2023/03/10 - Street Closure Report 1 Street Closure Report: Upcoming Closures smartsheet SCR Mar 13th - 19th Street/Intersection FFr..- Department Department Contact 1 Cordaro Ct Mira Vista or End of cul-de-sac 03/20/23 04/07/23 Mill&overlay curb and sidewalk Streets Jeff Jones 2 Riesling Dr Rhone or Merlot or 03/20/23 04/28/23 Concrete Panel and Sidewalk Repair Streets Roy San Miguel Exported on March 10,2023 10:33:10 AM CST 2 Street Closure Report: Current Closures smartsheet I 1lAllllllllllllllll Closure Start Closure End Street/Intersection 11 � I Date Date Description Department Department Contact 1 Allen St Mill St Wye St 12/12/22 03/17/23 Utility replacement and roadway Engineering Seth Garcia reconstruction 2 Angelina Bend 1416 Angelina Bend Sandy Creek 03/13/23 04/28/23 Street Reconstruction Engineering Dustin Draper 3 Angelina Bend Dr San Gabriel Or Angelina Bend Dr(1416) 01/17/23 04/28/23 Street Reconstruction Engineering Dustin Draper 4 Atlas Dr Hercules Ln Redstone Rd 10/17/22 03/24/23 Reconstruct Streets Jeremy Wilks 5 Augusta Or Colonial Dr Augusta Or(2900) 07/11/22 04/03/23 Utility installations and Engineering Scott Fettig pavement replacement. 6 Avenue S Prairie St E Dead End South 03/06/23 05/20/23 Utility installations and Engineering Scott Fettig pavement replacement. 7 Bailey St Willson St Dead End South 01/30/23 06/02/23 Utility installations and Engineering Scott Fettig pavement replacement. Bonnie Brae St Scripture Roundabout Oak St 02/09/23 03/31/23 Contractor is performing Engineering Robin Davis subgrade and pavement 8 repairs,. this will be a rolling closure while sections are repaired. traffic is reduced from 4 lanes to 2 in this area. 9 Bonnie Brae St Riney Rd Windsor Dr 03/10/23 07/31/23 Urbana at Bonnie Brae:Public Public Works Inspections Jeremiah Tillman-David Paving 10 Boxwood Or Plumbago Dr Daisy Dr 01/03/23 03/24/23 Street Panel and Sidewalk Streets Roy San Miguel Repair 11 Bradshaw St Hickory St McKinney St 03/21/22 05/31/23 Utility installations and Engineering Scott Fettig pavement replacement. 12 Bradshaw St Wilson St Prairie St East 01/30/23 06/02/23 Utility installations and Engineering Scott Fettig pavement replacement. 13 Bradshaw St Prairie St E Sycamore St 03/13/23 07/17/23 Utility installations and Engineering Scott Fettig pavement replacement. 14 Brook Hollow Or Greenway Dr Carriage Hill 10/07/22 04/03/23 Utility installations and Engineering Scott Fettig pavement replacement. Carroll Dr Oak St Mckinney St 12/09/22 04/13/23 Wastewater Collections will be Wastewater Tiffany Sherrane 15 installing a new sewer main line. Carroll Dr Oak St Mckinney St 12/09/22 04/13/23 Wastewater Collections will be Wastewater Tiffany Sherrane 16 installing a new sewer main line. 17 Castle Pines Ln Burr Oak Or @ Intersection 02/27/23 03/17/23 Concrete Street Panel repair Streets Roy San Miguel Clover Ln Robinwood Ln Glenwood Ln 12/09/22 04/05/23 Water Distribution will be Water Tiffany Sherrane 18 installing a new main line and services. 19 Colonial Dr Thunderbird Or Dead End South 07/11/22 04/03/23 Utility installations and Engineering Scott Fettig pavement replacement. 20 Crawford St Hickory St McKinney St 03/21/22 05/31/23 Utility installations and Engineering Scott Fettig pavement replacement. 21 Crescent St Alice Carroll Blvd 01/18/23 03/31/23 Street Reconstruction Engineering Dustin Draper Elm St Pecan St Oak St 01/23/23 03/17/23 Contractor continues work on Engineering Robin Davis the pedestrian ramps and 22 diagonal crossings improvements.