HomeMy WebLinkAbout2018-10-01 Agenda with Backup
!"#$$
!"'!()$"$
%&'!()!*+,--. !/)
0.-1-2!3.4#5!67%8&
999)+ 1:;.-1-)+1<
*))$+!,+)$-.
!"#$%&
*"$-. <!2%"=)1!4<!>64?44;56!,*
()$"$!/0(!)$1.&!2''%)3
4567!89!:"%#3!01))
!"#$$! %"&"!'$"(!)"&"*$ ! "(!)"(+ ,-". /"!'$"*$ ! "0 /$1$ /$ !"2,'-"*3!4,!"5.4/"&"
64+3!$$3" "# /.)7"8,!9$4":7";<:=".!"::>?<".@A@".!"!'$"*$ ! "02*"($ !4.-"8&&,$37":?<B"C@"D,+3!"
2!4$$!7"*$ ! 7"6$E.3".!"F','"!'$"&--F %"!$A3"F--"9$", 3/$4$/>
!"#$%&&'!()%*!"+&
0*":=T:KSU
,
G$,$H$"."4$14!"&4A"(!)"&"*$ ! "3!.&&". /"'-/"."/3,+33 "4$%.4/ %"!'$"&--F %"
, 3!4+,! "14I$,!3>"":J"0 !$43!.!$"?K"L$3!". /"M.3!7";J"N@2@"O%'F.)"?BB7"?J"6$.3-$)"
D. $" ,-+/ %"3/$F.-P37"QJ"R+-! "2!4$$!7"KJ"5 $"54.$"2!4$$!7"SJ"D1";==". /"
2'$4A. "*4H$@
(4=>!&!?!@A/!3B#-5C1B#1-!DB1E.+5)C;:
!"#$%&
(4=>!%!?!F-?/ 5.<!G.C1B)C;:
(4=>!H!?!I3FJ!K..B)C;:
0*":=T:KB?
-
G$,$H$"."4$14!"&4A"*$ ! "02*". /"'-/"."/3,+33 "4$%.4/ %"!'$"&+!+4$", 3!4+,! "
&"*$ ! "O%'"2,'-@
./!(0123'(45+%6&
V@""N /$4"2$,! "KK:@<Q;"&"!'$"6$E.3"81$ "#$$! %3"V,!7"4$31 /"!" W+4$3"&4A"!'$"(!)"(+ ,-"
4"!'$"*02*"4"!'$"1+9-,"F!'"31$,&,"&.,!+.-" &4A.! "4"4$,!.! "&"1-,)7"4".,,$1!"."1413.-"!"
1-.,$"!'$"A.!!$4" "!'$".%$ /."&4". "+1,A %"A$$! %""VC*""N /$4"2$,! "KK:@<Q:K"&"!'$"6$E.3"
81$ "#$$! %3"V,!7"14H/$"4$14!3".9+!"!$A3"&",AA+ !)" !$4$3!"4$%.4/ %"F','" ".,! "F--"9$"
!.P$ 7"!" ,-+/$>"$E14$33 3"&"!'. P37", %4.!+-.! 37"4", /-$ ,$X" &4A.! "4$%.4/ %"'-/.)"
3,'$/+-$3X". "' 4.4)"4"3.-+!.4)"4$,% ! "&"."1+9-,"&&,.-7"1+9-,"$A1-)$$7"4"!'$4",!Y$ X"."
4$A /$4".9+!". "+1,A %"$H$ !"4%. Y$/"4"31 34$/"9)"!'$"%H$4 %"9/)X" &4A.! "4$%.4/ %"."
3,.-7",$4$A .-7"4",AA+ !)"$H$ !"4%. Y$/"4"31 34$/"9)". "$ !!)"!'$4"!'. "!'$"%H$4 %"9/)"
!'.!"F.3".!!$ /$/"4"3"3,'$/+-$/"!"9$".!!$ /$/"9)"."A$A9$4"&"!'$"%H$4 %"9/)"4". "&&,.-"4"
$A1-)$$"&"!'$"A+ ,1.-!)X"4". ". + ,$A$ !" H-H %". "AA $ !"!'4$.!"!"!'$"1+9-,"'$.-!'". /"
3.&$!)"&"1$1-$" "!'$"A+ ,1.-!)"!'.!"'.3".43$ ".&!$4"!'$"13! %"&"!'$".%$ /.@
R--F %"!'$",A1-$! "&"!'$" !"#$$! %"F!'"!'$"*$ ! "0 /$1$ /$ !"2,'-"*3!4,!7"!'$"(!)"(+ ,-"
F--"4$, H$ $" "."21$,.-"(.--$/"#$$! %" "!'$"(+ ,-"L4P"2$33 "GA".!"(!)"O.--7";:K"M@"#,Z $)"
2!4$$!7"!", 3/$4"!'$"&--F %>
5+%6&7!"5(3'8'3291/!(&'3%"9+'!(
0*":=T:SQK
,
O-/"."/3,+33 ". /"%H$"/4$,! ", ,$4 %"!'$"#.)4\[3"+ F-- % $33"!"$E$,+!$". "
4/ . ,$"./1!$/"9)"(+ ,-" "6+$3/.)7"2$1!$A9$4";K7";<:="4$-.! %"!"."21$,&,"
N3$"\\$4A!"4$W+$3!"\]0*>"2:BT<<<B9J"!".--F"&4"."A+-!&.A-)"+3$" ".":;@?BT.,4$"3!$"
!'.!"3"%$ $4.--)"-,.!$/" "!'$"$.3!"3/$"&"54 P$4"G./7".114EA.!$-)"UU<"&$$!"3+!'"&"
'+,$#-).$)/012013*2
'(#)*)
!"#$%&*))$+!,+)$-.2%"=)1!4<!>64?
