2023/12/01 - Street Closure Report 1 Street Closure Report: Upcoming Closures smartsheet
SCR Dec 4th - 10th
Intersection • To . • - .•- - Description Department Department Contact
1 Barcelona St N 1-35 Service Rd Mesa Dr 1 12/07/23 12/12/23 Atmos gas relocation Atmos Gavin Petner
2 Matthew Ave Thistle Hill Intersection Andrew Ave 12/18/23 01/12/24 ADA Repair Streets Roy San Miguel
3 Wind River Ln Como Lake Rd Shoreline or 12/11/23 01/26/24 Concrete Panel Repair Streets Roy San Miguel
Exported on December 1,2023 11:18:19 AM CST
2 Street Closure Report: Current Closures smartsheet
_= I ulosure start Closure End Description Department ff Department Contact
-=00A M Date Date 17St
Eagle Dr Highland St 09/18/23 12/12/23 Relocation of gas lines. Atmos Gavin Petner
2 Maple St Highland St 10/02/23 12/30/23 Atmos gas relocation Atmos Gavin Petner
3 Parvin St Laurel St 05/30/23 12/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
4 Bell Ave Sycamore St Prairie St 08/21/23 03/31/24 Utility installations and Engineering Scott Fettig
pavement replacement.
5 Bernard St Acme St Roselawn Dr 05/30/23 01/30/24 Utility installations and Engineering Scott Fettig
pavement replacement.
Bonnie Brae St Elm St(US 77) Bronco Way/Riney Rd 11/13/23 12/29/23 Contractor will be installing a 16 Engineering Jesus Perez
6 inch water line off of the new 36
water line along US77.
7 Bradshaw St Wilson St Prairie St 01/30/23 01/31/24 Utility installations and Engineering Scott Fettig
pavement replacement.
8 Bradshaw St Prairie St Sycamore St 03/13/23 01/31/24 Utility installations and Engineering Scott Fettig
pavement replacement.
9 Brightwood Terrace Wilsonwood Dr Longfellow Ln 09/11/23 12/18/23 Utility Installation Engineering Taylor Halt
10 Buena Vista Dr Montecito Rd Mira Vista Dr 11/06/23 12/29/23 Street reconstruct Streets Jeff Jones
11 Camellia St Parvin St Laurel St 05/30/23 12/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
12 Chaparral Ct Cooper Branch E Dead End 08/14/23 12/18/23 Utility Replacement Engineering Taylor Holt
13 Cherry Tree Ln Clear River Ln dead end south 11/27/23 01/12/24 Sidewalk Repair Streets Roy San Miguel
14 Clear River Ln Montecito Dr Country Home Dr 11/27/23 01/12/24 Sidewalk Repair Streets Roy San Miguel
15 College Park Dr Peach St Dead End 10/02/23 01/31/24 Street reconstruct Streets Jeff Jones
16 Collins St Johnson St Dead End West 08/22/23 01/05/24 Utility installations and Engineering Scott Fettig
pavement replacement.
17 Crawford St Mulberry St Sycamore St 10/09/23 12/11/23 Utility installations and Engineering Scott Fettig
pavement replacement.
18 Crenshaw Ln Alderbrook Dr Hayling Way Intersection 11/20/23 01/19/24 Street Panels and Sidewalk Streets Roy San Miguel
Repair
19 Fowler Dr College Park Peach St 10/02/23 01/31/24 Street reconstruct Streets Jeff Jones
20 Hickory Creek Rd Riverpass Dr FM 1830 03/13/23 12/31/24 Bridge Installation Engineering Dustin Draper
21 Highland St Locust St Wainwright St 01/30/23 01/31/24 Utility installations and Engineering Scott Fettig
pavement replacement.
22 Industrial St Bell St Mulberry St 07/05/23 12/29/23 Utility installation and roadway Engineering Seth Garcia
work
23 Leslie St Willowwood St Dudley St 08/31/23 01/08/24 Utility installations and Engineering Scott Fettig
pavement replacement.
24 Lookout Ln Windsor Dr Westward Dr 10/16/23 12/08/23 Panel and Sidewalk Repair Streets Roy San Miguel
25 Maple St Elm St Carroll Blvd 09/15/23 12/31/23 Utility installations and Scott Fettig
pavement replacement.
26 Maple St Carroll Blvd Elm St 07/05/23 01/31/24 Utility installations and Engineering Scott Fettig
pavement replacement.
