2022/05/20 - Street Closure Report 1 Street Closure Report: Upcoming Closures smartsheet
SCR May 23rd - 29th
Street/Intersection Description In Department Contact
1 Atlas Hercules Ln Juno Ln 06/06/22 07/15/22 Replacing gas service lines,open trench,from new main.Road Atmos Public Works Ryan Dromgoole
will be closed from 8am-4pm Monday through Friday. Inspections
2 Bernard St. Hickory St. Chestnut St. 07/06/23 08/16/23 Water Distribution will be replacing the water main line and Water Tiffany Sherrane
services.
3 Bryan Street Scripture 228 Bryan Street 06/06/22 06/07/22 Closing Bryan Street June 6 and 7 from 7:00 AM to 4:30 PM to Public Works Inspections Stephany Trammell
remove tower crane from jobsite.
4 Oak St Fulton St Fry St 05/30/22 06/13/22 Utility work in roadway Gabrielle Milam
5L St James Wheeler Ridge Thoroughbred 06/06/22 07/08/22 Concrete Panel and Sidewalk Repair Streets Roy San Miguel
Exported on May 20,2022 11:03:28 AM CDT Page 1 of 1
2 Street Closure Report: Current Closures smartsheet
I Closure Start Closure End Department I
Street/Intersection From To Date Date Description Department Contact
1 Allred Rd. JM Prosperity Farm Rustic Barn Bonnie Brae St. 09/27/21 07/31/22 Storm Installation,Cutting Private Development Public Jeremiah Tillman-David
Venue Grade on Allred Works Inspections
Bonnie Brae Scripture 1-35 01/01/20 06/30/22 Installation of water Engineering Streets Water Robin Davis
2 transmission line and
restoration of asphalt
3 Box Wood Smoke Tree Cut V Sac 05/23/22 06/17/22 Concrete Panel Repair Streets Roy San Miguel
4 Bradshaw St.N Hickory St.E McKinney St.E 03/21/22 07/31/22 Utility installations and Engineering Scott Fettig
pavement replacement.
5 Chestnut St. Welch St.S Bernard St. 10/18/21 05/31/22 Utility installations and Engineering Scott Fettig
pavement replacement.
Clover Ln Robinwood Ln Glenwood Ln 05/23/22 09/19/22 Wastewater Collections will be Wastewater Tiffany.sherrane@cityofdenton.
6 installing a new sewer main line com
and services.
College Park Dr Peach St Fowler Dr 04/18/22 07/20/22 Water Distribution will be Water Tiffany Sherrane
7 installing a new water naim line
and services.
8 Crawford St N Hickory St E McKinney St E 03/21/22 07/31/22 Utility installations and Engineering Scott Fettig
pavement replacement.
Fowler Dr College Park Dr Peach St 04/18/22 07/20/22 Water Distribution will be Water Tiffany SHerrane
9 installing a new water main line
and services
10 Foxcroft Circle Archer Trail Northcrest Rd 04/25/22 06/03/22 Street reconstruction Engineering Dustin Draper
11 Foxcroft Circle Old North Emerson 02/11/22 05/27/22 Street reconstruction Engineering Dustin Draper
12 Fry Street Oak St Scripture 05/02/22 05/30/22 Drive Approaches/Sidewalk/ Private Development Public Gabrielle Milam
Water and Sanitary Sewer Works Inspections
13 Green Ivy Robinson Rd English Manor 05/23/22 06/17/22 Concrete Panel and Sidewalk Streets Roy San Miguel
Repair
14 Hattie St. Paisley St. McKinney St.E 03/21/22 07/31/22 Utility installations and Engineering Scott Fettig
pavement replacement.
15 Hickory St.E Exposition St. Ruddell St. 05/02/22 08/31/22 Utility installations and Engineering Scott Fettig
pavement replacement.
Hickory Street Eastbound from Oak Bonnie Brae Bonnie Brae 05/16/22 05/27/22 Southbound lanes on Bonnie Engineering Streets Traffic Robin Davis
Street Split Brae at Hickory will be closed Water
for pavement replacement.
16 Traffic on Bonnie Brae will not
be affected. Through traffic will
be closed at Hickory Street from
the Split on Oak Street.
17 Hillcrest St Scripture Panhandle 04/29/22 06/30/22 Street reconstruction Engineering Dustin Draper
Jim Chrystal Western Blvd. Masch Branch 04/18/22 08/31/22 Exeter PH2.Installing Public Private Development Public Jeremiah Tillman-David
18 Water,Sewer,and Storm Works Inspections
Utilities
Live Oak St Robinwood Ln Crestwood PI 05/23/22 09/19/22 Wastewater collections will be Wastewater Tiffany Sherrane
19 installing a new sewer main line
and services.