2+!'"D1";==" "!'$"(!)"&"*$ ! 7"*$ ! "(+ !)7"6$E.3@
-0*":=T:SQS
( 3/$4"."A! "!"3+31$ /"!'$"(+ ,-"G+-$3"&"\\4,$/+4$"4$-.! %"!"#! 3"&4"
G$, 3/$4.! ".3"14H/$/" "(!)"(/$7"2$,! ";T;U\]%J\]::J"3".3"!".--F". )"
(+ ,-"#$A9$4"!"A.P$"."A! "!"4$, 3/$4" ", $,! "F!'"0!$A"^:=T:SQB@
0*":=T:SQB
/
( 3/$4"."A! "!"4$, 3/$4"!'$"2$1!$A9$4";K7";<:="./1! "&". "4/ . ,$"
.114H %"."21$,&,"N3$"\\$4A!"\]0*>"2:BT<<<B9J"!".--F"."A+-!&.A-)"+3$" "."
:;@?BT.,4$"3!$"!'.!"3"%$ $4.--)"-,.!$/" "!'$"$.3!"3/$"&"54 P$4"G./7".114EA.!$-)"
UU<"&$$!"3+!'"&"2+!'"D1";==" "!'$"(!)"&"*$ ! 7"*$ ! "(+ !)7"6$E.3X"
14H/ %"&4"."1$ .-!)" "!'$"A.EA+A".A+ !"&"_;7<<<@<<"&4"H-.! 3"!'$4$&X"
14H/ %"&4"."3$H$4.9-!)",-.+3$". /". "$&&$,!H$"/.!$@""\]2T:BT<<<B.7"M ,-.H$".!"
*$ ! 7"O.)-$)"`.%+43PJ@
("M"G"6"0"R"0"("V"6"M
0",$4!&)"!'.!"!'$".9H$" !,$"&"A$$! %"F.3"13!$/" "!'$"9+--$! "9.4/".!"!'$"(!)"O.--"&"!'$"(!)"&"
*$ ! 7"6$E.37" "!'$"aaaaaaaa/.)"&"aaaaaaaaaaaaaaaaaaa7";<:=".!"aaaaaaaab,-,P"\].@A@J"\]1@A@J
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
(06c"2M(GM6VGc
C86M>6OM"*MC68C"02*"(MC6GVD"8RR0(M2"VC*"6OM"(06c"(8NC(0D"L8GZ"2M2208C"
G88#"VGM"V((M2205DM"0C"V((8G*VC(M"L06O"6OM"V#MG0(VC2"L06O"*02V50D060M2"
V(6@""6OM"(06c"L0DD"\\G8d0*M"20eC"DVCeNVeM"0C6MG\\GM6MG2"R8G"6OM"OMVG0Ce"
0#\\V0GM*"0R"GMfNM26M*"V6"DMV26"Q="O8NG2"0C"V*dVC(M"8R"6OM"2(OM*NDM*"
#MM60Ce@""\\DMV2M"(VDD"6OM"(06c"2M(GM6VGcb2"8RR0(M"V6"?QUT=?<U"8G"N2M"
6MDM(8##NC0(V608C2"*Md0(M2"R8G"6OM"*MVR"\]6**J"5c"(VDD0Ce":T=<<TGMDVcT6g"28"
6OV6"V"20eC"DVCeNVeM"0C6MG\\GM6MG"(VC"5M"2(OM*NDM*"6OG8NeO"6OM"(06c"
2M(GM6VGc\[2"8RR0(M@
'+,$#-).$)/012013*2
'(#)1)
City of Denton
City Hall
215 E. McKinney Street
Denton, Texas
www.cityofdenton.com
_____________________________________________________________________________________
AGENDA INFORMATION SHEET
DEPARTMENT: Transportation
CM/ DCM/ ACM: Mario Canizares
DATE: October 1, 2018
SUBJECT
Receive a report from City of Denton staff and hold a discussion regarding the following construction
projects; 1) Interstate 35 West and East, 2) U.S. Highway 377, 3) Teasley Lane including sidewalks, 4)
Fulton Street, 5) Bonnie Brae Street, 6) Loop 288 and Sherman Drive.
BACKGROUND
Staff provides a Texas Department of Transportation (TxDOT) On-System Report as part of the monthly
Denton City Council Mobility Committee meeting. This report is compiled by the City of Denton
Transportation Consultant ITS and outlines project budgets, status of specific projects, current construction
activities, project constraints, and traffic pattern impacts. A copy of the September 2018 On-System Report
has been attached as Exhibit 2 for reference. Staff will highlight project schedule and project components
and public outreach efforts associated with the I-35/Loop 288/Brinker/Mayhill project, I-35W project and
the U.S 377 project found in Exhibit 2.
35Express Phase 1B
The limits of this project extend from the IH-35E Dallas Drive/Business 77 ramp south to the IH-
35E/Mayhill Road intersection. There are four components to this project:(1) adding the third general
purpose lane (GP) on I-35E; (2) enhancing capacity of the Loop 288 intersection under I-35E; (3) adding a
new underpass connecting Brinker Road to the southbound I-35E frontage roads; and (4) adding a
southbound to northbound Texas U-turn at the I-35E/Mayhill Road intersection. OHL is the TxDOT
contractor for this project and initiated construction on this project in March 2017. In January 2018, TxDOT
indicated construction was scheduled to be complete by December 2018. In August, OHL notified TxDOT
construction would not be complete until July 2019. TxDOT is currently negotiating with OHL to
accelerate the project schedule, but at the time the report was submitted the July 2019 date is the official
schedule advertised by TxDOT
I-35E, Main Lane Shift and Schedule:
Phase I of the Phase 1B project was to complete a segment of new southbound frontage road from the
existing southbound off-ramp near the Goodwill Store to just south of the Achievers Gymnastics facility.
