DENTON 901-A Texas Street, Denton, TX 76209 • (940) 349-7160
Public Works Information Sheet
1. Location: Bellemead Drive (Emery Street to Thomas Street)
2. Proposed Date of Construction: October 19, 2017
3. Proposed Date of Completion: December 9, 2017
4. Brief Description of the Project:
This project is a reconstruction of Bellemead Drive from Emery to Thomas, this project
will be performed by Jagoe-Public Company, a City of Denton contractor. It includes
damaged concrete replacement followed by, seven inch asphalt removal (milling),
subgrade treatment, and seven inch asphalt replacement. This project is part of our 2012
Bond Program and is being replaced due to the deterating condition of the asphalt surface
and subgrade.
5. Special Requirements:
No parking will be allowed on the street unless otherwise advised to do so.
Detours will be provided.
All sod that is planted will be the homeowner's responsibility to irrigate.
6. Funding Source: 2012 Bond Program
7. Council District: District 3
8. Public Outreach: Public Outreach: Door hangers, map, and Street Construction
Report.
9. Map: Attached
10. Contact Information: Streets Manager. Robbin Webber 940-349-7146,
Robbin.Webber@cityofdenton.com
OUR CORE VALUES
Integrity•Fiscal Responsibility•Transparency• Outstanding Customer Service
ADA/EOE/ADEA www.cityofdenton.com TDD(800)735-2989
Bellemead Reconstruction Project r ' ��" — '. - �� �± �.� r , - ;� 4:,� •. e w� l_ = � � Legend
_tart Coat _l_t_k_ r 1' 201 7 � 0, , „•. -L,,�,� � ,�LJ- _:f � =rc=tr_�_ti=n
End date. 1IeCernber 8;2017 �� � ;,1'�� � ; � ;�� j ` •1 '- �.> `f' �• 7' 'i. ~'� �; �
Total Length of Fniject- 7 Weeks
zw-
L AU
'• m
VI
' —_ • � _ •� - �+.a _ - it //. - -
lit
'V s
r
• _ .its _ '.' dO
.��. •' M , i h r. � � �, fit_.t ��
CUMI
dm AAMW �� •M
�-t tip•-� ", do
—
,..� -dM'� _