20 Long Rd. Sherman Dr.E(428) Holy Springs Rd 05/16/22 06/03/22 Concrete Panel Repair Streets Roy San Miguel
21 McKinney St E Crawford Rd Audra Ln 05/19/22 09/30/22 Utility installations and Engineering Scott Fettig
pavement replacement.
Mistywood Ln Sherwood St Robinwood Ln 05/23/22 09/19/22 Wastewater Collections will be Wastewater Tiffany Sherrane
22 installing a new sewer main line
and services.
23 Mockingbird Ln Mingo Rd Stockton St 05/04/22 06/01/22 Sewer manhole installation and Public Works Inspections Armando Beltran
2 water taps.
Exported on May 20,2022 11:04:21 AM CDT Page 1 of 2
Street/Intersection From To Closure Start Description Department Department Contact
Date
North Texas Blvd. Eagle Dr. Oak St. 12/13/21 09/01/22 Utility installations and Engineering Scott Fettig
pavement replacement.There
24 will be multiple phases of
closures.Will not be all at one
time.
25 Oak St.E Crawford St.N Wood St.N 04/04/22 08/31/22 Utility installations and Engineering Scott Fettig
pavement replacement.
Peach St Locust St Palmer Dr 04/18/22 07/20/22 Water Distribution will be Water Tiffany Sherrane
26 installing a new water main line
and services.
Robinwood Ln Kayewwod Dr Emerson Ln 05/23/22 09/19/22 Wastewater Collections will be Wastewater Tiffany Sherrane
27 installing a new sewer main line
and services.
28 Rose St. Paisley St. Uland St. 04/25/22 08/31/22 Pavement Replacement Engineering Scott Fettig
29 Stella St. North Texas Blvd Bonnie Brae 10/29/21 06/15/22 Utility installations and Engineering Scott Fettig
pavement replacement.
30 Sycamore St Bernard Carroll Blvd 05/17/22 07/29/22 Street Reconstruction Engineering Dustin Draper
31 Uland St. Rose St, Railroad Ave. 04/25/22 08/31/22 Utility installations and Engineering Scott Fettig
pavement replacement.
32 Wolftrap Dr. Stuart Rd. Olympia Dr. 04/04/22 05/27/22 Laying RCP across the street to Private Development Tucker Eller
connect to existing storm drain.
33 Wood St.N McKinney St.E Hickory St.E 04/11/22 06/30/22 Utility installations and Engineering Scott Fettig
pavement replacement.
Exported on May 20,2022 11:04:21 AM CDT Page 2 of 2
3 Street Closure Report: Completed Closures smartsheet
Intersection • • ClosureDat- Closure_ • Description Department Department
1 Bonnie Brae intersection of Oak St. 05/10/22 05/14/22 Southbound lanes only Engineering Streets Water Robin Davis
2 Depaul Drexel Miramar Dr. 03/28/22 05/12/22 Concrete Panel and Sidewalk Streets Roy San Miguel
Repair
3 Foxcroft Circle Emerson Archer Trail 01/21/22 05/20/22 Street reconstruction Engineering Dustin Draper
4 Foxcroft Circle Northcrest Rd Old North 02/23/22 05/20/22 Street reconstruction Engineering Dustin Draper
5 Mayhill Rd. 1-35 Service road Colorado Blvd. 04/25/22 05/12/22 Concrete Panel repair Streets Rogelio San Miguel
6 Northwood Terrace Greenwood Dr. Cherrywood Ln 03/07/22 05/20/22 Street reconstruction Engineering Dustin Draper
Oak St.E Bradshaw St.S Wood St.N 04/01/22 05/06/22 Wastewater Collections will be Wastewater Tiffany Sherrane
7 installing a new wastewater
main line and services.
Oak Street Bonnie Brae Bonnie Brae 05/10/22 05/14/22 Southbound lanes on Bonnie Engineering Streets Water Robin Davis
Brae at Oak will be closed for
8 pavement replacement.Traffic
on Bonnie Brae won't be
affected.Through traffic will be
closed on Oak.
Old Bonnie Brae St. Bonnie Brae St./Roselawn Dr. Bonnie Brae St/Vintage 04/25/22 04/29/22 Road Closure will last Engineering Wastewater Tracy L.Beck,PE,PMP
approximately 2-3 days to install
9 Sanitary Sewer Line under Old
Bonne Brae Road. Weather
may impact timing of closure. .
10 Regency(801) Country Club Cul v Sac 04/11/22 04/21/22 Concrete Panel Repair Streets Roy San Miguel
11 Sweet Cloud Winding Stream Clear River 04/18/22 05/12/22 Concrete Street Panel and Streets Roy San Miguel
Sidewalk Repair
121 Winding Stream Silent Star Sweet Cloud 03/28/22 04/21/22 Concrete SideWalk Repair Streets Roy San Miguel
Exported on May 20,2022 11:04:38 AM CDT Page 1 of 1