27 Mayhill Rd @ Spencer Rd 03/28/23 12/28/23 Water main tie-in and turn lane Public Works Inspections Ryan Cuba
addition
28 Meadow Ln Sagewood St Shadow Trail 11/29/23 01/01/24 Street Reconstruction Engineering Taylor Holt
29 Mill Pond Rd Emerson Ln Old North Rd 09/11/23 12/25/23 Utility Installations&Pavement Engineering Taylor Holt
Reconstruction
30 Mingo Rd Mockingbird Ln Sirius Dr 09/25/23 12/29/23 Base Failures Streets Jeff Jones
Mingo Rd Nottingham Dr Pertain St 10/25/23 12/30/23 pouring approach and turn lane Public Works Inspections Ryan Cuba
31 flaggers will be present during
normal work hours
32 Mulberry St E Wood St Crawford St 10/09/23 12/12/23 Utility installations and Engineering Scott Fettig
pavement replacement.
Exported on December 1,2023 11:18:29 AM CST
Street/Intersection From To Description Department Department Contact
33 Mulberry St E Bell Ave Industrial St 08/21/23 03/01/24 Utility installations and Engineering Scott Fettig
pavement replacement.
34 Myrtle St Maple St Highland St 07/05/23 12/31/23 Utility installations and Scott Fettig
pavement replacement.
35 Myrtle St Eagle Dr Maple St 07/05/23 12/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
36 Myrtle St Fort Worth Dr(HW377) Eagle Dr 06/05/23 01/31/24 Utility installations and Engineering Scott Fettig
pavement replacement.
37 Oakwood Dr McCormick St East Dead End 10/02/23 02/08/24 Utility installations and Engineering Scott Fettig
pavement replacement.
38 Parkside Dr Windsor Dr W Bowling Green St 10/16/23 12/31/23 Pavement replacement Engineering Scott Fettig
39 Peach St Bell St N Locust St N 10/02/23 01/31/24 Street reconstruct Streets Jeff Jones
40 Pheasant Hollow St Willow Stone St Sagewood Ln 10/23/23 12/04/23 Pavement Replacement Engineering Taylor Holt
41 Pickwick Ln Oxford Ln Windsor Dr 08/21/23 12/18/23 Utility Replacement Engineering Taylor Holt
42 Pierce St Maple St Highland St 07/05/23 03/01/24 Utility installations and Scott Fettig
pavement replacement.
43 Plum Hollow Rd Locust St Pheasant Hollow St 10/23/23 12/04/23 Pavement Replacement Engineering Taylor Holt
44 Plum Hollow Rd Locust St Pheasant Hollow St 10/23/23 12/04/23 Pavement Replacement Engineering Taylor Holt
Prairie St Lakey St To Cemetary/Halfway down Prairie 08/17/23 12/08/23 Narrow lane closure from Lakey Public Works Inspections Stephany Trammell
45 up to Cemetery before
Bradshaw to install new storm
drain.
46 Smith St Johnson St Bell Ave 01/30/23 12/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
47 Smith St Dallas Dr(Hwy 77) Hill St 03/06/23 12/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
48 Sycamore St Wood St Crawford St 10/09/23 12/11/23 Utility installations and Engineering Scott Fettig
pavement replacement.
Sycamore St Exposition St Railroad Tracks on Sycamore 08/17/23 12/22/23 Work on manholes waterline for Public Works Inspections Stephany Trammell
49 Lang Railyard Private
Development
50 Sycamore St Industrial St Wainwright St 04/24/23 12/29/23 Roadway&Utilities Engineering Seth Garcia
51 Sycamore St Exposition St Crawford St 03/13/23 12/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
52 Trinity Rd Mills Rd Cooper Rd 10/12/23 12/15/23 Installation of force main and Public Works Inspections Ryan Cuba
demo of old system
53 Underwood St North Texas Blvd Kendolph Dr 08/28/23 12/31/23 Pavement replacement. Engineering Scott Fettig
54 Wainwright St Highland St Prairie St 03/13/23 12/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
55 Westwood Dr Dudley St Parvin St 10/30/23 12/08/23 Curb/Sidewalk/Valley Gutter Streets Roy San Miguel
repair
56 Wisteria St Parvin St Laurel St 05/30/23 12/31/23 Utility installations and Engineering Scott Fettig
pavement replacement.
