2023/04/07 - Street Closure Report 1 Street Closure Report: Upcoming Closures smartsheet
SCR Apr 10th - 16th
Street/Intersection From To Closure End Description Department Department Contact
Date
1 Avenue H Stella St Hickory St 04/17/23 04/28/23 Installing underground utilities open cut roadway Public Works Inspections Lee Thurmond
2 Clubhouse Dr Tuscan Hills Cir Paint Or 04/17/23 05/19/23 Street Panel and Sidewalk Repair Streets Roy San Miguel
3 Oak St Mounts Ave Fulton St 04/18/23 05/31/23 Wastewater Collections will be installing a new Wastewater Tiffany Sherrane
sewer main lines and services.
4 Oak St Thomas St Bonnie Brae St 04/17/23 04/21/23 Installing screen walls at the substation Public Works Inspections Lee Thurmond
5 Ottawa Or Great Bear Ln Wind River Ln 05/15/23 06/23/23 Street Panel and Sidewalk Repair Streets Roy San Miguel
61 Riesling Or Rhone Dr Merlot Or 05/01/23 06/02/23 Concrete Panel and Sidewalk Repair Streets Roy San Miguel
Exported on April 7,2023 10:54:10 AM CDT
2 Street Closure Report: Current Closures smartsheet
_WWF,0M Da"o- Closure End Description partment ff Department Contact
Street/Intersection tsure Start De
e Date
1 Angelina Bend Dr Angelina Bend Dr(1416) Sandy Creek Dr 03/13/23 i 05/05/23 Street Reconstruction Engineering Dustin Draper
2 Angelina Bend Dr San Gabriel Dr Angelina Bend Dr(1416) 01/17/23 05/05/23 Street Reconstruction Engineering Dustin Draper
3 Augusta Dr Colonial Dr Augusta Dr(2900) 07/11/22 07/10/23 Utility installations and Engineering Scott Fettig
pavement replacement.
4 Avenue S Prairie St E Dead End South 03/06/23 05/20/23 Utility installations and Engineering Scott Fettig
pavement replacement.
5 Bailey St Willson St Dead End South 01/30/23 06/02/23 Utility installations and Engineering Scott Fettig
pavement replacement.
6 Bonnie Brae St Riney Rd Windsor Dr 03/10/23 07/31/23 Urbana at Bonnie Brae:Public Public Works Inspections Jeremiah Tillman-David
Paving
7 Bradshaw St Hickory St McKinney St 03/21/22 05/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
8 Bradshaw St Wilson St Prairie St E 01/30/23 06/02/23 Utility installations and Engineering Scott Fettig
pavement replacement.
9 Bradshaw St Prairie St E Sycamore St 03/13/23 07/17/23 Utility installations and Engineering Scott Fettig
pavement replacement.
10 Brook Hollow Dr Greenway Dr Carriage Hill Rd 10/07/22 07/10/23 Utility installations and Engineering Scott Fettig
pavement replacement.
11 Brown Dr Roberts Woodland 03/28/23 05/19/23 Street Reconstruction Engineering Dustin Draper
Carroll Dr Oak St Mckinney St 12/09/22 04/17/23 Wastewater Collections will be Wastewater Tiffany Sherrane
12 installing a new sewer main
line.
Clover Ln Robinwood Ln Glenwood Ln 12/09/22 06/01/23 Water Distribution will be Water Tiffany Sherrane
13 installing a new main line and
services.
14 Colonial Dr Thunderbird Dr Dead End South 07/11/22 07/10/23 Utility installations and Engineering Scott Fettig
pavement replacement.
15 Crawford St Hickory St McKinney St 03/21/22 05/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
16 Elm St Oak St Hickory St 03/20/23 04/21/23 Installation of Diagonal Engineering Robin Davis
Crosswalks/Ramps
17 Eufemia Dr Hermalinda Dr Beatriz Dr 03/13/23 04/29/23 Sidewalk Repair Streets Roy San Miguel
18 Greenway Dr Thunderbird Dr Dead End South 07/11/22 07/10/23 Utility installations and Engineering Scott Fettig
pavement replacement.
