2022/02/04 - Street Closure Report 1 Street Closure Report: Upcoming Closures smartsheet
SCR Feb 7th - 13th
Street/Intersection =ME Description Department Contact
Bell Ave Texas St Withers St 02/19/22 03/25/22 Water Distribution will be Water Tiffany Sherrane
1 installing a new water main line
and services.
Bernard St Hickory St Chestnut St 06/20/23 07/31/23 Water Distribution will be Water Tiffany Sherrane
2 replacing the water main line
and services.
3 Mockingbird Christopher Dr Penniman Dr 02/07/22 02/21/22 Installing Junction Box and Private Development Armando Beltran
connecting waterline
Exported on February 4,2022 11:53:18 AM CST Page 1 of 1
2 Street Closure Report: Current Closures smartsheet
Street/Intersection M From To Closure Start Closure End I
Date Date Description Department Department Contact
1 Allred Rd JM Prosperity Farm Rustic Barn Bonnie Brae 09/27/21 07/31/22 Storm Installation,Cutting Private Development Public Jeremiah Tillman-David
Venue Grade on Allred Works Inspections
2 Amherst Georgetown Malone 10/18/21 02/25/22 Street Reconstruction Streets Roy San Miguel
Bell Ave Withers St Mingo Rd 01/07/22 02/18/22 Water Distribution will be Water Tiffany Sherrane
3 installing a new water main line
and services.
Bonnie Brae Street Scripture Panhandle 02/10/22 02/18/22 The contractor will begin Engineering Robin Davis
making the connection of the
new 42-inch Transmission Main
to the existing Main.Therefore,
both northbound lanes of
Bonnie Brae Street from
4 Scripture to Panhandle Street
will be closed.North bound
Traffic will be detoured to turn
right on Scripture,left on
Thomas,and left on Panhandle
to finally arrive back on Bonnie
Brae Street.Detour signs will be
posted accordingly.
5 Chestnut Street South Welch Street Bernard Street 10/18/21 03/31/22 Utility installations and Engineering Scott Fettig
pavement replacement.
8 Cyrus Way Teal Harvest Glen 01/10/22 02/18/22 Concrete Panel and Sidewalk Streets Roy San Miguel
Repair
Davis St Jannie St Hettie St 01/31/22 03/05/22 Wastewater Collections will be Wastewater Tiffany Sherrane
7 installing a new wastewater
main line and services.
Foxcroft Cir Emerson Old North 01/18/22 02/18/22 Residential roadway Engineering Dustin Draper
8 reconstruction and during the
construction only resident traffic
will be allowed.
9 Montecito Settlement Field Bend 01/18/22 03/04/22 Concrete Street Panel and Streets Roy San Miguel
Sidewalk Repair
10 North Texas Blvd. Eagle Dr to Oak There will be multiple phases of 12/13/21 08/01/22 Utility installations and Scott Fettig
closures.Will not be all at one pavement replacement.
Scripture St Marietta St Bradley St 02/01/22 03/04/22 Installation of 24"RCP pipe Drainage Gabriel Rodriguez
across the Street to a Storm
11 Drain Inlet on the south side of
the road on the south side of
the Road
12 Stella St. North Texas Blvd Bonnie Brae i 10/29/21 03/15/22 Utility installations and Engineering Scott Fettig
pavement replacement.
13 Welch Street Eagle Street West Collins St. 11/29/21 02/18/22 Utility installations and Engineering Scott Fettig
pavement replacement.
Exported on February 4,2022 11:55:00 AM CST Page 1 of 1
3 Street Closure Report: Completed Closures smartsheet
I Closure Starr, Closure End I
Street/Intersection From Date Date Description Department Department Contact
Archer Trail Foxcroft Circle Emerson 11/08/21 02/16/22 Residential roadway Engineering Dustin Draper
1 reconstruction and during the
construction only resident traffic
will be allowed.
Bell Ave at Mingo Rd 11/22/21 01/06/22 Water Distribution will be Water Tiffany Sherrane
2 installing a new water main line
and services.
Foxcroft CIR Archer Trail Emerson 01/05/22 02/04/22 Residential roadway Engineering Dustin Draper
3 reconstruction and during the
construction only resident traffic
will be allowed.
4 Frame St @ Railroad Crossing 01/06/22 01/06/22 UPRR Planned maintenance
5 Hickory St @ Railroad Crossing 01/05/22 01/05/22 UPRR Planned maintenance
6 McKinney St @ Railroad Crossing 01/05/22 01/05/22 UPRR Planned maintenance
Montecito Buena Vista Palo Verde 11/29/21 01/07/22 Concrete Sidewalk Repair. Streets Robbin Webber
7 Remove failed sections and
install new concrete
Orr Street Elm Street Locust Street 10/25/21 01/19/22 Roadway Reconstruction this Engineering Dustin Draper
8 project only affects one
business and notification was
direct with the business owner.
9 Stuart Rd South of Keystone Court North of Keystone Court 01/24/22 02/02/22 Replacing concrete road panels Private Development Tucker Eller
10�:. rschun
weet Gate Lake View Autumn Path 01/03/22 02/11/22 Concrete Street Panel Repair Streets Roy San Miguel
11 Rd E Sherman Dr(FM 428) Sauls Rd 12/08/21 01/21/22 Drainage pipe extension and Engineering Dustin Draper
Turn lane addition
Williamsburg Row Jamestown Ln Nottingham Dr 10/26/21 01/28/22 Wastewater Collection will be Wastewater Tiffany Sherrane
12 installing a new wastewater
main line and services
13 Willis St @ Railroad Crossing 01/06/22 01/06/22 UPRR Planned maintenance
14 Windsor Bonnie Brae Parkside 08/09/21 01/25/22 Pavement Restoration Private Development Public Jeremiah Tillman-David
Works Inspections
Exported on February 4,2022 11:55:12 AM CST Page 1 of 1