1514391385 01 Y Street Department
P
DENTON 901-A Texas Street, Denton, TX 76209 • (940) 349-7160
Public Works Information Sheet
1. Location: Ave H (Hickory St. to Stella St.)
2. Proposed Date of Construction: January 2, 2018
3. Proposed Date of Completion: May 7, 2018
4. Brief Description of the Project:
Ave H is a reconstruction project from N Hickory St to Stella St.
This project will include:
• Utility line location to verify depth of utility lines
• Damaged concrete replacement(curb, valley gutters, driveways,
etc.)
• Removal of seven inches of asphalt (milling process)
• Stabilization of subgrade
• Seven inch asphalt installation
The project is being done in conjunction with the Hickory project. Due to deteriorating
condition of the asphalt and subgrade, the street has also had new utility lines installation.
Residents are advised to refrain from parking in the street while workers are present
unless otherwise advised. Also any sod that is laid is the homeowner's responsibility to
irrigate.
5. Special Requirements: "No Parking" on street.
Detours will be provided.
Sod is the homeowner's responsibility to irrigate.
6. Funding Source: O&M
7. Council District: District 3
8. Public Outreach: Public Outreach: Door hangers and Street Construction Report.
9. Map: Attached
10. Contact Information: Streets Manager. Robbin Webber 940-349-7146