2023/11/09 - Street Closure Report 1 Street Closure Report: Upcoming Closures smartsheet
SCR Nov 13th - 19th
Street/Intersection From To Description Department Department Contact
1 Cherry Tree Ln Clear River Ln dead end south 11,27/23 01/12/24 Sidewalk Repair Streets Roy San Miguel
2 Clear River Ln Montecito or Country Home or 11,27/23 01/12/24 Sidewalk Repair Streets Roy San Miguel
3 Crenshaw Ln Alderbrook or Hayling Way Intersection 11/20/23 01/19/24 Street Panels and Sidewalk Repair Streets Roy San Miguel
4 Matthew Ave Thistle Hill Intersection Andrew Ave 12/18/23 01/12/24 ADA Repair Streets Roy San Miguel
5 Wind River Ln Como Lake Rd Shoreline Dr 12/11/23 01/26/24 Concrete Panel Repair Streets Roy San Miguel
Exported on November 9,2023 11:48:51 AM CST
2 Street Closure Report: Current Closures smartsheet
- re Start Closure End Description Department ff Department Contact
17St
Maple St Highland St 10/02/23 i 12/04/23 Atmos gas relocation Atmos Gavin Petner
2 Eagle Dr Highland St 09/18/23 12/12/23 Relocation of gas lines. Atmos Gavin Petner
3 Parvin St Laurel St 05/30/23 12/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
4 Bell Ave Sycamore St Prairie St 08/21/23 12/01/23 Utility installations and Engineering Scott Fettig
pavement replacement.
5 Bernard St Acme St Roselawn Dr 05/30/23 11/30/23 Utility installations and Engineering Scott Fettig
pavement replacement.
Bonnie Brae St Scripture St Hickory St 10/23/23 11/20/23 installing conduit across Public Works Inspections Lee Thurmond
roadway for dme substation.
6 closures will be rolling at times
and full during work hours.work
areas will be plated for traffic.
Bonnie Brae St Scripture St Hickory St 10/23/23 11/20/23 installing conduit across Public Works Inspections Lee Thurmond
roadway for dme substation.
7 closures will be rolling at times
and full during work hours.work
areas will be plated for traffic.
Bonnie Brae St Elm St(US 77) Bronco Way/Riney Rd 11/13/23 12/01/23 Contractor will be installing a 16 Engineering Jesus Perez
8 inch water line off of the new 36
water line along US77.
9 Bradshaw St Wilson St Prairie St 01/30/23 11/30/23 Utility installations and Engineering Scott Fettig
pavement replacement.
10 Bradshaw St Prairie St Sycamore St 03/13/23 11/30/23 Utility installations and Engineering Scott Fettig
pavement replacement.
11 Brightwood Terrace Wilsonwood Dr Longfellow Ln 09/11/23 11/20/23 Utility Installation Engineering Taylor Holt
12 Buena Vista Montecito Mira Vista 11/06/23 12/29/23 Street reconstruct Streets Jeff Jones
13 Camellia St Parvin St Laurel St 05/30/23 12/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
14 Chaparral Ct Cooper Branch E Dead End 08/14/23 11/20/23 Utility Replacement Engineering Taylor Holt
15 College Park Dr Peach St Dead End 10/02/23 01/31/24 Street reconstruct Streets Jeff Jones
16 Collins St Johnson St Dead End West 08/22/23 01/05/24 Utility installations and Engineering Scott Fettig
pavement replacement.
17 Crawford St Mulberry St Sycamore St 10/09/23 12/11/23 Utility installations and Engineering Scott Fettig
pavement replacement.
18 Fowler Dr College Park Peach St 10/02/23 01/31/24 Street reconstruct Streets Jeff Jones
19 Hickory Creek Rd Riverpass Dr FM 1830 03/13/23 12/31/24 Bridge Installation Engineering Dustin Draper
20 Highland St Locust St Wainwright St 01/30/23 11/30/23 Utility installations and Engineering Scott Fettig
pavement replacement.
