Public Works Information Sheet
1. Location: Fairway Drive (Ft. Worth Dr. to Club View Dr.)
2. Proposed Date of Construction: November 12, 2018
3. Proposed Date of Completion: November 21, 2018
4. Brief Description of the Project: Concrete street panel repair. The process starts with
barricading the failed sections of concrete pavement, remove the pavement and subgrade,
and install new concrete pavement. The new concrete has to cure for period of 7 days
before it can be opened up to traffic. This is done to allow the concrete to reach
sufficient strength to support traffic.
5. Special Requirements: During this time, there will be no parking on the street.
Detours will be provided when necessary. As part of the project, replacement sod maybe
placed in your yard and is the homeowner's responsibility to irrigate.
6. Funding Source: O & M
7. Council District: 3
8. Public Outreach: Public Outreach: Door hangers and Street Construction Report.
9. Map: Attached
10. Contact Information: Streets Manager. Robbin Webber 940-349-7146