ORDINANCE NO. ODp�S_ DD
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF DENTON, TEXAS
AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NUMBER THREE
TO THE CONTRACT BETWEEN THE CITY OF DENTON AND ARCHER WESTERN
CONTRACTORS, LTD.; PROVIDING FOR AN INCREASE IN THE SCOPE OF WORK AND
AN INCREASE IN PAYMENT AMOUNT; PROVIDING FOR THE EXPENDITURE OF FUNDS
THEREFORE; AND PROVIDING AN EFFECTIVE DATE [ORDINANCE NO. 2001-192; BID
NO. 2612 - LAKE RAY ROBERTS 20 MGD WATER TREATMENT PLANT AWARDED TO
ARCHER WESTERN CONTRACTORS, LTD. IN THE AMOUNT OF $35,785,257; PLUS
CHANGE ORDER NUMBER THREE IN THE AMOUNT NOT TO EXCEED $71,328.36; WILL
BE PAID FROM FUNDS WITHIN THE EXISTING CONTRACT (ALLOWANCE BB)].
WHEREAS, on May 1, 2001 by Ordinance No. 2001-192, the City awarded a public works
contract to Archer Western Contractors, Ltd., in the amount of $35,785,257 for the construction of
the Lake Ray Roberts 20 MGD Water Treatment Plant and related improvements; and
WHEREAS, the Staff having recommended, and the City Manager having recommended to
the Council that a change order be authorized to amend such contract agreement with respect to the
scope of work, materials, labor and an increase in the payment amount, and said change order being
in compliance with the requirements of Chapter 252 of the Local Government Code; NOW
THEREFORE,
THE COUNCIL OF THE CITY OF DENTON HEREBY ORDAINS:
SECTION 1. That Change Order No. Three, increasing the amount of the public works
contract between the City and Archer Western Contractors, Ltd., which is on file in the office of the
Purchasing Agent, in the amount of Seventy One Thousand Three Hundred Twenty Eight and
36/100 ($71,328.36) Dollars, is hereby approved and the expenditure of funds therefore is hereby
authorized in accordance with said change order. The total purchase order amount remains at
$35,785,257 and the funds allocated in the existing contract under Allowance BB thereto will be
used for payment to Archer Western Contractors, Ltd. therefor.
SECTION 2. That this ordinance shall become effective immediately upon its passage and
approval.
PASSED AND APPROVED this 0 �1 day of 2002.
ATTEST:
JENNIFER WALTERS, CITY SECRETARY
EULINE BROCK, MAYOR
APPROVED AS TO LEGAL FORM:
HERBERT L. PROUTY, CITY ATTORNEY
By: N
SAOur Documents\Ordinances\02Vvcher Westem Change Order No. 3 Ord.doc
z
®®
FREESE - NICHOLS
CHANGE ORDER
(4.43 /CO-001)
PROJECT: Lake Ray Roberts Water Treatment Plant PROJECT NUMBER:
OWNER: City of Denton, Texas
CONTRACTOR: Archer Western Contractor, Ltd. 201052
ENGINEER: Freese & Nichols, Inc. DNT00343
CHANGE ORDER NO.: 003 DATE:114102
Make the following additions, modifications or deletions to the work described in the Contract
Documents:
• Provide and install two (2) dual rated primary transformers. (Service: 15kV % 25kV)
• Change Order No. 003 is not to exceed $71,328.36
*See attached PCM-002 \ Primary Transformers
The compensation agreed upon in this Change Order is full, complete and final payment for all costs
the Contractor may incuras a result of or relating to this change whether said costs are known,
unknown, foreseen or unforseen at this time, including without limitation, any cost for delay,
extended overhead, ripple or impact cost, or any other effect on changed or unchanged work as a
result of this Change Order.
Original Contract Amount $ 35,785,257.00
Original Bid ttem %Allowance BB ($700,000.00)
Previously Approved Change Order Amount $ 121,059.15
Previously Approved %Allowance BB Amount ($578,940.85) $ (121,059.15)
Adjusted Contract Amount $ WA
Proposed Change Order Amount $ 71,328.36
Adjusted Bid Item \Allowance BB $ (71,328.36)
Proposed Bid Item %Allowance BB ($507,612.49)
Revised Contract Amount $ 35,785,257.00
Previous Contract Time 704 Days
Previous Substantial Completion Date February 2003
Previous Final Completion Date April 2003
Net Change in Contract Time None
Revised Contract Time N/A
Revised Substantial Completion Date N/A
Revised Final Completion Date N/A
Recommended by Approved by
FREESE.IAND NICHOLS, INC. Archer Western Contractor, Ltd.