-All Way Crossing 23 Eufemia Or Hermalinda Dr Beatriz Dr 03/13/23 04/14/23 Sidewalk Repair Streets Roy San Miguel 24 Fannin St Welch St Beatty St 02/03/23 03/31/23 Steet Reconstruction Engineering Dustin Draper 25 Greenway Dr Thunderbird Or Dead End South 07/11/22 04I03123 Utility installations and Engineering Scott Fettig pavement replacement. 26 Greenway Dr Thunderbird Or Windsor Farms Dr 10/07/22 04/03/23 Utility installations and Engineering Scott Fettig pavement replacement. Exported on March 10,2023 10:34:57 AM CST Street/Intersection From Closure Start Description Department Department Contact I— Date 27 Hattie St Paisley St McKinney St 03/21/22 05/31/23 Utility installations and Engineering Scott Fettig pavement replacement. 28 Hickory Creek Rd Riverpass FM 1830 03/13/23 12/31/24 Bridge Installation Engineering Dustin Draper 29 Hickory St Exposition St Ruddell St 05/02/22 05/31/23 Utility installations and Engineering Scott Fettig pavement replacement. 30 Highland St Locust St Wainwright St 01/30/23 06/02/23 Utility installations and Engineering Scott Fettig pavement replacement. 31 Industrial St Dead End Wye St 01/17/23 03/31/23 Utility replacement Engineering Seth Garcia 32 Jim Christal Rd Western Blvd Masch Branch Rd 04/18/22 03/17/23 Exeter PH2:Paving Jim Christal Private Development Public Kirk Winter Works Inspections 33 Johnson St Dallas Dr Daughtry St 01/19/23 03/17/23 Atmos working on gas main on Atmos Public Works Stephany Trammell Collins and Johnson Inspections 34 Johnson St Dallas Dr Wye St 01/17/23 03/31/23 Utility replacement Engineering Seth Garcia 35 Lakewood Dr Greenway Dr Carriage Hill 10/07/22 04/03/23 Utility installations and Engineering Scott Fettig pavement replacement. 36 Masch Branch Rd Lovers Ln Hampton Rd 06/24/22 03/21/23 Bridge collapse at 3288 N. Drainage Gabriel Rodriguez Masch Branch Rd 37 May St Henderson Dr Autumn Oak Dr 02/27/23 04/28/23 Street Reconstruction Engineering Dustin Draper 38 McKinney St Crawford Rd Audra Ln 05/19/22 05/31/23 Utility installations and Engineering Scott Fettig pavement replacement. 39 Mill St Allen St Johnson St 01/17/23 03/31/23 Utility Replacement Engineering Seth Garcia 40 Mill St Allen St Robertson St 02/27/23 05/31/23 Utility installation and roadway Engineering Seth Garcia reconstruction Mistywood Ln Robinwood Ln Sherwood Ln 12/09/22 04/05/23 Water Distribution will be Water Tiffany Sherrane 41 installing a new main line and services. North Texas Blvd 1-35 E Service Road Highland Park 02/17/23 03/31/23 Widening&Reconstruction, Engineering Robin Davis Traffic Signal Upgrade. traffic 42 from 135 will need to use Bonnie Brae Street. project is limited to one-way traffic from Highland Park to 135E. Oak St Elm St Cedar St 02/13/23 03/17/23 Contractor is working on the Engineering Robin Davis 43 diagonal crossing on the NE comer of Oak&Elm. -All Way Crossing Project 44 Oak St Crawford St Wood St 04/04/22 05/31/23 Utility installations and Engineering Scott Fettig pavement replacement. 45 Palamino Ct Mustang Dr Dead End West 03/06/23 03/31/23 Sidewalk Repair Streets Roy San Miguel 46 Park Access Rd Windsor Dr Riney Rd 12/15/22 07/31/23 Urbana Bonnie Brae Project: Private Development Public Jeremiah Tillman-David Water,Sewer,Storm,Paving. Works Inspections Robinwood Ln Kayewood Dr Emerson Ln 12/09/22 04/05/23 Water Distribution will be Water Tiffany Sherrane 47 installing a new main line and services. 48 Savannah Trl Whitney Ct Longridge Dr 02/02/23 04/28/23 Street Reconstruction Engineering Dustin Draper 49 Smith St Johnson St Bell Ave 01/30/23 06/02/23 Utility installations and Engineering Scott Fettig pavement replacement. 