This was completed in February 2018 which allowed the contractor to facilitate switching main lane as
follows:
Phase 1 Step 1: Transitioned the southbound frontage road traffic to the new southbound frontage
road . Shifted the main lane or general purpose (GP) traffic on
southbound I-35E to the old southbound frontage road. Shifted the northbound GP traffic to the old
southbound IH-35E GP lanes.
Phase 1 Step 2: Demolish Loop 288 bridge for northbound GP lanes and reconstruct bridge for new
northbound GP lanes. This new bridge, currently under construction, will allow for wider footprint
or more capacity, for Loop 288 under I-35E. At the time this report was submitted, OHL indicated
placement of the bridge beams for the northbound GP is lanes targeted for the weekend of September
28. This effort necessitates the closure of Loop 288 at 35E as a safety precaution.
Construction of a new bridge for northbound GP lanes at Brinker. Current schedule from TxDOT
indicates bridge to be completed late December 2018. Brinker access under I-35E, northbound
frontage road to southbound frontage road is targeted for February 2019.
Phase 2: Completion of the two bridges at 288 and Brinker will then allow for the GP lane traffic
switch similar to Phase 1 Step 1. Both temporary northbound and temporary southbound GP lanes
will be shifted to the newly constructed northbound lanes. The current TxDOT schedule indicates
the traffic switch will take place December 26, 2018.
This will then allow for the construction of the permanent southbound GP lanes and bridges. Phase
2 will also include construction of a segment of new southbound frontage road at Loop 288, and the
completion of the intersections at Loop 288 and Brinker Road.
I-35E - Loop 288 Access Improvements:
Currently, the Loop 288 underpass consists of two lanes in each direction with dedicated left turns from the
left lane and optional left/thru from the right lane, and there is single sub-standard Texas U-turn from the
southbound frontage road to the northbound frontage road. Upon completion of the OHL 35Express Phase
1Bproject, the Loop 288 intersection will consist of four lanes in each direction with the two inside lanes
used for left turn only movements and the two outside (right) lanes dedicated for through traffic. Finally,
Texas U-turns will be constructed for the north to south movement, as well as the south to north movement.
The travelling public has experienced increasing levels of construction congestion along all of the secondary
roadways on I-35E from Teasley Lane (FM 2181) to south of Mayhill Road. Staff expects this congestion
will continued to be experienced for the duration of the OHL project.
I-35E - Brinker Access Improvements:
Currently and the
Hilton Garden Inn, providing right in/right out access to the southbound frontage road. Upon completion
of the OHL project, Brinker Road will be connected to the southbound frontage road via a newly constructed
underpass under I-35E. Once completed, the Brinker Road intersection will have three lanes in each
direction with the inside lane dedicated for left only and the remaining two lanes for through traffic.
Additionally, TxDOT has warranted a signal at this intersection which will be constructed as a part of the
OHL project.
I-35E - Mayhill Access Improvements:
As an interim improvement, the project included the addition of a southbound to northbound Texas U-turn
atMayhill Road. This was opened to traffic summer 2018.
I-35E - Dallas Drive Closure and Detour:
Project construction phasing for the OHL project has called for the closure of the Dallas Drive entrance
ramp to southbound IH-35E. This southbound entrance ramp will remain closed for the duration of the
project to allow OHL to reconstruct the IH-35E/Loop 288 bridge structure. The official detour directs
southbound Dallas Drive traffic to the northbound frontage road near the I-35E entrance ramp to the I-
35E/Teasley Lane northbound to southbound Texas U-turn. This permits traffic to access the southbound
frontage road to continue south on IH-35E.
I-35E - Impacts to Teasley Lane:
Wh official detour route has been established, the reality is that much of the traffic travelling
southbound on Dallas Drive will often turn south on Teasley Lane and travel through the I-35E/Teasley
intersection. This increases the level of congestion at this location over the already high traffic volume at
that intersection leading to significant delays in this area.
I-35W Main Lanes I-35E/I-35W Split to SH 170:
The project limits for this project is from the I-35E/I-35W split to State Highway 170 (Alliance Boulevard)
in north Fort Worth. The project will widen the existing 4-lane rural interstate to a 6-lane urban interstate.
TxDOT hosted an Open House Public Meeting in April 2018 outlining the 30-percent schematic plans with
final approval of the schematic plans October 2018. Funding has not been identified at this point thus a
project schedule has not been made available for the main lane project.
TxDOT may advance the I-35W frontage roads, southbound and northbound, as part of a phased approach.
The current estimate for construction activity on the 35W frontage roads is late 2023.
US 377/Fort Worth Drive:
The limit of this project is from IH-35E south to ¼- mile south of FM 1830. TxDOT let the contract in July
and awarded the project to SEMA. Construction is scheduled to begin by mid to late October starting with
utility relocations. This project will widen US 377 from a two-lane rural roadway to a six-lane urban section
and replace the existing Union Pacific Rail Road bridge over US 377. Improvements to the intersection at
FM 1830/US 377/Hobson Lane will also be incorporated as part of this project.
TxDOT and the City of Denton will co-host a public meeting on October 8, 2019 at McMath Middle School
to provide an overview of the project to include construction phasing and traffic management plans.
FM 2181 Teasley Lane:
The project limits for FM 2181 are from Lillian Miller south to the City of Denton/City of Corinth city
limits near the intersection of FM 2499. This TxDOT project will widen the existing two-lane rural roadway
to a six-lane divided urban roadway, add traffic signals at Sundown, Robinson and Cedar Creek and provide
sidewalks on each side of the roadway throughout the corridor.
MCM is the TxDOT contractor for this project and started construction in November 2017 and anticipated
construction to be complete in January 2020. Travelers have already experienced construction detours as
the segments of the roadway have been shut down to one-lane during non-peak times, 9:00 am to 3:00 pm.
