1537541000 o i Street Department
DENTON 901-A Texas Street, Denton, TX 76209 • (940) 349-7160
Public Works Information Sheet
1. Location: Hickory Street (Avenue C—Avenue B)
2. Proposed Date of Construction: September 24, 2018
3. Proposed Date of Completion: January 2, 2019
4. Brief Description of the Project:
Hickory Street is a reconstruction project from North Texas Blvd to Ave C.
This project will include:
• Utility line location to verify depth of utility lines
• Damaged concrete replacement (curb, valley gutters, driveways, etc.)
• Removal of ten inches of asphalt(milling process)
• Stabilization of subgrade ten-inch asphalt installation
• Install ten-inch asphalt
The Hickory Street Project is part of our Bond Program and is being done by in-house
crews. Due to the deteriorating condition of the asphalt and subgrade and new utility
lines, the street is in need of reconstruction. Residents are advised to refrain from parking
in the street while workers are present unless otherwise advised. The City of Denton will
not be responsible for re-painting addresses or logos on curbs within the right of way.
Please report all irrigation issues within 60 days of the project's completion.
5. Special Requirements: "No Parking" on street. Detours will be provided.
Sod is the homeowner's responsibility to irrigate.
6. Funding Source:
2014 Bond Program/Estimated Cost for Project - $228,643.00
7. Council District: District 3
8. Public Outreach: Public Outreach: Door hangers and Street Construction Report.
9. Map: Attached
10. Contact Information: Streets Manager. Robbin Webber 940-349-7146