By 2t&A By � C /-%—o Z
[Date] [Date]
Approved by
City Dento , exas
By [ a
Date
,
SUBMITTAL TRANSMITTAL
PROJECT: Lake Ray Roberts Water Treatment Plant PROJECT NO.
OWNER: City of Denton, Texas
CONTRACTOR: Archer Western Contractors, Ltd. 201052
ENGINEER: Freese and Nichols DTNO0343
REFERENCE DATA:
Contractor's Submittal No. PCM-002 Specification Section: 01380
Plan Sheet No: N/A Description: PRIMARY TRANST ticks
CONTRACTOR'S CERTIFICATION: I hereby certify that this submittal has been reviewed by the
Contractor and is in strict conformance with the Contract Documents as modified by Addenda, Chango
Orders and Field O rs
Certified by: Date : 12/18/01
DATE
RECEIV 0 BY: DATE RETURNED:
;&P-Pa BY: Ag,-
TYPE
#
DESCRIPTION
#SENT
#RTN'D
Y03 "
CMR
Contractor's modification request
O Approved 1
0 Approved as Noted
O Not Approved
O Revise & Resubmit
O Filed as Received
Final Distribution
Change Order Issued
CTR
Certified Test Report
EIR
Equipment Installation Report
O&M
Operation & Maintenance Manual
NBC
Notification By Contractor
PCM
002
Proposed Contract Modification
t
PR
Payment Request
PP
Project Photographs
O Field Order Issued
O Recommended for Approval
0 Returned W/O Review
O Add'I Information Required
O Canceled
0 See Review Comments
RD
Record Date
RFI
Request For Information
SAM
Sample
SCH
Schedule Of Progress
SO
Shop Drawings
COMMENTS:
_
FOR ENGINEER'S USE ONLY
DISTRIBUTION
REVIEW
NO
SENT TO
NO
SENT TO
DEPT
BY
SENT
RET'D
1
City of Denton - Fisher
-
-
1
City of Denton - Field
1
Freese & Nichols, Inc.
1
FNI Field Office
Montgomery Watson
FREESE-NICHOLS
DEC 17 2001
PROPOSED CONTRACT MODIFICATION
ATTACHMENTA
(4.411 )
By
PROJECT: Lake Ray Roberts Water Treatment Plant PROJECT NUMBER:
OWNER: City of Denton, Texas
CONTRACTOR: Archer Western Contractors, Ltd. 201052
ENGINEER: Freese & Nichols, Inc. DNT00343
DESCRIPTION Primary Transformers NO. PCM-002
NOTIFICATION TO CONTRACTOR:
The Owner proposes to make the additions, modifications or deletions to the Work described in the
Contract Documents as shown in Attachment "A". We request that you take the following action within
10 calendar days:
❑ Notify us that you concur that this change does not require a change in Contract time or
amount. A Feld Order will be issued.
X Submit a Price/Credit Proposal with detailed cost breakdown of labor, materials,
equipment and all other costs related to this change. Impacts on Contract Time shall be
shown in a revised schedule, included with the submitted proposal.
❑ Proceed with the change. Payment will be made at the unit price bid.
10 Proceed with the change under the time and materials provisions of the Contract. II
Authorization to proceed with changes must be approved by the Owner through Change Order in !I
accordance with the Contract Documents.
By: . Steve Wilson Date: 12/17/01
CONTRACTOR'S RESPONSE:
We respond to your request as follows:
❑ We propose that this is a no cost or time change. Issue Field Order.
�$ We submit the attached Price/Credit Proposal with detailed cost breakdown
s�for performing the described change. f ii-i8--o/
❑ We are proceeding with the change at the unit price bid.
❑ We are proceeding with the change under the time and materials provisions of the
Contract.
By: Date: / Z —4 — o %
ACTION TAKEN:
❑ Proposed Contract Modification rejected. See comments.
❑ Field Order will be issued.
Ch e Order will be issued. C . O.` o0 3
By: Date:
®®
FREESE - NICHOLS
PROPOSED CONTRACT MODIFICATION
ATTACHMENTA
(4.411 )
The Owner proposes to make the following additions, modifications or deletions to the work described
in the Contract Documents. Authorization to proceed with these changes must be approved by Field
Order or Change Order in accordance with the Contract Documents, prior to commencing the work
involved.
