1. Location: Oak St from Crawford to Wood
2. Proposed Date of Construction: August 14, 20107
3. Proposed Date of Completion: September 29, 2017
4. Brief Description of the Project:
Jagoe Public is the contractor for the Oak St project for the City of Denton. The project is
a full street reconstruction that consists of a 7 inch depth milling of the asphalt, removal
and replacement of any nonfunctioning curb, driveways, and sidewalk, subgrade work,
and 7 inch asphalt paving. Any sod that is planted is the land owner's responsibility to
water. This project is part of our 2012 bond program and due to the degrading condition
of the asphalt and subgrade it is in need of repair.
5. Special Requirements:
Parking on the street will be unavailable during working hours, any driveway
replacement will be notified the day before it will be replaced, and watering of any sod is
the land owner's responsibility.
6. Funding Source: 2012 Bond program
7. Council District: 1
8. Public Outreach: Door Hangers will be placed prior to work.
9. Contact Information: Please provide the name, phone number, and e-mail of the project
manager.