2021/10/04 - Street Closure Report 1 Street Closure Report: Upcoming Closures smartsheet
SCR Oct 4th - 10th
Street/Intersection I Description Department Contact
Bell Ave Texas St Withers St 11/30/21 01/06/22 Water Distribution will be Water Tiffany Sherrane
1 installing a new water main line
and services.
Bell Ave Withers St Mingo Rd 01/07/22 02/18/22 Water Distribution will be Water Tiffany Sherrane
2 installing a new water main line
and services.
Bell Ave at Mingo Rd 10/18/21 11/29/21 Water Distribution will be Water Tiffany Sherrane
3 installing a new water main line
and services.
Bernard St Hickory St Chestnut St 05/18/22 06/29/22 Water Distribution will be Water Tiffany Sherrane
replacing the water main line
and services.
Keystone Ct West of Stuart East of 1109 Keyston�Courtl /18/21 10/29/21 Concrete panel repair Private Development Public Tucker Eller
Works Inspections
Exported on October 1,2021 11:50:52 AM CDT Page 1 of 1
2 Street Closure Report: Current Closures smartsheet
Street/Intersection From To Closure Start Closure End Description Department Department Contact
Date Date
1 Allred Rd JM Prosperity Farm Rustic Barn Bonnie Brae 09/27/21 07/31/22 Storm Installation,Cutting Private Development Public Jeremiah Tillman-David
Venue Grade on Allred Works Inspections
Bell Ave College St Texas St 08/04/21 10/14/21 Water Distribution will be Water Tiffany Sherrane
2 installing a new water main line
and services.
Bell PI at Mckinney St 07/08/21 10/08/21 Water Distribution will be Water Tiffany Sherrane
3 installing a new water main line
and services.
Bonnie Brae(SB) Oak Hickory 06/14/21 10/27/21 This block is closed to Other Mark Zimmerer
southbound traffic only,detours
are posted.Northbound lane
4 still open.Installation of electric
duct banks for DME substation
project and steel casing for
water main project
Carroll Blvd(SB)&(NB) Mulberry Eagle 07/12/21 10/29/21 Concrete Street Panel and Streets robbin.webber@cityofdenton.co
Sidewalk Repair.The process m
5 starts with Barricading the failed
sections of concrete pavement,
remove the pavement,and
install new concrete.
6 Elm Hickory Eagle 05/11/20 10/29/21 PEC 4 Utility Project Engineering Seth Garcia
Elm Street Eagle Drive (dead end) 05/17/21 10/29/21 Atmos Energy will be closing Atmos Alice Province
7 street intermittently to replace
and relocate an existing gas
main and service lines
Hickory Street Welch Carroll 08/31/20 10/15/21 Construction is set to begin on Engineering Kyle Pedigo
West Hickory Street between N.
Welch Street and Carroll Blvd in
October of 2020 and continue
8 through September of 2021.
Detailed lane closure
information is forthcoming
pending approval of the
contractor's phasing and traffic
control plans.
Mckinney duchess Glengarry 02/01/21 12/24/21 McKinney-Mayhill Intersection Engineering Trevor Crain
This project is widening the
intersection and 600'each way
9 to match existing conditions
along McKinney.Also includes
water,wastewater,and
drainage improvements.
McKinney St @ Elm St intersection 08/02/21 10/29/21 Temporary lane closures in Traffic James Andrews
10 place as crews work to safely
install new traffic signals at the
intersections
McKinney St @ Locust St intersection 08/02/21 10/29/21 Temporary lane closures in Traffic James Andrews
11 place as crews work to safely
install new traffic signals at the
intersections
12 Quail Ridge Cooper Branch E La Paloma Dr 09/07/21 10/29/21 Street Reconstruction Engineering Dustin Draper
Ruddell HWY 380 Mingo Rd 10/05/21 10/08/21 Water Distribution will be Water James Gideon
13 repairing a water main valve
and will re-open the road at the
end of the day.
