2023/02/17 - Street Closure Report 1 Street Closure Report: Upcoming Closures smartsheet
SCR Feb 20th - 26th
Street/Intersection From To Closure End Description Department Department Contact
1 Avenue S Prairie St E Dead End South 03/06/23 05/20/23 Utility installations and pavement replacement. Engineering Scott Fettig
2 Castle Pines Ln Burr Oak Dr @ Intersection 02/27/23 03/17/23 Concrete Street Panel repair Streets Roy San Miguel
3 Smith St Dallas or(Hwy 77) Hill St 03/06/23 06/07/23 Utility installations and pavement replacement. Engineering Scott Fettig
Exported on February 17,2023 11:47:18 AM CST
2 Street Closure Report: Current Closures smartsheet
�� i Closure Start Closure End Description Department Department Contact
Street/Intersection Date Date
1 Allen St Mill St Wye St 12/12/22 03/17/23 Utility replacement and roadway Engineering Seth Garcia
reconstruction
2 Angelina Bend Dr San Gabriel Dr Angelina Bend Dr(1416) 01/17/23 03/03/23 Street Reconstruction Engineering Dustin Draper
3 Atlas Dr Hercules Ln Redstone Rd 10/17/22 03/24/23 Reconstruct Streets Jeremy Wilks
4 Augusta Dr Colonial Dr Augusta Dr(2900) 07/11/22 04/03/23 Utility installations and Engineering Scott Fettig
pavement replacement.
5 Bailey St Willson St Dead End South 01/30/23 06/02/23 Utility installations and Engineering Scott Fettig
pavement replacement.
6 Bell Ave Mingo Rd 300'North 02/20/23 02/22/23 Mill and Overlay of Senior Jeff Jones
Center parking along bell
7 Boxwood Dr Plumbago Dr Daisy Dr 01/03/23 02/24/23 Street Panel and Sidewalk Streets Roy San Miguel
Repair
8 Bradshaw St Hickory St McKinney St 03/21/22 03/01/23 Utility installations and Engineering Scott Fettig
pavement replacement.
9 Bradshaw St Wilson St Prairie St East 01/30/23 06/02/23 Utility installations and Engineering Scott Fettig
pavement replacement.
10 Brook Hollow Dr Greenway Dr Carriage Hill 10/07/22 04/03/23 Utility installations and Engineering Scott Fettig
pavement replacement.
Clover Ln Robinwood Ln Glenwood Ln 12/09/22 04/05/23 Water Distribution will be Water Tiffany Sherrane
11 installing a new main line and
services.
12 Colonial Dr Thunderbird Dr Dead End South 07/11/22 04/03/23 Utility installations and Engineering Scott Fettig
pavement replacement.
13 Crawford St Hickory St McKinney St 03/21/22 03/01/23 Utility installations and Engineering Scott Fettig
pavement replacement.
14 Crescent St Fulton St Cordell St 01/16/23 02/24/23 installing new storm line along Private Development Lee Thurmond
crescent
15 Crescent St Alice Carroll Blvd 01/18/23 03/03/23 Street Reconstruction Engineering Dustin Draper
16 Dixon Ln Comer St Cope St 01/23/23 02/24/23 Sidewalk Repair Streets Roy San Miguel
17 Eagle Dr Bernard St Beatty St 02/20/23 03/03/23 Concrete Retaining Wall Repair Streets Roy San Miguel
Elm St Pecan St Oak St 01/23/23 02/24/23 Contractor continues work on Engineering Robin Davis
the pedestrian ramps and
18 diagonal crossings
improvements.-All Way
Crossing
19 Fannin St Welch St Beatty St 02/03/23 03/10/23 Steet Reconstruction Engineering Dustion Draper
20 Gober St Broadway St Panhandle St 01/02/23 02/24/23 Mill and Overlay Streets Jeff Jones
21 Greenway Dr Thunderbird Dr Dead End South 07/11/22 04/03/23 Utility installations and Engineering Scott Fettig
pavement replacement.
22 Greenway Dr Thunderbird Dr Windsor Farms Dr 10/07/22 04/03/23 Utility installations and Engineering Scott Fettig
pavement replacement.
23 Hattie St Paisley St McKinney St 03/21/22 03/01/23 Utility installations and Engineering Scott Fettig
pavement replacement.
24 Hickory St Exposition St Ruddell St 05/02/22 03/01/23 Utility installations and Engineering Scott Fettig
pavement replacement.
25 Highland St Locust St Wainwright St 01/30/23 06/02/23 Utility installations and Engineering Scott Fettig
pavement replacement.
26 Industrial St Dead End Wye St 01/17/23 03/31/23 Utility replacement Engineering Seth Garcia
27 Jim Christal Rd Western Blvd Masch Branch Rd 04/18/22 03/17/23 Exeter PH2:Paving Jim Christal Private Development Public Kirk Winter
Works Inspections
28 Johnson St Dallas Dr Daughtry St 01/19/23 03/17/23 Atmos working on gas main on Atmos Public Works Stephany Trammell
Collins and Johnson Inspections
29 Johnson St Dallas Dr Wye St 01/17/23 03131123 Utility replacement Engineering Seth Garcia
Exported on February 17,2023 11:47:25 AM CST
Intersection • To , • , • • �- • • •. Department Contact
ate
30 Kingfisher Ln(325) Meadowlark Ln Oriole Ln 02/20/23 03/13/23 Valley Gutter Repair Streets Roy San Miguel
31 Lakewood Dr Greenway Or Carriage Hill 10/07/22 04/03/23 Utility installations and Engineering Scott Fettig
pavement replacement.