An alternative option to FM 2181 is the recently opened segment of FM 2499 from FM 2181 to I-35E.
Fulton Street:
This project involves utility relocations and roadway reconstruction of Fulton Street from Oak to Cordell.
All utility relocations are complete with roadway reconstruction to begin after school closes in May of 2019.
Roadway reconstruction is anticipated to last 60-75 days.
Bonnie Brae:
Bonnie Brae is a project consisting of roadway capacity and safety improvements, storm water
improvements, and utility improvements/relocations. The project extends from Vintage Boulevard to the
south and extending north to Loop 288. The project will be delivered in multiple phases with the first phase
currently under construction along the extreme southern limits near Vintage Blvd. Utility locations along
the next phase north will begin in early 2019 with paving to follow. The segments of Bonnie Brae from I-
35E to University are currently under design and is currently on pace to begin construction early in 2019.
The segments of Bonnie Brae north of University are under design and is currently anticipated to begin
construction late in 2019. The target for completion of the northern segments is currently late 2021.
Loop 288 & Sherman:
The City is currently performing an area wide traffic study that will assess long term traffic impacts and
circulations needs. This study is anticipated to be complete in October of 2018. As this area continues to
grow, the City will be implementing capacity and safety enhancements in the form of small scope, high
impact projects in the short term as a result of the area wide traffic study. Larger improvements identified
in the study will be programmed into future debt programs or alternative funding mechanisms.
Conclusion:
The current and future projects outlined herein will provide substantial capacity to the transportation
infrastructure in our growing community, however construction congestion related to these major corridors,
IH-35E, FM 2181, 377 and the local projects on Mayhill Road and Bonnie Brae will be substantial. Staff
anticipates congestion on secondary roadways as traffic seeks other options. Staff has established
notification protocols so that we may better notify residents and businesses impacted by congested local
roadways due to construction on I-35E, Loop 288 and Brinker Road.
The City of Denton is working closely with TxDOT to provide accurate and timely information to residents
and businesses that will be impacted by TxDOT projects. Currently, notifications are distributed through a
posts. In the case of the US 377 project, TxDOT and the City of Denton will co-host a public meeting on
October 8, 2019 to provide an overview of the project to include construction phasing and traffic
management plans. City of Denton staff will facilitate the discussion with a PowerPoint presentation which
will be provided Monday morning, October 1 prior to the meeting.
PRIOR ACTION/REVIEW (Council, Boards, Commissions)
January 16, 2018 Council Work Session
Monthly - The On-System Report is reviewed monthly by the Mobility Committee and the On-
System project report is posted monthly on the City of Denton website.
STRATEGIC PLAN RELATIONSHIP
-oriented road map that will help the City achieve its vision.
The foundation for the plan is the five long-term Key Focus Areas (KFA): Organizational Excellence;
Public Infrastructure; Economic Development; Safe, Livable, and Family-Friendly Community; and
Sustainability and Environmental Stewardship. While individual items may support multiple KFAs, this
specific City Council agenda item contributes most directly to the following KFA and goal:
Related Key Focus Area: Public Infrastructure
Related Goal: 1.6 Collaborate with local, regional, state, and federal partners
EXHIBITS
1. Agenda Information Sheet Transportation Projects
2. City of Denton On-system Project Status Report
3. North Central Texas Council of Governments Letter dated September 25, 2018
Respectfully submitted:
Todd Estes, P.E.
Director of Capital Projects-City Engineer
Mark Nelson
Director of Transportation
City of Denton On-system Project Status Report
Prepared by ITS
September 2018
PROJECTS
FM 2181 North-South .................................... page 2
US 377/Fort Worth Drive ............................... page 4
I-35E/Mayhill Improvements ......................... page 6
I-35/Loop 288/Brinker/Mayhill ...................... page 7
I-35 North (US 380 to FM 3002) ...................... page 9
I-35W (I-35E to SH 170) ................................ page 10
US 380/Loop 288 Intersection Improvements ... page 11
US 380 East .................................................. page 12
Loop 288 ....................................................... page 13
FM 1515 ....................................................... page 14
FM 1830 ....................................................... page 15
FM 1173 ....................................................... page 17
City of Denton On-system Projects Update: August 2018 1
FM 2181 North-South
2054-02-015 December 15, 2005
CSJ: Schematic Approval:
Widen from two-lane to six-lane
January 28, 2008
Project Description: Environmental Clearance:
divided roadway
January 25, 2013
ROW Acquisition Completed:
From City of Denton/Corinth City
Limits:
limits to Lillian Miller
November 2017
Utility Relocations Complete:
$37,641,150 May 22, 2017
Construction Cost: 100% Plans:
Huitt-Zollars July 11, 2017
Firm: Let Date:
David Nufer February 2020
Contact: Construction Complete:
Current Activity:
Utilities: With the exception of City of Denton utilities, whose relocations have been incorporated into the
construction contract, utility relocations are complete. Additional conflicts located. Charter has begun
relocations. Estimated completion date is early September 2018. DME will pull poles when Charter
relocations are complete. Atmos conflict with proposed inlet boxes and installation of RCP drainage has
been located; Atmos will be relocating from Montecito Street south past Guyer High School. Meeting held
with Atmos. Work is to be phased due to trench conflicts (proposed line would be above and clear of
proposed sewer line but would create a constructability issue). No timeline for relocations available at this
time. City of Denton sewer line found to be in conflict. Contractor has received plans and will begin
working in the area once DISD fiber is relocated.
Construction: Project was awarded to MCM. See attached TxDOT construction report.
Signals: Signal on the north property line at Guyer High School will be included in the FM 2181 contract.
City has provided TxDOT with a copy of the signal warrant for the new signal request at Sundown near the
South Branch Library.
Sidewalks: Five-foot sidewalks with a 3-foot grass area between sidewalk and curb on both sides of
roadway are planned. In those areas where conditions dictate that the sidewalk be constructed adjacent to the
curb, the sidewalks will be 6 feet wide.
