for four (4) hours and all leaks properly repaired, 3.06 DISINFECTION ! i 0 All pipe shall be disinfected in accordance with Section 01001, 1.17, DISINFECTION. i r5, END OF SECTION I Y~ ~r {1 15061-3 1 t 77 1 1 r 15062 CAST IRON PIPE AND FITTINGS 1,00 GENERAL The Contractor shall furnish and install all cast iron pipe and fittings, including taps, connections, and appurtenances, either in trenches or supported completely as shown on the Plans and f, specified herein. The Contractor shall submit six (6) sets of full and complete shop drawings on the cast iron pipe in accordance with Section General conditions, Article 6, SHOP DRAWINGS. All of the drawings and data shall be complete and shall include a complete description of the pipe offered, including all pertinent engineering data required for a complete evaluation of the submittal. Submittal data shall be in such form and so presented that the Engineer may ' readily review the data. 2,00 PRODUCTS All cast iron pipe shall be cast from Ductile Iron in accordance a with ANSI Specification A21.51 (AWWA C-151), Pipe shall have i push-on joints in accordance with ANSI Specification A21.11 (AWWA C-111) and shall be similar to U.S. "Tyton", American "Fastite" or Clow "Bell-Tite", or shall be flanged as shown on the Plans. Outside coating shall be Standard Bituminous Outside Coating, ANSI A21,4, "Standard Thickness Lining", A bituminous seal coat shall be applied over the mortar lining, r All ductile iron pipe 6 inches in diameter and larger shall be a f minimum of Thickness Class 53, and shall be designed for 250 psi in accordance with ANSI Standard A21.5D (AWWA C-150) for laying I Condition "2" and with twelve (12') feet of cover, Pipe smaller than 6 inches in diameter shall be Class 55, Fittings shall have push-on joints unless otherwise indicated in accordance with ANSI Standard A21,11 (AWWA C-111), All piping shall have pushoii joints unless shown otherwise on the plans. Fittings for pipe, 12 inches in diameter and smaller shall be Class 250 gray iron castings, and fittings for pipe larger than 12 inches in diameter shall be Class 150 ductile iron castings, all conforming to ANSI Standard A21,10 (AWWA C-11.0), Coating for fittings shall be as specified above for cast iron pipe, ij 15062-1 r 1 A j 3,01 INSTALLATION Steel pipe shall be installed with flanged ends, victaulic ends, couplings, welded connections, and screw connections, all as indicated on the Plans and provided in these specifications. All piping shall be thoroughly cleaned to remove dirt, dust, rust, grease, and other foreign matter prior to laying. Pipe in trenches or otherwise shall be brought to the required line and grade and held securely in position while all connections are being made. No displacement of the pipe which would cause undue strain on the joint will be permitted. Flanged connections shall be made by means of erection bolts and drift pins, without undue "forcing", and with no restraint on the ends of the pipe or fitting which would prevent pressure from be- ing evenly and uniformly applied on the gasket. The pipe or fitt- ing must be free to move in any direction while bolting, Bolts shall be gradually tightened, each in turn, at a uniform rate around the entire flange. Flange bolts shall be installed with bolt heads in one direction. All field welding of steel pipe shall be done in accordance with the AWWA Specification Designation C206, "Field Welding of Steel Water Pipe Joints," All steel pipe connected by screwed fittings shall have all burrs removed by reaming prior to threading, Screw Joints shall be made with graphite and oil or an approved graphite compound, applied to male thread only. Threads shall be full cut, and not more than three threads on the pipe shall remain exposed, Caulking of threaded joint, to prevent leaks will not be permitted. Unions shall be provided where required for disconnection. Changes in i pipe sizes shall be made with reducing fittings; the use of long screws and bushings is prohibited. All piping shall be supported trom concrete structures as indicated on the plans or as required for proper installation, 3.02 SEAMS Girth seams, except in fabricated bends, shall be a minimum dis- tance of 20 feet apart. The angular change at miter welds in elbows shall not exceed 15 degrees, The maximum number of longitudinal seams shall be as follows; one seam for b" through 20"; two seams for 22" through 46". Pipe shall be connected by butt welding, screwed flanges, Dresser , or Uictaulic Style Couplings, as indicated on the plans, Ends i shall be prepared for the particular type of connection to be used. 15061-2 ter,` i _ The gaskets shall be carefully seated by hand so as to be even in the bell at all points. After drawing up the follower ring to uniform bearing against the gasket, the bolts are to be inserted and tightened by hand in pairs using bolts opposite each other. The nuts are to be tightened amply to hold the required % pressure, Extension wrenches, or pipes over wrench handles, will not be permitted. Ten (10") inch ratchet wrenches shall be used to tighten the nuts, unless other type wrenches are approved by the Engineer. The finished Joint shall be neat and uniform and shall ~ be watertight. 