Loading...
1515095655 01 Y Street Department P DENTON 901-A Texas Street, Denton, TX 76209 • (940) 349-7160 Public Works Information Sheet 1. Location: Silktree Court(Desert Willow Dr. to Cul de Sac) 2. Proposed Date of Construction: January 29, 2018 3. Proposed Date of Completion: March 5, 2018 4. Brief Description of the Project: Concrete street panel repair. The process starts with barricading the failed sections of concrete pavement, removing the pavement and subgrade, and installing new concrete pavement. The new concrete has to cure for a period of 7 to 14 days before it can be opened up to traffic. This is done to allow the concrete to reach sufficient strength to support traffic. 5. Special Requirements: "No Parking" on street. Detours will be provided. 6. Funding Source: O&M 7. Council District: District 2 8. Public Outreach: Public Outreach: Door hangers, Street Construction Report, and Public works Information Sheet. 9. Map: Attached 10. Contact Information: Streets Manager. Robbin Webber 940-349-7146 OUR CORE VALUES Integrity•Fiscal Responsibility•Transparency• Outstanding Customer Service ADA/EOE/ADEA www.cityofdenton.com TDD(800)735-2989