City participation: Funding city utility relocations.
City of Denton On-system Projects Update: August 2018 2
TxDOT Monthly Project Report
Date of report: August 2, 2018
R eport prepared by: Angel Karr, AIA Engineers
Project: STP 1702 (730)
Control: 2054-02-015
Highway: FM 2181
Limits: From: Lillian Miller Parkway in Denton
To: West of FM 2499 (Barrel Strap Rd)
Contractor: MCM
TxDOT Project manager: Angel Karr (AIA Engineers) Phone: (512) 293-3631
Phone: (225) 572-9619
Date Work Began: November 21, 2017
Anticipated Completion Date: February 17, 2020
Current Activities:
Current activities include: Continue with installation of City of Denton water and wastewater
utilities. Continue construction of temporary detour pavement from Bent Oaks to Primrose.
Maintaining SW3P within project limits.
Narrative d Continued with City of Denton water and sewer
relocations. Completed temporary traffic signals at Hickory Creek, Robinson, and Old Alton
intersections. Began temporary detour construction on east side of 2181. Continued maintenance of
environmental protection controls.
Narrative description of activities planned for next month: The Prime and their subcontractors will
work to complete temporary signals at Cedar Creek and Old Alton; continue detour pavement
construction; and continue with installation of sanitary, water lines, and storm sewer on the project.
Traffic issues: Ranchman closure for 2 weeks to install waterline will likely occur the first week of
September. Daily ongoing lane closures from Bent Oaks to Primrose for detour construction occurring
through December. Temporary lane closures for material deliveries and to complete construction of
drainage items Teasley.
Plans for changes in traffic patterns: N/A
Item(s) of work currently controlling project completion: Construction of city water and wastewater
and detour construction. Relocation of DME poles from Bluebonnet to Old Alton (Frontier electric
service relocation) due to conflict with storm drain. DISD communication line relocation on Ravencrest
property due to conflict with City of Denton SS force main. Relocation of Atmos, DME, City of Denton
fiber on east ROW from Windriver to Sundown.
Other items of significance: TxDOT working with City of Denton to potentially remove some utility
work from contract to mitigate time impacts. Temp signal at Cedar Creek waiting on material delivery.
City of Denton On-system Projects Update: August 2018 3
US 377/Fort Worth Drive
0081-04-025; 0081-04-035
CSJ:
From IH 35E to 0.26 miles south of FM 1830
Limits:
$43,621,757
Construction Cost:
Project will widen US 377 from a two-lane rural
roadway to a six-lane urban section and replace
Project Description:
existing UPRR bridge. Improve intersection-
1830/377/Hobson
Lochner
Firm:
Sheri Boyd
Key Contact:
July 2009
Schematic Approval:
April 25, 2012
Environmental Clearance:
January 31, 2018
Environmental Re-eval:
December 2017
ROW Acquisition Complete:
Utility Relocations Complete: October 2018
May 17, 2018
100% Plans:
July 10, 2018
Let Date:
October 2018
Construction Start:
Current Activity:
Utility Coordination (UC): See utility status report.
City Participation: Funding city utility relocations.
Public Involvement: TxDOT and City will conduct
public outreach on this project.
Construction: The project let on July 10, 2018. The
low bidder was Sema Construction with a low bid of
There are 632 working days and 25 months of
barricades. Project has been awarded; awaiting
authorization to begin work.
City of Denton On-system Projects Update: August 2018 4
US 377 Utility Status Report
UTILITY STATUS STATUS
ATMOS ENERGY /ƌĻğƩ
GRANDE COMMUNICATIONS /ƌĻğƩ
Because Charter will be raising only six inches,
DENTON MUNICIPAL ELECTRIC /ƌĻğƩ
DME no longer needs to relocate.
New conflict identified with railroad. Two
overhead crossings belonging to DME/Charter
and Frontier. Permit has been approved. Pre-
construction meeting held. Some issues with
permit; Frontier working with UPRR on new
FRONTIER Active permit.
City relocation plans are complete and will be
included in construction plans. Plans were
CITY OF DENTON WATER/WASTEWATER Active
submitted to TxDOT.
COSERV ELECTRIC /ƌĻğƩ
COSERV GAS /ƌĻğƩ
Oncor Electric Distribution /ƌĻğƩ
Devon Energy Corporation/Crosstex
Energy Services (Merged) /ƌĻğƩ
Denton ISD /ƌĻğƩ
Level 3 Communications /ƌĻğƩ
AT&T Distribution /ƌĻğƩ
Relocations completed in December; however,
new conflict identified with railroad; will not
affect roadway work. Two overhead crossings
belonging to DME/Charter and Frontier.
Meeting held at TxDOT to discuss. Permit has
Charter Communications Active
been submitted for approval.
City of Denton On-system Projects Update: August 2018 5
I-35E/Mayhill Improvements
0196-01-109 February 2011
CSJ: Schematic Approval:
IH-35E intersection with Mayhill Environmental Clearance: January 31, 2012
Limits:
Reconstruct interchange at Mayhill
and IH-35E and existing 4-lane *
Description: ROW Acquisition Completed:
frontage roads
$46,212,969 *
Estimated Construction Cost: Utility Relocations Complete:
LTRA September 2019
Firm: 100% Plans:
Travis Campbell, Teresita
Contact: December 2019
Ready to Let Date:
Sarmiento
Current Activity:
Advanced Planning: LTRA continued work on alternatives concepts. TxDOT and LTRA met to
review alternatives. Meeting with TxDOT and ITS on June 6, 2018, to discuss alternatives and
define path forward. LTRA continues with detailed PS&E. LTRA submitted bridge/retaining wall
layouts on August 31, 2018. Anticipate 30% plan submittal in November 2018.