2. Making Flanged Joints: Flanged pipe shall be erected in accordance with the controlling dimension shown on the Plans. Each piece of flanged pipe shall be thoroughly cleaned to remove dirt, rust, grease, and other foreign matter, and flanged faces shall be thoroughly wire brushed to insure even bearing for gaskets and mating flanges. Flange gaskets shall be 1/16" full faced, i ' fabric reinforced rubber gaskets, Flange bolts shall be tightened, each in turn, at a uniform rate around the ,joint. Finished joint shall be watertight, ~ 3. Making Push-On Joints: The jointing of this type of I joint shall be a~z recommended by the manufacturer. The E procedure for jointing shall be generally as follows: N . The spigot and bell shall be thoroughly cleaned and dried before starting the assembly of the ,joint. The gasket shall be wiped clean with a cloth. ,5,• r The gasket shall be placed into the gasket seat in the bell. A thin film of lubricant shall be applied to the surface of the gasket that will come in contact with the entering pipe spigot. If necessary, luN 'cant shall ` also be applied to the spigot. f the entering pipe so that its plain end will move past r the gasket, This exerting force may be of a crowbar, or fork-tool for B" and smaller or by use of a Jack on 10" or larger pipe. A 15062-3 I j 1 i D. BLOCKING Concrete blocking in accordance with Section 02201, EARTHWORK, shall be placed at bends, tees, crosses, and plugs, in buried lines. The concrete blocking shall be places so as to rest against firm undisturbed trench walls, normal to the thrust. The supporting area for each block shall be sufficient to withstand the thrust which may develop at the pipe design pressure. Each block shall rest on a firm, undisturbed foundation or trench bottom. " 3,02 HYDROSTATIC TEST After the pipe has been laid and backfilled, each section of newly laid pipe shall be subjected to a hydrostatic pressure test. For any section being tested, the pressure applied shall be such that at the lowest point in the section, the pressure shall be equal to the design pressure of the pipe or as indicated on the Plans. All pipe shall be disinfected in accordance with Section 01001, Paragraph 1,17, DISINFECTION, END OF SECTION - i i ~ i i r' 1 I + a i { 15062-4 r "1C i 15076 MISCELLANEOUS PIPING AND FITTINGS g 1.00 GENERAL The Contractor shall furnish and install all miscellaneous piping, N fitting, and ap urtenances as located on the plans and specified herein. Six (6~ sets of full and complete shop drawings shall be submitted on all miscellaneous piping in accordance with General 1 Conditions, Article 6, SHOP DRAWINGS. All of the drawings and data 1 shall be complete and shall include a complete description of all the miscellaneous piping equipment including all pertinent engineering data required for a complete evaluation of the submittal. Submittal data shall be in such form and so presented that the Engineer may readily review the data. 2.00 PRODUCTS i 2.01 PIPE COUPLINGS Dresser style pipe couplings where shown on the Plans shall be Dresser Industries, Style 38, or equal, for same pressure rating # as adjoining pipe. Couplings shall comprise a steel center band, steel gland rings, gaskets and bolts. Provide thrust harness as detailed where shown on the Plans. 2.02 VICTAULIC COUPLINGS ' Victaulic couplings, where shown on the Plans, shall be Style 44 as manufactured by Victaulic Company of America, or approved equal. The couplings shall be comprised of cast housing clamps and triple seal gasket. Pipe shall have shouldered ends for thrust anchorage. e 3.00 EXECUTION All piping shall be carefully handled and installed to prevent damage to the pipes. Water lines shall be disinfected in actor- 11 l dance with Section 01001, Paragraph 1.17, DISINFECTION. ~ All lines shall he tested for 'leaks. All leaks and defects shall be repaired or replaced and the test conducted over until no leaks or defects are discovered. The Contractor shall furnish aluminum sleeves for all lines passing through walls, floors, beams, roof slabs, etc. END OF SECTION 150/fl-1 r i i <'s 1 I 41 15101 GATE VALVES 1,00 GENERAL REQUIREMENTS 1.01 GENERAL urte- The Contractor shall furnish and install all valves and app mantes, including valve boxes, vaults, operators, bolts, nuts and gaskets, etc. completely as shown on the Plans and specified herein. lvsubmit The Contractor shall acsix cordanceewithfthelGeneraloConditionsp data shall be drawings o g Article 61 SHOP DRAWINGS. All of the drawings and g cinclud complete and atalogues, o cuts,eandsallppeortinenthengineerin9 Submittal ion of I~ V offered, including , data required for a complete evalaaresentedtthatuthe Engineer may data shall be in such farm and so p submit with readily review the data. The valve manufacturer shall the shop drawings list of ten (10) similar installations which have a been in satisfactory operation for at least three (3) 3) years 2,00 PRODUCT 2.01 GATE VALVE A. GENERAL Gate valves, 3 inches and smaller shall be all bronze construc- tion with threaded ends, valves 4 inches to 12 inches shall be resilient seat gate valves and valves 14 inches and larger shall be iron body l be with broncturednbynMuellersCotheDresserPeClowedor Valves shal approved equal. All gate valves with interior surfaces of cast iron, ductile } iron, or carbon steel exposed to water shall be coated