1. Location: Amarillo Street from Congress Street to Egan Street
2. Proposed Date of Construction: July 9 , 2018
3. Proposed Date of Completion: August 17, 2018
Brief Description of the Project:
• Utility line location to verify depth of utility lines
• Failed concrete replacement(curb, valley gutters, driveways,
etc.)
• Removal of seven inches of asphalt and subgrade material (milling process)
• Stabilization of subgrade
• Install seven inches of asphalt
The project is part of our 2014 Bond Program and is being contracted out to Jagoe-Public
Co. due to deteriorating condition of the asphalt and subgrade.
4. Special Requirements: During this time, there will be no parking on the street and there
will be limited access to driveways while crews are present. A door hanger will be placed
on your front door to notify you prior to your driveway being blocked. If your driveway
is blocked and you need temporary access in or out, you can speak with an on-site crew
member directly, or call Utilities Dispatch at (940) 349-7000 to have someone notify the
crews. Detours will be provided when necessary. As part of the project, replacement sod
may be placed in your yard and is the homeowner's responsibility to irrigate. Upon
completion of the project all homeowner's have thirty days to report all and any issues.
Any curb markings that are within the right of way will be replaced at homeowner's
expense.
5. Funding Source: 2014 Bond Program/Estimated - $71,949
6. Council District: District 2
7. Public Outreach: Public Outreach: Door hangers and Street Construction Report.
8. Map: Attached
9. Contact Information: Streets Manager. Robbin Webber 940-349-7146
OUR CORE VALUES
Integrity•Fiscal Responsibility•Transparency• Outstanding Customer Service
ADA/EOE/ADEA www.cityofdenton.com TDD(800)735-2989