1. Location: Silktree Court(Desert Willow Dr. to Cul de Sac)
2. Proposed Date of Construction: January 29, 2018
3. Proposed Date of Completion: March 5, 2018
4. Brief Description of the Project: Concrete street panel repair. The process starts with
barricading the failed sections of concrete pavement, removing the pavement and
subgrade, and installing new concrete pavement. The new concrete has to cure for a
period of 7 to 14 days before it can be opened up to traffic. This is done to allow the
concrete to reach sufficient strength to support traffic.
5. Special Requirements: "No Parking" on street.
Detours will be provided.
6. Funding Source: O&M
7. Council District: District 2
8. Public Outreach: Public Outreach: Door hangers, Street Construction Report, and
Public works Information Sheet.
9. Map: Attached
10. Contact Information: Streets Manager. Robbin Webber 940-349-7146
OUR CORE VALUES