32 Masch Branch Rd Lovers Ln Hampton Rd 06/24/22 02/28/23 Bridge collapse at 3288 N. Drainage Gabriel Rodriguez
Masch Branch Rd
33 McKinney St Crawford Rd Audra Ln 05/19/22 03/01/23 Utility installations and Engineering Scott Fettig
pavement replacement.
34 Mill St Allen St Johnson St 01/17/23 03/31/23 Utility Replacement Engineering Seth Garcia
Mistywood Ln Robinwood Ln Sherwood Ln 12/09/22 04/05/23 Water Distribution will be Water Tiffany Sherrane
35 installing a new main line and
services.
Oak St Elm St Cedar St 02/13/23 02/24/23 Contractor continues to work on Engineering Robin Davis
36 the new ramps for the diagonal
crosswalks-All Way Crossing
Project
37 Oak St Crawford St Wood St 04/04/22 03/01/23 Utility installations and Engineering Scott Fettig
pavement replacement.
38 Park Access Rd(Off Bonnie Brae) Windsor Dr Riney Rd 12/15/22 07/31/23 Urbana Bonnie Brae Project: Private Development Public Jeremiah Tillman-David
Water,Sewer,Storm,Paving. Works Inspections
39 Peach St Locust St Bell Ave 02/14/23 03/01/23 Mill&Overlay Streets Jeff Jones
Robinwood Ln Kayewood Dr Emerson Ln 12/09/22 04/05/23 Water Distribution will be Water Tiffany Sherrane
40 installing a new main line and
services.
41 Savannah Trl Whitney Ct Longridge Dr 02/02/23 03/09/23 Street Reconstruction Engineering Dustin Draper
42 Smith St Johnson St Bell Ave 01/30/23 06/02/23 Utility installations and Engineering Scott Fettig
pavement replacement.
43 Uland St Rose St Railroad Ave 04/25/22 03/01/23 Utility installations and Engineering Scott Fettig
pavement replacement.
44 Westward Dr Crestmeadow St Lookout Ln 01/23/23 02/24/23 water line tie in.open cut Private Development Public Lee Thurmond
roadway. Works Inspections
45 Whitney Ct Savannah Trl Dead End East 02/02/23 03/09/23 Street Reconstruction Engineering Dustin Draper
46 Wood St McKinney St Hickory St 04/11/22 03/01/23 Utility installations and Engineering Scott Fettig
pavement replacement.
47 Woodland St Brown Or Cherrywood Ln 01/17/23 02/27/23 Street Reconstruction Engineering Dustin Draper
48 Woodrow Ln McKinney St E Troy H Lagrone Dr 02/20/23 03/03/23 Water tie in Public Works Inspections Ryan Cuba
49 Wye St Crosstimbers St Mill St 12/05/22 02/24/23 Water/Wastewater replacement Engineering Seth Garcia
and full street reconstruction
Exported on February 17,2023 11:47:25 AM CST
3 Street Closure Report: Completed Closures smartsheet
Closure End I
Street/Intersection Date Description Department Department Contact
1 Ave A Ave A Greenlee St 11/08/22 02/10/23 Street Reconstruction Engineering Dustin Draper
Bell Ave @ Senior Center 02/06 223 02/17/23 Mill and Overlay,The parking Streets Jeff Jones
2 spaces off of Bell in front of
Senior Center
Carroll Dr Oak St Mckinney St 12/09/22 02/10/23 Wastewater Collections will be Wastewater Tiffany Sherrane
3 installing a new sewer main
line.
4 Cook St Robertson St Wye St 10/24/22 02/03/23 Utility installation and roadway Engineering Seth Garcia
reconstruction
5 Fulton St University Dr Westway St 01/09/23 01/27/23 Sidewalk Repair Streets Roy San Miguel
6 Fulton St Broadway St Panhandle St 12/05/22 01/27/23 Street Reconstruction Engineering Dustin Draper
7 Fulton St Cordell St Crescent St 12/27/22 02/17/23 Street Reconstruction Engineering Dustin Draper
8 Gardenview St Brooke St Evers Pkwy 01/16/23 01/27/23 Mill&Overlay Streets Jeff Jones
9 Hickory St W(221) Piner St Ceder St 01/16/23 02/17/23 Sidewalk Repair Streets Roy San Miguel
10 McCormick St Eagle Dr Fannin St 12/27/22 02/17/23 Street Reconstruction Engineering Dustin Draper
11 McKinney St Grissom Rd Fork St 12/19/22 01/20/23 Relocating inlet,installing drive Public Works Inspections Armando Beltran
approach.
North Texas Blvd 1-35W Oak St 12/13/21 01/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.There
12 will be multiple phases of
Closures.Will not be all at one
time.
13 North Texas Blvd Oak St Hickory St 06/10/22 01/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
14 Oak St Miller St North Texas Blvd 09/30/22 01/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
Oak St Elm St Cedar St 01/23/23 02/03/23 Contractor will be performing Engineering Robin Davis
15 work on the pedestrian ramps
and diagonal crossings
improvements.
16 Robertson St Bell Ave Morse St 08/15/22 01/27/23 Utility installations and Engineering Seth Garcia
pavement replacement.
17 Serenity Way Montecito Dr Glen Falls Ln 01/03/23 02/17/23 Street Panel and Sidewalk Streets Roy San Miguel
repair
18 Stella St North Texas Blvd Bonnie Brae St 10/29/21 01/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
19 Thistle Hill Cheek St Cul-de-sac 01/03/23 01/19/23 Sidewalk Repair Streets Roy San Miguel
20 Wayne St Boyd St Mozingo Rd 11/14/22 02/10/23 Street Reconstruction Engineering Dustin Draper
21 Woodrow Ln Morse St McKinney St 12/08/22 02/03/23 Water tie in,Right turn lane and Public Works Inspections Armando Beltran
approach construction.
Exported on February 17,2023 11:47:33 AM CST