2021/09/03 - Street Closure Report 1 Street Closure Report: Upcoming Closures smartsheet
SCR Sep 6th - 12th
Closure Start
Street/Intersection From To Date Description Department Contact
Bell Ave Texas St Withers St 09/30/21 11/03/21 Water Distribution will be Water Tiffany Sherrane
1 installing a new water main line
and services.
Bell Ave Withers St Mingo Rd 10/26/21 12/08/21 Water Distribution will be Water Tiffany Sherrane
2 installing a new water main line
and services.
Bell Ave at Mingo Rd 09/15/21 10/25/21 Water Distribution will be Water Tiffany Sherrane
3 installing a new water main line
and services.
Bernard St Hickory St Chestnut St 12/09/21 01/24/22 Water Distribution will be Water Tiffany Sherrane
replacing the water main line
and services.
Exported on September 3,2021 10:39:37 AM CDT Page 1 of 1
2 Street Closure Report: Current Closures smartsheet
Intersection • "07/03/21
Closure_ • fi- • fi-•. Department Contact
Bell Ave at Mckinney St 09/14/21 Water Distribution will be Water Tiffany Sherrane
1 installing a new water main line
and servicesBell Ave College St Texas St 08/0 / 09/29/21 Water Distribution will be Water Tiffany Sherrane
2 installing a new water main line
and services.
Bonnie Brae(SB) Oak Hickory 06/14/21 09/22/21 This block is closed to Other Mark Zimmerer
southbound traffic only,detours
are posted.Northbound lane
3 still open.Installation of electric
duct banks for DME substation
project and steel casing for
water main project
Carroll Blvd(SB)&(NB) Mulberry Eagle 07/12/21 10/01/21 Concrete Street Panel and Streets robbin.webber@cityofdenton.co
Sidewalk Repair.The process m
4 starts with Barricading the failed
sections of concrete pavement,
remove the pavement,and
install new concrete.
Chebi Lane Old North Road Freedom Lane 06/21/21 09/10/21 Full width pavement Engineering Streets Kyle Pedigo
5 replacement and subgrade
improvement.
College Park Dr Peach St End of College Park Dr 06/28/21 09/24/21 Wastewater collections will be Wastewater Tiffany Sherrane
6 installing a new wastewater
main line and services.
7 Eagle Locust Elm 06/28/21 09/10/21 Patching of utility trench lines. Engineering Seth Garcia
8 Elm Hickory Eagle 05/11/20 09/17/21 PEC 4 Utility Project Engineering Seth Garcia
Elm Street Eagle Drive (dead end) 05/17/21 09/30/21 Atmos Energy will be closing Atmos Alice Province
9 street intermittently to replace
and relocate an existing gas
main and service lines
F.M.428 Poinsettia Drive Loop 288 08/09/21 09/06/21 Concrete approach and turn TXDOT Robert Plato
10 lane improvements on TXDOT
Roadway
Fowler Dr College Park Dr Peach St 06/28/21 09/24/21 Wastewater collections will be Wastewater Tiffany Sherrane
11 installing a new wastewater
main line and services.
Hickory Street Welch Carroll 08/31/20 10/15/21 Construction is set to begin on Engineering Kyle Pedigo
West Hickory Street between N.
Welch Street and Carroll Blvd in
October of 2020 and continue
12 through September of 2021.
Detailed lane closure
information is forthcoming
pending approval of the
contractor's phasing and traffic
control plans.
Loop 288 SB On-Ramp at FM 428 Loop 288 Mainlanes 08/06/21 09/016/21 Placing concrete approaches TXDoT Robert Plato
13 FM428 for development at corner of
Loop 288 and FM428
Mckinney duchess Glengarry 02/01/21 12/24/21 McKinney-Mayhill Intersection Engineering Trevor Crain
This project is widening the
intersection and 600'each way
14 to match existing conditions
along McKinney.Also includes
water,wastewater,and
drainage improvements.
