2023/06/23 - Street Closure Report 1 Street Closure Report: Upcoming Closures smartsheet
SCR June 26th - July 2nd
Street/Intersection Department Contact
1 Green Oaks St(2300) Dunes St Cooper Branch 07/05/23 07/21/23 Valley Gutter Repair Streets Roy San Miguel
2 Industrial St Bell St Mulberry St 07/05/23 08/29/23 Utility installation Engineering Seth Garcia
3 Maple St Carroll Blvd Elm St 07/05/23 08/31/23 Utility installations and pavement replacement. Engineering Scott Fettig
4 Myrtle St Maple St Highland St 07/05/23 08/31/23 Utility installations and pavement replacement. Scott Fettig
5 Myrtle St. Eagle Dr Maple St 07/05/23 08/31/23 Utility installations and pavement replacement. Engineering Scott Fettig
6 Oak St Mounts Ave Fulton St 06/30/23 07/28/23 Wastewater Collections will be installing a new Wastewater Tiffany Sherrane
sewer main lines and services.
7 Pierce St Maple St Highland St 07/05/23 08/31/23 Utility installations and pavement replacement. Scott Fettig
8 Stallion St Lakeview Blvd Oak Creek Ln 07/03/23 08/11/23 Street Concrete Panel Repair Streets Roy San Miguel
Exported on June 23,2023 11:47:23 AM CDT
2 Street Closure Report: Current Closures smartsheet
Street/Intersection From r To ulosure a Description Department Ir Department Contact
Date I
1 Augusta Dr Colonial Dr Augusta Dr(2900) 07/11/22 07/10/23 Utility installations and Engineering Scott Fettig
pavement replacement.
2 Avenue S Prairie St Dead End South 03/06/23 07/01/23 Utility installations and Engineering Scott Fettig
pavement replacement.
3 Azalea St Parvin St Laurel St 05/30/23 08/01/23 Utility installations and Engineering Scott Fettig
pavement replacement.
4 Bailey St Willson St Dead End South 01/30/23 07/07/23 Utility installations and Engineering Scott Fettig
pavement replacement.
5 Bernard St Acme St Roselawn Dr 05/30/23 09/01/23 Utility installations and Engineering Scott Fettig
pavement replacement.
6 Bonnie Brae St Riney Rd University Dr(HW 380) 04/24/23 06/30/23 (2)8x16 TSV&8"WL Private Development Public Jeremiah Tillman-David
Installation Works Inspections
7 Bonnie Brae St Riney Rd Windsor Dr 03/10/23 07/31/23 Urbana at Bonnie Brae:Public Public Works Inspections Jeremiah Tillman-David
Paving
8 Bradshaw St Hickory St McKinney St 03/21/22 06/30/23 Utility installations and Engineering Scott Fettig
pavement replacement.
9 Bradshaw St Prairie St Sycamore St 03/13/23 07/17/23 Utility installations and Engineering Scott Fettig
pavement replacement.
10 Bradshaw St Wilson St Prairie St 01/30/23 08/01/23 Utility installations and Engineering Scott Fettig
pavement replacement.
11 Brook Hollow Dr Greenway Dr Carriage Hill Rd 10/07/22 07/10/23 Utility installations and Engineering Scott Fettig
pavement replacement.
12 Brookfield Ln(2603) Woodhaven St Emerson Ln 06/20/23 07/07/23 Curb an Valley Gutter repair Streets Roy San Miguel
13 Camellia St Parvin St Laurel.St 05/30/23 08/01/23 Utility installations and Engineering Scott Fettig
pavement replacement.
14 Carriage Hill Thunderbird Dr. Brookhollow Dr. 06/05/23 07/31/23 Pavement replacement. Engineering Scott Fettig
15 Carroll Blvd SB Parkway St Oak St 05/08/23 08/14/23 Concrete Panel Repair Streets Roy San Miguel
Clover Ln Robinwood Ln Glenwood Ln 12/09/22 07/10/23 Water Distribution will be Water Tiffany Sherrane
16 installing a new main line and
services.
