VCM Bonnie Brae Phase 3Bonnie Brae Phase 3
Thank you for joining us! The meeting will begin momentarily.
•Welcome
•City of Denton Staff Introductions
•Feedback and Q&A Opportunities
•Meeting Presentation
•Next Steps
•Stay Informed
Meeting Agenda
•All attendees are muted
•All attendees videos are disabled
•Questions
•Q&A
•Questions will be answered in the order they are received, and will only display in the Q&A after they are answered
•Select raise hand to request to speak
•Presentation will be available after meeting at
www.cityofdenton.com/virtualcommunitymeetings
Virtual Community Meeting Reminders
Project Scope
Scope-Widen Bonnie Brae
from Roselawn to IH35E
from 2 lanes to 4 lanes
including Street lighting,
Sidewalks, Traffic signals,
Drainage System, 5000’
Water line, 7000’ Sanitary
Sewer.
Current Project Timeline*
•Bid Project –February 2021
•Award Contract –May 2021
•Begin Construction –July 2021
•Construction Complete –July 2023
•Current Pending Items:
•Kansas City Southern Railroad Agreement
•En-Link Gas Relocation
•Franchise Utility relocations
*This timeline reflects the estimated dates for the remaining phases of the project. Timeline estimates are tentative
and subject to change. For the most up-to-date information, visit www.cityofdenton.com/bonniebraestreet.
•Construction solicitation development/bid process
•City Council consideration/award of contract
•Final pre-construction meeting after bid is awarded
Next Steps
•Bonnie Brae Phase 3 Project Manager, Seth Garcia
•Seth.Garcia@cityofdenton.com | (940) 349-8938
•Online:
•To check the status of the Bonnie Brae Phase 3 project at any time, visit
www.cityofdenton.com/bonniebraestreet
•Email:
•Sign up for Bonnie Brae Phase 3 email alerts at
www.cityofdenton.com/bonniebraestreet
Stay Informed