Exported on September 3,2021 10:39:49 AM CDT Page 1 of 2
Street/Intersection From To Closure Start Closure End Description Department Department Contact
Date Date
McKinney St @ Elm St intersection 08/02/21 10/29/21 Temporary lane closures in Traffic James Andrews
15 place as crews work to safely
install new traffic signals at the
intersections
McKinney St @ Locust St intersection 08/02/21 10/29/21 Temporary lane closures in Traffic James Andrews
16 place as crews work to safely
install new traffic signals at the
intersections
Mistywood Lane Old North Road Craig Lane 06/21/21 09/10/21 Full width pavement Engineering Streets Kyle Pedigo
17 replacement and subgrade
improvement.
Peach St N Locust Dr Fowler Dr 06/28/21 09/24/21 Wastewater collections will be Wastewater Tiffany Sherrane
18 installing a new wastewater
main line and services.
19 Provence Vintage Sonoma 09/03/21 09/17/21 Paving and Drainage work Drainage Engineering Seth Garcia
20 Quail Ridge Cooper Branch E La Paloma Dr 09/07/21 10/29/21 Street Reconstruction Engineering Dustin Draper
Scripture Bonnie Brae 1,300 ft.to the West 03/22/21 09/16/21 Reconstruct;Scripture from Streets robbin.webber@cityofdenton.co
Bonnie Brae to approximately m
1,300 ft.to the west.This
includes removal and
replacement of failed sections
of curb and gutter.Milling of the
old asphalt pavement and the
21 stabilization of subgrade and
the installation of new asphalt
pavement.
Phase I East Bound Outside
Lane
Phase II West Bound Outside
Lane
Phase III Middle Lane
Walnut Street Locust Street Elm Street 05/17/21 09/30/21 Atmos Energy will be Atmos Alice Province
22 excavating street to complete
replacement/relocation of their
existing gas main
23 Western Blvd Jim Chrystal Airport Rd 08/16/21 12/31/21 Paving:Decal Lanes Private Development Public Jeremiah Tillman-David
Works Inspections
24 Windsor Bonnie Brae Parkside 08/09/21 12/31/21 Pavement Restoration Private Development Public Jeremiah Tillman-David
Works Inspections
Windsor Dr East Broken Bow Armstrong 07/28/21 09/30/21 Street Reconstruction will be Engineering Dustin Draper
25 performed on the westbound
lane of E Windsor
Exported on September 3,2021 10:39:49 AM CDT Page 2 of 2
3 Street Closure Report: Completed Closures smartsheet
Street/Intersection From --l" Closure End Description Department p- Department Contact
wo Date
Avenue C 1-35 North Frontage Eagle Drive 07/26/21 Lane shift to allow for repair of Private Development Robert Plato
damaged streets due to
1 contractor activity on the
Carriage Square Apartment
0110111
project.
Bell Hickory McKinney 07/28/21 08/25/21 Storm drain installation across Engineering Streets Kyle Pedigo
2 Bell on Oak.Bell will be closed
half at a time as the storm drain
is installed
Collier Ave. 1-35 NB Frontage Road Eagle Drive 08/23/21 08/27/21 Repairing asphalt road Private Development Robert Plato
3 damaged during construction of
Carriage Square Apartments
Colorado Boulevard Valley Creek Road San Jacinto Boulevard 07/26/21 08/26/21 Building a right-turn lane into Public Works Inspections Robert Plato
the new Vista Verde project on
4 the west side of Colorado. The
right lane will be closed while
operations are being performed
to add the turn lane.
Lido Way and Balboa Court Bell Avenue End 07/05/21 09/01/21 Full width pavement Engineering Streets Kyle Pedigo
5 replacement and subgrade
improvement.
6 Locust Eagle Hickory 06/28/21 09/03/21 Patching of utility trench lines. Engineering Seth Garcia
Oak Street Bell Street UPRR Railroad 02/01/21 08/28/21 Adding drainage line to Oak Engineering kyle.pedigo@cityofdenton.com
7 Street as part of the Downtown
Storm Sewer Project.
8 Windsor Dr East Nottingham Branch Crossing 06/14/21 08/27/21 Roadway reconstruction Engineering Dustin.Draper@cityofdenton.co
Woodhaven Mistywood Emerson 04/05/21 08/12/21 This project will consist of the Streets robbin.webber@cityofdenton.co
removal and replacement of m
failed sections of curb and
9 gutter,the milling off the old
asphalt and base material,lime
stabilize the subgrade and the
installation of new asphalt
pavement.
Exported on September 3,2021 10:39:59 AM CDT Page 1 of 1