in accordance with AWWA C 550 "Protective Interior Coatings for Valves and Hydrants" with additional requirements described herein. The coating shall be a two part thehmsical,nchemical protective coating and shall function as a p y and electrical barrier between the base metal to which it is applied and the surroundings. The coating shall be non-toxic and shall not impart taste to water, The coating must be formulated and materials deemed acceptable per the FOOD AND DRUG ADMINISTRATION DOCUMENT TITLE ICACCOATING( SECTION r 21hentitled, RESINSREGULATIONS POLYMERFOOD 12i,2514 15101-1 , a a V , `Y11i I a The coating shall have a satin finish and shall be suitable for field overcoating and touchup with same coating material without sanding or special surface preparation, or application of heat in excess of room temperature. The coating shall have a successful record of performance in valves, pipe or other allied equipment for a minimum of two years. r' The coating adhesive to the substrate shall exceed cohesion of the coating film as demonstrated by the following test; ` a. Prepare test panel and apply coating per manufacturer's recommendation. b. After sample has properly cured per manufacturer's , recommendation, scribe an "X" using a sharp knife or i scalpel through the coating to the metal substrate. C. With the point of the knife at the juncture of two scribes, attempt to lift off coating. Coating should not lift off substrate or between coats readily, but should break up, leaving coating material on the substrate of this damaged area. d. No disbondment of the film shall be noted as tested above after immersion in tap water for 1500 hours at 100°F. A falling sand abrasion test using ASTM 0698 shall produce an abrasion coefficient of 25-30 liters/mil. As an alternative, a Taber Abrader Test should find 3.5 - 33 milligrams coating loss per 100 cycles when using a CSF 10 Wheal (1000 gram weigh. The Contractor shall pruvide an affidbwit stating that the furnished coated material conforms to the requirements of AWWA C550 and the additional requirements described herein. B. BRONZE GATE VALVES Bronze gate valves, 3 inch and smaller, shall be all bronze construction with non-rising stem, wedge disc and threaded ends. r Unless otherwise specified, they shall be for 300 psi working pressure, egoal to Crane No. 437. C. RESILIENT SEAT GATE VALVES Gate valves 4 inches to 12 inches shall be iron body, resilient 1 seat gate valves conforming to all applicable parts of AWWA C500 and C504. Ends shall be flanged or bells as indicated, Valves a shall have non-rising stems and shall turn clockwise to close. Valves shall be Mueller resilient sea-: pate valves or approved U equal, 15101-2 i 1 . 1 D. IRON BODY GATE VALVES Gate valves 14 inches and larger shall be double disc, parallel seat, internal wedging type with cast iron body and bronze ` mountings. Ends shall be flanged or bells as Indicated. Valves f shall have non-rising stems with rubber gasket stem seals, and " shall turn clockwise to close. Valves shall be manufactured in accordance with AWWA Designation C500 "Gate Valves, 3 through 48 Inc. NPS, for Water and Sewage Systems," Valves for working pressures other than those covered by the above specification shall meet the requirements of AWWA C500 except pressuring rating. . Flanged valves shall be drilled to ANSI Standards for the 1 pressure class required. Bell ends for valves shall have rubber gasket push-on joints for the particular type of pipe with which they are to be used, or mechanical joints where permitted, or specified. E. OPERATORS Valves shall have a handwheel operator unless otherwise shown. All manually operated valves 16 inch or larger shall be orovided with a bevel gear or spur gear and an extended gear case. Valves 16 inch and larger shall have a bypass valve with hand- I wheel operator. For buried valves, a 2-inch square nut operator instead of 6 - i handwheel shall be provided and shall be supplied with cast iron valve boxes. The valve box shall be firmly supported and maintained centered and plumb over the wrench nut of the gate valve, with box cover flush with the surface of the ground, Valve boxes shall be of the three piece cast iron extension type, Mueller No. 10380 or Clow F2454, with No. 6 round base. The three pieces shall consist of the top section, center section, and base plus the cover, Raised letters in the cover ` shall read "WATER", 3.00 EXECUTION Valves shall be carefully handled and positioned in such manner as to prevent damage to any part of the valves. The valve shall be placed in proper position with stem truly vertical or horizontal as re- quired, and shall be securely held until all connections have been h made, The Contractor shall be responsible for adjusting the valve boxes to the proper length to conform with the ground surface, 1 END OF SECTION R 3 15101-3 a i LILL 1 r 15103 BUTTERFLY- VALVE'S 1.00 GENERAL 1.01 SCOPE , The Contractor shall furnish and install butterfly valves completely as shown on Plans and specified herein. All butterfly valves supplied under this Contract shall be of the tightclosing, rubber-seated type with rubber seats that are securely fastened to the valve body. No metal-to-metal seating surfaces shall be permitted. Valves shall be bubble-tight at rated pressures with it flow in either direction and shall be satisfactory for applications involving valve operation after long periods of inactivity, All butterfly valves shall strictly conform to the design strength, testing, and performance requirements of AWWA 0504-80. r The manufacturer shall have manufactured tightclosing, rubber seat butterfly valves for this t pe service (municipal water and wastewater treatment plants} fora period of at least five (5) years. 