19 Greenway Dr Thunderbird Dr Windsor Farms Dr 10/07/22 07/10/23 Utility installations and Engineering Scott Fettig
pavement replacement.
20 Hattie St Paisley St McKinney St 03/21/22 05/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
21 Hickory Creek Rd Riverpass Dr FM 1830 03/13/23 12/31/24 Bridge Installation Engineering Dustin Draper
22 Hickory St Locust St Pecan St 03/20/23 04/21/23 Installation of Diagonal Engineering Robin Davis
Crosswalks/Ramps
23 Hickory St Exposition St Ruddell St 05/02/22 05/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
24 Highland St Locust St Wainwright St 01/30/23 06/02/23 Utility installations and Engineering Scott Fettig
pavement replacement.
25 Industrial St Dead End Wye St 01/17/23 04/21/23 Utility replacement Engineering Seth Garcia
26 Jim Christal Rd Western Blvd Masch Branch Rd 04/18/22 04/21/23 Exeter PH2:Paving Jim Christal Private Development Public Kirk Winter
Works Inspections
27 Johnson St Dallas Dr Daughtry St 01/19/23 04/14/23 Atmos working on gas main on Atmos Public Works Stephany Trammell
Collins and Johnson Inspections
28 Johnson St Dallas Dr Wye St 01/17/23 04/21/23 Utility replacement Engineering Seth Garcia
29 Lakewood Dr Greenway Dr Carriage Hill Rd 10/07/22 07/10/23 Utility installations and Engineering Scott Fettig
pavement replacement.
30 Maddox St Prairie St E Dead End 03/20/23 07/10/23 Utility installations and Engineering Scott Fettig
pavement replacement.
Exported on April 7,2023 10:54:18 AM CDT
Street/Intersection From To Description Department Department Contact
31 May St Henderson Dr Autumn Oak Dr 02/27/23 04/28/23 Street Reconstruction Engineering Dustin Draper
32 Mayhill Rd @ Spencer Rd 03/28/23 04/30/23 Water main tie-in and turn lane Public Works Inspections Ryan Cuba
addition
33 McKinney St Crawford Rd Audra Ln 05/19/22 05/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
34 Mill St Allen St Johnson St 01/17/23 05/26/23 Utility Replacement Engineering Seth Garcia
35 Mill St Allen St Robertson St 02/27/23 05/31/23 Utility installation and roadway Engineering Seth Garcia
reconstruction
Mistywood Ln Robinwood Ln Sherwood Ln 12/09/22 06/15/23 Water Distribution will be Water Tiffany Sherrane
36 installing a new main line and
services.
37 Myrtle St Eagle Dr Fort Worth Dr 04/05/23 04/26/23 Relocating gas main and Atmos Zabdiel Mota
service lines.
North Texas Blvd 1-35 E Service Road Highland Park Rd 02/17/23 04/28/23 Contractor will be working the Engineering Robin Davis
Traffic Signal Upgrade and
switchover. traffic from 135 will
38 need to use Bonnie Brae Street.
project is limited to one-way
traffic from Highland Park to
135E.
39 Oak St Crawford St Wood St 04/04/22 05/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
40 Panhandle St Malone St Aileen St 04/03/23 04/30/23 Driveway work and Street Engineering Dustin Draper
Resurfacing
41 Park Access Rd Windsor Dr Riney Rd 12/15/22 07/31/23 Urbana Bonnie Brae Project: Private Development Public Jeremiah Tillman-David
Water,Sewer,Storm,Paving. Works Inspections
Robinwood Ln Kayewood Dr Emerson Ln 12/09/22 04/28/23 Water Distribution will be Water Tiffany Sherrane
42 installing a new main line and
services.
43 Savannah Trl Whitney Ct Longridge Dr 02/02/23 04/28/23 Street Reconstruction Engineering Dustin Draper
44 Smith St Johnson St Bell Ave 01/30/23 06/02/23 Utility installations and Engineering Scott Fettig
pavement replacement.
45 Smith St Dallas Dr(Hwy 77) Hill St 03/06/23 06/07/23 Utility installations and Engineering Scott Fettig
pavement replacement.
