2021/10/11 - Street Closure Report 1 Street Closure Report: Upcoming Closures smartsheet
SCR Oct 11 th - 17th
Street/Intersection Description Department Contact
Bell Ave Texas St Withers St 11/30/21 01/06/22 Water Distribution will be Water Tiffany Sherrane
1 installing a new water main line
and services.
Bell Ave Withers St Mingo Rd 01/07/22 02/18/22 Water Distribution will be Water Tiffany Sherrane
2 installing a new water main line
and services.
Bell Ave at Mingo Rd 10/18/21 11/29/21 Water Distribution will be Water Tiffany Sherrane
3 installing a new water main line
and services.
Bernard St Hickory St Chestnut St 05/18/22 06/29/22 Water Distribution will be Water Tiffany Sherrane
4 replacing the water main line
and services.
5 Keystone Ct West of Stuart East of 1109 Keystone Court 10/18/21 10/29/21 Concrete panel repair Private Development Public Tucker Eller
Works Inspections
6 Stuart Rd South side Keystone Court North side Keystone Court 10/25/21 10/29/21 Repairing concrete panels Private Development Tucker Eller
Exported on October 8,2021 10:58:25 AM CDT Page 1 of 1
2 Street Closure Report: Current Closures smartsheet
Street/Intersection From To Closure Start Closure End Description Department Department Contact
Date Date
1 Allred Rd JM Prosperity Farm Rustic Barn Bonnie Brae 09/27/21 07/31/22 Storm Installation,Cutting Private Development Public Jeremiah Tillman-David
Venue Grade on Allred Works Inspections
Bell Ave College St Texas St 08/04/21 10/14/21 Water Distribution will be Water Tiffany Sherrane
2 installing a new water main line
and services.
Bonnie Brae(SB) Oak Hickory 06/14/21 10/27/21 This block is closed to Other Mark Zimmerer
southbound traffic only,detours
are posted.Northbound lane
3 still open.Installation of electric
duct banks for DME substation
project and steel casing for
water main project
Carroll Blvd(SB)&(NB) Mulberry Eagle 07/12/21 10/29/21 Concrete Street Panel and Streets robbin.webber@cityofdenton.co
Sidewalk Repair.The process m
starts with Barricading the failed
sections of concrete pavement,
remove the pavement,and
install new concrete.
Elm Hickory Eagle 05/11/20 10/29/21 PEC 4 Utility Project Engineering Seth Garcia
Elm Street Eagle Drive (dead end) 05/17/21 10/29/21 Atmos Energy will be closing Atmos Alice Province
street intermittently to replace
and relocate an existing gas
main and service lines
Hickory Street Welch Carroll 08/31/20 10/15/21 Construction is set to begin on Engineering Kyle Pedigo
West Hickory Street between N.
Welch Street and Carroll Blvd in
October of 2020 and continue
7 through September of 2021.
Detailed lane closure
information is forthcoming
pending approval of the
contractor's phasing and traffic
control plans.
Mckinney duchess Glengarry 02/01/21 12/24/21 McKinney-Mayhill Intersection Engineering Trevor Crain
This project is widening the
intersection and 600'each way
8 to match existing conditions
along McKinney.Also includes
water,wastewater,and
drainage improvements.
McKinney St @ Elm St intersection 08/02/21 10/29/21 Temporary lane closures in Traffic James Andrews
9 place as crews work to safely
install new traffic signals at the
intersections
McKinney St @ Locust St intersection 08/02/21 10/29/21 Temporary lane closures in Traffic James Andrews
10 place as crews work to safely
install new traffic signals at the
intersections
11 Quail Ridge Cooper Branch E La Paloma Dr 09/07/21 10/29/21 Street Reconstruction Engineering Dustin Draper
Ruddell HWY 380 Mingo Rd 10/05/21 10/08/21 Water Distribution will be Water James Gideon
12 repairing a water main valve
and will re-open the road at the
end of the day.
Ryan Rd Creekside Dr Paradise Ln 09/27/21 10/29/21 Wastewater Collections will be Wastewater Tiffany Sherrane
13 installing a new wastewater
main line
14 Welch Eagle Collins 08/23/21 10/30/21 Utility installations and Engineering Streets Water Kyle Pedigo
pavement replacement. Wastewater
Exported on October 8,2021 11:14:29 AM CDT Page 1 of 2
Street/Intersection From To Closure Start Closure End Description Department Department Contact
Date Date
Welch Street Chestnut Street Mulberry Street 09/27/21 11/23/21 University of North Texas Private Development Public Alice Province
1: excavating street to connect Works Inspections
services to Art Studio Building
16 Western Blvd Jim Chrystal Airport Rd 08/16/21 12/31/21 Paving:Decal Lanes Private Development Public Jeremiah Tillman-David
Works Inspections
17 Windsor Bonnie Brae Parkside 08/09/21 12/31/21 Pavement Restoration Private Development Public Jeremiah Tillman-David
Works Inspections
Exported on October 8,2021 11:14:29 AM CDT Page 2 of 2
3 Street Closure Report: Completed Closures smartsheet
Street/Intersection r i Closure Start losure End Description Department Department Contact
Bell PI at Mckinney St 07/08/21 10/08/21 Water Distribution will be Water Tiffany Sherrane
1 installing a new water main line
and services.
Chebi Lane Old North Road Freedom Lane 06/21/21 09/10/21 Full width pavement Engineering Streets Kyle Pedigo
2 replacement and subgrade
improvement.
College Park Dr Peach St End of College Park Dr 06/28/21 09/24/21 Wastewater collections will be Wastewater Tiffany Sherrane
3 installing a new wastewater
main line and services.
Eagle Locust Elm 06/28/21 09/10/21 Patching of utility trench lines. Engineering Seth Garcia
Fowler Dr College Park Dr Peach St 06/28/21 09/24/21 Wastewater collections will be Wastewater Tiffany Sherrane
installing a new wastewater
main line and services.
Mistywood Lane Old North Road Craig Lane 06/21/21 09/10/21 Full width pavement Engineering Streets Kyle Pedigo
6 replacement and subgrade
improvement.
Peach St N Locust Dr Fowler Dr 06/28/21 09/24/21 Wastewater collections will be Wastewater Tiffany Sherrane
7 installing a new wastewater
main line and services.
8 Provence Vintage Sonoma 09/03/21 09/21/21 Paving and Drainage work Drainage Engineering Seth Garcia
Scripture Bonnie Brae 1,300 ft.to the West 03/22/21 09/20/21 Reconstruct;Scripture from Streets robbin.webber@cityofdenton.co
Bonnie Brae to approximately m
1,300 ft.to the west.This
includes removal and
replacement of failed sections
of curb and gutter.Milling of the
old asphalt pavement and the
9 stabilization of subgrade and
the installation of new asphalt
pavement.
Phase I East Bound Outside
Lane
Phase II West Bound Outside
Lane
Phase III Middle Lane
Walnut Street Locust Street Elm Street 05/17/21 09/30/21 Atmos Energy will be Atmos Alice Province
10 excavating street to complete
replacement/relocation of their
existing gas main
Windsor Dr East Broken Bow Armstrong 07/28/21 09/30/21 Street Reconstruction will be Engineering Dustin Draper
11 performed on the westbound
lane of E Windsor
Exported on October 8,2021 11:14:41 AM CDT Page 1 of 1