21 Industrial St Bell St Mulberry St 07/05/23 12/29/23 Utility installation and roadway Engineering Seth Garcia
work
Katy Trail Edwards Rd DCTA MedPark Station 08/21/23 11/30/23 A small section of Katy Trail will Other Tracy L.Beck,PE,PMP
have intermittent closures to
22 accommodate the construction
of the new Mayhill Road Bridge
over the DCTA
23 Leslie St Willowwood St Dudley St 08/31/23 01/08/24 Utility installations and Engineering Scott Fettig
pavement replacement.
24 Lookout Ln Windsor Dr Westward Dr 10/16/23 11/24/23 Panel and Sidewalk Repair Streets Roy San Miguel
25 Maple St Carroll Blvd Elm St 07/05/23 11/30/23 Utility installations and Engineering Scott Fettig
pavement replacement.
26 Maple St Elm St Carroll Blvd 09/15/23 12/31/23 Utility installations and Scott Fettig
pavement replacement.
27 Mayhill Rd @ Colorado Blvd 10/06/23 11/13/23 One Turn Lane each direction Engineering Tracy L.Beck,PE,PMP
closed to allow material staging.
Exported on November 9,2023 11:49:00 AM CST
Street/Intersection From To Description Department Department Contact
Mayhill Rd IH 35 Colorado Blvd 10/06/23 11/13/23 One lane to be closed for Other Tracy L.Beck,PE,PMP
28 staging construction operations
for new bridge
29 Mayhill Rd @ Spencer Rd 03/28/23 11/17/23 Water main tie-in and turn lane Public Works Inspections Ryan Cuba
addition
30 McKinney St E Bell Ave Oakland St 11/13/23 11/30/23 Sidewalk and ADA repair Streets Roy San Miguel
31 Mill Pond Rd Emerson Ln Old North Rd 09/11/23 12/04/23 Utility Installations Engineering Taylor Holt
32 Mingo Rd Mockingbird Ln Sirius Or 09/25/23 11/30/23 Base Failures Streets Jeff Jones
Mingo Rd Nottingham Dr Pertain St 10/25/23 11/30/23 pouring approach and turn lane Public Works Inspections Ryan Cuba
33 flaggers will be present during
normal work hours
34 Mulberry St E Wood St Crawford St 10/09/23 12/12/23 Utility installations and Engineering Scott Fettig
pavement replacement.
35 Mulberry St E Bell Ave Industrial St 08/21/23 03/01/24 Utility installations and Engineering Scott Fettig
pavement replacement.
36 Myrtle St Fort Worth Dr(HW377) Eagle Dr 06/05/23 11/30/23 Utility installations and Engineering Scott Fettig
pavement replacement.
37 Myrtle St Maple St Highland St 07/05/23 12/31/23 Utility installations and Scott Fettig
pavement replacement.
38 Myrtle St Eagle Or Maple St 07/05/23 12/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
Oak St Thomas St Bonnie Brae St 10/23/23 11/21/23 installing conduit across Public Works Inspections Lee Thurmond
roadway for dme substation.
39 closures will be rolling at times
and full during work hours.work
areas will be plated for traffic.
Oak St Thomas St Bonnie Brae St 10/23/23 11/21/23 installing conduit across Public Works Inspections Lee Thurmond
roadway for dme substation.
40 closures will be rolling at times
and full during work hours.work
areas will be plated for traffic.
41 Oakwood Or McCormick St East Dead End 10/02/23 02/08/24 Utility installations and Engineering Scott Fettig
pavement replacement.
42 Palo Verde Or Brias Ct Montecito Or 09/08/23 11/30/23 Reconstruct Jeff Jones
43 Parkside Or Windsor Dr W Bowling Green St 10/16/23 12/31/23 Pavement replacement Engineering Scott Fettig
44 Peach St Bell St N Locust St N 10/02/23 01/31/24 Street reconstruct Streets Jeff Jones
45 Pheasant Hollow St Windbrook St Willow Stone St 10/23/23 11/20/23 Pavement Replacement Engineering Taylor Holt
46 Pheasant Hollow St Willow Stone St Sagewood Ln 10/23/23 11/20/23 Pavement Replacement Engineering Taylor Holt
47 Pickwick Ln Oxford Ln Windsor Or 08/21/23 11/20/23 Utility Replacement Engineering Taylor Holt
48 Pierce St Maple St Highland St 07/05/23 11/30/23 Utility installations and Scott Fettig
pavement replacement.