46 State School Rd 1-35E Bowie St 03/06/23 04/27/23 Utilities relocation along East Engineering Aaron Skinner
side of State School Rd
47 Sycamore St Exposition St Crawford St S 03/13/23 07/17/23 Utility installations and Engineering Scott Fettig
pavement replacement.
48 Vista Verde st Montecito West to dead end 04/06/23 04/14/23 Mill and Overlay Streets Jeff Jones
49 Wainwright St Highland St E Prairie St E 03/13/23 05/12/23 Utility installations and Engineering Scott Fettig
pavement replacement.
50 Whitney Ct Savannah Trl Dead End East 02/02/23 04/28/23 Street Reconstruction Engineering Dustin Draper
51 Wood St McKinney St Hickory St 04/11/22 05/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
52 Woodland St Brown Cherrywood 03/01/23 05/19/23 Street Reconstruction Engineering Dustin Draper
53 Woodrow Ln McKinney St E Troy H Lagrone Dr 02/20/23 04/22/23 Water tie in Public Works Inspections Ryan Cuba
Exported on April 7,2023 10:54:18 AM CDT
3 Street Closure Report: Completed Closures smartsheet
Street/Intersection From MINEW-T Closure Start Closure End
Date Date Description Department Department Contact
1 Allen St Mill St Wye St 12/12/22 03/17/23 Utility replacement and roadway Engineering Seth Garcia
reconstruction
2 Atlas Dr Hercules Ln Redstone Rd 10/17/22 03/24/23 Reconstruct Streets Jeremy Wilks
3 Ave A Ave A Greenlee St 11/08/22 03/10/23 Street Reconstruction Engineering Dustin Draper
Bonnie Brae St Scripture St(Roundabout) Oak St 03/27/23 04/07/23 Contractor is performing Engineering Robin Davis
subgrade and pavement
repairs,. Northbound traffic will
4 be moved to the inside
Southbound lane. Southbound
lanes will be converted to two-
way traffic until the northbound
lanes are repaired.
5 Boxwood Dr Plumbago Dr Daisy Dr 01/03/23 03/31/23 Street Panel and Sidewalk Streets Roy San Miguel
Repair
6 Castle Pines Ln Burr Oak Dr @ Intersection 02/27/23 03/16/23 Concrete Street Panel repair Streets Roy San Miguel
7 Cordero Ct Mira Vista Dr End of cul-de-sac 03/20/23 04/07/23 Mill&overlay curb and Streets Jeff Jones
sidewalk
8 Crescent St Fulton St Cordell St 01/16/23 03/10/23 installing new storm line along Private Development Lee Thurmond
crescent
9 Crescent St Alice St Carroll Blvd 01/18/23 03/31/23 Street Reconstruction Engineering Dustin Draper
Elm St Pecan St Oak St 01/23/23 03/17/23 Contractor continues work on Engineering Robin Davis
the pedestrian ramps and
10 diagonal crossings
improvements.-All Way
Crossing
11 Fannin St Welch St Beatty St 02/03/23 03/31/23 Steel Reconstruction Engineering Dustin Draper
12 Masch Branch Rd Lovers Ln Hampton Rd 06/24/22 03/31/23 Bridge collapse at 3288 N. Drainage Gabriel Rodriguez
Masch Branch Rd
13 McCormick St Eagle Dr Fannin St 12/27/22 03/10/23 Street Reconstruction Engineering Dustin Draper
Oak St Elm St Cedar St 02/13/23 03/17/23 Contractor is working on the Engineering Robin Davis
14 diagonal crossing on the NE
corner of Oak&Elm. -All Way
Crossing Project
15 Palamino Ct Mustang Dr Dead End West 03/06/23 03/31/23 Sidewalk Repair Streets Roy San Miguel
16 Wayne St Boyd St Mozingo Rd 11/14/22 03/24/23 Street Reconstruction Engineering Dustin Draper
17 Westward Dr Crestmeadow St Lookout Ln 01/23/23 03/22/23 water line tie in.open cut Private Development Public Lee Thurmond
roadway. Works Inspections
18 Woodland St Brown Dr Cherrywood Ln 01/17/23 03/31/23 Street Reconstruction Engineering Dustin Draper