2023/03/03 - Street Closure Report 1 Street Closure Report: Upcoming Closures smartsheet
SCR Mar 6th - 12th
Street/Intersection From To Department Department Contact
1 Bradshaw St Prairie St E Sycamore St 03/13/23 07/17/23 Utility installations and pavement replacement. Engineering Scott Fettig
2 Eufemia or Henmalinda or Beatriz or 03/13/23 04/14/23 Sidewalk Repair Streets Roy San Miguel
3 Riesling or Rhone or Merlot or 03/20/23 04/28/23 Concrete Panel and Sidewalk Repair Streets Roy San Miguel
4 Sycamore St Exposition St Crawford St S 03/13/23 07/17/23 Utility installations and pavement replacement. Engineering Scott Fettig
5 Wainwright St Highland St E Prairie St E 03/13/23 04/07/23 Utility installations and pavement replacement. Engineering Scott Fettig
Exported on March 3,2023 11:14:59 AM CST
2 Street Closure Report: Current Closures smartsheet
1�� i Closure Start Closure End Description Department Department Contact
Street/Intersection Date Date
1 Allen St Mill St Wye St 12/12/22 03/17/23 Utility replacement and roadway Engineering Seth Garcia
reconstruction
2 Angelina Bend Dr San Gabriel Or Angelina Bend Dr(1416) 01/17/23 03/24/23 Street Reconstruction Engineering Dustin Draper
3 Atlas Dr Hercules Ln Redstone Rd 10/17/22 03/24/23 Reconstruct Streets Jeremy Wilks
4 Augusta Or Colonial Dr Augusta Or(2900) 07/11/22 04/03/23 Utility installations and Engineering Scott Fettig
pavement replacement.
5 Ave A Ave A Greenlee St 11/08/22 03/10/23 Street Reconstruction Engineering Dustin Draper
6 Avenue S Prairie St E Dead End South 03/06/23 05/20/23 Utility installations and Engineering Scott Fettig
pavement replacement.
7 Bailey St Willson St Dead End South 01/30/23 06/02/23 Utility installations and Engineering Scott Fettig
pavement replacement.
Bonnie Brae St Scripture Roundabout Oak St 02/09/23 03/31/23 Contractor is performing Engineering Robin Davis
subgrade and pavement
8 repairs,. this will be a rolling
closure while sections are
repaired. traffic is reduced
from 4 lanes to 2 in this area.
9 Bonnie Brae St Riney Rd Windsor Dr 03/10/23 07/31/23 Urbana at Bonnie Brae:Public Public Works Inspections Jeremiah Tillman-David
Paving
10 Boxwood Or Plumbago Dr Daisy Dr 01/03/23 03/24/23 Street Panel and Sidewalk Streets Roy San Miguel
Repair
11 Bradshaw St Hickory St McKinney St 03/21/22 05/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
12 Bradshaw St Wilson St Prairie St East 01/30/23 06/02/23 Utility installations and Engineering Scott Fettig
pavement replacement.
13 Brook Hollow Or Greenway Dr Carriage Hill 10/07/22 04/03/23 Utility installations and Engineering Scott Fettig
pavement replacement.
Carroll Dr Oak St Mckinney St 12/09/22 04/13/23 Wastewater Collections will be Wastewater Tiffany Sherrane
14 installing a new sewer main
line.
Carroll Dr Oak St Mckinney St 12/09/22 04/13/23 Wastewater Collections will be Wastewater Tiffany Sherrane
15 installing a new sewer main
line.
16 Castle Pines Ln Burr Oak Or @ Intersection 02/27/23 03/17/23 Concrete Street Panel repair Streets Roy San Miguel
Clover Ln Robinwood Ln Glenwood Ln 12/09/22 04/05/23 Water Distribution will be Water Tiffany Sherrane
17 installing a new main line and
services.
18 Colonial Dr Thunderbird Or Dead End South 07/11/22 04/03/23 Utility installations and Engineering Scott Fettig
pavement replacement.