1.02 SUBMITTALS . 1 The Contractor shall submit six (6) sets of full and complete shop drawings on the butterfly valves in accordance with the General Conditions, Article 6, SHOP DRAWINGS, The data shall include catalogues, cuts, and any other pertinent engineering data required for a complete evaluation of the submittal, Submittal data shall be in such form and so presented that the Engineer may readily review the data, M The valve manufacturer shall submit a list of ten (10) similar installations which have been in satisfactory operation for at least three (3) years. Shop Drawings without this required information will not be accepted. 2.00 PRODUCTS 2.01 VALVE BODIES Valve bodies shall be constructed of cast iron ASTM A-126 Class ASTM A-48 Class B. Valve shall have ends designed for connection to pipe with `'tyle 44 Victaulic couplings, Valves shall have a retained seat and shall provide tight shut-off up to the full valve rating, Two trunnions for shaft bearings shall be integral with each valve + i body. ii a 15103-1 i 44 2.02 VALVE DISCS I' Valve discs shall be cast iron conforming to ASTM A-439, Type D2, Class 40 or ASTM A126, Class B; of alloy cast iron, conforming to ASTM A436, Type 1 or 2 or ASTM A-439, Type D2; or of aluminum bronze conforming to ASTM 148, Class 9A, all with a maximum lead content of 0.003 percent. There shall be no external ribs cast transverse to the flow path. The design of the valve disc shall be such as to sustain full differential pressures across a closed valve without exceeding a working stress of one-fifth (1/5) of the tensile strength of the material used. 2.03 VALVE SHAFTS Valve shafts shall be turned, ground and polished and shall be constructed of materials and diameters as required in Table 3 of AWWA C504-74 (Optional - or of corrosion resistant material (stainless steel) and diameters which give equivalent strength.) All valve shafts may consist of a one-piece unit extending completely through the valve disc, or may be of the "stub shaft" type, which comprises two separate shafts inserted into the valve disc hubs. If of the "stud shaft" construction, each stub shaft shall be inserted into the valve disc hubs for a distance of at least 1-112 shaft diameters and design shall be such that free play is taken up in assembly by tapered, wedged, or keying devices, or by close fit J shrink techniques; however, construction shall also allow easy 1 disassembly for maintenance service. 2.04 VALVE SEATS All valves shall have new natural or synthetic rubber resilient seats to provide tight shut off at the pressure specified. The resilient { seats must be capable of replacement in the field without grinding or burning. The seat may be applied to the body or disc. If the seat is applied to the disc, the mating seat surface shall be 18-8 stainless steel or a 95% pure nickel overlay. Sprayed or plated mating seat surfaces are not acceptable. 2.05 VALVE BEARINGS Valves shall be fitted with sleeve-type bearings, Bearings shall be of corrosion resistant and "self-lubricated" materials that will not deteriorate natural or synthetic rubber. Bearings shall be designed u for a pressure not exceeding one-fifth (1/5) of the compressive r strength of the bearing or shaft material. 2.06 VALVE SHAFT SEALS Where shafts project through the valve bodies for operator connection, a shaft seal shall be provided. ~i IS 15103-2 i i 2.07 MANUAL OPERATOR All manually operated valves shall be provided with a fully enclosed gear reducer operated completely immersed in oil and shall be equipped with a handwheel unless otherwise shown on the Plans or specified herein. Each valve shall be provided with a valve disc position indicator. All manually operated valves shall be of the traveling nut, self-locking type and shall be designed to hold the valve in any intermediate position between fully open and fully ` closed without creeping or fluttering. Each valve operator shall require an input force on the handwheel of not more than 40 pounds pull to develop specified minimum operator torque. The direction of rotation of each handwheel to open valve shall be counterclockwise. Each handwheel shall have an arrow and the word "Open" cast on it to indicate the direction of turn to open , the valve. ' i 2.08 VALVES REQUIRED The required valves and certain pertinent data is given below, This list is given to facilitate description of the various valves and as an aid to plan take-off and is not guaranteed to be complete. Butterfly valves shall be as manufactured by 8-I-F, Henry Pratt Company, Allis-Chalmers, or approved equal, All valves shall be full body style with Victaulic ends, except as noted otherwise. Size Max, Item Number and AWWA Diff, Type ` No, Service Req'd Ends Class PSI Operator Ground Storage 2 36" 1508 Handwheel ` Inlet & Outlet Victaulic and Gear Ends Reducer 3.00 