49 Plum Hollow Rd Locust St Pheasant Hollow St 10/23/23 11/20/23 Pavement Replacement Engineering Taylor Holt
50 Plum Hollow Rd Locust St Pheasant Hollow St 10/23/23 11/20/23 Pavement Replacement Engineering Taylor Holt
Prairie St Lakey St To Cemetery/Halfway down Prairie 08/17/23 11/17/23 Narrow lane closure from Lakey Public Works Inspections Stephany Trammell
51 up to Cemetary before
Bradshaw to install new storm
drain.
52 Railroad Ave Hickory St McKinney St 11/06/23 11/30/23 Sidewalk repair in front or HR Streets Roy San Miguel
53 Smith St Johnson St Bell Ave 01/30/23 12/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
54 Smith St Dallas Dr(Hwy 77) Hill St 03/06/23 12/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
55 Sycamore St Exposition St Railroad Tracks on Sycamore 08/17/23 11/17/23 Work on manholes and for Lang Public Works Inspections Stephany Trammell
Railyard Private Development
56 Sycamore St Wood St Crawford St 10/09/23 12/11/23 Utility installations and Engineering Scott Fettig
pavement replacement.
57 Sycamore St Industrial St Wainwright St 04/24/23 12/29/23 Roadway&Utilities Engineering Seth Garcia
Exported on November 9,2023 11:49:00 AM CST
Street/Intersection From To Description Department Department Contact
58 Sycamore St Exposition St Crawford St 03/13/23 12/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
59 Trinity Rd Mills Rd Cooper Rd 10/12/23 12/01/23 Installation of force main and Public Works Inspections Ryan Cuba
demo of old system
60 Underwood St North Texas Blvd Kendolph Dr 08/28/23 12/31/23 Pavement replacement. Engineering Scott Fettig
61 Wainwright St Prairie St Sycamore St 04/24/23 11/17/23 Roadway,utilities Engineering Seth Garcia
62 Wainwright St Highland St Prairie St 03/13/23 12/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
63 Westwood Dr Dudley St Parvin St 10/30/23 12/08/23 Curb/Sidewalk/Valley Gutter Streets Roy San Miguel
repair
64 Wisteria St Parvin St Laurel St 05/30/23 12/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
Exported on November 9,2023 11:49:00 AM CST
3 Street Closure Report: Completed Closures smartsheet
Intersection • • Date
Date
• D- • Department Department
1 Ave H Hickory St Stella St 09/30/23 10/10/23 Pavement replacement for Public Works Inspections Lee Thurmond
electrical substation
2 Masch Branch Rd Lovers Ln Darby Smith Rd 09/07/23 11/03/23 Base failure Streets Jeff Jones
3 McKinney St Mayhill Rd Ryan Rd 05/04/23 10/28/23 Turn lane Public Works Inspections Ryan Cuba
4 McKinney St Loop 288 Mayhill Rd 07/20/23 10/28/23 Sidewalk demo and new Public Works Inspections Ryan Cuba
sidewalk
5 Nicosia St Elm St(HWY 77) Santos Dr 09/11/23 11/03/23 Road is open-Work complete
6 Oak St Bonnie Brae St Thomas St 09/30/23 10/10/23 Pavement replacement for Public Works Inspections Lee Thurmond
electrical substation
Panhandle St Bonnie Brae St Eastpark Blvd 10/02/23 10/27/23 Water service taps,and street Private Development Zabdiel Mota
7 panel repairs for east bound
lane and turning lane.
8 Pheasant Hollow St Windbrook St Willow Stone St 09/11/23 10/23/23 Pavement Replacement Engineering Taylor Holt
9 Tanglewood St Locust St Pheasant Hollow St 09/11/23 11/06/23 Pavement replacement Engineering Taylor Holt
10 Thomas St Emery St Bellmead Dr 10/09/23 10/13/23 Relocating gas main Atmos Gregory McCutchen
11 Vista Verde Rd Montecito Dr Dead End East 09/11/23 10/20/23 Street Reconstruct Streets Jeff Jones
Exported on November 9,2023 11:49:09 AM CST