50 Smith St Dallas Dr(Hwy 77) Hill St 03/06/23 06/07/23 Utility installations and Engineering Scott Fettig pavement replacement. 51 State School Rd 1-35E Bowie St 03/06/23 04/06/23 Utilities relocation along East Engineering Aaron Skinner side of State School Rd 52 Sycamore St Exposition St Crawford St S 03/13/23 07/17/23 Utility installations and Engineering Scott Fettig pavement replacement. 53 Wainwright St Highland St E Prairie St E 03/13/23 04/07/23 Utility installations and Engineering Scott Fettig pavement replacement. Exported on March 10,2023 10:34:57 AM CST Street/Intersection From To Closure Start Description Department Department Contact Date M, 54 Wayne St Boyd St Mozingo Rd 11/14/22 03/24/23 Street Reconstruction Engineering Dustin Draper 55 Westward Dr Crestmeadow St Lookout Ln 01/23/23 03/17/23 water line tie in.open cut Private Development Public Lee Thurmond roadway. Works Inspections 56 Whitney Ct Savannah Trl Dead End East 02/02/23 04/28/23 Street Reconstruction Engineering Dustin Draper 57 Wood St McKinney St Hickory St 04/11/22 05/31/23 Utility installations and Engineering Scott Fettig pavement replacement. 58 Woodland St Brown Dr Cherrywood Ln 01/17/23 03/31/23 Street Reconstruction Engineering Dustin Draper 59 Woodrow Ln McKinney St E Troy H Lagrone Dr 02/20/23 03/17/23 Water tie in Public Works Inspections Ryan Cuba Exported on March 10,2023 10:34:57 AM CST 3 Street Closure Report: Completed Closures smartsheet Closure End Description Department Department Contact Street/Intersection Date 1 Ave A Ave A Greenlee St 03/10/23 Street Reconstruction Engineering Dustin Draper 2 Barthold Rd railroad crossing @ Masch Bra7-7 02/25/23 Railroad maintenance for KCS Darryl Ware Bell Ave @ Senior Center 02/17/23 Mill and Overlay,The parking Streets Jeff Jones 3 spaces off of Bell in front of Senior Center 4 Bell Ave Mingo Rd 300'North 02/20/23 02/22/23 Mill and Overlay of Senior Jeff Jones Center parking along bell 5 Crescent St Fulton St Cordell St 01/16/23 03/10/23 installing new storm line along Private Development Lee Thurmond crescent 6 Dixon Ln Comer St Cope St 01/23/23 03/02/23 Sidewalk Repair Streets Roy San Miguel 7 Eagle Dr Bernard St Beatty St 02/20/23 03/02/23 Concrete Retaining Wall Repair Streets Roy San Miguel 8 Elm Bottom Cir Sherman Dr city limits 02/23/23 02/28/23 Overlay Streets Jeff Jones 9 Fulton St Cordell St Crescent St 12/27/22 02/17/23 Street Reconstruction Engineering Dustin Draper 10 Gober St Broadway St Panhandle St 01/02/23 02/24/23 Mill and Overlay Streets Jeff Jones 11 Hickory St W(221) Piner St Ceder St 01/16/23 02/17/23 Sidewalk Repair Streets Roy San Miguel 12 Kingfisher Ln(325) Meadowlark Ln Oriole Ln 02/20/23 03/02/23 Valley Gutter Repair Streets Roy San Miguel 13 McCormick St Eagle Or Fannin St 12/27/22 03/10/23 Street Reconstruction Engineering Dustin Draper 14 Oak St W railroad crossing by Precision Or 02/25/23 02/25/23 Railroad maintenance for KCS Darryl Ware 15 Peach St Locust St Bell Ave 02/14/23 03/01/23 Mill&Overlay Streets Jeff Jones 16 Serenity Way Montecito Dr Glen Falls Ln 01/03/23 02/17/23 Street Panel and Sidewalk Streets Roy San Miguel repair 17 Uland St Rose St Railroad Ave 04/25/22 03/01/23 Utility installations and Engineering Scott Fettig pavement replacement. 18 Wye St Crosstimbers St Mill St 12/05/22 02/24/23 Water/wastewater replacement Engineering Seth Garcia and full street reconstruction Exported on March 10,2023 10:33:38 AM CST