EXECUTION The equipment manufacturer shall provide the services of a competent manufacturer's representative for whatever period of time Is required 1 to insure proper installation and operation of the equipment, 'r Upon completion of installation of the butterfly valves an acceptance test will be conducted to verify the satisfactory operation of the valves. The valves must perform in a manner acceptable to the Engineer before final acceptance will be made by the Owner, END OF SECTION a 15103-3 3 1 I 15136 MISCELLANEOUS VALVES 1,00 GENERAL The Contractor shall furnish and install miscellaneous valves com- pletely as shown on the Plans and specified herein, Six (6) sets of 1 full and complete shop drawings shall be submitted in accordance with ' GENERAL CONDITIONS, ARTICLE 6, SHOP DRAWINGS. The drawings and data kf r shall include complete descriptions of the valves offered, including catalogues, cuts, and all pertinent engineering data required for a complete evaluation of the submittal. Submittal data shall be in such form and so presented that the Engineer can readily review the data. i r 2,00 PRODUCTS i Flap valve, flanged end, ANSI 125#, Clow F-3012 or approved equal. I 3100 EXECUTION } Valves shall be carefully handled and installed in such a manner as to prevent damage to any part of the valves. I END OF SECTION , . ~ 1 ~ I i ~ 1 } 1 15136-1 1 1 4 DIVISION 16 ELECTRICAL 16000 GENERAL ELECTRICAL RE UIREMENTS 1.00 GENERAL I' 1.01 SCOPE v }•Y } F..1. The electrical work shall consist of ' providing complete and electrical operative installations as shown on these Specifications the Plans and provided for in operate all as well as that necessary to interface with and labor plant equipment. The work includes the furnishing of all furnished tbyithe'Owneretoiprovidexaecpmpletesancificall system, d workableselectricale # r 1.02 DRAWINGS ' The drawings are not intended to and do not show all a ui i though such i as j nctio itemspofutlboxes, conduit fittin s q pment and such equipment may not be specifi$ally similar, Even these specifications nor shown on the drawins drawings, if the Y mentioned in shall be included inethecworkrreto makeundernAlthesetee Instal onstallattishop on, they bons, 1.03 LOCATION OF EQUIPMENT specifica The drawin switches gsgshow the approximate location of cabinets ' suite Is location sliceptbeldete nu other equipment, 'panel boards, construction, The most Final location shall be as a pctual roposed aburtement he during i and approved by the Engineer, y the Contractor 1.04 AS - CONSTRUCTED DRAWINGS s The Contractor shall maintain a set of Drawings and Shop Drawings shall be markedeas they occ on, Changes, modifications, or corrections The underground conduits shallbe shown location and burial depth of set toct shall date and sign dimension complete set to the he Engineer upon completion, 1,05 CODES AND STANDARDS j ~ All electrical material with the applicable currentrstandard ruleseSreguhations in conformity specifications of the following authorities; ~ and 16000-1 4 , IF 541 yi - 1 + I '1 A. National Boa+d of Fire Underwriters (NBFU) and National Electric Code (NEC). B. National Electrical Manufacturers Association (NEMA). i C. Institute of Electrical and Electronics Engineers (IEEE). D. Insulated Power Cable Engineers Association (IPCEA), E. American National Standards Institute (ANSI). r F. National Electrical Contractors Association (NECA). G. Association Edison Illuminating Companies (AEIC). H. National Bureau of Standards (NBS) (National Electrical Safety Code). 1. Rural Electrification Administration (REA). J. City of Denton, Texas. All electrical work shall be performed under the direct supervision I of a Master Electrician holding a valid license in the State of Texas. 1.06 STORAGE AND CLEANUP All equipment stored on the fob prior to installation shall be suitably housed and protected from weather or other damage in full accordance with the manufacturer's recommendations. All equipment equipped with space heaters shall have the space heaters energized and operational as soon as possible following installation. Space heaters shall be kept in operation to protect equipment from moisture, All equipment shall have been properly oiled and lubricated during storage and before any operation and shall bAt the 1 checked by a manufacturer's representative prior to startup. completion of the work, the Contractor shall leave the storage area in a satisfactory condition. ii 1.07 SERVICE Y 120/208, 3-phase, 4W, provided by a power panel at H.S. Pump Sta. 5 (Currently under construction). 1.08 SUBMITTALS l ' Unless otherwise specified, the Contractor shall furnish to the Owner, for his approval, shop drawings showing all equipment he l t bentemplates submitted for incorporating directed, Equipment, ematerials, 16000-2 y J MWFIPW 1 } and articles installed or used without such approval shall be at the risk of subsequent rejection. The shop drawings shall include catalogue numbers and complete descriptions. Approval of such drawings, equipment and specifications shall not relieve the / Contractor of the responsibility for the satisfactory performance of kk the equipment as furnished and installed. 