17 Colonial Dr Thunderbird Dr Dead End South 07/11/22 07/10/23 Utility installations and Engineering Scott Fettig
pavement replacement.
18 Cordell St(1229) Fulton St Crescent St 06/26/23 07/14/23 Curb and Road repair Streets Roy San Miguel
19 Crawford St Hickory St McKinney St 03/21/22 06/30/23 Utility installations and Engineering Scott Fettig
pavement replacement.
20 Greenway Dr Thunderbird Dr Dead End South 07/11/22 07/10/23 Utility installations and Engineering Scott Fettig
pavement replacement.
21 Greenway Dr Thunderbird Dr Windsor Farms Dr 10/07/22 07/10/23 Utility installations and Engineering Scott Fettig
pavement replacement.
22 Hattie St Paisley St McKinney St 03/21/22 06/30/23 Utility installations and Engineering Scott Fettig
pavement replacement.
23 Hickory Creek Rd Riverpass Dr FM 1830 03/13/23 12/31/24 Bridge Installation Engineering Dustin Draper
24 Hickory St Exposition St Ruddell St 05/02/22 06/30/23 Utility installations and Engineering Scott Fettig
pavement replacement.
25 Highland St Locust St Wainwright St 01/30/23 06/30/23 Utility installations and Engineering Scott Fettig
pavement replacement.
26 Lakewood Dr Greenway Dr Carriage Hill Rd 10/07/22 07/10/23 Utility installations and Engineering Scott Fettig
pavement replacement.
27 Locust St Hickory St Oak St 06/05/23 07/14/23 Installation of Diagonal Engineering Robin Davis
Crosswalks
28 Maddox St Prairie St Dead End 03/20/23 07/10/23 Utility installations and Engineering Scott Fettig
pavement replacement.
29 Mayhill Rd @ Spencer Rd 03/28/23 06/30/23 Water main tie-in and turn lane Public Works Inspections Ryan Cuba
addition
Exported on June 23,2023 11:47:31 AM CDT
I I Closure Start
Street/Intersection From Date Description Department Department Contact
30 McKinney St Crawford Rd Audra Ln 05/19/22 06/30/23 Utility installations and Engineering Scott Fettig
pavement replacement.
31 McKinney St Mayhill Rd Ryan Rd 05/04/23 07/31/23 Turn lane Public Works Inspections Ryan Cuba
32 Mill St Allen St Johnson St 01/17/23 07/28/23 Utility Replacement Engineering Seth Garcia
33 Mill St Allen St Robertson St 02/27/23 07/28/23 Utility installation and roadway Engineering Seth Garcia
reconstruction
34 Myrtle St. Fort Worth Dr. Eagle Dr. 06/05/23 09/28/23 Utility installations and Engineering Scott Fettig
pavement replacement.
35 Oak St Crawford St Wood St 04/04/22 06/30/23 Utility installations and Engineering Scott Fettig
pavement replacement.
36 Oak St E Locust St Austin St 06/05/23 07/14/23 Installation of Diagonal Engineering Robin Davis
Crosswalks
37 oak street Thomas Bonnie Brae 06/16/23 06/30/23 installing underground utilities Public Works Inspections Lee Thurmond
open cut roadway
38 Ottawa Dr Great Bear Ln Wind River Ln 05/29/23 07/06/23 Street Panel and Sidewalk Streets Roy San Miguel
Repair
39 Park Access Rd Windsor Dr Riney Rd 12/15/22 07/31/23 Urbana Bonnie Brae Project: Private Development Public Jeremiah Tillman-David
Water,Sewer,Storm,Paving. Works Inspections
Plum Hollow St Sagewood St Shadow Trl 05/30/23 07/15/23 This work includes road Other Taylor Holt
40 reconstruction with subgrade
stabilization,asphalt paving,
and concrete curb and gutter.