19 Crawford St Hickory St McKinney St 03/21/22 05/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
20 Crescent St Fulton St Cordell St 01/16/23 03/10/23 installing new storm line along Private Development Lee Thurmond
crescent
21 Crescent St Alice Carroll Blvd 01/18/23 03/31/23 Street Reconstruction Engineering Dustin Draper
Elm St Pecan St Oak St 01/23/23 03/17/23 Contractor continues work on Engineering Robin Davis
the pedestrian ramps and
22 diagonal crossings
improvements.-All Way
Crossing
23 Fannin St Welch St Beatty St 02/03/23 03/31/23 Steet Reconstruction Engineering Dustin Draper
24 Greenway Dr Thunderbird Or Dead End South 07/11/22 04/03/23 Utility installations and Engineering Scott Fettig
pavement replacement.
25 Greenway Dr Thunderbird Or Windsor Farms Dr 10/07/22 04/03/23 Utility installations and Engineering Scott Fettig
pavement replacement.
Exported on March 3,2023 11:15:05 AM CST
Street/Intersection From To Closure Start Description Department Department Contact
Date
26 Hattie St Paisley St McKinney St 03/21/22 05/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
27 Hickory St Exposition St Ruddell St 05/02/22 05/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
28 Highland St Locust St Wainwright St 01/30/23 06/02/23 Utility installations and Engineering Scott Fettig
pavement replacement.
29 Industrial St Dead End Wye St 01/17/23 03/31/23 Utility replacement Engineering Seth Garcia
30 Jim Christal Rd Western Blvd Masch Branch Rd 04/18/22 03/17/23 Exeter PH2:Paving Jim Christal Private Development Public Kirk Winter
Works Inspections
31 Johnson St Dallas Dr Daughtry St 01/19/23 03/17/23 Atmos working on gas main on Atmos Public Works Stephany Trammell
Collins and Johnson Inspections
32 Johnson St Dallas Dr Wye St 01/17/23 03/31/23 Utility replacement Engineering Seth Garcia
33 Lakewood Dr Greenway Dr Carriage Hill 10/07/22 04/03/23 Utility installations and Engineering Scott Fettig
pavement replacement.
34 Masch Branch Rd Lovers Ln Hampton Rd 06/24/22 03/14/23 Bridge collapse at 3288 N. Drainage Gabriel Rodriguez
Masch Branch Rd
35 May St Henderson Dr Autumn Oak Dr 02/27/23 04/28/23 Street Reconstruction Engineering Dustin Draper
36 McCormick St Eagle Dr Fannin St 12/27/22 03/10/23 Street Reconstruction Engineering Dustin Draper
37 McKinney St Crawford Rd Audra Ln 05/19/22 05/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
38 Mill St Allen St Johnson St 01/17/23 03/31/23 Utility Replacement Engineering Seth Garcia
39 Mill St Allen St Robertson St 02/27/23 05/31/23 Utility installation and roadway Engineering Seth Garcia
reconstruction
Mistywood Ln Robinwood Ln Sherwood Ln 12/09/22 04/05/23 Water Distribution will be Water Tiffany Sherrane
40 installing a new main line and
services.
North Texas Blvd 1-35 E Service Road Highland Park 02/17/23 03/31/23 Widening&Reconstruction, Engineering Robin Davis
Traffic Signal Upgrade. traffic
41 from 135 will need to use Bonnie
Brae Street. project is limited to
one-way traffic from Highland
Park to 135E.
Oak St Elm St Cedar St 02/13/23 03/17/23 Contractor is working on the Engineering Robin Davis
42 diagonal crossing on the NE
comer of Oak&Elm. -All Way
Crossing Project
43 Oak St Crawford St Wood St 04/04/22 05/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
44 Palamino Ct Mustang Dr Dead End West 03/06/23 03/31/23 Sidewalk Repair Streets Roy San Miguel
45 Park Access Rd(Off Bonnie Brae) Windsor Dr Riney Rd 12/15/22 07/31/23 Urbana Bonnie Brae Project: Private Development Public Jeremiah Tillman-David
Water,Sewer,Storm,Paving. Works Inspections
Robinwood Ln Kayewood Dr Emerson Ln 12/09/22 04/05/23 Water Distribution will be Water Tiffany Sherrane
46 installing a new main line and
services.
47 Savannah Trl Whitney Ct Longridge Dr 02/02/23 03/24/23 Street Reconstruction Engineering Dustin Draper
48 Smith St Johnson St Bell Ave 01/30/23 06/02/23 Utility installations and Engineering Scott Fettig
pavement replacement.