Comments:
1) Provide primary cable insulation class for 25kV.
2) Provide dual rated transformers that would be required to allow the 24.94 kV on the primary.
By: Steve Wilson Date: 12/17/01
LAKE RAY ROBERTS WTP
AUBREY, TEXAS
PENDING CHANGE REQUEST COST ANALYSIS
To be completed by General Contractor or Subcontractor
as outlined in the Uniform General Conditions Section 6.6.1
Work performed by:
( ) General Contractor ( X ) Subcontractor
ircvw=tzctor, give co. =w. ACbM ELECTRIC COMPANY
Time Ext=Aw (if my)!
PROJECT: LAKE RAY ROBERTS WTP
CONTRACTOR ARCIM WESTERN
PCM#: 2
CPR#:
RM:
ASIM
1
Description of Change: 25KV UPGRADE
ADDITIONS AND/OR [CREDITS]
Line 1: Enter total of Columns A+E+C+D
Line II: If Line I indicates an ADD, Enter 15% of Line I.
If Line I indicates CREDIT, enter -0-
Line 111; Enter total Col E (Storage)
Line IV: Ender 40.4% of Col B for Worktnan's
Comp. Social Security, and like taxes
Line V: Total Line I thru Line IV
Enter here and on Summary Sheet
EXTENSION
A
B
C
D
E
Material
Labor
Equip .
Trans.
Storage
$12,000.00
$480,00
$120.00
54.80
521600.00
$480.00
$216.00
54.80
$3.120.00
$120.00
$31.20
$1.20
$3 600.00
$0.00
$36.00
$0.00
$9 504.00
$0.00
$95.04
$0.00
$1270.51
1 $260.40
1 $12.71
52.60
589.52
$130.80
$0.90
$1.31
$427.20
$297.60
$4.27
$2.99
$900.00
$150.00
$9.00
$1.50
$0.00
$960-00
$0.00
$9.60
$52,511.23
$2,878.90
1$0.00
$525.11
1 $28.79
SIGNATURE;_--. _ . Qpp oUtacy . DATE:
_ . CONI'RACMU SUBCONTRACTOR -
SIGNATURE: DATE:
$55,945-93
$8,391.59
$29
$1,163.04
$65,527.35
TOTAL P.62
I
FIELD CHANGE JUSTIFICATION
1
I
PROJECT ILAKERAYROBERTS
CITY
AUBREY
DATE:
12I18I01
COUNTY
DENTON
ITEM OF WORK
DUAL VOLTAGE PRIMARY TRANSFORMER
j
ESTIMATED QUANTITY
1
LUMP SUM
i
DESCRIPTION
QUANTITY
PRICE
LABOR
MATERIAL
EQUIPMENT 1
SUB
LABOR
72
$ 16.00
$ 1,152.00
55%INSURANCE AND
TAXES
$ 633.60
15%COMPENSATION
$ 95.04
TOTAL LABOR COST
$ 1,880.64
MATERIAL
I
CONCRETE
8
$ 70.00
$ 660.00
!
0
$
$
D$
is
0
$
$
0
$
$
0
$
$
i
I
I
i
SUBTOTAL
1
1 $ 560.00
1
15%COMPENSATI2N
1 $ 84.00
TOTAL MATERIAL COST
$ 844.00
I
I
I
EQUIPMENT
j
Oi
$
$
O$
$
Oi
$
$
o$
$
01$
$
I
I
SUBTOTAL
$
15%COMPENSATION
$ - I
TOTAL EQUIPMENT COST
1
$
I
SUBCONTRACTOR
i
I I
PERATTACHED
1
$ 65,527.35
f
$ 65,527.351
SUBTOTAL
$ 65,527.35
5%COMPENSATION
1 $ 3,276.37
TOTAL SUBCONTRACTOR COST
$ 68,803.72
TOTAL COST OF FIELD CHANGE ITEM
$ 71.328.36
UNIT PRICE OF FIELD CHANGE ITEM
$ 71,328.36
PLEASE NOTE THAT OWNER IS RESPONSIBLE FOR ANY IMPACT THIS
CHANGE MAY HAVE ON COMPLETION
DATE OF PROJECT