Robinwood Ln Kayewood Dr Emerson Ln 12/09/22 07/10/23 Water Distribution will be Water Tiffany Sherrane
41 installing a new main line and
services.
42 Roselawn St Bernard St Fort Worth Dr 06/20/23 06/28/23 Utility work Engineering Seth Garcia
43 Smith St Johnson St Bell Ave 01/30/23 07/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
44 Smith St Dallas Dr(Hwy 77) Hill St 03/06/23 08/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
45 Sycamore St Industrial St Wainwright St 04/24/23 07/11/23 Roadway&Utilities Engineering Seth Garcia
46 Sycamore St Exposition St Crawford St 03/13/23 07/17/23 Utility installations and Engineering Scott Fettig
pavement replacement.
47 Thunderbird Dr. Colonial Dr. Crestmeadow St. 06/05/23 07/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
48 Val Verde Ct Montecito Rd Dead End East 05/19/23 06/30/23 Mill and Overlay Streets Jeff Jones
49 Wainwright St Prairie St Sycamore St 04/24/23 07/11/23 Roadway,utilities Engineering Seth Garcia
50 Wainwright St Highland St Prairie St 03/13/23 07/14/23 Utility installations and Engineering Scott Fettig
pavement replacement.
Willow Stone St Pheasant Hollow St Shadow Trl 05/30/23 07/15/23 This work includes road Other Taylor Holt
51 reconstruction with subgrade
stabilization,asphalt paving,
and concrete curb and gutter.
52 Wisteria St Parvin St Laurel St 05/30/23 08/01/23 Utility installations and Engineering Scott Fettig
pavement replacement.
53 Wood St McKinney St Hickory St 04/11/22 06/30/23 Utility installations and Engineering Scott Fettig
pavement replacement.
54 Woodrow Ln McKinney St Troy H Lagrone Dr 02/20/23 07/05/23 Water tie in Public Works Inspections Ryan Cuba
Exported on June 23,2023 11:47:31 AM CDT
3 Street Closure Report: Completed Closures smartsheet
Intersection • To Date
Date
Closure End Description Department Department
1 Angelina Bend Dr San Gabriel Dr Angelina Bend Dr(1416) 01/17/23 05/31/23 Street Reconstruction Engineering Dustin Draper
2 Churchill Dr Nottingham Dr Burning Tree Ln 05/15/23 06/16/23 Pipe bursting sewer pipe Public Works Inspections Armando Beltran
3 Fulton St Crescent St Cordell St 05/08/23 06/16/23 Replacing public utilities in Public Works Inspections Lee Thurmond
roadway/intersection
4 Hickory St Elm St Austin St 03/20/23 06/06/23 Installation of Diagonal Engineering Robin Davis
Crosswalks
5 Locust St Walnut St Oak St 03/20/23 06/06/23 Installation of Diagonal Engineering Robin Davis
Crosswalks
Mistywood Ln Robinwood Ln Sherwood Ln 12/09/22 06/15/23 Water Distribution will be Water Tiffany Sherrane
6 installing a new main line and
services.
7 Myrtle St Eagle Dr Fort Worth Dr 04/05/23 06/09/23 Relocating gas main and Atmos Zabdiel Mote
service lines.
8 Oak St Thomas St Bonnie Brae St 06/08/23 06/16/23 Work on the DME substation Public Works Inspections Lee Thurmond
9 Riesling Dr Rhone Dr Merlot Dr 05/01/23 06/08/23 Concrete Panel and Sidewalk Streets Roy San Miguel
Repair
10 Sandy Creek Dr Angelina Bend Dr Angelina Bend Dr 05/18/23 06/23/23 Street Reconstruction Engineering Dustin Draper
Windsor Dr Burning Tree Ln Nottingham Dr 05/15/23 06/05/23 Shoulder closure-to locate a Public Works Inspections Armando Beltran
11 waterline for pipe bursting
project.
Exported on June 23,2023 11:47:42 AM CDT