City of Denton On-system Projects Update: August 2018 6
I-35E/Loop 288/Brinker/Mayhill
0196-01-106 February 2011
CSJ: Schematic Approval:
IH-35E intersections with Brinker,
May 13, 2016
Limits: Environmental Clearance:
Mayhill, and South Loop 288
Construct grade separation along IH 35E
July 2016
ROW Acquisition Completed:
at Brinker and intersection
Description:
improvements at Mayhill and South
December 2017
Utility Relocations Complete:
Loop 288
$27,503,078 August 5, 2016
Construction Cost: 100% Plans:
OHL September 22, 2016
Contractor: Let Date:
TxDOT Contacts: Branden Barnett July 2019
Construction Complete:
Current Activity:
Construction: This project was awarded to OHL on September 22, 2016, for a total construction
cost of $27,503,078. The contract allows for 442 working days and 17 months of barricades. See
attached TxDOT construction report. Project is currently in Phase 1, Step 2 configuration. It is
estimated that this configuration will remain in effect until December 2018. TxDOT is working
with OHL to expedite the Brinker portion of the project.
City participation: Funding $2.1 million for local match on Brinker underpass.
City of Denton On-system Projects Update: August 2018 7
TxDOT Monthly Project Report
Date of report: August 2, 2018
R eport prepared by: Branden Barnett
Project: STP 2017(083)MM
Control: 0196-01-106
Highway: IH 35E
Limits: From: State School Rd/Mayhill Rd (FM 2499)
To: SL 288
Contractor: OHL
TxDOT Project manager: Branden Barnett Phone: (214) 392-1791
Rick Clifton
Date Work Began: March 6, 2107
Anticipated Completion Date: July 2019
Current Activities:
Current activities include: Brinker Road Bridge construction, SL 288 bridge construction, IH-35E
northbound embankment and retaining walls; drainage along the northbound and Mayhill Road U-turn
(minor details).
: Brinker Road bridge construction, SL 288 bridge
construction, IH-35E northbound embankment, and Mayhill Road U-turn (minor details).
Narrative description of activities planned for next month: IH-35E northbound main lanes, Brinker
Road bridge construction, and SL 288 bridge construction.
Traffic issues: High volumes of traffic.
Plans for changes in traffic patterns: Northbound frontage road various daily lane closures and full
closures for retaining wall construction and culvert 4O construction; southbound frontage roads various
daily lane closures for culvert 4Q construction, and various daily lane closures at Mayhill U-Turn for
painting, sidewalk/ramp construction, and mow strip (weather permitting).
Item(s) of work currently controlling project completion: IH-35E northbound main lanes; Brinker
Road bridge and LP 288 bridge construction.
Other items of significance: None
City of Denton On-system Projects Update: August 2018 8
I-35 North
0195-01-116; 0195-02-074; 0195-03-087 December 2018
CSJ: Schematic Approval:
From US 380 to 0.7 miles north of FM
Environmental Clearance: March 2019
Limits:
3002 (Cooke County)
Estimated
$861 million December 2020
ROW Acquisition Completion:
Construction Cost:
Widen existing freeway from four lanes to
June 2020
Description: Utility Relocations Completion:
six lanes with continuous frontage roads
HDR *
Firm: 100% Plans:
Brian Swindell, Jeremy Doneghue /
Key Contact:
*
Ready to Let Date:
TxDOT: Nelson Underwood
Current Activity:
Schematic: The 90% schematic was submitted for FHWA, Design Division, and District review
on February 2, 2018. Received comments from Traffic Division. Received comments from
FHWA, Design Division, and District review. Consultant has addressed comments. Received
additional comments from Design Division and FHWA. Realigning main lane alignment 0.25
miles north of View Road to 0.25 miles north of CR 256. Awaiting approval of Traffic
Methodology and Projection Report from TPP. Schematic approval has been pushed back to the
fall 2018 timeframe due to potential historical property issue.
Portion of IH 35 at FM 455 will be broken out and built with the FM 455 project.
Environmental: Conducting preliminary data collection. Environmental efforts continue.
Received additional comments from ENV concerning potential historical property.
PS&E: To be developed in two segments after schematic and environmental approval.
Other: Project is currently only funded for planning. Additional funding will need to be identified
for right-of-way acquisition, utility relocation, final PS&E, and construction.
City of Denton On-system Projects Update: August 2018 9
I-35W Main Lanes
0081-13-050 *
CSJ: Schematic Approval:
From SH 170 (Alliance Boulevard) to
Environmental Clearance: *
Limits:
IH-35E
Estimated
$441 million *
ROW Acquisition Completion:
Construction Cost:
Widen 4-lane rural to 6-lane urban
*
Description: Utility Relocations Completion:
freeway with ramp relocation
HNTB *
Firm: 100% Plans:
Key Contact: Nicole Carillo *
Ready to Let Date:
Current Activities:
Environmental: Public meeting held Thursday,
April 19, 2018, at the Argyle Middle School.
HNTB continues work on the environmental
constraints report. Public meeting summary was
approved by TxDOT.
Schematic: Stakeholder meetings held to discuss
30% schematic, project history, and path forward.
First held with City of Fort Worth on January 11,
2018. Additional meetings held January 18, 2018,
with City of Argyle, Draper (formerly Corral City),
Haslet, Justin, Northlake, and Roanoke. Meetings
held with City of Denton, Town of Flower Mound,
and DCTA on February 15, 2018. HNTB met
again with Flower Mound on March 21, 2018.
HNTB submitted 30% schematic to TxDOT and
Denton County for review on November 3, 2017.
The 30% schematic has been returned to HNTB
with comments.
HNTB will be working with the frontage road
breakout project to evaluate the feasibility of
flipping some of the cross streets with I-35W.
Traffic data collection has been completed by sub-
consultant. Working on no-build and methodology
memo.
