2022/07/15 - Street Closure Report 1 Street Closure Report: Upcoming Closures smartsheet
SCR July 18th - 24th
Street/Intersection Department Department Contact
1 Harvard or Yale or Cul V sac 08/01/22 08/26/22 Curb and Sidewalk Repair Streets Roy San Miguel
2 Oak St Fulton St Fry St 08/12/22 08/26/22 Utility work in roadway Public Works Inspections Stephany Trammell
Exported on July 15,2022 11:09:17 AM CDT Page 1 of 1
2 Street Closure Report: Current Closures smartsheet
I Closure Start Closure End Department I
Street/Intersection From To Date Date Description Department Contact
1 Allred Rd JM Prosperity Farm Rustic Barn Bonnie Brae St 09/27/21 07/31/22 Storm Installation,Cutting Private Development Public Jeremiah Tillman-David
Venue Grade on Allred Works Inspections
Atlas Dr Hercules Ln Juno Ln 06/06/22 07/29/22 Replacing gas service lines, Atmos Public Works Ryan Dromgoole
open trench,from new main. Inspections
2 Sections of the Road will be
closed from 8am-5pm Monday
through Friday.Detour routes
will be posted.
3 Ave D Highland St Maple St 07/18/22 08/05/22 Street Reconstruction Engineering Dustin Draper
4 Bell Ave Texas Mingo Rd 05/16/22 08/12/22 6 in.Asphalt Mill and Overlay/ Streets Roy San Miguel
will be split in 3 Sections
5 Bradshaw St Hickory St McKinney St 03/21/22 07/31/22 Utility installations and Engineering Scott Fettig
pavement replacement.
Clover Ln Robinwood Ln Glenwood Ln 05/23/22 09/19/22 Wastewater Collections will be Wastewater Tiffany.sherrane@cityofdenton.
6 installing a new sewer main line com
and services.
College Park Dr Peach St Fowler Dr 04/18/22 08/19/22 Water Distribution will be Water Tiffany Sherrane
7 installing a new water naim line
and services.
8 Crawford St Hickory St McKinney St 03/21/22 07/31/22 Utility installations and Engineering Scott Fettig
pavement replacement.
9 Forest Ridge Dr El Paseo St Wellington Oaks Cir 07/19/22 08/19/22 Street Panels Repair Streets Roy San Miguel
Fowler Dr College Park Dr Peach St 04/18/22 08/19/22 Water Distribution will be Water Tiffany SHerrane
10 installing a new water main line
and services
11 Foxcroft Circle Old North Rd Archer Trail 05/02/22 08/05/22 Street Reconstruction Engineering Dustin Draper
12 Fry St Oak St Scripture St 05/10/22 07/29/22 Drive Approaches/Sidewalk/ Private Development Public Gabrielle Milam
Water and Sanitary Sewer Works Inspections
13 Hattie St Paisley St McKinney St 03/21/22 07/31/22 Utility installations and Engineering Scott Fettig
pavement replacement.
14 Hickory St Exposition St Ruddell St 05/02/22 08/31/22 Utility installations and Engineering Scott Fettig
pavement replacement.
15 Hill Alley St Jackson St Martin St 06/06/22 08/26/22 Utility replacement and roadway Engineering Seth Garcia
reconstruction
16 Hillcrest St Panhandle Scripture 05/10/22 07/29/22 Street Reconstruction Engineering Dustin Draper
17 Jackson St Morse St Hill Alley St 06/06/22 08/26/22 Utility replacement and roadway Engineering Seth Garcia
reconstruction
Jim Chrystal Rd Western Blvd Masch Branch Rd 04/18/22 08/31/22 Exeter PH2.Installing Public Private Development Public Jeremiah Tillman-David
18 Water,Sewer,and Storm Works Inspections
Utilities
19 Linden Dr Malone St Gober St 07/19/22 08/12/22 Curb and Gutter/Valley Gutter Streets Roy San Miguel
Repair
Live Oak St Robinwood Ln Crestwood PI 05/23/22 09/19/22 Wastewater collections will be Wastewater Tiffany Sherrane
20 installing a new sewer main line
and services.
21 Mack Or Paisley St Double Oak St 06/27/22 08/04/22 Street Reconstruction Engineering Dustin Draper
22 Marquette Dr(3608) Centenary Dr Cul v Sac 06/27/22 07/22/22 ADA/Sidewalk Repair Streets Roy San Miguel
23 Masch Branch Rd Lovers Ln Hampton Rd 06/24/22 09/30/22 Bridge collapse at 3288 N. Drainage Gabriel Rodriguez
Masch Branch Rd
24 McKinney St Crawford Rd Audra Ln 05/19/22 09/30/22 Utility installations and Engineering Scott Fettig
pavement replacement.
25 McKinney St E Bell St Frame St 07/18/22 08/01/22 Working on drainage and Public Works Inspections Armando Beltran
construction of Frame St.