57 Woodrow Ln McKinney St Morse Rd 10/12/23 12/28/23 remove and replace turn lane at Public Works Inspections Ryan Cuba
duchess dr
Exported on December 1,2023 11:18:29 AM CST
3 Street Closure Report: Completed Closures smartsheet
Intersection • • •.sure Start •_ re • Description Department Department
1 Avenue C Highland St Maple St 10/24/23 11/14/23 Atmos Relocation Work for Atmos Sheldon Gatewood
Neighborhood 2&6
Bonnie Brae St Scripture St Hickory St 10/23/23 11/20/23 installing conduit across Public Works Inspections Lee Thurmond
roadway for dme substation.
2 closures will be rolling at times
and full during work hours.work
areas will be plated for traffic.
Bonnie Brae St Scripture St Hickory St 10/23/23 11/20/23 installing conduit across Public Works Inspections Lee Thurmond
roadway for dme substation.
3 closures will be rolling at times
and full during work hours.work
areas will be plated for traffic.
41 Eagle Dr Collier St Avenue C 11/17/23 11/20/23 Core hole repair Public Works Inspections Gavin Petner
5 Highland St Elm St Pierce St 10/16/23 11/03/23 Utility installations and Engineering Scott Fettig
pavement replacement.
Katy Trail Edwards Rd DCTA MedPark Station 08/21/23 11/30/23 A small section of Katy Trail will Other Tracy L.Beck,PE,PMP
have intermittent closures to
6 accommodate the construction
of the new Mayhill Road Bridge
over the DCTA
71 Masch Branch Rd Lovers Ln Darby Smith Rd 09/07/23 11/03/23 Base failure Streets Jeff Jones
8 Mayhill Rd @ Colorado Blvd 10/06/23 11/13/23 One Turn Lane each direction Engineering Tracy L.Beck,PE,PMP
closed to allow material staging.
Mayhill Rd IH 35 Colorado Blvd 10/06/23 11/13/23 One lane to be closed for Other Tracy L.Beck,PE,PMP
9 staging construction operations
for new bridge
10 McKinney St E Bell Ave Oakland St 11/13/23 11/30/23 Sidewalk and ADA repair Streets Roy San Miguel
11 Meadow Ln PI Hercules Ln Meadow Ln 11/29/23 12/01/23 Street Reconstruction Taylor Holt
12 Nicosia St Elm St(HWY 77) Santos Dr 09/11/23 11/03/23 Road is open-Work complete
Oak St Thomas St Bonnie Brae St 10/23/23 11/21/23 installing conduit across Public Works Inspections Lee Thurmond
roadway for dme substation.
13 closures will be rolling at times
and full during work hours.work
areas will be plated for traffic.
Oak St Thomas St Bonnie Brae St 10/23/23 11/21/23 installing conduit across Public Works Inspections Lee Thurmond
roadway for dme substation.
14 closures will be rolling at times
and full during work hours.work
areas will be plated for traffic.
15 Palo Verde Dr Brias Ct Montecito Dr 09/08/23 11/24/23 Reconstruct Jeff Jones
16 Pheasant Hollow St Windbrook St Willow Stone St 10/23/23 11/20/23 Pavement Replacement Engineering Taylor Holt
17 Pierce St. Highland St. Stroud St. 10/16/23 11/03/23 Utility installations and Engineering Scott Fettig
pavement replacement.
18 Prairie St. Bradshaw St. Bell Ave. 10/16/23 11/03/23 Utility installations and Engineering Scott Fettig
pavement replacement.
19 Prairie St. Elm St. Carroll Blvd. 10/16/23 11/03/23 Utility installations and Engineering Scott Fettig
pavement replacement.
20 Railroad Ave Hickory St McKinney St 11/06/23 11/30/23 Sidewalk repair in front or HR Streets Roy San Miguel
21 Tanglewood St Locust St Pheasant Hollow St 09/11/23 11/06/23 Pavement replacement Engineering Taylor Holt
22 Wainwright St Prairie St Sycamore St 04/24/23 11/17/23 Roadway,utilities Engineering Seth Garcia
23 Woodrow Ln McKinney St Morse St 11/17/23 11/30/23 Remove and replace turn lane Public Works Inspections Lee Thurmond
paving
Exported on December 1,2023 11:19:18 AM CST