HNTB will utilize the Jacobs files from the
breakout frontage road project to develop the main
lane portion for submittal. HNTB awaiting receipt
of schematic files from Jacobs in order to proceed with main lanes project.
Utilities: SUE work is ongoing.
City of Denton On-system Projects Update: August 2018 10
US 380/Loop 288 Intersection Improvements
1035-10-057; RMC 6325-49-001 NA
CSJ: Environmental Clearance:
US 380 at Loop 288 NA
Limits: ROW Acquisition Completed:
* NA
Construction Cost: Utility Relocations Complete:
Improve northbound Loop 288 exit
NA
Description: 100% Plans:
ramps to US 380
TxDOT March 7, 2018
Firm: Let Date:
Danny Henderson August 2018
Contact: Construction Complete:
Current Activity:
This exit ramp is included in the full depth concrete repair project which let on March 7, 2018.
The contract has been awarded. The pre-construction meeting was held on May 15, 2018.
Contractor mobilized on June 4, 2018. Roadway pavement work is complete. Striping is
complete. Project is open to traffic. Contractor has installed signage and regraded ditch. Minor
punch-list items remain.
City of Denton On-system Projects Update: August 2018 11
US 380 East
0135-10-050; 0135-10-057 April 24, 2017
CSJ: Schematic Approval:
0135-10-050: from US 377 to Collin County line
June 29, 2018
Limits: Environmental Clearance:
0135-10-057: from Loop 288 to US 377
Widen existing roadway from 4/6-lane to 6-
June 2019
Description: ROW Acquisition Complete:
lane divided with intersection improvements
$130 million February 2021
Est. Construction Cost: Utility Relocations Complete:
AECOM (EA and schematic) TranSystems and
*
Firm: 100% Plans:
White Oak Engineers (PS&E)
TxDOT: Stephen Endres, Don Vo, Emmanuel
May 2021
Key Contact: Ready to Let Date:
Navarro / AECOM: Rajesh Janarthanan
CSJ: 0135-10-057
CSJ: 0135-10-050
Current Activity:
ENV: Finding of No Significant Impact (FONSI) received on June 29, 2018.
PS&E: TxDOT design team made the 30% PS&E for CSJ 0135-10-057 (from Loop 288 to US
377) on June 25, 2018. The 30% plan comments have been addressed. Currently working toward
60% plan set. Estimated timeline for 60% submittal is in December 2018. TxDOT consultant
continues work on PS&E for CSJ 0135-10-050 (from US 377 to county line). The 30% submittal
was made on July 27, 2018. Estimated timeline for 60% submittal is in January 2019.
ROW: AECOM finalized proposed ROW.
Utilities: Utilities notified of upcoming project at utility coordination meeting on April 19, 2018.
Received test hold information for utilities that may be in conflict.
Funding: For CSJ -050, TxDOT has identified $47.1 million in Proposition 1 funds and $14
million in STP-MM for a total of $61.1 million; for CSJ -057, TxDOT has identified $13 million in
Proposition 1 funds. US 380 has been listed as a project on the 10-year plan with an additional
$28.6 million. NCTCOG has agreed to cost share the addition of a 10-ft wide side path from
Mayhill to the Greenbelt Corridor. City council approved a LPAFA on September 12, 2017, for
the 10-foot sidewalk component from Mayhill to the Greenbelt in the amount of $848,874.75.
City participation: City is funding 20% local match of NCTCOG funding.
City of Denton On-system Projects Update: August 2018 12
Loop 288 West
2250-00-013 (from I-35 to US 380) /
February 2019
CSJ:Schematic Approval:
2250-00-014 (from US 380 to I-35W)
From I-35 to I-35W Environmental Clearance: September 2020
Limits:
Frontage road only: $40M
Estimated
-013 (including frontage roads): $108M; July 2021
ROW Acquisition Complete:
Construction Cost:
-014 (including frontage roads): $150M
Construct controlled access freeway July 2022
Description: Utility Relocations Complete:
CP&Y December 2021
Firm: 100% Plans:
March 2022 (-013); September
Tom Cochill, Andrea Klocinski
Key Contact: Ready to Let Date:
2022 (-014)
Current Status:
Environmental: CP&Y developed ICI analysis and report. Environmental study has begun.
Beginning coordination for scheduling of first public meeting; date TBD.
Schematic: Four direct connectors at I-35W/Loop 288: NB-WB, EB-SB, EB-NB, and SB-WB to
be included. CP&Y has extended the scope of the project to include the design of eight additional
direct connector ramps: four at I-35 interchange and four at I-35W interchange. CP&Y developed
a preliminary design that is included in the 30% schematic submittal. Bridge details for all 19
bridges were submitted to TxDOT on July 31, 2018. CP&Y reduced/shifted corridor to avoid
damage to existing structures as much as possible. Working with ITS and City of Denton to
confirm cross street locations and grade separations. Meeting date to be determined.
CP&Y has received aerial survey but is awaiting utility information at IH 35W to be provided by
TxDOT. Date for receipt to be determined.
Design approximately 60% complete. CP&Y received 30% schematic comments on June 20,
2018. TxDOT review meeting to discuss comments held on June 26, 2018. The 60% schematic
was submitted to TxDOT for review on August 20, 2018. City of Denton received 60% schematic
for review on August 24, 2018. The 60% review comments are expected to be complete by
September 21, 2018. Comment review meeting tentatively set for September 24, 2018.
Stakeholder meetings and first public meeting to follow.
Value engineering kicked off; beginning coordination to schedule VE study.
City of Denton passed resolution supporting the northbound frontage road.