49 Smith St Dallas Dr(Hwy 77) Hill St 03/06/23 06/07/23 Utility installations and Engineering Scott Fettig
pavement replacement.
50 State School Rd 1-35E Bowie St 03/06/23 04/06/23 Utilities relocation along East Engineering Aaron Skinner
side of State School Rd
51 Wayne St Boyd St Mozingo Rd 11/14/22 03/10/23 Street Reconstruction Engineering Dustin Draper
52 Westward Dr Crestmeadow St Lookout Ln 01/23/23 03/10/23 water line tie in.open cut Private Development Public Lee Thurmond
roadway. Works Inspections
53 Whitney Ct Savannah Trl Dead End East 02/02/23 03/31/23 Street Reconstruction Engineering Dustin Draper
Exported on March 3,2023 11:15:05 AM CST
Intersection • To ,ate Closure , • • Description Department Department
54 Wood St McKinney St Hickory St 04/11/22 05/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
55 Woodland St Brown Dr Cherrywood Ln 01/17/23 03/31123 Street Reconstruction Engineering Dustin Draper
56 Woodrow Ln McKinney St E Troy H Lagrone Dr 02/20/23 03/17/23 Water tie in Public Works Inspections Ryan Cuba
Exported on March 3,2023 11:15:05 AM CST
3 Street Closure Report: Completed Closures smartsheet
Street/Intersection From Closure Start Closure End Description D Department Contact
Date Date
1 Barthold Rd railroad crossing @ Masch Branch Rd 02/25/23 02/25/23 Railroad maintenance for KCS Darryl Ware
Bell Ave @ Senior Center 02/06/23 02/17/23 Mill and Overlay,The parking Streets Jeff Jones
2 spaces off of Bell in front of
Senior Center
3 Bell Ave Mingo Rd 300'North 02/20/23 02/22/23 Mill and Overlay of Senior Jeff Jones
Center parking along bell
4 Cook St Robertson St Wye St 10/24/22 02/03/23 Utility installation and roadway Engineering Seth Garcia
reconstruction
5 Dixon Ln Comer St Cope St 01/23/23 03/02/23 Sidewalk Repair Streets Roy San Miguel
6 Eagle Dr Bernard St Beatty St 02/20/23 03/02/23 Concrete Retaining Wall Repair Streets Roy San Miguel
7 Elm Bottom Cir Sherman Dr city limits 02/23/23 02/28/23 Overlay Streets Jeff Jones
8 Fulton St Cordell St Crescent St 12/27/22 02/17/23 Street Reconstruction Engineering Dustin Draper
9 Gober St Broadway St Panhandle St 01/02/23 02/24/23 Mill and Overlay Streets Jeff Jones
10 Hickory St W(221) Piner St Ceder St 01/16/23 02/17/23 Sidewalk Repair Streets Roy San Miguel
11 Kingfisher Ln(325) Meadowlark Ln Oriole Ln 02/20/23 03/02/23 Valley Gutter Repair Streets Roy San Miguel
Oak St Elm St Cedar St 01/23/23 02/03/23 Contractor will be performing Engineering Robin Davis
12 work on the pedestrian ramps
and diagonal crossings
improvements.
13 Oak St W railroad crossing by Precision Dr 02/25/23 02/25/23 Railroad maintenance for KCS Darryl Ware
14 Peach St Locust St Bell Ave 02/14/23 03/01/23 Mill&Overlay Streets Jeff Jones
15 Serenity Way Montecito Dr Glen Falls Ln 01/03/23 02/17/23 Street Panel and Sidewalk Streets Roy San Miguel
repair
16 Uland St Rose St Railroad Ave 04/25/22 03/01/23 Utility installations and Engineering Scott Fettig
pavement replacement.
17 Woodrow Ln Morse St McKinney St 12/08/22 02/03/23 Water tie in,Right turn lane and Public Works Inspections Armando Beltran
approach construction.
18 Wye St Crosstimbers St Mill St 12/05/22 02/24/23 Water/wastewater replacement Engineering Seth Garcia
and full street reconstruction
Exported on March 3,2023 11:15:16 AM CST