2.00 PRODUCTS 2.01 MATERIALS I A. GENERAL it All material shall be new unless otherwise specified. All t r, materials of a type for which the Underwriter Laboratories have established a standard shall be listed by the Underwriter's Laboratories, Inc,, and shall bear their label, r 3.00 EXECUTION 3.01 INSTALLATION . All work shall be performed by competent workmen, skilled in this type of work. Work shall be neat throughout, and structurally sound. 3.02 TESTING All circuits shall be rung out and on completion of the work all of { the installations shall be entirely free of grounds and short circuits. 3,03 GUARANTEE s The Contractor shall guarantee against mechanical defects in any or all materials and workmanship covered by these specifications and r shall make good, repair and replace, at his own expense, any defective work, material, or part which may show itself within a period of one year after final acceptance of the work. END OF SECTION } ~a a a 16000-3 16100 WIRE AND CONDUIT SYSTEM 1.00 GENERAL 1.01 SCOPE I The work covered by this item of the Specification includes furnishing all labor and material and performing the necessary operations to provide a complete wire and conduit system. 2.00 PRODUCTS i 2.01 MATERIALS A. LOW VOLTAGE WIRE (60OV) 1 All conductors shall be 600 volt thermoplastic insulated single conductor copper, 75°C, Type THHN/THWN for sizes #8 AWG and smaller, Type THW for sizes #6 AWG and larger, wet or dry. The wire shall be water tank tested and approved as machine tool wire in accordance with the National Machine Tool Builders Association. w No. P-142 C for y Type Specification THW, i Anaconda, or -400 for Type THHN/THWN and approved equal. B. PAIRED SHIELDED CABLE All paired shielded cables shall be 7/28 stranded copper ' conductors with 013" extruded PVC insulation, twisted into r pairs, stranded into a core and enclosed in a non-hydroscopic core tape, 100% coverage helically wound aluminum foil shield, t drain wire, and ,035" minimum extruded PVC jacket. Pairs shall be black/white with each conductor printed with a pair number at to meet one -725 h and intervals. IEEE l 383, and Cables shall shall be b Alpha rated No. 5610/2000, o NEC approved equal. C. PLASTIC CONDUIT Plastic conduit shall be used for all underground applications. All plastic conduit shall be schedule 40, rigid, high impact polyvinylchloride, conforming to Federal Specification W-C-1094 and Underwriters' Laboratories, Inc., Standard UL-651. Plastic 4 conduit shall be Certainteed, or approved equal. D. RIGID STEEL CONDUIT j • Rigid steel conduit shall be used for all exposed and above f, ground applications, All rigid steel galvanized conduit shall be hot dipped galvanized inside and out and shall conform in all 16100-1 I _ r' respects to Federal Specification WW-C-581d, ASA C80,1 and Underwriters' Laboratories specifications. The conduit shall be protected by a chromic acid rinse, Conduit shall be Triangle PWC, or approved equal. / E. FLEXIBLE CONDUIT All flexible conduit shall be American Metal Hose with a neoprene jacket and Appleton Sealtite fittings, or other approved equal. 3.00 INSTALLATION { 3.01 WIRE A. GENERAL All electrical wiring systems shall be color coded in accordance with the National Electrical Code. In conduits or runs containing from two to seven conductors, no two conductors shall be of the same color, In conduits or runs containing from eight to fourteen conductors, the same color shall not appear more than twice. For runs of more than fourteen conductors, the same color shall not appear more than three times Unless rdcessary for pulling purposes, conductors shall be continuous from ` terminal block to terminal block without splice. Under no ! [ condition shall conductors of a different color be s!Tc"-"ce toget er. All-circuits sha a -tagged at terminals. All wire and cable p8 AWG and larger shall be stranded, The ' minimum size conductors permitted is N12 AWG, except as , specifically indicated on the Plans. All wire shall bear the approval of Underwriters' Laboratories, Inc. B. LOW VOLTAGE All conductors shall be continuous from o,itlet to outlet and no splices shall be made except at outlets. Sufficient wire shall # be left at all outlets to make connections to equipment without straining. All splices and taps shall be made with mechanical type, compression type or spring connectors. Splices and taps shall then be reinsulated with Scotch Tape No. 33, half lapped, to a thickness of 1-1.12 times the conductor and insulations thickness. C. PAIRED SHIELDED CABLE a Paired shielded cables shall be grounded at the Instrument Panel end only and shall be insulated from ground elsewhere. The shier; shall be made continuous for the entire run. The 300 i i 16100-2 t a volt cable shall not be laced with or placed in the same conduit with cable rated at 600 volts or greater. D. GROUNDING All conduits, motors, cabinets, outlets, and other equipment shall be properly grounded in accordance with National Electric x Code requirements. The ground wire shall be bare stranded copper, sized as shown on the Plans. Where ground wire is exposed to mechanical damage, it shall be installed in thick wall conduit. Connections shall be made to equipment with soiderless connections. Wire connections to the ground conductor shall be of the fused type equal to the Cadweld process. The metal surface under the grounding lug shall be cleaned to bright