City of Denton On-system Projects Update: August 2018 13
FM 1515
1951-01-011 September 2019
CSJ: Schematic Approval:
From Bonnie Brae to Masch Branch Road Environmental Clearance: December 2020
Limits:
Widen existing 2-lane rural section to a 6-
*
Description: ROW Acquisition Complete:
lane divided urban roadway
$17,671,121 *
Est. Const. Cost: Utility Relocations Complete:
LTRA *
Firm: 100% Plans:
Key Contact: Tyler Martin *
Ready to Let Date:
Current Activity:
Planning: LTRA is coordinating with TxDOT to provide survey and aerial mapping
information. LTRA has completed DSR. LTRA is developing conceptual alternatives and
alignments. LTRA reviewed planning information and Denton County parcel information.
LTRA prepared project location map and adjacent property owner list. Traffic counts
collected. LTRA continues evaluating crash data from TxDOT CRIS. LTRA continues
preparing collision diagrams for study intersections. LTRA continues work on development of
30% schematic.
Environmental: Right of entry letters sent for environmental surveys to be completed this fall.
Public Involvement: LTRA prepared draft public involvement plan, including project mailing
list. Public hearing is expected to be held in July 2020.
City of Denton On-system Projects Update: August 2018 14
FM 1830
1785-01-032; 1785-01-034 *
CSJ: Schematic Approval:
From FM 407 to US 377 Environmental Clearance: *
Limits:
5.5 miles *
Length: ROW Acquisition Completed:
$3,627,951 September 2017
Construction Cost: Utility Relocations Completed:
Widening roadway to provide three-foot
*
100% Plans:
shoulders and replacing bridge and
Description:
October 5, 2016
Let Date:
approaches at Fincher Creek
CAT 1 and CAT 11 August 2018
Funding: Construction Complete:
Current Activity:
Construction: Project was awarded to Jagoe Public. There are 400 working days and 19
months of barricades. Construction began on April 17, 2017. Time was suspended from April
24 to June 11 due to contractor scheduling. See attached TxDOT construction report.
City of Denton On-system Projects Update: August 2018 15
TxDOT Monthly Project Report
Date of report: August 7, 2018
R eport prepared by: Andrew Juarez
Project: STP 1602(424)
Control: 1785-01-032
Highway: FM 1830
Limits: From: FM 407
To: US 377 5.477 MI.
Contractor: Jagoe-Public Company
TxDOT Project manager: Mark Wiley Phone: (214) 336-0326
Phone: (940) 390-3441
Date Work Began: April 17, 2017
Anticipated Completion Date: August 2018
Current Activities:
Current activities include: Sodding and seeding on (034) bridge portion of job.
Narrative d Signs and mailboxes being installed on the (034)
bridge portion of job.
Narrative description of activities planned for next month: Watering vegetation.
Traffic issues: NA
Plans for changes in traffic patterns: NA
Item(s) of work currently controlling project completion: Sod and seeding. Watering vegetation.
Other items of significance: NA
City of Denton On-system Projects Update: August 2018 16
FM 1173
1059-01-047 October 2018
CSJ: Schematic Approval:
From IH-35E to FM 156 Environmental Clearance: *
Limits:
Feasibility study to widen to 4/6-lane
*
Description: ROW Acquisition Completed:
divided urban road
* *
Construction Cost: Utility Relocations Complete:
Garver *
Firm: 100% Plans:
Nelson Underwood *
Key Contact: Ready to Let Date:
Current Activity:
Planning: Garver continues compiling and addressing comments from public meeting.
TxDOT has performed preliminary review of concept schematic. Traffic methodology is under
review. Meeting with City of Krum held on August 24, 2018.
Environmental: Public meeting held on May 8, 2018, at Krum High School. Garver
continues compiling and addressing comments from public meeting.
Utilities: SUE work from TxDOT has been ordered and is now ongoing.
ROW: Garver has received the apparent ROW files. Garver continues refining alignments in
front of the Dollar General and Sonic to reduce ROW impacts.
City of Denton On-system Projects Update: August 2018 17
// �.,
� �.�
c�r�h ���tr�l ������ ��u��ol C�f �e���rr�rr7�e�t�
TO: Mark Nelson DATE: September 26, 2018
Directar af Transportation
City of Denton
FROM: Karla Weaver
Senior Program Manager
SUBJECT: Updat� on Bonnie Bra� Funding Request
I wanted to provide you a quic�C update on the status of Bonnie Brae roadway fur�ding request
that was received by the No�th Central Texas Cauncil of Gavernments (NCTCOG} from the City
of Denton and Denton Independent ScF�ool District (Dentan ISD).
As you know there was initial interest from Denton ISD in partnership opportunities ior
transportation needs related to Bonnie Brae from Elm to Windsor to assist Fn access to the new
High School being planned. There were then discussions about op�ortunities tfl potentEally
ext�nd the road fu�ther south, and advance larger gaals af the City and to go north to Loop 288
in coordination with the Texas D�partment af Transportation {TxD�T}.
A mesting was held in May 20i8 to discuss variaus o�tions and initial costs ar�d phasing. Our
staffs have been warking #ogether to gei clarity on the p�oject scape, segment priorities, and
schedules, Funding partnership discussions are still being held to understar�d commitments to
the project from the City, County, Denton ISD, and TxDOT, but I am hopeful those are close to
5eing complete.
We are working through the review of a seri�s of regional parknership projects a�d are
tentatively scheduled to take pr�liminary praject recammendatians to the Surface Transpor�ation
Technical Committee in October with final approva! from the Regionaf Transportatior� Council in
the DecemberlJanuary timeframe.
We appreciate yau and your staff s res�onsiveness to questions as w� go through the project
e�aluation. Feel free to contact me at 817-608-2376 or kweaver ._nctcop.orq.
r�l.� ►�A:i�
Karla Weaver
; � �.,r�r:.�M. ��� r;. �:r�
�,,, � i►,: ,��, ��, 1' ft-�,
� '#�'� ,� � i d ���� '�{'; .k�
„•