2021/11/15 - Street Closure Report 1 Street Closure Report: Upcoming Closures smartsheet
SCR Nov 15th - 21 st
Closure Start
Street/Intersection From To Date Description Department Contact
Bell Ave Texas St Withers St 01/03/22 02/07/22 Water Distribution will be Water Tiffany Sherrane
1 installing a new water main line
and services.
Bell Ave Withers St Mingo Rd 02/08/22 03/21/22 Water Distribution will be Water Tiffany Sherrane
2 installing a new water main line
and services.
Bernard St Hickory St Chestnut St 06/18/22 07/30/22 Water Distribution will be Water Tiffany Sherrane
3 replacing the water main line
and services.
Hopkins Dr Travis St Hopkins Dr 11/22/21 12/07/21 Wastewater Collections will be Wastewater Tiffany.sherrane@cityofdenton.
4 installing a new wastewater com
main line and services.
Montecito Buena Vista Palo Verde 11/29/21 12/17/21 Concrete Sidewalk Repair. Streets Robbin Webber
5 Remove failed sections and
install new concrete
Exported on November 12,2021 10:26:21 AM CST Page 1 of 1
2 Street Closure Report: Current Closures smartsheet
I Closure Start Closure End Department I
Street/Intersection From To Date Date Description Department Contact
1 Allred Rd JM Prosperity Farm Rustic Barn Bonnie Brae 09/27/21 07/31/22 Storm Installation,Cutting Private Development Public Jeremiah Tillman-David
Venue Grade on Allred Works Inspections
2 Amherst Georgetown Malone 10/18/21 01/21/22 Street Reconstruction Streets Robbin Webber
Archer Trail Foxcroft Circle Emerson 11/08/21 12/23/21 Residential roadway Engineering Dustin Draper
3 reconstruction and during the
construction only resident traffic
will be allowed.
Bell Ave at Mingo Rd 10/30/21 12/11/21 Water Distribution will be Water Tiffany Sherrane
4 installing a new water main line
and services.
5 Chestnut Street South Welch Street Bernard Street 10/18/21 01/03/22 Utility installations and Engineering Scott Fettig
pavement replacement.
6 Elm Hickory Eagle 05/11/20 11/19/21 PEC 4 Utility Project Engineering Seth Garcia
Hickory Street Welch Carroll 08/31/20 11/19/21 Construction is set to begin on Engineering Kyle Pedigo
West Hickory Street between N.
Welch Street and Carroll Blvd in
October of 2020 and continue
7 through September of 2021.
Detailed lane closure
information is forthcoming
pending approval of the
contractor's phasing and traffic
control plans.
Locksley Lane Emerson Maid Marion 11/08/21 12/17/21 Residential Roadway Engineering Dustin Draper
8 reconstruction,and during the
construction resident traffic only
will be allowed.
Mckinney duchess Glengarry 02/01/21 12/24/21 McKinney-Mayhill Intersection Engineering Trevor Crain
This project is widening the
intersection and 600'each way
9 to match existing conditions
along McKinney.Also includes
water,wastewater,and
drainage improvements.
Orr Street Elm Street Locust Street 10/25/21 11/30/21 Roadway Reconstruction this Engineering Dustin Draper
10 project only affects one
business and notification was
direct with the business owner.
11 Quail Ridge Cooper Branch E La Paloma Dr 09/07/21 12/10/21 Street Reconstruction Engineering Dustin Draper
12 Stella St. North Texas Blvd Bonnie Brae 10/29/21 03/15/22 Utility installations and Engineering Scott Fettig
pavement replacement.
Williamsburg Row Jamestown Ln Nottingham Dr 10/26/21 11/19/21 Wastewater Collection will be Wastewater Tiffany Sherrane
13 installing a new wastewater
main line and services
14 Windsor Bonnie Brae Parkside 08/09/21 12/31/21 Pavement Restoration Private Development Public Jeremiah Tillman-David
Works Inspections
Exported on November 12,2021 10:28:18 AM CST Page 1 of 1
3 Street Closure Report: Completed Closures smartsheet
Street/Intersection r i Closure Start 7closure End Description Department Department Contact
M Date -1 Date
Bonnie Brae(SB) Oak Hickory 06/14/21 10/27/21 This block is closed to Other Mark Zimmerer
southbound traffic only,detours
are posted.Northbound lane
1 still open.Installation of electric
duct banks for DME substation
project and steel casing for
water main project
Carroll Blvd(SB)&(NB) Mulberry Eagle 07/12/21 11/09/21 Concrete Street Panel and Streets robbin.webber@cityofdenton.co
Sidewalk Repair.The process m
2 starts with Barricading the failed
sections of concrete pavement,
remove the pavement,and
install new concrete.
Elm Street Eagle Drive (dead end) 05/17/21 10/29/21 Atmos Energy will be closing Atmos Alice Province
3 street intermittently to replace
and relocate an existing gas
main and service lines
4 Keystone Ct West of Stuart East of 1109 Keystone Court 10/18/21 10/29/21 Concrete panel repair Private Development Public Tucker Eller
Works Inspections
5 Long Road W of LaGrone Academy School E of LaGrone Academy School 10/25/21 10/29/21 Replacing concrete road panels Private Development Tucker Eller
McKinney St @ Elm St intersection 08/02/21 10/29/21 Temporary lane closures in Traffic James Andrews
6 place as crews work to safely
install new traffic signals at the
intersections
McKinney St @ Locust St intersection 08/02/21 10/29/21 Temporary lane closures in Traffic James Andrews
7 place as crews work to safely
install new traffic signals at the
intersections
Ryan Rd Creekside Dr Paradise Ln 09/27/21 10/29/21 Wastewater Collections will be Wastewater Tiffany Sherrane
8 installing a new wastewater
main line
9 Stuart Rd South side Keystone Court North side Keystone Court 10/25/21 10/29/21 Repairing concrete panels Private Development Tucker Eller
10 Welch Eagle Collins 08/23/21 10/30/21 Utility installations and Engineering Streets Water Kyle Pedigo
pavement replacement. Wastewater
Welch Street Chestnut Street Mulberry Street 09/27/21 11/14/21 University of North Texas Private Development Public Alice Province
11 excavating street to connect Works Inspections
services to Art Studio Building
12 Western Blvd Jim Chrystal Airport Rd 08/16/21 12/31/21 Paving:Decal Lanes Private Development Public Jeremiah Tillman-David
Works Inspections
Exported on November 12,2021 10:28:30 AM CST Page 1 of 1