metal. Connections to motors shall be to the grounding stud which shall be threaded into the stationary frame and not 1 an end bell, and the ground wire shall not be lugged to a mounting bolt. Equipment not specifically shown connected to a ` grounding conductor shall be grounded by means of a conduit supplying the equipment. Where direct metallic connections cannot be made, bonding jumpers shall be used. 4 Grounding mats shall be constructed and installed as indicated 1 on the Plans. I 3.02 CONDUIT E A. GENERAL All conduit buried in earth or in concrete shall be rigid PVC. Unless otherwise indicated, all other conduit shall be rigid steel, At the transition from underground or from concrete, PVC conduit shall be protected from mechanical damage by extending rigid steel conduit a maximum of twelve incises and a minimum of four inches into earth or concrete at the transition. Conduit sizes shall be as shown on the Plans, except that in no case i shall a conduit size be less than that required by the National Electric Code. The minimum size permitted shall be 3/4 inch. 6, UNDERGROUND All underground conduits shall be buried a minimum of la inches deep and as shown on the Plans. Buried conduit bank shall be + backfilled with material free from large rack, paving material, or large angular substance which may damage the conduits. C. ROUTING AND SUPPORT Conduits in buildings shall be exposed on unfinished ceilings i and basement areas as shown on the plans. Ccnuults shall be i 16100-3 t rigidly supported to the building structure by means of straps or clamps, bolted or screwed to the structure. The straps shall be of the two-hole pipe strap type and clamps shall he of the one-hole pipe strap type. D. TERMINATIONS Double locknut construction shall be used on all conduit terminating in stamped metal motor terminal, motor starter, safety switch, outlet, junction or pull box, etc,, with approved type of bushing over end of conduit. Length of conduit threads shall be increased at outlets, Junction and pull boxes wiere necessary to accommodate double locknuts and bushings. All bushings shall be fully seated against end of conduit. E. BUSHINGS Bushings shall be composed of an outer threaded metal ring with an inner insulated compound ring molded into the metal ring, or shall be of the threaded type, composed entirely of an approved insulating material. { F. NIPPLES Conduit nipples shall have two independent sets of threads, Running threads shall not be used. Where conditions require joining two fixed conduits into a continuous run, a conduit union shall be used. G. PULL BOXES AND JUNCTION BORES "Condulet" type fittings shall not be used on conduits containing wire N4 AWG or larger. Pull boxes shall be provided and installed where necessary to facilitate the installation of cable and wires. The pull boxes shall be N.E.C, size, Junction or pull boxes installed in concrete slabs shall be cast iron, All other boxes and outlets shall be 304 stainless steel or cast iron with watertight covers. All pull boxes and Junction boxes shall be accessible and not buried. H. EXPANSION JOINTS Expansion joints shall be installed in all conduits crossing concrete expansion ,joints. Provisions shall be made to prevent shear strain at crossings, 1. MOTOR CONNECTIONS Connections to motors shall be flexible metal conduit for a distance not to exceed thirty (30) inches. 16100-4 vi r `7 i r J A it J. INSTRUMENTATION Transmitters shall be of the thin film strain gage solid state electronic type having a 4-20 ma d-c output signal proportional to the calibrated pressure range. The transmitters shall have 315 stainless steel wetted parts and Hastelloy C diaphragm. The transmitters shall have a heremetically sealed enclosure with externally adjustable span and zero, an integral ,junction box with an output meter reading 0-10 and an accuracy of 0.25% of span, , A Transmitters shall be Gould Statham PD 3000 Siers, Leeds and Northrup, Taylor, Foxboro, or approved equal. Each transmitter shali include an integrally or externally mounted transient protector to protect the instrument against f lightning produced voltage spikes and other transient surges. i Each transmitter ;hall be furnished with a 3 valve manifold with NORMAL, ZERO, BLOCK, CALIBRATE and BLOWDOWN functions. s' K. PULL BOXES Pull boxes shown on the Plans shall be precast concrete. Pull i boxes shall be 3'010' Boxes shall be provided with a traffic cover, and shall be Brooks Type PB33-36, or approved equT - I END OF SECTION I A i 1 j 1 i iC I k S 16100-5 t T a eV yl \ 415 I• r . p .r ( S~ `Ct r:: are I'a r Str,rnl kl ' ~~rrgt N0 tr 4,:4E t' Oft 1` a I• _ ~ 11 Y7`~~I r ~ rq// { r p ro~~ fMA ~I e,<1sf ~ ~ , I ~ c~ ,ulwRtr' ' , . ~I,Qt v ~ ~f•:.~,s ~jI ~r Welded t } 1 ' ' 14/re W Hull.' .I s -AROFb5E0 COWRR7CF._ ~ _ e 14': N11 I 1 ~bK 4 1 p YVIl 4-11 {~j I~ { a..,. 111 r f j - ; ~sf C'wEA A' F. tl. 1 1 0.l l,:l h Et4" ~j. 'M I 1 / u 'L 1`~ AY I' Ix►A \igi'On LR Y/16,;iMIT 'S'IC ,i`ldt9i'r yfw ''fr. ~ a 'h I fW) [n 3I h S l' , I eoln ~ VIT Ee113 T 1N3 0A\L0 1% 0A , r , ' i 1 j , ~,.-I+ 1. Cd~ DI CeMon rIriJTi it7 rl4L! 40 ( de Mn recl ~ 1. . e7 - fl.fi t.t„ r414t tWt } „ . R, y, IN_ oex r1 l) /NG r Kr -VI d'I {I _h ~'riVOr• .7i / ? 