Exported on July 15,2022 11:09:57 AM CDT Page 1 of 2
Street/Intersection From To Closure Start Department Department Contact
Date
Mistywood Ln Sherwood St Robinwood Ln 05/23/22 09/19/22 Wastewater Collections will be Wastewater Tiffany Sherrane
26 installing a new sewer main line
and services.
27 Morse St Lakey St Jackson St 06/06/22 08/26/22 Utility replacement and roadway Engineering Seth Garcia
reconstruction
North Texas Blvd 1-35W Oak St 12/13/21 09/01/22 Utility installations and Engineering Scott Fettig
pavement replacement.There
28 will be multiple phases of
closures.Will not be all at one
time.
29 North Texas Blvd Oak St Hickory St 06/10/22 08/31/22 Utility installations and Engineering Scott Fettig
pavement replacement.
30 Oak St.E Crawford St Wood St 04/04/22 08/31/22 Utility installations and Engineering Scott Fettig
pavement replacement.
31 Parkside Or Windsor Or Bowling Green St 05/31/22 09/02/22 Utility installations and Engineering Scott Fettig
pavement replacement.
Peach St Locust St Palmer Dr 04/18/22 08/19/22 Water Distribution will be Water Tiffany Sherrane
32 installing a new water main line
and services.
33 Peach St Locust St N Fowler Dr 07/18/22 08/15/22 Upgrading 15 Storm pipe to Drainage Gabriel Rodriguez
18"
Robinwood Ln Kayewwod Dr Emerson Ln 05/23/22 09/19/22 Wastewater Collections will be Wastewater Tiffany Sherrane
34 installing a new sewer main line
and services.
35 Rose St Paisley St Uland St 04/25/22 08/31/22 Pavement Replacement Engineering Scott Fettig
36 St James PI Wheeler Ridge Dr Thoroughbred Trl 06/27/22 08/05/22 Concrete Panel and Sidewalk Streets Roy San Miguel
Repair
37 Stella St North Texas Blvd Bonnie Brae St 10/29/21 08/31/22 Utility installations and Engineering Scott Fettig
pavement replacement.
38 Sycamore St Bernard St Carroll Blvd 05/17/22 07/29/22 Street Reconstruction Engineering Dustin Draper
39 Sycamore St W Bernard St Welch St S 07/18/22 08/26/22 Street Reconstruction Engineering Dustin Draper
40 Uland St Rose St Railroad Ave 04/25/22 08/31/22 Utility installations and Engineering Scott Fettig
pavement replacement.
41 Windsor Dr Fireside Ln Bonnie Brae St 06/06/22 08/26/22 Utility installations and Engineering Scott Fettig
pavement replacement.
42 Wood St McKinney St Hickory St 04/11/22 08/31/22 Utility installations and Engineering Scott Fettig
pavement replacement.
Exported on July 15,2022 11:09:57 AM CDT Page 2 of 2
3 Street Closure Report: Completed Closures smartsheet
Street/Intersection From Mur, Closure End Description Department Department Contact
Date
1 Ave A Maple St Highland St 07/05/22 07/15/22 Valley Gutter Repair Streets Roy San Miguel
Bonnie Brae St Scripture St 1-35 01/01/20 06/30/22 Installation of water Engineering Streets Water Robin Davis
2 transmission line and
restoration of asphalt
3 Box Wood Dr Smoketree Trl Cul v Sac North 05/23/22 06/16/22 Concrete Panel Repair Streets Roy San Miguel
4 Foxcroft Cir Old North Rd Emerson Ln 02/11/22 06/27/22 Street reconstruction Engineering Dustin Draper
5 Green Ivy Rd Robinson Rd English Manor Rd 05/23/22 07/13/22 Concrete Panel and Sidewalk Streets Roy San Miguel
Repair
6 Hillcrest St Scripture St Panhandle St 04/29/22 06/30/22 Street reconstruction Engineering Dustin Draper
7 Long Rd Sherman Dr(428) Holy Springs Rd 05/16/22 06/16/22 Concrete Panel Repair Streets Roy San Miguel
McKinney St Elm St Locust St 06/16/22 07/01/22 Restoring concrete from Atmos Public Works Inspections Ryan Dromgoole
8 replacing Gas Main and
Services.Inside Lane Closure
on NB Locust
9 Oak St.W Bradley St North Texas Blvd 06/10/22 06/22/22 Utility installations and Engineering Scott Fettig
pavement replacement.
10 Shagbark Dr Vintage Blvd Buckthorn Ln 05/31/22 06/24/22 Concrete Panel Replacement Engineering Seth Garcia
Trinity Rd Mills Rd Grissom Rd 06/27/22 07/01/22 Water tap into the Woodlands Public Works Inspections Armando Beltran
11 Privet
development.
Exported on July 15,2022 11:10:15 AM CDT Page 1 of 1