Ryan Rd Creekside Dr Paradise Ln 09/27/21 10/29/21 Wastewater Collections will be Wastewater Tiffany Sherrane
14 installing a new wastewater
Lmain line
Exported on October 1,2021 11:51:00 AM CDT Page 1 of 2
Street/Intersection From To Closure Start Closure End Description Department Department Contact
Date Date
15 Welch Eagle Collins 08/23/21 10/30/21 Utility installations and Engineering Streets Water Kyle Pedigo
pavement replacement. Wastewater
Welch Street Chestnut Street Mulberry Street 09/27/21 11/23/21 University of North Texas Private Development Public Alice Province
16 excavating street to connect Works Inspections
services to Art Studio Building
17 Western Blvd Jim Chrystal Airport Rd 08/16/21 12/31/21 Paving:Decal Lanes Private Development Public Jeremiah Tillman-David
Works Inspections
18 Windsor Bonnie Brae Parkside 08/09/21 12/31/21 Pavement Restoration Private Development Public Jeremiah Tillman-David
Works Inspections
Exported on October 1,2021 11:51:00 AM CDT Page 2 of 2
3 Street Closure Report: Completed Closures smartsheet
• • ■Closure. Date
Closure • Description Department F
Chebi Lane Old North Road Freedom Lane 06/21/21 09/10/21 Full width pavement Engineering Streets Kyle Pedigo
1 replacement and subgrade
improvement.
College Park Dr Peach St End of College Park Dr 06/28/21 09/24/21 Wastewater collections will be Wastewater Tiffany Sherrane
2 installing a new wastewater
main line and services.
3 Eagle Locust Elm 06/28/21 09/10/21 Patching of utility trench lines. Engineering Seth Garcia
F.M.428 Poinsettia Drive Loop 288 08/09/21 09/06/21 Concrete approach and turn TXDoT Robert Plato
4 lane improvements on TXDOT
Roadway
Fowler Dr College Park Dr Peach St 06/28/21 09/24/21 Wastewater collections will be Wastewater Tiffany Sherrane
5 installing a new wastewater
main line and services.
Lido Way and Balboa Court Bell Avenue End 07/05/21 09/01/21 Full width pavement Engineering Streets Kyle Pedigo
6 replacement and subgrade
improvement.
7 Locust Eagle Hickory 06/28/21 09/03/21 Patching of utility trench lines. Engineering Seth Garcia
Loop 288 SB On-Ramp at FM 428 Loop 288 Mainlanes 08/06/21 09/06/21 Placing concrete approaches TXDOT Robert Plato
8 FM428 for development at corner of
Loop 288 and FM428
Mistywood Lane Old North Road Craig Lane 06/21/21 09/10/21 Full width pavement Engineering Streets Kyle Pedigo
9 replacement and subgrade
improvement.
Peach St N Locust Dr Fowler Dr 06/28/21 09/24/21 Wastewater collections will be Wastewater Tiffany Sherrane
10 installing a new wastewater
main line and services.
11 Provence Vintage Sonoma 09/03/21 09/21/21 Paving and Drainage work Drainage Engineering Seth Garcia
Scripture Bonnie Brae 1,300 ft.to the West 03/22/21 09/20/21 Reconstruct;Scripture from Streets robbin.webber@cityofdenton.co
Bonnie Brae to approximately m
1,300 ft.to the west.This
includes removal and
replacement of failed sections
of curb and gutter.Milling of the
old asphalt pavement and the
12 stabilization of subgrade and
the installation of new asphalt
pavement.
Phase I East Bound Outside
Lane
Phase II West Bound Outside
Lane
Phase III Middle Lane
Walnut Street Locust Street Elm Street 05/17/21 09/30/21 Atmos Energy will be Atmos Alice Province
13 excavating street to complete
replacement/relocation of their
existing gas main
Windsor Dr East Broken Bow Armstrong 07/28/21 09/30/21 Street Reconstruction will be Engineering Dustin Draper
14 performed on the westbound
lane of E Windsor
Exported on October 1,2021 11:51:10 AM CDT Page 1 of 1