21-0. SM% 6020uvo'saa9 . f TANK i ' 1 1 , ' i i d CtafRNCCI RfrAiN/N6 WACC onAas N G WIT ~T _ ! a h, } _y - ! l ❑ Cafainlet RYU EY6101Ayy Power Panei u 1 uvb, GOA 2012 046, !!lV4 ;f t N #I ~0 6atterfyValti -Main L 1 't"rtrl)atk►I , II Yt.P.'brtk Neaf 1 . t. ' }k f=. \ / I Ta . ~ a'r0atktl 1'Ipt.l920 P tat A{eamtnt, S>ai 0. C ,~rL.yr ~.r trip M,# C'r~ _•i~l 7 iii } 'I t u' i+y ;r'7, ~athodk,Priot2 ta0at'' ISet(?16,M'A4,s/4'C~ ' I;.r 7raI rrul; a' Dash;b ; - Sun P 1~hr1 ( Sµn,p Pan.e) / " 1 1 I~ tthedel s I , Spere! ,S Prat. 4 489 , ~ I (c~tlydr Pr'olactkn) . t = t , = . ~ ~ } ;~X1STING PI'M R PANFI I , t } y* II (Now shown underlined I 3. i Iza. c I I . 1 hh I n~ :.1•~ . ' Includes f'LLhltsht BrtokdY) 1 P _...I -+r . 'r J w 4` o t y II ! } / f, l~ i -yea r f 1 i ry [a {;~},iJ,~) ul ' M7 / ' \ I) I If 1 h tlW_ j Y 1 1 c " IPf 1 / i1 P1„AN H. 5.P DE oki57t Sri 1t~o~a,,fy~e, e /n ~ j Scale.. I/la*'I'~-C" .:r ' I a h1A I I ELEC ICAL LECxE!tj i i (I rroA rN r.- ` I 0 let, ear I i , - ~ ~ J~~.r tn+eM , h I e 1 Wirt A Corlduft EAfrpslri' w w t ` pe R ~1r yN°e M) i I +I BUYI{d S•'' j 'tf tel. ,T I 1 1 k WIC 6 4l CdeftdLLif r'f > i I Wfrt i C41,dltlf Valtl 0111 4 J....._I ~ r 7 aj 1 ~~JS r I• i V V I ry td uP r t ~1/'A A, c jt 7t{ 1 1 ♦ - N Ilfey I~f"~ t " do r e 1 ~II - - wL d 'CcMdu11 it yr~cyl p~wn`~ f ' , tvncl.ea 9 u]tu, II. e r y' d fzoat~f?Y`~!'~,~; r*1~ 1 i ` ~Pe Pik 11 60A t,NO tioroh dQA1f•1or1 J. Tys+idaify TOW Wly"t,C (t; R+Yl1+ . T e., o 11 ly J+,netldq bore' Mwnttd TO V of I~wF~g ee~~ Tint a , 4 +j t Rt ulrt . ('Stt Vaiuil Na 1) Ldaot P.aerdyh w :a + y N} I I 1 .°e : F~rdre 6plranq by CafhcJfc Prateotian c r.cr" y 1 ni ~q o + A u : u f ,l Por. New ?fppK (on'Ty) Instatiil OIL Ntra Gaihedla Pry~ltECl(Eyl 9gntyM P.a tail 10 1 k SK40 $e r t`Y ~l rl _i .t f{f t Irr ,li f, r1 r i tyy ~ s . yye~tt I .'~1411~~/. h+N=!e' ♦..b frrr mr..C i ~ 1 4 { { h ~ 'AS ' ! t WAT" TREATMENT PLANT ED(PANS*N i 1 1 J. q I r'a r, a PLAN1 •OYAur r„~sc, - alit'""' / lu'►,;r ~~e. Ala ' { tib , r , r Yi-Y tsi:,a NICHOLRING a"t is t , rr{s OOif91NINC IML1M{M ' ,w{ Itq} P f , oeolr r'P.e' IGIIY I a. f:;% tt err ~ ilo',e l.r ~ ' ! ~ I•!G P>tw foul PV r¢' ~ I c r;.n - J! Cdr bar 'r' Vole L, CCo,f / f ve/ I % 1• le e,N, _ r. r ~ \ d•n / hire MUh l rx of if d'._.l -4. '1'C: Y'.tt. ~ L_ l .44'~r !2'M"ub/F/or.9e GV.~ i lcl.' 2'_6.1 r ECTION B 8 y~\ rd • car ,e' - - - A iro• deolr ! 1 I 4 I4 ,.a10 A i;l I l` ,I ~ ~ r y L 4 es s•o 1 1 t t ~ r--1 6a po.. o;e X P6.^o .1'Y~ i 011 !'O !o i !O ra 1 j Z se o .e+ - l4r",o •7 cb•r r AO PLAN m.1404OV icz u Vj, rr S ! ee' C re-l i, o r art / f All 0-5 eta's 044 otpooo'd"s 6 + r r . 1' ` '•k ' 1 i 6e r. 67' !C - { ~ I t a ! r1 S2 ~c t' 4 1rla...i Iii Ole / ! ,T Ske: Cr'i q iIII I ! /'•6 t S6 ca -h x'° Y SECTION C C ` 1 E. or Nork I vase. aatr!r mA, bra tY_ r6'oe ccQs'y^_Q'_hS+i' { fnll".]do folk 1 - ! ~ it 0.ne! JmY I J ~I'C[I n, Hff f ~ ~ I '1 ~r .Y' p;t a ir.1.a!! ,e,v btari 1 _ ] ~I1 1 L~ ! r7 day 'l : : I rI' C o YAt ,e.'J to .'j old pe lldI 3d ~Y1.1e: rl _I. \.l. we d. • 111 ~ p Eau trey i i l ~F.. 52 i ; I t 00 ~ y \ ~ n i _...CTION DAD ((~'t y WA L l! 1 \ •,1 ,f',111f ~1 r 3. 41 E DEMON, TEXAS WATER TREATMENT PLANT EXPANSION C= ' .'~:•,..•..l: 2MG STEEL GPOUND t STORAGE TANK 'Er a1 tct FNE£SE8NICNOLS,mc Y11 r[e,ises i{ rr» tee t04YUlANG (tiGIM(( mi AS 4a1to ,e 'Axo (a. t. LORI 1VORIN, IUIJS tITN B 000 it a 3 j 1 1 T , I 4 r9 j Ca fh.:dc P, tee h'a' Errclc d.rre rteSl,r•f(.- ir/ / AP L /~t.•n /~/,~j~ ~ \ L.d r ~'l Cca Mcaa~d 4 ~f Coto /e FIalrry__,., M5 $It'Yl ' a/f .e /on)tw j / . TpAr Cl2 G-,'/s'C. O•:,d4 fwd r•.pDETAIL No to n F v. "rir / z r crir fry, 1 111 ~ ~Sc 72 _ I u'r N. W.F! Concrete i r~ •:.~orr SECT/ON - RrnSw•a!/ t fl. 7 ftbrJ /lt nf„ Or MiMn.y, 4'(C,VAM P:ip 111 •rY Se 1 4 Cr'C Sp glONA Or lpv~/ 4.- f III F X16 ~ ~ I lBpddi s~1 _ 4 corm It4 _ S/.e ry ~~•p ed. . j ~ I r el 1 ,y -,i--hmp 2wgw/tGJ~ 1 -4qe N1wE C / t ( a b4Cfrlr H ..q (See Plan Far u\ jt'Wf Only -4 \ Mra Re, nf. - Lt. r 1 x~Ill'r ra t! \ r_f/rr. _ rt Ape, Per i Yu. 1 brreJN51 p r Sump Permp(for Onl/el V4 tee, BnrS Y.ray kR,115Y, r/, 60,v1, \ / rviHe• % ,r. ~ 2 w 4 fa I °:~;•r UErs1l~ 'lA'' 6UrrE.QF_L_Y VALVE VAU SCIlD fool' try. FLAN Scv'rr ld"~ /'~0 i.... r , u47,..(.,v . 1v L. l ~ I 5 a. 1 ' F I f ~ 11 L x5'12' f tf J I I , b I••~ T 1'c' BW. IJYe SD'?7 K r /led -077 r--~ J J(r~` ~ Gene. Mre,n, 4L I • l + ' Ihie I' 1?. E.JJb ~ G~GN.W.F. . 5do to s SECT/ON _ a , ~~I' ~I. ~ F_ _ ~ ~ _~~•-•_P~nI V, IA /~pArll art/ le... d r7 tell ~tu1 ' f~ .io J • Z . , ~ ~ I I ' i _ ~~~I Pl.< f D46 EFFF~455 rl 4 ~ ae VV cue Ikfe J de 14 f "r1 Mon,r'acrurerS Cable. k tw _C.! f.U4AAole Steps w-.,.«N~~n a Steps I 1 { wI d 6 ~ " ~ IS''ic staggered oufler Al.r N"10 y , LL tl, yz'~ R, /1Y J0, F0 M2. r /I AIrI✓ of l4N II I '.71'{Y'J~'i' k'= + r ♦ 7' Yc s • 4e ~ cim A Su~o i \ Ys "Capper Line- ' le:'GJnc..m da/loN ` d 9unjp _c.0r10N Is c, I 1 ~ "7 Ncte , PI-essurc 1~ \ l Pipe Stand Mountedf to F/oart [Far ov<1o15 valve vault Onyl _ 7 nru ~a S,~efuU o J i, I men Yo H uOnyl JE.a Jr~ IrorJ~,c DfNroN, TEXAS { WATER TREATMENT PLANT EXPANSION r' LT CLEARWELL RETAINING WALL DETAILS PC7 uuxr toz FREESE 0NI CHOLS, INC. jum--r-ca, l905 ` Acq'? ~ , true c'J [t1N5U[IIf10 (t1UY[[RS KJ[t M Jmtt 1 awt t.c,c. OTN FM M'[MfR ftiAt aA0 009 _ tt m yr=, is ~ r... . 1 f r ~ t I I i 1 1 I I M I ( _,555 I 1 i Y~l ~'3 1 Al N'p]gJ l\~J I L:1 r l' ..li \r~ { 4 'I